A method for synchronous cutting and dismantling of large steel beams by gas welding

By using the gas welding synchronous cutting method in the cutting process of large steel beams, combined with the use of hanging baskets and crank-arm trucks, the problem of difficulty in ensuring the synchronization and safety of two-person cutting in the existing technology is solved, and the rapid and efficient cutting of steel beams is achieved. , safe dismantling.

CN118492983BActive Publication Date: 2024-10-01DALIAN CONSTR ENG GRP
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410964975.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-18
Publication Date
2024-10-01
Estimated Expiration
2044-07-18

AI Technical Summary

Technical Problem

During the cutting and demolition process of large steel beams, it is difficult to effectively control the frequency of two-person cutting synchronization and the working position of construction workers with existing technology, making it difficult to ensure safety.

Method used

Using the gas welding synchronous cutting method, by setting up hanging baskets and crank-arm trucks on both sides of the steel beam, the steel beam is pre-lifted and the appropriate cutting angle and sequence are selected to ensure the synchronization and safety of the cutting operation, including lifting and placing at high altitudes. Specific cutting steps and angle design when falling to the ground.

Benefits of technology

It achieves fast, efficient and safe cutting and dismantling of large steel beams, ensuring the safety of construction workers and construction machinery to the greatest extent and avoiding production safety accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118492983B_ABST
    Figure CN118492983B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of large steel beam dismantling, and particularly relates to a method for gas welding synchronous cutting and dismantling of large steel beams. According to whether the I-beam is lifted from the operating area from a high altitude or directly dropped to the ground, the corresponding cutting angle and cutting sequence are selected for cutting. The present invention is carefully designed from many aspects such as the order of steel beam cutting, the cutting angle, the frequency of two-person cutting synchronization, and the working position of the personnel. During the gas welding cutting construction, it must be implemented strictly in accordance with the formulated plan to meet the safety requirements for dismantling large steel beams. The present invention can meet the needs of cutting workers to complete the construction quickly, efficiently, and safely when cutting steel beams to the greatest extent, and the steel beams can be smoothly lifted off or placed on the ground. Ensure the safety of construction workers and construction machinery to avoid production safety accidents.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of large steel beam dismantling, and in particular relates to a large steel beam gas welding synchronous cutting and dismantling method. Background Art

[0002] In modern public buildings, in order to achieve the requirements of lightness, beauty and unique shape, steel structure is often used as the main building structure type in structural design. When steel structure buildings do not meet the requirements of structural safety and structural earthquake resistance for various reasons and must be demolished, segmented cutting and disassembly is one of the main demolition methods.

[0003] With the development of technology, cutting operations are usually performed by machinery, and hydraulic shears are generally used to cut steel columns and beams to achieve fast, efficient and safe construction requirements. However, in actual construction, there are often restrictions such as site operating conditions, construction height and mechanical equipment performance that prevent mechanical operations, so manual gas welding cutting is also often used in actual construction.

[0004] The large steel beam is 33.8m long, 1.3m high, 0.3m wide, 13.28t heavy, and has a flange thickness of 32mm. The existing cutting and dismantling method uses manual gas welding cutting, and the construction is carried out according to the different cutting angles when it is lifted off or dropped to the ground. The problem is that it is difficult to control the frequency of the two-person cutting synchronization and the working position of the construction workers. Since the component is large in size, how to better ensure the safety of the construction work has become the top priority of this work when cutting large steel beams. Summary of the invention

[0005] In order to solve the problem of how to better ensure the safety of construction operations during the cutting and dismantling of large steel beams in the above-mentioned prior art, the present invention proposes a method for synchronous cutting and dismantling of large steel beams with gas welding.

[0006] To achieve the above purpose, the technical solution of the present invention is as follows:

[0007] A large steel beam gas welding synchronous cutting and dismantling method, characterized in that it comprises the following steps:

[0008] S1. Use a truck crane or a boom truck with a hanging basket to move the cutting workers to the vicinity of the steel beam at the corresponding positions on both sides of the steel beam, hang the steel wire ropes at the symmetrical positions on both sides of the steel beam, and pre-lift the steel beam with the crawler lifting hook;

[0009] S2. Cutting workers clean the fire retardant coating on the outside of the steel beam;

[0010] S3. After cleaning, select the corresponding cutting angle according to whether the I-beam is lifted from the working area from a high altitude or dropped directly to the ground: when lifted from a high altitude, use the \ / cutting line to cut at the symmetrical positions on both sides of the large steel beam; when dropped to the ground, use the / | cutting line to cut.

