Construction method of cast-in-place concrete Y-shaped column
By using mechanical connection joints and wooden formwork reinforcement, the construction method solves the problems of low formwork turnover rate and high safety risks in the construction of cast-in-place concrete Y-shaped columns, thereby reducing construction costs and improving safety. It is suitable for tall Y-shaped bifurcated column projects.
Patent Information
- Application Number
- CN202410399319.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2044-04-03
AI Technical Summary
In the construction of cast-in-place concrete Y-shaped columns, the turnover rate of formwork is low and the cost is high. When the bifurcation angle is not uniform, the safety risks are high. In particular, the internal reinforcement of long bifurcation columns is dense, making the construction complex and posing safety hazards.
The construction method employs mechanical connection joints, wooden formwork, and steel reinforcement. The steel bars are tied in sections, and a wooden circular formwork and steel square tube support system are used. Concrete is poured in layers, and the design and construction process of the formwork support system are combined, including the gradual installation and pouring of the lower columns, the core area of the column top, and the sub-columns.
It improves the turnover rate of templates, reduces construction costs, enhances construction safety and stress uniformity, simplifies the construction process, and is suitable for tall Y-shaped bifurcated column projects.
Smart Images

Figure CN118110345B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to a method for constructing cast-in-place concrete Y-shaped columns. Background Technology
[0002] Y-shaped column construction is common in transportation hubs and sports stadiums, and can be mainly divided into steel-concrete structures, steel pipe columns, and concrete columns. For cast-in-place concrete columns, steel formwork is currently widely used. However, when the bifurcation angles of the Y-shaped columns within the stadium are not uniform, a separate formwork is generally required for each column, resulting in low turnover, a large amount of detailed design work, and relatively high costs. If wooden formwork is used, the contact area between the bifurcation section of the Y-shaped column and the support system is small, especially for longer bifurcation columns with dense internal reinforcement and heavy weight, posing certain safety risks during construction. Therefore, the formwork support system and construction methods are extremely important. Summary of the Invention
[0003] The purpose of this invention is to provide a method for constructing cast-in-place concrete Y-shaped columns.
[0004] To address the above problems, this invention provides a method for constructing cast-in-place concrete Y-shaped columns, comprising:
[0005] First, the lower column reinforcement is tied, then the lower column formwork is installed around the lower column reinforcement, and then the lower column concrete is poured in layers inside the lower column formwork.
[0006] After the lower column is poured, the column top formwork is installed first, then the column top core area formwork is installed on the upper part of the column top formwork, then the column top core area reinforcement is tied inside the column top core area formwork, and then the column top core area concrete is poured inside the column top core area formwork.
[0007] Above the core area of the completed column top, the bottom formwork of each sub-column is installed. Then, the steel reinforcement of the corresponding sub-column is tied on the bottom formwork of each sub-column. Next, the upper formwork of the corresponding sub-column is installed layer by layer on the bottom formwork of each sub-column. Finally, the concrete of each sub-column is poured in layers inside the upper formwork.
[0008] Furthermore, in the above method, the lower column reinforcement is first tied, including:
[0009] First, the lower column reinforcement is tied. The column reinforcement is connected by mechanical connection, and the sleeve grade is Grade I. To facilitate the tightening of the reinforcement joint, positive and negative thread sleeves are used.
[0010] For columns with a height exceeding 8m, each longitudinal reinforcement bar should have one additional mechanical connection joint, and each longitudinal reinforcement bar should have two mechanical connection joints, avoiding non-connection zones.
[0011] Furthermore, in the above method, the reinforcement binding of the core area at the top of the column includes:
[0012] The core area of the column top has densely intersecting stirrups and reinforcing bars. The variable length stirrups are made by welding two open stirrups together after on-site installation and adjustment to form closed stirrups.
[0013] Furthermore, in the above method, the corresponding reinforcement binding of the sub-columns is performed, including:
[0014] Each longitudinal reinforcement bar of the support column is equipped with two mechanical connection joints.
