Installation method of right angle square steel pipe column
By using a combination method of lifting fixtures and anti-fall bases, the right-angle square steel pipe columns are lifted and installed, which solves the impact of traditional installation methods on the visual quality of finished components, and achieves the effect of saving repair costs and shortening construction period.
Patent Information
- Application Number
- CN202310471865.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-27
- Publication Date
- 2025-06-06
- Estimated Expiration
- 2043-04-27
AI Technical Summary
The traditional right-angle square steel pipe column installation method affects the visual quality of finished components by welding the hoisting lugs, and increases the construction cost and construction period.
The combination of lifting fixtures and anti-fall bases is adopted to hoist and install right-angle square steel pipe columns, and the stability and safety of the pipe columns are ensured through the limit of safety ropes.
This method directly lifts and installs, avoids damage to finished components, saves repair costs, shortens construction period, and reduces construction difficulty and hazard coefficient.
Smart Images

Figure CN116411721B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel structure installation, and in particular to a method for installing a right-angle square steel pipe column. Background Art
[0002] Modern museums, stadiums and other exhibition halls have complex facades, and most of them use steel structures to meet the designer's aesthetic requirements for the shape, and they are also very demanding in terms of visual quality. The installation and construction are difficult. As decorative steel columns (such as the Baoding Natural History Museum), the angles of each square tube column are different. Since square tube columns are exposed decorative steel structures, they have extremely high requirements for the appearance of the finished product. The right-angled edges of the square tube columns must not be bumped or worn, and the paint surface of the finished components must not be scratched or peeled. However, the traditional installation method of steel tube columns is to install them by welding lugs on the column body. After installation, the lugs need to be cut, polished, and repainted, which can easily damage the finished components. Even after polishing and repairing, it is difficult to achieve consistency with the overall appearance, and it increases additional construction costs and prolongs the construction period. Summary of the invention
[0003] The embodiment of the present invention provides a method for installing a right-angle square steel pipe column. The method can directly hoist and install the right-angle square steel pipe without damaging the visual quality of the finished component, thereby reducing construction costs and improving construction efficiency.
[0004] The present invention adopts the following technical solution:
[0005] A method for installing a right-angle square steel pipe column is carried out according to the following steps:
[0006] (1) Make a lifting fixture and an anti-drop base. The lifting fixture consists of two U-shaped frame structures, which are connected by bolts. Lifting ears are provided at both ends of each U-shaped frame. The anti-drop base is welded by channel steel and is provided with rubber pads.
[0007] (2) Wrap a circle of rubber pads near the top of the square steel pipe column and install the lifting fixture on the outside of the rubber pads; install the anti-drop base at the bottom of the square steel pipe column, pass the lower end of the safety rope through the bottom of the anti-drop base, and connect the upper end through the lifting lug; the lifting lug is connected to the lifting mechanism through the lifting wire rope;
[0008] (3) Start the lifting mechanism to lift the square steel pipe column. When the square steel pipe column is lifted to the installation position, first connect the ear plate at the upper end of the square steel pipe column to the steel beam, then remove the lifting fixture and separate the anti-drop base from the lower end of the square steel pipe column;
[0009] (4) Then use the fall chain to fine-tune the lower end of the square steel pipe column to the installation position and connect it to the steel beam. Remove the fall chain to complete the installation.
[0010] Compared with the prior art, the present invention has the following beneficial effects:
[0011] When installing right-angled square steel pipe columns with strict requirements on visual quality, the present invention uses a lifting fixture to cooperate with an anti-drop base to lift the square steel pipe columns, which solves the problem of the visual quality of the finished components being affected by cutting, grinding, and repainting after installation using lifting ears in the traditional construction method. Direct lifting and installation saves subsequent repair costs, shortens the construction period, and also reduces the construction difficulty and risk factor of high-altitude operations.
