A construction technology for assembled ancient building wall

Through the optimized connection of prefabricated ancient building wall construction technology and epoxy interface agent, the appearance effect, hoisting problems and connection stability problems in ancient building construction are solved, efficient and green construction and quality consistency are achieved, and the quality is improved. Construction efficiency and water and alkali resistance.

CN118390704BActive Publication Date: 2024-10-29BEIJING FANGXIUYI CONSTR ENG CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410388777.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-01
Publication Date
2024-10-29
Estimated Expiration
2044-04-01

AI Technical Summary

Technical Problem

During the construction of ancient buildings, traditional prefabricated buildings have problems such as the appearance effect being difficult to achieve the level of traditional dry-fluted white walls, the difficulty in using hoisting machinery, the difficulty in handling board joints and wall through joints, and the insufficient stability of insulation wall connections.

Method used

A prefabricated ancient building wall construction technology is adopted, including wall production, hoisting and wall treatment steps. The prefabricated wall is processed in the factory, and an epoxy interface agent is used to optimize the connection between the brick layer and the concrete wall. Combined with Sponge strips and polyurethane foam glue are used to fill gaps to ensure the overall quality of the wall.

Benefits of technology

It achieves efficient and green construction of ancient building walls, reduces on-site wet work and dust, improves construction efficiency and quality consistency, solves lifting problems and connection stability issues, and achieves better appearance and water and alkali resistance. performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118390704B_ABST
    Figure CN118390704B_ABST
Patent Text Reader

Abstract

A construction process for an assembled ancient building wall specifically includes the following process steps: step one, wall production; step two, wall hoisting; step three, wall surface treatment; step two wall hoisting step specifically includes: 1) crane support; 2) wall hoisting in place; 3) diagonal brace setting; 4) wall correction; 5) bottom and top bolt adjustment and tightening; 6) connection part grouting; 7) review and acceptance; wherein, step three wall surface treatment step specifically includes: 1) wall surface review and acceptance; 2) welding of angle steel on the upper part of the wall; 3) stone installation; 4) cleaning of plate joints and brick joints; 5) caulking at the plate surface and connectors; 6) brick laying at the joints; 7) ice tray eaves and mountain peaks; 8) overall wall jointing; 9) wall surface tilling.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a new type of construction technology for industrialized building walls, in particular to a construction technology for assembled ancient building walls. Background Art

[0002] Traditional ancient building wall construction generally has problems such as cumbersome procedures, high pollution, serious material consumption, and uncontrollable energy-saving coefficient. In order to develop a greener, energy-saving, and efficient ancient building construction system, we specially carry out prefabricated research and development and application for the walls in ancient buildings. Prefabricated buildings refer to buildings assembled on site with prefabricated components. For example, the building walls have been prefabricated in the factory. When building on the site, you only need to install the prefabricated walls to the designated location and then cast them into shape. Prefabricated buildings are easy to install, have a short construction period, and have stable building structure quality, and can form an industrialized production and processing system.

[0003] At present, in the common construction of prefabricated walls, the prefabricated wall is first hoisted to the surface to be constructed, and then the slurry is poured into the prefabricated wall. After the slurry dries, the wall can be formed. However, with the introduction of the construction technology of prefabricated buildings in the construction of antique buildings or the maintenance of ancient buildings, the problems faced are also more prominent: First, can the appearance of the prefabricated walls of ancient buildings reach the same level as the dry-laid and whitewashed walls in the traditional ancient building technology; second, the construction site of the prefabricated construction of ancient buildings is generally narrow. Due to the limitations of site conditions, large-scale hoisting machinery is difficult to apply to the construction site. How to complete the hoisting of the prefabricated walls of ancient buildings is a major difficulty; third, during construction, how to handle the board joints and wall joints of prefabricated ancient buildings and control the quality. This is because the prefabricated walls of ancient buildings are different from the newly built prefabricated walls. The prefabricated walls of ancient buildings also include the surface layer. The treatment of the board joints and how the gray joints of the ancient building walls are connected together need to be controlled. Fourthly, the problem of how to construct the thermal insulation wall of prefabricated antique buildings, specifically how to achieve a safe, long-term and stable connection between the outer brick layer and the inner thermal insulation concrete wall. Summary of the invention

[0004] The present invention discloses a construction process for an assembled ancient building wall, which specifically includes the following process steps:

[0005] Step 1: wall production; Step 2: wall hoisting; Step 3: wall surface treatment;

[0006] Step 2 Wall hoisting steps specifically include: 1) Crane support; 2) Wall hoisting in place; 3) Bracing installation; 4) Wall correction; 5) Adjustment and tightening of bottom and top bolts; 6) Grouting of connection parts; 7) Review and acceptance;

[0007] Step three: wall treatment steps specifically include: 1) wall review and acceptance; 2) welding of angle steel on the upper part of the wall; 3) stone installation; 4) cleaning of board joints and brick joints; 5) caulking of board surfaces and connectors; 6) laying of facing bricks at joints; 7) laying of ice tray eaves and mountain peaks; 8) grouting of the entire wall; 9) tilling of wall joints.

