A construction method for casting irregularly shaped monolithic foundations in one go.
By using sheet piles to form a closed ring in the construction of long-span bridges, drilling and driving piles, and pouring concrete in an alternating manner, the problem of concrete pouring in the central area was solved, and the irregular integral pier cap was formed in one go, which improved construction safety and quality.
Patent Information
- Application Number
- CN202311647603.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-04
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2043-12-04
AI Technical Summary
In the construction of long-span irregular-shaped bridges, it is difficult to pour concrete in the central area, which can easily lead to the separation of aggregate and mortar, affecting construction quality and safety.
A press machine is used to insert steel sheet piles to form a closed ring. Fixed piles are then drilled and driven into the pit. After the foundation pit is excavated and the foundation layer is poured, concrete is poured into multiple closed rings in a staggered manner using a foundation steel cage and formwork. The pouring process is carried out in batches from the side to the center, using a wave-shaped staggered pouring process.
It effectively shortens the concrete pouring distance, avoids the separation of aggregate and mortar, shortens the construction period, improves construction safety and quality, and avoids cracks in the foundation.
Smart Images

Figure CN117385888B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of foundation construction technology, specifically relating to a construction method for casting irregularly shaped integral foundations in one go. Background Technology
[0002] With the rapid development of highway construction, the scale of long-span, irregularly shaped bridges is constantly increasing, leading to a growing number of bridge piers adopting irregularly shaped, monolithic, large-volume concrete structures. These piers are characterized by large concrete consumption, thick structures, complex engineering conditions, significant heat of cement hydration, and high construction technical requirements. Besides meeting strength, integrity, and durability requirements, controlling temperature deformation cracks is also crucial, making it an extremely important aspect of bridge construction. Bridge piers are also vital load-bearing structures, forming the foundation for the safety and stability of long-span bridges. If the construction quality of large-volume concrete piers is not guaranteed, the safety of the entire bridge will be compromised.
[0003] Therefore, some construction methods have emerged that use skip-pour method to pour large-area foundations. Skip-pour method makes full use of the "resistance and release" characteristics of concrete, which is easy to release internal stress before the concrete has stabilized and solidified completely within 5 to 10 days. It divides the building foundation or large-area concrete plane into several areas and constructs them according to the principle of "block planning, block construction, layered pouring, and overall forming". Its pattern is the same as checkers, that is, pouring a section at a time.
[0004] When using the skip-pour method for concrete pouring, gaps exist between the pouring areas from the edges towards the center. Because the center is far from the edges, it's inconvenient to pour concrete into the central area. This leads to a tendency for aggregate and mortar to separate during the pouring process from the edges towards the center. Therefore, a foundation pouring method is needed to solve the problem of long-distance pouring. Summary of the Invention
[0005] To address the problem of inconvenience in pouring concrete into the central area, the present invention aims to provide a construction method for casting irregularly shaped monolithic foundations in one go, thereby solving the aforementioned problem.
[0006] To achieve the above objectives, the present invention provides the following technical solution: a construction method for one-time casting of an irregularly shaped integral foundation, comprising the following steps: S1: A press machine is used to press down the steel sheet piles so that multiple steel sheet piles can be inserted into the soil and form multiple closed rings; S2: Drill holes and drive fixed piles into multiple closed rings formed by steel sheet piles; S3: Excavation of the foundation pit, using excavation equipment to excavate the soil within the multiple closed rings formed by the steel sheet piles; S4: Pour the foundation layer inside the foundation pit; S5: Fabricate the steel reinforcement cage for the foundation and install it in the excavated foundation pit; S6: Install and fix the formwork on the foundation steel cage; S7: Concrete is poured into multiple closed rings in a staggered manner; The specific steps for pouring concrete in an alternating sequence are as follows: S701: Divide multiple closed rings into two rows from the side to the center as one pouring batch; S702: Divide a pouring batch into two pouring processes. The specific steps of the pouring process are as follows: The first process pours concrete into multiple closed rings, so that the multiple closed rings of concrete are generally wavy. The second process pours concrete into multiple closed rings, so that the multiple closed rings of concrete are generally wavy and intersect with the first process, so that the closed rings poured in the first process and the closed rings poured in the second process can fill all the closed rings in a pouring batch.
