Construction method of anti-shear signal strip structure for lifting platform in theater

By employing a modular construction method and utilizing structures such as facade decorative panels, U-shaped hooks, and angle steel, the convenience and stability issues of the anti-shear signal belt on the theater stage lifting platform were resolved, thereby improving construction speed and quality.

CN118441925BActive Publication Date: 2026-11-17CHINA CONSTR COMM ENG GRP UNITED +2
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410640409.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-22
Publication Date
2026-11-17
Estimated Expiration
2044-05-22

AI Technical Summary

Technical Problem

In existing technologies, the construction of anti-shear signal strips for theater stage lifting platforms is difficult to guarantee in terms of convenience, accuracy, and stability. Furthermore, it is constrained by the construction progress of horizontal wooden floors, resulting in slow construction speed and difficulty in ensuring quality.

Method used

The modular construction method is adopted, which uses vertically arranged facade decorative panels, U-shaped hooks, angle steel and hanging base to achieve convenient installation and precise fixation of anti-shear signal strips. This includes the pre-installation of anti-shear signal strips under the facade decorative panels, the inverted connection of U-shaped hooks, the inverted L-shaped setting of angle steel and the fixed connection of hanging base.

Benefits of technology

This enables convenient installation of anti-shear signal strips, reduces construction time, ensures installation accuracy and stability, and improves construction quality and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118441925B_ABST
    Figure CN118441925B_ABST
Patent Text Reader

Abstract

This invention discloses a construction method for an anti-shear signal strip structure on a theater lifting platform. The method includes a vertically arranged facade decorative panel, an anti-shear signal strip detachably connected to the underside of the facade decorative panel, a U-shaped hook connected to the inner side of the facade decorative panel, horizontal longitudinal and horizontal square tubes connected to the underside of wooden blocks, a support structure connected to the underside of the horizontal square tubes, an angle steel connected to the support structure near the facade decorative panel, and a hanging base at the top of the angle steel. This invention utilizes modular assembly of the anti-shear signal strip, ensuring convenient installation and eliminating the influence of the wooden floor installation sequence, thus greatly saving construction time. The U-shaped hooks and hanging base facilitate the sliding installation of the anti-shear signal strip and allow for precise fine-tuning during installation. The angle steel ensures the stability of the hanging base, thereby guaranteeing the effective fixation of the anti-shear signal strip.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of lifting platform construction technology, and in particular to a construction method for an anti-shear signal strip structure for a lifting platform in a theater. Background Technology

[0002] Theaters, as important carriers of cultural dissemination, are under construction in many cities. Stage lifting anti-shear signal belts are an essential component to ensure the safety of actors and staff. Conventional construction involves installing the horizontal wooden floor first, followed by the vertical boards, with additional joists added to the lower edge of the vertical boards to install the anti-shear signal belts. This method not only makes it difficult to guarantee construction quality but is also extremely arduous to install. To ensure that the anti-shear signal belts are easy to install, no longer constrained by the construction schedule of the horizontal wooden floor, thus accelerating construction and guaranteeing their stability and precision after installation, a targeted design is needed. Summary of the Invention

[0003] This invention provides a construction method for an anti-shear signal strip structure on a theater lifting platform, which solves the technical problems of convenient construction, precise installation and effective fixation of the anti-shear signal strip.

[0004] To achieve the above objectives, the present invention adopts the following technical solution: A construction method for an anti-shear signal strip structure for a lifting platform in a theater includes a vertically arranged facade decorative panel, an anti-shear signal strip detachably connected to the bottom of the facade decorative panel, a U-shaped hook connected to the inner side of the facade decorative panel, a wooden floor and a fire-retardant board located above the facade decorative panel, a wooden block set below the fire-retardant board, a horizontal longitudinal square tube and a horizontal transverse square tube connected below the wooden block, a support structure connected below the horizontal transverse square tube, an angle steel set at one end of the support structure near the facade decorative panel, and a hanging base set at the top of the angle steel. The specific steps for constructing the anti-shear signal strip structure of the theater's lifting platform are as follows: Step 1: Divide the stage in the theater into units, then refine the CAD drawings and number the wooden floor units; highlight the edge sections of the wooden floor and determine their three-dimensional coordinates. Step 2: First, install anti-shear signal strips under the facade decorative panels, then invert the U-shaped hooks to form an inverted U-shape to create a facade decorative panel installation unit; the inverted U-shaped hooks are placed in the lower middle part of the inner side of the facade decorative panels; Step 3: Install the support structure. Position and install the horizontal longitudinal square tubes and the horizontal transverse square tubes on the support structure. Then, install wooden blocks on the corresponding horizontal longitudinal square tubes. The top surface of the wooden blocks should be higher than the height of the facade decorative panel to be installed. Step 4: Fix angle steel to the side between the horizontal longitudinal square tube and the supporting structure. The angle steel is installed on one side of the facade decorative panel to be installed. The angle steel is set in an inverted L shape. Fix the hanging base on the horizontal part. Step 5: Install the facade decorative panel installation unit with U-shaped hooks on the corresponding mounting base, and adjust the position of the U-shaped hooks and the mounting base accordingly so that the position of the facade decorative panel installation unit corresponds to the design requirements; Step Six: After the facade decorative panels and anti-shear signal strip are accurately positioned and verified, install the flame-retardant board and wooden flooring on top of the wooden blocks; then, uniformly apply the topcoat of the wooden flooring and the facade decorative panels, thereby completing the anti-shear signal strip structure of the theater's lifting platform.

