A wind turbine blade monitoring system and method based on optical fiber technology

Through distributed strain fiber monitoring of blade bending and wind power changes, predicting blade bending and seepage, the error problem of the blade monitoring system of the wind turbine unit in bad weather is solved, and more accurate monitoring of the clearance distance between the tip and the tower is achieved and The internal cavity of the blade is predicted, reducing the risk of accidents.

CN116641849BActive Publication Date: 2024-11-08STATE POWER INVESTMENT CORP JIANGSU OFFSHORE WIND POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310380537.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-04-11
Publication Date
2024-11-08
Estimated Expiration
2043-04-11

AI Technical Summary

Technical Problem

The existing wind turbine blade monitoring system has a large monitoring error in bad weather, which cannot effectively predict the water seepage in the blade cavity, resulting in water leakage icing and damage to the inner core material of the blade, and it is impossible to accurately predict the clearance distance between the blade tip and the tower, increasing The risk of accidents.

Method used

Distributed strain fiber is used to monitor the elastic bending position and bending amount of the blade, combine wind power changes to predict the bending amount at the next moment, judge the crack length, and predict the water seepage in the blade through the seepage coefficient, monitor the clearance distance in real time, and issue an early warning.

Benefits of technology

The blade monitoring accuracy is improved, the risk of tower sweeping accidents is reduced, and early warnings are issued before the accident occurs, avoiding water seepage damage to the internal core material of the blade, and enhancing the system monitoring effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116641849B_ABST
    Figure CN116641849B_ABST
Patent Text Reader

Abstract

The present invention discloses a wind turbine blade monitoring system and method based on optical fiber technology, belonging to the technical field of blade status monitoring. The present invention comprises: S10: monitoring the actual clearance distance between the blade tip and the tower according to the data collected by the distributed strain optical fiber, combined with the rotation of the blade and the change of wind force; S20: judging whether a crack will be generated at the corresponding bending position of the blade according to the maximum bending amount of the blade at the bending position predicted in S10 at the next moment, and if a crack is generated, predicting the length of the generated crack; S30: predicting the amount of water seepage in the inner cavity of the blade according to the crack length predicted in S20; S40: the early warning system selects whether to issue an early warning message according to the clearance distance predicted in S10 and the amount of water seepage predicted in S30. The present invention determines the extension of the crack of the blade before and after the cracking point based on the bending degree of the segmentation points before and after the cracking point, ensuring that the obtained blade crack length is highly matched with the actual value.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of blade status monitoring, and in particular to a wind turbine blade monitoring system and method based on optical fiber technology. Background Art

[0002] Wind turbine blades are the core components of wind turbines that convert natural wind energy into electrical energy for wind turbines, and are also the main basis for measuring the design and technical level of wind turbines.

[0003] Under extreme operating conditions such as high turbulence and gusty winds, wind turbine blades may approach the tower or even hit it, causing damage to the blades or even the risk of tower collapse. Existing systems usually use lidar to monitor the safe distance between blades and towers, but monitoring errors are prone to occur in severe weather, thereby reducing the system's monitoring accuracy. In addition, when monitoring cracks at the blade bonding points, the existing technology cannot predict the amount of water seepage into the blade cavity, resulting in the water seeping into the blade cavity freezing, damaging the internal core material of the blade, and causing cracks to spread and grow, reducing the system's monitoring effect. Summary of the Invention

[0004] The object of the present invention is to provide a wind turbine blade monitoring system and method based on optical fiber technology to solve the problems raised in the above background technology.

[0005] In order to solve the above technical problems, the present invention provides the following technical solution: a wind turbine blade monitoring method based on optical fiber technology, the method comprising:

[0006] S10: Distributed strain optical fibers are arranged transversely along the inner wall of the blade. Based on data collected by the distributed strain optical fibers, the location where the blade elastically bends is determined. Based on the determination result, the maximum bending amount of the blade at the bending position at the next moment is predicted in combination with the rotation of the blade and the change in wind force. Based on the prediction result, the actual clearance distance between the blade tip and the tower is monitored.

[0007] S20: judging whether a crack will occur at the corresponding bending position of the blade based on the maximum bending amount of the blade at the bending position at the next moment predicted in S10, and predicting the length of the crack if a crack occurs;

[0008] S30: predicting the amount of water seepage into the blade cavity based on the crack length predicted in S20;

[0009] S40: The early warning system selects whether to issue an early warning message based on the clearance distance predicted in S10 and the water seepage amount predicted in S30.

[0010] Furthermore, the S10 includes:

[0011] S101: When the wind turbine is facing the wind, data monitored by the distributed strain optical fiber is acquired, the value acquired by the distributed strain optical fiber at the corresponding position is compared with the critical value of elastic deformation of the blade at the corresponding position, and the position where the elastic bending of the blade occurs is determined based on the comparison result;

[0012] S102: Calculate the maximum bending amount of the blade at the elastic bending position determined in S101 using the formula maxX=(Ff) / k, where F represents the strain force monitored by the distributed strain optical fiber at the elastic bending position of the blade, f represents the strain force monitored by the distributed strain optical fiber at the critical point, k represents the stiffness coefficient of the blade, and X represents the bending amount of the blade at the elastic bending position;

[0013] S103: The real-time change of wind force and the change of blade rotation speed under the action of wind force are obtained, and the wind force change rate at the next moment is predicted based on the real-time change of wind force. The blade rotation speed at the next moment is predicted based on the predicted wind force change rate and the blade rotation speed at the current moment. Based on the prediction result, the maximum bending amount of the blade at the elastic bending position at the next moment is predicted. The specific prediction formula Q is:

[0014] Q={[(1+(tt') / t')*V'] / V}*maxX;

[0015] Where t represents the wind force at the current moment, t' represents the wind force at the previous moment, V' represents the blade speed at the current moment, V represents the blade speed when the wind turbine is facing the wind, maxX represents the maximum bending amount of the blade at the elastic bending position, and Q represents the predicted maximum bending amount of the blade at the elastic bending position at the next moment.

