Intelligent sewage treatment method and system

By collecting and analyzing data in the sewage treatment area, automatically adjusting treatment parameters, and recovering sewage treatment energy, it solves the problems of insufficient sewage treatment performance coordination and energy optimization in the existing technology, achieves efficient sewage treatment and energy management, and reduces cost and pollution.

CN118505435BActive Publication Date: 2024-10-01INNER MONGOLIA DONGYUAN ENVIRONMENTAL PROTECTION TECH CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410933485.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-10-01
Estimated Expiration
2044-07-12

AI Technical Summary

Technical Problem

Existing intelligent sewage treatment technology has deficiencies in coordinating and optimizing sewage treatment performance on a regional scale, resulting in energy waste and increased operating costs.

Method used

By dividing the sewage treatment area, collecting and analyzing sewage treatment data, using GIS software to identify pollution sources and water flow directions, building a water quality prediction model, automatically adjusting treatment parameters, and recycling the energy generated during the sewage treatment process for self-supply of energy, integrating data to form a comprehensive Wastewater data view.

Benefits of technology

It achieves dynamic optimization of the sewage treatment process, improves treatment efficiency and energy utilization efficiency, and reduces operating costs and environmental pollution.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118505435B_ABST
    Figure CN118505435B_ABST
Patent Text Reader

Abstract

The present invention discloses an intelligent sewage treatment method and system, which relates to the technical field of sewage treatment, including dividing sewage treatment areas, collecting sewage treatment data of each area, and analyzing and predicting water quality data; preliminarily adjusting sewage treatment parameters of each area according to the analysis results, and automatically adjusting sewage treatment parameters of the area to be optimized according to the comparison results of sewage treatment performance of different areas after the preliminary adjustment. The present invention collects sewage treatment data by dividing different areas, analyzes and predicts water quality data, formulates preliminary adjustment measures according to the results, and further adjusts sewage treatment measures according to the comparison results of sewage treatment data of the standard area and the area to be optimized, collects energy generated in the sewage treatment process in real time, and self-supplies energy for sewage treatment equipment, thereby realizing dynamic optimization of the sewage treatment process, improving the efficiency of sewage treatment and the utilization efficiency of energy, reducing the operating cost of the sewage treatment process, and reducing environmental pollution.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of sewage treatment, and in particular to an intelligent sewage treatment method and system. Background Art

[0002] With the rapid development of industrialization and urbanization, the pollution of water resources has become increasingly serious. The advancement of sewage treatment technology has become an important research direction in the field of environmental protection. Traditional sewage treatment technologies mainly include physical, chemical and biological methods. These methods have been widely used and continuously developed in the past few decades. In recent years, with the rapid development of information technology and intelligent manufacturing, intelligent sewage treatment methods have gradually become a research hotspot. Although existing technologies can optimize a single treatment site, there is still room for improvement in the coordination and optimization of sewage treatment performance within a regional scope. The use of energy in the treatment process is often not fully optimized, resulting in energy waste and increased operating costs. Summary of the invention

[0003] In view of the problems existing in the above-mentioned existing intelligent sewage treatment methods and systems, the present invention is proposed.

[0004] Therefore, the problem to be solved by the present invention is that although the existing technology can optimize a single treatment site, there is still room for improvement in the coordination and optimization of sewage treatment performance within a regional scope. The use of energy in the treatment process is often not fully optimized, resulting in energy waste and increased operating costs.

[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: an intelligent sewage treatment method, which includes dividing sewage treatment areas, collecting sewage treatment data of each area and analyzing and predicting water quality data; preliminarily adjusting sewage treatment parameters of each area according to the analysis results and automatically adjusting sewage treatment parameters of the area to be optimized according to the comparison results of sewage treatment performance of different areas after the preliminary adjustment; recycling the energy generated during the sewage treatment process to provide energy for sewage treatment equipment, and integrating sewage treatment data of different areas to form a comprehensive sewage data view.