[0007] In a preferred embodiment, the foundation pit needs to be excavated in multiple stages. Each time the foundation pit is excavated, the depth of the foundation pit is reached to a preset position. When the foundation pit is excavated to the preset position, a support structure for supporting the slope of the foundation pit needs to be installed inside the foundation pit. The next excavation of the foundation pit can only be carried out after the support structure is installed. It is necessary to ensure that the bottom of the foundation pit after excavation is lower than the height of the top of the fixed pile.
[0008] As a preferred embodiment, the interior of the foundation pit needs to be treated before pouring the foundation layer. The specific steps for treating the interior of the foundation pit include: S301: Remove the fixed piles that are higher than the bottom of the foundation pit so that the steel bars inside the fixed piles can be exposed; S302: Level the soil at the bottom of the foundation pit. After leveling, compaction equipment is needed to compact the bottom of the foundation pit.
[0009] In a preferred embodiment, step S301, the specific steps for removing the fixed pile include: S301a: Measure the portion of the fixed pile that is above the bottom of the foundation pit and mark the location that needs to be removed on the fixed pile; S301b: Use cutting equipment to make a circumferential cut at the marked location of the fixed pile, wherein the depth of the circumferential cut should be less than the distance between the reinforcing steel bar inside the fixed pile and the side wall of the fixed pile; S301c: Use a pneumatic hammer to remove the concrete above the circumferential cut of the fixed pile. When removing the concrete, it is necessary to remove it from top to bottom along the pile head so that the reinforcing steel inside the fixed pile can be exposed. S301d: Drilling equipment is used to drill holes in the concrete between the exposed reinforcing bars, so that the concrete between the reinforcing bars can be separated from the fixed pile; S301e: Use hoisting equipment to remove concrete blocks that have separated from the reinforcing bars; S301f: Clean the fractured part of the fixed pile so that the fractured part of the fixed pile can form a cross section with a high center and low sides.
[0010] As a preferred implementation method, before pouring the foundation layer, it is necessary to lay out and position the fixed piles, and use fixed templates to create a construction area around the fixed piles. When pouring the foundation layer concrete, the foundation layer concrete should be vibrated to compact it, and the surface of the foundation layer concrete should be flat.
[0011] In a preferred embodiment, in step S6, before installing the foundation steel cage in the foundation pit, the exposed steel bars on the fixed pile need to be bent so that the steel bars on the fixed pile have hooks. After placing the foundation steel cage in the foundation pit, the foundation steel cage can be located above the cushion layer, and wire needs to be used to connect the foundation steel cage to the steel bars on the fixed pile.
[0012] As a preferred embodiment, after the foundation pit is excavated, a water collection ditch needs to be dug above and below the foundation pit so that the foundation pit is located in the center of the water collection ditch above, and multiple fixed piles are located in the center of the water collection ditch at the bottom of the foundation pit.
[0013] In a preferred embodiment, after the fixed pile is removed, it needs to be inspected. The specific steps for inspecting the fixed pile include: S100: Place a bearing plate and a pad on top of the fixed pile to protect it; S200: Fix the hydraulic jack to the pad, ensuring that the hydraulic jack is perpendicular to the fixing pile; S300: Construct a load-bearing platform around the fixed pile; S400: Stack heavy objects on a load-bearing platform so that the heavy objects are above the hydraulic jack; S500: Connect the oil pump and oil pressure sensor to the hydraulic jack, wherein the oil pressure sensor is connected in parallel at the oil supply pipe port of the oil pump. S600: Displacement sensors are installed on both sides of the pressure plate so that the receiver can be perpendicular to the pressure plate and is connected to a static load tester to collect data.
[0014] As a preferred implementation method, when pouring concrete into the closed ring, it is necessary to use a chute to pour symmetrically, and it should be poured in multiple layers. After each pour is completed, the concrete needs to be vibrated to ensure that there are no air bubbles inside the concrete before the next pour can be carried out. After the concrete is poured, the surface of the concrete needs to be finished to ensure that the surface of the concrete is flat.