[0008] Among them, in step 1, during the wall production, the weight of the wall produced is 1.4-1.6 tons.

[0009] Among them, in step 3 (5), the specific process for filling the gaps between the board surface and the connectors is to fill with polyurethane foam and apply cement mortar.

[0010] Among them, in step three 8), after grouting the entire wall surface, there is also a specific step of softening the core wall.

[0011] Among them, in step three, after 9) wall surface cracking, the method also includes 10) spot repair or spot cracking.

[0012] Among them, step 3 10) dot repair is mainly for dry-laid walls. After the dry-laid walls are built, they need to be repaired, including dry work, dot repair, flood repair and flushing. Dry work: Use a grinding head to smooth the raised parts of the joints between bricks. Dot repair: Use brick surface ash (brick medicine) to fill the broken parts of the bricks and the sand holes on the bricks. Flood repair: Use a grinding head dipped in water to smooth the dotted areas and the areas where the dry work has been done, and then dip in water to rub the entire wall surface to achieve consistency in color and texture. Flushing: Use clean water and a soft brush to clean and rinse the entire wall surface to show "real bricks and real seams". Flushing should be arranged after the wall is completed and before the scaffolding is removed to avoid dirtying the wall surface due to construction.

[0013] Among them, step three 10) is mainly for marking the seams of whitewashed walls. The seams of whitewashed walls need to be controlled at 4-6mm. When processing the wall, use a 5mm fixed-size sponge strip to control the seams. After the wall is installed and fixed, remove the sponge strip to mark the wall seams. Dark moon white lime or old slurry lime should be used for marking the seams of whitewashed walls, and small hemp lime should be used, that is, the hemp content in the lime should be appropriately reduced and the hemp should be cut short.

[0014] How to fill the gaps: Use a tile trowel, a small wooden stick or a nail to scratch along the brick joints, and then use a special tool "duckbill" or a small roller to "feed" the small hemp ash into the brick joints. The ash should be leveled with the brick wall and rolled flat. Then use a short-bristled brush with a small amount of clean water to brush along the brick joints. This can not only make the ash adhere more firmly, but also keep the brick edges clean.

[0015] In step 2, the wall hoisting step, before hoisting the prefabricated components, it is necessary to check whether the upper and lower elevations of the wall installation position meet the design requirements, whether the size of the ground beam of the lower structure of the wall is correct, whether the upper surface is flat, and whether the position of the embedded parts reserved for the ground beam is accurate. If there is any deviation, measures should be taken to adjust it in time.

[0016] The wall treatment steps mainly cover the covering treatment of wall connectors, the caulking treatment of wall joints, the post-installation of stones, the treatment of the connecting parts of the exterior walls, and the masonry construction of the non-prefabricated parts of the walls.

[0017] Before wall treatment, you should check whether the wall elevation is correct, whether the wall is flat, whether the prefabricated wall joints are straight, whether there is enough space reserved for stone installation, etc. The wall treatment construction can only be carried out after the wall installation quality is completed and accepted.

[0018] Before treating the wall surface, the sponge strips and sponge blocks used in wall construction should be cleaned.

[0019] Among them, step 1, wall production:

[0020] The thickness of the assembled ancient building wall is 210-330 mm, preferably 250-300 mm, and includes, from the outer wall to the inner wall, a 30-50 mm thick brick layer, a 40-60 mm thick concrete outer page layer, a 60-100 mm thick insulation layer and an 80-120 mm thick concrete structure wall inner page layer. The preparation method thereof comprises the following steps:

[0021] 1) Mold cleaning;

[0022] 2) Arrange the bricks and fill the seams with sponge strips to obtain the facing brick layer, and make grooves on the side of the facing brick layer close to the outer page layer;

[0023] 3) Cement mortar filling;

[0024] 4) Apply interface agent by brush;

[0025] 5) Lay the first layer of steel bars and set the upper and lower layer steel bar tie embedded parts;

[0026] 6) pouring concrete to obtain the outer layer;

[0027] 7) Laying the insulation layer;

[0028] 8) Lay the second layer of steel bars, connect the first and second layers of steel bars, and pre-embed water and electricity pipelines, hoisting parts, and connectors;

[0029] 9) pouring the inner layer of concrete;

[0030] 10) Wall demoulding, maintenance and acceptance.

[0031] The wall is a sill wall, a gable wall or a rear eaves wall.

[0032] Among them, the concrete in the inner layer of the concrete structure wall is preferably lightweight aggregate concrete.

[0033] The heat-insulating material of the heat-insulating layer is a molded polystyrene board, an extruded polystyrene board or a foamed polystyrene board.

[0034] The sill wall is dry-laid, and the sill wall core is made of Begonia pond hard core square bricks. The dry-laid wall surface brick arrangement should be tested in advance, and the front test of each brick joint is confirmed to be correct before it can be reversed in the mold.

[0035] The gable is a moon-white soft-core wall; the soft-core wall needs to reserve plastering thickness, otherwise the plastering thickness of the mortar joints at the wall joints will not reach the plastering layer and will easily fall off during the later wall treatment.

[0036] The rear eaves wall is painted with white mud.

