Energy pile bionic fan blade deicing device and deicing method thereof
Through the energy pile bionic wind turbine blade de-icing device, the geothermal energy is converted into de-icing water and transferred to the blades using the hub heating circuit. This solves the performance degradation and safety hazard problems caused by ice on the wind turbine blades, and achieves efficient and energy-saving de-icing. The effect is to avoid high energy consumption and secondary pollution in traditional technology.
Patent Information
- Application Number
- CN202410415873.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-08
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-04-08
AI Technical Summary
Existing wind turbine blades freeze in cold and humid environments, leading to performance degradation and safety hazards. Traditional de-icing technology has problems such as high energy consumption, physical damage and secondary pollution.
The energy pile bionic fan blade de-icing device is used to convert geothermal energy into de-icing water through the geothermal energy extraction circuit and the heat pump unit circulation circuit. The hub heating circuit is used to transfer heat to the blades for de-icing, achieving an efficient and energy-saving de-icing effect.
It reduces wind power operating costs and safety hazards, avoids secondary pollution, and provides a more stable de-icing effect without affecting the safety and life of the blades.
Smart Images

Figure CN118423240B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of wind power generation equipment, and in particular to an energy pile bionic wind turbine blade deicing device and a deicing method thereof. Background Art
[0002] Wind energy is a renewable and clean energy source. Its role in alleviating dependence on fossil energy, reducing environmental pollution and preventing global climate change has been widely recognized. In order for the blades of horizontal-axis wind turbines to rotate in one direction around the horizontal under wind load to drive the wind turbine to convert wind energy into electrical energy, the design of the blade shape refers to the principle of bird wings. The thickness of the wind blade gradually decreases from the windward leading edge to the trailing edge, and also gradually decreases from the root to the tip of the blade. The curvature of the windward side is greater than the curvature of the leeward side to ensure that the air pressure on the windward side is less than the air pressure on the leeward side so that the blade rotates in a fixed direction. When the wind turbine is in a high-altitude environment with cold climate and high humidity, especially in winter or high altitude areas, the moisture in the low temperature environment will freeze on the surface of the blade. This situation has a huge impact on the performance and safety of the wind turbine. Icing will change the aerodynamic shape of the wind turbine blade, reduce its power generation efficiency, and may even cause the unit to shut down. At the same time, due to the weight of ice, the burden on the blade will increase, which may cause the blade to break, seriously endangering the safety of the wind farm.
[0003] Therefore, the de-icing technology of wind turbine blades has become an important research topic in the field of wind power. The current development of these technologies includes but is not limited to: 1) Mechanical de-icing: mechanical means such as vibration or impact are used to remove the ice layer. Traditional mechanical de-icing technology has problems of physical damage, safety issues and high maintenance costs. Traditional de-icing tools will cause certain scratches, splits and even cracks on the surface of the blades. Long-term use will affect the life of the blades and have an irreversible impact on the performance and efficiency of the blades. Mechanical de-icing requires the use of high-power machinery and equipment, which consumes relatively large power. In addition, the high speed will also physically impose a huge mechanical load on the blade surface, which also brings high energy consumption problems. 2) Hot air de-icing: The ice layer is melted by heating elements inside the blades, such as heating coils. 3) Electric de-icing: Electric heating tape or heating film is used to cover the surface of the blades, and ice accumulation is prevented or removed by resistive heating. However, the traditional heating de-icing process consumes a lot of energy, which will increase the cost of wind power generation. Especially when heating and deicing are performed under long-term low temperature conditions, energy loss will be more serious. The electric heating wires used will generate extremely high heat and electromagnetic field interference to the equipment, and there are certain fire and safety hazards. 4) Super-hydrophobic coating: Super-hydrophobic materials are applied to the surface of the fan blades to reduce water adhesion and form ice layers. Under extreme snowfall and cold climate conditions, such as severe freezing rain and freezing snow, the deicing effect of the super-hydrophobic coating cannot be fully guaranteed, and other deicing technologies need to be introduced to supplement it. In addition, it is subject to long-term collision and erosion by wind and sand, which may cause the coating to be scratched or scratched, resulting in failure and loss. In addition, the fallen super-hydrophobic material will be deposited or combined under certain conditions to form new pollutants, leading to secondary pollution.
[0004] Influenced by technological progress and environmental requirements, the efficiency and cost optimization of these technologies, as well as the search for more environmentally friendly and sustainable solutions, remain the focus of future technological development, aiming to improve the anti-icing performance of wind turbine blades, ensure the stable and safe operation of wind turbines, and thus improve the overall economic benefits of wind farms. To this end, it is particularly important to propose a deicing device and method that is highly efficient, energy-saving, has no secondary pollution, and does not affect blade safety. Summary of the invention
[0005] In view of the above problems in the prior art, the present invention provides an energy pile bionic fan blade deicing device and a deicing method thereof, which solves the problem in the prior art of lacking a deicing device that is efficient and energy-saving, has no secondary pollution and does not affect the safety of the blades.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is as follows:
[0007] On the one hand, an energy pile bionic wind turbine blade de-icing device includes a wind tower, characterized in that the wind tower includes: a geothermal energy extraction circuit, the geothermal energy extraction circuit includes a plurality of energy piles located in the foundation of the wind tower; a heat pump unit circulation circuit, the heat pump unit circulation circuit is arranged inside the tower of the wind tower, and is connected to the geothermal energy extraction circuit, for improving the energy grade of geothermal energy; a hub heating circuit, the hub heating circuit is arranged inside the tower, the nacelle and the hub, and is connected to the heat pump unit circulation circuit, for transferring geothermal energy to the hub of the wind tower; a blade de-icing circuit, the blade de-icing circuit is arranged in a plurality of blades of the wind tower, and is connected to the hub, for heating each blade by geothermal energy.