[0015] Furthermore, in the above method, the installation of the lower column formwork includes:
[0016] The lower column formwork uses 18mm high-quality plywood formwork, the two sides are standardized round column formwork, the secondary keel uses 50×100mm timber, and the main keel uses 48mm diameter steel pipe.
[0017] The lower column formwork is fixed in the middle by two 14mm tie rods 107 spaced 500mm apart, and the outer side of the lower column formwork is reinforced with integral steel strips 105 spaced 300mm apart.
[0018] Furthermore, in the above method, the layered installation of the upper formwork of the support column includes:
[0019] The inner and outer support columns of the Y-shaped column are made of wooden round templates spliced together. The two templates at the upper and lower connection of the round template are installed in a staggered manner, and the round template is reinforced with steel bands as column hoops.
[0020] The circular cross-section of the support column is installed at an angle. To ensure the similarity and fit of the lower formwork arc, a No. 10 channel steel bent and shaped base is used, with the spacing consistent with the bottom support of the beam. The bottom beam of the support column is replaced with a 40mm×40mm×2mm square tube. The wooden formwork and the square tube are fixed with steel nails at a spacing of 300-500mm.
[0021] Furthermore, the above method also includes the construction of a formwork scaffolding system, including:
[0022] The formwork support system uses steel pipes with couplers, and the steel pipes are 48mm in diameter and 3.0mm in diameter.
[0023] The formwork support system is over 10m high. Based on modeling calculations, the longitudinal and transverse spacing of the bottom diagonal members perpendicular to the bifurcation columns is 450mm. Longitudinal square tubes are spaced 300mm apart along the entire length of the bifurcation columns, and channel steel bases are spaced 450mm apart. To ensure overall stability, the height-to-width ratio of the formwork support system is no less than 3. The scaffolding arrangement within the inner bifurcation column area is adjusted appropriately according to the plan to meet the height-to-width ratio requirements.
[0024] The formwork support system is equipped with horizontal scissor bracing every 4 steps along the step height, at the bottom and top; vertical scissor bracing is installed every 6m or less around the perimeter of the frame, in the longitudinal and transverse directions inside; the width of each vertical scissor bracing is 6m to 9m, and the angle between the diagonal bracing and the horizontal plane is 45° to 60°.
[0025] The formwork support system should be connected to the pre-cast lower vertical columns by a tie-in, with a spacing of no more than 4 step distances.
[0026] The diagonal supports at the bottom of the branch columns are arranged perpendicularly to the branch columns. Three supports are set under each column hoop. The diagonal supports are connected to the steel pipe columns by swivel couplers. Each diagonal support is connected to at least four vertical columns. Three longitudinal diagonal steel pipes are set along the direction of the Y-shaped bifurcated column and connected to the diagonal supports perpendicular to the bottom of the column.
[0027] The fixed round wooden molds for the support columns are connected to the steel square tubes with steel nails;
[0028] Dense safety netting was hung all around the frame.
[0029] Furthermore, in the above method, the lower column concrete is poured in layers within the lower column formwork, including:
[0030] The lower concrete was poured for the first time up to the bottom of the horizontal tie beam.
[0031] Furthermore, in the above method, the pouring of concrete for the core area of the column top within the formwork includes:
[0032] The second beam-column joint is poured and extended 600-900mm to the inner and outer bifurcated columns to form the core area at the top of the column. The construction joint is separated by quick-closing mesh and a construction joint perpendicular to the cross-section of the bifurcated column is left.
[0033] Furthermore, in the above method, the concrete for each sub-support is poured in layers, including:
[0034] The third stage involves symmetrically pouring the inner and outer bifurcated columns in segments, each segment being 2m long, with the inner and outer pouring heights spaced 0.5m apart each time.
