A method for testing loosened zone of surrounding rock in tunnel

By establishing a tunnel finite element model and on-site data verification, the problem of predicting loose circles in the surrounding rock of the unexcavated tunnel is solved, and the accurate prediction and dynamic support optimization of loose circles are achieved, which reduces construction costs and improves safety.

CN117094057BActive Publication Date: 2024-11-19THE 5TH ENGINEERING CO LTD OF CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311058613.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-08-22
Publication Date
2024-11-19
Estimated Expiration
2043-08-22

AI Technical Summary

Technical Problem

The prior art cannot accurately predict the loose coils of the surrounding rock of the unexcavated tunnel, and the loose coil detection is dangerous when the tunnel just excavated does not reach a stable state, and the support parameters cannot be adjusted dynamically.

Method used

By establishing a tunnel finite element model, numerical simulation, verification and correction of the model based on the formation model and field data, and loose circle prediction and analysis are carried out until the error range is reached, and on-site detection is carried out in combination with acoustic well loggers and geological radars.

Benefits of technology

Accurate prediction of the loose ring of surrounding rock in unexcavated tunnels is achieved, preliminary support plans are dynamically optimized, project costs are reduced, construction costs are saved, and safety is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117094057B_ABST
    Figure CN117094057B_ABST
Patent Text Reader

Abstract

The invention discloses a method for testing the loosening zone of tunnel surrounding rock, which belongs to the technical field of tunnel mining, and comprises: establishing a tunnel model; assigning a value to a stratum model where the tunnel model is located based on the tunnel model to obtain a numerical model; verifying the numerical model according to field measured data, and if the numerical model does not meet the requirements, correcting the tunnel model until it meets the requirements; when the numerical model meets the requirements, numerically analyzing the size of the loosening zone of a selected tunnel section, and detecting the loosening zone at a corresponding position of the numerical model on site; comparing the calculated result of the numerical model with the field measured data, and if the comparison result is within a set error range, using the numerical model to predict the loosening zone of the surrounding rock of an un-excavated tunnel; by establishing a finite element model of the tunnel, the initial support scheme can be dynamically optimized according to the predicted loosening zone data, thereby greatly reducing the engineering cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel mining, and in particular to a method for testing a loosening zone of surrounding rock in a tunnel. Background Art

[0002] When drilling and blasting is used for rock tunnel construction, the shock waves and vibrations generated by tunnel blasting often damage the surrounding rock around the tunnel. The extent of tunnel surrounding rock damage is generally evaluated by the size of the surrounding rock loosening zone, and the initial tunnel support structure is designed based on the size of the loosening zone. Therefore, accurately measuring the loosening zone of the surrounding rock has important theoretical and engineering practice guiding significance.

[0003] At present, the commonly used testing methods for the loose zone of surrounding rock are mostly to use on-site detection of sonic detectors and geological radars or to adopt a combined testing method of the two methods to test the loose zone of tunnel surrounding rock.

[0004] However, the existing methods cannot make preliminary predictions for unexcavated areas. Since support must be carried out in a timely manner after excavation, there is no time to dynamically adjust the support parameters. In addition, the tunnel has not yet reached a stable state after excavation. At this time, conducting loose circle detection has certain risks for operators. Summary of the invention

[0005] In order to solve the problems of the prior art, the present invention provides a method for testing the loosening zone of surrounding rock in a tunnel, comprising the following steps:

[0006] Step 1: Establish a tunnel model;

[0007] Step 2: Based on the tunnel model, assign a value to the stratum model where the tunnel model is located to obtain a numerical model;

[0008] Step 3: verify the numerical model according to the field measured data. If the numerical model does not meet the requirements, modify the tunnel model until it meets the requirements.