[0008] The working principle of this scheme is to extract geothermal energy through multiple energy piles in the geothermal energy extraction loop, and use the heat pump unit circulation loop to improve the energy grade of geothermal energy, convert geothermal energy into deicing water, and transfer the heat of deicing water to the hub of the wind turbine through the hub heating loop, so that the hub uses heated air or high-temperature deicing water to de-ice the blades through the blade deicing loop. Compared with mechanical deicing and electric deicing in the prior art, this scheme reduces energy consumption, reduces the operating cost and safety hazards of wind power, and has the effect of energy saving and efficiency improvement. And compared with the super-hydrophobic coating in the prior art, the deicing effect of this scheme is more stable and there is no secondary pollution.
[0009] Furthermore, the geothermal energy extraction loop also includes a ground source side circulation pump and a ground source side manifold located on the foundation of the wind turbine tower. The ground source side circulation pump, the ground source side manifold and multiple energy piles are connected through a ground source side water pipe. In this solution, water or other liquids are used as the circulating medium. The circulating medium enters the heat exchange tube in the energy pile under the action of the ground source side circulation pump. Since the underground temperature is relatively constant and higher than the surface temperature of the wind turbine tower in winter, the circulating medium absorbs the geothermal energy in the shallow underground layer and brings the geothermal energy back to the ground source side manifold, thereby completing the extraction of geothermal energy.
[0010] Furthermore, the circulation loop of the heat pump unit includes an evaporator connected to the geothermal energy extraction loop, the evaporator is connected to the compressor and the expansion valve respectively, the other ends of the compressor and the expansion valve are connected to the condenser, and the water outlet pipe of the condenser is connected to the wind power auxiliary hot water tank. In this scheme, the evaporator, condenser, compressor, and expansion valve are used to complete the reverse Carnot cycle to convert low-grade geothermal energy into high-grade deicing water. At the same time, the temperature of the deicing water after the condenser completes the condensation and heat dissipation process can be detected by a temperature detector. If the deicing water temperature cannot meet the deicing requirements, the wind power auxiliary hot water tank can be started, and the electricity generated by the wind turbine tower is used as the power supply of the wind power auxiliary hot water tank to heat the deicing water.
[0011] Furthermore, the hub heating circuit includes a deicing side circulation pump connected to the water outlet of the condenser, and the deicing side circulation pump is connected to the sealing slip ring, the fan coil unit, the air conditioning equipment and the return water end of the condenser in sequence through the heating water pipe circuit; the sealing slip ring is arranged on the rotor main shaft in the cabin, the fan coil unit is arranged inside the inner cabin, and the air conditioning equipment is fixed to the inner bottom of the tower. The heating water pipe circuit of the yaw platform section at the top of the tower should adopt a hose to facilitate synchronous rotation during the steering process of the cabin and ensure the connectivity of the heating water pipe circuit. In this scheme, the hub heating circuit transfers the heat of the deicing water to the hub and completes the recovery of the deicing water.
[0012] Furthermore, the sealing slip ring includes a slip ring outer ring fixed in the cabin, a slip ring inner ring is rotatably arranged in the inner ring of the slip ring outer ring, and the inner ring of the slip ring inner ring is fixed on the rotor main shaft in the cabin; multiple water guide channels are arranged on the slip ring outer ring and the slip ring inner ring, and sealing rings are arranged at both ends of each water guide channel; the multiple water guide channels on the slip ring outer ring are connected to the fan coil unit; the multiple water guide channels on the slip ring inner ring are connected to the heating water pipe circuit. In this solution, the setting of the sealing slip ring realizes the circulation of deicing water during the free rotation of the hub, and the number of water guide channels can be appropriately adjusted to meet the flow and pressure requirements of the deicing water.
[0013] Furthermore, a heat-insulating partition is provided in the hub, which divides the hub into an inner cabin and an outer cabin. The fan coil unit group includes three fan coils located in the inner cabin, and the inner cabin is connected to three blades on the wind turbine tower through the supply and return air ducts respectively; each blade is hollow inside, and each blade and each supply and return air duct are provided with S-shaped ribs along their axial direction. The ribs in the blade divide the inside of the blade into a supply air chamber and a return air chamber that are connected; the ribs in the supply and return air duct divide its inside into a supply air chamber and a return air chamber, and the supply air chamber and the return air chamber are connected to the supply air chamber and the return air chamber respectively; and the supply air chamber and the return air chamber are close to the leading edge and the trailing edge of the blade respectively. Each supply and return air duct is cylindrical and has openings at both ends; one end of the supply and return air duct is provided on the heat-insulating partition through a bearing, and the other end of the supply and return air duct is hemispherical and connected to the root of the blade; a rotating gear is provided at the connection between the supply and return air duct and the blade, and the rotating gear is meshed and connected with the output gear on the steering motor located in the hub. Since the angle at which each blade is installed on the hub needs to be adjusted in real time according to the local wind direction and wind speed to maximize the acquisition of wind resources, the supply and return air ducts and blades of this solution are simultaneously meshed and connected with the output gears on the steering motor, ensuring that the supply air duct and the supply air chamber, and the return air duct and the return air chamber can always remain connected to ensure heat circulation.