[0037] Among them, wooden space is reserved in the window area, and vertical bricks are used under the window.

[0038] In order to avoid the formation of through-joints at the junctions of walls, a tooth-shaped joint area is reserved for subsequent masonry construction (the same applies to the corners of the walls).

[0039] The facing bricks used are from the same batch of bricks fired in the same furnace to ensure a uniform overall wall effect and reduce color differences.

[0040] The corner flowers and line squares in the core of the sill wall square bricks are made by the factory with unified molds and unified specifications for production and processing control, which reduces the uncertainty of errors that may occur during manual on-site polishing, speeds up the wall production cycle, and further improves wall production efficiency.

[0041] In the mold cleaning step, the mold is first inspected and accepted, and the corresponding wall mold is carefully checked and accepted according to the dimensions specified in the design drawings, and the overall dimensions of the mold, the staggered dimensions, the firmness of the connecting parts, and the flatness and smoothness of the bottom plate are checked and checked.

[0042] Since a single wall block is heavy, a crane is required for lifting. Therefore, corresponding lifting parts and connecting parts required for connecting and fixing various parts of the wall need to be embedded in the wall. The embedded lifting parts should be firmly connected to the wall structural steel bars and sealed inside the wall.

[0043] After adopting the above technical solution, the present invention has at least the following beneficial effects:

[0044] (1) The construction process of the assembled ancient building wall of the present invention can prepare the ancient building prefabricated wall, which is processed and formed in an integrated factory and then transported to the site for hoisting, avoiding on-site wet operations, better solving the restrictions on winter construction of ancient buildings, and providing assistance for accelerating the progress of project construction; the application of the ancient building prefabricated wall reduces the inevitable dust-raising operations of construction on the construction site under traditional processes from the aspect of wall masonry, and reduces the corresponding manpower and cost expenditures. At the same time, the manufacture and construction of the ancient building prefabricated wall reduces the demand and dependence on workers with ancient building construction capabilities, which is conducive to the construction and repair of ancient buildings to achieve large-scale production, and the consistency of the quality of ancient buildings is effectively guaranteed.

[0045] (2) The factory-based room temperature production conditions and maintenance effectively guarantee the quality of the prefabricated walls of ancient buildings. At the same time, the prefabricated walls of ancient buildings basically eliminate the alkali reaction phenomenon that is difficult to avoid during wall construction in winter, achieving better quality results.

[0046] (3) In the construction process of the assembled ancient building wall of the present invention, a small hoisting machine such as a spider crane can be used when hoisting the wall, which solves the problem of hoisting operations in narrow space construction.

[0047] (4) Use sponge strips when filling seams, especially sponge strips with a width of 5 mm, which can effectively control the wall mortar joints during wall processing and facilitate cleaning without affecting subsequent construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] Figure 1 The process flow chart of the construction of prefabricated ancient building walls

[0049] Figure 2 A schematic diagram of the structure of the present invention

[0050] In the accompanying drawings: 1, facing brick layer, 2, outer page layer, 3, insulation layer, 4, inner page layer. DETAILED DESCRIPTION

[0051] The construction process of the assembled ancient building wall in the embodiment of the present invention includes:

[0052] Step 1: Making the wall of an ancient building; wherein the wall of the ancient building is an assembled wall of an ancient building, and the assembled wall of the ancient building is further limited to be 210-330 mm thick, preferably 250-300 mm thick, and includes, from the outer wall to the inner wall, a 30-50 mm thick brick layer 1, a 40-60 mm thick outer page layer 2, a 60-100 mm thick insulation layer 3, and an 80-120 mm thick inner page layer 4. For example, the brick layer 1 can be a small mud brick layer, the outer page layer 2 can be a concrete outer page layer, the insulation layer 3 can be an extruded polystyrene board insulation layer, and the inner page layer 4 can be a lightweight aggregate concrete structural wall inner page layer. The wall of the ancient building is a sill wall, a gable, or a rear eaves wall.

[0053] For example, the preparation steps of the ancient building wall mainly include: (1) cleaning the mold; (2) arranging bricks and filling the seams with sponge strips to obtain the face brick layer, and grooving the side of the face brick layer close to the outer page layer; (3) filling the seams with cement mortar; (4) brushing the interface agent; (5) laying the first layer of steel bars and setting the upper and lower layers of steel bar tie embedded parts; (6) pouring concrete to obtain the outer page layer; (7) laying the insulation layer; (8) laying the second layer of steel bars, connecting the first and second layers of steel bars, and pre-embedding water and electricity pipelines, hanging parts, and connecting parts; (9) pouring the inner page layer of concrete; (10) demoulding, curing, and acceptance of the wall.

