Underwater extension structure and construction method after double-walled steel cofferdam sinks and gets stuck

By extending the underwater structure after the double-walled steel cofferdam was sunk and jammed, and connecting the extended structure with the double-walled steel cofferdam using concrete and grout layers, the jamming problem was solved, the cofferdam was sealed and water stopped, and the construction of the pier cap was ensured to proceed smoothly.

CN117822622BActive Publication Date: 2026-11-17THE 2ND CONSTR COMPANY LTD OF CHINA RAILWAY CONSTR 15TH
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202410135052.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-31
Publication Date
2026-11-17
Estimated Expiration
2044-01-31

AI Technical Summary

Technical Problem

After the double-walled steel cofferdam was sunk and jammed, it could not be lowered to the design elevation, which made construction difficult. In addition, the existing technology of using a steel cofferdam with a concrete retaining wall occupies internal space and affects the construction of the foundation.

Method used

An extension structure, consisting of a concrete layer and a grout layer, is adopted. The extension structure is connected to the double-walled steel cofferdam through an underwater casting trench. Grouting is carried out through grouting pipes to enhance the sealing performance, ensuring that the cofferdam reaches the design elevation and eliminating the influence of obstructions.

Benefits of technology

It achieves sealing and water stoppage of the cofferdam in a stuck state, avoids internal space occupation, ensures smooth construction of the pier cap, and is simple and low-cost to construct.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117822622B_ABST
    Figure CN117822622B_ABST
Patent Text Reader

Abstract

This invention relates to the field of bridge construction technology, specifically to an underwater extension structure and its construction method for a double-walled steel cofferdam that has sunk and become stuck in a clay layer. It solves the problem in existing technologies where a double-walled steel cofferdam, stuck due to special reasons, cannot be lowered to the design elevation, leading to difficulties in water sealing. The underwater extension structure for a double-walled steel cofferdam that has sunk and become stuck includes the double-walled steel cofferdam itself. A casting groove is located below the double-walled steel cofferdam, and an extension structure is cast into the casting groove. The extension structure is connected to the cutting edge of the double-walled steel cofferdam. The beneficial effects of this invention are: the extension structure extends the lower part of the double-walled steel cofferdam, allowing it to reach the design elevation and seal it when it cannot be lowered to the design elevation, eliminating the influence of obstructions on the double-walled steel cofferdam. Furthermore, the extension structure can adapt to obstructions of different shapes, has good water-stopping effect, and has strong applicability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of bridge construction technology, and in particular to the underwater extension structure and construction method of a double-walled steel cofferdam in a clay layer after it sinks and gets stuck. Background Technology

[0002] Currently, in the construction of bridges spanning various rivers, lakes, and seas, the water-retaining equipment used for the deep-water foundation piers of large bridges is either single-walled or double-walled steel cofferdams. In the design of piers for large bridges navigable in deep water, the piers are often positioned below the riverbed scour line to ensure navigation, increasing construction difficulty. To increase the rigidity and settling force of the cofferdam during on-site construction, the double-walled steel cofferdam method is often adopted. However, the double-walled steel cofferdam is significantly affected by the geological conditions below the riverbed during its lowering process, especially in special circumstances where it may be difficult to lower or even become stuck, preventing it from reaching the designated position. The "stuck state" refers to a situation where, even after increasing the weight of the double-walled steel cofferdam by injecting water and pouring concrete, the cofferdam still cannot sink. Furthermore, according to the exploration of the surrounding soil during construction, the soil layer was found to be hard plastic clay with a large amount of calcareous nodules. At the same time, a ring of concrete was applied to the outside of the cofferdam during construction, and the cofferdam's sinking coefficient was less than 1.0, indicating that the double-walled steel cofferdam could no longer sink.

[0003] Patent CN105649094A discloses a three-walled steel cofferdam for deep-water foundation construction, comprising a cofferdam body, an inner support frame on the top inner side of the cofferdam body, and a working platform mounted on the inner support frame. The cofferdam body comprises an outer wall, a middle wall, and an inner wall from the outside in. The outer wall and the middle wall are at the same height, with reinforcing ribs between them. The inner wall is lower than the middle wall, with a concrete pouring layer between them. A foundation is located at the bottom inner side of the cofferdam body, and several concrete piles are installed at the bottom of the foundation. The cofferdam body, the concrete pouring layer between the inner and middle walls, and the bedrock form a unified structure, resulting in a more robust structure that better meets the requirements of construction in deep water with high flow velocities.