[0016] S104: Calculate the difference between the maximum bending amount of the blade at the next moment predicted in S103 and the standard clearance distance between the blade tip and the tower to obtain the actual clearance distance between the blade tip and the tower.

[0017] Further, S201: calculating the bending amount of the blade at the location where elastic bending occurs according to the formula X=(Ff) / k, and simulating the bending condition of the blade in a three-dimensional model based on the bending amount of the blade at the corresponding location;

[0018] S202: Segment the elastically bent portion of the blade by distance s. Based on the blade bending conditions simulated in S201, obtain the bending amount of the blade at the segment points. Construct a mathematical model W based on the obtained information. i-1 =[arctan(h i / d i+1 )+arctan(hi+2 / d i+2 )] / π, the bending degree of the blade at each segment point is determined, where i=1,2,…,m-1, represents the number corresponding to the segment point, m represents the total number of segment points, h i Indicates the bending amount corresponding to the i-th segment point position, d i+1 W represents the length of the arc formed between the i-th segment point and the i+1-th segment point of the blade when it is projected as a straight line. i-1 Indicates the bending degree corresponding to the segment point numbered i-1. When i=1, W i-1 =W0= arctan(h1 / d1) / π,W m =1-1.5*arctan(D / h m ), D represents the length of the arc formed between the mth segment point of the blade and the tip when projected as a straight line, 0<s<g, g represents the blade length;

[0019] S203: Compare the bending degree of the blade at each segment point determined in S202 with the critical bending degree. When the bending degree of the corresponding segment point is greater than or equal to the critical bending degree, it indicates that the corresponding segment point is a cracking point. When the bending degree of the corresponding segment point is less than the critical bending degree, it indicates that the corresponding segment point is not a cracking point. The cracking point of the blade is determined based on the comparison result. Combined with the bending degrees corresponding to the segment points before and after the cracking point, the crack length of the blade is predicted. The specific prediction formula A is:

[0020] A=M*s+W b *s+W b+M-1 *s;

[0021] Where M represents the number of cracking points on the leaf, b represents the number corresponding to the first cracking point on the leaf, and W b Indicates the bending degree corresponding to the segment point numbered b, W b+M-1 It represents the bending degree corresponding to the segment point numbered b+M-1, 1≤b<m, and A represents the predicted blade crack length.

[0022] Furthermore, the specific method for predicting the water seepage amount in the blade cavity is:

[0023] The ratio of the blade crack length predicted in S203 to the blade length is used as the blade water seepage coefficient;

[0024] Determine whether the blade crack is located in the direction of rain or away from rain. If the blade crack is in the direction of away from rain, it means that the water seepage in the blade cavity can be ignored. If the blade crack is in the direction of rain, the product of the blade water seepage coefficient and the rainfall per unit time is calculated to obtain the water seepage in the blade cavity per unit time. Based on the rainfall time, the water seepage in the blade cavity can be predicted.

[0025] Furthermore, the S40 includes:

[0026] S401: Calculate the difference between the standard clearance distance and the actual clearance distance between the blade tip and the tower calculated in S104. If the difference is ≥ 2 / 3*standard clearance distance, the early warning system issues an early warning message. If the difference is < 2 / 3*standard clearance distance, the early warning system does not issue an early warning message.

[0027] S402: Calculate the product of the water seepage predicted in S30 and the expansion coefficient. If 0 < the calculated result < 2 / 3 * the blade cavity volume, the early warning system will not issue an early warning message. If 2 / 3 * the blade cavity volume ≤ the calculated result ≤ the blade cavity volume, the early warning system will issue an early warning message. The expansion coefficient refers to the ratio of the volume of ice to the volume of water after water freezes into ice.

[0028] A wind turbine blade monitoring system based on optical fiber technology, comprising a tower sweep monitoring module, a blade crack monitoring module, a blade water seepage prediction module, and an early warning module;

[0029] Distributed strain optical fibers are arranged laterally along the inner wall of the blade;

[0030] The tower sweep monitoring module is used to determine the location where the blade elastically bends based on the data collected by the distributed strain optical fiber, and based on the determination result, in combination with the rotation of the blade and the change in wind force, predict the maximum bending amount of the blade at the bending position at the next moment, based on the prediction result, monitor the actual clearance distance between the blade tip and the tower, and transmit the predicted maximum bending amount of the blade at the bending position at the next moment to the blade tower sweep monitoring module, and transmit the monitoring result to the early warning module;

[0031] The blade crack monitoring module is used to receive the maximum bending amount of the blade at the bending position at the next moment transmitted by the tower sweep monitoring module, and based on the received information, determine whether a crack will occur in the blade at the corresponding bending position. If a crack occurs, the length of the crack is predicted and the prediction result is transmitted to the blade water seepage prediction module;

[0032] The blade water seepage prediction module is used to receive the predicted crack length transmitted by the blade crack monitoring module, predict the water seepage in the blade cavity based on the received information, and transmit the prediction result to the early warning module;

[0033] The early warning module is used to receive the monitoring results transmitted by the tower sweeping monitoring module and the prediction results transmitted by the blade water seepage prediction module, and select whether to issue an early warning message based on the received information.