[0006] As a preferred solution of the intelligent sewage treatment method described in the present invention, the division of sewage treatment areas to collect sewage treatment data of each area refers to collecting terrain, hydrology, population distribution and industrial layout data of each area of ​​the city, loading the collected data into GIS software, building a preliminary geographic information model, using the spatial analysis tool of GIS software to identify the distribution of pollution sources and the flow direction of water bodies, identifying the current status of sewage treatment in each area based on the spatial analysis results, and dividing each area into a standard area and an area to be optimized. The standard area refers to an area where sewage treatment facilities operate well, water quality meets or exceeds environmental protection standards all year round, and no additional treatment measures are required. The area to be optimized includes a high-optimization area and a low-optimization area. The high-optimization area refers to an area including industrial concentration areas and areas with large pollutant emissions. The low-optimization area refers to an area with relatively low pollution levels and treatment requirements. Water quality monitoring sensors are installed in the divided areas to collect water quality data in real time and transmit it to the central database for storage.

[0007] As a preferred solution of the intelligent sewage treatment method of the present invention, the analysis and prediction of water quality data refers to selecting parameters that affect the sewage treatment effect in each area from the central database for pre-processing, arranging the pre-processed parameters in chronological order, and each parameter forms an independent time series;

[0008] Use statistical methods to analyze the time series of each parameter, identify and extract trend components, and use seasonal decomposition of the time series to decompose the time series of each parameter and extract seasonal and cyclical characteristics;

[0009] Use autoregressive moving average models to analyze cyclical fluctuations and outliers in time series data;

[0010] The extracted trend, seasonality, periodicity and outlier features are feature encoded, and the correlation coefficient matrix is ​​used to evaluate the correlation between different features to remove multicollinearity problems;

[0011] Use the LSTM model to build a water quality prediction model, set the number of LSTM layers to 2, set 128 neural units in each layer, and use ReLU as the activation function;

[0012] Use the feature importance score of random forest to evaluate the contribution of each feature to the predictive ability of the water quality prediction model, select the most informative features, and determine the final feature set based on the importance of the features and their contribution to the prediction target;

[0013] The historical water quality data is used as a training set to input into the water quality prediction model for iterative training, and the loss function and Adam optimizer are defined to iteratively optimize the model parameters. When the loss of the water quality prediction model no longer decreases significantly during the continuous iteration process, the iteration is stopped and the model parameters are output to update the water quality prediction model.

[0014] The feature set and real-time water quality data are input into the water quality prediction model to obtain the predicted values ​​of the water quality parameters in the area to be optimized.

[0015] As a preferred scheme of the intelligent sewage treatment method described in the present invention, wherein: the preliminary adjustment of the sewage treatment parameters of each area according to the analysis results refers to obtaining the predicted values ​​of the water quality parameters of each area to be optimized according to the analysis results of the water quality prediction model, determining the parameters that need to be adjusted in each area according to the predicted values ​​of the water quality parameters, formulating corresponding adjustment plans and executing them.

[0016] As a preferred solution of the intelligent sewage treatment method of the present invention, wherein: the automatic adjustment of the sewage treatment parameters of the area to be optimized according to the comparison results of the sewage treatment performance of different areas after the preliminary adjustment refers to real-time monitoring of the sewage treatment performance of each area after the preliminary adjustment and calculating the performance index of each area according to the real-time monitoring data, and summarizing the calculated performance index of each area into a central database;

[0017] Use data analysis tools to compare the performance data of the area to be optimized and the standard area, identify the specific indicators of the area to be optimized whose performance is lower than that of the standard area, calculate the degree of difference in performance indicators, analyze the reasons for the difference in sewage treatment performance and formulate adjustment strategies to automatically adjust the sewage treatment parameters of the area to be optimized.

[0018] As a preferred solution of the intelligent sewage treatment method of the present invention, wherein: the energy generated in the sewage treatment process is recovered to provide energy for the sewage treatment equipment, which means extracting the sludge generated in the sewage treatment process and pre-treating the sludge, selecting a continuous stirring reactor from an anaerobic digester according to the sludge characteristics, and installing key equipment of the continuous stirring reactor;

[0019] Collect microbial strains from sludge, select microbial strains that can be active under low temperature and high organic load conditions, use gene sequencing and expression analysis technology to identify genes related to methane production, and edit the genes of microbial strains through gene editing technology to enhance the methane production ability of microbial strains, gradually add pretreated sludge and microbial strains to the digester, adjust operating parameters including temperature, pH value and residence time, monitor the production of biogas in real time and collect it;

[0020] The heat recovered from the anaerobic digestion process is used to dry the treated sludge, and the dried sludge is crushed and sieved to adjust the particle size distribution;

