An integrated construction method for riprap concrete
By adopting an integrated pouring method in riprap concrete construction, different grades of concrete are poured simultaneously, which solves the problems of increased material costs and reduced efficiency caused by zonal pouring, and achieves cost savings and improved construction efficiency.
Patent Information
- Application Number
- CN202410208387.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-26
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2044-02-26
AI Technical Summary
The current method of sectional pouring in riprap concrete construction increases the amount of formwork and tie rods used, resulting in high material costs and low construction efficiency.
An integrated pouring method is adopted, with a transition zone set up between the functional area and the riprap area. Two different grades of concrete are poured simultaneously, allowing them to come into direct contact in the transition zone. The pouring speed and volume are controlled to prevent concrete from flowing into areas where it should not.
The use of formwork and tie rods was reduced, material costs were lowered, construction efficiency was improved, and the concrete interface was ensured to be dense, thus enhancing overall performance.
Smart Images

Figure CN118087527B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of water conservancy and hydropower engineering, and in particular to an integrated construction method for riprap concrete. Background Technology
[0002] Rockfill concrete is a new type of large-volume concrete technology. It refers to the use of high-performance self-compacting concrete (HSCC) to fill the voids in the rockfill body, forming a complete, dense concrete that meets design requirements. Rockfill concrete is generally divided into ordinary rockfill concrete and riprap-type rockfill concrete. Ordinary rockfill concrete refers to the technique of first piling rocks and then pouring high-performance self-compacting concrete, which is mainly suitable for gravity dams, arch dams, concrete cofferdams, and embankments. Riprap-type rockfill concrete refers to the technique of first pouring anti-segregation self-compacting concrete and then riprap, which is mainly suitable for caisson backfilling, anti-slide pile backfilling, and high sidewalls.
[0003] When pouring rockfill concrete dams, a zoned pouring method is adopted. First, formwork is installed between the functional zone and the rockfill zone. Then, tie rods are placed on the formwork, and the functional zone concrete is poured. Once the concrete strength is sufficient to prevent damage during formwork removal, the formwork is removed, and then lower-grade concrete is poured. This zoned pouring method not only increases the steps of formwork installation and removal, and tie rod placement at the interface between the two types of concrete, but also increases the amount of formwork and tie rod materials used, increasing material costs and reducing construction efficiency. Summary of the Invention
[0004] To address the technical problems existing in the prior art, this application proposes an integrated construction method for riprap concrete, which effectively saves costs and improves construction efficiency by adopting an integrated pouring method.
[0005] An integrated construction method for riprap concrete includes: erecting a formwork on the surface to be poured to form a slab; the slab includes a functional area and a riprap area, wherein the functional area and / or the riprap area is filled with riprap of a predetermined height; before concrete pouring, determining a pouring plan, the pouring plan including multiple pouring locations and pouring sequence, as well as the pouring speed and pouring volume at each pouring location; the pouring steps include: Step 1: pouring a first concrete A in the functional area or transition area, and pouring a second concrete B in the riprap area or transition area adjacent to the transition area, such that the first concrete A and the second concrete B are in direct contact in the transition area, wherein the transition area is located between the functional area and the riprap area, and the first concrete A is used to pour the riprap concrete. The functional area and / or part of the transition area, the second concrete B is used to pour the riprap area and / or part of the transition area; Step 2: Control the pouring speed of the first concrete A and the second concrete B respectively, so that the contact interface of the first concrete A and the second concrete B rises synchronously, and the second concrete B does not flow into the functional area. When the pouring height of the first concrete A at the pouring point and the pouring height of the second concrete B at the pouring point reach the preset height respectively, stop pouring; Step 3: Move the pouring point of the first concrete A and the pouring point of the second concrete B along the preset direction by a preset distance, and pour concrete according to the method of Step 2; Step 4: Repeat Step 3 until the first concrete A in the functional area is poured.
[0006] The integrated construction method for riprap concrete described above uses calculation to determine the pouring scheme. The determination of the pouring scheme includes: simplifying the integrated pouring area into a two-dimensional model, determining the pouring location and pouring sequence of the concrete, and then determining the pouring speed and pouring volume of the first concrete A and the second concrete B at each pouring location. The pouring point of the first concrete A is located in the functional area or transition area, and the pouring point of the second concrete B is located in the riprap area.
[0007] In the integrated construction method of riprap concrete described above, in step 2, when Δh1<h≤(n-1)Δh1, the pouring speed v1 of the first concrete A and the pouring speed v2 of the second concrete B need to meet the following formula relationship:
[0008]
[0009] Wherein, v1 is the pouring speed of the first concrete A, v2 is the pouring speed of the second concrete B, β is the volume ratio of concrete in the riprap concrete of the functional area and / or transition area, α is the volume ratio of concrete in the riprap concrete of the riprap area, h is the pouring height of the first concrete A at the pouring point, n is the quotient of the surface height H divided by Δh1, Δh1 is the initial single-layer pouring height of the concrete at the pouring point, W is the sum of the lengths of the functional area and the transition area, W=W1+W2, where W1 is the width of the area completely filled by the first concrete A, W2 is the width of the riprap concrete area filled by the first concrete A, and i is the flow slope ratio of the second concrete B.
[0010] In the integrated construction method of riprap concrete described above, in step 2, when (n-1)Δh1<h≤H-Δh3, the pouring speed v1 of the first concrete A and the pouring speed v2 of the second concrete B need to meet the following formula relationship:
[0011]
[0012] Wherein, v1 is the pouring speed of the first concrete A, v2 is the pouring speed of the second concrete B, β is the volume ratio of concrete in the riprap concrete of the functional area and / or transition area, α is the volume ratio of concrete in the riprap concrete of the riprap area, h is the pouring height of the first concrete A at the pouring point, n is the quotient of the surface height H divided by Δh1, Δh1 is the initial single-layer pouring height of the concrete at the pouring point, Δh2 is the single-layer pouring height of the second concrete B at the pouring point when the pouring height reaches the preset height, Δh3 is the single-layer pouring height of the first concrete A at the pouring point when the pouring height reaches the preset height, W is the sum of the lengths of the functional area and the transition area, W = W1 + W2, where W1 is the width of the area completely filled by the first concrete A, W2 is the width of the riprap concrete area filled by the first concrete A, and i is the flow slope ratio of the second concrete B.