[0034] Furthermore, the tower sweeping monitoring module includes an elastic bending position determination unit, a calculation unit, a prediction unit and a clearance distance determination unit;

[0035] The elastic bending position determination unit acquires data monitored by the distributed strain optical fiber when the wind turbine generator completes wind response, compares the value acquired by the distributed strain optical fiber at the corresponding position with the critical value of elastic deformation of the blade at the corresponding position, and determines that elastic bending occurs at the corresponding position of the blade when the acquired value is greater than the critical value, and transmits the determined position information of the elastic bending to the calculation unit;

[0036] The calculation unit receives the determination result of the elastic bending position, constructs a mathematical model maxX=(Ff) / k based on the received information, calculates the maximum bending amount of the blade at the determined elastic bending position, transmits the calculation result to the prediction unit, and transmits the constructed mathematical model to the blade crack monitoring module, wherein F represents the strain force monitored by the distributed strain optical fiber when the blade elastically bends, f represents the strain force monitored by the distributed strain optical fiber at the critical point, k represents the stiffness coefficient of the blade, and X represents the bending amount of the blade at the elastic bending position;

[0037] The prediction unit receives the calculation result transmitted by the calculation unit, obtains the real-time change of wind force and the change of the rotation speed of the blade under the action of wind force, predicts the change rate of wind force at the next moment according to the real-time change of wind force, and predicts the rotation speed of the blade at the next moment based on the predicted wind force change rate and the rotation speed of the blade at the current moment. According to the prediction result, a prediction model Q={[(1+(tt') / t')*V'] / V}*maxX is constructed to predict the maximum bending amount of the blade at the elastic bending position at the next moment, and the prediction result is transmitted to the clearance distance determination unit, wherein t represents the wind force value at the current moment, t' represents the wind force value at the previous moment, V' represents the rotation speed of the blade at the current moment, V represents the rotation speed of the blade when the wind turbine completes the wind, maxX represents the maximum bending amount of the blade at the elastic bending position, and Q represents the predicted maximum bending amount of the blade at the elastic bending position at the next moment;

[0038] The clearance distance determination unit receives the prediction result transmitted by the prediction unit, calculates the difference between the predicted maximum bending amount of the blade at the next moment and the standard clearance distance between the blade tip and the tower, obtains the actual clearance distance between the blade tip and the tower, and transmits the obtained actual clearance distance to the early warning module.

[0039] Furthermore, the blade crack monitoring module includes a simulation unit, a bending degree prediction unit and a blade crack length prediction unit;

[0040] The simulation unit receives the mathematical model transmitted by the calculation unit, calculates the bending amount of the blade at the location where elastic bending occurs according to the mathematical model X=(Ff) / k, simulates the bending condition of the blade in a three-dimensional model based on the bending amount of the blade at the corresponding location, and transmits the simulation result to the bending degree prediction unit;

[0041] The bending degree prediction unit receives the simulation results transmitted by the simulation unit, segments the elastic bending portion of the blade by distance s, obtains the bending amount of the blade at the segment points based on the simulated blade bending situation, and constructs a mathematical model W based on the obtained information. i-1 = [arctan(h i / d i+1 )+arctan(h i+2 / d i+2 )] / π, the bending degree of the blade at each segment point is determined, and the determined bending degree is transmitted to the blade crack length prediction unit, where i=1,2,…,m-1, represents the number corresponding to the segment point, m represents the total number of segment points, h i Indicates the bending amount corresponding to the i-th segment point position, d i+1 W represents the length of the arc formed between the i-th segment point and the i+1-th segment point of the blade when it is projected as a straight line. i-1 Indicates the bending degree corresponding to the segment point numbered i-1. When i=1, W i-1 =W0= arctan(h1 / d1) / π,W m =1-1.5*arctan(D / h m ), D represents the length of the arc formed between the mth segment point of the blade and the tip when projected as a straight line, 0<s<g, g represents the blade length;

[0042] The blade crack length prediction unit receives the bending degree of the blade at each segment point transmitted by the bending degree prediction unit, and compares the received bending degree of the blade at each segment point with the critical bending degree. When the bending degree of the corresponding segment point is greater than or equal to the critical bending degree, it indicates that the corresponding segment point position is a cracking point. When the bending degree of the corresponding segment point is less than the critical bending degree, it indicates that the corresponding segment point position is not a cracking point. The cracking point of the blade is determined based on the comparison result, and a mathematical model A=M*s+W is constructed in combination with the bending degrees corresponding to the segment points before and after the cracking point. b *s+W b+M-1 *s, predict the crack length of the blade and transmit the predicted crack length to the blade water seepage prediction module, where M represents the number of crack points on the blade, b represents the number corresponding to the first crack point on the blade, and W b Indicates the bending degree corresponding to the segment point numbered b, W b+M-1 It represents the bending degree corresponding to the segment point numbered b+M-1, 1≤b<m, and A represents the predicted blade crack length.

[0043] Furthermore, the blade water seepage amount prediction module includes a blade water seepage coefficient determination unit, a judgment unit and a blade water seepage amount prediction unit;

[0044] The blade water seepage coefficient determination unit receives the predicted blade crack length transmitted by the blade crack length prediction unit, uses the ratio of the predicted blade crack length to the blade length as the blade water seepage coefficient, and transmits the determined blade water seepage coefficient to the blade water seepage amount prediction unit;

[0045] The judgment unit is used to judge whether the position of the blade crack is in the direction of facing the rain or the direction of facing the rain. If the blade crack is in the direction of facing the rain, it means that the water seepage in the blade cavity is negligible. If the blade crack is in the direction of facing the rain, the rainfall per unit time is transmitted to the blade water seepage prediction unit;

[0046] The blade water seepage prediction unit receives the blade water seepage coefficient transmitted by the blade water seepage coefficient determination unit and the rainfall per unit time transmitted by the judgment unit, calculates the product between the blade water seepage coefficient and the rainfall per unit time, obtains the water seepage in the blade cavity per unit time, predicts the water seepage in the blade cavity based on the rainfall time, and transmits the predicted water seepage in the blade cavity to the early warning module.

[0047] Furthermore, the early warning module includes a first early warning unit and a second early warning unit;

[0048] The first warning unit receives the actual clearance distance transmitted by the clearance distance determination unit, calculates the difference between the standard clearance distance and the received actual clearance distance, and issues a warning message when the difference is greater than or equal to 2 / 3*standard clearance distance;

[0049] The second warning unit receives the predicted water seepage amount of the blade cavity transmitted by the blade water seepage prediction unit, calculates the product between the received water seepage amount of the blade cavity and the expansion coefficient, and issues a warning message when 2 / 3*blade cavity volume ≤ calculated result ≤ blade cavity volume. The expansion coefficient refers to the ratio of the volume of ice to the volume of water after water freezes into ice.