[0014] In this solution, the fan coil unit is set up to facilitate the heat of the de-icing water to be better dissipated into the air of the hub, so that hot air is formed in the hub. The hot air enters the air supply cavity through the air supply tube, and the hot air exchanges heat with the ice on the wall of the air supply cavity to become cold air. The cold air is discharged from the outer cabin through the return air cavity and the return air tube, completing the heat transfer cycle and effectively removing the ice on the leading edge of the blade. The S-shaped setting of the ribs can optimize the volume of the air supply cavity and the return air cavity in the blade, and the rounded corners on the ribs can simultaneously avoid the interference of the edges and corners on the wind field in the blade, reducing the vibration of the fan blade caused by the airflow.
[0015] Furthermore, the blade deicing circuit includes a plurality of phase-change heat rods located in the air supply cavity, each phase-change heat rod includes a heat absorption section, a heat insulation section and a heat dissipation section connected in sequence; the heat absorption section extends into the inner cabin through the air supply tube, the heat dissipation section extends to the inner part of the blade near the tip, and a plurality of heat dissipation ribs fixed on the inner wall of the air supply cavity are arranged on the heat dissipation section. The cross section of the phase-change heat rod is divided into three layers from the outside to the inside: a closed pipe, a capillary core, and a hollow cavity. In this scheme, liquid ammonia, acetone or Freon thermosensitive materials that can undergo phase change are contained in the heat absorption section, and the thermosensitive materials in the heat absorption section are vaporized into a gas state after absorbing heat and migrate to the heat dissipation section. After the heat of the heat dissipation section is absorbed by the ice layer attached to the surface of the blade tip, the thermosensitive material inside the heat dissipation section condenses into a liquid state and then migrates back to the heat absorption section by overcoming gravity with the help of the capillary force in the capillary core. The setting of the phase-change heat rod is conducive to heat transfer between the hub and the blade.
[0016] Furthermore, the blade deicing circuit includes a bionic heat dissipation network located in the inner cavity of the blade, and the bionic heat dissipation network is arranged on the windward side and the leeward side of the inner wall of the blade; the bionic heat dissipation network is distributed in the shape of leaf veins, and includes a main vein, which is connected to multiple side veins, and each side vein is connected to multiple capillary veins. The bionic heat dissipation network has a leaf vein-like structure that can more evenly distribute heat transfer media such as coolant or air, ensuring that the entire heat dissipation process is more balanced and effective, avoiding local overheating or uneven cooling, and making the leaf vein structure have good mechanical properties and reducing weight while ensuring structural stability and strength.
[0017] On the other hand, a method for operating an energy pile bionic wind turbine blade deicing device is provided, comprising the steps of:
[0018] S1. Using multiple energy piles in a geothermal energy extraction loop to extract geothermal energy, and using a heat pump unit circulation loop to convert geothermal energy into de-icing water with a higher energy grade than the geothermal energy;
[0019] S2, using a hub heating circuit to transfer the heat of the de-icing water to the hub of the wind turbine tower;
[0020] S3. A blade de-icing circuit is used to transfer heat from the hub to the inner cavity of each blade on the wind turbine tower to melt the ice on the blade.
[0021] Further, step S3 includes any of the following steps:
[0022] S31, dividing the inner cavity of each blade into a connected air supply cavity and a return air cavity, and transferring the heat in the hub to the air supply cavity and the return air cavity in sequence using air as a medium;
[0023] S32, dividing the inner cavity of each blade into a connected air supply cavity and a return air cavity, and providing at least one phase change heat rod in the air supply cavity, and transferring the heat in the hub to the air supply cavity and the return air cavity in sequence using the phase change heat rod as a medium;
[0024] S33, a bionic heat dissipation network is set in the inner cavity of each blade, and connected to the heating water pipe loop in the wheel hub, and heat is transferred to the bionic heat dissipation network in sequence using deicing water as the medium.
[0025] The present invention discloses an energy pile bionic fan blade deicing device and an operation method thereof, and the beneficial effects thereof are:
[0026] 1. This solution uses geothermal energy to generate hot air to de-ice the blades. Compared with mechanical de-icing and electric de-icing in the prior art, it reduces energy consumption, reduces the operating cost and safety hazards of wind power, and has the effect of energy saving and efficiency improvement.
[0027] 2. This solution uses clean shallow geothermal energy and does not require the use of electricity or chemicals. Compared with the super-hydrophobic coating in the existing technology, this solution has a more stable deicing effect and will not cause secondary pollution to the environment at all, making it environmentally friendly.
[0028] 3. This solution realizes the circulation of de-icing water during the free rotation of the hub and blades by setting up a sealing slip ring and a return air duct, thereby improving the problem of twisting and tangling of water pipes during the free rotation of the nacelle, hub and blades in the existing geothermal de-icing device technology, avoiding the additional load on the blades caused by the internal pipes of the blades in the existing technology, and will not cause damage to the blades, thus avoiding damage to the blades caused by mechanical vibration and impact. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 This is the schematic diagram of the energy pile bionic fan blade deicing device;
[0030] Figure 2 It is a schematic diagram of the structure of the blade deicing device;
[0031] Figure 3 It is a schematic diagram of the structure for fixing the water supply riser and the tower;
[0032] Figure 4 This is a top view schematic diagram of the fixation of the water supply riser and the tower.
[0033] Figure 5 Schematic diagram of the connection between the nacelle and the hub.
