A method and system for collaborative control of energy storage power in renewable energy power generation configuration
By using a coordinated control method that combines new energy power generation with energy storage power, multiple control function modes can be automatically switched, improving the coordinated regulation performance of new energy power generation and energy storage systems, solving the problem of low energy storage utilization, and realizing the safe and stable operation of the power grid and the diversification of new energy revenue.
Patent Information
- Application Number
- CN202311244264.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-26
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2043-09-26
AI Technical Summary
When existing new energy power generation and energy storage systems are used in combination, the changes in grid operation demand are not fully considered, resulting in low energy storage utilization, inability to achieve multiple function regulation, and inability to fully stimulate the value of energy storage and diversify the revenue channels of new energy power generation.
A collaborative control method for energy storage power in conjunction with new energy power generation is designed. Through the power collaborative control system, multiple control function modes are automatically switched according to the operating status of new energy power generation and changes in grid demand, and the power regulation of the energy storage system is optimized. This includes emergency direct regulation control of energy storage system AGC, primary frequency regulation control of energy storage auxiliary station, AGC control of energy storage auxiliary station, and power prediction control of energy storage auxiliary station, so as to realize the collaborative control of new energy power station and energy storage system.
It has improved the active power regulation performance of new energy power generation, increased the functional value and benefits of energy storage systems, ensured the safe and stable operation of the power grid, enhanced the grid-source coordination capability, and realized the diversification of revenue channels for new energy power generation and the maximization of energy storage functions.
Smart Images

Figure CN117293864B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of renewable energy power generation, and specifically relates to a method and system for collaborative control of energy storage power in renewable energy power generation configuration. Background Art
[0002] The large-scale access of renewable energy power generation to the power grid has brought certain challenges to the safe and stable operation of the power grid due to its discontinuous and unstable non-steady-state characteristics. New energy storage technology, with its advantages such as flexible adjustment capabilities, has gradually become a key link in building a new power system and promoting the green and low-carbon transformation of energy. The configuration of renewable energy power generation with energy storage systems can improve the output characteristics of renewable energy power generation, thereby alleviating the problem of uneven distribution of power in the power system in time and space, which is conducive to ensuring a stable supply of electricity and improving the utilization rate of renewable energy power generation.
[0003] At present, many regions have made clear requirements for the configuration of energy storage capacity for centralized renewable energy power generation and grid connection, but the configuration of energy storage for renewable energy power generation is still in the early stages of development, and some regions have the problem of "built but not used". Under the guidance of the existing market mechanism, the joint operation of renewable energy power generation and energy storage systems can obtain economic benefits of auxiliary services by improving the accuracy of power prediction, improving the performance of station AGC and primary frequency regulation, etc. However, most projects only achieve single functional regulation, and do not fully consider the impact of renewable energy power generation operation status and changes in grid operation demand on energy storage utilization, and cannot fully stimulate the value of multiple reuse functions of energy storage to achieve the diversification of renewable energy power generation revenue channels and maximize the value of energy storage functions.
[0004] Therefore, how to carry out multifunctional and efficient coordinated control of energy storage supporting new energy power generation has become a technical problem that needs to be solved. Summary of the invention
[0005] Purpose: In view of at least one of the above technical problems, the present invention provides a method and system for coordinated control of energy storage power configured with renewable energy power generation, which realizes automatic switching of multi-function control modes based on the operating status of renewable energy power generation and changes in grid operation requirements, improves the active power regulation performance of renewable energy power generation and the value of energy storage functions, and ensures safe and stable operation of the grid.
[0006] Technical solution: To solve the above technical problems, the technical solution adopted by the present invention is:
[0007] In a first aspect, the present invention provides a method for collaboratively controlling energy storage power in a renewable energy power generation configuration, comprising:
[0008] Step 1: The power coordinated control system communicates with the station remote communication terminal RTU and the power prediction system to receive relevant control instructions; then the total power control target instruction P is calculated according to different control function modes. Σ, forwarded to the energy management system of the new energy power generation unit and the energy storage energy management system by means of communication through the in-station device; wherein the control function mode includes four functions: AGC emergency direct regulation control of the energy storage system, primary frequency regulation control of the energy storage auxiliary station, AGC control of the energy storage auxiliary station, and power prediction control of the energy storage auxiliary station;
[0009] Step 2: Dynamically collect the current and voltage of the grid connection point of the new energy station and the grid connection point of the energy storage system, calculate the active power of the grid connection point of the new energy station, the grid frequency and the active power of the grid connection point of the energy storage system in real time, and send them to the synchronous phasor measurement unit PMU substation of the new energy station. The substation is directly uploaded to the dispatching PMU master station through the PMU substation for the evaluation and calculation of the whole station AGC, primary frequency regulation, power prediction and energy storage system AGC emergency direct regulation control performance;
[0010] Step 3: The power coordination control system involves designing four functions, including the AGC emergency direct regulation control of the energy storage system, the primary frequency regulation control of the energy storage auxiliary station, the AGC control of the energy storage auxiliary station, and the power prediction control of the energy storage auxiliary station. Multiple functional modules are put into use separately or simultaneously according to the operation requirements of the new energy station. The system automatically switches functions according to the operation status of the new energy power generation and the changes in the operation requirements of the power grid.