[0009] When the numerical model meets the requirements, the size of the loose zone of the selected tunnel section is numerically analyzed, and the loose zone at the corresponding position of the numerical model is tested on site;

[0010] Step 4: Compare the calculated results of the numerical model with the measured data on site. If the comparison result is within the set error range, the numerical model is used to predict the loosening zone of the surrounding rock of the unexcavated tunnel, or the loosening zone range is calculated and analyzed for the part of the tunnel that has not completed the initial support after excavation;

[0011] If the comparison result exceeds the set error range, the numerical model is corrected until the comparison result is within the set error range, and the corrected numerical model is used to predict the loosening zone of the surrounding rock of the unexcavated tunnel, or to calculate and analyze the loosening zone range of the part of the tunnel after excavation that has not completed preliminary support.

[0012] Furthermore, in step 1, the tunnel model is established using finite element calculation software, including:

[0013] Establish a tunnel model, establish a stratum model of the tunnel according to geological exploration data, stratify the tunnel model based on the stratum model, determine the tunnel excavation model according to the on-site construction method and excavation technology, and then divide the tunnel cross section into four parts, and divide the tunnel model into unit groups according to the excavation footage;

[0014] According to the requirements of the initial support construction plan of the project department, support models are established in the tunnel model respectively.

[0015] Furthermore, the tunnel cross section was divided into four parts using a three-step temporary invert method.

[0016] Furthermore, in step 2, assigning a numerical model to the tunnel model includes:

[0017] By drilling and sampling at each location of each stratum and tunnel face on site, the surrounding rock mechanics test is carried out on the samples obtained to obtain the experimental mechanical parameters;

[0018] Determine the physical and mechanical parameters of the corresponding support materials through the material grades used in the support construction plan;

[0019] According to the experimental physical and mechanical parameters, the physical and mechanical parameters of each stratum in the stratum model are assigned corresponding values ​​to obtain a numerical model.

[0020] Furthermore, the step 2 further comprises: correcting the experimental physical and mechanical parameters according to the Hoek-Brown strength criterion to obtain actual physical and mechanical parameters;

[0021] According to the actual physical and mechanical parameters, corresponding values ​​are assigned to the physical and mechanical parameters of each stratum in the stratum model to obtain a numerical model.

[0022] Further, in step 3, the numerical model is verified based on field measured data, including;

[0023] Perform gravity balance calculation on the numerical model obtained in step 2;

[0024] Simulate excavation of the numerical model, remove the tunnel model, replace the physical and mechanical parameters of the surrounding rock with parameters corresponding to the initial support at the initial support position, obtain simulated construction parameters, and then calculate the displacement value of the surrounding rock of the simulated tunnel;

[0025] Carry out actual excavation according to the construction plan, remove the corresponding parts and units in the simulated excavation, and take initial support measures. Perform stress balance calculation during the excavation process to obtain the actual construction parameters, that is, the actual tunnel surrounding rock displacement value;

[0026] The simulated tunnel surrounding rock displacement value and the actual tunnel surrounding rock displacement value are verified and compared. If the displacement data error of the two is within the set range, it indicates that the data model is reliable; otherwise, the numerical model is re-established until the displacement data error of the two is within the set range.

[0027] Furthermore, the verification and comparison between the simulated tunnel surrounding rock displacement value and the actual tunnel surrounding rock displacement value selects the same section and mileage data of the numerical model and the actual excavated tunnel for verification and comparison.

[0028] Furthermore, in step 4, the numerical analysis of the size of the loose zone of the selected tunnel section includes:

[0029] A certain section mileage is selected in the numerical model, and the finite element software FLAC3D is used for simulation analysis to calculate the loose zone range of the tunnel section arch crown, arch span, arch waist, side wall and arch foot;

[0030] On-site detection of loose circles at corresponding positions of the numerical model, including:

[0031] The corresponding positions of the numerical model in the field are detected by using an acoustic logging instrument and / or a geological radar to obtain the range of the loose zone at the actual tunnel end face arch crown, arch shoulder, arch waist, side wall and arch foot.

[0032] Furthermore, the setting error range is 0-5%.