[0034] Figure 6 A half-section diagram of a sealing slip ring.
[0035] Figure 7 It is a schematic diagram of the structure of the hub and the return air duct.
[0036] Figure 8 Schematic diagram of the connection between the return air duct and the blades.
[0037] Fig. 9 Schematic diagram of the connection between the hub and the blades.
[0038] Fig.10 Schematic diagram of the leaf.
[0039] Fig.11 A schematic cross-sectional view of a blade.
[0040] Fig.12 Schematic diagram of the bionic heat dissipation network.
[0041] Among them: 1. geothermal energy extraction loop; 11. energy pile; 12. ground source side circulation pump; 13. ground source side water pipe; 131. ground source side water supply pipe; 132. ground source side water return pipe; 14. ground source side manifold;
[0042] 2. Heat pump unit circulation loop; 21. Evaporator; 22. Condenser; 23. Heat pump loop water pipe; 24. Compressor; 25. Expansion valve; 26. Wind power auxiliary hot water tank;
[0043] 3. Hub heating circuit; 31. Fan coil unit; 32. De-icing side circulation pump; 33. Heating water pipe circuit; 3311. Water supply riser; 3312. Water return riser; 3321. Water supply hose; 3322. Water return hose; 3331. Water supply auxiliary pipe; 3332. Water return auxiliary pipe; 34. Flow valve; 35. Air conditioning equipment;
[0044] 4. Blade deicing circuit; 41. Blade; 411. Leading edge; 412. Trailing edge; 413. Blade root; 414. Blade tip; 415. Air supply cavity; 416. Air return cavity; 417. Rotating gear; 42. Phase change heat rod; 421. Heat absorption section; 422. Heat insulation section; 423. Heat dissipation section; 424. Heat dissipation ribs; 43. Ribs; 44. Bionic heat dissipation pipe network; 441. Main vein; 442. Side veins; 443. Capillary veins;
[0045] 5. Hub; 51. Inner cabin; 52. Outer cabin; 53. Supply and return air duct; 531. Bearing; 532. Supply air duct; 533. Return air duct; 54. Rotor main shaft; 55. Steering motor;
[0046] 6. Cabin; 61. Cabin base; 62. Cabin shell; 63. Sealing slip ring; 631. Slip ring outer ring; 632. Slip ring inner ring; 633. Water channel; 634. Sealing ring;
[0047] 7. Tower; 71. Substation; 72. Support; 73. Buckle; DETAILED DESCRIPTION
[0048] The specific implementation modes of the present invention are described below so that those skilled in the art can understand the present invention. However, it should be clear that the present invention is not limited to the scope of the specific implementation modes. For those of ordinary skill in the art, as long as various changes are within the spirit and scope of the present invention as defined and determined by the attached claims, these changes are obvious, and all inventions and creations utilizing the concept of the present invention are protected.
[0049] Example 1
[0050] refer to Figures 1 to 12 The present embodiment provides an energy pile bionic wind turbine blade deicing device, including a wind turbine tower, which includes a geothermal energy extraction loop 1, a heat pump unit circulation loop 2, a hub heating loop 3 and a blade deicing loop 4.
[0051] Specifically, the geothermal energy extraction loop 1 is used to extract geothermal energy, and includes a plurality of energy piles 11 , a ground source side circulation pump 12 , a ground source side water pipe 13 and a ground source side manifold 14 .
[0052] refer to Figure 1 and Figure 2 , multiple energy piles 11 are fixed inside the foundation of the power tower to extract geothermal energy. The ground source side circulation pump 12 and the ground source side manifold 14 are arranged on the foundation of the wind power tower, and the ground source side circulation pump 12, the ground source side manifold 14 and multiple energy piles 11 are connected through the ground source side water pipe 13. The ground source side water pipe 13 includes a ground source side water supply pipe 131 and a ground source side water return pipe 132 which are respectively connected to the water outlet and water inlet of the energy pile 11.
[0053] In the geothermal energy extraction loop 1, water or other liquids are used as circulating media. The circulating media enters the heat exchange tubes in the energy pile 11 under the action of the ground source side circulation pump 12. Since the underground temperature is relatively constant and higher than the surface temperature of the wind tower in winter, the circulating medium absorbs geothermal energy located in the shallow underground layer and brings the geothermal energy back to the ground source side manifold 14, thereby completing the extraction of geothermal energy.
[0054] Specifically, the heat pump unit circulation loop 2 is arranged inside the tower 7, the nacelle 6 and the hub 5 of the wind power tower, and is connected to the geothermal energy extraction loop 1 to improve the energy quality of geothermal energy.
[0055] refer to Figure 1 and Figure 2 The heat pump unit circulation loop 2 includes an evaporator 21, a condenser 22, a heat pump loop water pipe 23, a compressor 24, an expansion valve 25 and a wind power auxiliary hot water tank 26. The water inlet and outlet on one side of the evaporator 21 are respectively connected to the ground source side water collector 14 and the water inlet of the energy pile 11; the water inlet and outlet on the other side of the evaporator 21 are respectively connected to the compressor 24 and the expansion valve 25. The other ends of the compressor 24 and the expansion valve 25 are both connected to the condenser 22, and the water outlet pipe of the condenser 22 is connected to the wind power auxiliary hot water tank 26, and the wind power auxiliary hot water tank 26 is electrically connected to the battery located in the inner wall of the tower 7.