[0011] Step 4: Under different control function modes, the power cooperative control system can automatically optimize and distribute the power to the energy management system of each power generation unit according to the operating status of the new energy power generation unit and the energy storage. The energy management system of each power generation unit can quickly receive and execute the power control command to achieve the coordinated control of the power regulation of the new energy station and the energy storage system; wherein the control function mode includes four functions: AGC emergency direct regulation control of the energy storage system, primary frequency regulation control of the energy storage auxiliary station, AGC control of the energy storage auxiliary station, and power prediction control of the energy storage auxiliary station;
[0012] Step 5: The power cooperative control system sends the control instruction P to the energy storage energy management system. ES It should be constrained by the regulation capability of the energy storage system and the capacity of the primary equipment within the station to avoid the energy storage system regulation speed being unable to track the rapid changes in active power instructions and to avoid safety problems in the energy storage system and new energy stations.
[0013] In some embodiments, step 1 comprises:
[0014] The power cooperative control system receives the remote control command signals of the whole station AGC control, the energy storage system AGC emergency direct control control, the whole station AGC request input, and the energy storage system AGC emergency direct control request input from the dispatching master station through the station telecontrol terminal RTU device;
[0015] According to the relevant control function requirements, the power control total target instruction P is formed Σ ;
[0016] The power cooperative control system is responsible for the overall power control target instruction P Σ Calculation and allocation are performed and sent to the energy management system of the new energy power generation unit and the energy storage energy management system. Each energy management system then controls the wind turbines, photovoltaic inverters and energy storage PCS equipment in the station to ultimately achieve rapid power regulation.
[0017] In some embodiments, step 3 includes: the power coordinated control system design includes four functions including energy storage system AGC emergency direct regulation control, energy storage auxiliary station primary frequency regulation control, energy storage auxiliary station AGC control, and energy storage auxiliary station power prediction control;
[0018] When more than two functions are put into operation, the system executes in the priority order of energy storage system AGC emergency direct control > energy storage auxiliary station primary frequency regulation control > energy storage auxiliary station AGC control > energy storage auxiliary station power prediction control.
[0019] Furthermore, in some embodiments, after the AGC emergency direct regulation control function of the energy storage system is put into operation, the power cooperative control system sends a "AGC emergency direct regulation control function of the energy storage system has been put into operation" signal to the dispatching master station through the station RTU, which indicates that the energy storage system of the new energy station has the ability to be emergency directly regulated by the AGC of the power grid dispatching organization; when the power grid fails or there is an operation risk, the dispatching master station sends a "AGC emergency direct regulation request for energy storage system" signal through the station RTU according to the status information sent by the energy storage system. After the power cooperative control system receives the "AGC emergency direct regulation request for energy storage system" instruction, the new energy station operator operates the AGC emergency direct regulation function switch button of the energy storage system in the system again, and the power cooperative control system enters the AGC emergency direct regulation control mode of the energy storage system, and controls the remote regulation instruction P according to the AGC control remote regulation instruction P of the energy storage system. agc The energy storage system control target instruction P is calculated by the active power P0' of the energy storage system station and the grid connection point ES , ensuring the safe and stable operation of the power grid.
[0020] Furthermore, in some embodiments, in the energy storage auxiliary station AGC control mode, the power cooperative control system is based on the whole station AGC control instruction P AGC , the active power P0 of the whole station and the active power P0 of the new energy station are calculated to obtain the total target power control instruction P Σ ; Set the power control total target instruction P Σ Prioritize the optimization of allocation to the energy management system of the new energy power generation unit for active power regulation, monitor the active power output of the new energy station in real time, and dynamically correct the control instructions P sent to the energy storage energy management system ES =P Σ-P0", improves the AGC control response speed and accuracy of the entire station through rapid adjustment of the energy storage system.
[0021] Furthermore, in some embodiments, the energy storage assists the station in primary frequency regulation control mode:
[0022] When the power grid system frequency is abnormal, the power cooperative control system calculates the primary frequency regulation load instruction ΔP according to the power grid frequency measurement value f measured at the grid connection points of the entire station and the active power-frequency droop control:
[0023]
[0024] Where: ΔP is the primary frequency modulation power command (MW), f d is the primary frequency modulation dead zone, P N is the rated power of the new energy station (MW), f N is the rated frequency of the power grid system (Hz), δ is the regulation rate (%), and f is the measured value of the power grid frequency;
[0025] According to the primary frequency regulation load instruction ΔP and the whole station AGC control instruction, the total power control target instruction P is calculated. Σ ;
[0026] The power cooperative control system gives priority to the power control total target instruction P Σ Optimize the allocation to the energy management system of the new energy power generation unit for active power regulation, monitor the active power output of the new energy station in real time, and dynamically correct the control instructions P sent to the energy storage energy management system ES =P Σ -P0", the rapid adjustment of the energy storage system is used to assist in achieving rapid response of the primary frequency regulation of the entire station.