[0033] Beneficial effects of the present invention:

[0034] By establishing a finite element model of the tunnel, the loose zone of the unexcavated part of the tunnel can be predicted, so that the project department can dynamically optimize the initial support plan based on the predicted loose zone data, greatly reducing the project cost and saving construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0036] Figure 1 It is a schematic block diagram of the process provided by the present invention. DETAILED DESCRIPTION

[0037] To make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.

[0038] See also Figure 1 , a method for testing the loosening zone of surrounding rock in a tunnel, comprising the following steps:

[0039] Step 1: Establish tunnel model:

[0040] The tunnel model is established with the help of finite element calculation software. The specific process is as follows:

[0041] According to the nonlinear characteristics of rock materials, FLAC3D is widely used in geotechnical engineering, and the results calculated by the software can well reflect the actual effect of the project. Therefore, this method uses FLAC3D for numerical simulation analysis.

[0042] Since the FLAC3D software pre-operation needs to be realized through command stream, the operation is difficult and complicated, so the tunnel model is established with the help of Midas-gts;

[0043] The tunnel model is established for the stratum where the tunnel is located according to the geological exploration data of the project department, and the tunnel model is layered according to the actual situation. At the same time, the tunnel excavation model is determined according to the on-site construction method and excavation technology. The tunnel cross section is divided into four parts according to the three-step temporary invert method adopted by the project, and the tunnel model is divided into unit groups according to the requirements according to the excavation footage;

[0044] Among them, because the tunnel excavation in practice has a footage, the surrounding rock of a footage must be divided into a group. The purpose of this unit group is to excavate the tunnel according to the actual excavation plan; the unit group is necessary for model building. Each finite element model will be grouped according to the sequence of actual construction conditions to achieve a construction sequence consistent with the actual situation. In other words, in order to be consistent with the actual engineering construction sequence, the finite element model completes the division of different unit groups according to the stratum conditions, excavation cycle footage, and construction method;

[0045] According to the requirements of the initial support construction plan of the project department, the support measures were restored in different ways. The shotcrete was made of solid units, that is, the unit body was divided separately according to the construction requirements during the tunnel model establishment process. The anchor rods in the project were simulated using the built-in cable unit of the software. Most of the steel arches were simulated by increasing the elastic modulus of the initial support shotcrete within the corresponding range. The steel mesh was considered as a strength reserve because the software did not have a suitable unit type for simulation.

[0046] Step 2: Based on the tunnel model, assign a value to the stratum model where the tunnel model is located to obtain a numerical model;

[0047] The samples were drilled at various locations on site in various strata and tunnel faces, with a size of 50 mm in diameter and 100 mm in height, and transported to the indoor laboratory for surrounding rock mechanics tests;

[0048] The internal friction angle and cohesion parameter values ​​of the rock sample are determined according to the Mohr envelope diagram, and the elastic modulus and Poisson's ratio of the surrounding rock are calculated according to the stress-strain curve of the rock sample obtained from the test data. Then, according to the Hoek-Brown strength criterion, the physical and mechanical parameters measured in the laboratory are further matched with the site to finally obtain the actual physical and mechanical parameters of the surrounding rock site, which include deformation modulus, Poisson's ratio, cohesion, internal friction angle and density;

[0049] The material grades used in the initial support plan of the project were consulted in the relevant specifications to determine the physical quantities of concrete and anchor elastic modulus, density and Poisson's ratio, and the elastic modulus of the steel arch, the cross-sectional area of ​​the steel bars and the cross-sectional area of ​​the concrete were consulted as coefficients to convert the simulated effect of the steel arch into the concrete equivalently;

[0050] Finally, the physical and mechanical parameters of different strata are assigned corresponding values ​​through the command stream, including the tunnel model. After the tunnel model is excavated, the tunnel model is excavated, and the physical and mechanical parameters of the surrounding rock are replaced with the parameters corresponding to the initial support at the initial support position to achieve the effect of initial support in reality.

[0051] Step 3: Verify the numerical model based on the field measured data. If the numerical model does not meet the requirements, modify the tunnel model until it meets the requirements.