[0021] Select a gasification reactor according to the physical and chemical properties of the sludge, select a catalyst type according to the main organic components in the sludge, calculate the required amount of catalyst based on the sludge input and the desired gasification efficiency, mix the calculated amount of catalyst and the sludge after particle size distribution adjustment, load the mixture into the reactor, set the operating parameters of the reactor and monitor the temperature, pressure, gas output and composition in real time during the reaction process, and adjust the reactor operating parameters according to the monitoring results;

[0022] The synthesis gas produced by the gas is condensed and cleaned to remove impurities and condensates and to recover the waste heat of the high-temperature gas produced during the gasification process;

[0023] Install the CHP system and sensors, select the CHP model based on the expected gas production and composition, and design the system configuration, including generators, heat exchangers, and control systems;

[0024] Start the CHP system to convert the received biogas and syngas into electricity and heat through the generator;

[0025] Use deep learning models to predict the energy demand of sewage treatment equipment, automatically adjust the power generation and heat output of the CHP system based on the prediction results, and use PID controllers to adjust the operating parameters of the generator;

[0026] Install an energy storage system integrated with the CHP system to store the energy extracted from the sludge in the energy storage system;

[0027] Analyze the costs of different energy supply sources, including the operation and maintenance costs of self-produced energy and the market price of purchased energy, automatically adjust energy distribution according to the predicted energy demand of the sewage treatment equipment and cost-benefit analysis, use the energy stored in the energy storage system when the power demand of the sewage treatment equipment is low, and purchase the most cost-effective external electricity when the power demand of the sewage treatment equipment is high.

[0028] As a preferred solution of the intelligent sewage treatment method described in the present invention, the integration of sewage treatment data from different regions to form a comprehensive sewage data view refers to collecting sewage treatment related data from various regions, storing them in a central database, and using ETL tools to integrate data from different data sources, correlating the overall water quality indicators, sewage treatment efficiency, and total energy generation in each region with the energy required by sewage treatment equipment, and using data visualization tools to build an interactive data dashboard to form a comprehensive sewage data view.

[0029] Another object of the present invention is to provide an intelligent sewage treatment system, which comprises:

[0030] The regional division module is used to collect sewage treatment data in various areas of the city and divide them into standard areas and areas to be optimized;

[0031] Data analysis module, used to predict changes in water quality parameters and formulate sewage treatment measures based on water quality data of each area to be optimized;

[0032] A comparison and adjustment module is used to compare the differences in sewage treatment processes between the area to be optimized and the standard area after the implementation of adjustment measures, and formulate adjustment measures for sewage treatment;

[0033] Energy recovery module, used to recover the energy generated in the sewage treatment process in real time and use the energy for sewage equipment to achieve energy self-supply and select the best energy according to cost-effectiveness at different energy demand stages;

[0034] The visualization module is used to integrate the sewage treatment data of each region and visualize the data to form a comprehensive sewage data view.

[0035] A computer device comprises: a memory and a processor; the memory stores a computer program, and the processor implements the steps of an intelligent sewage treatment method when executing the computer program.

[0036] A computer-readable storage medium stores a computer program, which implements the steps of an intelligent sewage treatment method when executed by a processor.

[0037] The beneficial effects of the present invention are as follows: the present invention collects sewage treatment data by dividing different areas and analyzes and predicts the water quality data, formulates preliminary adjustment measures based on the results and further adjusts the sewage treatment measures based on the comparison results of the sewage treatment data of the standard area and the area to be optimized, collects the energy generated in the sewage treatment process in real time to realize energy self-supply of the sewage treatment equipment, realizes dynamic optimization of the sewage treatment process, improves the efficiency of sewage treatment and energy utilization efficiency, reduces the operating cost of the sewage treatment process and reduces environmental pollution. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0039] Figure 1 Schematic diagram of the process of intelligent sewage treatment method.

[0040] Figure 2 This is a structural diagram of the intelligent sewage treatment system. DETAILED DESCRIPTION

[0041] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings.

[0042] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0043] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor is it a separate or selective embodiment that is mutually exclusive with other embodiments.