[0035] Compared with existing technologies, the construction method for cast-in-place concrete Y-shaped columns of this invention overcomes the construction problems of core area reinforcement binding, wooden formwork reinforcement, and concrete pouring, and has the following advantages:
[0036] 1) Mechanical connection joints are set in sections of steel bars, which facilitates the installation of stirrups and on-site construction;
[0037] 2) The wooden formwork is lightweight and easy to install on site;
[0038] 3) High turnover rate and lower construction cost compared to steel formwork;
[0039] 4) Wooden formwork can be cut and assembled on-site;
[0040] 5) The concrete is poured in sections symmetrically, resulting in uniform stress distribution and high safety;
[0041] 6) The square tube and channel steel formwork system has high load-bearing capacity and uniform stress distribution;
[0042] 7) The construction method is simple in principle, the materials are readily available, and it is highly feasible.
[0043] 8) The successful practice of the Y-shaped column construction method has broad promotion and application value, and provides ideas and reference for other projects, especially tall Y-shaped bifurcated columns. Attached Figure Description
[0044] Figure 1 This is a schematic diagram of a Y-shaped column according to an embodiment of the present invention;
[0045] Figure 2 yes Figure 1 Cross-sectional view along the AA direction;
[0046] Figure 3 yes Figure 2 Cross-sectional view along the BB direction;
[0047] Figure 4 This is an elevation view of a Y-shaped column formwork support according to an embodiment of the present invention;
[0048] Figure 5 This is a schematic diagram of a lower elliptical cylinder reinforcement method according to an embodiment of the present invention;
[0049] Figure 6 This is a schematic diagram of a Y-shaped column shaft side template support according to an embodiment of the present invention;
[0050] Figure 7 This is a partial detailed view of a Y-shaped column base support according to an embodiment of the present invention;
[0051] Among them, 101—Y-shaped column; 102—lower elliptical column; 103—upper bifurcated column; 104—circular wooden formwork; 105—reinforcing steel strip; 106—timber; 107—tie rod; 108—slanted thick square tube at the bottom of the bifurcated column; 109—standardized arc-shaped channel steel; 110—steel pipe top support; 111—slanted support steel pipe; 112—longitudinal continuous slanted steel pipe; 113—vertical scissor brace; 114—horizontal scissor brace; 115—vertical upright; 116—horizontal bar; 117—steel nail; 118—construction joint; 119—horizontal tie beam. Detailed Implementation
[0052] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0053] like Figures 1 to 7 As shown, the present invention provides a method for constructing a cast-in-place concrete Y-shaped column, comprising:
[0054] Step S1: First, tie the lower column reinforcement bars, then install the lower column formwork around the lower column reinforcement bars, and then pour the lower column concrete in layers inside the lower column formwork.
[0055] Step S2: On the upper part of the lower column after the pouring is completed, first install the column top formwork, then install the column top core area formwork on the upper part of the column top formwork, then tie the column top core area reinforcement in the column top core area formwork, and then pour the column top core area concrete in the column top core area formwork.
[0056] Step S3: On the upper part of the core area of the completed column top, install the bottom formwork of each sub-column, then tie the corresponding sub-column reinforcement on the upper part of the bottom formwork of each sub-column, then install the upper formwork of the corresponding sub-column in layers on the upper part of the bottom formwork of each sub-column, and finally pour the concrete of each sub-column in layers inside the upper formwork.
[0057] Hereinafter, the construction process of the present invention is as follows: lower column reinforcement binding → lower column formwork installation → lower column concrete layered pouring → column top core area formwork installation → column top core area reinforcement binding → column top core area concrete pouring → sub-column bottom formwork installation → sub-column reinforcement binding → sub-column upper formwork layered installation → sub-column concrete layered pouring.
[0058] Y-shaped columns have a large bifurcation angle, making installation difficult due to dense reinforcement. Furthermore, bifurcation columns typically weigh over 15 tons, resulting in higher safety risks during construction. Therefore, the formwork support system and construction methods are crucial.
[0059] like Figures 1 to 7 As shown, it includes:
[0060] This invention mainly includes three aspects: construction of internal column reinforcement, construction of the lower elliptical concrete column segment, and construction of the upper forked segment. For dense reinforcement, a combination of forward and reverse threading and segmented installation techniques is used; the lower elliptical concrete column segment is fixed using a wooden circular formwork with integral steel straps; the bottom of the upper forked concrete column segment uses 40mm square tubing and a bent No. 10 channel steel base to improve fit and contact area, thereby increasing support safety.
