Steel sheet pile cofferdams and construction methods for complex riverbeds
By employing technologies such as pre-drilling, integrated pile driving guide frame, steel casing support, external steel reinforcement, and multiple drainage systems, the difficulties in driving and tilting of steel sheet pile cofferdams in complex riverbeds have been resolved, improving construction quality and efficiency and achieving efficient water-stopping effects.
Patent Information
- Application Number
- CN202410574931.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2044-05-10
AI Technical Summary
In complex riverbeds, especially in strata of sand and large-diameter pebbles, the construction of sheet pile cofferdams faces challenges such as high difficulty in driving the piles, low efficiency, and a tendency to tilt, which affect the construction quality and schedule.
The project employs an integrated guide frame for borehole drilling and pile driving, temporary auxiliary support for steel casing, external steel reinforcement, easily changeable internal support, multiple drainage systems, and steel casing lifting technology. Through precise borehole drilling, vertical pile driving, and enhanced overall cofferdam integrity, it improves the efficiency of bottom sealing concrete leveling and water drainage.
It improves the construction accuracy and integrity of sheet pile cofferdams, enhances construction quality and efficiency, and achieves a highly efficient water-stopping effect for sheet pile cofferdams.
Smart Images

Figure CN118257280B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of sheet pile cofferdam construction, specifically to sheet pile cofferdams for complex riverbeds and their construction methods. Background Technology
[0002] Steel sheet pile cofferdams, as retaining structures for underwater foundation construction, offer advantages such as ease of operation, low construction costs, and excellent water-stopping effects. However, for complex riverbeds, especially in strata of lean sand and large-diameter pebbles, steel sheet pile construction faces challenges such as high driving difficulty, low efficiency, and easy tilting, which severely restrict the construction quality and progress of steel sheet pile cofferdams.
[0003] Addressing the technical challenges of constructing sheet pile cofferdams in complex riverbeds, particularly in strata of lean sand and large-diameter pebbles, this invention provides a sheet pile cofferdam and its construction method for complex riverbeds, aiming to improve the construction quality and efficiency of sheet pile cofferdams. This construction method improves the accuracy of sheet pile driving, enhances the overall integrity and water-stopping effect of the sheet pile cofferdam, and can achieve good technical and economic benefits when applied to practical engineering projects. Summary of the Invention
[0004] The purpose of this invention is to provide a complex riverbed steel sheet pile cofferdam and construction method that can improve the construction accuracy of steel sheet piles, enhance the integrity and water-stopping effect of steel sheet pile cofferdams, and achieve better technical and economic benefits when applied to practical engineering.
[0005] To solve the above-mentioned technical problems, the present invention adopts the following specific solution: a construction method for steel sheet pile cofferdams in complex riverbeds, comprising the following steps:
[0006] Step 1, Piling location pilot hole: Use a guide frame to ensure the verticality of the pilot hole steel casing, and perform rotary drilling and interlocking pilot hole operation to ensure that the pile location is completely broken;
[0007] Step 2, Sheet Pile Driving and Closure: After the pile location is broken, a hydraulic pile driver is used to drive the sheet piles, and the sheet piles are closed to form an integral cofferdam structure.
[0008] Step 3: Ring beam installation: Install the ring beam on top of the steel sheet piles;
[0009] Step 4: Construction of external steel structure for cofferdam: Steel guide frames are installed at intervals outside the cofferdam. The external steel structure is then lowered using a vibratory hammer until it contacts the outer side of the sheet pile.
[0010] Step 5: Install internal supports: Weld walers to the inside of the sheet piles, and install internal supports inside the walers;
[0011] Step Six: Underwater Bottom Sealing Concrete Pouring: After the bottom of the cofferdam is cleared of silt, bottom sealing concrete is poured.
[0012] Step 7: Cofferdam dewatering: After the bottom concrete has hardened, use a mud pump to dewater the inside of the cofferdam.
[0013] Step 8: Cutting the steel casing: After the water inside the cofferdam is drained, cut off the inner steel casing and lift it away; then chisel away the pile head.