[0027] Furthermore, if the capacity of the energy storage system meets the primary frequency regulation capacity requirement, the power cooperative control system responds to the primary frequency regulation load instruction ΔP alone, specifically including:
[0028] During the primary frequency regulation action, the new energy generation unit blocks the load change, and the energy storage system performs a frequency regulation dynamic response P alone. ES =ΔP, giving full play to the millimeter-level rapid response capability of energy storage, can effectively reduce the mechanical wear and power loss caused by the frequent participation of new energy power generation in the primary frequency regulation of the power grid.
[0029] Further, in some embodiments, after the energy storage auxiliary station power prediction control function is put into use, when the new energy station AGC is in free power generation mode, the power coordination control system automatically enters the energy storage auxiliary station power prediction control mode;
[0030] The power cooperative control system and the power prediction system communicate in real time using SFTP. The power cooperative control system receives the information transmitted by the power prediction system and reads the power prediction value P forecast As the power control total target instruction P Σ The energy storage system realizes accurate power prediction and tracking and bidirectional energy output according to the actual power input of renewable energy power generation. ES =P forecast -P Collectingline, At the same time, the power cooperative control system converts the active power P of the new energy generation collection line Collectingline It is superimposed with the active power P0' of the energy storage grid-connected point and sent to the dispatching master station as the power forecast assessment calculation value for the entire station.
[0031] In some embodiments, step 5, the power cooperative control system sends a control instruction P to the energy storage energy management system. ES It should be subject to the regulation capacity of the energy storage system and the capacity of the primary equipment in the station, including:
[0032] The power cooperative control system obtains the energy storage system capacity and primary equipment capacity status information from the energy storage energy management system;
[0033] According to the capacity of the energy storage system and the capacity status information of the primary equipment, the maximum allowable charging power value P of the energy storage system is calculated. max-c and the maximum allowable discharge power of the energy storage system P max-f ;
[0034] The control instructions of the energy storage energy management system should meet P max-c ≤P ES ≤P max-f , to avoid the energy storage system's adjustment speed being unable to track the rapid changes in active power instructions, and to avoid safety problems in the energy storage system and new energy stations.
[0035] In a second aspect, the present invention provides a new energy power generation configuration energy storage power collaborative control system, including a power collaborative control system; the power collaborative control system is deployed on the upper layer of the new energy power generation unit energy management system and the energy storage energy management system, and the power collaborative control system interacts with the station RTU, the new energy power generation unit energy management system and the energy storage energy management system respectively, and is connected to the new energy station power prediction system; it also includes a processor and a storage medium;
[0036] The storage medium is used to store instructions;
[0037] The processor is used to operate according to the instructions to execute the steps of the method according to the first aspect.
[0038] The power cooperative control system is configured as follows:
[0039] Dynamically collect the current and voltage of the grid connection point of the new energy station, calculate the active power and grid frequency of the grid connection point in real time, receive the station-wide automatic power generation control AGC instructions issued by the dispatching master station through the station RTU, and dynamically correct the energy storage power control target value according to the operating status of the new energy power generation unit, to help improve the power regulation performance of the whole station;
[0040] Based on the measured grid frequency, the primary frequency regulation control instructions are dynamically calculated to assist the entire station in quickly participating in the primary frequency regulation response of the grid;
[0041] Obtain the power forecast target value from the power forecast system of the new energy station. When the new energy station is in the free power generation mode, smooth the active power output of the new energy station, assist in improving the power forecast accuracy, and reduce the power forecast deviation assessment of the whole station;
[0042] Dynamically collect the current and voltage of the grid connection point in the energy storage system station, calculate the active power of the grid connection point in real time, receive the AGC emergency direct adjustment control instructions of the energy storage system issued by the dispatching master station through the remote communication terminal RTU, and participate in the AGC emergency direct adjustment of the power grid under special circumstances of power grid operation to ensure the safe and stable operation of the power grid;
[0043] The power collaborative control system generates power control instructions for the energy storage system from four methods, including the dispatching master station, the power prediction system of the new energy site, or local calculation, thereby effectively improving the active power regulation performance of the power grid.
[0044] In a third aspect, the present invention provides a storage medium having a computer program stored thereon, wherein the computer program, when executed by a processor, implements the steps of the method described in the first aspect.
[0045] In a fourth aspect, the present invention provides a device, comprising:
[0046] One or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and are configured to be executed by the one or more processors, and the one or more programs include instructions for executing any of the methods described in the first aspect.