[0013] The integrated construction method for riprap concrete described above uses calculation to determine the pouring scheme. The determination of the pouring scheme includes: determining the pouring position and pouring sequence of concrete by simulating a three-dimensional pouring model of the integrated pouring area, and then determining the pouring speed and pouring volume of the first concrete A and the second concrete B at each pouring position. The pouring points of the first concrete A and the second concrete B are both within the transition zone.
[0014] The integrated construction method for riprap concrete as described above is characterized in that, in step 2, the pouring volume of the first concrete A is... The second concrete B pouring volume is: Among them, V A V represents the volume of the first concrete pour, A. BLet H be the pouring volume of the second concrete B, H be the height of the pouring surface, l be the distance between the pouring point of the second concrete B and the formwork away from the functional area along the transverse river direction, and M be the distance between the pouring point of the first concrete A and the formwork close to the functional area along the transverse river direction.
[0015] In the riprap concrete construction method described above, the ratio of the pouring volume of the second concrete B to the pouring volume of the first concrete A is: That is, the ratio of the average pouring speed of the second concrete B to the average pouring speed of the first concrete A is .
[0016] In the integrated construction method of riprap concrete described above, in step 3, the pouring volume of the first concrete A is: The pouring volume of the second concrete B is: Among them, V' A V′ represents the pouring volume of the first concrete A. B H is the pouring volume of the second concrete B, l is the height of the slab surface, l is the distance between the pouring point of the second concrete B and the formwork on the side away from the functional area along the transverse direction, M is the distance between the pouring point of the first concrete A and the formwork on the side near the functional area along the transverse direction, N is the preset distance, and n is the flow slope ratio of the first concrete A and the flow slope ratio of the second concrete B on the riprap.
[0017] In the integrated construction method of riprap concrete described above, the ratio of the pouring volume of the second concrete B to the pouring volume of the first concrete A is: That is, the ratio of the average pouring speed of the second concrete B to the average pouring speed of the first concrete A is .
[0018] In the integrated construction method of riprap concrete described above, the width of the functional zone is 30mm-5000mm, and the width of the transition zone is 200-5000mm.
[0019] In the integrated construction method of riprap concrete as described above, the preset direction is the direction across the river and / or the direction along the river, the pouring method includes any one of unidirectional, opposite, and back-to-back directions, and the preset distance is 2m-6m.
[0020] In the integrated construction method of riprap concrete as described above, the first concrete A is poured at the center line of the transition zone along the transverse river direction, the second concrete B is poured at the side of the first concrete A pouring point near the riprap zone and in the same transverse river direction, and the distance between the first concrete A pouring point and the second concrete B pouring point is not less than 100mm.
[0021] The integrated construction method of riprap concrete as described above includes the following functional zones: seepage prevention zone, frost prevention zone, erosion and abrasion resistance zone, as well as corridors and orifices.
[0022] This application employs an integrated casting method, simultaneously casting the first concrete A and the second concrete B, and controlling the convergence of the two types of concrete in the transition zone. This prevents excessive flow of concrete from the more expensive functional areas into the riprap area, while simultaneously ensuring a denser bond between the functional area and the riprap area concrete, resulting in better overall performance. Furthermore, it reduces the need for formwork and tie rods between the functional area and the riprap area, optimizing the construction process, reducing manual labor, and improving construction efficiency. Attached Figure Description
[0023] The preferred embodiments of this application will now be described in further detail with reference to the accompanying drawings, wherein:
[0024] Figure 1 This is a schematic flowchart of an integrated riprap concrete construction method according to an embodiment of this application;
[0025] Figure 2A This is a schematic diagram of the pouring direction structure of the concrete pouring surface in the initial position according to an embodiment of this application;
[0026] Figure 2B This is a schematic diagram of the shape structure of the first concrete A being poured at the initial position according to an embodiment of this application;
[0027] Figure 2C This is a schematic diagram of the shape structure of the second concrete B poured at the initial position according to an embodiment of this application;
[0028] Figure 3 This is a schematic diagram of the pouring direction structure of the concrete pouring surface after moving a preset distance according to an embodiment of this application;
[0029] Figure 4 This is a schematic diagram of the cross-sectional structure of a concrete pouring slab according to an embodiment of this application;
[0030] Figure 5A This is a structural schematic diagram of a unidirectional casting method in an integrated casting area according to an embodiment of this application;
[0031] Figure 5B This is a structural schematic diagram of an opposing pouring method in an integrated pouring area according to an embodiment of this application;
[0032] Figure 5C This is a structural schematic diagram of a back-to-back casting method in an integrated casting area according to an embodiment of this application;
[0033] Figure 6AThis is a schematic diagram of the pouring direction structure of an "S"-shaped concrete pouring slab in a rockfill area according to an embodiment of this application;
[0034] Figure 6B This is a schematic diagram of the pouring direction of the concrete pouring surface in an "N"-shaped concrete pouring area according to an embodiment of this application. Detailed Implementation
[0035] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0036] In the following detailed description, reference can be made to the accompanying drawings, which form part of this application and illustrate specific embodiments of the present application. In the drawings, similar reference numerals describe substantially similar components in different figures. Specific embodiments of the present application are described in sufficient detail below to enable those skilled in the art to implement the technical solutions of the present application. It should be understood that other embodiments may also be utilized, or structural, logical, or electrical changes may be made to the embodiments of the present application.
[0037] To facilitate understanding of the integrated riprap concrete construction method proposed in this application, the following is a brief description of the concepts and technical terms that may be involved in the embodiments of this application.
[0038] In the construction of rockfill concrete dams, the surface of the concrete work surface is a general term for the concrete work surface during the dam pouring process. Construction of the dam can continue on the surface of the concrete work surface. Specifically, the surface of the concrete work surface generally refers to the upper surface of the already poured layer. The concrete work surface of the entire dam can be called the surface of the concrete work surface.
[0039] A dam surface is a construction area formed after templates are set up on the dam site. If the dam body is large, it needs to be constructed in sections. Each construction area generally needs to have templates set up on the upstream and / or downstream sides. Therefore, each section of construction area is called a dam surface. Dams not only need to be constructed in sections above and below, but also in sections within the same section.