[0044] Example 1: Reference Figure 1 , which is the first embodiment of the present invention, and provides an intelligent sewage treatment method, the intelligent sewage treatment method comprising:

[0045] S1. Divide the sewage treatment areas, collect sewage treatment data from each area, and analyze and predict water quality data;

[0046] Specifically, dividing sewage treatment areas and collecting sewage treatment data in various areas refers to collecting terrain, hydrology, population distribution and industrial layout data of various areas in the city, loading the collected data into GIS software, building a preliminary geographic information model, and using the spatial analysis tools of GIS software to identify the distribution of pollution sources and the flow direction of water bodies. Based on the spatial analysis results, the current status of sewage treatment in each area is identified, and each area is divided into a standard area and an area to be optimized. The standard area refers to an area where sewage treatment facilities operate well, the water quality meets or exceeds environmental protection standards all year round, and no additional treatment measures are required. The area to be optimized includes a high-optimization area and a low-optimization area. The high-optimization area refers to an industrial concentration area and an area with large pollutant emissions. The low-optimization area refers to an area with relatively low pollution levels and treatment requirements. Water quality monitoring sensors are installed in the divided areas to collect water quality data in real time and transmit it to the central database for storage.

[0047] Through detailed regional division, we can accurately identify areas with high and low demand for sewage treatment, effectively allocate sewage treatment resources, and optimize treatment efficiency. The division of standard areas and areas to be optimized will help concentrate treatment resources in high-pollution areas, improve treatment effects, and reduce overall treatment costs. Comprehensive data collection provides basic support for the intelligent management of sewage treatment systems. Accurate geographic information models can accurately simulate the diffusion paths of pollutants and help formulate more effective treatment strategies. GIS software can integrate multi-source data, conduct complex spatial analysis, and provide visualization of pollution source distribution and water flow paths.

[0048] Furthermore, the analysis and prediction of water quality data refers to selecting parameters (chemical oxygen demand (COD), biochemical oxygen demand (BOD), total suspended solids (TSS) and ammonia nitrogen) that have an impact on the sewage treatment effect in each region from the central database for pretreatment through historical data analysis and relevant literature research, arranging the pretreated parameters in chronological order, and each parameter forms an independent time series;

[0049] Use statistical methods to analyze the time series of each parameter, identify and extract trend components, and use seasonal decomposition of the time series to decompose the time series of each parameter and extract seasonal and cyclical characteristics;

[0050] Use autoregressive moving average models to analyze cyclical fluctuations and outliers in time series data;

[0051] The extracted trend, seasonality, periodicity and outlier features are feature encoded, and the correlation coefficient matrix is ​​used to evaluate the correlation between different features to remove multicollinearity problems;

[0052] Use the LSTM model to build a water quality prediction model, set the number of LSTM layers to 2, set 128 neural units in each layer, and use ReLU as the activation function;

[0053] Use the feature importance score of random forest to evaluate the contribution of each feature to the predictive ability of the water quality prediction model, select the most informative features, and determine the final feature set based on the importance of the features and their contribution to the prediction target;

[0054] The historical water quality data is used as a training set to input into the water quality prediction model for iterative training, and the loss function and Adam optimizer are defined to iteratively optimize the model parameters. When the loss of the water quality prediction model no longer decreases significantly during the continuous iteration process, the iteration is stopped and the model parameters are output to update the water quality prediction model.

[0055] The feature set and real-time water quality data are input into the water quality prediction model to obtain the predicted values ​​of the water quality parameters in the area to be optimized.

[0056] Collect historical data of water quality parameters such as COD and BOD, and perform time series analysis through statistical methods, including seasonal decomposition, to identify the basic trends and seasonal fluctuations of each water quality parameter, and provide the necessary pre-data structure and baseline for in-depth analysis of periodic changes and outliers. Based on the trends and seasonality extracted in the first step, the autoregressive moving average (ARMA) model is used in the second step to further analyze the subtle periodic fluctuations and sudden anomalies of the time series data. The periodic fluctuations and outliers identified by the precise model enable sewage treatment operations to respond more flexibly to sudden changes and continuous trends, and optimize the timing and methods of operation. The periodic and abnormal features identified in the second step become the focus of further analysis. In the third step, these features are converted into a format that can be used by the machine learning model through feature encoding, and the correlation coefficient matrix is ​​used to evaluate the correlation between different features, thereby removing multicollinearity problems in the data. Feature encoding and removal of multicollinearity Heavy collinearity ensures the prediction accuracy and stability of the model, avoids prediction errors caused by the mutual influence of features, and makes the final water quality prediction model more reliable and accurate in practical applications. In-depth data prediction using the autoregressive moving average (ARMA) model and the long short-term memory network (LSTM) model can accurately predict the dynamic changes of water quality and help sewage treatment facilities make more effective treatment decisions. The random forest algorithm is used to evaluate the importance of each feature and select the most helpful features for model prediction to optimize the model's prediction ability, ensuring that the most critical data features are used to predict water quality, thereby improving the accuracy and efficiency of the prediction. The optimized water quality prediction model is applied to real-time data to predict the water quality status of the area to be optimized, and the sewage treatment parameters are adjusted according to the prediction results. Real-time prediction enables sewage treatment to respond to water quality changes immediately and dynamically adjust the treatment process, greatly improving treatment efficiency and water quality safety.