[0056] In the heat pump unit circulation loop 2, the evaporator 21, the condenser 22, the compressor 24, and the expansion valve 25 are used to complete the reverse Carnot cycle, and the low-grade geothermal energy is converted into high-grade deicing water. At the same time, a temperature detector can be installed on the outlet pipe of the condenser 22. The temperature detector is used to detect the temperature of the deicing water after the condenser 22 completes the condensation and heat dissipation process. If the deicing water temperature cannot meet the deicing requirements, the wind power auxiliary hot water tank 26 can be started, and the electricity generated by the wind power tower is used as the power supply of the wind power auxiliary hot water tank 26 to heat the deicing water.
[0057] Specifically, the hub heating circuit 3 is arranged on the inner wall of the tower 7 and is connected to the heat pump unit circulation circuit 2. The hub heating circuit 3 is used to transfer the heat of the deicing water to the hub 5 and complete the recovery of the deicing water.
[0058] refer to Figure 1 and Figure 2 The hub heating circuit 3 includes a deicing side circulation pump 32 connected to the outlet pipe of the condenser 22, and the deicing side circulation pump 32 is connected to the sealing slip ring 63, the fan coil unit, the air conditioning equipment 35 and the return water end of the condenser 22 through the heating water pipe circuit 33; the sealing slip ring is arranged on the rotor main shaft 54 in the nacelle 6, the fan coil unit is arranged inside the inner cabin 51, and the air conditioning equipment 35 is fixed to the inner bottom of the tower 7. The three fan coils 31 of the fan coil unit are connected in parallel, and the hub heating circuit 3 is connected in parallel with the air conditioning equipment 35 for heating and cooling the tower transformer substation 71.
[0059] Specifically, the blade deicing circuit 4 is disposed in a plurality of blades 41 of the wind turbine tower and is in communication with the hub 5 for heating each blade 41 by geothermal energy.
[0060] The working principle of this embodiment is to extract geothermal energy through multiple energy piles 11 in the geothermal energy extraction loop 1, and use the heat pump unit circulation loop 2 to improve the energy grade of geothermal energy, convert geothermal energy into deicing water, and the heat of the deicing water is transferred to the hub 5 of the wind tower through the hub heating loop 3, so that the hub 5 deices the blades 41 through the blade deicing loop 4 by heating air. Compared with mechanical deicing and electric deicing in the prior art, this solution reduces energy consumption, reduces the operating cost and safety hazards of wind power, and has the effect of energy saving and efficiency improvement. And compared with the super hydrophobic coating in the prior art, the deicing effect of this solution is more stable and there is no secondary pollution.
[0061] As a further solution of this embodiment, refer to Figure 5-6 The sealing slip ring 63 includes a slip ring outer ring 631 fixed in the nacelle 6, a slip ring inner ring 632 is rotatably arranged in the inner ring of the slip ring outer ring 631, and the inner ring of the slip ring inner ring 632 is fixed on the rotor main shaft 54 in the shell 62 of the nacelle 6; a plurality of water guide channels 633 are arranged on the slip ring outer ring 631 and the slip ring inner ring 632, and a sealing ring 634 is arranged at both ends of each water guide channel 633; the plurality of water guide channels 633 on the slip ring outer ring 631 are connected to the fan coil unit; the plurality of water guide channels 633 on the slip ring inner ring 632 are connected to the heating water pipe loop 33. In this solution, the setting of the sealing slip ring 63 realizes the circulation of the deicing water during the free rotation of the hub 5, and the number of the water guide channels 633 can be appropriately adjusted to meet the flow and pressure requirements of the deicing water.
[0062] As a further solution of this embodiment, the heating water pipe loop 33 includes a water supply vertical pipe 3311, a water return vertical pipe 3312, a water supply hose 3321, a water return hose 3322, a water supply sub-pipe 3331, and a water return sub-pipe 3332. The water supply vertical pipe 3311 and the water return vertical pipe 3312 are respectively fixed on the inner wall of the tower 7 in the vertical direction, one end of the water supply vertical pipe 3311 and the water return vertical pipe 3312 are respectively connected to the de-icing side circulation pump 32 and the air conditioning coil 74, the other end of the water supply vertical pipe 3311 and the water return vertical pipe 3312 are respectively connected to the water supply hose 3321 and the water return hose 3322, and the water supply hose 3321 and the water return hose 3322 are respectively connected to the water guide channel 633 on the slip ring outer ring 631 and the slip ring inner ring 632. The other end of the water guide channel 633 is connected to the water supply sub-pipe 3331 and the water return sub-pipe 3332, and the water outlet of the water supply sub-pipe 3331 and the water inlet of the water return sub-pipe 3332 are respectively connected to the fan coil unit 31. The arrangement of the water supply hose 3321 and the water return hose 3322 can facilitate the synchronous rotation of the cabin 6 during the steering process, ensuring the connectivity of the heating water pipe loop 33.
[0063] Preferably, the water supply vertical pipe 3311 and the return vertical pipe 3312 in this embodiment are galvanized steel pipes, extending from the bottom of the tower 7 to the yaw platform section at the top of the tower 7, and the pipe walls of the water supply vertical pipe 3311 and the return vertical pipe 3312 are provided with an insulation layer made of foamed polyurethane insulation material. Figure 3-4 The inner wall of the tower 7 is provided with triangular support members 72 every 1 to 2 m in the vertical direction, and the water supply vertical pipe 3311 and the return vertical pipe 3312 are fixed on multiple support members 72 by buckles 73 or tube bundles.