[0040] The types of formwork used in dams include: cantilever formwork, tilting formwork, self-elevating formwork, and precast formwork. The advantage of precast formwork is that it can be integrated into the dam structure, reducing the need for formwork removal.
[0041] Figure 1This is a schematic flowchart illustrating an integrated construction method for riprap concrete according to an embodiment of this application. Figure 1 As shown, the integrated construction method for riprap concrete includes:
[0042] Preparation step 1: Build a template on the surface of the silo to be poured so that it forms a silo with the silo surface;
[0043] Preparation step 2: The storage area includes a functional area and a riprap area, and the functional area and / or riprap area is filled with riprap of a preset height;
[0044] Preparation step 3: Before pouring concrete, determine the pouring plan, which includes multiple pouring locations and pouring sequence, as well as the pouring speed and pouring volume at each pouring location;
[0045] The pouring process includes:
[0046] Step 1: Pour a first concrete A in the functional area or transition area, and pour a second concrete B in the riprap area or transition area adjacent to the transition area, so that the first concrete A and the second concrete B are in direct contact in the transition area, wherein the transition area is located between the functional area and the riprap area, the first concrete A is used to pour the functional area and / or part of the transition area, and the second concrete B is used to pour the riprap area and / or part of the transition area;
[0047] Step 2: Control the pouring speed of the first concrete A and the second concrete B respectively, so that the contact interface of the first concrete A and the second concrete B rises synchronously, and the second concrete B does not flow into the functional area. When the pouring height of the first concrete A at the pouring point and the pouring height of the second concrete B at the pouring point reach the preset height respectively, stop pouring.
[0048] Step 3: Move the first concrete pouring point A and the second concrete pouring point B along the preset direction by a preset distance, and pour concrete in the manner of Step 2.
[0049] Step 4: Repeat step 3 until the first concrete A in the functional area is poured;
[0050] During the concrete pouring process, the contact between the first concrete A and the second concrete B in the transition zone is monitored to ensure that the concrete from the riprap area does not enter the functional area.
[0051] Generally, functional areas are not filled with riprap, while riprap areas are. However, depending on the actual construction situation, functional areas may also be filled with riprap, and some areas of the riprap area may not be filled with riprap; no restrictions are placed here. A transition zone is set between the functional areas and the riprap areas. The transition zone can be part of the riprap area. The transition zone should prioritize riprap construction, but may not be filled with riprap.
[0052] This application employs an integrated construction method, which involves setting up a transition zone between the functional area and the riprap area, and simultaneously pouring two different grades of concrete. This allows the concrete from the riprap area to come into contact with the concrete from the functional area in the transition zone. The two types of concrete rise synchronously at the contact interface, and the second concrete (B) does not flow into the functional area, achieving integrated pouring. There is no need to set up formwork between the functional area and the riprap area, improving work efficiency. Furthermore, the direct contact between the concrete from the functional area and the riprap area in the transition zone eliminates the need for tie rods, reducing construction costs.
[0053] In some embodiments of this application, optionally, during the design of the pouring scheme, the location of the pouring points of the first concrete A and the second concrete B, as well as the relationship between the pouring speed and the pouring quantity, are determined by combining relevant engineering experience or conducting on-site tests. Using the above method to determine the pouring parameters is more accurate and meets the actual working conditions.
[0054] In calculating the concrete pouring volume and pouring speed, the pouring volume refers to the volume required to ensure the concrete in the functional area and the concrete in the riprap area meet at the transition zone when the first concrete (A) and the second concrete (B) are poured simultaneously. Calculating the concrete pouring volume requires determining the pouring point and pouring layer height. These factors ensure direct contact between the concrete in the functional area and the concrete in the riprap area at the transition zone. This avoids the problem of a large amount of functional area concrete flowing into the riprap area if formwork is not erected when pouring concrete in the functional area alone.
[0055] When calculating the concrete pouring volume and pouring speed, it is advisable to consider obtaining data through actual pouring tests. Different working conditions (variables include layer pouring height and pouring point location) can be designed, and the pouring points, layer heights, and pouring speeds can be determined based on the actual pouring volume and the intersection situation in the transition zone. Alternatively, a conservative estimate of the concrete volume in the pouring area can be made to determine the concrete pouring speed. Conservative estimation methods include estimating the pouring point location and concrete volume using a simplified two-dimensional model and estimating the concrete volume using a three-dimensional model simulating the concrete.
[0056] In some embodiments of this application, optionally, a calculation method is used to determine the pouring scheme. Determining the pouring scheme includes: simplifying the integrated pouring area into a two-dimensional model, determining the pouring location and sequence of the concrete, and then determining the pouring speed and volume of the first concrete A and the second concrete B at each pouring location. The pouring point of the first concrete A is located within the functional area or transition zone, and the pouring point of the second concrete B is located within the riprap zone. This method uses the coverage area of the poured concrete to calculate the pouring speed of the first concrete A and the second concrete B, simplifying the calculation process.
[0057] In some embodiments of this application, optionally, a calculation method is used to determine the pouring scheme. Determining the pouring scheme includes: determining the pouring location and sequence of concrete by simulating a three-dimensional pouring model of the integrated pouring area, and then determining the pouring speed and volume of the first concrete A and the second concrete B at each pouring location. The pouring points of the first concrete A and the second concrete B are both within the transition zone. Controlling the pouring speed of the first concrete A and the second concrete B ensures that the contact interface between the first concrete A and the second concrete B rises synchronously, preventing the second concrete B from flowing into the functional area.
[0058] Optionally, in some embodiments of this application, when the pouring volume of the first concrete A and the second concrete B per unit time is the same, the ratio of the pouring speed of the second concrete B to that of the first concrete A is... The ratio of the pouring volume of the second concrete B and the first concrete A Same The first concrete, A, costs more than the second concrete, B. If the pouring speed of the first concrete, A, is faster than that of the second concrete, B, the first concrete, A, will flow into the riprap area, increasing construction costs. Therefore, controlling the pouring speed of the first concrete, A, and B, to minimize the amount of the first concrete, A, flowing into the riprap area, can save on construction costs.