[0012] Further, the preferred embodiment adopted by the present invention is:
[0013] Lifting ears are respectively arranged vertically at both ends of the U-shaped frame, through holes are respectively opened at the upper part and the lower part of each lifting ear, and a U-shaped shackle is respectively arranged in each through hole.
[0014] Connecting plates are respectively extended from both ends of the U-shaped frame, and the connecting plates at corresponding positions of the two U-shaped frames are connected by bolts.
[0015] The anti-drop base includes a transverse channel steel and a longitudinal channel steel. Two transverse channel steels and two longitudinal channel steels are respectively arranged in parallel. The longitudinal channel steel is placed in parallel on the upper part of the transverse channel steel. A rubber pad is respectively arranged on each longitudinal channel steel. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The drawings described herein are used to provide a further understanding of the present invention, constitute a part of the present application, and do not constitute a limitation of the present invention. In the drawings:
[0017] Figure 1 It is a schematic diagram of the present invention during hoisting;
[0018] Figure 2 This is a structural diagram of the lifting fixture during lifting;
[0019] Figure 3 A schematic diagram of the structure of the anti-drop base;
[0020] Figure 4 It is a structural schematic diagram of a square steel pipe column;
[0021] In the figure: a lifting fixture 1; a U-shaped frame 101; a lifting lug 102; a connecting plate 103; a square steel pipe column 2; an upper lug plate 201; a lower lug plate 202; an anti-drop base 3; a longitudinal channel steel 301; a transverse channel steel 302; a safety rope 4; a lifting wire rope 5; a rubber pad 6; a rubber pad 7; a U-shaped shackle 8; and a bolt 9. DETAILED DESCRIPTION
[0022] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments and the accompanying drawings. Here, the illustrative embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention.
[0023] A method for installing a right-angle square steel pipe column is carried out according to the following steps:
[0024] (1) The size of the lifting fixture 1 is determined according to the width of the square steel pipe column 2, and the lifting fixture 1 and the anti-drop base 3 are manufactured. The lifting fixture 1 is composed of two U-shaped frames 101, and the two U-shaped frames 101 are respectively made by stamping steel plates. Connecting plates 103 are respectively extended at both ends of the U-shaped frames 101, so that the two U-shaped frames 101 are placed opposite to each other, and the connecting plates 103 at both ends of the two U-shaped frames 101 can be connected and fixed by bolts 9; each U-shaped frame 101 is also symmetrically provided with lifting ears 102 at both ends, and the lifting ears 102 are fixedly connected to the U-shaped frame 101. Through holes are respectively opened at the upper and lower parts of each lifting ear 102, and a U-shaped shackle 8 is respectively installed in each through hole.
[0025] The anti-drop base 3 is welded by four channel steels, including two transverse channel steels 302 and two longitudinal channel steels 301. The two transverse channel steels 302 are spaced apart at the bottom, and the two longitudinal channel steels 301 are spaced apart at the top of the transverse channel steels 302. The two longitudinal channel steels 301 are welded and fixed to the upper surfaces of the two transverse channel steels 302; a rubber pad 7 is also installed on the top of each longitudinal channel steel 301.
[0026] (2) Wrap a circle of rubber pad 6 around the position near the top of the square steel pipe column 2, and buckle the two U-shaped frames 101 of the lifting fixture 1 on the square steel pipe column 2 at the position corresponding to the rubber pad 6, and then use bolts 9 to connect and fix the two U-shaped frames 101; place the bottom of the square steel pipe column 2 on the anti-drop base 3, so that the lower end ear plate of the square steel pipe column is placed in the gap between the two longitudinal channel steels; adjust the length of the safety rope 4 according to the height of the square steel pipe column 2, prepare four safety ropes 4, each safety rope 4 corresponds to a U-shaped shackle 8 at the bottom of the lifting ear 102, and the four safety ropes 4 pass through the bottom of the anti-drop base 3, and then connect the two ends of each safety rope 4 together to form a ring rope, and then use the U-shaped shackle 8 corresponding to each safety rope 4 to connect with the lifting ear 102, so that the four safety ropes 4 limit the square steel pipe column 2; then the U-shaped shackle 8 at the top of each lifting ear 102 is connected to the lifting mechanism through the lifting wire rope 5.