[0005] Furthermore, the facade decorative panel is also provided with a T-shaped notch, and the T-shaped protrusions on the T-shaped notch corresponding to the U-shaped hooks can be slidably connected; the U-shaped hooks are spaced apart on the facade decorative panel.

[0006] Furthermore, the facade decorative panel is fixedly connected to the U-shaped hook by a connector, which is a screw.

[0007] Furthermore, the opening of the U-shaped hook is connected to the hanging base, and a wedge-shaped gasket is also provided at the connection point. The angle of the wedge-shaped gasket corresponds to the required angle for adjusting the facade decorative panel.

[0008] Furthermore, the hanging base is a right-angled corner piece, wherein the horizontal part is fixedly connected to the top of the angle steel, and the vertical part is correspondingly connected to the opening of the U-shaped hook.

[0009] Furthermore, the top height of the angle steel is lower than that of the horizontal longitudinal square tube, and the height of the hanging base at the top of the angle steel is flush with that of the horizontal longitudinal square tube.

[0010] Furthermore, the horizontal longitudinal square tubes and the horizontal transverse square tubes are arranged vertically and in a mesh pattern, and a rubber pad is also provided between the horizontal longitudinal square tubes and the wooden block.

[0011] Furthermore, after the wood flooring is installed, the squareness of the wood flooring on the horizontal surface and the straightness between each platform are re-measured; for the wood flooring that exceeds the straightness, a line is drawn and the wood is cut off using a woodworking saw; for the few severely uneven areas, sanding and re-filling with putty are carried out; after the flatness is controlled to 2mm, the top layer of wood paint is the same color as the wood flooring on the horizontal surface.

[0012] The beneficial effects of this invention are reflected in: 1) This invention uses a modular assembly of anti-shear signal strips, which facilitates easy installation and is not affected by the installation sequence of the wooden floor, thus greatly saving construction time. 2) The present invention, through the setting of U-shaped hooks and hanging base, facilitates the sliding installation of anti-shear signal strips on the one hand, and the precise fine-tuning during the installation process on the other hand. 3) The present invention, by setting angle steel, helps to ensure the stability of the hanging base installation, thereby ensuring the effective fixation of the anti-shear signal band.

[0013] Other features and advantages of the invention will be set forth in the description which follows, and will be apparent in part from the description, or may be learned by practicing the invention; the main objects and other advantages of the invention may be realized and obtained by means of the embodiments particularly pointed out in the description. Attached Figure Description

[0014] Figure 1 This is a schematic diagram of the anti-shear signal band structure of the lifting platform in the theater; Figure 2 This is a schematic diagram of the facade decorative panels, anti-shear signal strips, and U-shaped hooks; Figure 3 This is a schematic diagram of angle steel and its connections.

[0015] Attached reference numerals: 1-Front facade decorative panel, 2-Anti-shear signal strip, 3-U-shaped hook, 4-Wooden floor, 5-Flame retardant board, 6-Wooden pad, 7-Hanging base, 8-Horizontal longitudinal square tube, 9-Horizontal transverse square tube, 10-Angle steel, 11-Supporting structure, 12-Rubber pad, 13-Connector. Detailed Implementation

[0016] Taking a grand theater stage as an example, it is divided into a main stage, north and south side stages, a rear stage, and an orchestra pit. The main stage has five upper and lower lifting platforms, eight side auxiliary lifting platforms, five rear compensation lifting platforms, one rear auxiliary lifting platform, and the orchestra pit lifting platform. During the lifting process, these platforms will create misalignment with adjacent structures. To ensure the safety of performers and staff, anti-shear sensor signal strips need to be installed on the side walls of these stages. For example... Figures 1 to 3 As shown, the construction method of the anti-shear signal strip structure of the lifting platform in the theater includes a vertically arranged facade decorative panel 1, an anti-shear signal strip 2 detachably connected to the lower part of the facade decorative panel 1, a U-shaped hook 3 connected to the inner side of the facade decorative panel 1, a wooden floor 4 and a flame-retardant board 5 located above the facade decorative panel 1, a wooden block 6 set below the flame-retardant board 5, a horizontal longitudinal square tube 8 and a horizontal transverse square tube 9 connected below the wooden block 6, a support structure 11 connected below the horizontal transverse square tube 9, an angle steel 10 connected to the support structure 11 near one end of the facade decorative panel 1, and a hanging base 7 set at the top of the angle steel 10.