[0059] Optionally, in some embodiments of this application, in step 2, the pouring volume of the first concrete A is: The second concrete B pouring volume is:
[0060] Among them, V A V represents the volume of the first concrete pour, A. B Let H be the pouring volume of the second concrete B, l be the height of the formwork, l be the distance between the pouring point of the second concrete B and the formwork on the side away from the functional area in the transverse direction, and M be the distance between the pouring point of the first concrete A and the formwork on the side closer to the functional area in the transverse direction. Using the above formula, the pouring volume of the first concrete A and the second concrete B at the initial position can be roughly calculated. Quantifying the pouring volume of both is beneficial for controlling their pouring speed.
[0061] Optionally, in some embodiments of this application, the ratio of the amount of the second concrete B poured to the amount of the first concrete A poured is: That is, the ratio of the pouring speed of the second concrete B to the pouring speed of the first concrete A is . Using the above formula, the pouring speed of the second concrete B can be controlled to match the pouring speed of the first concrete A, so that the contact interface between the first concrete A and the second concrete B at the initial position rises synchronously, and the second concrete B does not flow into the functional area.
[0062] Optionally, in some embodiments of this application, in step 3, the pouring volume of the first concrete A is:
[0063] The pouring volume of the second concrete B is:
[0064] Among them, V′ A V' is the pouring volume of the first concrete A. B Let H be the pouring volume of the second concrete B, l be the height of the pouring surface, l be the distance between the pouring point of the second concrete B and the formwork on the side away from the functional area in the transverse direction, M be the distance between the pouring point of the first concrete A and the formwork on the side near the functional area in the transverse direction, N be the preset distance, and n be the flow slope ratio of the first concrete A and the flow slope ratio of the second concrete B on the riprap. Using the above formula, the pouring volume of the first concrete A and the second concrete B at non-initial positions can be roughly calculated. Quantifying the pouring volume of both helps to control their pouring speed.
[0065] Optionally, in some embodiments of this application, the ratio of the amount of the second concrete B poured to the amount of the first concrete A poured is: That is, the ratio of the pouring speed of the second concrete B to the pouring speed of the first concrete A is . Using the above formula, the pouring speed of the second concrete B can be controlled to match the pouring speed of the first concrete A, so that the contact interface between the first concrete A and the second concrete B at non-initial positions rises synchronously, and the second concrete B does not flow into the functional area.
[0066] In some embodiments of this application, optionally, the width of the functional zone is 30mm-5000mm, and the width of the transition zone is 200mm-5000mm. The widths of the functional zone and the transition zone can be related to factors such as the width of the dam body and the river channel, as well as the performance of the concrete, and can be determined according to the actual construction situation. If the width of the transition zone is too narrow, the second concrete B is prone to flow into the functional zone, weakening the seepage prevention function of the functional zone and increasing the safety hazards of the dam body.
[0067] In some embodiments of this application, optionally, the first concrete A pouring point is located on the centerline of the transition zone along the transverse river direction, and the second concrete B pouring point is located on the side of the first concrete A pouring point closer to the rubble pile area and in the same downstream direction, with a distance of not less than 100mm between the first concrete A pouring point and the second concrete B pouring point. Spacing the first concrete A pouring point and the second concrete B pouring point a certain distance prevents the first concrete A and the second concrete B from mixing at the pouring point. Furthermore, setting the second concrete B pouring point on the side of the first concrete A pouring point closer to the rubble pile area and in the same downstream direction prevents the first concrete A from flowing into the rubble pile area, thus saving construction costs.
[0068] In some embodiments of this application, optionally, the preset direction is the direction across the river and / or the direction along the river, the pouring method includes any one of unidirectional, opposite, and back-to-back directions, and the preset distance is 2m-6m. Setting a reasonable preset distance can avoid the problem of large areas not being poured. The preset distance is related to the flow slope ratio of the concrete and the pouring height.
[0069] Figure 2A This is a schematic diagram of the pouring direction structure of a concrete pouring site at an initial position, according to an embodiment of this application. Figure 2A As shown, a first template 201, a second template 202, a third template 203, and a fourth template 204 are installed around the warehouse surface. The first template 201 and the third template 203 are templates in the direction along the river (D), while the second template 202 and the fourth template 204 are templates in the direction across the river (P). The direction along the river (D) is parallel to the river channel, and the direction across the river (P) is perpendicular to the river channel.
[0070] refer to Figure 2A First formwork 201, second formwork 202, third formwork 203, and fourth formwork 204 are erected on the surface to be poured, forming a storage area with the enclosed surface. The storage area is divided into a rockfill zone 205, a transition zone 206, and a functional zone 207. The transition zone 206 is located between the rockfill zone 205 and the functional zone 207, directly connecting the rockfill zone 205 to the functional zone 207 without intermediate formwork. The transition zone 206 is actually a part of the rockfill zone 205.
[0071] In one embodiment, stones are piled up in the riprap zone 205 and the transition zone 206, while no stones are piled up in the functional zone 207; in another embodiment, stones may also be piled up in the functional zone 207. The main difference between the functional zone 207 and the riprap zone 205 is that a first concrete A is poured in the functional zone 207, while a second concrete B is poured in the riprap zone 206. The first concrete A and the second concrete B have different grades and serve different purposes. The first concrete A and the second concrete B are poured simultaneously in the transition zone 206, so that the rising speed of the first concrete A at the interface between part of the transition zone 206 and the functional zone 207 is synchronized with the rising speed of the second concrete B at the contact interface between part of the transition zone 206 and the riprap zone 205. The second concrete B does not flow into the functional zone, and the first concrete A and the second concrete B are in direct contact in the transition zone 206.
[0072] According to one embodiment of this application, the width of functional zone 207 is 30mm-5000mm, and the width of transition zone 206 is 200-5000mm. Functional zone 207 can be a seepage prevention zone, a frost prevention zone, an erosion control zone, and areas around corridors and orifices, etc. Concrete with different functional properties is poured in functional zones to form different layers. Corridors are set in the dam to meet the needs of grouting, drainage, monitoring, traffic, and operation and maintenance. Orifices are classified into surface orifices, intermediate orifices, and bottom orifices according to their different installation heights and functions. Surface orifices: generally located in the upper part of the dam body, used for flood discharge; intermediate orifices: generally located in the middle of the dam body, also used for flood discharge; bottom orifices: generally located at the bottom of the dam body, used for flood discharge, sediment flushing, and emptying the reservoir.