[0064] Preferably, in this embodiment, the water supply hose 3321 and the water return hose 3322 are made of polyethylene tubes, and a rubber layer is provided on the outer wall to improve the heat preservation effect.
[0065] As a further solution of this embodiment, the substation 71 fixed on the bottom of the tower 7 includes an air-conditioning device 35 connected in parallel to the heating water pipe loop 33. The air-conditioning device 35 can provide cooling in summer and heating in winter, thereby ensuring that the substation 71 can operate normally.
[0066] As a further solution of this embodiment, an insulating partition is provided in the hub 5 . The thickness of the insulating partition is 100 to 300 mm. The insulating partition divides the hub 5 into an inner cabin 51 and an outer cabin 52 . The temperature of the inner cabin 51 is higher than that of the outer cabin 52 .
[0067] refer to Figure 2 The fan coil unit group includes three fan coil units 31 located in the inner cabin 51. The three fan coil units 31 are connected to three blades 41 on the wind power tower through the supply and return air ducts 53 respectively. Each blade 41 is hollow inside. Each blade 41 and each supply and return air duct 53 are provided with S-shaped ribs 43 along their axial direction. The thickness of the ribs 43 is 10-30 mm. The ribs 43 in the blade 41 divide the inside of the blade 41 into a supply air chamber 415 and a return air chamber 416 which are connected. The ribs 43 in the supply and return air duct 53 divide the inside of the blade 41 into a supply air chamber 532 and a return air chamber 533. The supply air chamber 415 and the return air chamber 416 are connected to the supply air chamber 532 and the return air chamber 533 respectively. The supply air chamber 415 and the return air chamber 416 are close to the leading edge 411 and the trailing edge 412 of the blade 41 respectively. The S-shaped arrangement of the ribs 43 can optimize the volumes of the air supply cavity 415 and the air return cavity 416 in the fan blade 41. The rounded corners on the ribs 43 can simultaneously avoid the interference of the edges and corners on the wind field in the fan blade 41 and reduce the vibration of the fan blade 41 caused by the airflow.
[0068] In this solution, the fan coil 31 facilitates better dissipation of the heat of the de-icing water into the air in the inner cabin 51, so that hot air is formed in the inner cabin 51, and the hot air enters the air supply cavity 415 through the air supply duct 532. The hot air exchanges heat with the ice on the wall of the air supply cavity 415 and becomes cold air. The cold air enters the outer cabin 52 through the return air cavity 416 and the return air duct 533 and is discharged into the atmosphere, completing the heat transfer cycle and effectively removing the ice on the leading edge 411 of the blade 41.
[0069] As a further structure of the return air cylinder 53, refer to Figure 7 to Figure 9 Each return air duct 53 is cylindrical and has openings at both ends. One end of the return air duct 53 is arranged on the heat-insulating partition through a bearing 531, and the other end of the return air duct 53 is hemispherical and connected to the blade root 413 of the blade 41; a rotating gear 417 is arranged at the connection between the return air duct 53 and the blade 41, and the two rotating gears 417 are meshed and connected with the output gear on the steering motor 55 located in the hub 5. In this solution, since the angle at which each blade 41 is installed on the hub 5 needs to be adjusted according to the local wind conditions to maximize the acquisition of wind resources, the return air duct 53 of this solution is meshed and connected with the output gear on the steering motor 55 at the same time as the blade 41, ensuring that the supply air duct 532 and the supply air chamber 415, the return air duct 533 and the return air chamber 416 can always remain connected to ensure the circulation of heat.
[0070] Specifically, the blade deicing circuit 4 includes a plurality of phase change heat rods 42 fixed in the air supply cavity 415 , each phase change heat rod 42 has a length of 50 to 80 cm, and simultaneously passes through the air supply cavity 415 , the air supply cylinder 532 and the inner cabin 51 of the hub 5 .
[0071] refer to Figures 9 to 11 Each phase change heat rod 42 includes a heat absorption section 421, a heat insulation section 422 and a heat dissipation section 423 which are connected in sequence; the cross section of the phase change heat rod 42 can be divided into three layers from the outside to the inside: a closed pipe, a capillary core, and a hollow cavity. The heat absorption section 421 extends into the inner cabin 51 through the air supply tube 532, and the heat dissipation section 423 extends to the inside of the blade 41 near the blade tip 414, and a plurality of heat dissipation ribs 424 fixed on the inner wall of the air supply cavity 415 are arranged on the heat dissipation section 423, and each heat dissipation rib 424 is arranged obliquely on the inner wall of the blade 41.
[0072] In this embodiment, the heat absorbing section 421 contains liquid ammonia, acetone or Freon thermosensitive materials that can undergo phase change. After absorbing heat, the thermosensitive materials in the heat absorbing section 421 are vaporized into gaseous state and migrate to the heat dissipating section 423. After the heat of the heat dissipating section 423 is absorbed by the ice layer attached to the surface of the blade tip 414, the thermosensitive materials inside the heat dissipating section 423 condense into liquid state and then migrate back to the heat absorbing section 421 by means of the capillary force in the capillary core to overcome gravity. The setting of the phase change heat rod 42 is conducive to the transfer of heat in the hub 5.
[0073] As another solution of this embodiment, refer to Fig.12 The blade deicing circuit 4 includes a bionic heat dissipation network 44, which is arranged on the windward side and the leeward side of the inner wall of the blade 41. The bionic heat dissipation network 44 is made of coaxial double tubes and micro single U tubes, distributed in the shape of leaf veins, including a main vein 441, which is connected to multiple side veins 442, and each side vein 442 is connected to multiple capillary veins 443.