[0011] In the step S3, when the large steel beam is lifted from a high altitude, the steps specifically include the following:

[0012] S31. Cut the web first, and use the \ / cutting line at the symmetrical position of the web on both sides of the large steel beam, cutting from top to bottom;

[0013] S32. After cutting to the bottom, cut a hole of 8-10 cm near the lower flange plate. The operator uses gas welding to directly cut the lower flange plate on the side away from the operator horizontally through the hole to avoid the operator working at the bottom of the steel beam;

[0014] S33, after the lower flange plate is cut, the operation is stopped, and after the workers on both sides have finished cutting the web plate and the lower part, the truck crane or the articulated arm truck lifts two workers to synchronously cut the upper flange plate horizontally;

[0015] S34. After the upper flange plate is cut, it is lifted away after the workers in the car crane basket or the articulated arm car and the surrounding personnel have evacuated.

[0016] The included angle between the cutting line and the horizontal plane is 45°-60°.

[0017] In step S3, when the large steel beam is placed on the ground, the steps specifically include the following:

[0018] S31. Cut the left web first. Use the / cutting line on the left web of the large steel beam and cut from top to bottom. After cutting to the bottom, cut a hole of 8-10cm near the lower flange plate.

[0019] S32. Cut the right side web again, using the | cutting line, from top to bottom. After cutting to the bottom, cut a hole of 8-10 cm near the lower flange plate;

[0020] S33. The workers use gas welding to horizontally cut the lower flange plate on the side away from the workers through the openings on both sides to avoid the workers working at the bottom of the steel beam;

[0021] S34. After the lower flange plate is cut, stop the operation. After the workers on both sides have finished cutting the web plate and the lower part, cut the upper flange plate on the right side. Cut vertically 10 cm from the cutting line of the right web plate, and then cut horizontally to meet the cutting line of the right web plate.

[0022] S35, horizontally cut the left upper flange plate;

[0023] S36. After the upper flange plate is cut, it is lowered to the ground after the workers in the car crane basket or the articulated arm car and the surrounding personnel have evacuated.

[0024] The angle between the cutting line and the horizontal plane is 45°-60°.

[0025] The present invention is carefully designed from many aspects such as the order of steel beam cutting, cutting angle, frequency of two-person cutting synchronization, and personnel working position. During gas welding and cutting construction, it must be implemented strictly in accordance with the established plan to meet the safety requirements for dismantling large steel beams. The present invention can meet the needs of cutting workers to complete the construction quickly, efficiently, and safely when cutting steel beams to the greatest extent, and the steel beams can be smoothly lifted off or placed on the ground. The safety of construction workers and construction machinery is guaranteed to avoid production safety accidents. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a web cutting line arrangement diagram when a large steel beam of the present invention is lifted from high altitude;

[0027] Figure 2 This is the cutting sequence and cutting direction diagram of the large steel beam of the present invention when it is lifted from high altitude:

[0028] Figure 3 It is a web cutting line layout diagram when the large steel beam of the present invention is placed on the ground;

[0029] Figure 4 It is a cutting sequence and cutting direction diagram when the large steel beam of the present invention is placed on the ground;

[0030] In the figure, 1, upper flange plate, 2, lower flange plate, 3, rib plate, 4, web plate, 5, web plate cutting line, 6, gas welding cutting hole, 7, cut web plate. DETAILED DESCRIPTION

[0031] The present invention is further described below in conjunction with the accompanying drawings, but the present invention is not limited to the specific embodiments. Example 1

[0032] The large steel beam comprises an upper flange plate 1, a lower flange plate 2, a rib plate 3 and a web plate 4.

[0033] A large steel beam gas welding synchronous cutting and dismantling method comprises the following steps:

[0034] S1. Use a truck crane or a boom truck with a hanging basket to move the cutting workers to the vicinity of the steel beam at the corresponding positions on both sides of the steel beam, hang the steel wire ropes at the symmetrical positions on both sides of the steel beam, and pre-lift the steel beam with the crawler lifting hook;

[0035] S2. Cutting workers clean the fire retardant coating on the outside of the steel beam;

[0036] S3. After cleaning, when the large steel beam is lifted from the high altitude, the specific steps include:

[0037] S31, such as Figure 1-Figure 2 As shown, the arrow indicates the cutting direction. The web 4 is cut first, and the web cutting line 5 of ∠ is used at the symmetrical position of the web 4 on both sides of the large steel beam, and the cutting is carried out from top to bottom;

[0038] S32, after cutting to the bottom, cut a hole with a size of 8-10 cm near the lower flange plate 2 as the gas welding cutting hole 6, and the operator uses gas welding to directly horizontally cut the lower flange plate 2 on the side away from the operator through the hole to avoid the operator working at the bottom of the steel beam;

[0039] S33, after the lower flange plate 2 is cut, the operation is stopped, and after the workers on both sides have finished cutting the web plate 4 and the lower flange plate 2, the truck crane or the articulated arm truck lifts two workers to synchronously cut the upper flange plate 1 horizontally;

[0040] S34. After the upper flange plate 1 is cut, it is lifted away after the workers in the car crane basket or the crank truck and the surrounding personnel have evacuated.