[0047] Beneficial effects: The method, device, equipment and storage medium for coordinated control of energy storage power in new energy power generation provided by the present invention have the following advantages: In view of the current situation that the supporting energy storage application mode on the new energy station side is single and the economy is not high, the present invention utilizes the advantages of energy storage such as rapid response, precise tracking and bidirectional energy output to assist new energy stations in greatly improving power regulation performance, making up for the impact and influence of fluctuations in new energy power generation on the power grid, and effectively improving the economic benefits obtained by new energy stations when participating in power grid AGC, primary frequency regulation, and power forecasting assessment, thereby realizing the diversification of new energy power generation revenue channels and maximizing the value of energy storage functions, which is of great significance to improving the network source coordination capability and ensuring the safe and stable operation of the power grid. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] Figure 1 A schematic diagram of the topological architecture of a new energy side energy storage power regulation collaborative control system according to an embodiment of the present invention;
[0049] Figure 2 A schematic diagram of information collection of energy storage grid connection points on the new energy side according to an embodiment of the present invention;
[0050] Figure 3 Schematic diagram of the control strategy of the energy storage power coordination control function on the new energy side according to an embodiment of the present invention. DETAILED DESCRIPTION
[0051] The present invention will be further described below in conjunction with the accompanying drawings and embodiments. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.
[0052] In the description of the present invention, "several" means more than one, "many" means more than two, "greater than", "less than", "exceed", etc. are understood to exclude the number itself, and "above", "below", "within", etc. are understood to include the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0053] In the description of the present invention, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0054] Example 1
[0055] like Figure 1 As shown in the figure, a new energy-energy storage power collaborative control system is established in the new energy station. The system is deployed on the upper layer of the new energy power generation unit energy management system and the energy storage energy management system. It dynamically collects the current and voltage of the grid connection point of the new energy station, calculates the active power and grid frequency of the grid connection point in real time, and receives the full-station AGC (Automatic Generation) issued by the dispatching master station through the RTU (Remote Terminal Unit, telecontrol communication terminal). The system uses automatic power generation control (APC) control instructions to dynamically correct the target value of energy storage power control according to the operating status of the new energy power generation unit, and assist in improving the power regulation performance of the entire station. The system is also designed to dynamically calculate the primary frequency regulation control instructions based on the measured grid frequency, and assist the entire station to quickly participate in the primary frequency regulation response of the grid. At the same time, the system also obtains the power prediction target value from the power prediction system of the new energy station. When the new energy station is in the free power generation mode, it smoothes the active power output of the new energy station, assists in improving the power prediction accuracy, and reduces the power prediction deviation assessment of the entire station. In addition, the system also dynamically collects the current and voltage of the energy storage system at the grid connection point in the station, calculates the active power of the energy storage system at the grid connection point in real time, receives the AGC emergency direct regulation control instructions of the energy storage system issued by the dispatching master station through the RTU, and participates in the AGC emergency direct regulation of the grid in special circumstances to ensure the safe and stable operation of the grid. In general, this method enables the power collaborative control system to form the power control instructions of the energy storage system from four methods, such as the dispatching master station, the power prediction system of the new energy station, or local calculation, thereby effectively improving the active power regulation performance of the grid.
[0056] A method for collaboratively controlling energy storage power in a renewable energy power generation configuration, comprising:
[0057] Step 1: The power coordinated control system communicates with the station remote communication terminal RTU and the power prediction system to receive relevant control instructions; then the total power control target instruction P is calculated according to different control function modes. Σ , forwarded to the energy management system of the new energy power generation unit and the energy storage energy management system by means of communication through the in-station device; wherein the control function mode includes four functions: AGC emergency direct regulation control of the energy storage system, primary frequency regulation control of the energy storage auxiliary station, AGC control of the energy storage auxiliary station, and power prediction control of the energy storage auxiliary station;
[0058] Step 2: Dynamically collect the current and voltage of the grid connection point of the new energy station and the grid connection point of the energy storage system, calculate the active power of the grid connection point of the new energy station, the grid frequency and the active power of the grid connection point of the energy storage system in real time, and send them to the synchronous phasor measurement unit PMU substation of the new energy station. The substation is directly uploaded to the dispatching PMU master station through the PMU substation for the evaluation and calculation of the whole station AGC, primary frequency regulation, power prediction and energy storage system AGC emergency direct regulation control performance;
[0059] Step 3: The power coordination control system involves designing four functions, including the AGC emergency direct regulation control of the energy storage system, the primary frequency regulation control of the energy storage auxiliary station, the AGC control of the energy storage auxiliary station, and the power prediction control of the energy storage auxiliary station. Multiple functional modules are put into use separately or simultaneously according to the operation requirements of the new energy station. The system automatically switches functions according to the operation status of the new energy power generation and the changes in the operation requirements of the power grid.
[0060] Step 4: Under different control function modes, the power cooperative control system can automatically optimize and distribute the power to the energy management system of each power generation unit according to the operating status of the new energy power generation unit and the energy storage. The energy management system of each power generation unit can quickly receive and execute the power control command to achieve the coordinated control of the power regulation of the new energy station and the energy storage system; wherein the control function mode includes four functions: AGC emergency direct regulation control of the energy storage system, primary frequency regulation control of the energy storage auxiliary station, AGC control of the energy storage auxiliary station, and power prediction control of the energy storage auxiliary station;
[0061] Step 5: The power cooperative control system sends the control instruction P to the energy storage energy management system. ES It should be constrained by the regulation capability of the energy storage system and the capacity of the primary equipment within the station to avoid the energy storage system regulation speed being unable to track the rapid changes in active power instructions and to avoid safety problems in the energy storage system and new energy stations.