[0015] As a preferred embodiment, the length and width of the multiple closed loops should not exceed forty meters, and the time interval between pouring of two closed loops should be greater than seven days.
[0016] Compared with the prior art, the beneficial effects of the present invention are: This construction method for casting an irregularly shaped monolithic foundation in one go divides the area to be cast into multiple casting batches, with each two rows of casting areas forming one casting batch. Therefore, the entire area to be cast can be divided into multiple casting batches from the side to the center. Multiple casting batches can be constructed sequentially from the side to the center. The subsequent casting batches can be constructed on the area that was cast first, which can shorten the concrete casting distance and avoid the separation of aggregate and mortar. This construction method for casting an irregularly shaped monolithic foundation in one go employs a skip-pouring method, ensuring that multiple pouring areas are not adjacent when pouring, and allowing for simultaneous pouring of multiple non-adjacent areas. This shortens the pouring period, avoids cracks in the foundation, and improves safety. Attached Figure Description
[0017] Figure 1 This is a flowchart of a construction method for one-time casting of an irregularly shaped integral foundation proposed in this invention; Figure 2 This is a construction area division diagram for a construction method of casting an irregularly shaped integral foundation in one go, as proposed in this invention. Detailed Implementation
[0018] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0019] For examples, please refer to Figure 1-2 This invention provides a construction method for casting an irregularly shaped integral foundation in one go, comprising the following steps: S1: A press machine is used to press down the steel sheet piles so that multiple steel sheet piles can be inserted into the soil and form multiple closed rings. The inside of the closed rings is the construction area. When inserting the steel sheet piles, the steel sheet piles need to be fixed at the same time to avoid the phenomenon of piles connecting together. S2: Drill holes and drive fixed piles into multiple closed rings formed by steel sheet piles. The fixed piles are concrete piles. First, use drilling equipment to drill holes in the soil, then lower a steel cage into the hole, and finally pour concrete into the hole so that the concrete solidifies and combines with the steel cage to form a pile, which is used to support the formed foundation. S3: Excavation of the foundation pit. Excavation equipment is used to excavate the soil within the multiple closed rings formed by the steel sheet piles. During the excavation of the foundation pit, contact between the excavation equipment and the fixed piles should be avoided to prevent damage to the fixed piles and ensure their stability. S4: Pour a cushion layer in the foundation pit. The cushion layer is located between the bottom of the foundation pit and the foundation cap. It serves to level the ground and facilitates the installation of the steel cage for the construction of the foundation cap. S5: Fabricate the foundation steel cage and install it in the excavated foundation pit. The steel cage needs to be designed according to the size of the foundation pit and the size of the fixed piles so that the bundled steel cage can be accurately installed inside the foundation pit. S6: Install and fix the formwork on the foundation reinforcement cage. The formwork is used to cover the concrete and can be used to pour concrete in the closed space formed by the formwork. The formwork needs to be fixed with steel structure during construction to prevent the formwork from collapsing under pressure. At the joints of multiple formworks, tape, cloth or other flexible materials need to be used to seal the leaks to prevent concrete leakage. S7: Concrete is poured into multiple closed rings in a staggered manner; The specific steps for pouring concrete in an alternating sequence are as follows: S701: Divide multiple closed rings into two rows from the side to the center as one pouring batch; S702: Divide a pouring batch into two pouring processes, wherein the specific steps of the pouring process are as follows: the first process pours concrete into multiple closed rings, so that the multiple closed rings of poured concrete are generally wavy; the second process pours concrete into multiple closed rings, so that the multiple closed rings of poured concrete are generally wavy and intersect with the first process, so that the closed rings poured in the first process and the closed rings poured in the second process can fill all the closed rings in a pouring batch. It should be noted that you should refer to [link / reference]. Figure 2 The dashed box represents a pouring area, i.e., a closed loop. The area between two solid boxes represents a pouring batch. Within a pouring batch, the filled area represents one pouring process, and the blank area represents another pouring process.