[0014] Preferably, in step one, an outer steel casing is installed on the outside of the guide frame, and a bracket is installed on the outer steel casing. The guide frame rests on the bracket on the outer steel casing. The guide frame has a double-layer frame structure, consisting of a first type of steel and a second type of steel. The first type of steel is located above the second type of steel, forming the upper frame structure of the guide frame, and the second type of steel forms the lower frame structure of the guide frame. Both the first and second types of steel are installed on the bracket on the outer steel casing. Guide holes are provided on the first and second types of steel. When the pilot hole steel casing is lowered, the pilot hole steel casing passes through the guide holes.
[0015] As a preferred option: In step two, an inner steel casing is installed on the inner side of the guide frame, and a bracket and an elastic straightening device are installed on the inner steel casing; during the sheet pile driving operation, one side of the sheet pile contacts the bracket and the elastic straightening device, and the verticality of the sheet pile is controlled by the elastic straightening device.
[0016] As a preferred option: In step three, a steel section is placed on the upper part of the ring beam, and vertical hangers are set on both sides of the steel section. The lower end of the vertical hangers is used to suspend the platform plate; a corbel support is set on the inside of the steel sheet pile, and an I-beam is set on the corbel support. The bottom of the platform plate rests on the I-beam.
[0017] As a preferred method: In step four, the external steel section is guided by a steel guide frame; the steel guide frame consists of three parts: a steel guide plate, a guide rail cross brace, and a positioning steel section. The positioning steel section is set on the guide rail cross brace, and the steel guide plate is set on the positioning steel section. The steel guide plate is provided with a steel guide groove; when the external steel section is laid, the steel guide plate is fixed at the piling position, and the external steel section is driven into the stratum through the steel guide groove on the steel guide plate.
[0018] As a preferred option: In step six, a concrete leveling device is installed on the inner steel casing; the concrete leveling device includes a scraper and a ring plate; four scrapers are installed on the outer side of the ring plate, and the ring plate is fitted onto the inner steel casing. By rotating the ring plate, the ring plate drives the scrapers to rotate, thereby achieving the leveling of the bottom sealing concrete.
[0019] As a preferred option: In step seven, during dewatering, a drainage pipe is installed at the bottom of the sealing concrete; the water inside the cofferdam is drained through the drainage pipe into the sealing ditch and then collected in the blind well, and pumped out to the outside of the cofferdam by a mud pump; a sealing pipe is installed outside the sheet piles, and the sealing pipe is set at the connection of adjacent sheet piles. Sealing material is injected into the connection of the sheet piles through the sealing pipe to seal the leakage of the sheet piles.
[0020] As a preferred option: In step eight, when lifting the inner steel casing, a lifting lug is welded to the upper part of the steel casing to be lifted, and the sling is connected to the lifting lug on the steel casing to be lifted and transported; an inner support bracket is installed inside the steel casing to provide internal support for the steel casing to be lifted and to prevent the inner steel casing from deforming during the lifting process.
[0021] As a preferred embodiment, the inner support bracket consists of a support arc support, a vertical connecting rod, and a radial support rod. One end of the radial support rod is connected to the vertical connecting rod, and the other end of the radial support rod is connected to the support arc support, which is in the shape of an arc. When the inner support bracket is placed into the steel casing that has been lifted out of the casing, the support arc support fits against the inner surface of the steel casing that has been lifted out of the casing.
[0022] A steel sheet pile cofferdam for complex riverbeds, constructed using a complex riverbed steel sheet pile cofferdam and construction method.
[0023] (1) The present invention adopts an integrated guide frame for drilling and pile driving, which improves the accuracy of drilling and pile driving of steel sheet piles.
[0024] (2) The present invention adopts the technology of temporary auxiliary support of steel sheet pile with steel casing, and sets up brackets and elastic straightening devices to temporarily support the steel sheet pile, thereby ensuring the verticality of the steel sheet pile.
[0025] (3) The upper part of the operating platform plate of the present invention is suspended by steel sections, and the lower part is supported by steel sheet pile brackets, which solves the installation problem of the operating platform.
[0026] (4) The present invention adopts the external steel reinforcement technology of the cofferdam, which improves the integrity of the steel cofferdam by adding external steel outside the steel sheet pile cofferdam.