[0057] S2. Preliminarily adjust the sewage treatment parameters of each area according to the analysis results and automatically adjust the sewage treatment parameters of the area to be optimized according to the comparison results of the sewage treatment performance of different areas after the preliminary adjustment;

[0058] Specifically, preliminarily adjusting the sewage treatment parameters of each region according to the analysis results means obtaining the predicted values ​​of the water quality parameters of each region to be optimized according to the analysis results of the water quality prediction model, determining the parameters that need to be adjusted in each region according to the predicted values ​​of the water quality parameters, formulating corresponding adjustment plans and executing them.

[0059] Based on the predicted values, the system can accurately identify specific parameters that need to be adjusted, such as the type and dosage of chemical agents, aeration time and intensity, etc. This precise adjustment can significantly improve sewage treatment efficiency and reduce resource waste. The adjustment plan includes detailed operating steps and time arrangements to ensure the efficient execution of parameter adjustments, the smooth progress of the adjustment process and timely feedback on the results. According to the formulated adjustment plan, the sewage treatment system will automatically or manually adjust the corresponding treatment parameters. Through real-time monitoring and feedback mechanisms, it can ensure that the adjustment effect meets the expected goals and correct deviations in a timely manner.

[0060] Further, automatically adjusting the sewage treatment parameters of the area to be optimized according to the comparison results of the sewage treatment performance of different areas after the preliminary adjustment means real-time monitoring the sewage treatment performance of each area after the preliminary adjustment and calculating the performance index of each area according to the real-time monitoring data, and aggregating the calculated performance index of each area into a central database;

[0061] Use data analysis tools to compare the performance data of the area to be optimized and the standard area, identify the specific indicators of the area to be optimized whose performance is lower than that of the standard area, calculate the degree of difference in performance indicators, analyze the reasons for the difference in sewage treatment performance and formulate adjustment strategies to automatically adjust the sewage treatment parameters of the area to be optimized.

[0062] Real-time monitoring of the performance of sewage treatment in each area and calculation of performance indicators such as COD, BOD, TSS, etc. Aggregating these data into a central database ensures the real-time and integrity of the data, and provides the necessary data basis for subsequent comparison and analysis. The availability of real-time data is the key to making fast and accurate decisions. Using aggregated real-time data and applying data analysis tools to compare the sewage treatment performance of different areas, especially the performance comparison between the area to be optimized and the standard area, can accurately identify areas with substandard performance, providing a basis for targeted adjustments. By identifying these differences, problems in specific areas can be solved more targetedly. After identifying areas with poor performance, analyze the reasons for these differences, such as equipment aging, insufficient treatment capacity or improper chemical treatment, and formulate specific adjustment strategies accordingly. By implementing these adjustment strategies, intervention can be made directly on the problems found, thereby improving sewage treatment efficiency and overall water quality. The automatic adjustment mechanism makes this process faster and more accurate, reducing delays and errors in human intervention.

[0063] S3. Recycle the energy generated during sewage treatment to provide energy for sewage treatment equipment, and integrate sewage treatment data from different regions to form a comprehensive sewage data view;

[0064] Specifically, recycling the energy generated in the sewage treatment process to achieve energy self-supply of sewage treatment equipment means extracting the sludge generated in the sewage treatment process and pre-treating the sludge, selecting a continuous stirred reactor from the anaerobic digester according to the sludge characteristics, and installing the key equipment of the continuous stirred reactor (digester body, mixer, heating element, temperature and pH control system);

