A low-cost, pollution-free foundation pit reinforcement construction device and method
By using a combination of PRC pipe piles and reinforcement adjustment components in foundation pit reinforcement, soil moisture is monitored and managed, and the biological growth box is combined for interlaced connection, the problems of insufficient reinforcement strength and high cost in the existing technology are solved, and the foundation is realized Stability and economic reinforcement of pits.
Patent Information
- Application Number
- CN202410139202.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-01
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-02-01
AI Technical Summary
During the existing foundation pit reinforcement construction, the low-cost support rods are insufficient, resulting in loose reinforcement after rainwater washing, and the high-cost reinforcement joint welding increases economic burden and affects construction efficiency.
Multiple groups of PRC pipe piles are combined with reinforcement and adjustment components, and water is monitored and extracted through soil moisture sensors. Stage-type moisture management is performed using water-pulled solid-liquid separation head and guide pump, and interlaced connection and reinforcement are combined with biological growth boxes to form low-cost and no-cost Polluted foundation pit reinforcement device.
It effectively reduces the reinforcement loosening caused by rainwater erosion, reduces construction costs, ensures the stability of the foundation pit and environmental safety, and achieves a low-cost and efficient reinforcement effect.
Smart Images

Figure CN117868152B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of foundation pit support, and in particular to a low-cost, pollution-free foundation pit reinforcement construction device and method. Background Art
[0002] As the scale of urban construction in my country continues to increase, there are more and more foundation pit excavation and support projects, especially subway projects. The requirements for foundation pit support are getting higher and higher, and problems are also coming along. Foundation pit support plays the role of retaining soil, stabilizing the pit bottom and intercepting water in engineering construction, ensuring the safety of the surrounding environment and the safety of engineering construction. In order to ensure the construction safety of structural engineering and the safety of the surrounding environment, it is necessary to rely on foundation pit support to control the soil surface shape. Its main function is to fix and ensure the stability of the pit bottom.
[0003] However, in the prior art, during the foundation pit reinforcement construction operation, support rods and the like are used for support at a low cost, but the overall strength cannot meet the reinforcement requirements, which may easily lead to water flow during subsequent rain scouring, causing the reinforcement to loosen. The overall reinforcement operation has a high economic cost by using multiple sets of reinforcement connecting frame welding and other mechanisms. Overall reinforcement will cause economic deviations in the construction operation and affect subsequent construction operations. Therefore, it is necessary to propose a low-cost and pollution-free foundation pit reinforcement construction device and method. Summary of the invention
[0004] The purpose of the present invention is to provide a low-cost and pollution-free foundation pit reinforcement construction device and method to solve the above-mentioned background technology that in the process of foundation pit reinforcement construction, low-cost support rods and the like are used for support, but the overall strength of the whole cannot meet the reinforcement requirements, which may easily lead to water flow during subsequent rain scouring, causing the reinforcement to loosen. The use of multiple sets of reinforcement connecting frame welding and other mechanisms has a high economic cost for the overall reinforcement operation. Overall reinforcement will cause economic deviations in the construction operation and affect the subsequent construction operations.
[0005] To achieve the above object, the present invention provides the following technical solutions: a low-cost and pollution-free foundation pit reinforcement construction device, comprising a foundation pit, wherein a plurality of groups of PRC pipe piles are installed inside the foundation pit, and a reinforcement adjustment assembly is installed and slidably installed inside the plurality of groups of PRC pipe piles, and slots are symmetrically opened on both sides of the outer wall of the top of the plurality of groups of PRC pipe piles;
[0006] The reinforcement and adjustment component includes a pipe column slide, the bottom end of the pipe column slide is fastened with a processing disk, the bottom end of the processing disk is fastened with a bottom mounting plate by bolts, limit bolt rods are inserted into the left and right side surfaces of the pipe column slide, the limit bolt rods and the slots are butt-jointed, welding fixing grooves are equally divided around the bottom wall surface of the bottom mounting plate, a resisting force frame is welded inside the bottom end of the welding fixing groove, a soil moisture extractor is installed at the bottom axial end of the bottom mounting plate, a guide pump is connected to the side end of the soil moisture extractor, a moisture extraction pipe is connected to the side end of the soil moisture extractor, and the A reinforcing connecting frame is installed at the bottom end of the resisting force frame, and a pumping controller is connected to the bottom end of the reinforcing connecting frame. An annular pipe is installed inside the pumping controller, and the side end of the annular pipe is connected to a pumping solid-liquid separation head. A soil moisture sensor is arranged outside the pumping solid-liquid separation head. A conical fixing rod is connected through the inside of the pumping controller, and the top of the conical fixing rod is tightly connected to the bottom wall surface of the reinforcing connecting frame. A pressurized air cavity is installed on the top of the pipe column slide, and an isolation plate is installed on the top of the pressurized air cavity. The isolation plate is snap-connected to the inner wall surface of the PRC pipe pile.
