A method for fixing pre-embedded anchor bolt sleeves in a steam turbine foundation

By combining the sleeve assembly and the fixing assembly, the problems of the embedded anchor bolt sleeve deviating from the design position and the waste of steel are solved, and the precise positioning of the embedded anchor bolts and material saving are achieved.

CN117385924BActive Publication Date: 2026-11-17河南省第二建设集团有限公司
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311374113.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-23
Publication Date
2026-11-17
Estimated Expiration
2043-10-23

AI Technical Summary

Technical Problem

In the existing technology, the channel steel support frame is prone to displacement during the welding process, causing the pre-embedded anchor bolt sleeve to deviate from the design position. In addition, the square support frame formed by welding the channel steel is poured into the concrete together, resulting in steel waste.

Method used

The system employs a combination structure of sleeve assembly, fixing assembly, positioning steel plate and bottom formwork. The pre-embedded bolt sleeve is fixed by positioning screws and connecting fasteners to ensure its accurate position. The temporary structure is removed after the concrete reaches the design strength, reducing material waste.

Benefits of technology

This improved the positioning accuracy of the pre-embedded anchor bolts, reduced material waste from the channel steel support being poured inside the concrete, and improved the economy and precision of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117385924B_ABST
    Figure CN117385924B_ABST
Patent Text Reader

Abstract

This invention belongs to the field of construction technology, specifically relating to a sleeve assembly and fixing method for pre-embedded anchor bolts in a steam turbine foundation. It aims to solve the problem in existing technologies where a square support frame welded from channel steel is poured into the concrete along with the steel, resulting in significant steel waste. This invention includes: a sleeve assembly, a fixing assembly, a positioning steel plate, a bottom template, and a sleeve positioning hole. The sleeve assembly is coaxially fixed to the circumferential surface of the sleeve positioning hole, which is located on the positioning steel plate. The positioning steel plate is detachably fixed to the bottom template, and the sleeve assembly is detachably fixed to the fixing assembly. The fixing assembly is used for fixing and positioning the sleeve assembly. This invention reduces the amount of channel steel support poured into the main concrete structure, improves the positioning accuracy of the pre-embedded anchor bolts, and reduces material waste.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of construction technology, and specifically relates to a pre-embedded anchor bolt sleeve assembly and fixing method for a steam turbine foundation. Background Technology

[0002] During construction, to ensure accurate connection between anchor bolts and equipment, pre-embedded bolt sleeves are usually installed, which facilitates precise fixing of the anchor bolt positions later.

[0003] The conventional practice for pre-embedded anchor bolt sleeves on site is to weld a square support frame with channel steel and fix the pre-embedded anchor bolt sleeves.

[0004] This conventional approach has the following drawbacks: the channel steel support frame is prone to displacement during welding, causing the pre-embedded anchor bolt sleeves to deviate from their designed positions. Furthermore, the square support frame formed by welding the channel steel is poured into the concrete along with it, resulting in a significant waste of steel.

[0005] Based on this, the present invention proposes a pre-embedded anchor bolt sleeve assembly and fixing method for a steam turbine foundation. Summary of the Invention

[0006] To address the aforementioned problems in existing technologies, namely, the easy displacement of the channel steel support frame during welding, causing the pre-embedded anchor bolt sleeves to deviate from their designed positions, and the significant waste of steel due to the square support frame formed by welding the channel steel being poured into the concrete along with it, this invention provides a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation and a fixing method therefor.

[0007] One aspect of the present invention provides a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation, comprising a sleeve assembly, a fixing assembly, a positioning steel plate, a bottom template, and a sleeve positioning circular hole;

[0008] The sleeve assembly is coaxially fixed with the circumferential surface of the sleeve positioning hole, the sleeve positioning hole is formed on the positioning steel plate, the positioning steel plate is detachably fixed with the bottom template, and the bottom template is used to position the sleeve assembly.

[0009] Multiple sets of the sleeve assembly, positioning steel plate, and sleeve positioning holes are evenly arranged along the length and width of the bottom template. The multiple sets of sleeve assemblies are detachably fixed to the fixing component, which is used to fix and position the sleeve assembly.