[0065] Collect microbial strains from sludge, select microbial strains that can be active under low temperature and high organic load conditions, use gene sequencing and expression analysis technology to identify genes related to methane production, and edit the genes of microbial strains through gene editing technology to enhance the methane production ability of microbial strains, gradually add pretreated sludge and microbial strains to the digester, adjust operating parameters including temperature, pH value and residence time, monitor the production of biogas in real time and collect it;

[0066] The heat recovered from the anaerobic digestion process is used to dry the treated sludge, and the dried sludge is crushed and sieved to adjust the particle size distribution;

[0067] Select a gasification reactor according to the physical and chemical properties of the sludge, select a catalyst type according to the main organic components in the sludge, calculate the required amount of catalyst based on the sludge input and the desired gasification efficiency, mix the calculated amount of catalyst and the sludge after particle size distribution adjustment, load the mixture into the reactor, set the operating parameters of the reactor and monitor the temperature, pressure, gas output and composition in real time during the reaction process, and adjust the reactor operating parameters according to the monitoring results;

[0068] The synthesis gas produced by the gas is condensed and cleaned to remove impurities and condensates and to recover the waste heat of the high-temperature gas produced during the gasification process;

[0069] Install the CHP system and sensors, select the CHP model based on the expected gas production and composition, and design the system configuration, including generators, heat exchangers, and control systems;

[0070] Start the CHP system to convert the received biogas and syngas into electricity and heat through the generator;

[0071] Use deep learning models to predict the energy demand of sewage treatment equipment, automatically adjust the power generation and heat output of the CHP system based on the prediction results, and use PID controllers to adjust the operating parameters of the generator;

[0072] Install an energy storage system (lithium-ion battery or flow battery) integrated with the CHP system to store the energy extracted from the sludge in the energy storage system;

[0073] Analyze the costs of different energy supply sources, including the operation and maintenance costs of self-produced energy and the market price of purchased energy, automatically adjust energy distribution according to the predicted energy demand of the sewage treatment equipment and cost-benefit analysis, use the energy stored in the energy storage system when the power demand of the sewage treatment equipment is low, and purchase the most cost-effective external electricity when the power demand of the sewage treatment equipment is high.

[0074] Extract sludge and pre-treat it, select suitable anaerobic digesters and key equipment to ensure that the conditions of sludge are suitable for the growth of microorganisms and the effective production of methane, maximize the initial energy recovery efficiency, extract energy from the pre-treated sludge, and further convert it into usable biogas through genetically optimized microbial strains to increase methane production, ensure the high efficiency and stability of the energy recovery process, and use the conversion of biogas to provide the necessary electricity and heat energy to make energy use more efficient, improve energy self-sufficiency, reduce dependence on external energy, and reduce energy costs. Based on the energy that has been generated and stored, optimize energy use and allocation to ensure the balance between energy supply and demand. Through the intelligent energy management system, energy use can be adjusted according to actual needs to maximize economic benefits and environmental sustainability;

[0075] The automatic adjustment mechanism of sewage treatment parameters ensures that the sewage treatment efficiency is always in the best state, responds to water quality changes and treatment needs, and combines energy recovery steps to not only optimize the water quality treatment process, but also use the energy generated in the treatment process itself to support operations, thereby achieving energy self-sufficiency. It pays attention to both sewage treatment efficiency and energy efficiency, so that energy use and water quality treatment are optimally matched. Although a single automatic adjustment mechanism improves sewage treatment efficiency, it still relies on external power supply in terms of energy consumption, and energy recovery alone cannot maximize its potential without effective real-time performance adjustment support. The combination of the two steps not only makes sewage treatment more efficient, but also produces the required energy, ensuring that all recoverable energy is effectively utilized, significantly reducing dependence on external electricity, and enhancing the environmental and economic sustainability of sewage treatment. This optimized energy recovery and utilization cannot be achieved by a single step, and the best effect can only be achieved when real-time adjustment and energy recovery work simultaneously.

[0076] Furthermore, integrating sewage treatment data from different regions to form a comprehensive sewage data view means collecting sewage treatment-related data from various regions and storing them in a central database, using ETL tools to integrate data from different data sources, and associating the overall water quality indicators, sewage treatment efficiency, and total energy generation in each region with the energy required by sewage treatment equipment. Using data visualization tools to build an interactive data dashboard to form a comprehensive sewage data view.