[0062] In some embodiments, step 1 comprises:
[0063] The power cooperative control system receives the remote control command signals of the whole station AGC control, the energy storage system AGC emergency direct control control, the whole station AGC request input, and the energy storage system AGC emergency direct control request input from the dispatching master station through the station telecontrol terminal RTU device via the IEC104 protocol and other means;
[0064] According to the relevant control function requirements, the power control total target instruction P is formed Σ ;
[0065] The power cooperative control system is responsible for the overall power control target instruction P Σ Calculation and allocation are carried out, and then quickly sent to the energy management system of the new energy power generation unit and the energy storage energy management system through communication protocols such as GOOSE. Each energy management system then controls the wind turbines, photovoltaic inverters, energy storage PCS and other equipment in the station to ultimately achieve rapid power regulation.
[0066] Step 2 Figure 2The power coordination control system dynamically collects the current and voltage information of the grid connection points of the whole new energy station and the grid connection points of the energy storage system, calculates the active power and frequency of the grid connection points of the whole station and the active power of the grid connection points of the energy storage system in real time, and sends it to the PMU substation of the new energy station by means of 26865.2 protocol or 4-20mA hard wiring, and directly uploads it to the dispatching WAMS main station through the PMU substation for the evaluation and calculation of the whole station AGC, primary frequency regulation, power prediction and energy storage system AGC emergency direct regulation control performance.
[0067] In some embodiments, step 3 includes: the power coordinated control system design includes four functions including energy storage system AGC emergency direct regulation control, energy storage auxiliary station primary frequency regulation control, energy storage auxiliary station AGC control, and energy storage auxiliary station power prediction control;
[0068] When more than two functions are put into operation, the system executes in the priority order of energy storage system AGC emergency direct control > energy storage auxiliary station primary frequency regulation control > energy storage auxiliary station AGC control > energy storage auxiliary station power prediction control.
[0069] Furthermore, in some embodiments, after the AGC emergency direct regulation control function of the energy storage system is put into operation, the power cooperative control system sends a "AGC emergency direct regulation control function of the energy storage system has been put into operation" signal to the dispatching master station through the station RTU, which indicates that the energy storage system of the new energy station has the ability to be emergency directly regulated by the AGC of the power grid dispatching organization; when the power grid fails or there is an operation risk, the dispatching master station sends a "AGC emergency direct regulation request for energy storage system" signal through the station RTU according to the status information sent by the energy storage system. After the power cooperative control system receives the "AGC emergency direct regulation request for energy storage system" instruction, the new energy station operator operates the AGC emergency direct regulation function switch button of the energy storage system in the system again, and the power cooperative control system enters the AGC emergency direct regulation control mode of the energy storage system, and controls the remote regulation instruction P according to the AGC control remote regulation instruction P of the energy storage system. agc The energy storage system control target instruction P is calculated by the active power P0' of the energy storage system station and the grid connection point ES , ensuring the safe and stable operation of the power grid.
[0070] Furthermore, in some embodiments, in the energy storage auxiliary station AGC control mode, the power cooperative control system is based on the whole station AGC control instruction P AGC , the active power P0 of the whole station and the active power P0 of the new energy station are calculated to obtain the total target power control instruction P Σ ; Set the power control total target instruction P Σ Prioritize the optimization of allocation to the energy management system of the new energy power generation unit for active power regulation, monitor the active power output of the new energy station in real time, and dynamically correct the control instructions P sent to the energy storage energy management systemES =P Σ -P0", improves the AGC control response speed and accuracy of the entire station through rapid adjustment of the energy storage system.
[0071] Furthermore, in some embodiments, the energy storage assists the station in primary frequency regulation control mode:
[0072] When the power grid system frequency is abnormal, the power cooperative control system calculates the primary frequency regulation load instruction ΔP according to the power grid frequency measurement value f measured at the grid connection points of the entire station and the active power-frequency droop control:
[0073]
[0074] Where: ΔP is the primary frequency modulation power command (MW), f d is the primary frequency modulation dead zone, P N is the rated power of the new energy station (MW), f N is the rated frequency of the power grid system (Hz), δ is the regulation rate (%), and f is the measured value of the power grid frequency;
[0075] According to the primary frequency regulation load instruction ΔP and the whole station AGC control instruction, the total power control target instruction P is calculated. Σ ;
[0076] The power cooperative control system gives priority to the power control total target instruction P Σ Optimize the allocation to the energy management system of the new energy power generation unit for active power regulation, monitor the active power output of the new energy station in real time, and dynamically correct the control instructions P sent to the energy storage energy management system ES =P Σ -P0", the rapid adjustment of the energy storage system is used to assist in achieving rapid response of the primary frequency regulation of the entire station.