[0010] In some preferred embodiments, the sleeve assembly includes a pre-embedded bolt sleeve and a temporary sealing steel plate;

[0011] The outer circumferential surface of one end of the pre-embedded bolt sleeve is coaxially fixed with the circumferential surface of the sleeve positioning hole, and the end face of the other end of the pre-embedded bolt sleeve is detachably fixed with the temporary sealing steel plate.

[0012] In some preferred embodiments, the fixing components include connecting fasteners, transverse reinforcing bars, longitudinal positioning bars, formwork scaffolding, and fixing fasteners;

[0013] The transverse reinforcing rod is fixed to the template scaffold and the longitudinal positioning rod respectively through the connecting fastener. Two sets of longitudinal positioning rods are arranged along both sides of the pre-embedded bolt sleeve. The longitudinal positioning rod is fixed to the end of the pre-embedded bolt sleeve away from the bottom template through the fixing fastener.

[0014] In some preferred embodiments, the positioning steel plate is fixed to the bottom template by the positioning screws.

[0015] In some preferred embodiments, the transverse reinforcing rod is parallel to the width direction of the bottom template, and the longitudinal positioning rod is parallel to the length direction of the bottom template.

[0016] In another aspect, the present invention provides a method for fixing a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation, the method comprising the following steps:

[0017] Step S10: Fix one end of the pre-embedded bolt sleeve in the sleeve assembly to the positioning steel plate, and fix the temporary sealing steel plate in the sleeve assembly to the end face of the other end of the pre-embedded bolt sleeve. The fixed pre-embedded bolt sleeve, the temporary sealing steel plate and the positioning steel plate are used as the first assembly.

[0018] Step S20: Mark the positions of multiple pre-embedded bolt sleeves on the bottom template as the first positions, and fix multiple first components at the first positions by positioning screws;

[0019] Step S30: Fix the transverse reinforcing rod and the formwork scaffold in the fixing assembly using connecting fasteners, then fix the transverse reinforcing rod to the longitudinal positioning rod in the fixing assembly using the connecting fasteners, clamp the pre-embedded bolt sleeve using the longitudinal positioning rod, and fix it using the fixing fasteners in the fixing assembly;

[0020] Step S40: Pour the main concrete. After the concrete reaches the design strength, remove the formwork, the formwork scaffolding, the connecting fasteners, the horizontal reinforcing rods, the temporary sealing steel plates, the longitudinal positioning rods, and the fixing fasteners to complete the construction.

[0021] In a third aspect, the present invention provides another type of pre-embedded anchor bolt sleeve assembly for turbine foundations, comprising a sleeve assembly, a fixing assembly, a positioning steel plate, a bottom template, and a sleeve positioning round hole;

[0022] The sleeve assembly is coaxially fixed with the circumferential surface of the sleeve positioning hole, the sleeve positioning hole is formed on the positioning steel plate, the positioning steel plate is detachably fixed with the bottom template, and the bottom template is used to position the sleeve assembly.

[0023] Multiple sets of the sleeve assembly, positioning steel plate, and sleeve positioning holes are evenly arranged along the length and width of the bottom template. The multiple sets of sleeve assemblies are detachably fixed to the fixing component, which is used to fix and position the sleeve assembly.

[0024] In some preferred embodiments, the sleeve assembly includes a supporting steel pipe, a pre-embedded bolt sleeve, a connecting nut, and anchor bolts;

[0025] The outer circumferential surface of one end of the supporting steel pipe is coaxially fixed with the circumferential surface of the positioning hole of the sleeve, and the end face of the other end of the supporting steel pipe is coaxially fixed with the connecting nut. The connecting nut is threadedly connected to the anchor bolt, and the surface of the connecting nut on the side away from the bottom template is coaxially fixed with the pre-embedded bolt sleeve.

[0026] In some preferred embodiments, the fixing components include connecting fasteners, transverse reinforcing bars, longitudinal positioning bars, formwork scaffolding, and fixing fasteners;

[0027] The transverse reinforcing rod is fixed to the template scaffold and the longitudinal positioning rod respectively through the connecting fastener. Two sets of longitudinal positioning rods are arranged along both sides of the pre-embedded bolt sleeve. The longitudinal positioning rod is fixed to the end of the pre-embedded bolt sleeve away from the bottom template through the fixing fastener.