[0077] Collect sewage treatment related data in real time from different regions, including water quality indicators (such as COD, BOD, TSS, NH3-N, etc.), treatment efficiency, energy consumption and output, etc., and store them in the central database. This process ensures the integrity and timeliness of the data, and provides a reliable foundation for subsequent data integration and analysis. Use ETL tools to extract data from different data sources, perform standardized processing and load it into the central database to ensure data consistency and availability. ETL tools can handle a large number of heterogeneous data sources, realize automatic data integration, and improve data processing efficiency. Correlation analysis of water quality indicators, treatment efficiency and energy data in each region can provide a comprehensive understanding of the operating status and resource utilization of the sewage treatment system. Through this correlation, potential problems and optimization space can be discovered.

[0078] Example 2: Reference Figure 2 , which is the second embodiment of the present invention, and which is different from the previous embodiment, provides an intelligent sewage treatment system, which includes:

[0079] The regional division module is used to collect sewage treatment data in various areas of the city and divide them into standard areas and areas to be optimized;

[0080] Data analysis module, used to predict changes in water quality parameters and formulate sewage treatment measures based on water quality data of each area to be optimized;

[0081] A comparison and adjustment module is used to compare the differences in sewage treatment processes between the area to be optimized and the standard area after the implementation of adjustment measures, and formulate adjustment measures for sewage treatment;

[0082] Energy recovery module, used to recover the energy generated in the sewage treatment process in real time and use the energy for sewage equipment to achieve energy self-supply and select the best energy according to cost-effectiveness at different energy demand stages;

[0083] The visualization module is used to integrate the sewage treatment data of each region and visualize the data to form a comprehensive sewage data view.

[0084] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the methods described in various embodiments of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc., which can store program codes.

[0085] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute instructions), or in conjunction with such instruction execution systems, devices or apparatuses. For the purposes of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in conjunction with such instruction execution systems, devices or apparatuses.

[0086] More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk case (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be a paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, deciphering or, if necessary, processing in another suitable manner, and then stored in a computer memory.

[0087] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit with a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit with a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.

Claims

1. An intelligent sewage treatment method, characterized in that: include, Divide sewage treatment areas, collect sewage treatment data from each area, and analyze and predict water quality data; Preliminarily adjust the sewage treatment parameters of each area according to the analysis results and automatically adjust the sewage treatment parameters of the area to be optimized according to the comparison results of the sewage treatment performance of different areas after the preliminary adjustment; Recycle the energy generated during sewage treatment to provide energy for sewage treatment equipment, and integrate sewage treatment data from different regions to form a comprehensive sewage data view; The division of sewage treatment areas and collection of sewage treatment data of each area refers to collecting topographic, hydrological, population distribution and industrial layout data of each area of ​​the city, loading the collected data into GIS software, building a preliminary geographic information model, using the spatial analysis tool of GIS software to identify the distribution of pollution sources and the flow direction of water bodies, identifying the current status of sewage treatment in each area based on the spatial analysis results, and dividing each area into a standard area and an area to be optimized. The standard area refers to an area where sewage treatment facilities operate well, water quality meets or exceeds environmental protection standards all year round, and no additional treatment measures are required. The area to be optimized includes a high-optimization area and a low-optimization area. The high-optimization area refers to an area including industrial concentration areas and areas with large pollutant emissions. The low-optimization area refers to an area with relatively low pollution levels and treatment requirements. Water quality monitoring sensors are installed in the divided areas to collect water quality data in real time and transmit it to the central database for storage; The analysis and prediction of water quality data refers to selecting parameters that affect the sewage treatment effect in each area from the central database for pre-processing, arranging the pre-processed parameters in chronological order, and each parameter forms an independent time series; Use statistical methods to analyze the time series of each parameter, identify and extract trend components, and use seasonal decomposition of the time series to decompose the time series of each parameter and extract seasonal and cyclical characteristics; Use autoregressive moving average models to analyze cyclical fluctuations and outliers in time series data; The extracted trend, seasonality, periodicity and outlier features are feature encoded, and the correlation coefficient matrix is ​​used to evaluate the correlation between different features to remove multicollinearity problems; Use the LSTM model to build a water quality prediction model, set the number of LSTM layers to 2, set 128 neural units in each layer, and use ReLU as the activation function; Use the feature importance score of random forest to evaluate the contribution of each feature to the predictive ability of the water quality prediction model, select the most informative features, and determine the final feature set based on the importance of the features and their contribution to the prediction target; The historical water quality data is used as a training set to input into the water quality prediction model for iterative training, and the loss function and Adam optimizer are defined to iteratively optimize the model parameters. When the loss of the water quality prediction model no longer decreases significantly during the continuous iteration process, the iteration is stopped and the model parameters are output to update the water quality prediction model. Input the feature set and real-time water quality data into the water quality prediction model to obtain the predicted values ​​of the water quality parameters in the area to be optimized; The preliminary adjustment of the sewage treatment parameters of each region according to the analysis results refers to obtaining the predicted values ​​of the water quality parameters of each region to be optimized according to the analysis results of the water quality prediction model, determining the parameters to be adjusted in each region according to the predicted values ​​of the water quality parameters, formulating and executing corresponding adjustment plans; The automatic adjustment of the sewage treatment parameters of the area to be optimized according to the comparison results of the sewage treatment performance of different areas after the preliminary adjustment refers to real-time monitoring of the sewage treatment performance of each area after the preliminary adjustment and calculating the performance index of each area according to the real-time monitoring data, and summarizing the calculated performance index of each area into the central database; Use data analysis tools to compare the performance data of the area to be optimized and the standard area, identify the specific indicators of the area to be optimized whose performance is lower than that of the standard area, calculate the degree of difference in performance indicators, analyze the reasons for the difference in sewage treatment performance and formulate adjustment strategies to automatically adjust the sewage treatment parameters of the area to be optimized.