[0052] Because there is no gravity after the tunnel model is established, while gravity does exist in reality, gravity calculation must be performed first; gravity balance is to make this numerical model calculate under the condition of applying only gravity, so as to achieve the state of the tunnel project without excavation;

[0053] Specifically, after assigning values ​​to the physical and mechanical parameters of each stratum, the numerical model is first subjected to gravity balance calculation, that is, a force with a magnitude of gravity acceleration is applied vertically downward to the entire model until the calculation is completed;

[0054] According to the construction plan of the project department, excavation simulation is carried out. The actual excavation removes the corresponding units in the model. When the excavation work is completed, the initial support measures are taken in time. In the numerical model, the physical and mechanical parameters of the units at the initial support position are replaced, and the stress balance calculation is started until the tunnel excavation is completed;

[0055] The tunnel surrounding rock displacement values ​​calculated by the finite element software FLAC3D, including surface settlement, vault settlement and peripheral convergence, are compared and verified with the actual monitoring results of the on-site project department. The same section mileage in the numerical model and the actual one is selected for comparison. If the displacement data error is within 5%, it indicates that the numerical model is reliable and effective; otherwise, the numerical model establishment process is repeated, focusing on re-meshing and optimizing the connection parts of the unit groups until the two results are basically consistent.

[0056] Step 4: Compare the calculated results of the numerical model with the measured data on site. If the comparison result is within the set error range, the numerical model is used to predict the loosening zone of the surrounding rock of the unexcavated tunnel, or the loosening zone range is calculated and analyzed for the part of the tunnel that has not completed the initial support after excavation;

[0057] If the comparison result exceeds the set error range, the numerical model is corrected (the correction process is: the finite element solid model needs to be re-established to avoid overly sharp parts of the solid unit, pay attention to meshing, and focus on optimizing the connections between different solid units until the two results are basically consistent) until the comparison result is within the set error range, and the corrected numerical model is used to predict the loosening zone of the surrounding rock of the unexcavated tunnel, or to calculate and analyze the loosening zone range of the part of the tunnel after excavation that has not completed the initial support.

[0058] After completing the reliability verification of the numerical model, the loose circle detection index analysis is carried out. By selecting a certain mileage section, the finite element software FLAC3D is used for simulation analysis to calculate the loose circle range at the arch crown, arch span, arch waist, side wall and arch foot of the tunnel section;

[0059] At the same time, actual loosening zone detection is carried out on site, and the following should be followed during on-site detection: sonic logging instruments are used for measurement in places with relatively good lithology, less prone to borehole collapse, and strong water storage capacity; geological radar is used for detection in places with weak water storage capacity such as the crown and spandrels. Then, through post-data processing and analysis, the range of loosening zones at the crown, spandrel, waist, side wall and arch foot of the same section can be sorted out.

[0060] The loosening zone range calculated by the finite element software FLAC3D and the data obtained by on-site measurement are compared and analyzed. If the comparison error between the two results is within 5%, it is considered that the numerical model can well detect and predict the loosening zone range; if the error is too large, the numerical model is re-established, focusing on re-meshing and optimizing the connection parts of the unit group until the two results are basically consistent.

[0061] The project department uses numerical models to make preliminary predictions of loose zones in the unexcavated parts of the tunnel. It can also calculate and analyze the range of loose zones in the parts of the tunnel that have just been excavated but not yet completed with initial support, and dynamically set on-site support parameters to save construction costs. At the same time, regular on-site loose zone detection is carried out and compared with the existing numerical models to ensure the reliability of the model.