[0028] In some preferred embodiments, the positioning steel plate is fixed to the bottom template by the positioning screws.

[0029] In some preferred embodiments, the transverse reinforcing rod is parallel to the width direction of the bottom template, and the longitudinal positioning rod is parallel to the length direction of the bottom template.

[0030] In a fourth aspect, the present invention provides another method for fixing the pre-embedded anchor bolt sleeve assembly of the turbine foundation, the method comprising the following steps:

[0031] Step A10: Fix one end of the support steel pipe in the sleeve assembly to the positioning steel plate, and fix the connecting nut in the sleeve assembly to the end face of the other end of the support steel pipe. Connect the connecting nut to the anchor bolt in the sleeve assembly. Pour concrete into the support steel pipe through the positioning hole of the sleeve. After the concrete solidifies, fix the pre-embedded bolt sleeve on the connecting nut. The fixed support steel pipe, the positioning steel plate, the connecting nut, the anchor bolt, and the pre-embedded bolt sleeve are used as the second assembly.

[0032] Step A20: Mark the positions of multiple pre-embedded bolt sleeves on the bottom template as the second positions, and fix multiple second components at the second positions by positioning screws;

[0033] Step A30: Fix the transverse reinforcing rod and the formwork scaffold in the fixing assembly using connecting fasteners, then fix the transverse reinforcing rod to the longitudinal positioning rod in the fixing assembly using the connecting fasteners, clamp the pre-embedded bolt sleeve with the longitudinal positioning rod, and fix it with the fixing fasteners in the fixing assembly;

[0034] Step A40: Pour the main concrete. After the concrete reaches the design strength, remove the formwork, the formwork scaffolding, the connecting fasteners, the horizontal reinforcing rods, the longitudinal positioning rods, and the fixing fasteners to complete the construction.

[0035] The beneficial effects of this invention are:

[0036] This invention enables the construction of both through-type and direct-buried anchor bolts. The invention places a square positioning steel plate on the main body's bottom template, ensuring the positioning accuracy of the anchor bolts. The longitudinal positioning rods and transverse reinforcing rods above can be removed after the main body is completed, reducing material waste. It also reduces the amount of channel steel supports poured into the main concrete, thus improving the positioning accuracy of the anchor bolts. Attached Figure Description

[0037] Other features, objects, and advantages of this application will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings:

[0038] Figure 1 This is an overall isometric view of a turbine foundation pre-embedded anchor bolt sleeve assembly according to the first embodiment of the present invention;

[0039] Figure 2 This is an overall isometric view of a turbine foundation pre-embedded anchor bolt sleeve assembly according to the third embodiment of the present invention;

[0040] Figure 3 This is a schematic diagram of a positioning steel plate for a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation according to the present invention;

[0041] Figure 4 This is a schematic diagram of the anchor bolt connection of a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation according to the third embodiment of the present invention;

[0042] Figure 5 This is a schematic diagram of the pre-embedded bolt sleeve connection of a turbine foundation pre-embedded anchor bolt sleeve assembly according to the third embodiment of the present invention. Detailed Implementation

[0043] The present application will now be described in further detail with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for illustrative purposes only and are not intended to limit the invention. Furthermore, it should be noted that, for ease of description, only the parts relevant to the invention are shown in the accompanying drawings.

[0044] It should be noted that, unless otherwise specified, the embodiments and features described in this application can be combined with each other. This application will now be described in detail with reference to the accompanying drawings and embodiments.

[0045] The first embodiment of the present invention, see [link to embodiment]. Figure 1 , Figure 3 A turbine foundation pre-embedded anchor bolt sleeve assembly is provided, including sleeve assembly, fixing assembly, positioning steel plate 1, bottom template 10, and sleeve positioning round hole 11;

[0046] The sleeve assembly is coaxially fixed with the circumferential surface of the sleeve positioning hole 11. The sleeve positioning hole 11 is formed on the positioning steel plate 1. The positioning steel plate 1 is detachably fixed with the bottom template 10. The bottom template 10 is used to position the sleeve assembly.

[0047] Multiple sets of the sleeve assembly, positioning steel plate 1, and sleeve positioning round hole 11 are evenly arranged along the length and width of the bottom template 10. The multiple sets of the sleeve assembly are detachably fixed to the fixing component, and the fixing component is used to fix and position the sleeve assembly.