[0077] Furthermore, if the capacity of the energy storage system meets the primary frequency regulation capacity requirement, the power cooperative control system responds to the primary frequency regulation load instruction ΔP alone, specifically including:
[0078] During the primary frequency regulation action, the new energy generation unit blocks the load change, and the energy storage system performs a frequency regulation dynamic response P alone. ES =ΔP, giving full play to the millimeter-level rapid response capability of energy storage, can effectively reduce the mechanical wear and power loss caused by the frequent participation of new energy power generation in the primary frequency regulation of the power grid.
[0079] Further, in some embodiments, after the energy storage auxiliary station power prediction control function is put into use, when the new energy station AGC is in free power generation mode, the power coordination control system automatically enters the energy storage auxiliary station power prediction control mode;
[0080] The power cooperative control system and the power prediction system communicate in real time using SFTP. The power cooperative control system receives the information transmitted by the power prediction system and reads the power prediction value P forecast As the power control total target instruction P Σ The energy storage system realizes accurate power prediction and tracking and bidirectional energy output according to the actual power input of renewable energy power generation. ES =P forecast -P Collecting line, At the same time, the power cooperative control system converts the active power P of the new energy generation collection line Collecting line It is superimposed with the active power P0' of the energy storage grid-connected point and sent to the dispatching master station as the power forecast assessment calculation value for the entire station.
[0081] In the assessment of power auxiliary services, power forecast assessment can usually be divided into different assessment methods such as medium-term and ultra-short-term. The power cooperative control system adopts a multi-objective optimization algorithm according to different grid assessment requirements and assessment calculation methods under different assessment methods to automatically optimize the total power control target instruction P Σ , helping to minimize the power forecast and assessment of new energy stations.
[0082] In different control function modes described in step 4, the power control total target instruction calculation and automatic switching are as follows: Figure 3 When no coordinated control function is put into use, the power coordinated control system is in the local control operation mode, and the operator can manually set and send power control instructions to the energy management system of each power generation unit to solve the problem of flexible power regulation and control of new energy stations when some power generation units fail or are under maintenance.
[0083] In some embodiments, in step 5, to ensure the safety of the energy storage system during rapid power regulation, the power cooperative control system sends a control instruction P to the energy storage energy management system. ES It should be subject to the regulation capacity of the energy storage system and the capacity of the primary equipment in the station, including:
[0084] The power cooperative control system obtains the energy storage system capacity and primary equipment capacity status information from the energy storage energy management system;
[0085] According to the capacity of the energy storage system and the capacity status information of the primary equipment, the maximum allowable charging power value P of the energy storage system is calculated. max-c and the maximum allowable discharge power of the energy storage system P max-f ;
[0086] The control instructions of the energy storage energy management system should meet P max-c ≤P ES ≤P max-f, to prevent the energy storage system from adjusting its speed and failing to track the rapid changes in active power instructions, and to avoid safety problems in the energy storage system and new energy stations.
[0087] The technology of the present invention can utilize the advantages of energy storage such as rapid response, precise tracking and bidirectional energy output, assist new energy sites to greatly improve power regulation performance, compensate for the impact and influence of fluctuations in new energy power generation on the power grid, and effectively improve the economic benefits obtained by new energy sites when participating in power grid AGC, primary frequency regulation, and power forecast assessment, thereby achieving the diversification of new energy power generation revenue channels and maximizing the value of energy storage functions, which is of great significance to improving the network source coordination capability and ensuring the safe and stable operation of the power grid.
[0088] Example 2
[0089] Second, as Figure 1 As shown, this embodiment provides a new energy power generation configuration energy storage power collaborative control system, including a power collaborative control system; the power collaborative control system is deployed on the upper layer of the new energy power generation unit energy management system and the energy storage energy management system, and the power collaborative control system interacts with the site RTU, the new energy power generation unit energy management system and the energy storage energy management system respectively, and is connected to the new energy site power prediction system; it also includes a processor and a storage medium;
[0090] The storage medium is used to store instructions;
[0091] The processor is used to operate according to the instructions to execute the steps of the method according to the first aspect.
[0092] The power cooperative control system is configured as follows:
[0093] Dynamically collect the current and voltage of the grid connection point of the new energy station, calculate the active power and grid frequency of the grid connection point in real time, receive the station-wide automatic power generation control AGC instructions issued by the dispatching master station through the station RTU, and dynamically correct the energy storage power control target value according to the operating status of the new energy power generation unit, to help improve the power regulation performance of the whole station;
[0094] Based on the measured grid frequency, the primary frequency regulation control instructions are dynamically calculated to assist the entire station in quickly participating in the primary frequency regulation response of the grid;
[0095] Obtain the power forecast target value from the power forecast system of the new energy station. When the new energy station is in the free power generation mode, smooth the active power output of the new energy station, assist in improving the power forecast accuracy, and reduce the power forecast deviation assessment of the whole station;
[0096] Dynamically collect the current and voltage of the grid connection point in the energy storage system station, calculate the active power of the grid connection point in real time, receive the AGC emergency direct adjustment control instructions of the energy storage system issued by the dispatching master station through the remote communication terminal RTU, and participate in the AGC emergency direct adjustment of the power grid under special circumstances of power grid operation to ensure the safe and stable operation of the power grid;
[0097] The power collaborative control system generates power control instructions for the energy storage system from four methods, including the dispatching master station, the power prediction system of the new energy site, or local calculation, thereby effectively improving the active power regulation performance of the power grid.