[0073] When functional zone 207 is a seepage prevention zone, one side of the seepage prevention zone is the water-facing side of the dam body. Due to long-term contact with water, it needs to have seepage prevention capabilities. Therefore, the cost of concrete poured in the seepage prevention zone is higher than that of concrete in the rockfill zone 205. The first concrete A and the second concrete B have different gradations, and the width requirements for the transition zone 206 also differ. The transition zone 206 should not exceed 5000mm, and to prevent concrete from the rockfill zone 205 from flowing into functional zone 207 during construction, the width of the transition zone 206 should not be less than 200mm.
[0074] To determine the pouring volume and pouring speed of the first concrete A and the second concrete B, ensuring that they rise synchronously at their meeting point in the transition zone and that the second concrete B does not flow into the functional zone, two calculation methods are used. Method one involves calculating the volume of each concrete pouring volume separately; method two involves calculating the cross-sectional area of each concrete pouring volume. Both methods can roughly calculate the ratio of their pouring speeds. In method one, the pouring locations are both within the transition zone; in method two, the pouring location is either within the functional zone or the transition zone, and the pouring location is within the riprap zone. The specific calculation processes for methods one and two are as follows:
[0075] Method 1:
[0076] refer to Figure 2A Within the initial position S of the transition zone 206, a first concrete pouring point A 208 and a second concrete pouring point B 209 are simultaneously set. The initial position S is located 100mm-3000mm from the formwork on the side closer to the river-direction D. (Reference) Figure 2A The initial position S is 100mm-3000mm away from the first formwork 201 in the Yokogawa direction. This ensures that the concrete near the first formwork 201 is poured densely and avoids the problem of grout leakage caused by impact on the first formwork 201 during pouring.
[0077] In the initial position, the first concrete A pouring point 208 is located on the center line of the transition zone 206 along the transverse river direction P. The second concrete B pouring point 209 is located on the side of the first concrete A pouring point 208 closer to the rockfill area and on the same transverse river direction D. The distance between the first concrete A pouring point 208 and the second concrete B pouring point 209 is not less than 100mm. The certain distance between the first concrete A pouring point 208 and the second concrete B pouring point 209 can prevent the first concrete A and the second concrete B from mixing together during pouring, ensuring that they can diffuse in the rockfill area 205 and the functional area 207 respectively.
[0078] According to one embodiment of this application, the ratio of the pouring volume of the second concrete B to that of the first concrete A is: The ratio of the pouring speed of the second concrete B to that of the first concrete A is: When the first concrete A and the second concrete B are poured at the same time Therefore, if the pouring volume of the first concrete A and the second concrete B at the initial position S can be calculated, the pouring speed of the two at the initial position can be calculated, so that the interface between the first concrete A and the second concrete B rises to the same height.
[0079] Figure 2B This is a schematic diagram of the shape structure of the first concrete A being poured at an initial position according to an embodiment of this application. (Reference) Figure 2B and combined Figure 2A As shown, when the first concrete A is poured at pouring point 208, the first concrete A diffuses in the directions of the fourth formwork 204 and the third formwork 203 respectively. The diffusion shape of the first concrete A is approximately a triangular prism, which can be calculated using the volume formula of a triangular prism.
[0080] Figure 2C This is a schematic diagram of the shape structure of the second concrete B poured at the initial position according to an embodiment of this application. The second concrete B diffuses towards the second formwork 202 and the third formwork 203, and the diffusion shape is similar to a quarter cone. The volume of a cone can be calculated using the formula for the volume of a cone. Therefore, the pouring volume of the first concrete A and the pouring volume of the second concrete B are respectively:
[0081] The pouring volume of the first concrete A is:
[0082] The second concrete B pouring volume is:
[0083] In the above formula and Figure 2B and Figure 2C In the middle, V A V represents the volume of the first concrete pour, A. B Let H be the pouring volume of the second concrete B, H be the height of the pouring surface, l be the distance between the pouring point of the second concrete B and the formwork on the side away from the functional area in the direction of the river, and M be the distance between the pouring point of the first concrete A and the formwork on the side closer to the functional area in the direction of the river.
[0084] From equations (1) and (2), it can be seen that the ratio of the amount of the second concrete B poured to the amount of the first concrete A poured is _____.
[0085] That is, the ratio of the pouring speed of the second concrete B to the pouring speed of the first concrete A is .
[0086] Among them, S A S represents the pouring speed of the first concrete A; B The pouring speed for the second concrete B.
[0087] For example, the dam body has a width of 40m across the river and a width of 20m along the river, a surface height H of 2m, a transition zone 206 width of 1m, a first concrete A grade of C30 with a flow slope ratio of 1:10, a second concrete B grade of C25 with a flow slope ratio of 1:20, a flow slope ratio of 1:10 in the rockfill area, a functional width of 1m, a pouring point 208 of the first concrete A and a pouring point 209 of the second concrete B with a distance of 0.2m, then the distance l from the pouring point 209 of the second concrete B to the second formwork 202 is 18.3m, and the distance M from the pouring point 208 of the first concrete A to the fourth formwork 204 is 1.5m.
[0088] As can be seen from the above, the ratio of the pouring speed of the second concrete B to the pouring speed of the first concrete A is [value missing]. Therefore, the ratio of the pouring speed of the second concrete B to that of the first concrete A is approximately 3.19. By calculating and quantifying the pouring speeds of the second concrete B and the first concrete A, the interface rise rate between the first concrete A and the second concrete B can be controlled more accurately, ensuring construction quality. Pouring is stopped when the pouring height of the first concrete A and the second concrete B at the meeting point in the transition zone is the same as the height of the formwork surface.
[0089] Figure 3 This is a schematic diagram of the pouring direction of concrete in a pouring slab after moving a preset distance according to an embodiment of this application. Figure 3 and combined Figure 2A As shown, the preset distance is to move the first concrete A pouring point 208 and the second concrete B pouring point 209 along the junction of the first concrete A and the second concrete B by a preset distance, and pour the first concrete A and the second concrete B in the manner described above.