[0004] The aforementioned patent uses a double-walled steel cofferdam with a concrete retaining wall for construction. The concrete retaining wall is located inside the double-walled cofferdam, which occupies a large space and encroaches on the space of the original design pier. This results in insufficient internal space of the double-walled steel cofferdam, ultimately affecting the construction of the pier. Summary of the Invention

[0005] This invention proposes an underwater extension structure and construction method for a double-walled steel cofferdam after it has sunk and become stuck. This solves the problem in the prior art where a double-walled steel cofferdam cannot be lowered to the design elevation due to special reasons, making it difficult to stop the water flow. At the same time, it avoids the problem in the prior art where a concrete retaining wall is installed over the steel cofferdam, which occupies the internal space of the double-walled steel cofferdam and affects the construction of the foundation.

[0006] The technical solution of this invention is implemented as follows: The underwater extension structure for a double-walled steel cofferdam after sinking and becoming stuck includes a double-walled steel cofferdam with a casting groove at its lower part. The extension structure is cast into the casting groove and connects to the cutting edge of the double-walled steel cofferdam. The extension structure extends the lower part of the double-walled steel cofferdam, sealing it before it reaches the design elevation. This ensures the cofferdam structure reaches the design elevation, eliminates the influence of obstructions, and is adaptable to obstructions of different shapes, providing good water-stopping effect and strong applicability.

[0007] The bottom height of the extension structure is no higher than the design elevation of the bottom of the double-walled steel cofferdam, and the extension structure is tightly connected to the base of the casting trench. After the extension structure is connected to the double-walled steel cofferdam as a whole, the extension structure is used as a cofferdam to bring the cofferdam to the designated elevation.

[0008] The extension structure includes a concrete layer and a grout layer, with the concrete layer located above the grout layer and connected to the cutting edge of the double-walled steel cofferdam. The grout layer provides a watertight seal to the gap between the concrete layer and the bottom of the casting trench, thereby ensuring that the extension structure has good watertight performance.

[0009] A grouting conduit is pre-embedded within the grout layer. The grouting conduit is a U-shaped pipe with evenly distributed grout outlets on both sides of its bottom. The grouting port of the U-shaped pipe is detachably connected to the grouting conduit, and the drain outlet of the U-shaped pipe is detachably connected to the plug. The transverse portion of the U-shaped pipe is located in the soil at the bottom of the pouring trench. During grouting, the grout is first forced out through the outlet, and then the drain outlet is immediately sealed with the plug. Then, grouting begins slowly, pressurizing to the required grouting pressure value, stabilizing the pressure for a certain period of time, and circulating 1 to 2 times. This ensures that the grout fully penetrates into the soil below the concrete layer, enhancing the strength and sealing of the extended structure, thereby preventing water from seeping into the double-walled steel cofferdam through weak points in the concrete layer.

[0010] The grouting port and drainage port extend upwards from the top surface of the extension structure. During grouting, the grouting conduit and the grouting port are connected, and then the grouting machine performs grouting through the grouting conduit. The grout displaces the water in the grouting pipe through the drainage port, and after the water is discharged, the drainage port is sealed with a plug to ensure that all the grout injected into the soil is grout.

[0011] A construction method for an underwater extension structure after the double-walled steel cofferdam has sunk and become stuck includes the following steps: S1, the double-walled steel cofferdam is in a stuck state of sinking. Excavate the soil inside the double-walled steel cofferdam until the height of the soil base is level with the top of the cutting edge of the double-walled steel cofferdam; the stuck state refers to the situation where the double-walled steel cofferdam still cannot sink after increasing its self-weight by injecting water or pouring concrete into the double-walled steel cofferdam; it is determined that there is an obstruction on the lower side of the double-walled steel cofferdam preventing it from descending to the design elevation, and it cannot be removed due to special circumstances.

[0012] S2, drill holes along the inner edge of the double-walled steel cofferdam, and connect the holes to form a rectangular trench; the rectangular trench serves as the working space for clearing the soil under the cutting edge, and the trench has a limited height and is stable, thus creating a safe working environment.

[0013] S3. Divers excavate and clear the soil on the sides of the rectangular trench underwater to form a casting trench. Divers carry high-pressure water jets or pneumatic picks to wash away the secondary hard soil under the cutting edge or impact cutting edge of the double-walled steel cofferdam to ensure the continuity of the trench, with a cross-sectional area of ​​not less than 70% of the design cross-section and no soft mud covering the rectangular trench.

[0014] S4. A grouting pipe is embedded at the bottom of the pouring trench to pour concrete into the trench to form a concrete layer for the extension structure. When pouring concrete, the grouting method is used for underwater pouring in different areas. The pouring height of the concrete layer for the extension structure needs to be controlled to avoid increasing the top surface of the concrete layer for the extension structure too high, which would increase the workload of chiseling after dewatering and ensure the smooth progress of the subsequent foundation construction.