[0054] When making the walls of ancient buildings, the inventors found in the research process that the key technology to obtain prefabricated ancient building walls in which the brick layer (i.e., the face brick layer) and the thermal insulation concrete wall are integrally formed is the connection problem between the brick layer and the thermal insulation concrete wall. Compared with the currently used connectors, when integrally formed, improving the interlayer adhesion between the face brick layer and the concrete wall is the first technical problem to be solved, so as to avoid cracking between different layers during movement, and also prevent cracks between the face brick layer and the concrete wall over time. The inventors have tried a large number of existing adhesives to improve the adhesion between the face brick layer and the concrete wall layer, but they are either prone to cracking during hoisting, or are not water-resistant and alkali-resistant. Over time, the bonding performance of the adhesive decreases, and cracks will gradually appear, which makes the prefabricated ancient building wall have quality risks. The inventors and the interface agent supplier conducted joint scientific research on the structure of the wall and the type of adhesive, and found that the following process can significantly improve the interlayer adhesion between the face brick layer and the concrete wall, and it is effective for a long time:

[0055] 1) The structure of the brick layer is optimized by grooving to increase the wall bonding pull-out force and ensure the stability and safety of the brick layer, wherein the cross-sectional shape of the groove is square, rectangular or trapezoidal, and more preferably trapezoidal.

[0056] 2) Applying an epoxy interface agent having strong bonding performance, alkali resistance and water resistance on the side of the face brick layer facing the outer layer of concrete, wherein the interface agent is prepared by mixing component A and component B in a weight ratio of (4-6):1.

[0057] Component A comprises the following components by weight: 60-80 parts of epoxy acrylic resin, 10-20 parts of active diluent, 5-10 parts of auxiliary agent, 10-30 parts of conventional diluent A, and 20-30 parts of filler.

[0058] Component B contains: 10-30 parts of curing agent and conventional diluent B.

[0059] The auxiliary agents include wetting agents, leveling agents, defoaming agents, dispersants and anti-settling agents.

[0060] Further, the wetting agent is H-140;

[0061] The defoamers were Evonik Chemicals AIREX 900 and BYK-1794;

[0062] The leveling agent is BYK 354;

[0063] The dispersants are BYK 110 and BYK 163 from BYK Chemical;

[0064] The anti-settling agent is fumed silica, selected from R972 and R816 of Degussa.

[0065] The filler includes silicon micropowder, titanium dioxide, calcite powder, heavy calcium carbonate and talcum powder.

[0066] The preparation method of the interface agent comprises the following steps:

[0067] (1) mixing and stirring the epoxy acrylic resin, reactive diluent, auxiliary agent, and conventional diluent A in a high-speed disperser to obtain a mixture;

[0068] (2) adding filler to the mixture obtained in step (1) in a disperser while stirring to obtain component A;

[0069] (3) The curing agent and conventional diluent B are mixed and stirred using a disperser to prepare component B.

[0070] In step (1), the rotation speed of the high-speed disperser is 800-1000 rpm, and the stirring time is 15-20 min.

[0071] In step (2), the rotation speed of the disperser is 1200-1500 rpm, and the stirring time is 30-45 min.

[0072] In step (3), the rotation speed of the disperser is 600-800 rpm, and the stirring time is 5-10 min.

[0073] The epoxy acrylic resin is prepared by free radical copolymerization of a first monomer, a second monomer and a third monomer.

[0074] The first monomer is an acrylate monomer having three or more unsaturated carbon-carbon double bonds, and specifically may be trimethylolpropane trimethacrylate.

[0075] The second monomer is a monomer having an unsaturated carbon-carbon double bond and an epoxy group, and specifically can be glycidyl methacrylate.

[0076] The third monomer is γ-methacryloxypropyltrimethoxysilane.

[0077] The mass ratio of the first monomer, the second monomer and the third monomer is 2:(4-6):(0.4-0.6), and the preferred mass ratio is 2:5:0.5. The amount of the first monomer cannot be too much compared to the second monomer with unsaturated carbon-carbon double bonds and epoxy groups. If it is too much, the cross-linking density is too high. Although the adhesion is good, the flexibility of the interface layer is poor, and it is easy to crack when encountering instantaneous rigid force. If the amount is too little, it is not easy to obtain strong adhesion. As for the amount of the third monomer, if the amount is too much, the cost is too high, and if the amount is too little, the effect of improving the adhesion, water resistance and alkali resistance of the interface agent is not obvious.

[0078] The preparation method of epoxy acrylic resin comprises dissolving the first monomer, the second monomer and the third monomer in an organic solvent system under stirring, heating after they are completely dissolved, adding an initiator, and reacting for 3-5 hours in a reflux manner to obtain an epoxy acrylic resin solution, wherein the resin has an organosilicon functional group.

[0079] Amine curing agent: selected from triethylenetetramine, polyamide or polyetheramine and / or aminopropyltriethoxysilane (KH550), preferably a mixture of polyamide (POLYPOXW804, aradur-450, Versamid 228) and γ-aminopropyltriethoxysilane KH550, wherein the mass ratio of polyamide to γ-aminopropyltriethoxysilane is (8-10):1.

[0080] The active diluent is 1,4-butanediol diglycidyl ether, ethylene glycol diglycidyl ether, fatty glycidyl ether and / or butyl glycidyl ether, preferably a combination of active diluents with a mass ratio of 1,4-butanediol diglycidyl ether and butyl glycidyl ether of (1-2):1. This is because 1,4-butanediol diglycidyl ether not only has two epoxy groups, but also has a longer chain, and cross-links to form chains and networks during curing, which can significantly improve the tensile strength, impact strength and other properties of the interface layer. Butyl glycidyl ether contains both ether bonds and epoxy groups in the molecule, which not only has an excellent dilution effect, but also produces hydrogen bonds between the ether bonds, which can also give the interface layer a strong adsorption force. Therefore, 1,4-butanediol diglycidyl ether and butyl glycidyl ether as active diluents can significantly improve the mechanical properties of the interface layer while ensuring good adhesion, and the ability to reduce viscosity and dilution is very excellent.