[0048] Preferred, see Figure 1 , Figure 3 The sleeve assembly includes a pre-embedded bolt sleeve 4 and a temporary sealing steel plate 7;

[0049] The outer circumferential surface of one end of the pre-embedded bolt sleeve 4 is coaxially fixed with the circumferential surface of the sleeve positioning hole 11, and the end face of the other end of the pre-embedded bolt sleeve 4 is detachably fixed with the temporary sealing steel plate 7.

[0050] The specific method for "the end face of the other end of the pre-embedded bolt sleeve 4 is detachably fixed to the temporary sealing steel plate 7" can be as follows: the end face of the other end of the pre-embedded bolt sleeve 4 is welded and fixed to the temporary sealing steel plate 7.

[0051] The specific method for "fixing the outer circumferential surface of one end of the pre-embedded bolt sleeve 4 coaxially with the circumferential surface of the sleeve positioning hole 11" can be as follows: the outer circumferential surface of one end of the pre-embedded bolt sleeve 4 is coaxially welded and fixed with the circumferential surface of the sleeve positioning hole 11.

[0052] In this embodiment, the sleeve assembly, positioning steel plate 1, and sleeve positioning round holes 11 are evenly arranged in 6 groups along the length direction of the bottom template 10 and in 2 groups along the width direction of the bottom template, but are not limited to 6 groups and 2 groups. Any number can be set according to actual needs.

[0053] Preferred, see Figure 1 , Figure 3 The fixing components include connecting fasteners 5, transverse reinforcing rods 6, longitudinal positioning rods 8, template scaffolding 9, and fixing fasteners 15;

[0054] The transverse reinforcing rod 6 is fixed to the template scaffold 9 and the longitudinal positioning rod 8 respectively through the connecting fastener 5. Two sets of longitudinal positioning rods 8 are arranged along both sides of the pre-embedded bolt sleeve 4. The longitudinal positioning rod 8 is fixed to the end of the pre-embedded bolt sleeve 4 away from the bottom template 10 through the fixing fastener 15.

[0055] The specific method of "fixing the longitudinal positioning rod 8 to the end of the pre-embedded bolt sleeve 4 away from the bottom template 10 by means of the fixing fastener 15" is as follows: two fixing fasteners 15 are set at the diagonal of the intersection point of the longitudinal positioning rod 8 and the pre-embedded bolt sleeve 4 to fix the pre-embedded bolt sleeve 4.

[0056] In this embodiment, the template scaffolding 9 and the transverse reinforcing rods 6 are evenly arranged in 3 sets along the length direction of the bottom template 10, but not limited to 3 sets. The two sets of longitudinal positioning rods 8 are symmetrically arranged in 2 sets along the centerline of the width direction of the bottom template 10, but not limited to 2 sets.

[0057] Preferred, see Figure 1 The positioning steel plate 1 is fixed to the bottom template 10 by the positioning screws 12.

[0058] In this embodiment, the positioning steel plate 1 is fixed to the bottom template 10 by four positioning bolts 12 at its four corners. However, the number of positioning bolts 12 is not limited to four.

[0059] In this embodiment, the positioning steel plate 1 is square, but not limited to square; it can be any shape such as round or rhomboid.

[0060] Preferred, see Figure 1The transverse reinforcing rod 6 is parallel to the width direction of the bottom template 10, and the longitudinal positioning rod 8 is parallel to the length direction of the bottom template 10.

[0061] Wherein, the length direction of the bottom template 10 is Figure 1 The long side direction shown is the width direction of the bottom template 10. Figure 1 The direction of the shorter side is shown.

[0062] The second embodiment of the present invention is described in [reference needed]. Figure 1 , Figure 3 A method for fixing a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation is proposed. Based on the first embodiment of the pre-embedded anchor bolt sleeve assembly for a steam turbine foundation, the method includes the following steps:

[0063] Step S10: Fix one end of the pre-embedded bolt sleeve 4 in the sleeve assembly to the positioning steel plate 1, and fix the temporary sealing steel plate 7 in the sleeve assembly to the end face of the other end of the pre-embedded bolt sleeve 4. The fixed pre-embedded bolt sleeve 4, the temporary sealing steel plate 7 and the positioning steel plate 1 are used as the first assembly.