[0027] (5) The present invention adopts a prefabricated internal support technology that is easy to change the system. The inner side of the waler is provided with a two-way joint for the internal support, which ensures the safety when the internal support is changed.
[0028] (6) The present invention adopts a steel casing guide rotation scraping device, and a scraper that can be rotated in a cross direction is set on the outside of the steel casing to solve the problem of scraping the bottom concrete.
[0029] (7) The present invention adopts a multi-drainage system of steel sheet pile cofferdam, and the cofferdam is equipped with drainage pipe network, bottom sealing ditch, etc., which improves the drainage efficiency of water accumulation in the cofferdam.
[0030] (8) The present invention adopts the steel casing external hanging internal support lifting technology. The casing is equipped with an internal support bracket and a lifting lug on the outside, which solves the problem of lifting the steel casing. Attached Figure Description
[0031] Figure 1 This is a plan view of the integrated guide frame for sheet pile drilling and pile driving;
[0032] Figure 2 This is a cross-sectional view (AA).
[0033] Figure 3 This is a schematic diagram of temporary support sheet piles for steel casings;
[0034] Figure 4 This is a schematic diagram of a steel frame suspended safety operating platform;
[0035] Figure 5 This is a magnified diagram of B;
[0036] Figure 6 This is a schematic diagram of an external steel guide frame;
[0037] Figure 7 This is a schematic diagram of a prefabricated internally supported cofferdam that is easy to modify.
[0038] Figure 8 This is a schematic diagram of the bottom sealing concrete construction;
[0039] Figure 9 This is a schematic diagram of a concrete leveling device;
[0040] Figure 10 This is a plan view of the multiple drainage system of the steel sheet pile cofferdam;
[0041] Figure 11 This is a cross-sectional view of a multi-drainage system for a steel sheet pile cofferdam;
[0042] Figure 12 This is a schematic diagram of the steel casing being lifted off the ground;
[0043] Figure 13 This is a schematic diagram of the internal support bracket of the steel casing.
[0044] In the diagram: 1-Outer steel casing; 2-Corner bracket; 3-Guide frame; 4-Inner steel casing; 5-Guide casing with pilot hole; 6-First type steel; 7-Second type steel; 8-Steel sheet pile; 9-Elastic straightening device; 10-Platform plate; 11-Ring beam; 12-Vertical hanger; 13-Steel section; 14-I-beam; 15-Steel guide frame; 16-Steel guide plate; 17-Guide rail cross brace; 18-Positioning steel; 19-External steel; 20-Two-way connection 21-Walter; 22-Newly installed internal support; 23-Original internal support; 24-Bottom sealing concrete; 25-Concrete leveling device; 26-Scraper; 27-Ring plate; 28-Drainage conduit; 29-Bottom sealing ditch; 30-Blind well; 31-Leak-sealing conduit; 32-Leak-sealing material; 33-Mud pump; 34-Steel casing lifted off the ground; 35-Lifting lug; 36-Internal support bracket; 37-Supporting arc support; 38-Vertical connecting rod; 39-Radial support. Detailed Implementation
[0045] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention are within the scope of protection of the present invention.
[0046] Those skilled in the art should understand that, in the disclosure of this invention, the terms "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, the above terms should not be construed as limiting this invention.
[0047] It is understood that the term "a" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element can be one, while in another embodiment, the number of the element can be multiple, and the term "a" should not be understood as a limitation on the number.
[0048] like Figures 1-13 The present invention provides a steel sheet pile cofferdam for complex riverbeds and a construction method thereof, including the following construction steps:
[0049] Step 1, Piling location pilot hole: Use guide frame 3 to control the verticality of the sinking of the pilot hole steel casing 5, and carry out rotary drilling and interlocking pilot hole operation to ensure that the pile location is completely broken;
[0050] An outer steel casing 1 is installed on the outer side of the guide frame 3, and a bracket 2 is installed on the outer steel casing 1. The bracket 2 is used to temporarily support the guide frame 3, which rests on the bracket 2 on the outer steel casing 1. The guide frame 3 has a double-layer frame structure, consisting of a first steel section 6 and a second steel section 7. The first steel section 6 is located above the second steel section 7, forming the upper frame structure of the guide frame 3, and the second steel section 7 forms the lower frame structure. Both the first steel section 6 and the second steel section 7 are mounted on the bracket 2 on the outer steel casing 1. The guide frame 3 has guide holes, which are located on the first steel section 6 and the second steel section 7, with the guide holes on the first steel section 6 corresponding to the guide holes on the second steel section 7. When the pilot hole steel casing 5 is lowered, it passes through the guide holes. The guide frame 3 is used for construction accuracy control during both pilot hole and pile driving operations.