[0074] Example 2
[0075] This embodiment is further limited on the basis of the embodiment 1, and the specific improvement lies in how to perform deicing operation based on the energy pile bionic wind turbine blade deicing device. For other parts not mentioned, refer to the embodiment 1 or the prior art.
[0076] This embodiment provides an operation method of an energy pile bionic wind turbine blade deicing device, which comprises the following steps:
[0077] S1. Use multiple energy piles 11 in the geothermal energy extraction loop 1 to extract geothermal energy, and use the heat pump unit circulation loop 2 to convert the geothermal energy into deicing water with a higher energy grade than the geothermal energy.
[0078] Specifically, in the heat pump unit circulation loop 2, an evaporator 21, a condenser 22, a compressor 24, and an expansion valve 25 are used to complete a reverse Carnot cycle, converting low-grade geothermal energy into high-grade deicing water.
[0079] S2. Use the hub heating circuit 3 to transfer the heat of the de-icing water to the hub 5 of the wind turbine tower.
[0080] Specifically, the de-icing side circulation pump 32 delivers de-icing water carrying high-grade heat along the water supply riser 3311 to the water supply hose 3321 of the yaw platform section at the top of the tower 7. The water supply hose 3321 passes through the cabin base 61 and delivers the de-icing water to the sealing slip ring 63 of the cabin 6 to avoid twisting and tangling of the water pipe during the free rotation of the cabin 6 and the hub 5.
[0081] The de-icing water passes through the water guide channel 633 of the outer ring 631 of the sealing slip ring 63, and flows into the inner cabin 51 of the hub 5 through the water supply auxiliary pipe 3331; and is connected to the fan coil 31 to achieve heating for the inner cabin 51. After heating, the temperature of the de-icing water decreases, and it returns to the condenser 22 along the return water auxiliary pipe 3332, the return water hose 3322, and the return water vertical pipe 3312 in sequence.
[0082] S3. Use the blade deicing circuit 4 to transfer the heat in the hub 5 to the inner cavity of each blade 41 on the wind tower to melt the ice on the blade 41.
[0083] As a further solution of this embodiment, step S3 includes any of the following steps:
[0084] S31, the inner cavity of each blade 41 is divided into a connected air supply cavity 415 and a return air cavity 416, and the heat in the inner chamber 51 is transferred to the air supply cavity 415 and the return air cavity 416 in sequence using air as a medium.
[0085] S32, the inner cavity in each blade 41 is divided into a connected air supply cavity 415 and a return air cavity 416, and at least one phase change heat rod 42 is arranged in the air supply cavity 415, and the heat in the inner chamber 51 is transferred to the air supply cavity 415 and the return air cavity 416 in sequence using the phase change heat rod 42 as the medium.
[0086] S33, a bionic heat dissipation network 44 is set in the inner cavity of each blade 41, and the heat in the heating water pipe loop 33 is sequentially transferred to the bionic heat dissipation network 44 using deicing water as the medium. The setting of the bionic heat dissipation network 44 can diffuse the heat to every corner of the windward side and the leeward side of the blade 41, and finally flow back to the return water auxiliary pipe 3332 of the inner cabin 51, and then return to the condenser 22 along the return water hose 3322 and the return water vertical pipe 3312 in sequence.
[0087] In step 33, the bionic heat dissipation network 44 has a leaf vein-like structure that can more evenly distribute heat transfer media such as coolant or air, ensuring that the entire heat dissipation process is more balanced and effective, avoiding local overheating or uneven cooling, and making the leaf vein structure have good mechanical properties and reducing weight while ensuring structural stability and strength.
[0088] Although the specific implementation of the invention is described in detail in conjunction with the drawings, it should not be understood as limiting the scope of protection of this patent. Within the scope described in the claims, various modifications and variations that can be made by those skilled in the art without creative work still fall within the scope of protection of this patent.