[0015] S5, grouting is performed on the soil under the concrete layer through the grouting pipe to form a grout layer for the extended structure; after the concrete layer reaches the required strength, grout is injected into the grouting pipe through the grouting machine to form a grout layer. The grout layer can enhance the sealing between the concrete layer and the soil below, thereby enhancing the water-stopping ability of the extended structure.

[0016] S6. Pump out the water from the inside of the double-walled steel cofferdam. Install the inner supports of the steel cofferdam sequentially from top to bottom. Excavate the soil inside the double-walled steel cofferdam to the design elevation. Remove any protruding parts of the long structure from the inner wall of the double-walled steel cofferdam. After tidying up, pour the concrete foundation layer. During pouring, prepare water collection wells as needed, and use water pumps to periodically drain the water from the foundation pit, thus creating a waterless and safe environment for the foundation construction. After the water is pumped out from the inside of the double-walled steel cofferdam, the inner supports are tightly pressed against the inner wall of the double-walled steel cofferdam to prevent it from tilting under water pressure, ensuring the safety of the foundation construction.

[0017] In section S1, after excavation of the soil within the double-walled steel cofferdam, the soil base elevation is the same as the top surface of the concrete extension structure. Excavation of the weak layer is carried out using a long-arm excavator and a cutter pump, or by rotary drilling rigs to remove soil, followed by soil extraction using cutter pumps, air suction dredgers, and long-arm excavators. Only the soil inside the double-walled steel cofferdam is excavated, as water remains inside to prevent pressure imbalance and potential collapse of the cofferdam.

[0018] In S2, a rotary drilling rig is used to drill interlocking holes along the inner edge of the double-walled steel cofferdam. The bottom height of the rectangular trench is the design elevation of the bottom of the double-walled steel cofferdam. The rotary drilling rig uses an interlocking pile trenching construction process, where the circumference of two adjacent holes is partially interlocked to ensure that all holes are connected to form a rectangular trench.

[0019] In S3, after the rectangular trench is stabilized, divers excavate the soil below the double-walled steel cofferdam and clear the surface of any obstructions that cannot be excavated below the double-walled steel cofferdam. After excavation, ensure that the cross-sectional area of ​​the pouring trench is not less than 70% of the designed cross-section, and ensure that the extension structure is fully connected to the cutting edge of the double-walled steel cofferdam.

[0020] In S4, concrete layers are poured in several sections within the pouring trench. Underwater concrete is poured using a grouting method via a concrete duct. The junction of the poured concrete layers corresponds to the middle position of the grouting duct. This junction is a weak point in the extended structure, prone to water seepage. During grouting, grout exits from the grout outlet in the middle of the grouting duct, filling and sealing the weak point, enhancing the waterproofing performance of the concrete layer junction, and thus ensuring the watertightness of the extended structure.

[0021] In S6, the strength of the extended structure and the grout-reinforced soil should be assessed before dewatering. Dewatering can only proceed after the strength meets the requirements. Dewatering should begin slowly for observation, then proceed at a uniform rate, and the dewatering time should not be too short. After the bottom is reached, the soil inside the cofferdam should be quickly leveled, and then the foundation layer or underwater sealing concrete should be constructed immediately. If any concrete extension structure is found to be too high or too wide and encroaching on the foundation, it can be manually removed or stripped away with a high-pressure water jet. If seepage still occurs after the bottom is reached, and the seepage rate is stable, a water collection well can be installed at an appropriate location at the bottom of the cofferdam, and water can be pumped out periodically to achieve a waterless working environment.

[0022] By reducing the height of the soil inside the cofferdam in S1, the depth of the trench is reduced, providing a relatively safe working environment for the S3 construction. In S3, depending on the difficulty of the excavation, it is only necessary to ensure that the excavation cross-section of the pouring trench reaches 70% of the design cross-section. The key is to clean the cutting edge of the steel cofferdam thoroughly, and the weak layer at the contact surface of the pouring trench under the cutting edge must be cleaned up, and the thickness of the sediment in the pouring trench must be strictly controlled.

[0023] The soil in contact with the casting trench inside the double-walled steel cofferdam is cohesive soil, which has good inherent stability. During the casting of the extension structure, this soil is used as a soil mold to form the interface of the extension structure. Furthermore, clay generally has good strength and low permeability, providing internal support for the extension structure and thus creating a safe, watertight environment.

[0024] The beneficial effects of this invention are as follows: the extension structure extends the lower part of the double-walled steel cofferdam underwater, so that when the double-walled steel cofferdam cannot be lowered to the design elevation, the lower part of the double-walled steel cofferdam can be extended to reach the design elevation and sealed by the extension structure, eliminating the influence of obstructions on the double-walled steel cofferdam. In addition, the extension structure can adapt to obstructions of different shapes, has a good water-stopping effect, and has strong applicability.