[0061] Y-shaped column 101; elliptical column at the bottom of Y-shaped column 101 102; bifurcated column at the top of Y-shaped column 101 103; 18mm thick high-quality round wooden formwork 104; reinforcing steel strip 105; 50mm×100mm timber 106; 14mm tie rod 107; 40mm×40mm×2mm thick square tube at the bottom of the bifurcated column 108; 10# standardized arc-shaped channel steel 109; steel pipe top support 110; 48mm diameter diagonal support steel pipe 111; longitudinal continuous diagonal steel pipe 112; vertical scissor brace 113; horizontal scissor brace 114; vertical upright 115; horizontal bar 116; steel nail 117; construction joint 118; horizontal tie beam 119.
[0062] In one embodiment of the cast-in-place concrete Y-shaped column construction method of the present invention, the reinforcement engineering construction includes:
[0063] a. First, tie the lower column reinforcement. The column reinforcement is connected by mechanical connection. The sleeve grade is Grade 1. To facilitate the tightening of the reinforcement joint, positive and negative thread sleeves are used.
[0064] b. For Y-shaped columns with larger cross-sections, in order to facilitate the installation of stirrups, each longitudinal bar with a height exceeding 8m in the lower part of the column should have one additional mechanical connection joint, and each longitudinal bar should have two mechanical connection joints, while avoiding non-connection areas as much as possible.
[0065] c. Calculate the installation length and angle of the reinforcing bars according to their numbers, and bend the reinforcing bars into shape in one go;
[0066] d. The stirrups and reinforcing bars in the core area of the column top are densely intersecting. For stirrups of varying lengths, two open stirrups can be installed and adjusted on-site and then welded together to form closed stirrups.
[0067] e. The reinforcement bars of each sub-support should be installed after the bottom formwork of the sub-support is installed, and the bending angle should be ensured to be correct. If there are any discrepancies, a hand-held bending machine can be used to adjust them to avoid repeated bending that could damage the reinforcement bars.
[0068] f. Since the support columns are relatively long, two mechanical connection joints are provided for each longitudinal bar to facilitate installation. Please refer to the length settings for specific details.
[0069] In one embodiment of the cast-in-place concrete Y-shaped column construction method of the present invention, the construction of the lower elliptical concrete column segment includes:
[0070] a. The lower elliptical column formwork uses 18mm high-quality plywood formwork 104, the two sides are standardized round column formwork, the secondary keel uses 50×100mm timber 106, and the main keel uses 48mm diameter steel pipe 116.
[0071] b. The lower column formwork is fixed in the middle with two 14mm tie rods (107@500mm), and the outer side of the lower column formwork is reinforced with an integral steel strip (105@300mm).
[0072] In one embodiment of the construction method for cast-in-place concrete Y-shaped columns of the present invention, the construction of each bifurcated column segment at the top includes:
[0073] a. The inner and outer support columns of the Y-shaped column are made of wooden circular templates spliced together. The two templates at the upper and lower connection of the circular template are installed in a staggered manner. The circular template is reinforced with steel bands as column hoops.
[0074] b. The circular cross-section of the sub-support is installed at an angle. To ensure the similarity and fit of the lower template arc, No. 10 channel steel is bent and shaped into a base. The spacing is consistent with the bottom support of the beam. The bottom beam of the sub-support is replaced with a 40mm×40mm×2mm square tube. The wooden formwork and the square tube are fixed with steel nails at a spacing of 300-500mm.
[0075] In one embodiment of the construction method for cast-in-place concrete Y-shaped columns of the present invention, the formwork frame system construction includes:
[0076] a. The Y-shaped column has an elliptical-like base, with both inner and outer branches being circular components. The formwork support system uses steel pipes with couplers; the steel pipes are 48mm in diameter and 3.0mm in diameter.