[0090] After moving the preset distance, the pouring volume of the first concrete A is:
[0091] After moving the preset distance, the pouring volume of the second concrete B is: Among them, V′ A V' is the pouring volume of the first concrete A. B Let H be the pouring volume of the second concrete B, l be the height of the pouring surface, l be the distance between the pouring point of the second concrete B and the formwork on the side away from the functional area in the direction of the river, M be the distance between the pouring point of the first concrete A and the formwork on the side closer to the functional area in the direction of the river, N be the preset distance, and n be the flow slope ratio of the first concrete A and the flow slope ratio of the second concrete B on the riprap. From equations (5) and (6), it can be seen that after moving the preset distance, the ratio of the pouring volume of the second concrete B to the pouring volume of the first concrete A is...
[0092] That is, the ratio of the pouring speed of the second concrete B to the pouring speed of the first concrete A is . Among them, S' A S' is the pouring speed of the first concrete A; B The pouring speed for the second concrete B.
[0093] For example, the dam body has a width of 40m across the river and a width of 20m along the river, a surface height H of 2m, a transition zone 206 width of 1m, a first concrete A grade of C30 with a flow slope ratio n of 1:10, a second concrete B grade of C25 with a flow slope ratio of 1:20, a flow slope ratio n of 1:10 in the rockfill area, a functional zone width of 1m, a pouring point 208 of the first concrete A and a pouring point 209 of the second concrete B with a spacing of 0.2m, then the distance l from the second concrete B pouring point 209 to the second formwork 202 is 18.3m, the distance M from the first concrete A pouring point 208 to the fourth formwork 204 is 1.5m, and the preset distance N is 4m.
[0094] As can be seen from the above, the ratio of the pouring speed of the second concrete B to the pouring speed of the first concrete A is [value missing]. Therefore, the ratio of the pouring speed of the second concrete B to that of the first concrete A is approximately 5.45. Those skilled in the art should understand that the above calculation method only represents the approximate volume of concrete to be poured, and is not a precise calculation, but it is sufficient to calculate the approximate ratio of the pouring speeds of the first concrete A and the second concrete B.
[0095] According to one embodiment of this application, the preset distance is 2m-6m, preferably 4m. Setting a reasonable preset distance can avoid the problem of large areas not being poured. The preset distance is related to the flow slope ratio of the concrete and the pouring height.
[0096] Method 2:
[0097] In Method Two, the three-dimensional irregular pouring volume is simplified to a two-dimensional regular pouring volume per unit width (volume = plane area * 1, i.e., expressed in plane area). The pouring speed of the first concrete A and the second concrete B is calculated by calculating the plane area covered by the first concrete A and the second concrete B. During pouring, to ensure that the contact interface between the first concrete A and the second concrete B rises synchronously and that the second concrete B does not flow into the functional area, two key elements are involved: the layout of pouring points and the control of pouring speed. Method Two decomposes the entire slab into multiple layers of pouring per unit height, so the calculation method of Method Two is applicable to both Step 2 and Step 3.
[0098] Figure 4 This is a schematic diagram of the cross-sectional structure of a concrete pouring slab according to one embodiment of this application. Figure 4As shown, the left side of the silo cross-section is the functional area, the right side is the riprap area, and the area between the functional area and the riprap area is the transition zone. The silo height is H. For safety reasons, it is assumed that the transition zone is entirely filled with the first concrete A, i.e., the sum of the lengths of the functional area and the transition zone is W. The flow slope ratio of the second concrete B is i (i≥1 / 35), and the initial single-layer pouring height is Δh1, where 0.3m≤Δh1≤0.5m. Δh1 is the specified single-layer pouring height. The quotient of H / Δh1 is n, and the remainder is Δh2. Therefore, Δh3=H-(n-1)Δh1-Δh2. The initial pouring point of the riprap area is located at a distance of Δh1 / i from the boundary of the transition zone.
[0099] First, a second concrete B with a height of Δh1 is poured at a distance of Δh1 / i from the boundary of the transition zone. The second concrete B can flow exactly to the boundary of the transition zone.
[0100] Then, simultaneously pour the first concrete A in the functional area or transition area and the second concrete B in the riprap area. Pouring stops when the second concrete B reaches a height of Δh1. At this point, the pouring points of both the first concrete A and the second concrete B have risen by Δh1. This process is repeated. The pouring speed per unit width of the first concrete A is v1, and the pouring speed per unit width of the second concrete B is v2. When Δh1 < h ≤ (n-1)Δh1, the pouring speeds v1 and v2 conform to the following formula relationship:
[0101]
[0102] Wherein, v1 is the pouring speed of the first concrete A, v2 is the pouring speed of the second concrete B, α is the volume ratio of concrete in the riprap concrete in the riprap area, β is the volume ratio of concrete in the riprap concrete in the functional area and / or transition area, h is the pouring height of the first concrete A at the pouring point, n is the quotient of the surface height H divided by Δh1, Δh1 is the initial single-layer pouring height of the concrete at the pouring point, W is the sum of the lengths of the functional area and the transition area, W=W1+W2, where W1 is the width of the area completely filled by the first concrete A, W2 is the width of the riprap concrete area filled by the first concrete A, and i is the flow slope ratio of the second concrete B.
[0103] When the first concrete A and the second concrete B are poured simultaneously, their pouring times are the same. Based on the fact that their pouring times are the same, the following formula can be obtained:
[0104]
[0105] refer to Figure 4 WΔh1 is the area of rectangle 410, and W1Δh1+β·W2Δh1 is the area of rectangle 410 that needs to be filled with concrete. This refers to the area of concrete that needs to be filled in the two parallelograms 420 (the second concrete B spreads to the left and right sides).
[0106] To ensure that the concrete heights in the transition zone and the riprap zone rise simultaneously, or that the pouring time of the first concrete A is less than or equal to the pouring time of the second concrete B, the following formula can be obtained:
[0107]
[0108] By transforming and simplifying formula (11), we can obtain formula (9). By controlling the pouring speeds v1 and v2 as shown in formula (9), we can ensure that the second concrete B will not flow into the transition zone, and that the contact interface between the first concrete A and the second concrete B rises synchronously.