[0051] Step 2, Sheet Pile Driving and Closure: After the pile location is broken, a hydraulic pile driver is used to drive sheet pile 8, and the sheet pile 8 are closed to form a cofferdam.
[0052] The guide frame 3 has an inner steel casing 4 on its inner side. A bracket 2 and an elastic straightening device 9 are mounted on the inner steel casing 4. The bracket 2 and elastic straightening device 9 on the inner steel casing 4 are used to temporarily control the verticality of the sheet pile 8. During the driving operation of the sheet pile 8, one side of the sheet pile 8 contacts the bracket 2 and the elastic straightening device 9, and the verticality of the sheet pile 8 is controlled by the elastic straightening device 9.
[0053] Step 3: Ring Beam Installation: A ring beam 11 is installed on top of the sheet piles 8 to strengthen the overall integrity of the cofferdam. A steel section 13 is placed on top of the ring beam 11, with vertical hangers 12 on both sides of the steel section 13. The lower end of the vertical hangers 12 suspends the platform plate 10. A corbel support 2 is installed inside the sheet piles 8, with an I-beam 14 mounted on it. The bottom of the platform plate 10 rests on the I-beam 14. The platform plate 10 provides a working platform for operators.
[0054] Step 4: Construction of external steel sections for the cofferdam: Steel guide frames 15 are installed at intervals outside the cofferdam. External steel sections 19 are lowered using a vibratory hammer to reinforce the integrity of the cofferdam. The steel guide frames 15 guide the external steel sections 19. The external steel sections 19 contact the outer side of the sheet piles 8.
[0055] The steel guide frame 15 comprises three parts: a steel guide plate 16, a guide rail cross brace 17, and a positioning steel section 18. The positioning steel section 18 is mounted on the guide rail cross brace 17, and the steel guide plate 16 is mounted on the positioning steel section 18. The steel guide plate 16 is provided with a steel guide groove. When lowering the external steel section 19, the steel guide plate 16 is fixed at the piling position, and the external steel section 19 is driven into the stratum through the steel guide groove on the steel guide plate 16.
[0056] Step 5: Installation of internal support: Weld walers 21 to the inside of the sheet piles 8, and install internal support inside the walers 21 to reinforce the integrity of the cofferdam.
[0057] Both the waler 21 and the inner support are prefabricated components; a two-way joint 20 is provided on the inner side of the waler 21; the two-way joint 20 has reserved longitudinal and diagonal support joints, and the two-way joint 20 can connect the original inner support 23 and the newly installed inner support 22 after the system conversion at the same time; the original inner support 23 and the newly installed inner support 22 are both connected to the two-way joint 20 by bolt connection.
[0058] Step Six: Underwater Bottom Sealing Concrete Pouring: After the bottom of the cofferdam is cleared of silt, bottom sealing concrete is poured for 24 minutes.
[0059] A concrete leveling device 25 is installed on the inner steel casing 4. The concrete leveling device 25 includes a scraper 26 and a ring plate 27. Four scrapers 26 are provided on the outer side of the ring plate 27. The ring plate 27 is fitted on the inner steel casing 4. By rotating the ring plate 27, the ring plate 27 drives the scraper 26 to rotate, thereby achieving the leveling of the bottom sealing concrete 24.
[0060] Step 7: Cofferdam dewatering: After the bottom concrete 24 has hardened, the inside of the cofferdam is dewatered using mud pump 33.
[0061] During drainage, a drainage pipe 28 is installed at the bottom of the sealing concrete 24; water inside the cofferdam is drained through the drainage pipe 28 to the sealing ditch 29 and then collected in the blind well 30, and pumped out to the outside of the cofferdam by the mud pump 33; a sealing pipe 31 is installed on the outside of the sheet pile 8, and the sealing pipe 31 is set at the connection of adjacent sheet piles 8. The sealing material 32 can be injected into the connection of the sheet pile 8 through the sealing pipe 31 to seal the leakage of the sheet pile 8.