[0064] Step S20: Mark the positions of multiple pre-embedded bolt sleeves 4 on the bottom template 10 as the first positions, and fix multiple first components at the first positions by positioning screws 12;

[0065] Step S30: Fix the transverse reinforcing rod 6 and the template scaffold 9 in the fixing assembly using the connecting fastener 5, then fix the transverse reinforcing rod 6 to the longitudinal positioning rod 8 in the fixing assembly using the connecting fastener 5, clamp the pre-embedded bolt sleeve 4 using the longitudinal positioning rod 8, and fix it with the fixing fastener 15 in the fixing assembly.

[0066] Step S40: Pour the main concrete. After the concrete reaches the design strength, remove the formwork, the formwork scaffolding 9, the connecting fasteners 5, the horizontal reinforcing rods 6, the temporary sealing steel plates 7, the longitudinal positioning rods 8, and the fixing fasteners 15 to complete the construction.

[0067] After the first component is assembled, it is placed in a temporary storage area before measurement and layout are carried out.

[0068] In step S40, the templates in "removing the templates" include all the templates of the turbine base as a whole, including the bottom template 10.

[0069] The third embodiment of the present invention is described in [reference needed]. Figure 2 , Figure 3 , Figure 4 , Figure 5A pre-embedded anchor bolt sleeve assembly for steam turbine foundation is proposed, including sleeve assembly, fixing assembly, positioning steel plate 1, bottom template 10, and sleeve positioning round hole 11;

[0070] The sleeve assembly is coaxially fixed with the circumferential surface of the sleeve positioning hole 11. The sleeve positioning hole 11 is formed on the positioning steel plate 1. The positioning steel plate 1 is detachably fixed with the bottom template 10. The bottom template 10 is used to position the sleeve assembly.

[0071] Multiple sets of the sleeve assembly, positioning steel plate 1, and sleeve positioning round hole 11 are evenly arranged along the length and width of the bottom template 10. The multiple sets of the sleeve assembly are detachably fixed to the fixing component, and the fixing component is used to fix and position the sleeve assembly.

[0072] Preferred, see Figure 2 , Figure 3 , Figure 4 , Figure 5 The sleeve assembly includes a supporting steel pipe 3, a pre-embedded bolt sleeve 4, a connecting nut 13, and an anchor bolt 14;

[0073] One end of the supporting steel pipe 3 is coaxially fixed with the circumferential surface of the sleeve positioning hole 11, and the end face of the other end of the supporting steel pipe 3 is coaxially fixed with the connecting nut 13. The connecting nut 13 is threadedly connected to the anchor bolt 14, and the surface of the connecting nut 13 away from the bottom template 10 is coaxially fixed with the pre-embedded bolt sleeve 4.

[0074] In this embodiment, the number of sleeve components, positioning steel plates 1, and sleeve positioning round holes 11 uniformly arranged along the bottom template 10 is the same as that in the first embodiment.

[0075] The method of "fixing the outer circumferential surface of one end of the supporting steel pipe 3 coaxially with the circumferential surface of the sleeve positioning hole 11" can be: welding fixation.

[0076] The method of "fixing the end face of the other end of the supporting steel pipe 3 coaxially with the connecting nut 13" can be: welding fixation.

[0077] The method of "fixing the surface of the connecting nut 13 on the side away from the bottom template 10 coaxially with the pre-embedded bolt sleeve 4" can be: welding fixation.

[0078] Preferred, Figure 2 The fixing components include connecting fasteners 5, transverse reinforcing rods 6, longitudinal positioning rods 8, template scaffolding 9, and fixing fasteners 15;

[0079] The transverse reinforcing rod 6 is fixed to the template scaffold 9 and the longitudinal positioning rod 8 respectively through the connecting fastener 5. Two sets of longitudinal positioning rods 8 are arranged along both sides of the pre-embedded bolt sleeve 4. The longitudinal positioning rod 8 is fixed to the end of the pre-embedded bolt sleeve 4 away from the bottom template 10 through the fixing fastener 15.