[0007] Preferably, a plurality of groups of PRC pipe piles are externally installed with reinforcing edge hoops, the outer wall surfaces of the reinforcing edge hoops are fixed by concrete through reinforcing base blocks and the surrounding inner wall surfaces of the foundation pit, bottom guard plates are welded to the inner wall surfaces of the bottom ends of the plurality of groups of PRC pipe piles, arc-shaped welding surfaces are arranged on both side surfaces of the bottom guard plates, a plurality of groups of mixing piles are arranged inside the plurality of groups of PRC pipe piles, a central bearing foundation pile is installed on the central ends of the plurality of groups of mixing piles, and an annular duct is laid on the top surface of the foundation pit.
[0008] Preferably, a force-bearing frame is embedded and inserted inside the bottom guard plate, a grouting groove is opened on the top wall surface of the force-bearing frame, the side end of the force-bearing frame is connected to a pipe rack for installation, a grouting end is provided on the side end of the pipe rack, and a side reinforcing cone rod is fastened to the side end of the pipe rack.
[0009] Preferably, a plurality of groups of the PRC pipe piles, a plurality of groups of mixing piles and a central bearing foundation pile are externally sleeved and installed with a connecting bolt assembly, wherein the connecting bolt assembly comprises a first clamp sleeve, wherein the first clamp sleeve is sleeved on the outside of the PRC pipe pile, wherein the side end surface of the first clamp sleeve is fastened with a connecting anchor rod, and the side end of the connecting anchor rod is fastened with a second clamp sleeve.
[0010] Preferably, the second clamp sleeve is sleeved on the outside of the mixing pile, and a reinforced central sleeve is fastened to the side wall surface of the second clamp sleeve, and the reinforced central sleeve is sleeved on the outside of the central bearing pile.
[0011] Preferably, the outer wall surface of the first hoop sleeve and the inner wall surface of the reinforced side hoop are tightly connected, and the first hoop sleeve, the second hoop sleeve and the reinforced center hoop form a staggered and tightly connected connection between multiple groups of PRC pipe piles, multiple groups of mixing piles and the central bearing foundation pile.
[0012] Preferably, the side end of the annular tube is connected to the surface of the soil moisture extractor through a circulation pipeline, and the side end of the moisture extraction tube passes through the side wall of the bottom mounting plate and is connected to a flexible length tube.
[0013] Preferably, the side end of the flexible length tube is communicated with the annular conduit, and the top end of the annular conduit is provided with an inlet and outlet end.
[0014] Preferably, convex sliding prisms are provided on the inner wall surfaces of the multiple groups of PRC pipe piles, the convex sliding prisms are slidably connected to the pipe column slide, and the gap ends of the multiple groups of PRC pipe piles, multiple groups of mixing piles and central bearing foundation piles are placed in multiple groups of biological growth boxes.