[0081] Conventional diluent A may be xylene, butyl acetate, propylene glycol methyl ether acetate, ethylene glycol methyl ether, ethylene glycol butyl ether, acetone, butanone and or cyclohexanone.

[0082] Conventional diluent B may be xylene, butyl acetate, propylene glycol methyl ether acetate, butanol, butanone and cyclohexanone and or isopropanol.

[0083] Furthermore, after applying the epoxy interface agent, a layer of inorganic interface agent can be applied to further improve the affinity with the concrete wall layer, thereby improving the adhesion performance.

[0084] Through the above specific preparation process, the prepared ancient building wall has the following excellent properties:

[0085] (1) By optimizing the structure of the tile layer, i.e., adopting the groove treatment method, not only the construction area of ​​the interface agent is increased, the wall bonding pull-out force is increased, and the stability and safety of the tile layer are ensured. At the same time, the special-shaped connection between the tile layer and the concrete layer produces a snap-fit ​​effect. The vertical snap-fit ​​and the interface bonding force of the groove three surfaces are significantly improved compared with the common single-sided bonding.

[0086] Furthermore, the cross-sectional shape of the groove is square, rectangular or trapezoidal, more preferably trapezoidal. This is because after the concrete solidifies, the trapezoidal snap-fit ​​connection between the facing brick layer and the concrete layer has not only vertical snap-fitting, but also horizontal snap-fitting. Combined with the bonding force of the interface agent, the interlayer bonding force between the facing brick layer and the concrete layer is further greatly enhanced.

[0087] (2) During the research and development of the prefabricated ancient building wall, the inventors and the interface agent supplier improved the original interface agent according to the product characteristics. Although the cost has increased, the adhesion, water resistance and alkali resistance have been significantly improved. First, the main epoxy resin is a silicone-modified acrylic epoxy resin obtained by polymerizing an acrylate monomer with more than three unsaturated carbon-carbon double bonds, a monomer with unsaturated carbon-carbon double bonds and epoxy groups, and an unsaturated silicone such as γ-methacryloxypropyltrimethoxysilane. The epoxy resin has the characteristics of excellent adhesion, water resistance and good alkali resistance, and the acrylate with more than three unsaturated carbon-carbon double bonds produces a network cross-linked interpenetrating system with it, which greatly improves the density of the epoxy group, so that the adhesion, water resistance and alkali resistance of the modified epoxy resin are significantly improved compared with general epoxy resins, and the polyacrylate in the modified epoxy resin brings its inherent flexibility, which can effectively improve the mechanical properties such as tensile strength of the interface layer, and prevent the interface layer from lacking toughness due to excessive cross-linking density. The addition of unsaturated silicone monomers makes the modified epoxy resin contain polysilane, which not only brings hydrophobicity to the epoxy resin, but also the presence of a large number of hydroxyl groups improves the adhesion of the interface agent and further enhances the water and alkali resistance of the interface agent.

[0088] In addition, the interface agent in this application also uses an active diluent, which reduces the use of solvents, increases the curing speed of the interface agent at room temperature or even in winter, and reduces the negative impact of excessive solvent use on the solidification and maintenance of adjacent concrete layers, allowing the next concrete pouring process to be implemented within 30-60 minutes, greatly improving production efficiency.

[0089] The curing agent of the interface agent is preferably polyamide and γ-aminopropyl triethoxysilane. The polyamide curing agent has an internal plasticizing effect, which greatly improves the toughness of the interface agent layer. It also has amide groups and hydroxyl groups. The cured epoxy resin system has excellent adhesion, and has a polar amino group at one end and a non-polar long-chain hydrocarbon group at the other end. Therefore, it can adhere to and replace the water film on the wet surface. Therefore, the interface agent made by the polyamide curing agent has good adhesion to the concrete layer formed by the subsequent concrete pouring process, and there is no need to worry about the negative impact of the water-containing concrete on the interface agent. When γ-aminopropyl triethoxysilane is added to the curing agent, its amino group not only cross-links and cures with the epoxy resin to increase the cross-linking density, but also introduces the hydrophobicity of organic silicon to improve water resistance and alkali resistance. At the same time, the silanol generated by its hydrolysis, together with the silanol in the modified epoxy resin, can produce a strong coupling anchoring effect with the inorganic material of the concrete layer, significantly improving the bonding force of the interface agent.

[0090] Step 2: After the ancient building wall is prepared, the ancient building wall is hoisted. Specifically, it includes: (1) crane support (2) wall hoisting into place; (3) diagonal brace setting; (4) wall correction; (5) bottom and top bolt adjustment and tightening; (6) grouting of connection parts; (7) review and acceptance.