[0027] (3) Start the lifting mechanism to lift the square steel pipe column 2. When the square steel pipe column 2 is lifted to the installation position, first connect the ear plate 201 at the upper end of the square steel pipe column 2 with the corresponding steel beam at the upper end of the square steel pipe column, and then remove the lifting fixture 1 and separate the anti-drop base 3 from the lower end of the square steel pipe column 2.
[0028] (4) Then install a fall chain on the lower end ear plate 202 of the square steel pipe column 2. Use the fall chain to fine-tune the lower end of the square steel pipe column 2 to the installation position and connect it to the steel beam corresponding to the lower end of the square steel pipe column 2. Remove the fall chain and the rubber pad on the upper end of the square steel pipe column 2 to complete the installation.
[0029] When the right-angle square steel pipe column with strict requirements on the visual quality is installed by the lifting fixture and the anti-drop base, the safety rope is used to limit the square steel pipe column so as to ensure that the square steel pipe column will not fall off the lifting fixture, thereby solving the problem of cutting, grinding, and repainting after installation with lifting ears in the traditional construction method, which affects the visual quality of the finished component, saves the cost of later repairs, and saves the construction period; at the same time, it also reduces the difficulty of construction and installation during the construction process, reduces the construction risk factor, and the anti-drop base and the lifting fixture can also be used in a turnover manner.
[0030] The above description is only a preferred embodiment of the present invention and is not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention are included in the protection scope of the present invention.
Claims
1. A method for installing a right-angle square steel pipe column. It is characterized in that Follow these steps: (1) Make a lifting fixture and an anti-drop base. The lifting fixture consists of two U-shaped frame structures, which are connected by bolts. Lifting ears are provided at both ends of each U-shaped frame. The anti-drop base is welded by channel steel and is provided with rubber pads. (2) Wrap a circle of rubber pads near the top of the square steel pipe column and install the lifting fixture on the outside of the rubber pads; install the anti-drop base at the bottom of the square steel pipe column, pass the lower end of the safety rope through the bottom of the anti-drop base, and connect the upper end through the lifting lug; the lifting lug is connected to the lifting mechanism through the lifting wire rope; (3) Start the lifting mechanism to lift the square steel pipe column. When the square steel pipe column is lifted to the installation position, first connect the ear plate at the upper end of the square steel pipe column to the steel beam, then remove the lifting fixture and separate the anti-drop base from the lower end of the square steel pipe column; (4) Then use the fall chain to fine-tune the lower end of the square steel pipe column to the installation position and connect it to the steel beam. Remove the fall chain to complete the installation.
2. The installation method of the right-angle square steel pipe column according to claim 1, Features: Lifting ears are respectively arranged vertically at both ends of the U-shaped frame, through holes are respectively opened at the upper part and the lower part of each lifting ear, and a U-shaped shackle is respectively arranged in each through hole.
3. The installation method of the right-angle square steel pipe column according to claim 1, Features: Connecting plates are respectively extended from both ends of the U-shaped frame, and the connecting plates at corresponding positions of the two U-shaped frames are connected by bolts.
4. The installation method of the right-angle square steel pipe column according to claim 1, Features: The anti-drop base includes a transverse channel steel and a longitudinal channel steel. Two transverse channel steels and two longitudinal channel steels are respectively arranged in parallel. The longitudinal channel steel is placed in parallel on the upper part of the transverse channel steel. A rubber pad is respectively arranged on each longitudinal channel steel.
Citation Information
Patent Citations
Hoisting device and hoisting method for steel pipe concrete column
CN106760208A
Structural steel beam installing structure and construction method
CN111206783A