[0017] The specific steps for constructing the anti-shear signal strip structure of the theater's lifting platform are as follows: Step 1: Divide the stage in the theater into units, then refine the CAD drawings and number the wooden floor units 4; highlight the edge sections of the wooden floor 4 and determine their three-dimensional coordinates.

[0018] Step 2: First, install the anti-shear signal strip 2 under the facade decorative panel 1, and then invert the U-shaped hook 3 to form an inverted U shape to form the facade decorative panel 1 installation unit; the inverted U-shaped hook 3 is set in the lower middle part of the inner side of the facade decorative panel 1.

[0019] In this embodiment, the facade decorative panel 1 is also provided with a T-shaped notch, and the T-shaped protrusions on the T-shaped notch corresponding to the U-shaped hooks 3 are slidably connected; the U-shaped hooks 3 are spaced apart on the facade decorative panel 1. The facade decorative panel 1 is fixedly connected to the U-shaped hooks 3 by a connector 13, wherein the connector 13 is a screw.

[0020] Step 3: Install the support structure 11. Position and install the horizontal longitudinal square tube 8 and the horizontal transverse square tube 9 on the support structure 11. Then, install the wooden pad 6 on the horizontal longitudinal square tube 8. The top surface of the wooden pad 6 is higher than the installation height of the facade decorative panel 1.

[0021] The horizontal longitudinal square tubes 8 and the horizontal transverse square tubes 9 are arranged vertically in a mesh pattern, and rubber pads 12 are also provided between the horizontal longitudinal square tubes 8 and the wooden blocks 6. The spacing between adjacent keels of the horizontal longitudinal square tubes 8 and the horizontal transverse square tubes 9 is no greater than 600×600mm.

[0022] Step 4: Fix angle steel 10 to the side between the horizontal longitudinal square tube 8 and the supporting structure 11. The angle steel 10 is installed on one side of the facade decorative panel 1 to be installed. The angle steel 10 is set in an inverted L shape. The hanging base 7 is fixedly installed on the horizontal part. Among them, the hanging base 7 is a right-angled corner piece, in which the horizontal part is fixedly connected to the top of the angle steel 10, and the vertical part is correspondingly connected to the opening of the U-shaped hook 3.

[0023] In this embodiment, the top height of the angle steel 10 is lower than that of the horizontal longitudinal square tube 8, and the height of the top mounting base 7 of the angle steel 10 is flush with that of the horizontal longitudinal square tube 8.

[0024] Step 5: Install the facade decorative panel 1 installation unit with U-shaped hooks 3 on the corresponding hanging base 7, and adjust the positions of the U-shaped hooks 3 and the hanging base 7 accordingly so that the position of the facade decorative panel 1 installation unit corresponds to the design requirements.

[0025] The opening of the U-shaped hook 3 is connected to the hanging base 7, and a wedge-shaped gasket is also provided at the connection point. The angle of the wedge-shaped gasket is adjusted to the required angle according to the facade decorative panel 1.

[0026] Step Six: After the facade decorative panel 1 and the anti-shear signal strip 2 are accurately positioned and verified, install the flame-retardant board 5 and the wooden floor 4 on top of the wooden pad 6; then, uniformly configure the topcoat of the wooden floor 4 and the facade decorative panel 1, thereby completing the structure of the anti-shear signal strip 2 of the theater's lifting platform.

[0027] In this embodiment, after the wood flooring 4 is installed in place, the squareness of the horizontal wood flooring 4 and the straightness between each platform are re-measured; for the wood flooring 4 that exceeds the straightness, a line is drawn and cut off with a woodworking saw; for the few severely uneven areas, sanding and puttying are carried out; after the flatness is controlled to 2mm, the top layer of wood paint is the same color as the horizontal wood flooring 4.

[0028] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any changes or substitutions that can be conceived by those skilled in the art within the scope of the technology disclosed in the present invention should be included within the scope of protection of the present invention.