[0091] Furthermore, before hoisting the prefabricated components, it is necessary to check whether the upper and lower elevations of the wall installation position meet the design requirements, whether the size of the ground beam of the lower structure of the wall is correct, whether the upper surface is flat, and whether the position of the embedded parts reserved for the ground beam is accurate. If there is any deviation, measures should be taken to adjust it in time.

[0092] Step 3: After the hoisting is completed, the wall of the ancient building is treated; the wall treatment steps mainly involve covering the wall connectors, caulking the wall joints, post-installation of stones, treatment of the external wall connection parts, and masonry construction of the non-prefabricated part of the wall. Specifically include: (1) wall review and acceptance; (2) welding of angle steel on the upper part of the wall; (3) stone installation; (4) cleaning of board joints and brick joints; (5) caulking of board surfaces and connectors; the specific process of caulking of board surfaces and connectors is to fill with polyurethane foam glue and apply cement mortar; (6) brick masonry at the joints; (7) masonry of ice tray eaves and mountain peaks; (8) overall wall grouting; (9) wall jointing. After the overall wall jointing, there is a specific step of softening the core wall. After the wall jointing, it also includes (10) repair or grouting.

[0093] Among them, the dotting repair in step three (10) is mainly for dry-laid walls. After the dry-laid walls are built, they need to be repaired, including dry work, dotting, flooding and flushing. Dry work: Use a grinding head to grind the raised parts of the joints between bricks. Dotting: Use brick ash (brick medicine) to fill the broken parts of the bricks and the sand holes on the bricks. Flooding: Use a grinding head dipped in water to grind the dotted areas and the areas where the dotting has been done, and then dip in water to rub the entire wall surface to achieve consistency in color and texture. Flushing: Use clean water and a soft brush to clean and rinse the entire wall surface to show the "real bricks and real seams". Flushing should be arranged after the wall is completed and before the scaffolding is removed to avoid dirtying the wall surface due to construction.

[0094] Among them, the spotting of the seams in step 3 (10) is mainly for whitewashed walls. The mortar seams of whitewashed walls need to be controlled at 4-6mm. During wall processing, a 5mm fixed-size sponge strip is used to control the mortar seams. After the wall is installed and fixed, the sponge strip is removed to perform the spotting of the wall seams. Dark moon white ash or old slurry ash should be used for spotting the seams of whitewashed walls, and small hemp ash should be used, that is, the hemp content in the ash should be appropriately reduced and the hemp should be cut short.

[0095] How to fill the gaps: Use a tile trowel, a small wooden stick or a nail to scratch along the brick joints, and then use a special tool "duckbill" or a small roller to "feed" the small hemp ash into the brick joints. The ash should be leveled with the brick wall and rolled flat. Then use a short-bristled brush with a small amount of clean water to brush along the brick joints. This can not only make the ash adhere more firmly, but also keep the brick edges clean.

[0096] Furthermore, before wall treatment, the wall installation elevation should be checked to see if it is correct, the wall surface is flat, the prefabricated wall joints are straight, and there is enough space for stone installation. The wall treatment construction can only be carried out after the wall installation quality is completed and accepted. Before wall treatment, the sponge strips and sponge blocks used in wall production should also be cleaned.

[0097] The technical solution of the invention is described in detail below in conjunction with specific embodiments.

[0098] Example 1 Preparation of epoxy type interface agent

[0099] The interface agent is prepared by mixing component A and component B in a weight ratio of 6:1;

[0100] Component A comprises the following components in parts by weight: 60 parts of epoxy acrylic resin, 15 parts of active diluent, 5 parts of auxiliary agent, 20 parts of conventional diluent A, and 20 parts of filler.

[0101] The active diluent is a combination of 1,4-butanediol diglycidyl ether and butyl glycidyl ether in a mass ratio of 1:1, each of which is 7.5 parts. The auxiliary agents are 1 part of wetting agent, 0.5 part of leveling agent, 1 part of defoaming agent, 2 parts of dispersant, and 0.5 part of fumed silica anti-settling agent.

[0102] The filler includes 7.5 parts of silicon micropowder, 7.5 parts of talc powder and 5 parts of titanium dioxide.

[0103] Component B comprises: 15 parts of a curing agent, 5 parts of a conventional diluent B, and a mixture of polyamide and γ-aminopropyltriethoxysilane in a mass ratio of 9:1.

[0104] Conventional diluent A and conventional diluent B are both propylene glycol methyl ether acetate.

[0105] The epoxy acrylic resin is prepared by free radical copolymerization of trimethylolpropane trimethacrylate, glycidyl methacrylate and γ-methacryloxypropyl trimethoxysilane in a mass ratio of 2:5:0.5. The specific preparation method comprises dissolving the three monomers in an organic solvent system under stirring, heating after they are completely dissolved, adding an initiator, and reacting for 4 hours in a reflux manner to obtain an epoxy acrylic resin solution.

[0106] The preparation method of the interface agent comprises the following steps:

[0107] (1) mixing and stirring the epoxy acrylic resin, reactive diluent, auxiliary agent, and conventional diluent A in a high-speed disperser to obtain a mixture;

[0108] (2) adding filler to the mixture obtained in step (1) while stirring to obtain component A;

[0109] (3) The curing agent and conventional diluent B are mixed and stirred using a disperser to obtain component B. When in use, component A and component B are blended again.