[0080] The specific method of "fixing the longitudinal positioning rod 8 to the end of the pre-embedded bolt sleeve 4 away from the bottom template 10 by means of the fixing fastener 15" is as follows: two fixing fasteners 15 are set at the diagonal of the intersection point of the longitudinal positioning rod 8 and the pre-embedded bolt sleeve 4 to fix the pre-embedded bolt sleeve 4.

[0081] In this embodiment, the number of longitudinal positioning rods 8, template scaffolding 9, and transverse reinforcing rods 6 is set according to the number in the first embodiment.

[0082] Preferred, see Figure 2 The positioning steel plate 1 is fixed to the bottom template 10 by the positioning screws 12.

[0083] In this embodiment, the positioning steel plate 1 is fixed to the bottom template 10 by four positioning bolts 12 at its four corners. However, the number of positioning bolts 12 is not limited to four.

[0084] In this embodiment, the positioning steel plate 1 is square, but not limited to square; it can be any shape such as round or rhomboid.

[0085] Preferred, see Figure 2 The transverse reinforcing rod 6 is parallel to the width direction of the bottom template 10, and the longitudinal positioning rod 8 is parallel to the length direction of the bottom template 10.

[0086] Wherein, the length direction of the bottom template 10 is Figure 1 The long side direction shown is the width direction of the bottom template 10. Figure 2 The direction of the shorter side is shown.

[0087] The fourth embodiment of the present invention is described in [reference needed]. Figure 2 , Figure 3 , Figure 4 , Figure 5 A method for fixing a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation is proposed. Based on the third embodiment of the pre-embedded anchor bolt sleeve assembly for a steam turbine foundation, the method includes the following steps:

[0088] Step A10: Fix one end of the support steel pipe 3 in the sleeve assembly to the positioning steel plate 1, and fix the connecting nut 13 in the sleeve assembly to the end face of the other end of the support steel pipe 3. Connect the connecting nut 13 to the anchor bolt 14 in the sleeve assembly. Pour concrete into the support steel pipe 3 through the positioning hole 11 of the sleeve. After the concrete solidifies, fix the pre-embedded bolt sleeve 4 on the connecting nut 13. The fixed support steel pipe 3, the positioning steel plate 1, the connecting nut 13, the anchor bolt 14 and the pre-embedded bolt sleeve 4 are used as the second component.

[0089] Step A20: Mark the positions of multiple pre-embedded bolt sleeves 4 on the bottom template 10 as the second positions, and fix multiple second components at the second positions by positioning screws 12;

[0090] Step A30: Fix the transverse reinforcing rod 6 and the template scaffold 9 in the fixing assembly using the connecting fastener 5, then fix the transverse reinforcing rod 6 to the longitudinal positioning rod 8 in the fixing assembly using the connecting fastener 5, clamp the pre-embedded bolt sleeve 4 using the longitudinal positioning rod 8, and fix it with the fixing fastener 15 in the fixing assembly;

[0091] Step A40: Pour the main concrete. After the concrete reaches the design strength, remove the formwork, the formwork scaffolding 9, the connecting fasteners 5, the horizontal reinforcing rods 6, the longitudinal positioning rods 8, and the fixing fasteners 15 to complete the construction.

[0092] After the second component is assembled, it is placed in a temporary storage area. Then, measurements and layout are carried out.

[0093] In step A40, the templates in "removing the templates" include all the templates of the turbine base as a whole, including the bottom template 10.

[0094] The terms “first”, “second”, etc., are used to distinguish similar objects, not to describe or indicate a specific order or sequence.

[0095] The term "comprising" or any other similar term is intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus / device that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent in such process, method, article, or apparatus / device.

[0096] The technical solution of the present invention has been described above with reference to the preferred embodiments shown in the accompanying drawings. However, it will be readily understood by those skilled in the art that the scope of protection of the present invention is obviously not limited to these specific embodiments. Without departing from the principles of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will all fall within the scope of protection of the present invention.