[0041] The angle between the web cutting line 5 and the horizontal plane is 45°-60°. Example 2

[0042] The method for synchronous cutting and dismantling of a large steel beam by gas welding described in this embodiment is the same as that in Embodiment 1 except that:

[0043] In step S3, when the large steel beam is placed on the ground, the steps specifically include the following:

[0044] S31, such as Figure 3-Figure 4 As shown, the arrow indicates the cutting direction. The left web 4 is cut first. The web cutting line 5 of / is used on the left web 4 of the large steel beam. Cut from top to bottom. After cutting to the bottom, cut a hole of 8-10 cm near the lower flange plate 2.

[0045] S32, cut the right side web 4 again, using the | cutting line, cutting from top to bottom, and after cutting to the bottom, cut a hole with a size of 8-10 cm near the lower flange plate 2;

[0046] S33, the operator uses gas welding to directly horizontally cut the lower flange plate 2 on the side away from the operator through the openings on both sides to avoid the operator working at the bottom of the steel beam;

[0047] S34, stop the operation after the lower flange plate 2 is cut, wait until the workers on both sides have finished cutting the web plate 4 and the lower flange plate 2, and then cut the upper flange plate 1 on the right side, cut vertically at a position 10 cm away from the cutting line of the cut web plate 7, and then cut horizontally to meet the cutting line of the cut web plate 7;

[0048] S35, horizontally cut the left upper flange plate 1;

[0049] S36. After the upper flange plate 1 is cut, it is placed on the ground after the workers in the car crane basket or the articulated arm car and the surrounding personnel have evacuated.

[0050] The angle between the web cutting line 5 and the horizontal plane is 45°-60°.

Claims

1. A method for synchronous cutting and dismantling of large steel beams by gas welding, characterized in that: The following steps are involved: S1. Use a truck crane or a boom truck with a hanging basket to move the cutting workers to the vicinity of the steel beam at the corresponding positions on both sides of the steel beam, hang the steel wire ropes at the symmetrical positions on both sides of the steel beam, and pre-lift the steel beam with the crawler lifting hook; S2. Cutting workers clean the fire retardant coating on the outside of the steel beam; S3. After cleaning, select the corresponding cutting angle according to whether the I-beam is lifted from the working area from high altitude or dropped directly to the ground: when lifted from high altitude, use the \ / cutting line to cut at the symmetrical positions on both sides of the large steel beam; when dropped to the ground, use the / | cutting line to cut; When large steel beams are lifted from high altitude, the following steps are specifically included: S31. Cut the web first, and use the \ / cutting line at the symmetrical position of the web on both sides of the large steel beam, cutting from top to bottom; S32. After cutting to the bottom, cut a hole of 8-10 cm near the lower flange plate. The operator uses gas welding to directly cut the lower flange plate on the side away from the operator horizontally through the hole to avoid the operator working at the bottom of the steel beam; S33, after the lower flange plate is cut, the operation is stopped, and after the workers on both sides have finished cutting the web plate and the lower part, the truck crane or the articulated arm truck lifts two workers to synchronously cut the upper flange plate horizontally; S34. After the upper flange plate is cut, the crane basket or the crankshaft is lifted away after the workers in the crane basket and the surrounding personnel have evacuated; When placing large steel beams on the ground, the specific steps include: S31. Cut the left web first. Use the / cutting line on the left web of the large steel beam and cut from top to bottom. After cutting to the bottom, cut a hole of 8-10cm near the lower flange plate. S32. Cut the right side web again, using the | cutting line, from top to bottom. After cutting to the bottom, cut a hole of 8-10 cm near the lower flange plate; S33. The workers use gas welding to horizontally cut the lower flange plate on the side away from the workers through the openings on both sides to avoid the workers working at the bottom of the steel beam; S34. After the lower flange plate is cut, stop the operation. After the workers on both sides have finished cutting the web plate and the lower part, cut the upper flange plate on the right side. Cut vertically 10 cm from the cutting line of the right web plate, and then cut horizontally to meet the cutting line of the right web plate. S35, horizontally cut the left upper flange plate; S36. After the upper flange plate is cut, it is lowered to the ground after the workers in the car crane basket or the articulated arm car and the surrounding personnel have evacuated.

2. A large steel beam gas welding synchronous cutting and dismantling method according to claim 1, characterized in that: The included angle between the cutting line and the horizontal plane is 45°-60°.

3. The method for synchronous cutting and dismantling of large steel beams by gas welding according to claim 1 is characterized in that: The angle between the cutting line and the horizontal plane is 45°-60°.

Citation Information

Patent Citations

  • Beam end weakened replacement type steel frame beam shock proof node

    CN101100877A

  • Soft steel shearing lag return damper

    CN101413296A

  • Multi-point shear energy-absorbing roll-over protection device for construction vehicles

    CN101560783A

  • Low-yield-point steel buckling-restrained shearing plate damper

    CN103696505A

  • Piano sound hammer cutting machine

    CN103835115A