[0050] Compared with the prior art, the beneficial effects achieved by the present invention are:

[0051] 1. The present invention uses distributed strain optical fiber to determine the location where elastic bending occurs in the blades of a wind turbine. The maximum bending amount of the blade at the elastic bending location is determined based on the data monitored by the distributed strain optical fiber. Combined with the real-time changes in wind force and the changes in the blade rotation speed under the action of wind force, the maximum bending amount of the blade at the elastic bending location at the next moment is predicted. Based on the prediction result, the actual clearance distance between the blade tip and the tower is determined. This process relies on the effect of wind force on the blade to monitor the actual clearance distance between the blade tip and the tower in real time. The monitoring result is not affected by other factors, further improving the monitoring accuracy of the system, ensuring that early warning information is issued before a tower sweep accident occurs, and improving the use effect of the system.

[0052] 2. The present invention divides the portion of the blade where elastic bending occurs into segments, and predicts the bending degree of the blade at each segment point based on the calculated bending amount of the blade at the corresponding bending position. In the process of predicting the bending degree, the bending degree of the middle segment point is represented by the angle change of the front and rear segment points compared with the projection point of the middle segment point, thereby reducing the amount of data processing and ensuring that the determined bending degree is more representative.

[0053] 3. The present invention determines the cracking point of the blade by the bending degree of each segmented point, and determines the extension of the crack of the blade before and after the cracking point based on the bending degree of the segmented points before and after the cracking point, to ensure that the obtained blade crack length is highly matched with the actual value, and uses the ratio of the predicted blade crack length to the blade length as the blade water seepage coefficient to represent the ability of rainwater to enter the blade cavity, thereby realizing effective monitoring of the blade water seepage amount, thereby avoiding damage to the internal core material of the blade when the seepage water freezes in the blade cavity, and further improving the monitoring effect of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0054] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0055] Figure 1 This is a schematic diagram of the workflow of a wind turbine blade monitoring system and method based on optical fiber technology of the present invention;

[0056] Figure 2 This is a schematic diagram of the working principle and structure of a wind turbine blade monitoring system and method based on optical fiber technology of the present invention;

[0057] Figure 3 The present invention is a schematic diagram of a blade cross-sectional structure of a wind turbine blade monitoring system and method based on optical fiber technology. Implementation Method

[0058] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0059] See also Figure 1 、 Figure 2 and Figure 3 The present invention provides a technical solution: a wind turbine blade monitoring method based on optical fiber technology, the method comprising:

[0060] S10: Distributed strain optical fibers are arranged transversely along the inner wall of the blade. Based on data collected by the distributed strain optical fibers, the location where the blade elastically bends is determined. Based on the determination result, the maximum bending amount of the blade at the bending position at the next moment is predicted in combination with the rotation of the blade and the change in wind force. Based on the prediction result, the actual clearance distance between the blade tip and the tower is monitored.

[0061] The S10 includes:

[0062] S101: When the wind turbine is facing the wind, data monitored by the distributed strain optical fiber is acquired, and a value acquired by the distributed strain optical fiber at a corresponding position is compared with a critical value for elastic deformation of the blade at the corresponding position. If the acquired value is greater than the critical value, it indicates that elastic bending occurs at the corresponding position of the blade; if the acquired value is less than or equal to the critical value, it indicates that elastic bending does not occur at the corresponding position of the blade. Based on the comparison result, the position where the elastic bending of the blade occurs is determined.

[0063] S102: Calculate the maximum bending amount of the blade at the elastic bending position determined in S101 using the formula maxX=(Ff) / k, where F represents the strain force monitored by the distributed strain optical fiber at the elastic bending position of the blade, f represents the strain force monitored by the distributed strain optical fiber at the critical point, k represents the stiffness coefficient of the blade, and X represents the bending amount of the blade at the elastic bending position;

[0064] S103: The real-time change of wind force and the change of blade rotation speed under the action of wind force are obtained, and the wind force change rate at the next moment is predicted based on the real-time change of wind force. The blade rotation speed at the next moment is predicted based on the predicted wind force change rate and the blade rotation speed at the current moment. Based on the prediction result, the maximum bending amount of the blade at the elastic bending position at the next moment is predicted. The specific prediction formula Q is:

[0065] Q={[(1+(tt') / t')*V'] / V}*maxX;

[0066] Where t represents the wind force at the current moment, t' represents the wind force at the previous moment, V' represents the blade speed at the current moment, V represents the blade speed when the wind turbine is facing the wind, maxX represents the maximum bending amount of the blade at the elastic bending position, and Q represents the predicted maximum bending amount of the blade at the elastic bending position at the next moment.

[0067] S104: Calculate the difference between the maximum bending amount of the blade at the next moment predicted in S103 and the standard clearance distance between the blade tip and the tower to obtain the actual clearance distance between the blade tip and the tower.

[0068] S20: judging whether a crack will occur at the corresponding bending position of the blade based on the maximum bending amount of the blade at the bending position at the next moment predicted in S10, and predicting the length of the crack if a crack occurs;

[0069] S201: calculating the bending amount of the blade at the location where elastic bending occurs according to the formula X=(Ff) / k, and simulating the bending condition of the blade in a three-dimensional model based on the bending amount of the blade at the corresponding location;

[0070] S202: Segment the elastically bent portion of the blade by distance s. Based on the blade bending conditions simulated in S201, obtain the bending amount of the blade at the segment points. Construct a mathematical model W based on the obtained information. i-1 =[arctan(h i / d i+1 )+arctan(h i+2 / d i+2)] / π, the bending degree of the blade at each segment point is determined, where i=1,2,…,m-1, represents the number corresponding to the segment point, m represents the total number of segment points, h i Indicates the bending amount corresponding to the i-th segment point position, d i+1 W represents the length of the arc formed between the i-th segment point and the i+1-th segment point of the blade when it is projected as a straight line. i-1 Indicates the bending degree corresponding to the segment point numbered i-1. When i=1, W i-1 =W0= arctan(h1 / d1) / π,W m =1-1.5*arctan(D / h m ), D represents the length of the arc formed between the mth segment point of the blade and the tip when projected as a straight line, 0<s<g, g represents the blade length;