[0062] Among them, the bottom sealing ditch 29 is set around the bottom sealing concrete 24, and the blind well 30 is located at the four corners of the bottom sealing concrete 24.
[0063] Step 8: Cutting the steel casing: After the water inside the cofferdam is drained, cut off the inner steel casing 4 and lift the inner steel casing 4 away; then chisel off the pile head to facilitate the subsequent construction of the cofferdam's internal foundation.
[0064] When lifting the inner steel casing 4, lifting lugs 35 are welded to the upper part of the steel casing 34 being lifted. The slings are connected to the lifting lugs 35 on the steel casing 34 being lifted and used to lift the steel casing 34. An internal support bracket 36 is installed inside the steel casing 34 to provide internal support and stabilize it, preventing deformation of the inner steel casing 4 during the lifting process.
[0065] The inner support bracket 36 consists of a support arc support 37, a vertical connecting rod 38, and a radial support rod 39. One end of the radial support rod 39 is connected to the vertical connecting rod 38, and the other end is connected to the support arc support 37. The support arc support 37 is arc-shaped; when the inner support bracket 36 is placed into the steel casing 34 being lifted, the support arc support 37 fits against the inner surface of the steel casing 34 being lifted.
[0066] A steel sheet pile cofferdam for complex riverbeds, constructed using the aforementioned construction method for steel sheet pile cofferdams for complex riverbeds.
[0067] This invention is not limited to the preferred embodiments described above. Anyone can derive other products in various forms under the guidance of this invention. However, regardless of any changes in shape or structure, any technical solution that is the same as or similar to this application falls within the protection scope of this invention.
Claims
1. A method for constructing a complex riverbed steel sheet pile cofferdam, characterized by, Includes the following steps: Step 1, Piling location pilot hole: Use guide frame (3) to control the verticality of the pilot hole steel casing (5) and carry out rotary drilling and interlocking pilot hole operation to ensure that the pile location is completely broken; Step 2, Steel Sheet Pile Sinking and Closure: After the pile position is broken, the steel sheet piles (8) are sinked using a hydraulic pile driver, and the steel sheet piles (8) are closed to form an overall cofferdam structure. Step 3, Ring Beam Installation: Install a ring beam (11) on top of the sheet pile (8); place a steel section (13) on the upper part of the ring beam (11), set vertical hangers (12) on both sides of the steel section (13), and hang a platform plate (10) at the lower end of the vertical hangers (12); set a corbel bracket (2) on the inner side of the sheet pile (8), set an I-beam (14) on the corbel bracket (2), and place the bottom of the platform plate (10) on the I-beam (14); Step 4: Construction of external steel structure of cofferdam: Steel guide frames (15) are set at intervals outside the cofferdam. External steel structure (19) is lowered using a vibratory hammer. External steel structure (19) contacts the outside of steel sheet pile (8). Step 5, Installation of internal support: Weld a waler (21) to the inside of the sheet pile (8), and install internal support inside the waler (21); Step 6, underwater bottom sealing concrete pouring: After the bottom of the cofferdam is cleared, bottom sealing concrete (24) is poured; Step 7, Cofferdam dewatering: After the bottom concrete (24) has hardened, the inside of the cofferdam is dewatered using a mud pump (33). Step 8: Cutting the steel casing: After the water inside the cofferdam is drained, cut off the inner steel casing (4), lift the inner steel casing (4) away, and then chisel off the pile head.
2. The complex riverbed steel sheet pile cofferdam construction method according to claim 1, characterized by, In step one, an outer steel casing (1) is set on the outside of the guide frame (3), and a bracket (2) is set on the outer steel casing (1). The guide frame (3) rests on the bracket (2) on the outer steel casing (1). The guide frame (3) is a double-layer frame structure. The guide frame (3) is composed of a first type steel (6) and a second type steel (7). The first type steel (6) is located above the second type steel (7). The first type steel (6) constitutes the upper frame structure of the guide frame (3), and the second type steel (7) constitutes the lower frame structure of the guide frame (3). The first type steel (6) and the second type steel (7) are both set on the bracket (2) on the outer steel casing (1). Guide holes are set on the first type steel (6) and the second type steel (7). When the pilot hole steel casing (5) is lowered, the pilot hole steel casing (5) passes through the guide hole.