[0110] In step (1), the rotation speed of the disperser is 800 rpm, and the stirring time is 20 min.

[0111] In step (2), the rotation speed of the disperser is 1200 rpm, and the stirring time is 40 min.

[0112] The speed of the disperser in step (3) is 600 rpm, and the stirring time is 8 min.

[0113] Example 2 Preparation of assembled ancient building threshold wall A

[0114] The thickness of the prefabricated ancient building threshold wall is 270mm, specifically including a 40mm thick small mud brick layer, a 50mm thick concrete outer page layer, an 80mm thick extruded polystyrene board insulation layer and a 100mm thick lightweight aggregate concrete structural wall inner page layer, which includes the following steps:

[0115] 1) Mold cleaning;

[0116] 2) Brick arrangement, specifically, dry brick arrangement on the wall is adopted, and the seams are plugged with sponge strips to obtain a face brick layer, and the face brick layer is grooved, and the cross-sectional shape of the groove is a trapezoidal structure, which is a type of wide at the bottom and narrow at the top;

[0117] 3) Cement mortar filling;

[0118] 4) applying the epoxy interface agent prepared in Example 1;

[0119] 5) Lay the first layer of steel bars and set the upper and lower layer steel bar tie embedded parts;

[0120] 6) pouring concrete outer page to obtain outer page layer;

[0121] 7) Laying the insulation layer;

[0122] 8) Lay the second layer of steel bars, connect the first and second layers of steel bars, and pre-embed water and electricity pipelines, hoisting parts, and connectors;

[0123] 9) Casting lightweight aggregate concrete inner wall layer;

[0124] 10) Wall demoulding, maintenance and acceptance.

[0125] Example 3 Preparation of assembled ancient building threshold wall B

[0126] Except that in step 2), when the facing brick layer is grooved, the cross-sectional shape of the groove is a rectangular structure, and the other preparation methods are the same.

[0127] Example 4 Preparation of assembled ancient building threshold wall C

[0128] Except that the facing brick layer is not grooved in step 2), the other preparation methods are the same.

[0129] Example 5 Preparation of assembled ancient building threshold wall D

[0130] Except that the interface agent used in step 4) is a common interface agent purchased on the market, the other preparation methods are the same.

[0131] Example 6 Preparation of assembled ancient building threshold wall E

[0132] Except that the facing brick layer is not grooved in step 2) and the interface agent used in step 4) is a common interface agent purchased on the market, the other preparation methods are the same.

[0133] Example 7 Construction technology of assembled ancient building threshold wall

[0134] Step 1: Use Example 2 to make the wall, the wall weight is 1.5 tons; Step 2: Wall hoisting; Step 3: Wall surface treatment;

[0135] Step 2 Wall hoisting steps specifically include: 1) Crane support; 2) Wall hoisting in place; 3) Diagonal brace setting; 4) Wall correction; 5) Adjustment and tightening of bottom and top bolts; 6) Grouting of connection parts; 7) Review and acceptance;

[0136] Step 3 Wall treatment steps specifically include: 1) Wall review and acceptance; 2) Welding of angle steel on the upper part of the wall; 3) Installation of stone materials; 4) Cleaning of board joints and brick joints; 5) Filling of board surfaces and connectors, filling with polyurethane foam, and plastering with cement mortar; 6) Laying of bricks at joints; 7) Laying of ice tray eaves and mountain peaks; 8) Jointing of the entire wall; 9) Tillage of wall joints; 10) Pointing and repair, including dry work, point-finishing, flooding and flushing. Dry work: Use a grinding head to smooth the raised part of the joint between bricks. Point-finishing: Use brick face ash (brick medicine) to fill the incomplete parts of the bricks and the sand holes on the bricks. Flooding: Use a grinding head dipped in water to smooth the dotted areas and the areas where the dry work has been done, and then dip in water to rub the entire wall surface again to achieve consistency in color and texture. Flushing: Use clean water and a soft brush to clean and rinse the entire wall surface to show the "real bricks and solid seams". Flushing should be done after the wall is completed and before the scaffolding is removed to avoid dirtying the wall surface due to construction.

[0137] Performance Testing

[0138] The assembled ancient building sill wall AE prepared in Examples 2-6 was subjected to hoisting and moving bonding strength tests and water and alkali resistance tests.