[0071] S203: Compare the bending degree of the blade at each segment point determined in S202 with the critical bending degree. When the bending degree of the corresponding segment point is greater than or equal to the critical bending degree, it indicates that the corresponding segment point is a cracking point. When the bending degree of the corresponding segment point is less than the critical bending degree, it indicates that the corresponding segment point is not a cracking point. The cracking point of the blade is determined based on the comparison result. Combined with the bending degrees corresponding to the segment points before and after the cracking point, the crack length of the blade is predicted. The specific prediction formula A is:

[0072] A=M*s+W b *s+W b+M-1 *s;

[0073] Where M represents the number of cracking points on the leaf, b represents the number corresponding to the first cracking point on the leaf, and W b Indicates the bending degree corresponding to the segment point numbered b, W b+M-1 It represents the bending degree corresponding to the segment point numbered b+M-1, 1≤b<m, and A represents the predicted blade crack length.

[0074] S30: predicting the amount of water seepage into the blade cavity based on the crack length predicted in S20;

[0075] The specific method for predicting the water seepage in the blade cavity is:

[0076] The ratio of the blade crack length predicted in S203 to the blade length is used as the blade water seepage coefficient;

[0077] Determine whether the blade crack is located in the direction of rain or away from rain. If the blade crack is in the direction of away from rain, it means that the water seepage in the blade cavity can be ignored. If the blade crack is in the direction of rain, the product of the blade water seepage coefficient and the rainfall per unit time is calculated to obtain the water seepage in the blade cavity per unit time. Based on the rainfall time, the water seepage in the blade cavity can be predicted. When the blade crack is in the state of away from rain, rainwater will flow along the outer surface of the blade. When the rainwater flows, it is affected by gravity, wind, etc. Even if rainwater enters the blade cavity, the infiltration amount is very small and can be ignored.

[0078] S40: The early warning system selects whether to issue an early warning message based on the clearance distance predicted in S10 and the water seepage amount predicted in S30.

[0079] The S40 includes:

[0080] S401: Calculate the difference between the standard clearance distance and the actual clearance distance between the blade tip and the tower calculated in S104. If the difference is ≥ 2 / 3*standard clearance distance, the early warning system issues an early warning message. If the difference is < 2 / 3*standard clearance distance, the early warning system does not issue an early warning message.

[0081] S402: Calculate the product of the water seepage predicted in S30 and the expansion coefficient. If 0 < the calculated result < 2 / 3 * the blade cavity volume, the early warning system will not issue an early warning message. If 2 / 3 * the blade cavity volume ≤ the calculated result ≤ the blade cavity volume, the early warning system will issue an early warning message. The expansion coefficient refers to the ratio of the volume of ice to the volume of water after water freezes into ice.

[0082] A wind turbine blade monitoring system based on optical fiber technology, comprising a tower sweep monitoring module, a blade crack monitoring module, a blade water seepage prediction module, and an early warning module;

[0083] Distributed strain optical fibers are arranged laterally along the inner wall of the blade;

[0084] The tower-sweeping monitoring module is used to determine the location where the blade elastically bends based on the data collected by the distributed strain optical fiber. Based on the determination result, the maximum bending amount of the blade at the bending position at the next moment is predicted in combination with the rotation of the blade and the change in wind force. Based on the prediction result, the actual clearance distance between the blade tip and the tower is monitored, and the predicted maximum bending amount of the blade at the bending position at the next moment is transmitted to the blade tower-sweeping monitoring module, and the monitoring result is transmitted to the early warning module.

[0085] The tower sweep monitoring module includes an elastic bending position determination unit, a calculation unit, a prediction unit and a clearance distance determination unit;

[0086] When the wind turbine generator set is facing the wind, the elastic bending position determination unit acquires data monitored by the distributed strain optical fiber, compares the value acquired by the distributed strain optical fiber at the corresponding position with the critical value of elastic deformation of the blade at the corresponding position, and when the acquired value is greater than the critical value, determines that the blade has elastically bent at the corresponding position, and transmits the determined elastic bending position information to the calculation unit;

[0087] The calculation unit receives the determination result of the elastic bending position, and based on the received information, constructs a mathematical model maxX=(Ff) / k, calculates the maximum bending amount of the blade at the elastic bending position, and transmits the calculation result to the prediction unit, and transmits the constructed mathematical model to the blade crack monitoring module, wherein F represents the strain force monitored by the distributed strain optical fiber when the blade elastically bends, f represents the strain force monitored by the distributed strain optical fiber at the critical point, k represents the stiffness coefficient of the blade, and X represents the bending amount of the blade at the elastic bending position;

[0088] The prediction unit receives the calculation result transmitted by the calculation unit, obtains the real-time change of wind force and the change of the rotation speed of the blade under the action of wind force, predicts the change rate of wind force at the next moment according to the real-time change of wind force, and predicts the rotation speed of the blade at the next moment based on the predicted wind force change rate and the rotation speed of the blade at the current moment. According to the prediction result, a prediction model Q={[(1+(tt') / t')*V'] / V}*maxX is constructed to predict the maximum bending amount of the blade at the elastic bending position at the next moment, and the prediction result is transmitted to the clearance distance determination unit, wherein t represents the wind force value at the current moment, t' represents the wind force value at the previous moment, V' represents the rotation speed of the blade at the current moment, V represents the rotation speed of the blade when the wind turbine completes the wind, maxX represents the maximum bending amount of the blade at the elastic bending position, and Q represents the predicted maximum bending amount of the blade at the elastic bending position at the next moment;

[0089] The clearance distance determination unit receives the prediction result transmitted by the prediction unit, calculates the difference between the predicted maximum bending amount of the blade at the next moment and the standard clearance distance between the blade tip and the tower, obtains the actual clearance distance between the blade tip and the tower, and transmits the obtained actual clearance distance to the early warning module.