[0025] In addition, the extension structure will not encroach on the internal space of the double-walled steel cofferdam, thus avoiding interference with the construction of the pier cap and ensuring the smooth progress of construction.

[0026] Cofferdams are typically extended above water. However, this scheme addresses the issue of a double-walled steel cofferdam becoming stuck and unable to sink further. Instead, it utilizes underwater concrete pouring to extend the cofferdam to the design elevation, thus achieving the original construction plan's objectives. The design and construction of this extended cofferdam fully leverages the performance of the original steel cofferdam, while also taking advantage of the high strength and low permeability of the cofferdam's clay. The underwater concrete extension of the double-walled steel cofferdam involves a smaller workload and lower costs.

[0027] This method makes full use of the existing machinery and equipment on the construction site, and construction can be carried out without special equipment. The construction procedures are simple, the technology is mature, and there are few restrictions on the construction process. It has the characteristics of safe and convenient construction and controllable risks. Attached Figure Description

[0028] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0029] Figure 1 This is a schematic diagram of the sinking and jamming state of a double-walled steel cofferdam. Figure 2 A schematic diagram showing the excavation and elevation reduction within the cofferdam; Figure 3 For rotary drilling rigs to form grooves; Figure 4 This is a diagram illustrating underwater operations by divers. Figure 5 A schematic diagram of underwater concrete pouring for the extension of the cofferdam body using a duct. Figure 6 After the concrete reaches the required strength, water is pumped out, the subbase is constructed, and a good working environment is created before constructing the foundation. Figure 7 For rotary drilling rigs to form grooves; Figure 8 Schematic diagram of underwater grouting pipe arrangement; Figure 9 This is a schematic diagram of the grouting conduit structure.

[0030] In the diagram: 1. Trestle platform, 2. Double-walled steel cofferdam, 3. Clay layer, 4. Obstruction, 5. Water surface, 6. Foundation pile, 7. Long-arm excavator, 8. Rotary drilling rig, 9. Rectangular trench, 10. Pouring trench, 11. Air suction dredger, 12. Concrete guide pipe, 13. Extension structure, 131. Concrete layer, 132. Grout layer, 14. Grouting guide pipe, 141. Grouting port, 142. Drainage outlet, 143. Grout outlet hole, 15. Concrete cushion layer, 16. Foundation, 17. Steel cofferdam inner support. Detailed Implementation

[0031] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0032] Example 1, as Figure 6As shown, the underwater extension structure after the double-walled steel cofferdam sinks and gets stuck includes a double-walled steel cofferdam 2. A casting groove 10 is provided below the double-walled steel cofferdam 2. An extension structure 13 is cast in the casting groove 10. The extension structure 13 is connected to the cutting edge of the double-walled steel cofferdam 2. The obstruction 4 that causes the double-walled steel cofferdam 2 to become stuck is located below the double-walled steel cofferdam 2, and the obstruction 4 is embedded in the extension structure 13. In this embodiment, the obstruction 4 is a boulder, hard soil layer, or other material that prevents the double-walled steel cofferdam 2 from descending, and because it is located in an ecological protection area, it is impossible to take forceful measures to remove it. The extension structure 13 extends the lower part of the double-walled steel cofferdam 2, so that when the double-walled steel cofferdam 2 has not descended to the design elevation, the lower part of the double-walled steel cofferdam 2 is sealed by pouring concrete and grout to form the extension structure 13, eliminating the influence of the obstruction 4 on the double-walled steel cofferdam 2. Furthermore, the obstruction 4 and the extension structure 13 are connected as one unit. The extension structure 13 can adapt to obstructions 4 of different shapes and has strong applicability.

[0033] Furthermore, the bottom height of the extension structure 13 is not higher than the bottom design elevation of the double-walled steel cofferdam 2, and the extension structure 13 is tightly connected to the base of the casting trough 10. After the extension structure 13 is connected to the bottom cutting edge of the double-walled steel cofferdam 2 as a whole, the extension structure 13 is used as a cofferdam to bring the cofferdam to the designated elevation. Ensuring that the extension structure 13 has sufficient depth ensures the sealing performance of the cofferdam.

[0034] Furthermore, such as Figure 8 As shown, the extension structure 13 includes a concrete layer 131 and a grout layer 132. The concrete layer 131 is located above the grout layer 132 and is connected to the cutting edge of the double-walled steel cofferdam 2. The grout layer 132 provides a water-stopping seal for the gap between the concrete layer 131 and the bottom of the casting trench 10, thereby ensuring that the extension structure 13 has good water-stopping performance.