[0015] A low-cost and pollution-free foundation pit reinforcement construction method comprises the following steps:
[0016] S1. First, multiple groups of PRC pipe piles are installed in the prefabricated foundation pit shape, and the surrounding pile structure is formed by driving them into the ground to reinforce the retaining structure of the foundation pit. According to the needs, the reinforcement adjustment components are slid to the bottom along the inside of the multiple groups of PRC pipe piles, and the soil moisture sensor is used to judge. When there is moisture, it is extracted in time to ensure the continuous stability of the overall foundation pit operation;
[0017] S2, then use multiple groups of mixing piles to mix soil and concrete inside the enclosure, and drive the central bearing foundation pile into the center. After the mixing operation of the multiple groups of mixing piles is completed, the multiple groups of PRC pipe piles, the multiple groups of mixing piles and the central bearing foundation pile are connected and fixed in sequence by connecting the bolt assembly;
[0018] S3. Secondly, the surface of the concrete base is initially poured, and then the biological growth boxes are placed in a regional interactive manner according to the placement of the PRC piles, so that the grass inside the biological growth box grows along the formed connection and fixed structure during the subsequent foundation pit reinforcement, and is staggered and connected;
[0019] S4. Then, according to the needs of the construction work, the reinforcement adjustment components are taken out through the pre-connected ropes, and the interior of multiple groups of PRC pipe piles are poured. According to the working hours, the operation is repeated, and after waiting for the molding, the reinforced foundation pit structure is finally formed.
[0020] Compared with the prior art, the present invention has the following beneficial effects:
[0021] 1. In the present invention, the limit bolt rod is pulled out with the cooperation of the reinforcement adjustment component, so that the pipe column slide drives the relevant structure to slide down to the bottom of the PRC pipe pile along the convex sliding prism. Under the action of gravity or the pressure device, the conical fixing rod is plugged into the foundation pit ground, and under the action of the resistance force frame, the impact feedback generated on the soil moisture sensor, the soil moisture extractor and the guide pump is reduced. After that, when it arrives, with the cooperation of the soil moisture sensor, the inside of the foundation pit is continuously detected to avoid rain erosion during long-term construction work, resulting in a large moisture content in the foundation pit soil and insufficient soil bearing capacity. When there is moisture, The soil moisture sensor sends a sensor signal to the soil moisture extractor, which starts the soil moisture extractor and extracts moisture through the pumping solid-liquid separation head. Then, under the action of the guide pump, the extracted moisture is transported to the moisture extraction pipe through the annular pipe under the action of the pumping controller, and with the cooperation of the flexible length pipe, an external pump is used to cooperate with the inlet and outlet ends to extract the moisture into the annular duct for convergence and discharge. The overall operation is adjusted in stages with the construction hours, effectively ensuring the overall stability of the foundation pit, and effectively reducing the problem of water flow and loose reinforcement caused by subsequent rainwater scouring, forming a low-cost, pollution-free and efficient reinforcement operation form.
[0022] 2. In the present invention, with the cooperation of the connecting bolt assembly, after the mixing operation of multiple groups of mixing piles is completed, the first clamp sleeve, the connecting anchor rod, the second clamp sleeve and the reinforced central sleeve are used to fasten and connect by welding, threading and reinforcement processes, so that multiple groups of PRC pipe piles, multiple groups of mixing piles and central bearing piles form an overall stable connection, and then the concrete base surface inside the foundation pit is initially poured, and according to the placement position of the preset biological growth box, the installation groove and the operation groove are reserved, and then according to the placement of the PRC pipe piles, the biological growth box is placed in a regional interactive manner, so that the grass inside the biological growth box grows along the formed connection and fixing structure in the subsequent foundation pit reinforcement, and is staggered and connected, and cooperates with multiple groups of biological growth boxes, so that a biological reinforcement operation is further formed to ensure the stability of the overall foundation pit.
[0023] 3. In the present invention, the bottom guard plate is fitted and fixed on the inner wall surface of multiple groups of PRC pipe piles in turn by using the arc welding surface under the cooperation of the stress frame, the grouting end and the grouting groove. Then the construction personnel drive the pipe rack and the side reinforcement cone rod through the surface of the bottom guard plate by the stress frame, and fix the side reinforcement cone rod and the side surface of the foundation pit through the external hydraulic device. After that, the prepared special slurry is injected through the grouting groove so that it overflows from the grouting end, and the connection surface between the side reinforcement cone rod and the side surface of the foundation pit is reinforced. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1It is a schematic diagram of the main structure of a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0025] Figure 2 This is a schematic diagram of the separation structure of the main body in a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0026] Figure 3 It is a structural schematic diagram of a force-bearing frame, a grouting end and a grouting groove in a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0027] Figure 4 It is a schematic diagram of the installation position structure of the annular guide tube, the stirring pile and the central bearing foundation pile in a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0028] Figure 5 It is a structural schematic diagram of a connecting bolt assembly in a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0029] Figure 6 It is a schematic diagram of the installation position structure of the reinforcement adjustment component in a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0030] Figure 7 It is a structural schematic diagram of a reinforcement adjustment component in a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0031] Figure 8 It is a structural schematic diagram of the separation of the reinforcement adjustment components in a low-cost and pollution-free foundation pit reinforcement construction device of the present invention;
[0032] Fig. 9 The present invention is a schematic diagram of the installation position structure of a pumping controller, an annular pipe, a soil moisture sensor and a pumping solid-liquid separation head in a low-cost and pollution-free foundation pit reinforcement construction device.