[0098] Example 3
[0099] In a third aspect, this embodiment provides a storage medium on which a computer program is stored. When the computer program is executed by a processor, the steps of the method described in Example 1 are implemented.
[0100] Example 4
[0101] In a fourth aspect, the present invention provides a device, comprising:
[0102] One or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and are configured to be executed by the one or more processors, and the one or more programs include instructions for executing any of the methods described in Example 1.
[0103] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0104] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0105] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0106] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0107] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for coordinated control of energy storage power in a renewable energy power generation configuration, characterized in that: include: Step 1: The power coordinated control system communicates with the station remote communication terminal RTU and the power prediction system to receive relevant control instructions; then the total power control target instruction P is calculated according to different control function modes. Σ , forwarded to the energy management system of the new energy power generation unit and the energy storage energy management system by means of communication through the in-station device; wherein the control function mode includes four functions: AGC emergency direct regulation control of the energy storage system, primary frequency regulation control of the energy storage auxiliary station, AGC control of the energy storage auxiliary station, and power prediction control of the energy storage auxiliary station; Step 2: Dynamically collect the current and voltage of the grid connection point of the new energy station and the grid connection point of the energy storage system, calculate the active power of the grid connection point of the new energy station, the grid frequency and the active power of the grid connection point of the energy storage system in real time, and send them to the synchronous phasor measurement unit PMU substation of the new energy station. The substation is directly uploaded to the dispatching PMU master station through the PMU substation for the evaluation and calculation of the whole station AGC, primary frequency regulation, power prediction and energy storage system AGC emergency direct regulation control performance; Step 3. The power collaborative control system design includes four functions: AGC emergency direct regulation control of energy storage system, primary frequency regulation control of energy storage auxiliary station, AGC control of energy storage auxiliary station, and power prediction control of energy storage auxiliary station. Multiple functional modules are put into use separately or simultaneously according to the operation requirements of new energy stations. The system automatically switches functions according to the operation status of new energy power generation and changes in grid operation requirements. When more than two functions are put into use, the system executes them in the order of priority: AGC emergency direct regulation control of energy storage system > primary frequency regulation control of energy storage auxiliary station > AGC control of energy storage auxiliary station > power prediction control of energy storage auxiliary station. Energy storage auxiliary station primary frequency regulation control mode: When the power grid system frequency is abnormal, the power cooperative control system calculates the primary frequency regulation load instruction ΔP according to the power grid frequency measurement value f measured at the grid connection points of the entire station and the active power-frequency droop control: Where: ΔP is the primary frequency modulation power command, f d is the primary frequency modulation dead zone, P N is the rated power of the new energy station, f N is the rated frequency of the power grid system, δ is the modulation rate, and f is the measured value of the power grid frequency; According to the primary frequency regulation load instruction ΔP and the whole station AGC control instruction, the total power control target instruction P is calculated. Σ ; The power cooperative control system gives priority to the power control total target instruction P Σ Optimize the allocation to the energy management system of the new energy power generation unit for active power regulation, monitor the active power P0" output of the new energy station in real time, and dynamically correct the control instructions P0" sent to the energy storage energy management system ES =P Σ -P0”, the rapid adjustment of the energy storage system is used to assist in achieving rapid response of the primary frequency regulation of the entire station; If the capacity of the energy storage system meets the primary frequency regulation capacity requirements, the power cooperative control system responds to the primary frequency regulation load command ΔP alone, including: during the primary frequency regulation action, the new energy power generation unit blocks the load change, and the energy storage system performs a primary frequency regulation dynamic response P alone ES =ΔP, giving full play to the millimeter-level rapid response capability of energy storage, reducing mechanical wear and power loss caused by frequent participation of new energy power generation in primary frequency regulation of the power grid; After the power prediction control function of the energy storage auxiliary station is put into use, when the AGC operation of the new energy station is in the free power generation mode, the power coordination control system automatically enters the power prediction control mode of the energy storage auxiliary station; The power cooperative control system and the power prediction system communicate in real time using sftp. The power cooperative control system receives the information transmitted by the power prediction system and reads the power prediction value Pforecast as the power control total target instruction PΣ. The energy storage system realizes accurate power prediction tracking and bidirectional energy output P according to the actual power input of renewable energy power generation. ES =Pforecast-PCollecting line. At the same time, the power coordination control system superimposes the active power of the new energy generation collection line PCollecting line and the active power of the energy storage grid connection point P0', and sends it to the dispatching master station as the power forecast assessment calculation value of the whole station; Step 4: Under different control function modes, the power cooperative control system automatically optimizes and distributes the information to the energy management system of each power generation unit according to the operating status of the new energy power generation unit and the energy storage. The energy management system of each power generation unit can quickly receive and execute the power control command to achieve the coordinated control of the power regulation of the new energy station and the energy storage system; wherein the control function mode includes four functions: AGC emergency direct regulation control of the energy storage system, primary frequency regulation control of the energy storage auxiliary station, AGC control of the energy storage auxiliary station, and power prediction control of the energy storage auxiliary station; Step 5: The power cooperative control system sends the control instruction P to the energy storage energy management system. ES It should be constrained by the regulation capability of the energy storage system and the capacity of the primary equipment within the station to avoid the energy storage system regulation speed being unable to track the rapid changes in active power instructions and to avoid safety problems in the energy storage system and new energy stations.