[0139] For the bonding strength, it mainly depends on whether there are obvious cracks or even complete cracks during the lifting and moving process. The water resistance and alkali resistance are to observe whether the interface layer is obviously whitened or bubbling after the wall is stored for three months. The specific performance results of the test side are shown in Table 1

[0140] Table 1 Performance test results of prefabricated ancient building sill wall

[0141] Example Threshold wall Bonding effect Water resistance Example 2 Prefabricated ancient building threshold wall A Excellent, no cracks good Example 3 Prefabricated ancient building threshold wall B Excellent, very few fine cracks good Example 4 Prefabricated ancient building threshold wall C Generally, there are a few cracks good Example 5 Prefabricated ancient building threshold wall D Generally, there are a few cracks Slight whitening Example 6 Prefabricated ancient building threshold wall E Failed, fell off Slight whitening

Claims

1. A construction process for an assembled ancient building wall, characterized in that: The prefabricated ancient building wall comprises, from the outer wall to the inner wall, a 30-50mm thick brick layer, a 40-60mm thick concrete outer layer, a 60-100mm thick insulation layer and an 80-120mm thick concrete structural wall inner layer. The wall is a sill wall, a gable wall or a rear eaves wall. The thickness of the prefabricated ancient building wall is 250-300mm. The insulation material of the insulation layer is an extruded polystyrene board or a foamed polystyrene board, and specifically comprises the following steps: Step 1: wall production; Step 2: wall hoisting; Step 3: wall surface treatment; Among them, in step 1, in the wall production, the weight of the wall produced is 1.4-1.6 tons, and step 1, in the wall production, includes the following steps: (1) Mold cleaning; (2) Arrange the bricks and fill the seams with sponge strips to obtain the facing brick layer, and make grooves on the side of the facing brick layer close to the outer layer of concrete. The cross-sectional shape of the groove is square, rectangular or trapezoidal; (3) Filling joints with cement mortar; (4) Applying an interface agent on the side of the tile layer close to the outer layer of the concrete, wherein the interface agent is prepared by mixing component A and component B in a weight ratio range of (4-6):1; component A comprises the following components in weight: 60-80 parts of epoxy acrylic resin, 10-20 parts of active diluent, 5-10 parts of auxiliary agent, 10-30 parts of conventional diluent A, and 20-30 parts of filler; component B comprises: 10-30 parts of curing agent and conventional diluent B; the auxiliary agent includes a wetting agent, a leveling agent, a defoaming agent, a dispersant, and an anti-settling agent; wherein the epoxy acrylic resin is prepared by free radical copolymerization of a first monomer, a second monomer, and a third monomer; the first monomer is an acrylate monomer having three or more unsaturated carbon-carbon double bonds; the second monomer is a monomer having an unsaturated carbon-carbon double bond and an epoxy group; the third monomer is γ-methacryloxypropyltrimethoxysilane; the mass ratio of the first monomer, the second monomer, and the third monomer is 2:(4-6):(0.4-0.6); (5) Lay the first layer of steel bars and install the upper and lower layer steel bar tie embedded parts; (6) pouring concrete to obtain an outer concrete layer; (7) Laying the insulation layer; (8) Lay the second layer of steel bars, connect the first layer of steel bars with the second layer of steel bars, and pre-embed water and electricity pipelines, lifting parts, and connectors; (9) Casting the inner layer of the concrete structure wall; (10) Wall demoulding, maintenance and acceptance; Among them, step 2 of wall hoisting includes: 1) crane support; 2) wall hoisting in place; 3) diagonal brace setting; 4) wall correction; 5) bottom and top bolt adjustment and tightening; 6) grouting of connection parts; 7) review and acceptance; Among them, step three wall treatment includes: 1) wall review and acceptance; 2) welding of angle steel on the upper part of the wall; 3) stone installation; 4) cleaning of board joints and brick joints; 5) caulking of board surfaces and connectors; 6) laying of facing bricks at joints; 7) laying of ice tray eaves and mountain peaks; 8) grouting of the entire wall; 9) tilling of wall joints.

2. The construction process according to claim 1, characterized in that: In step 2, 5) the diagonal brace setting process can be advanced to 2) after the wall is hoisted into place, and 3) before the wall is corrected.

3. The construction process according to claim 1, characterized in that: In step 3 (5), the specific process for filling the joints on the board surface and connecting parts is to fill with polyurethane foam and apply cement mortar.

4. The construction process according to claim 1, characterized in that: In step three (8), after grouting the entire wall, there are specific steps to soften the core wall.

5. The construction process according to claim 1, characterized in that: Step three 9) after wall jointing also includes 10) making repairs or filling the joints.

6. The construction process according to claim 5, characterized in that: Step 3 (10) The spot repair is mainly for dry-slab walls. Repairs are carried out after the dry-slab walls are built, which include dry work, spot repair, flooding work and flushing.

7. The construction process according to claim 6, characterized in that: The manual work includes grinding the raised parts of the joints between bricks with a grinding head.

8. The construction process according to claim 6, characterized in that: The dotting includes filling the incomplete parts of the bricks and the sand holes on the bricks with brick mortar.

9. The construction process according to claim 6, characterized in that: The flooding work includes using a grinding head dipped in water to smooth the marked areas and the areas where the work has been done, and then dipping the grinding head in water to rub the entire wall surface again to achieve consistency in color and texture.

10. The construction process according to claim 6, characterized in that: The flushing includes cleaning and rinsing the entire wall surface with clean water and a soft brush to reveal "real bricks and real seams". The flushing is performed after the wall is completely completed and before the scaffolding is removed.

Citation Information

Patent Citations

  • Waste brick veneer prefabricated heat-insulating external wall panel and manufacturing method thereof

    CN106499088A

  • Design and construction method of fabricated antique building steel structure board room system