[0033] In the figure: 1, PRC pile; 2, bottom guard plate; 3, pipe rack; 4, side reinforcement cone rod; 5, reinforcement side hoop; 6, connection bolt assembly; 61, first clamp sleeve; 62, connection anchor rod; 63, second clamp sleeve; 64, reinforcement center hoop; 7, reinforcement adjustment assembly; 71, pipe column slide; 72, limit bolt rod; 73, bottom mounting plate; 74, resistance force frame; 75, soil moisture extractor; 76, guide pump; 77, moisture extraction pipe; 78, pressurized air cavity; 7 9. Isolation plate; 790. Welding fixing groove; 791. Strengthening connecting frame; 792. Conical fixing rod; 793. Pumping controller; 794. Ring pipe; 795. Soil moisture sensor; 796. Pumping solid-liquid separation head; 8. Ring guide tube; 9. Mixing pile; 10. Center bearing pile; 11. Flexible length pipe; 12. Inlet and outlet ends; 13. Arc welding surface; 14. Force frame; 15. Grouting end; 16. Grouting groove; 17. Slot; 18. Convex sliding prism. DETAILED DESCRIPTION
[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the implementation regulations described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] Reference Figure 1-Figure 9As shown: a low-cost and pollution-free foundation pit reinforcement construction device, including a foundation pit, multiple groups of PRC pipe piles 1 are installed inside the foundation pit, and reinforcement adjustment components 7 are installed and slidably installed inside the multiple groups of PRC pipe piles 1. Slots 17 are symmetrically opened on the two sides of the top outer wall of the multiple groups of PRC pipe piles 1; the reinforcement adjustment component 7 includes a pipe column slide 71, the bottom end of the pipe column slide 71 is fastened with a processing disk, and the bottom end of the processing disk is fastened with a bottom mounting plate 73 by bolts. The left and right side surfaces of the pipe column slide 71 are plugged with limited bolt rods 72, and the limited bolt rods 72 and the slots 17 are docked and inserted. The bottom wall surface of the bottom mounting plate 73 is surrounded by equally divided welding fixing grooves 790, and the bottom end of the welding fixing groove 790 is welded with a resisting force frame 74. The bottom axial end of the bottom mounting plate 73 is installed with a soil moisture extractor 75. The soil moisture extractor The side end of the device 75 is connected to a guide pump 76, and the side end of the soil moisture extractor 75 is connected to a moisture extraction pipe 77. A reinforcing connecting frame 791 is installed at the bottom end of the resisting force frame 74, and a pumping controller 793 is connected to the bottom end of the reinforcing connecting frame 791. An annular tube 794 is installed inside the pumping controller 793, and the side end of the annular tube 794 is connected to a pumping solid-liquid separation head 796. A soil moisture sensor 795 is arranged outside the pumping solid-liquid separation head 796. A conical fixing rod 792 is connected to the inside of the pumping controller 793, and the top of the conical fixing rod 792 is tightly connected to the bottom wall surface of the reinforcing connecting frame 791. A pressurized air chamber 78 is installed on the top of the pipe column slide 71, and an isolation plate 79 is installed on the top of the pressurized air chamber 78. The isolation plate 79 is engaged and connected with the inner wall surface of the PRC pipe pile 1.