2. The method for coordinated control of energy storage power in renewable energy power generation configuration according to claim 1 is characterized in that: The step 1 comprises: The power cooperative control system receives the remote control command signals of the whole station AGC control, the energy storage system AGC emergency direct control control, the whole station AGC request input, and the energy storage system AGC emergency direct control request input from the dispatching master station through the station telecontrol terminal RTU device; According to the relevant control function requirements, the power control total target instruction P is formed Σ ; The power cooperative control system is responsible for the overall power control target instruction P Σ Calculation and allocation are performed and sent to the energy management system of the new energy power generation unit and the energy storage energy management system. Each energy management system then controls the wind turbines, photovoltaic inverters and energy storage PCS equipment in the station to ultimately achieve rapid power regulation.
3. The method for coordinated control of energy storage power in renewable energy power generation configuration according to claim 1 is characterized in that: After the AGC emergency direct control function of the energy storage system is put into operation, the power cooperative control system sends the "AGC emergency direct control function of the energy storage system has been put into operation" signal to the dispatching master station through the station RTU. This signal indicates that the energy storage system of the new energy station has the ability to be emergency directly adjusted by the AGC of the power grid dispatching organization; when the power grid fails or there is an operation risk, the dispatching master station sends the "AGC emergency direct adjustment request for the energy storage system" signal through the station RTU according to the status information sent by the energy storage system. After the power cooperative control system receives the "AGC emergency direct adjustment request for the energy storage system", the new energy station operator operates the AGC emergency direct adjustment function switch button of the energy storage system in the system again, and the power cooperative control system enters the AGC emergency direct adjustment control mode of the energy storage system. According to the AGC remote adjustment command P of the energy storage system, the power cooperative control system agc The energy storage system control target instruction P is calculated by the active power P0' of the energy storage system station and the grid connection point ES , ensuring the safe and stable operation of the power grid.
4. The method for coordinated control of energy storage power in renewable energy power generation configuration according to claim 1, characterized in that: In the energy storage auxiliary station AGC control mode, the power cooperative control system follows the AGC control instruction P of the whole station. AGC , the active power P0 of the whole station and the active power P0 of the new energy station are calculated to obtain the total target power control instruction P Σ ; Set the power control total target instruction P Σ Prioritize the optimization of allocation to the energy management system of the new energy power generation unit for active power regulation, monitor the active power output of the new energy station in real time, and dynamically correct the control instructions P sent to the energy storage energy management system ES =P Σ -P0", improves the AGC control response speed and accuracy of the entire station through rapid adjustment of the energy storage system.
5. The method for coordinated control of energy storage power in renewable energy power generation configuration according to claim 1, characterized in that: Step 5: The power cooperative control system sends the control instruction P to the energy storage energy management system. ES It should be subject to the regulation capacity of the energy storage system and the capacity of the primary equipment in the station, including: The power cooperative control system obtains the energy storage system capacity and primary equipment capacity status information from the energy storage energy management system; According to the capacity of the energy storage system and the capacity status information of the primary equipment, the maximum allowable charging power value P of the energy storage system is calculated. max-c and the maximum allowable discharge power of the energy storage system P max-f ; The control instructions of the energy storage energy management system should meet P max-c ≤P ES ≤P max-f , to avoid the energy storage system's adjustment speed being unable to track the rapid changes in active power instructions, and to avoid safety problems in the energy storage system and new energy stations.
6. A new energy power generation configuration energy storage power collaborative control system, characterized in that: It includes a power collaborative control system; the power collaborative control system is deployed on the upper layer of the energy management system of the new energy power generation unit and the energy storage energy management system, and the power collaborative control system interacts with the station RTU, the energy management system of the new energy power generation unit and the energy storage energy management system respectively, and is connected to the power prediction system of the new energy station; it also includes a processor and a storage medium; The storage medium is used to store instructions; The processor is configured to operate according to the instructions to execute the steps of the method according to any one of claims 1 to 5.