[0035] Example 2, based on Example 1, involves an underwater extension structure after the double-walled steel cofferdam sinks and becomes stuck, such as... Figure 9 As shown, a grouting conduit 14 is pre-embedded within the grout layer 132. The grouting conduit 14 is a U-shaped pipe, with evenly distributed grout outlet holes 143 on both sides of the bottom of the U-shaped pipe. The grouting port 141 of the U-shaped pipe is detachably connected to the grouting conduit, and the drain port 142 of the U-shaped pipe is detachably connected to the plug. In this embodiment, the grout outlet holes 143 are distributed crisscrossingly on both sides of the bottom of the U-shaped pipe, with a spacing of 10cm between two adjacent grout outlet holes 143, and the diameter of the grout outlet holes 143 is 3~8mm. Both the grouting port 141 and the drain port 142 of the U-shaped pipe are threaded. The grouting conduit of the grouting machine is threadedly connected to the grouting port, and the plug is threadedly connected to the drain port 142.

[0036] Specifically, during construction, the transverse portion of the U-shaped pipe is first pre-embedded in the soil at the bottom of the casting trench 10, followed by the pouring of the concrete layer. Once the concrete layer has sufficient strength, grouting begins. Grout is first pumped out from the drain outlet 142 and the grout outlet 143. After the grout fills the grouting conduit 14, the drain outlet 142 is immediately sealed with a plug. Slow grouting then begins, pressurizing to 2.5 MPa, stabilizing the pressure for 60 seconds, and circulating twice. This allows the grout to exit from the grout outlet 143 at the bottom of the U-shaped pipe and enter the soil below the casting trench 10, ensuring the grout fully penetrates the gap between the concrete layer 131 and the soil. This enhances the strength and sealing of the extended structure 13, preventing water from seeping into the cofferdam through weak points. During the grouting process, a two-component grout of equal parts cement and water glass is used.

[0037] Furthermore, the grouting port 141 and the drain port 142 extend upwards from the top surface of the extension structure 13. The grouting conduit 14 is made of a steel pipe with a diameter of 50 mm and a wall thickness of 3 mm, bent into shape. The width of the grouting conduit 14 is 2 m. After the grouting conduit 14 is placed, multiple evenly arranged grouting conduits 14 are placed in the pouring trough 10. The bottom of the U-shaped pipe is located 30 cm from the bottom of the pouring trough 10. The grouting port 141 and the drain port 142 of the U-shaped pipe are 50 mm above the top of the pouring trough 10. The distance between two adjacent grouting conduits 14 is 3 m.

[0038] Example 3, based on Example 1 or Example 2, provides a construction method for the underwater extension structure after the double-walled steel cofferdam has sunk and become stuck, comprising the following steps: S1, the double-walled steel cofferdam 2 is in a subsided and stuck state. Excavate the soil inside the double-walled steel cofferdam 2 until the height of the soil base is level with the top of the cutting edge of the double-walled steel cofferdam 2; if Figure 1 , Figure 2 As shown, in this embodiment, the "stuck state" refers to the situation where the double-walled steel cofferdam 2 cannot sink even after increasing its weight by injecting water or pouring concrete into it. It is determined that there is an obstruction 4 on the lower side of the double-walled steel cofferdam 2 preventing it from descending to the design elevation. Specifically, there is an obstruction 4 below the double-walled steel cofferdam 2, which is a boulder, hard soil layer, or other material that prevents the double-walled steel cofferdam 2 from descending. Due to the presence of the obstruction 4, and because it cannot be removed for special reasons, the double-walled steel cofferdam 2 cannot descend to the design elevation. At this time, using a grabber and excavator, the soil inside the double-walled steel cofferdam 2 is directly excavated to lower the soil height, allowing the soil inside the double-walled steel cofferdam 2 to descend to the height of the top of the cutting edge of the double-walled steel cofferdam 2 when it is stuck.

[0039] S2, Drill holes along the inner edge of the double-walled steel cofferdam 2, and connect the drilled holes to form a rectangular trench 9; as shown Figure 3As shown, the rectangular trough 9 is set along the inner edge of the double-walled steel cofferdam 2. The rectangular trough 9 can serve as an underwater channel, facilitating divers to clear the soil below the double-walled steel cofferdam 2 underwater. Specifically, as shown... Figure 7 As shown, the circumferences between two adjacent drill holes are interlocked, connecting all the drill holes.