[0036] according to Figure 1-Figure 3 As shown, a reinforcing edge hoop 5 is installed outside the multiple groups of PRC pipe piles 1, and the outer wall surface of the reinforcing edge hoop 5 is fixed by concrete through the reinforcement base block and the surrounding inner wall surface of the foundation pit, and a bottom guard plate 2 is welded to the inner wall surface of the bottom end of the multiple groups of PRC pipe piles 1, and arc welding surfaces 13 are arranged on the two side surfaces of the bottom guard plate 2, and multiple groups of mixing piles 9 are arranged inside the multiple groups of PRC pipe piles 1. The central ends of the multiple groups of mixing piles 9 are installed with central bearing foundation piles 10, and an annular guide tube 8 is laid on the top surface of the foundation pit. After the multiple groups of PRC pipe piles 1 are placed, the reinforcing edge hoop 5 is fixed on the outside of the multiple groups of PRC pipe piles 1, and is fixed by concrete through the reinforcement base block and the surrounding inner wall surface of the foundation pit to improve the fixity of the overall operation, and then the construction personnel enter the inside of the foundation pit and fix the bottom guard plate 2 on the inner wall surface of the multiple groups of PRC pipe piles 1 in turn using the arc welding surface 13.
[0037] according to Figure 3As shown, a force-bearing frame 14 is inserted and inserted into the interior of the bottom guard plate 2, a grouting groove 16 is opened on the top wall surface of the force-bearing frame 14, the side end of the force-bearing frame 14 is connected to the pipe rack 3 installed, and a grouting end 15 is provided on the side end of the pipe rack 3, and the side end of the pipe rack 3 is fastened to the side reinforcement cone rod 4. Then the construction personnel drive the pipe rack 3 and the side reinforcement cone rod 4 to penetrate the surface of the bottom guard plate 2 with the force-bearing frame 14, and fix the side reinforcement cone rod 4 and the side surface of the foundation pit through an external hydraulic device, and then inject the prepared special slurry through the grouting groove 16, so that it overflows from the grouting end 15, and reinforces the connection surface between the side reinforcement cone rod 4 and the side surface of the foundation pit.
[0038] according to Figure 1 , Figure 2 , Figure 4 and Figure 5 As shown, a connecting bolt assembly 6 is installed on the outside of multiple groups of PRC pipe piles 1, multiple groups of mixing piles 9 and a central bearing foundation pile 10. The connecting bolt assembly 6 includes a first clamp sleeve 61, which is located on the outside of the PRC pipe pile 1 and is sleeved. The side end surface of the first clamp sleeve 61 is fastened with a connecting anchor rod 62, and the side end of the connecting anchor rod 62 is fastened with a second clamp sleeve 63. The first clamp sleeve 61, the connecting anchor rod 62 and the second clamp sleeve 63 form an interlaced connection structure to connect and fix the PRC pipe pile 1 and the mixing pile 9.
[0039] according to Figure 1 , Figure 2 , Figure 4 and Figure 5 As shown, the second clamp sleeve 63 is located on the outside of the mixing pile 9 and is sleeved thereon. The side wall surface of the second clamp sleeve 63 is fastened with a reinforced central sleeve 64. The reinforced central sleeve 64 is located on the outside of the central bearing pile 10 and is sleeved thereon. The second clamp sleeve 63 and the reinforced central sleeve 64 are fastened and connected by welding, threading and reinforcement processes, so as to facilitate forming a whole and stable connection between multiple groups of PRC pipe piles 1, multiple groups of mixing piles 9 and the central bearing pile 10.
[0040] according to Figure 1 , Figure 2 , Figure 4 and Figure 5 As shown, the outer wall surface of the first clamp sleeve 61 and the inner wall surface of the reinforcement side hoop 5 are fastened together, and the first clamp sleeve 61, the second clamp sleeve 63 and the reinforcement center hoop 64 form a staggered fastened connection between multiple groups of PRC pipe piles 1, multiple groups of mixing piles 9 and the central bearing foundation pile 10, and the prepared biological growth chambers are placed in sequence in the gaps formed by the staggered fastened connection between the multiple groups of PRC pipe piles 1, multiple groups of mixing piles 9 and the central bearing foundation pile 10.