[0020] Furthermore, during the excavation of the foundation pit, it is necessary to excavate the foundation pit in multiple stages. Each time the foundation pit is excavated, the depth of the foundation pit is reached to a predetermined position. When the foundation pit is excavated to the predetermined position, a support structure for supporting the slope of the foundation pit needs to be installed inside the foundation pit. The next excavation of the foundation pit can only be carried out after the support structure is installed. It is necessary to ensure that the bottom of the foundation pit after excavation is lower than the height of the top of the fixed pile. The foundation pit is excavated by means of excavation and protection at the same time, which can prevent the foundation pit from collapsing and improve the safety of construction. In this embodiment, the interior of the foundation pit needs to be treated before pouring the foundation layer inside the pit. The specific steps for treating the interior of the foundation pit include: S301: Remove the fixed piles that are higher than the bottom of the foundation pit so that the steel bars inside the fixed piles can be exposed, making it easier to connect the exposed steel bars to the steel cage, thereby improving the stability of the steel cage. S302: Level the soil at the bottom of the foundation pit. After leveling, compaction equipment is needed to compact the bottom of the foundation pit. First, remove the protruding parts at the bottom of the foundation pit and fill the depressions at the bottom of the foundation pit. Then, use compaction equipment to compact the bottom of the foundation pit to improve stability. Furthermore, in step S301, the specific steps for removing the fixed pile include: S301a: Measure the portion of the fixed pile that is higher than the bottom of the foundation pit, and mark the location that needs to be removed on the fixed pile. The location that needs to be removed needs to be designed and calculated according to the overall construction plan. S301b: Use a cutting device to perform a circumferential cut at the marked location of the fixed pile. The depth of the circumferential cut should be less than the distance between the reinforcing steel inside the fixed pile and the side wall of the fixed pile. This is to avoid contact between the cutting device and the reinforcing steel inside the fixed pile, thereby preventing damage or breakage of the reinforcing steel inside the fixed pile and ensuring safety. S301c: Use a pneumatic hammer to remove the concrete above the circumferential cut of the fixed pile. When removing the concrete, it is necessary to remove it from top to bottom along the pile head so that the reinforcing steel inside the fixed pile can be exposed. S301d: Drill holes in the concrete between the exposed reinforcing bars using drilling equipment, so that the concrete between the reinforcing bars can be separated from the fixed pile. Multiple holes are drilled above the circumferential cut, and then the end of the fixed pile is struck so that the concrete at the end of the fixed pile can break at the hole, making it easy to remove the end of the concrete. S301e: Using hoisting equipment to remove concrete blocks separated between reinforcing bars, the concrete at the end of the fixed pile can be moved upwards from between multiple reinforcing bars, avoiding bending of the reinforcing bars and thus preventing damage to the reinforcing bars, thereby improving safety; S301f: Clean the broken part of the fixed pile to make the broken part of the fixed pile flat, and at the same time make the broken part of the fixed pile form a cross section with a high center and low sides. Before pouring the foundation layer, the fixed piles need to be laid out and positioned to ensure accuracy. A fixed template is used to create a construction area around the fixed piles. The fixed template can cover the concrete, allowing the concrete solidified inside the template to form the foundation layer. The area and height of the fixed template need to be designed and calculated according to the overall construction needs. When pouring the foundation layer concrete, the concrete should be vibrated to compact it and the surface of the foundation layer concrete should be flat to ensure the stability and strength of the foundation layer. In step S6, before installing the foundation steel cage in the foundation pit, the exposed steel bars on the fixed piles need to be bent so that the steel bars on the fixed piles have hooks, which makes it easier for the steel bars on the fixed piles to connect with the foundation steel cage. After placing the foundation steel cage in the foundation pit, the foundation steel cage can be located above the cushion layer to ensure the stability of the foundation steel cage. Iron wire is also needed to connect the foundation steel cage to the steel bars on the fixed piles. After the foundation pit is excavated, drainage ditches need to be dug above and at the bottom of the foundation pit so that the foundation pit is centered in the drainage ditch above. The drainage ditch above the foundation pit can collect water from the ground surface. Water pumps can be used to discharge