[0040] S3, Divers excavate and clear the soil on the sides of the rectangular trench 9 underwater to form the casting trench 10; as Figure 4 As shown, divers excavate and clear the soil below the double-walled steel cofferdam 2 along the rectangular trench 9, ensuring that the bottom surface of the pouring trench 10 reaches the design elevation of the double-walled steel cofferdam 2. This guarantees the sealing of the cutting edge of the subsequent pouring of the extension structure 13 to the double-walled steel cofferdam 2. Simultaneously, the obstruction 4 below the double-walled steel cofferdam 2 is flushed to ensure its surface is clean and free of any weak layers, facilitating a tight bond between the concrete and obstruction 4 during subsequent concrete pouring. This ensures a tight seal between the concrete and obstruction 4, preventing water seepage at the connection point. The pouring trench 10 serves as a template for the subsequent pouring of the extension structure 13 and also provides support for the poured extension structure.

[0041] S4, a grouting pipe 14 is embedded at the bottom of the pouring trench 10 to pour concrete into the pouring trench 10 to form a concrete layer 131 for the extension structure 13; such as Figure 5 As shown, the pouring trench 10 is divided into several pouring areas, and several guide pipes are used to pour underwater concrete according to the underwater concrete "grouting method" construction process. During construction, care must be taken to move the guide pipes. When pouring the concrete layer 131 of the extension structure 13, the soil surrounding the pouring trench 10 can serve as the pouring formwork, eliminating the need for additional underwater formwork. This reduces the construction process, facilitates the construction of the concrete layer 131 of the extension structure 13, and improves construction efficiency. Furthermore, before pouring, the trench needs to be inspected to ensure that the dimensions, depth, and sediment thickness of the pouring trench 10 meet the requirements.

[0042] S5, grouting is performed on the soil under the concrete layer 131 through the grouting pipe 14 to form a grout layer 132 for the extension structure 13; after the concrete layer 131 reaches the required strength, grouting is performed through the grouting pipe 14. The grouting fluid is a two-component grout made of equal amounts of cement and water glass. The grout layer 132 can enhance the sealing between the concrete layer 131 and the soil below, thereby enhancing the water-stopping ability of the extension structure.

[0043] S6, pump out the water inside the double-walled steel cofferdam 2, install the inner steel cofferdam support 17 from top to bottom inside the double-walled steel cofferdam 2, excavate the soil inside the double-walled steel cofferdam 2 to the design elevation, remove the part of the connecting long structure 13 protruding from the inner wall of the double-walled steel cofferdam 2, and after tidying up, pour the concrete cushion layer 15. (Example) Figure 6As shown, an experimental pumping test was first conducted to verify the water-stopping effect of the double-walled steel cofferdam 2 and the extension structure 13. Based on the water-stopping effect and the geological conditions inside the double-walled steel cofferdam 2, the concrete foundation 15 was constructed using either dry sealing or underwater concrete sealing methods to provide favorable working conditions for the construction of the foundation 16. Furthermore, when the water inside the double-walled steel cofferdam 2 was pumped out, the inner steel cofferdam supports 17 were installed sequentially from top to bottom according to the design and tightened against the inner wall of the double-walled steel cofferdam 2 to prevent instability of the double-walled steel cofferdam 2 under water pressure, thereby ensuring the safety of the foundation construction.

[0044] In addition, after pumping out the water, workers can remove the part of the extension structure 13 that protrudes from the inner wall of the double-walled steel cofferdam 2 by manual chiseling or high-pressure water jet stripping. This will prevent the extension structure 13 from encroaching on the internal space of the double-walled steel cofferdam 2, avoid interference with the construction of the pier cap 16, and ensure the smooth progress of the construction.

[0045] Example 4 differs from Example 3 in that it describes a construction method for an underwater extension structure after the double-walled steel cofferdam sinks and becomes stuck. In S1, after excavating the soil inside the double-walled steel cofferdam 2, the soil base elevation is the elevation of the top surface of the concrete extension structure 13. A long-arm excavator and a cutter pump are used to excavate the weak layer, or a rotary drilling rig is used to remove soil, followed by soil extraction using a cutter pump, an air suction dredger, and a long-arm excavator. In this example, a long-arm excavator 7 is used to excavate the soil inside the double-walled steel cofferdam 2. Specifically, the long-arm excavator 7 is moved to the trestle platform 1, and it excavates the soil inside the double-walled steel cofferdam 2. During the excavation process, it is ensured that the long-arm excavator 7 will not damage the foundation piles 6 in the soil. When the soil surface inside the double-walled steel cofferdam 2 drops to the design elevation of the foundation piles 16, the foundation piles 6 are exposed on the soil surface.

[0046] Furthermore, in S2, a rotary drilling rig 8 is used to drill along the inner edge of the double-walled steel cofferdam 2, and the bottom height of the rectangular trench 9 is the design elevation of the bottom of the double-walled steel cofferdam 2. Specifically, the rotary excavator 8 is moved to the trestle platform 1, and a small-diameter rotary drilling rig is used for drilling. The drilling adopts the construction process of interlocking pile trenching, which forms an underwater trench channel along the wall of the double-walled steel cofferdam 2, creating a good working environment for clearing the soil under the double-walled steel cofferdam 2.