Claims

1. A construction method of a non-shear signal belt structure of a stage lift platform body, characterized by, It includes a vertically arranged facade decorative panel (1), a shear signal strip (2) detachably connected to the lower part of the facade decorative panel (1), a U-shaped hook (3) connected to the inner side of the facade decorative panel (1), a wooden floor (4) and a flame-retardant board (5) located above the facade decorative panel (1), a wooden block (6) set below the flame-retardant board (5), a horizontal longitudinal square tube (8) and a horizontal transverse square tube (9) connected below the wooden block (6), a support structure (11) connected below the horizontal transverse square tube (9), an angle steel (10) connected to the support structure (11) near the facade decorative panel (1), and a hanging base (7) set at the top of the angle steel (10). The specific steps for constructing the anti-shear signal strip structure for the lifting platform in the theater are as follows: Step 1: Divide the stage in the theater into units, then refine the CAD drawings and number the unit wooden floor (4); highlight the edge section wooden floor (4) and determine its three-dimensional coordinates; Step 2: Install anti-shear signal strip (2) under the facade decorative panel (1) in advance, and then invert the U-shaped hook (3) to form an inverted U-shape to form the facade decorative panel (1) installation unit; the inverted U-shaped hook (3) is set in the lower middle part of the inner side of the facade decorative panel (1); Step 3: Install the support structure (11), and position and install the horizontal longitudinal square tube (8) and the horizontal transverse square tube (9) on the support structure (11). Then, install the wooden pad (6) on the horizontal longitudinal square tube (8). The top surface of the wooden pad (6) is higher than the height of the facade decorative panel (1) to be installed. Step 4: Fix angle steel (10) on the side between the horizontal longitudinal square tube (8) and the supporting structure (11). The angle steel (10) is installed on one side of the facade decorative panel (1) to be installed. The angle steel (10) is set in an inverted L shape. The hanging base (7) is fixedly installed on the horizontal part. Step 5: Install the facade decorative panel (1) installation unit with U-shaped hook (3) on the corresponding hanging base (7), and adjust the position of the U-shaped hook (3) and the hanging base (7) accordingly so that the position of the facade decorative panel (1) installation unit corresponds to the design requirements; Step 6: After the facade decorative panel (1) and anti-shear signal strip (2) are accurately positioned, install the flame retardant board (5) and wooden floor (4) on the wooden pad (6); then, uniformly configure the topcoat of the wooden floor (4) and the topcoat of the facade decorative panel (1), thereby completing the structure of the anti-shear signal strip (2) of the lifting platform in the theater.

2. The construction method of a non-shear signal belt structure of a stage lift platform body in a theater according to claim 1, characterized in that, The facade decorative panel (1) is also provided with a T-shaped notch, and the T-shaped protrusions on the T-shaped notch corresponding to the U-shaped hooks (3) are slidably connected; the U-shaped hooks (3) are spaced apart on the facade decorative panel (1).

3. The construction method of the anti-shear signal strip structure for a theater lifting platform as described in claim 1, characterized in that, The facade decorative panel (1) is fixedly connected to the U-shaped hook (3) by a connector (13), wherein the connector (13) is a screw.

4. The construction method of the anti-shear signal strip structure for a theater lifting platform as described in claim 1, characterized in that, The opening of the U-shaped hook (3) is connected to the hanging base (7), and a wedge-shaped gasket is also provided at the connection point. The angle of the wedge-shaped gasket corresponds to the required angle of the facade decorative panel (1).

5. The construction method of the anti-shear signal strip structure for a theater lifting platform as described in claim 1, characterized in that, The hanging base (7) is a right-angled corner piece, wherein the horizontal part is fixedly connected to the top of the angle steel (10), and the vertical part is correspondingly connected to the opening of the U-shaped hook (3).

6. The construction method of the anti-shear signal strip structure for a theater lifting platform as described in claim 1, characterized in that, The top height of the angle steel (10) is lower than that of the horizontal longitudinal square tube (8), and the height of the top hanging base (7) of the angle steel (10) is flush with that of the horizontal longitudinal square tube (8).

7. The construction method of the anti-shear signal strip structure for a theater lifting platform as described in claim 1, characterized in that, The horizontal longitudinal square tube (8) and the horizontal transverse square tube (9) are arranged vertically and in a mesh pattern. A rubber pad (12) is also provided between the horizontal longitudinal square tube (8) and the wooden block (6).

8. The construction method of the anti-shear signal strip structure for a theater lifting platform as described in claim 1, characterized in that, After the wood flooring (4) is installed in place, the squareness of the horizontal wood flooring (4) and the straightness between each platform are re-measured; the wood flooring (4) in the position that exceeds the straightness is marked with a chalk line and cut off with a wood saw; for the few serious uneven positions, sanding and puttying are used; after the flatness is controlled to 2mm, the top layer of wood paint is the same color as the horizontal wood flooring (4).

Citation Information

Patent Citations

  • Aluminum square tube mounting structure with externally-hung decorative plates

    CN112709397A

  • Unitized curtain wall hangs sign indicating number component

    CN207553385U