[0090] The blade crack monitoring module is used to receive the maximum bending amount of the blade at the bending position at the next moment transmitted by the tower sweep monitoring module, and based on the received information, determine whether the blade will have a crack at the corresponding bending position. If a crack occurs, the length of the crack is predicted and the prediction result is transmitted to the blade water seepage prediction module;

[0091] The blade crack monitoring module includes a simulation unit, a bending degree prediction unit and a blade crack length prediction unit;

[0092] The simulation unit receives the mathematical model transmitted by the calculation unit, calculates the bending amount of the blade at the elastic bending position according to the mathematical model X=(Ff) / k, simulates the bending condition of the blade in a three-dimensional model based on the bending amount of the blade at the corresponding position, and transmits the simulation result to the bending degree prediction unit;

[0093] The bending degree prediction unit receives the simulation results transmitted by the simulation unit, and segments the elastic bending part of the blade by distance s. Based on the simulated blade bending situation, the bending amount of the blade at the segment point is obtained, and a mathematical model W is constructed based on the obtained information. i-1 = [arctan(h i / d i+1 )+arctan(h i+2 / d i+2 )] / π, the bending degree of the blade at each segment point is determined, and the determined bending degree is transmitted to the blade crack length prediction unit, where i=1,2,…,m-1, represents the number corresponding to the segment point, m represents the total number of segment points, h i Indicates the bending amount corresponding to the i-th segment point position, d i+1 W represents the length of the arc formed between the i-th segment point and the i+1-th segment point of the blade when it is projected as a straight line. i-1 Indicates the bending degree corresponding to the segment point numbered i-1. When i=1, W i-1 =W0= arctan(h1 / d1) / π,W m =1-1.5*arctan(D / h m ), D represents the length of the arc formed between the mth segment point of the blade and the tip when projected as a straight line, 0<s<g, g represents the blade length;

[0094] The blade crack length prediction unit receives the bending degree of the blade at each segment point transmitted by the bending degree prediction unit, and compares the received bending degree of the blade at each segment point with the critical bending degree. When the bending degree of the corresponding segment point is ≥ the critical bending degree, it indicates that the corresponding segment point position is a cracking point. When the bending degree of the corresponding segment point is < the critical bending degree, it indicates that the corresponding segment point position is not a cracking point. The cracking point of the blade is determined according to the comparison result, and the mathematical model A=M*s+W is constructed in combination with the bending degrees corresponding to the segment points before and after the cracking point. b *s+W b+M-1*s, predict the crack length of the blade and transmit the predicted crack length to the blade water seepage prediction module, where M represents the number of crack points on the blade, b represents the number corresponding to the first crack point on the blade, and W b Indicates the bending degree corresponding to the segment point numbered b, W b+M-1 It represents the bending degree corresponding to the segment point numbered b+M-1, 1≤b<m, and A represents the predicted blade crack length.

[0095] The blade water seepage prediction module is used to receive the predicted crack length transmitted by the blade crack monitoring module, predict the water seepage in the blade cavity based on the received information, and transmit the prediction result to the early warning module;

[0096] The blade water seepage prediction module includes a blade water seepage coefficient determination unit, a judgment unit and a blade water seepage prediction unit;

[0097] The blade water seepage coefficient determination unit receives the predicted blade crack length transmitted by the blade crack length prediction unit, uses the ratio of the predicted blade crack length to the blade length as the blade water seepage coefficient, and transmits the determined blade water seepage coefficient to the blade water seepage amount prediction unit;

[0098] The judgment unit is used to judge whether the blade crack is located in the direction of rain or the direction of back rain. If the blade crack is in the direction of back rain, it means that the water seepage in the blade cavity is negligible. If the blade crack is in the direction of rain, the rainfall per unit time is transmitted to the blade water seepage prediction unit;

[0099] The blade water seepage prediction unit receives the blade water seepage coefficient transmitted by the blade water seepage coefficient determination unit and the rainfall per unit time transmitted by the judgment unit, calculates the product between the blade water seepage coefficient and the rainfall per unit time, obtains the water seepage in the blade cavity per unit time, predicts the water seepage in the blade cavity based on the rainfall time, and transmits the predicted water seepage in the blade cavity to the early warning module.

[0100] The early warning module is used to receive the monitoring results transmitted by the tower sweeping monitoring module and the prediction results transmitted by the blade water seepage prediction module, and choose whether to issue an early warning message based on the received information.

[0101] The early warning module includes a first early warning unit and a second early warning unit;

[0102] The first warning unit receives the actual clearance distance transmitted by the clearance distance determination unit, calculates the difference between the standard clearance distance and the received actual clearance distance, and issues a warning message when the difference is ≥ 2 / 3 * standard clearance distance;

[0103] The second early warning unit receives the predicted water seepage amount of the blade inner cavity transmitted by the blade water seepage prediction unit, calculates the product between the received water seepage amount of the blade inner cavity and the expansion coefficient, and issues an early warning message when 2 / 3*blade inner cavity volume ≤ calculated result ≤ blade inner cavity volume. The expansion coefficient refers to the ratio of the volume of ice to the volume of water after water freezes into ice.

[0104] It should be noted that, in this document, relational terms such as first and second, etc., are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus.

[0105] Finally, it should be noted that the above descriptions are merely preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art will be able to modify the technical solutions described in the aforementioned embodiments or substitute equivalents for some of the technical features. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention shall be included within the scope of protection of the present invention.