[0062] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for testing the loosening zone of surrounding rock in a tunnel, characterized in that: The following steps are involved: Step 1: Establish a tunnel model; The tunnel model is established by using finite element calculation software, including: establishing a tunnel model, establishing a tunnel model for the stratum where the tunnel is located according to the geological exploration data of the project department, stratifying the tunnel model according to the actual situation, and determining the tunnel excavation model according to the on-site construction method and excavation technology, dividing the tunnel cross section into four parts according to the three-step temporary invert method adopted by the project, and dividing the tunnel model into unit groups according to the requirements according to the excavation footage; According to the requirements of the initial support construction plan of the project department, support models are established in the tunnel model respectively; Among them, because the tunnel excavation in practice has a footage, the surrounding rock of a footage should be divided into a group. The purpose of this unit group is to excavate the tunnel according to the actual excavation plan; Step 2: Based on the tunnel model, assigning a value to the stratum model where the tunnel model is located, and obtaining a numerical model includes: By drilling and sampling at each location of each stratum and tunnel face on site, the surrounding rock mechanics test is carried out on the samples obtained to obtain the experimental physical and mechanical parameters; Determine the physical and mechanical parameters of the corresponding support materials through the material grades used in the support construction plan; According to the experimental physical and mechanical parameters, the physical and mechanical parameters of each stratum in the stratum model are assigned corresponding values ​​to obtain a numerical model; According to the Hoek-Brown strength criterion, the experimental physical and mechanical parameters are corrected to obtain actual physical and mechanical parameters; According to the actual physical and mechanical parameters, corresponding values ​​are assigned to the physical and mechanical parameters of each stratum in the stratum model to obtain a numerical model; Step 3: verify the numerical model according to the field measured data. If the numerical model does not meet the requirements, modify the tunnel model until it meets the requirements. When the numerical model meets the requirements, the size of the loose zone of the selected tunnel section is numerically analyzed, and the loose zone at the corresponding position of the numerical model is tested on site; The numerical model was validated based on field measured data, including; Perform gravity balance calculation on the numerical model obtained in step 2; Simulate excavation of the numerical model, remove the tunnel model, replace the physical and mechanical parameters of the surrounding rock with parameters corresponding to the initial support at the initial support position, obtain simulated construction parameters, and then calculate the displacement value of the surrounding rock of the simulated tunnel; Carry out actual excavation according to the construction plan, remove the corresponding parts and units in the simulated excavation, and take initial support measures. Perform stress balance calculation during the excavation process to obtain the actual construction parameters, that is, the actual tunnel surrounding rock displacement value; Verify and compare the displacement value of the surrounding rock of the simulated tunnel and the displacement value of the surrounding rock of the actual tunnel. If the displacement data error of the two is within the set range, it indicates that the data model is reliable; otherwise, the numerical model is re-established until the displacement data error of the two is within the set range; Step 4: Compare the calculated results of the numerical model with the measured data on site. If the comparison result is within the set error range, the numerical model is used to predict the loosening zone of the surrounding rock of the unexcavated tunnel, or the loosening zone range is calculated and analyzed for the part of the tunnel that has not completed the initial support after excavation; If the comparison result exceeds the set error range, the numerical model is corrected until the comparison result is within the set error range, and the corrected numerical model is used to predict the loosening zone of the surrounding rock of the unexcavated tunnel, or to calculate and analyze the loosening zone range of the part of the tunnel after excavation that has not completed preliminary support.

2. A tunnel surrounding rock loosening zone testing method according to claim 1, characterized in that: The verification and comparison between the simulated tunnel surrounding rock displacement value and the actual tunnel surrounding rock displacement value selects the same section and mileage data of the numerical model and the actual excavated tunnel for verification and comparison.

3. A tunnel surrounding rock loosening zone testing method according to claim 2, characterized in that: In step 4, the numerical analysis of the loose zone size of the selected tunnel section includes: A certain section mileage is selected in the numerical model, and the finite element software FLAC3D is used for simulation analysis to calculate the loose zone range of the tunnel section arch crown, arch span, arch waist, side wall and arch foot; On-site detection of loose circles at corresponding positions of the numerical model, including: The corresponding positions of the numerical model in the field are detected by using an acoustic logging instrument and / or a geological radar to obtain the range of the loose zone at the actual tunnel end face arch crown, arch shoulder, arch waist, side wall and arch foot.

4. A tunnel surrounding rock loosening zone testing method according to claim 1, characterized in that: The setting error range is 0-5%.