[0109] For example, the height H of the storage area is 2m, the width W of the functional area and the transition area is 1m, where W1 = 0.8m, W2 = 0.2m, the layer height Δh1 of the layered pouring is 0.3m, the first concrete A grade is C25, the second concrete B grade is C20, and their flow slope ratio is 1:20. The flow slope ratio i in the riprap concrete is 1:10. The concrete volume ratio β in the riprap concrete of the functional area and / or transition area is 0.55, and the concrete volume ratio α in the riprap concrete of the riprap area is 0.45. Then, using formula (9), the following can be calculated:
[0110]
[0111] Then, when the height Δh2 of parallelogram 430 is less than Δh1, i.e., (n-1)Δh1<h≤H-Δh3, the first concrete A is poured simultaneously in the functional area or transition area (e.g., Figure 4 (e.g., rectangular 430) and pouring a second concrete B in the riprap area (e.g.) Figure 4 For parallelogram 440), the pouring speeds v1 and v2 conform to the following formula relationship:
[0112]
[0113] Wherein, v1 is the pouring speed of the first concrete A, v2 is the pouring speed of the second concrete B, β is the volume percentage of concrete in the riprap concrete of the functional area and / or transition area, and α is the volume percentage of concrete in the riprap concrete of the riprap area. h is the pouring height of the first concrete A at the pouring point, n is the quotient of the surface height H divided by Δh1, Δh1 is the initial single-layer pouring height of the concrete at the pouring point, Δh2 is the single-layer pouring height of the second concrete B at the pouring point when the pouring height reaches the preset height, Δh3 is the single-layer pouring height of the first concrete A at the pouring point when the pouring height reaches the preset height, W is the sum of the lengths of the functional area and the transition area, W = W1 + W2, where W1 is the width of the area completely filled by the first concrete A, W2 is the width of the riprap concrete area filled by the first concrete A, and i is the flow slope ratio of the second concrete B.
[0114] For example, the height H of the storage area is 2m, the width W of the functional area and the transition area is 1m, the layer height Δh1 of the layered pouring is 0.3m, the first concrete A grade is C30, the second concrete B grade is C25, the flow slope ratio is 1:20, the flow slope ratio i in the riprap area is 1:10, the concrete volume ratio β in the riprap concrete of the functional area and / or transition area is 0.55, and the concrete volume ratio α in the riprap concrete of the riprap area is 0.45. The calculation process according to formula (12) is as follows:
[0115] 2 ÷ 0.3 = 6…0.2
[0116] As can be seen from the above, n is 6, Δh2 is 0.2m, and Δh3 is 0.3m.
[0117] When the pouring height h of the first concrete A at the pouring point is 1.5m < h ≤ 1.7m, the result can be calculated using formula 9:
[0118]
[0119] Finally, the first concrete A is poured into the unpoured portion of the slab surface (i.e., Figure 4 (450) until the entire surface of the container is filled with water.
[0120] Figure 5A This is a structural schematic diagram of a unidirectional casting method in an integrated casting area according to an embodiment of this application. Figure 5B This is a structural schematic diagram of an opposite casting method in an integrated casting area according to an embodiment of this application. Figure 5C This is a structural schematic diagram of a back-to-back casting method in an integrated casting area according to an embodiment of this application. Figure 5A , Figure 5B or Figure 5CAs shown, the integrated casting area includes the functional area, the transition area, and the adjacent riprap area. Casting methods include unidirectional, opposing, and reverse casting. During casting, it is necessary to follow... Figure 5A , Figure 5B or Figure 5C The middle arrows indicate the sequence of pouring points, which are then poured in an integrated manner. Figure 6A This is a schematic diagram of the pouring direction of the concrete pouring surface in an "S"-shaped concrete pouring area according to an embodiment of this application. Figure 6B This is a schematic diagram of the pouring direction structure of an "N"-shaped concrete pouring site in a rockfill area according to one embodiment of this application. After the first concrete A in functional zone 207 is poured, the integrated pouring is completed. Then, the second concrete B continues to be poured in rockfill zone 205 until the rockfill zone 205 is completed. When pouring the second concrete B in rockfill zone 205, a unidirectional, point-by-point pouring principle should be followed, with adjacent pouring points spaced 3m-5m apart. After each pouring point reaches a preset height, the pourer moves to the next pouring point. In one embodiment, the upstream of the dam is poured first, followed by the downstream of the dam. (Reference) Figure 6A When the silo area is small, a two-way moving method is used for pouring, namely "S" shaped pouring. Figure 6A The pouring points 210, 212, 213, and 214 only indicate the pouring sequence and do not represent the actual pouring locations. The side of the first pouring point 210 is the water-facing side; therefore, pouring begins on the water-facing side of the rockfill area 205, proceeding sequentially from the first pouring point 210, to the second pouring point 212, to the third pouring point 213, to the fourth pouring point 214, and so on, until the entire rockfill area 205 is poured.
[0121] refer to Figure 6B When the silo area is large, a unidirectional moving method is used for pouring, namely "N" type pouring. Figure 6B The pouring points 214, 215, 216, and 217 only indicate the pouring sequence and do not represent the actual pouring locations. The side of the first pouring point 214 is the water-facing side; therefore, pouring begins on the water-facing side of the rockfill area 205. The first pouring point 210, the second pouring point 212, and the third pouring point 213 are poured sequentially. When one longitudinal section of the rockfill area 205 is completed, the pouring point is moved back to the side where it began pouring, and pouring continues from the fourth pouring point 214, and so on, until the entire rockfill area 205 is poured.
[0122] Finally, after the surface is poured, the insulation and moisturizing curing time is set at 25-30 days.
[0123] In summary, this application employs an integrated casting method, simultaneously casting the first concrete A and the second concrete B, and controlling the convergence of the two types of concrete in the transition zone. This avoids excessive flow of concrete from the high-cost functional areas into the riprap area, thus reducing casting costs. Furthermore, it allows for a denser bond between the concrete in the functional areas and the concrete in the riprap area, resulting in better overall structural performance. In terms of construction technology, it reduces the need for formwork and tie rods between the functional areas and the riprap area, optimizing the construction process, reducing manual labor, and improving construction efficiency.