[0047] Furthermore, in S3, after the rectangular trench 9 is stabilized, divers excavate the soil below the double-walled steel cofferdam 2 and clear the surface of any obstructions below the double-walled steel cofferdam 2 that cannot be excavated. For example... Figure 4As shown, divers, equipped with high-pressure water jets or pneumatic drills, use the rectangular trench 9 to wash the cutting edge of the double-walled steel cofferdam 2, excavating and disturbing the soil below the double-walled steel cofferdam 2 to form the pouring trench 10. The trench 10 is then cleaned, removing any boulders or hard soil layers that cannot be removed. The bottom of the pouring trench 10 must reach the design elevation of the bottom of the double-walled steel cofferdam 2. Then, an air suction dredger 11 is used to clean the pouring trench 10 and the area below the double-walled steel cofferdam 2. This ensures the continuity of the pouring trench 10 and that the sidewalls of the pouring trench 10 are free of weak mud, minimizing the formation of weak areas in the concrete at the interface.

[0048] In addition, after the soil is excavated, the width of the pouring trench 10 is ensured to be equal to the sum of the thickness of the double-walled steel cofferdam 2 and the diameter of the rotary drilling rig 8. This ensures that the concrete of the extension structure 13 can be fully connected to the lower part of the double-walled steel cofferdam 2 after pouring, thus ensuring the sealing of the connection between the lower part of the double-walled steel cofferdam 2 and the extension structure 13, and thus ensuring the water-stopping performance of the cofferdam during construction.

[0049] In S4, concrete layers 131 are poured in several areas within the pouring trench 10. Underwater concrete pouring is performed using a grouting method via concrete guide pipe 12. The junction of the poured concrete layers 131 corresponds to the middle position of the grouting guide pipe 14. This junction is the weakest point of the extended structure 13 and is most prone to water seepage. During grouting, grout is discharged from the grout outlet 143 in the middle of the grouting guide pipe 14. The grout fills and seals the weak point, enhancing the waterproof performance of the junction of the concrete layers 131 and thus ensuring the water-stopping performance of the extended structure 13.

[0050] Example 5, based on Example 3, provides a construction method for the underwater extension structure after the double-walled steel cofferdam has sunk and become stuck, comprising the following steps: Determined to be stuck: After completing the construction trestle platform, a rotary drilling rig was used to construct the lead-in trench. Then, relying on the pile foundation steel casing, an assembly platform was erected to assemble the double-walled steel cofferdam 2. After a seepage test, lowering began, but it was blocked at an elevation of 0.75m and could not continue. Concrete was poured to increase counterweight, and overnight, the double-walled steel cofferdam 2 subsided by 2.3cm, with a north-south elevation difference of 27.3cm. On the same day, the double-walled steel cofferdam 2 was lifted to correct its posture, but a broken strand was discovered in the lifting steel strand, and the operation was immediately stopped. This was abandoned, and a long-arm excavator and grab bucket were used to excavate the soil inside the cofferdam, but excavation was difficult. Furthermore, the space in the trench at the foot of the cofferdam body was limited, making it difficult and dangerous for divers to handle. Therefore, a ring of concrete was poured outside the cofferdam to stop the water flow. After the strength was sufficient, a pumping test was conducted, revealing a large amount of water gushing from inside the cofferdam. Considering the soil layers of the cofferdam and the reality of the external ring of concrete to stop the water flow, it was determined that the cofferdam was stuck.

[0051] S1. Excavate the soil within the cofferdam to lower the soil elevation to the designated elevation. Use a long-arm excavator and a cutter pump to excavate the weak layers. In special areas with clay layers, use a rotary drilling rig to disturb the soil layers, and then use a cutter pump, air suction dredger, and site excavator to excavate the soil within the cofferdam.

[0052] S2. Drilling trenches along the cofferdam. Using an SR60 rotary drilling rig, trenches are constructed along the cofferdam body to create interlocking piles. This forms an underwater trench along the cofferdam wall, providing a favorable working environment for clearing the soil beneath the steel cofferdam.

[0053] S3. Excavation of the lower part of the cofferdam while it is submerged. Divers, carrying high-pressure water jets or pneumatic drills, will excavate along the channel to wash the cutting edge of the cofferdam and disturb the soil below it until the design elevation is reached. A suction sludge machine will then be used to remove debris from the channel and under the cofferdam.