3. The construction method for steel sheet pile cofferdams in complex riverbeds according to claim 1, characterized in that: In step two, an inner steel casing (4) is installed on the inner side of the guide frame (3), and a bracket (2) and an elastic straightening device (9) are installed on the inner steel casing (4). When the sheet pile (8) is being driven, one side of the sheet pile (8) contacts the bracket (2) and the elastic straightening device (9), and the verticality of the sheet pile (8) is controlled by the elastic straightening device (9).
4. The construction method for steel sheet pile cofferdams in complex riverbeds according to claim 1, characterized in that: In step four, the external steel section (19) is guided by the steel section guide frame (15). The steel section guide frame (15) consists of three parts: steel section guide plate (16), guide rail cross brace (17), and positioning steel section (18). The positioning steel section (18) is set on the guide rail cross brace (17), and the steel section guide plate (16) is set on the positioning steel section (18). The steel section guide plate (16) is provided with a steel section guide groove. When the external steel section (19) is laid, the steel section guide plate (16) is fixed at the piling position, and the external steel section (19) is driven into the stratum through the steel section guide groove on the steel section guide plate (16).
5. The construction method for steel sheet pile cofferdams in complex riverbeds according to claim 1, characterized in that: In step six, a concrete leveling device (25) is installed on the inner steel casing (4); the concrete leveling device (25) includes a scraper (26) and a ring plate (27); four scrapers (26) are installed on the outside of the ring plate (27), and the ring plate (27) is fitted on the inner steel casing (4). By rotating the ring plate (27), the ring plate (27) drives the scraper (26) to rotate, thereby achieving the leveling of the bottom sealing concrete (24).
6. The construction method for steel sheet pile cofferdams in complex riverbeds according to claim 1, characterized in that: In step seven, during the dewatering process, a drainage pipe (28) is installed at the bottom of the sealing concrete (24); the water inside the cofferdam is drained through the drainage pipe (28) to the sealing open ditch (29) and then collected in the blind well (30), and pumped out to the outside of the cofferdam by the mud pump (33); a sealing pipe (31) is installed outside the sheet pile (8), and the sealing pipe (31) is set at the connection of adjacent sheet piles (8). The sealing material (32) is injected into the connection of the sheet pile (8) through the sealing pipe (31) to seal the leakage of the sheet pile (8).
7. The construction method for steel sheet pile cofferdams in complex riverbeds according to claim 1, characterized in that: In step eight, when the inner steel casing (4) is lifted away, a lifting lug (35) is welded on the upper part of the steel casing (34) to be lifted away. The sling is connected to the lifting lug (35) on the steel casing (34) to be lifted away and to lift the steel casing (34) to be lifted away. An inner support bracket (36) is installed inside the steel casing (34) to provide internal support for the steel casing (34) to prevent the inner steel casing (4) from deforming during the lifting process.
8. The construction method for steel sheet pile cofferdams in complex riverbeds according to claim 7, characterized in that: The inner support bracket (36) consists of a support arc support (37), a vertical connecting rod (38), and a radial support rod (39). One end of the radial support rod (39) is connected to the vertical connecting rod (38), and the other end of the radial support rod (39) is connected to the support arc support (37). The support arc support (37) is in the shape of an arc. When the inner support bracket (36) is placed into the steel casing (34) that has been lifted away, the support arc support (37) is in contact with the inner surface of the steel casing (34) that has been lifted away.
9. A steel sheet pile cofferdam for complex riverbeds, characterized in that: The steel sheet pile cofferdam construction method for complex riverbeds as described in any one of claims 1-8 is used.
Citation Information
Patent Citations
Continuous steel wall and method for constructing same
CN102472031A
Cofferdam lead hole slotting and grouting construction method for deepwater hard rock steel plate pile
CN108457283A
Construction method of rotary excavating hole-guiding steel sheet pile cofferdam in deepwater inclined rock environment
CN110700293A