[0041] according to Figure 1 , Figure 2, Figure 4 and Figure 6 As shown, the side end of the annular tube 794 is connected to the surface of the soil moisture extractor 75 through a circulation pipeline, and the side end of the moisture extraction pipe 77 passes through the side wall of the bottom mounting plate 73 and is connected to a flexible length pipe 11. The soil moisture extractor 75 is used to extract moisture from the inside of the foundation pit, and is connected to an external water pump through the moisture extraction pipe 77 and the flexible length pipe 11 to discharge the contained moisture, thereby further strengthening the overall solidity of the foundation pit.
[0042] according to Figure 1 and Figure 2 As shown, the side end of the flexible length tube 11 is connected to the annular conduit 8, and the top of the annular conduit 8 is provided with an inlet and outlet end 12, which is connected to an external water pump via the inlet and outlet end 12, so that the water extracted from the flexible length tube 11 is gathered and discharged through the annular conduit 8.
[0043] according to Figure 6 As shown, convex sliding prisms 18 are provided on the inner wall surfaces of the multiple groups of PRC pipe piles 1, and the convex sliding prisms 18 are slidably connected to the pipe column slide 71. The gap ends of the multiple groups of PRC pipe piles 1, the multiple groups of mixing piles 9 and the central bearing foundation piles 10 are placed in multiple groups of biological growth boxes. The convex sliding prisms 18 can be used to drive the pipe column slide 71 to slide to the bottom of the PRC pipe pile 1 for fixation.
[0044] The wiring diagram of the soil moisture extractor 75, the delivery pump 76, the pumping controller 793, the soil moisture sensor 795 and the pumping solid-liquid separation head 796 in the present invention is common knowledge in the field, and its working principle is a well-known technology. The model is selected according to the actual use. Therefore, the control method and wiring layout of the soil moisture extractor 75, the delivery pump 76, the pumping controller 793, the soil moisture sensor 795 and the pumping solid-liquid separation head 796 will not be explained in detail.
[0045] The method of use and working principle of the device are as follows: first, multiple groups of PRC pipe piles 1 are installed in the shape of a prefabricated foundation pit, and a surrounding pile structure is formed by driving them into the ground to reinforce the surrounding structure of the foundation pit. Then, the reinforcing side hoop 5 is fixed on the outside of the multiple groups of PRC pipe piles 1, and the reinforced base block and the inner wall surface of the surrounding side of the foundation pit are concreted and fixed to improve the fixity of the overall operation. Then, the construction personnel enter the interior of the foundation pit and successively fit and fix the bottom guard plate 2 on the inner wall surface of the multiple groups of PRC pipe piles 1 using the arc welding surface 13. Then, the construction personnel drive the pipe rack 3 and the side reinforcement cone rod 4 to penetrate the surface of the bottom guard plate 2 with the force-bearing frame 14, and fix the side reinforcement cone rod 4 and the surrounding side surface of the foundation pit through an external hydraulic device, and then use the grouting groove 16 to The prepared special slurry is injected to overflow from the grouting end 15, and the connection surface between the side reinforcement cone rod 4 and the surrounding surface of the foundation pit is reinforced. According to the needs, the limit bolt rod 72 is pulled out, so that the pipe column slide 71 drives the relevant structure to slide along the convex sliding prism 18 to the bottom end of the PRC pipe pile 1. Under the action of gravity or the pressure device, the conical fixing rod 792 is plugged into the foundation pit ground, and under the action of the resistance force frame 74, the impact feedback generated on the soil moisture sensor 795, the soil moisture extractor 75 and the guide pump 76 is reduced. After that, when it arrives, with the cooperation of the soil moisture sensor 795, the inside of the foundation pit is continuously detected to avoid rain erosion during long-term construction work, causing the foundation to be The soil in the pit has a large moisture content, which causes insufficient soil bearing capacity. When there is moisture, the soil moisture sensor 795 sends a sensor signal to the soil moisture extractor 75, so that the soil moisture extractor 75 is started and the moisture is extracted through the water pumping solid-liquid separation head 796. Then, under the action of the guide pump 76, the extracted moisture is transported to the moisture extraction pipe 77 through the annular pipe 794 under the action of the pumping controller 793, and with the cooperation of the flexible length pipe 11, the external pumping pump is used in conjunction with the inlet and outlet ends 12 to extract the moisture into the annular conduit 8 