[0077] b. The height of the Y-shaped column formwork support system is over 10m. According to modeling calculations, the longitudinal and transverse spacing of the bottom diagonal members 111 perpendicular to the bifurcation column is 450mm. The longitudinal square tubes 108 are spaced 300mm apart and run the length of the bifurcation column. The 10# channel steel bases 109 are spaced 450mm apart. To ensure the overall stability of the frame, the height-to-width ratio of the formwork support system should not be less than 3. The arrangement of the inner branch support can be adjusted appropriately according to the plan to meet the height-to-width ratio requirement, which needs to be calculated based on the stress.
[0078] c. The Y-shaped column formwork support system shall be equipped with horizontal scissor bracing 114 every 4 steps along the step height, at the bottom and top; vertical scissor bracing 113 shall be installed at intervals of no more than 6m around the perimeter of the frame, in the longitudinal and transverse directions inside; the width of each vertical scissor bracing 113 shall be 6m to 9m, and the angle between the diagonal bar of the scissor bracing and the horizontal plane shall be 45° to 60°.
[0079] d. The Y-shaped column formwork support system should be tied to the lower vertical columns that are poured first, with a spacing of no more than 4 steps, in order to improve the overall stability of the frame.
[0080] e. The diagonal supports 111 at the bottom of the branch column are arranged perpendicularly to the branch column, with 3 supports under each column hoop. The diagonal supports 111 are connected to the steel pipe columns by swivel couplers, and each diagonal support is connected to at least 4 vertical uprights 115; 3 longitudinal diagonal steel pipes 112 are installed along the direction of the Y-shaped bifurcation column and connected to the diagonal supports 111 perpendicular to the column bottom to increase stability;
[0081] f. The fixed round wooden mold of the support column and the steel square tube 108 are connected with steel nails 117.
[0082] g. Hang dense safety netting around the entire perimeter of the frame.
[0083] In one embodiment of the construction method for cast-in-place concrete Y-shaped columns of the present invention, concrete pouring includes:
[0084] a. The first pour of concrete at the bottom of the Y-shaped column reaches the bottom of the horizontal tie beam. The second pour is at the beam-column joint, extending 600-900mm to the inner and outer bifurcated columns to form the core area at the top of the column. Quick-closing mesh is used to separate the construction joints, leaving construction joints perpendicular to the cross-section of the bifurcated column. The third pour is carried out in sections of the inner and outer bifurcated columns, symmetrically poured in sequence. Each section is 2m long, and the pouring height of the inner and outer columns can be spaced 0.5m apart each time to reduce the horizontal force on the frame and the Y-shaped column.
[0085] b. Strictly control the concrete pouring speed. When pouring concrete in sections for columns, the upper section of concrete should be poured before the lower section of concrete has initially set.
[0086] c. Concrete vibration shall be performed using an immersion vibrator. When pouring in layers, the vibrator shall be inserted 50mm into the lower layer of concrete. Due to the close spacing of the stirrups in the support columns, two stirrup spacings shall be reserved at the vibrator opening, one upward and one downward. The stirrup spacing shall be restored promptly after the concrete is vibrated.
[0087] d. After pouring, cure in time. After reaching a certain strength, the upper semi-circular formwork of the bifurcated column can be removed for reuse. After the design requirements are met, the remaining formwork support can be removed.
[0088] This invention employs a wooden formwork and a fastener-type steel pipe support system to optimize the formwork support method and construction approach for Y-shaped columns, thereby improving safety and saving project costs.
[0089] This invention is mainly aimed at the construction of tall Y-shaped columns. It adopts a combination of adding mechanical connection joints, wooden formwork, steel strips, steel square tube beams, channel steel arc supports, and symmetrical pouring. According to the test results of relevant projects, this method can increase the stability of the wooden formwork support system and reduce project investment. The test results show that the method is successful and feasible.