[0054] S4. Underwater Concrete Extension of the Cofferdam. The underwater trench is divided into four areas, and four guide pipes are used simultaneously to pour underwater concrete using the "grouting method." Care must be taken to control the pouring elevation during construction. Concrete test specimens prepared at the same time and under the same conditions are also prepared. When the concrete strength reaches 75% of the design strength, a 1:1 cement-water glass grout is injected into the grouting pipes.

[0055] S5. Concrete sealing of the bottom of the double-walled steel cofferdam. Depending on the water-stopping effect and the geological conditions within the cofferdam, dry sealing or underwater concrete sealing will be adopted.

[0056] Finally, the construction of the double-walled steel cofferdam 2 was successfully completed, and the pouring of the foundation 16 was also successfully completed.

[0057] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A construction method for underwater extension structures after a double-walled steel cofferdam has sunk and become stuck, characterized in that... The system includes a double-walled steel cofferdam (2), with a casting trough (10) below the double-walled steel cofferdam (2). An extension structure (13) is cast in the casting trough (10), and the extension structure (13) is connected to the cutting edge of the double-walled steel cofferdam (2). The bottom height of the extension structure (13) is not higher than the bottom design elevation of the double-walled steel cofferdam (2). The extension structure (13) includes a concrete layer (131) and a grout layer (132). The concrete layer (131) is located above the grout layer (132), and the concrete layer (131) is connected to the cutting edge of the double-walled steel cofferdam (2). It also includes the following steps: S1, the double-walled steel cofferdam (2) is in a sinking and stuck state. Excavate the soil inside the double-walled steel cofferdam (2) until the height of the soil base is level with the height of the top of the cutting edge of the double-walled steel cofferdam (2). S2, drill holes along the inner edge of the double-walled steel cofferdam (2), and connect the holes to form a rectangular trough (9). S3, the diver excavates and clears the soil on the side of the rectangular trench (9) underwater to form a casting trench (10). S4, a grouting pipe (14) is embedded at the bottom of the pouring trench (10) to pour concrete into the pouring trench (10) to form a concrete layer (131) for the extension structure (13). S5, grouting is performed on the soil under the concrete layer (131) through the grouting pipe (14) to form a grout layer (132) for extending the structure (13). S6, pump out the water inside the double-walled steel cofferdam (2), install the steel cofferdam inner support (17) from top to bottom inside the double-walled steel cofferdam (2), excavate the soil inside the double-walled steel cofferdam (2) to the design elevation, remove the part of the long structure protruding from the inner wall of the double-walled steel cofferdam (2), and pour the concrete cushion layer (15) after cleaning.

2. The construction method for the underwater extension structure after the double-walled steel cofferdam sinks and gets stuck, as described in claim 1, is characterized in that... A grouting conduit (14) is pre-embedded in the grout layer (132); the grouting conduit (14) is a U-shaped pipe with grout outlet holes (143) evenly arranged on both sides of the bottom of the U-shaped pipe. The grouting port (141) of the U-shaped pipe is detachably connected to the grouting conduit, and the drain port (142) of the U-shaped pipe is detachably connected to the plug.

3. The construction method for the underwater extension structure after the double-walled steel cofferdam sinks and gets stuck, as described in claim 2, is characterized in that... The grouting port (141) and the drain port (142) extend upwards from the top surface of the extension structure (13).

4. The construction method for the underwater extension structure after the double-walled steel cofferdam sinks and gets stuck, as described in claim 1, is characterized in that... In S1, after the soil inside the double-walled steel cofferdam (2) is excavated, the soil base elevation is the elevation of the top surface of the concrete extension structure (13); the weak layer is excavated by using a long-arm excavator and a cutter pump, or the soil is extracted by rotary drilling rig and then the soil is pumped out by cutter pump, air suction dredger and long-arm excavator.

5. The construction method for the underwater extension structure after the double-walled steel cofferdam sinks and gets stuck, as described in claim 1, is characterized in that... In S2, a rotary drilling rig (8) is used to drill along the inner edge of the double-walled steel cofferdam (2), and the bottom height of the rectangular trench (9) is the bottom design elevation of the double-walled steel cofferdam (2).

6. The construction method for the underwater extension structure after the double-walled steel cofferdam sinks and gets stuck, as described in claim 4 or 5, is characterized in that... In S3, after the rectangular trench (9) is stabilized, the divers excavate the soil below the double-walled steel cofferdam (2) and clean the surface of the obstruction below the double-walled steel cofferdam (2).

7. The construction method for the underwater extension structure after the double-walled steel cofferdam sinks and gets stuck, as described in claim 6, is characterized in that... In S4, concrete layers (131) are poured in several areas within the pouring trough (10). Underwater concrete pouring is carried out through the concrete conduit (12) using the grouting method. The junction of the concrete layers (131) corresponds to the middle position of the grouting conduit (14).