for convergence and discharge. The overall operation is staged and adjusted with the construction hours to effectively ensure the overall stability of the foundation pit. Then, multiple groups of mixing piles 9 are used to mix the soil and concrete inside the enclosure. The mixing operation is performed, and the central bearing pile 10 is driven into the center. After the mixing operation of the multiple groups of mixing piles 9 is completed, the first clamp sleeve 61, the connecting anchor rod 62, the second clamp sleeve 63 and the reinforcement center sleeve 64 are used to fasten and connect by welding, threading and reinforcement processes, so that the multiple groups of PRC pipe piles 1, the multiple groups of mixing piles 9 and the central bearing pile 10 form an integral and stable connection. After that, the concrete base surface inside the foundation pit is initially poured, and according to the preset placement position of the biological growth box, the installation groove and the operation groove are reserved. After that, according to the placement of the PRC pipe piles, the biological growth box is placed in a regional interactive manner, so that the grass inside the biological growth box grows along the formed connection and fixing structure in the subsequent foundation pit reinforcement, and is staggered and connected.Afterwards, according to the construction work requirements, the reinforcement adjustment component 7 can be taken out through the pre-connected rope, or the reinforcement adjustment component 7 can be directly left in the PRC pile 1, and multiple groups of PRC piles 1 are poured inside, and the operation is repeated according to the working hours, and after the molding, the reinforced foundation pit structure is finally formed.
[0046] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A low-cost, pollution-free foundation pit reinforcement construction device, characterized in that: It comprises a foundation pit, wherein a plurality of groups of PRC pipe piles (1) are installed inside the foundation pit, a reinforcement adjustment assembly (7) is slidably installed inside the plurality of groups of PRC pipe piles (1), and slots (17) are symmetrically provided on both sides of the outer wall of the top end of the plurality of groups of PRC pipe piles (1); The reinforcement adjustment component (7) comprises a pipe column slide (71), the bottom end of the pipe column slide (71) is fastened with a processing disk, the bottom end of the processing disk is fastened with a bottom mounting plate (73) by bolts, the left and right side surfaces of the pipe column slide (71) are plugged with limit bolts (72), the limit bolts (72) and the slots (17) are butt-jointed, the bottom wall surface of the bottom mounting plate (73) is equally divided with welded fixing grooves (790), the bottom end of the welded fixing grooves (790) is welded with a resisting force frame (74), the bottom axial end of the bottom mounting plate (73) is mounted with a soil moisture extractor (75), the side end of the soil moisture extractor (75) is connected to a guide pump (76), the side end of the soil moisture extractor (75) is connected to a moisture extraction pipe (77), the resisting force frame (74) A reinforcing connecting frame (791) is installed at the bottom end of the reinforcing connecting frame (791), a pumping controller (793) is connected to the bottom end of the reinforcing connecting frame (791), an annular tube (794) is installed inside the pumping controller (793), the side end of the annular tube (794) is connected to a pumping solid-liquid separation head (796), a soil moisture sensor (795) is arranged outside the pumping solid-liquid separation head (796), a conical fixing rod (792) is connected to the inside of the pumping controller (793), the top end of the conical fixing rod (792) is tightly connected to the bottom wall surface of the reinforcing connecting frame (791), a pressurized air chamber (78) is installed at the top of the pipe column slide (71), an isolation plate (79) is installed at the top of the pressurized air chamber (78), and the isolation plate (79) is snap-fitted to the inner wall surface of the PRC pipe pile (1).
2. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 1 is characterized in that: A reinforcement edge hoop (5) is installed outside the plurality of groups of PRC pipe piles (1), and the outer wall surface of the reinforcement edge hoop (5) is concrete-fixed by reinforcing the base block and the inner wall surface of the surrounding side of the foundation pit. A bottom guard plate (2) is welded to the inner wall surface of the bottom end of the plurality of groups of PRC pipe piles (1), and arc-shaped welding surfaces (13) are arranged on both side surfaces of the bottom guard plate (2). A plurality of groups of stirring piles (9) are arranged inside the plurality of groups of PRC pipe piles (1), and a central bearing foundation pile (10) is installed at the central end of the plurality of groups of stirring piles (9). An annular guide tube (8) is laid on the top surface of the foundation pit.
3. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 2 is characterized in that: A force-bearing frame (14) is inserted and engaged inside the bottom guard plate (2), a grouting groove (16) is provided on the top wall surface of the force-bearing frame (14), the side end of the force-bearing frame (14) is connected to a pipe rack (3) for installation, a grouting end (15) is provided on the side end of the pipe rack (3), and a side reinforcing cone rod (4) is fastened to the side end of the pipe rack (3).
4. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 3 is characterized in that: A connecting bolt assembly (6) is installed on the outside of a plurality of groups of PRC pipe piles (1), a plurality of groups of mixing piles (9) and a central bearing foundation pile (10). The connecting bolt assembly (6) comprises a first clamping sleeve (61). The first clamping sleeve (61) is located outside the PRC pipe pile (1) and is sleeved thereon. A connecting anchor rod (62) is fastened to the side end surface of the first clamping sleeve (61). A second clamping sleeve (63) is fastened to the side end of the connecting anchor rod (62).
5. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 4 is characterized in that: The second clamp sleeve (63) is sleeved on the outside of the mixing pile (9), and the side wall surface of the second clamp sleeve (63) is fastened with a reinforcing central sleeve (64), and the reinforcing central sleeve (64) is sleeved on the outside of the central bearing pile (10).
6. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 5 is characterized in that: The outer wall surface of the first clamp sleeve (61) and the inner wall surface of the reinforcing side hoop (5) are tightly connected, and the first clamp sleeve (61), the second clamp sleeve (63) and the reinforced central sleeve hoop (64) form a staggered and tightly connected connection between multiple groups of PRC pipe piles (1), multiple groups of mixing piles (9) and the central bearing foundation pile (10).
7. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 6 is characterized in that: The side end of the annular tube (794) is connected to the surface of the soil moisture extractor (75) through a circulation pipeline, and the side end of the moisture extraction tube (77) passes through the side wall of the bottom mounting plate (73) and is connected to a flexible length tube (11).
8. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 7 is characterized in that: The side end of the flexible length tube (11) is in communication with the annular conduit (8), and the top end of the annular conduit (8) is provided with an inlet and outlet end (12).
9. The low-cost and pollution-free foundation pit reinforcement construction device according to claim 8 is characterized in that: Convex and slippery prisms (18) are arranged on the inner wall surfaces of the plurality of groups of PRC pipe piles (1), the convex and slippery prisms (18) are slidably connected to the pipe column slide frame (71), and the gap ends of the plurality of groups of PRC pipe piles (1), the plurality of groups of mixing piles (9) and the central bearing foundation pile (10) are placed in the plurality of groups of biological growth boxes.
10. A low-cost and pollution-free foundation pit reinforcement construction method, characterized in that: The low-cost and pollution-free foundation pit reinforcement construction device according to claim 9 is used, comprising the following steps: S1. First, multiple groups of PRC pipe piles (1) are installed in a prefabricated foundation pit shape and driven into the ground to form a surrounding pile structure for reinforcing the surrounding structure of the foundation pit. According to the needs, the reinforcement adjustment component (7) is slid along the inside of the multiple groups of PRC pipe piles (1) to the bottom, and the soil moisture sensor (795) is used to determine if there is moisture. When moisture is present, it is extracted in time to ensure the continuous stability of the overall foundation pit operation; S2, then use multiple groups of mixing piles (9) to mix soil and concrete in the enclosed interior, and drive the central bearing foundation pile (10) into the center. After the mixing operation of the multiple groups of mixing piles (9) is completed, the multiple groups of PRC pipe piles (1), the multiple groups of mixing piles (9) and the central bearing foundation pile (10) are connected and fixed in sequence by connecting the bolt assembly (6); S3. Secondly, the surface of the concrete base is initially poured, and then the biological growth boxes are placed in a regional interactive manner according to the placement of the PRC piles, so that the grass inside the biological growth box grows along the formed connection and fixed structure during the subsequent foundation pit reinforcement, and is staggered and connected; S4. After that, according to the construction work requirements, the reinforcement adjustment component (7) is taken out through the pre-connected rope, and the interior of multiple groups of PRC pipe piles (1) are poured, and the operation is repeated according to the working hours, and after waiting for the molding, a reinforced foundation pit structure is finally formed.