Claims
1. An energy pile bionic wind turbine blade deicing device, including a wind turbine tower, characterized in that: The wind power tower comprises: A geothermal energy extraction circuit (1), comprising a plurality of energy piles (11) located within a wind tower foundation; A heat pump unit circulation loop (2), the heat pump unit circulation loop (2) being arranged inside a tower barrel (7) of a wind power tower and being in communication with a geothermal energy extraction loop (1) for improving the energy quality of geothermal energy; the heat pump unit circulation loop (2) comprising an evaporator (21) in communication with the geothermal energy extraction loop (1), the evaporator (21) being in communication with a compressor (24) and an expansion valve (25) respectively, the other ends of the compressor (24) and the expansion valve (25) both being in communication with a condenser (22), the water outlet pipe of the condenser (22) being in communication with a wind power auxiliary hot water tank (26); A hub heating circuit (3), the hub heating circuit (3) being arranged inside the tower (7), the nacelle (6) and the hub (5), and being in communication with the heat pump unit circulation circuit (2), for transferring geothermal energy to the hub (5) of the wind turbine tower; the hub heating circuit (3) comprising a deicing side circulation pump (32) in communication with the water outlet of the condenser (22), the deicing side circulation pump (32) being in communication with the sealing slip ring (63), the fan coil unit, the air conditioning device (35) and the return water end of the condenser (22) in sequence through a heating water pipe circuit (33); the sealing slip ring being arranged on the rotor main shaft in the nacelle (6), the fan coil unit being arranged inside the hub (5), and the air conditioning device (35) being fixed to the inner bottom of the tower; The hub (5) is provided with an insulating partition, which divides the hub (5) into an inner cabin (51) and an outer cabin (52). The fan coil unit group includes three fan coil units (31) located in the inner cabin (51). The inner cabin (51) is connected to the three blades (41) on the wind power tower through the supply and return air ducts (53). Each blade (41) is hollow inside. Each blade (41) and each supply and return air duct (53) are provided with S-shaped ribs (43) along their axial direction. The ribs (43) in the blade (41) divide the inside of the blade (41) into a supply air chamber (415) and a return air chamber (416) which are connected. The ribs (43) in the supply and return air duct (53) divide the inside of the blade (41) into a supply air duct (532) and a return air duct (53). 3), the air supply chamber (415) and the return air chamber (416) are respectively connected to the air supply tube (532) and the return air tube (533); and the air supply chamber (415) and the return air chamber (416) are respectively close to the leading edge (411) and the trailing edge (412) of the blade (41); each of the air supply and return tubes (53) is cylindrical and has openings at both ends; one end of the air supply and return tube (53) is arranged on the heat-insulating partition plate through a bearing (531), and the other end of the air supply and return tube (53) is hemispherical and connected to the blade (41); a rotating gear (417) is provided at the connection between the air supply and return tube (53) and the blade (41), and the rotating gear (417) is meshed with the output gear on the steering motor (55) located in the wheel hub (5); A blade deicing circuit (4) is provided in a plurality of blades (41) of a wind turbine tower and is in communication with the hub (5) for heating each blade (41) by geothermal energy; the blade deicing circuit (4) comprises a plurality of phase-changing heat rods (42) located in the air supply cavity (415); the cross section of each phase-changing heat rod (42) is divided into a three-layer structure from the outside to the inside: a closed pipe, a capillary core, and a hollow cavity; The heating rod (42) includes a heat absorbing section (421), a heat insulating section (422) and a heat dissipating section (423) which are connected in sequence; the heat absorbing section (421) extends into the inner cabin (51) through the air supply tube (532); the heat dissipating section (423) extends to the interior of the blade (41) near the blade tip (414); and a plurality of heat dissipating ribs (424) fixed to the inner wall of the air supply cavity (415) are provided on the heat dissipating section (423).
2. The energy pile bionic wind turbine blade deicing device according to claim 1 is characterized in that: The geothermal energy extraction circuit (1) further comprises a ground source side circulation pump (12) and a ground source side manifold (14) located on the foundation of the wind power tower; the ground source side circulation pump (12), the ground source side manifold (14) and the plurality of energy piles (11) are connected via a ground source side water pipe (13).
3. The energy pile bionic wind turbine blade deicing device according to claim 1 is characterized in that: The sealing slip ring (63) includes a slip ring outer ring (631) fixed in the nacelle (6), a slip ring inner ring (632) is rotatably arranged in the inner ring of the slip ring outer ring (631), and the inner ring of the slip ring inner ring (632) is fixed on the rotor main shaft (54) in the nacelle (6); A plurality of water guide channels (633) are provided on both the outer ring (631) and the inner ring (632) of the slip ring, and a sealing ring (634) is provided at both ends of each water guide channel (633); the plurality of water guide channels (633) on the outer ring (631) of the slip ring are connected to the fan coil unit; the plurality of water guide channels (633) on the inner ring (632) of the slip ring are connected to the heating water pipe circuit (33).
4. The energy pile bionic wind turbine blade deicing device according to claim 1 is characterized in that: The blade deicing circuit (4) includes a bionic heat dissipation network (44) located in the inner cavity of the blade (41), and the bionic heat dissipation network (44) is arranged on the windward side and the leeward side of the inner wall of the blade (41); The bionic heat dissipation pipe network (44) is distributed in a leaf vein shape, and includes a main vein (441). The main vein (441) is connected to multiple side veins (442), and each side vein (442) is connected to multiple capillary veins (443).
5. An operating method of the energy pile bionic wind turbine blade deicing device according to any one of claims 1 to 4, characterized in that: Including steps: S1. Extracting geothermal energy using multiple energy piles in a geothermal energy extraction loop, and converting the geothermal energy into de-icing water with a higher energy grade using a heat pump unit circulation loop; S2, using a hub heating circuit to transfer the heat of the de-icing water to the hub of the wind turbine tower; S3. Use the blade de-icing circuit to transfer heat from the hub to the inner cavity of each blade on the wind turbine tower to melt the ice on the blade.
6. The operating method according to claim 5, characterized in that: The step S3 includes any of the following steps: S31, dividing the inner cavity of each blade into a connected air supply cavity and a return air cavity, and transferring the heat in the hub to the air supply cavity and the return air cavity in sequence using air as a medium; S32, dividing the inner cavity of each blade into a connected air supply cavity and a return air cavity, and disposing at least one phase change heat rod in the air supply cavity, and transferring the heat in the hub to the air supply cavity and the return air cavity in sequence through the phase change heat rod as a medium; S33. A bionic heat dissipation network is set in the inner cavity of each blade and connected to the heating water pipe loop in the hub, and heat is transferred to the bionic heat dissipation network in sequence using deicing water as the medium.
Citation Information
Patent Citations
Air-heating deicing device for wind turbine blades
CN110821762A
Wind generating set blade deicing device
CN212027990U
Wind power generation device based on geothermal deicing
CN219366243U