Claims

1. A wind turbine blade monitoring method based on optical fiber technology, characterized in that: The method comprises: S10: a distributed strain optical fiber is arranged laterally along the inner wall of the blade, and the position where the blade undergoes elastic bending is determined according to data collected by the distributed strain optical fiber. Based on the determination result, the maximum bending amount of the blade at the bending position at the next moment is predicted in combination with the rotation of the blade and the change of wind force. Based on the prediction result, the actual clearance distance between the blade tip and the tower is monitored; The S10 includes: S101: when the wind turbine generator set is facing the wind, the data monitored by the distributed strain optical fiber is acquired, the value acquired by the distributed strain optical fiber at the corresponding position is compared with the critical value of the elastic deformation of the blade at the corresponding position, and the position where the blade is elastically bent is determined according to the comparison result; S102: Calculate the maximum bending amount of the blade at the elastic bending position determined in S101 using the formula maxX=(Ff) / k, where F represents the strain force monitored by the distributed strain optical fiber when the blade is at the elastic bending position, f represents the strain force monitored by the distributed strain optical fiber at the critical point position, k represents the stiffness coefficient of the blade, and X represents the bending amount of the blade at the elastic bending position; S103: The real-time change of wind force and the change of the rotation speed of the blade under the action of wind force are obtained, and the change rate of wind force at the next moment is predicted according to the real-time change of wind force. Based on the predicted wind force change rate and the rotation speed of the blade at the current moment, the rotation speed of the blade at the next moment is predicted. According to the prediction result, the maximum bending amount of the blade at the elastic bending position at the next moment is predicted. The specific prediction formula Q is: Q={[(1+(tt') / t')*V'] / V}*maxX; Wherein, t represents the wind force value at the current moment, t' represents the wind force value at the previous moment, V' represents the rotation speed of the blade at the current moment, V represents the rotation speed of the blade when the wind turbine completes the wind, maxX represents the maximum bending amount of the blade at the elastic bending position, and Q represents the predicted maximum bending amount of the blade at the elastic bending position at the next moment; S104: Calculate the difference between the maximum bending amount of the blade at the next moment predicted in S103 and the standard clearance distance between the blade tip and the tower to obtain the actual clearance distance between the blade tip and the tower; S20: judging whether cracks will occur at the corresponding bending position of the blade according to the maximum bending amount of the blade at the bending position at the next moment predicted in S10, and predicting the length of the cracks if cracks occur; S201: calculating the bending amount of the blade at the position where elastic bending occurs according to the formula X=(Ff) / k, and simulating the bending condition of the blade in a three-dimensional model based on the bending amount of the blade at the corresponding position; S202: Segment the portion of the blade where elastic bending occurs according to the distance s, obtain the bending amount of the blade at the segmentation point based on the blade bending condition simulated in S201, and construct a mathematical model W based on the obtained information i-1 =[arctan(h i / d i+1 )+arctan(h i+2 / d i+2 )] / π, the bending degree of the blade at each segment point is determined, where i=1,2,…,m-1, represents the number corresponding to the segment point, m represents the total number of segment points, and h i represents the bending amount corresponding to the position of the i-th segment point, d i+1 W represents the length of the arc formed between the i-th segmentation point and the i+1-th segmentation point of the blade when it is projected as a straight line. i-1 Indicates the bending degree corresponding to the segment point numbered i-1. When i=1, W i-1 =W0 = arctan(h1 / d1) / π, W m =1-1.5*arctan(D / h m ), D represents the length of the arc formed between the mth segment point of the blade and the tip when it is projected as a straight line, 0<s<g, g represents the length of the blade; S203: Compare the bending degree of the blade at each segment point determined in S202 with the critical bending degree. When the bending degree of the corresponding segment point is ≥ the critical bending degree, it indicates that the corresponding segment point is a cracking point. When the bending degree of the corresponding segment point is < the critical bending degree, it indicates that the corresponding segment point is not a cracking point. The cracking point of the blade is determined according to the comparison result. Combined with the bending degrees corresponding to the segment points before and after the cracking point, the crack length of the blade is predicted. The specific prediction formula A is: A=M*s+W b *s+W b+M-1 *s; Where M represents the number of cracking points on the leaf, b represents the number corresponding to the first cracking point on the leaf, and W b Indicates the bending degree corresponding to the segment point numbered b, W b+M-1 It indicates the bending degree corresponding to the segment point numbered b+M-1, 1≤b<m, and A indicates the predicted blade crack length; S30: According to the crack length predicted in S20, the water seepage amount in the blade cavity is predicted, and the specific method is as follows: The ratio of the blade crack length predicted in S203 to the blade length is used as the blade water seepage coefficient; Determine whether the blade crack is in the direction facing the rain or the direction away from the rain. If the blade crack is in the direction away from the rain, it means that the water seepage in the blade cavity can be ignored. If the blade crack is in the direction facing the rain, the product of the blade water seepage coefficient and the rainfall per unit time is calculated to obtain the water seepage in the blade cavity per unit time. Based on the rainfall time, the water seepage in the blade cavity can be predicted. S40: The early warning system selects whether to issue an early warning message according to the clearance distance predicted in S10 and the water seepage volume predicted in S30.

2. The wind turbine blade monitoring method based on optical fiber technology according to claim 1 is characterized in that: The S40 includes: S401: Calculate the difference between the standard clearance distance and the actual clearance distance between the blade tip and the tower calculated in S104. If the difference is ≥ 2 / 3*standard clearance distance, the early warning system issues an early warning message. If the difference is < 2 / 3*standard clearance distance, the early warning system does not issue an early warning message. S402: Calculate the product of the water seepage predicted in S30 and the expansion coefficient. If 0<calculated result<2 / 3*blade inner cavity volume, the early warning system will not issue an early warning message. If 2 / 3*blade inner cavity volume≤calculated result≤blade inner cavity volume, the early warning system will issue an early warning message.

3. A wind turbine blade monitoring system based on optical fiber technology, which is used to implement the method of claim 2, characterized in that: The system includes a tower sweeping monitoring module, a blade crack monitoring module, a blade water seepage prediction module and an early warning module; Distributed strain optical fibers are arranged laterally along the inner wall of the blade; The tower scanning monitoring module is used to determine the position where the blade elastically bends according to the data collected by the distributed strain optical fiber, and based on the determination result, the maximum bending amount of the blade at the bending position at the next moment is predicted in combination with the rotation of the blade and the change of wind force, and based on the prediction result, the actual clearance distance between the blade tip and the tower is monitored, and the predicted maximum bending amount of the blade at the bending position at the next moment is transmitted to the blade tower scanning monitoring module, and the monitoring result is transmitted to the early warning module; The blade crack monitoring module is used to receive the maximum bending amount of the blade at the bending position at the next moment transmitted by the tower sweeping monitoring module, and judge whether the blade will have cracks at the corresponding bending position based on the received information. If cracks occur, the length of the cracks is predicted, and the prediction result is transmitted to the blade water seepage prediction module; The blade water seepage prediction module is used to receive the predicted crack length transmitted by the blade crack monitoring module, predict the water seepage amount of the blade cavity based on the received information, and transmit the prediction result to the early warning module; The early warning module is used to receive the monitoring results transmitted by the tower scanning monitoring module and the prediction results transmitted by the blade water seepage prediction module, and select whether to issue an early warning message based on the received information.