the water from the drainage ditch, preventing water from entering the foundation pit and thus avoiding any impact on construction. Multiple fixed piles can be located in the center of the drainage ditch at the bottom of the foundation pit so that water seeping out of the foundation pit can be collected by the drainage ditch at the bottom of the foundation pit. Water pumps can be used to discharge the water from the drainage ditch, preventing water from contacting the fixed piles and the foundation layer in the foundation pit, thus avoiding any impact on construction. In this embodiment, after the fixed piles are removed, they need to be inspected. Inspecting the fixed piles ensures the safety of the foundation construction. The specific steps for inspecting the fixed piles include: S100: A bearing plate and a pad are placed on top of the fixed pile to protect it. The bearing plate and pad protect the end of the fixed pile and prevent it from being damaged by pressure. S200: Fix the hydraulic jack to the pad plate, ensuring that the hydraulic jack is perpendicular to the fixed pile, so that both the hydraulic jack and the fixed pile can be subjected to force evenly, preventing the hydraulic jack from bending after tipping over, preventing damage to the fixed pile, and improving the accuracy of the test. S300: A load-bearing platform is erected around the fixed pile, and the platform is used to place heavy objects for testing. S400: Stack heavy objects on a load-bearing platform so that the heavy objects are above the hydraulic jacks. The total weight of the heavy objects must be strictly calculated according to the design of the testing plan. The heavy objects can be materials with a large weight, such as soil, sand, gravel, or metal. S500: Connects an oil pump and an oil pressure sensor to the hydraulic jack. The oil pressure sensor is connected in parallel at the oil supply pipe port of the oil pump, which can detect the pressure of the oil pump in real time and improve safety. S600: Displacement sensors are installed on both sides of the bearing plate so that the receiver can be perpendicular to the bearing plate. After being connected to the static load tester, data is collected. By analyzing the data collected by the static load tester, the overall data of the fixed pile can be determined, thus achieving the effect of testing the fixed pile, ensuring that the fixed pile can achieve the predetermined bearing capacity, and improving the safety of subsequent construction. When pouring concrete into a closed ring, a chute should be used for symmetrical pouring. The chute method can prevent the aggregate from separating from the mortar when the concrete falls, ensuring the quality of the pouring. The pouring should be carried out in multiple layers. After each pour, the concrete needs to be vibrated to ensure that there are no air bubbles inside before the next pouring can be carried out. By pouring and vibrating multiple times, the quality of the pouring can be ensured, the presence of air bubbles in the concrete can be avoided, and the hardness of the concrete can be guaranteed. After the concrete is poured, the surface of the concrete needs to be finished to ensure that the surface of the concrete is flat. The length and width of multiple closed loops should not exceed 40 meters to avoid cracking of the concrete poured inside the closed loops and improve safety. When pouring adjacent closed loops, the time interval between the two closed loops should be greater than seven days to ensure that the concrete is completely cured before pouring the subsequent areas.
[0021] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A construction method for casting an irregularly shaped monolithic foundation in one go, characterized in that, Includes the following steps: S1: A press machine is used to press down the steel sheet piles, so that multiple steel sheet piles can be inserted into the soil and form multiple closed rings; S2: Drill holes and drive fixed piles into multiple closed rings formed by steel sheet piles; S3: Excavation of the foundation pit, using excavation equipment to excavate the soil within the multiple closed rings formed by the steel sheet piles; S4: Pour the foundation layer inside the foundation pit; S5: Fabricate the steel reinforcement cage for the foundation and install it in the excavated foundation pit; S6: Install and fix the formwork on the foundation steel cage; S7: Concrete is poured into multiple closed rings in a staggered manner; The specific steps for pouring concrete in an alternating sequence are as follows: S701: Divide multiple closed rings into two rows from the side to the center as one pouring batch; S702: Divide a pouring batch into two pouring processes. The specific steps of the pouring process are as follows: The first process pours concrete into multiple closed rings, so that the multiple closed rings of concrete are generally wavy. The second process pours concrete into multiple closed rings, so that the multiple closed rings of concrete are generally wavy and intersect with the first process, so that the closed rings poured in the first process and the closed rings poured in the second process can fill all the closed rings in a pouring batch.
2. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: During the excavation of the foundation pit, it is necessary to excavate the foundation pit in multiple stages. Each time the foundation pit is excavated, the depth of the foundation pit should reach the preset position. When the foundation pit is excavated to the preset position, a support structure for supporting the slope of the foundation pit needs to be installed inside the foundation pit. The next excavation of the foundation pit can only be carried out after the support structure is installed. It is necessary to ensure that the bottom of the foundation pit after excavation is lower than the height of the top of the fixed pile.
3. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: Before pouring the foundation layer inside the excavation pit, the interior of the pit needs to be treated. The specific steps for treating the interior of the excavation pit include: S301: Remove the fixed piles that are higher than the bottom of the foundation pit so that the steel bars inside the fixed piles can be exposed; S302: Level the soil at the bottom of the foundation pit. After leveling, compaction equipment is needed to compact the bottom of the foundation pit.
4. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 3, characterized in that: In step S301, the specific steps for removing the fixed pile include: S301a: Measure the portion of the fixed pile that is above the bottom of the foundation pit and mark the location that needs to be removed on the fixed pile; S301b: Use cutting equipment to make a circumferential cut at the marked location of the fixed pile, wherein the depth of the circumferential cut should be less than the distance between the reinforcing steel bar inside the fixed pile and the side wall of the fixed pile; S301c: Use a pneumatic pick to remove the concrete above the circumferential cut of the fixed pile. When removing the concrete, it is necessary to remove it from top to bottom along the pile head so that the reinforcing steel inside the fixed pile can be exposed. S301d: Drilling equipment is used to drill holes in the concrete between the exposed reinforcing bars, so that the concrete between the reinforcing bars can be separated from the fixed pile; S301e: Use hoisting equipment to remove concrete blocks that have separated from the reinforcing bars; S301f: Clean the fractured part of the fixed pile so that the fractured part of the fixed pile can form a cross section with a high center and low sides.
5. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: Before pouring the foundation layer, the fixed piles need to be laid out and positioned. A construction area is made around the fixed piles using a fixed template. When pouring the foundation layer concrete, the concrete should be vibrated to compact it and the surface of the foundation layer concrete should be flat.
6. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: In step S6, before installing the foundation steel cage in the foundation pit, the exposed steel bars on the fixed pile need to be bent so that the steel bars on the fixed pile have hooks. After placing the foundation steel cage in the foundation pit, the foundation steel cage can be located above the cushion layer, and wire needs to be used to connect the foundation steel cage to the steel bars on the fixed pile.
7. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: After the foundation pit is excavated, a water collection ditch needs to be dug above and below the foundation pit so that the foundation pit is located in the center of the water collection ditch above, and so that multiple fixed piles are located in the center of the water collection ditch at the bottom of the foundation pit.
8. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: After the fixed piles are removed, they need to be inspected. The specific steps for inspecting the fixed piles include: S100: Place a bearing plate and a pad on top of the fixed pile to protect it; S200: Fix the hydraulic jack to the pad, ensuring that the hydraulic jack is perpendicular to the fixing pile; S300: Construct a load-bearing platform around the fixed piles; S400: Stack heavy objects on a load-bearing platform so that the heavy objects are above the hydraulic jack; S500: Connect the oil pump and oil pressure sensor to the hydraulic jack, wherein the oil pressure sensor is connected in parallel at the oil supply pipe port of the oil pump. S600: Displacement sensors are installed on both sides of the pressure plate so that the receiver can be perpendicular to the pressure plate and is connected to a static load tester to collect data.
9. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: When pouring concrete into a closed ring, it is necessary to use a chute to pour symmetrically, and it should be poured in multiple layers. After each pour, the concrete needs to be vibrated to ensure that there are no air bubbles inside before the next pour can be carried out. After the concrete is poured, the surface of the concrete needs to be finished to ensure that the surface of the concrete is flat.
10. The construction method for one-time casting of an irregularly shaped integral foundation according to claim 1, characterized in that: The length and width of multiple closed loops should not exceed forty meters, and the time interval between pouring of two adjacent closed loops should be greater than seven days.
Citation Information
Patent Citations
Method for constructing large-volume concrete bearing platform of large-scale low-temperature storage tank
CN112049143A
Bridge pile foundation and bearing platform connecting structure
CN214219717U