[0090] This invention discloses a method for constructing cast-in-place concrete Y-shaped columns, including the construction of internal reinforcement within the Y-shaped column, fixing of the lower elliptical concrete column, upper forked segment support, and concrete pouring. This method can save costs, ensure construction quality, provide uniform stress distribution, and increase support safety. The reinforcement work employs a process of forward and reverse threading, segmented installation, and the addition of mechanical connection joints; the lower elliptical concrete column segment is fixed using a wooden circular formwork and integral steel straps; the upper forked segment concrete column base uses steel square tube beams and a No. 10 channel steel bent and shaped base; and the concrete is poured symmetrically in segments. Each longitudinal reinforcement bar has two mechanical connection joints, depending on the specific length; the lower elliptical column formwork uses 18mm high-quality plywood formwork, the secondary joists are made of 50mm×100mm timber, the main joists are made of 48mm diameter steel pipes, and the middle is fixed with two 14mm tie rods @500mm, and the outside of the formwork is reinforced with integral steel strips @300mm; the upper forked concrete column base beams use 40mm×40mm×2mm thick square tubing @300mm, the main beams are 10# channel steel bent and shaped bases, spaced 450mm apart, consistent with the beam bottom support, and the circular wooden formwork and... Square tubes are fixed with steel nails at intervals of 300-500mm, and cylindrical wooden formwork is fixed with steel straps. The bottom diagonal supports of the branch columns are arranged perpendicularly to the branch columns, with 3 supports under each column hoop. The diagonal supports are connected to the steel pipe columns with swivel couplers. Each support is connected to at least 4 uprights. Three longitudinal diagonal braces are set at the bottom and connected to the diagonal supports. The concrete pouring is divided into 3 stages. The first pouring is up to the bottom of the horizontal tie beam. The second pouring is up to the bifurcation column node, extending 600-900mm. The third pouring is symmetrical in sections of the bifurcation column, with each section being 2m long. The pouring height of the inner and outer sections can be spaced 0.5m apart each time.
[0091] The construction method for cast-in-place concrete Y-shaped columns of this invention overcomes the construction problems of core area reinforcement binding, wooden formwork reinforcement, and concrete pouring, and has the following advantages:
[0092] 1) Mechanical connection joints are set in sections of steel bars, which facilitates the installation of stirrups and on-site construction;
[0093] 2) The wooden formwork is lightweight and easy to install on site;
[0094] 3) High turnover rate and lower construction cost compared to steel formwork;
[0095] 4) Wooden formwork can be cut and assembled on-site;
[0096] 5) The concrete is poured in sections symmetrically, resulting in uniform stress distribution and high safety;
[0097] 6) The square tube and channel steel formwork system has high load-bearing capacity and uniform stress distribution;
[0098] 7) The construction method is simple in principle, the materials are readily available, and it is highly feasible.
[0099] 8) The successful practice of the Y-shaped column construction method has broad promotion and application value, and provides ideas and reference for other projects, especially tall Y-shaped bifurcated columns.
[0100] The various embodiments in this specification are described in a progressive manner, with each embodiment focusing on the differences from other embodiments. The same or similar parts between the various embodiments can be referred to each other.
[0101] Obviously, those skilled in the art can make various modifications and variations to the invention without departing from the spirit and scope of the invention. Therefore, if these modifications and variations fall within the scope of the claims of the invention and their equivalents, the invention is also intended to include these modifications and variations.