[0124] The above embodiments are for illustrative purposes only and are not intended to limit the scope of this application. Those skilled in the art can make various changes and modifications without departing from the scope of this application. Therefore, all equivalent technical solutions should also fall within the scope of this application.
Claims
1. A method of integrated construction of rockfill concrete, characterized in that, include: Erect a template on the surface of the silo to be poured so that it forms a silo with the silo surface; The storage area includes a functional area and a riprap area, and the functional area and / or riprap area is filled with riprap of a preset height. Before pouring concrete, a pouring plan is determined, which includes multiple pouring locations and pouring sequence, as well as the pouring speed and pouring volume at each pouring location. The pouring process includes: Step 1: Pour a first concrete A in the functional area or transition area, and pour a second concrete B in the riprap area or transition area adjacent to the transition area, so that the first concrete A and the second concrete B are in direct contact in the transition area, wherein the transition area is located between the functional area and the riprap area, the first concrete A is used to pour the functional area and / or part of the transition area, and the second concrete B is used to pour the riprap area and / or part of the transition area; Step 2: Control the pouring speed of the first concrete A and the second concrete B respectively, so that the contact interface of the first concrete A and the second concrete B rises synchronously, and the second concrete B does not flow into the functional area. When the pouring height of the first concrete A at the pouring point and the pouring height of the second concrete B at the pouring point reach the preset height respectively, stop pouring. The pouring scheme is determined by calculation. The determination of the pouring scheme includes: simplifying the integrated pouring area into a two-dimensional model, determining the pouring position and pouring sequence of the concrete, and then determining the pouring speed and pouring volume of the first concrete A and the second concrete B at each pouring position. The pouring point of the first concrete A is in the functional area or transition area, and the pouring point of the second concrete B is in the rockfill area. When Δh1<h≤(n-1)Δh1, the pouring speed v1 of the first concrete A and the pouring speed v2 of the second concrete B must satisfy the following formula relationship: ; When (n-1)Δh1<h≤H-Δh3, the pouring speed v1 of the first concrete A and the pouring speed v2 of the second concrete B must satisfy the following formula relationship: Where v1 is the pouring speed of the first concrete A, v2 is the pouring speed of the second concrete B, and β is the volume percentage of concrete in the riprap concrete of the functional area and / or transition area. Let be the volume percentage of concrete in the riprap concrete of the riprap area, h be the pouring height of the first concrete A at the pouring point, n be the quotient of the surface height H divided by Δh1, Δh1 be the initial single-layer pouring height of the concrete at the pouring point, Δh2 be the single-layer pouring height of the second concrete B at the pouring point when the pouring height reaches the preset height, Δh3 be the single-layer pouring height of the first concrete A at the pouring point when the pouring height reaches the preset height, W be the sum of the lengths of the functional area and the transition area, W = W1 + W2, where W1 is the width of the area completely filled by the first concrete A, W2 is the width of the riprap concrete area filled by the first concrete A, and i be the flow slope ratio of the second concrete B. Step 3: Move the first concrete pouring point A and the second concrete pouring point B along a preset direction by a preset distance, and pour concrete in the manner described in Step 2; Step 4: Repeat step 3 until the first concrete A in the functional area is poured.
2. The integrated construction method for riprap concrete according to claim 1, characterized in that, Another calculation method is used to determine the pouring scheme, which includes: determining the pouring position and pouring sequence of concrete by simulating a three-dimensional pouring model of the integrated pouring area, and then determining the pouring speed and pouring volume of the first concrete A and the second concrete B at each pouring position. The pouring points of the first concrete A and the second concrete B are both within the transition zone.
3. The integrated construction method for riprap concrete according to claim 2, characterized in that, In step 2, the amount of the first concrete A poured is: ; The second concrete B pouring volume is: ; Wherein, V A is the first concrete A pouring amount, V B is the second concrete B pouring amount, H is the warehouse surface height, l is the distance between the pouring point of the second concrete B and the formwork away from the functional area along the transverse river direction, and M is the distance between the pouring point of the first concrete A and the formwork close to the functional area along the transverse river direction.
4. The integrated construction method for riprap concrete according to claim 3, characterized in that, The ratio of the amount of the second concrete B poured to the amount of the first concrete A poured is: That is, the ratio of the average pouring speed of the second concrete B to the average pouring speed of the first concrete A is . .
5. The integrated construction method for riprap concrete according to claim 2, characterized in that, In step 3, the amount of the first concrete A poured is: ; The pouring volume of the second concrete B is: ; in, This represents the pouring volume of the first concrete, A. H is the pouring volume of the second concrete B, l is the height of the slab surface, l is the distance between the pouring point of the second concrete B and the formwork on the side away from the functional area along the transverse direction, M is the distance between the pouring point of the first concrete A and the formwork on the side near the functional area along the transverse direction, N is the preset distance, and n is the flow slope ratio of the first concrete A and the flow slope ratio of the second concrete B on the riprap.
6. The integrated construction method for riprap concrete according to claim 5, characterized in that, The ratio of the amount of the second concrete B poured to the amount of the first concrete A poured is: That is, the ratio of the average pouring speed of the second concrete B to the average pouring speed of the first concrete A is . .
7. The integrated construction method for riprap concrete according to claim 1, characterized in that, The width of the functional area is 30mm-5000mm, and the width of the transition area is 200mm-5000mm.
8. The integrated construction method for riprap concrete according to claim 1, characterized in that, The preset direction is the direction across the river and / or the direction along the river, and the pouring method includes any one of unidirectional, opposite, and back-to-back directions. The preset distance is 2m-6m.
9. The integrated construction method for riprap concrete according to claim 2, characterized in that, The first concrete A pouring point is on the center line of the transition zone along the transverse river direction, and the second concrete B pouring point is on the side of the first concrete A pouring point close to the rockfill area and in the same transverse river direction. The distance between the first concrete A pouring point and the second concrete B pouring point is not less than 100mm.
10. The integrated construction method for riprap concrete according to claim 1, characterized in that, The functional areas include: seepage prevention zone, frost prevention zone, impact and abrasion resistance zone, as well as corridors and orifices.
Citation Information
Patent Citations
Self-compacting concrete construction method
CN110820750A
Construction method for pouring rock-fill concrete dam body
CN117286840A