Claims

1. A steam turbine foundation pre-embedded anchor bolt sleeve assembly, characterized in that, The anchor bolt sleeve assembly includes a sleeve assembly, a fixing assembly, a positioning steel plate (1), a bottom template (10), and a sleeve positioning round hole (11). The sleeve assembly is coaxially fixed with the circumferential surface of the sleeve positioning hole (11). The sleeve positioning hole (11) is opened on the positioning steel plate (1). The positioning steel plate (1) is detachably fixed with the bottom template (10). The bottom template (10) is used to position the sleeve assembly. The sleeve assembly, positioning steel plate (1), and sleeve positioning round hole (11) are evenly arranged in multiple sets along the length and width direction of the bottom template (10). The multiple sets of sleeve assemblies are detachably fixed to the fixing assembly. The fixing assembly is used to fix and position the sleeve assembly. The sleeve assembly includes a supporting steel pipe (3), a pre-embedded bolt sleeve (4), a connecting nut (13), and an anchor bolt (14). One end of the supporting steel pipe (3) is coaxially fixed with the circumferential surface of the sleeve positioning hole (11), the end face of the other end of the supporting steel pipe (3) is coaxially fixed with the connecting nut (13), the connecting nut (13) is threadedly connected with the anchor bolt (14), and the surface of the connecting nut (13) away from the bottom template (10) is coaxially fixed with the pre-embedded bolt sleeve (4). Concrete is poured into the supporting steel pipe (3) through the positioning hole (11) of the sleeve, and after the concrete solidifies, the pre-embedded bolt sleeve (4) is fixed on the connecting nut (13). The fixing components include connecting fasteners (5), transverse reinforcing bars (6), longitudinal positioning bars (8), formwork scaffolding (9), and fixing fasteners (15). The transverse reinforcing rod (6) is fixed to the template scaffold (9) and the longitudinal positioning rod (8) respectively through the connecting fastener (5). Two sets of the longitudinal positioning rod (8) are set along both sides of the pre-embedded bolt sleeve (4). The longitudinal positioning rod (8) is fixed to the end of the pre-embedded bolt sleeve (4) away from the bottom template (10) through the fixing fastener (15). The positioning steel plate (1) is fixed to the bottom template (10) by positioning screws (12); The transverse reinforcing rod (6) is parallel to the width direction of the bottom template (10), and the longitudinal positioning rod (8) is parallel to the length direction of the bottom template (10).

2. The turbine foundation pre-embedded anchor bolt sleeve assembly according to claim 1, characterized in that, The end face of the pre-embedded bolt sleeve (4) away from the connecting nut (13) is detachably fixed to the temporary sealing steel plate (7).

3. A method for fixing a pre-embedded anchor bolt sleeve assembly for a steam turbine foundation, based on the pre-embedded anchor bolt sleeve assembly for a steam turbine foundation as described in any one of claims 1 or 2, characterized in that... The method includes the following steps: Step A10: Fix one end of the support steel pipe (3) in the sleeve assembly to the positioning steel plate (1), and fix the connecting nut (13) in the sleeve assembly to the end face of the other end of the support steel pipe (3). Connect the connecting nut (13) to the anchor bolt (14) in the sleeve assembly. Pour concrete into the support steel pipe (3) through the sleeve positioning hole (11). After the concrete solidifies, fix the pre-embedded bolt sleeve (4) on the connecting nut (13). The fixed support steel pipe (3), the positioning steel plate (1), the connecting nut (13), the anchor bolt (14) and the pre-embedded bolt sleeve (4) are used as the second component. Step A20: Mark the positions of multiple pre-embedded bolt sleeves (4) on the bottom template (10) as the second position, and fix multiple second components at the second position by positioning screws (12); Step A30: Fix the transverse reinforcing rod (6) and the template scaffold (9) in the fixing assembly using the connecting fastener (5), then fix the transverse reinforcing rod (6) to the longitudinal positioning rod (8) in the fixing assembly using the connecting fastener (5), clamp the pre-embedded bolt sleeve (4) using the longitudinal positioning rod (8), and fix it using the fixing fastener (15) in the fixing assembly; Step A40: Pour the main concrete. After the concrete reaches the design strength, remove the formwork, the formwork scaffold (9), the connecting fasteners (5), the horizontal reinforcing rods (6), the longitudinal positioning rods (8), and the fixing fasteners (15) to complete the construction.

Citation Information

Patent Citations

  • Installation and construction method for high-precision embedded bolt on top of column

    CN114673190A

  • Pre-embedded high-strength foundation bolt of reciprocating piston type compressor

    CN210567053U