Claims
1. A method for constructing a cast-in-place concrete Y-shaped column, characterized in that, include: First, the lower column reinforcement is tied, then the lower column formwork is installed around the lower column reinforcement, and then the lower column concrete is poured in layers inside the lower column formwork. After the lower column is poured, the column top formwork is installed first, then the column top core area formwork is installed on the upper part of the column top formwork, then the column top core area reinforcement is tied inside the column top core area formwork, and then the column top core area concrete is poured inside the column top core area formwork. Above the core area of the completed column top, the bottom formwork of each sub-column is installed. Then, the steel reinforcement of the corresponding sub-column is tied on the bottom formwork of each sub-column. Then, the upper formwork of the corresponding sub-column is installed layer by layer on the bottom formwork of each sub-column. Finally, the concrete of each sub-column is poured in layers inside the upper formwork. First, the lower column reinforcement bars are tied, including: First, the lower column reinforcement is tied. The column reinforcement is connected by mechanical connection, and the sleeve grade is Grade I. To facilitate the tightening of the reinforcement joint, positive and negative thread sleeves are used. For columns with a height exceeding 8m, each longitudinal reinforcement bar should have one additional mechanical connection joint, and each longitudinal reinforcement bar should have two mechanical connection joints, avoiding non-connection areas. The core reinforcement of the column top is tied, including: The core area of the column top has densely intersecting stirrups and reinforcing bars. The variable length stirrups are made by welding two open stirrups together after on-site installation and adjustment to form closed stirrups. Perform the corresponding reinforcement binding for the sub-support columns, including: Each longitudinal reinforcement bar of the support column is equipped with two mechanical connection joints; Install the lower column formwork, including: The lower column formwork uses 18mm plywood formwork, the two sides use standardized round column formwork, the secondary keel uses 50×100mm timber, and the main keel uses 48mm diameter steel pipe. The lower column formwork is fixed in the middle by two 14mm tie rods 107 spaced 500mm apart, and the outer side of the lower column formwork is reinforced with integral steel strips 105 spaced 300mm apart. The layered installation of the upper formwork of the support columns includes: The inner and outer support columns of the Y-shaped column are made of wooden round templates spliced together to form the column template. The two templates at the upper and lower connection points of the column template are installed in a staggered manner, and the column template is reinforced with steel bands as column hoops. The circular cross-section of the support column is installed at an angle. To ensure the similarity and fit of the lower formwork arc, a No. 10 channel steel bent and shaped base is used, with the spacing consistent with the bottom support of the beam. The bottom beam of the support column is replaced with a 40mm×40mm×2mm square tube. The wooden formwork and the square tube are fixed with steel nails at a spacing of 300~500mm. It also includes the construction of the formwork scaffolding system, including: The formwork support system uses steel pipes with couplers, and the steel pipes are 48mm in diameter and 3.0mm in diameter. The height of the template support system is over 10m. According to the modeling calculation, the longitudinal and transverse spacing of the bottom diagonal members perpendicular to the sub-column is 450mm. The longitudinal square tubes are set at 300mm intervals along the length of the sub-column, and the channel steel bases are spaced at 450mm intervals. The formwork support system is equipped with horizontal scissor bracing every 4 steps along the step height, at the bottom and top; vertical scissor bracing is installed every 6m or less around the perimeter of the frame, in the longitudinal and transverse directions inside; the width of each vertical scissor bracing is 6m to 9m, and the angle between the diagonal bracing and the horizontal plane is 45 degrees to 60 degrees. The formwork support system should be connected to the pre-cast lower vertical columns by a tie-in, with a spacing of no more than 4 step distances. The diagonal bracing at the bottom of the branch column is arranged perpendicular to the branch column. Three bracings are set under each column hoop. The diagonal bracing is connected to the steel pipe column by a swivel coupler. Each diagonal bracing is connected to at least four vertical uprights. Three longitudinal diagonal steel pipes are set along the Y-shaped branch column direction and connected to the diagonal bracing perpendicular to the bottom of the column. The fixed round wooden molds for the support columns are connected to the steel square tubes with steel nails; Dense safety netting was fully hung around the perimeter of the frame. The lower column concrete is poured in layers within the lower column formwork, including: The lower concrete was poured for the first time up to the bottom of the horizontal tie beam; The concrete pouring for the core area of the column is carried out in the formwork of the core area of the column top, including: The second beam-column joint is poured and the inner and outer sub-columns are extended by 600-900mm to form the core area at the top of the column. The construction joint is separated by quick-closing mesh and a construction joint perpendicular to the cross-section of the sub-column is left. The concrete for each sub-support column is poured in layers, including: The third stage involves symmetrical pouring of the inner and outer support sections, each 2m long, with a 0.5m interval between each pour.
Citation Information
Patent Citations
Construction process for coating faced concrete outside ultrahigh steel tube column after floor is closed
CN103015717A
Y-type cast-in-place concrete column formwork system and construction method thereof
CN104088461A
Cast-in-place reinforced concrete inclined cylinder construction mold and method
CN112663949A