4. The wind turbine blade monitoring system based on optical fiber technology according to claim 3 is characterized in that: The tower sweeping monitoring module includes an elastic bending position determination unit, a calculation unit, a prediction unit and a clearance distance determination unit; The elastic bending position determination unit acquires data monitored by the distributed strain optical fiber when the wind turbine generator set is facing the wind, compares the value acquired by the distributed strain optical fiber at the corresponding position with the critical value of elastic deformation of the blade at the corresponding position, and determines that the blade is elastically bent at the corresponding position when the acquired value is greater than the critical value, and transmits the determined position information of the elastic bending to the calculation unit; The calculation unit receives the determination result of the elastic bending position, constructs a mathematical model maxX=(Ff) / k based on the received information, calculates the maximum bending amount of the blade at the elastic bending position, transmits the calculation result to the prediction unit, and transmits the constructed mathematical model to the blade crack monitoring module; The prediction unit receives the calculation result transmitted by the calculation unit, obtains the real-time change of wind force and the change of the rotation speed of the blade under the action of wind force, predicts the change rate of wind force at the next moment according to the real-time change of wind force, predicts the rotation speed of the blade at the next moment based on the predicted wind force change rate and the rotation speed of the blade at the current moment, constructs a prediction model Q={[(1+(tt') / t')*V'] / V}*maxX according to the prediction result, predicts the maximum bending amount of the blade at the elastic bending position at the next moment, and transmits the prediction result to the clearance distance determination unit; The clearance distance determination unit receives the prediction result transmitted by the prediction unit, calculates the difference between the predicted maximum bending amount of the blade at the next moment and the standard clearance distance between the blade tip and the tower, obtains the actual clearance distance between the blade tip and the tower, and transmits the obtained actual clearance distance to the early warning module.

5. The wind turbine blade monitoring system based on optical fiber technology according to claim 4 is characterized in that: The blade crack monitoring module includes a simulation unit, a bending degree prediction unit and a blade crack length prediction unit; The simulation unit receives the mathematical model transmitted by the calculation unit, calculates the bending amount of the blade at the position where elastic bending occurs according to the mathematical model X=(Ff) / k, simulates the bending condition of the blade in the three-dimensional model based on the bending amount of the blade at the corresponding position, and transmits the simulation result to the bending degree prediction unit; The bending degree prediction unit receives the simulation results transmitted by the simulation unit, performs segmentation processing on the part of the blade where elastic bending occurs according to the distance s, obtains the bending amount of the blade at the segmentation point based on the simulated blade bending situation, and constructs a mathematical model W based on the obtained information i-1 =[arctan(h i / d i+1 )+arctan(h i+2 / d i+2 )] / π, determining the bending degree of the blade at each segment point, and transmitting the determined bending degree to the blade crack length prediction unit; The blade crack length prediction unit receives the bending degree of the blade at each segment point transmitted by the bending degree prediction unit, and compares the received bending degree of the blade at each segment point with the critical bending degree. When the bending degree of the corresponding segment point is ≥ the critical bending degree, it indicates that the corresponding segment point position is a cracking point. When the bending degree of the corresponding segment point is < the critical bending degree, it indicates that the corresponding segment point position is not a cracking point. The cracking point of the blade is determined according to the comparison result, and a mathematical model A=M*s+W is constructed in combination with the bending degrees corresponding to the segment points before and after the cracking point. b *s+W b+M-1 *s, predict the crack length of the blade and transmit the predicted blade crack length to the blade water seepage prediction module.

6. The wind turbine blade monitoring system based on optical fiber technology according to claim 5 is characterized in that: The blade water seepage prediction module includes a blade water seepage coefficient determination unit, a judgment unit and a blade water seepage prediction unit; The blade water seepage coefficient determination unit receives the predicted blade crack length transmitted by the blade crack length prediction unit, takes the ratio of the predicted blade crack length to the blade length as the blade water seepage coefficient, and transmits the determined blade water seepage coefficient to the blade water seepage amount prediction unit; The judging unit is used to judge whether the position of the blade crack is in the direction facing the rain or in the direction away from the rain. If the blade crack is in the direction away from the rain, it means that the water seepage in the blade cavity can be ignored. If the blade crack is in the direction facing the rain, the rainfall per unit time is transmitted to the blade water seepage prediction unit. The blade water seepage prediction unit receives the blade water seepage coefficient transmitted by the blade water seepage coefficient determination unit and the rainfall per unit time transmitted by the judgment unit, calculates the product between the blade water seepage coefficient and the rainfall per unit time, obtains the water seepage amount in the blade cavity per unit time, predicts the water seepage amount in the blade cavity based on the rainfall time, and transmits the predicted water seepage amount in the blade cavity to the early warning module.

7. The wind turbine blade monitoring system based on optical fiber technology according to claim 6 is characterized in that: The early warning module includes a first early warning unit and a second early warning unit; The first warning unit receives the actual clearance distance transmitted by the clearance distance determination unit, calculates the difference between the standard clearance distance and the received actual clearance distance, and issues a warning message when the difference is ≥ 2 / 3*standard clearance distance; The second warning unit receives the predicted blade cavity water seepage amount transmitted by the blade water seepage amount prediction unit, calculates the product between the received blade cavity water seepage amount and the expansion coefficient, and issues a warning message when 2 / 3*blade cavity volume ≤ calculated result ≤ blade cavity volume.