2. The intelligent sewage treatment method according to claim 1, characterized in that: The energy self-supply of the sewage treatment equipment by recycling the energy generated in the sewage treatment process refers to extracting the sludge generated in the sewage treatment process and pre-treating the sludge, selecting a continuous stirring reactor from the anaerobic digester according to the sludge characteristics, and installing the key equipment of the continuous stirring reactor; Collect microbial strains from sludge, select microbial strains that can be active under low temperature and high organic load conditions, use gene sequencing and expression analysis technology to identify genes related to methane production, and edit the genes of microbial strains through gene editing technology to enhance the methane production ability of microbial strains, gradually add pretreated sludge and microbial strains to the digester, adjust operating parameters including temperature, pH value and residence time, monitor the production of biogas in real time and collect it; The heat recovered from the anaerobic digestion process is used to dry the treated sludge, and the dried sludge is crushed and sieved to adjust the particle size distribution; Select a gasification reactor according to the physical and chemical properties of the sludge, select a catalyst type according to the main organic components in the sludge, calculate the required amount of catalyst based on the sludge input and the desired gasification efficiency, mix the calculated amount of catalyst and the sludge after particle size distribution adjustment, load the mixture into the reactor, set the operating parameters of the reactor and monitor the temperature, pressure, gas output and composition in real time during the reaction process, and adjust the reactor operating parameters according to the monitoring results; The synthesis gas produced by the gas is condensed and cleaned to remove impurities and condensates and to recover the waste heat of the high-temperature gas produced during the gasification process; Install the CHP system and sensors, select the CHP model based on the expected gas production and composition, and design the system configuration, including generators, heat exchangers, and control systems; Start the CHP system to convert the received biogas and syngas into electricity and heat through the generator; Use deep learning models to predict the energy demand of sewage treatment equipment, automatically adjust the power generation and heat output of the CHP system based on the prediction results, and use PID controllers to adjust the operating parameters of the generator; Install an energy storage system integrated with the CHP system to store the energy extracted from the sludge in the energy storage system; Analyze the costs of different energy supply sources, including the operation and maintenance costs of self-produced energy and the market price of purchased energy, automatically adjust energy distribution according to the predicted energy demand of the sewage treatment equipment and cost-benefit analysis, use the energy stored in the energy storage system when the power demand of the sewage treatment equipment is low, and purchase the most cost-effective external electricity when the power demand of the sewage treatment equipment is high.

3. The intelligent sewage treatment method according to claim 2, characterized in that: The integration of sewage treatment data from different regions to form a comprehensive sewage data view refers to collecting sewage treatment related data from various regions, storing them in a central database, and using ETL tools to integrate data from different data sources, correlating the overall water quality indicators, sewage treatment efficiency, and total energy generation in each region with the energy required for sewage treatment equipment, and using data visualization tools to build an interactive data dashboard to form a comprehensive sewage data view.

4. An intelligent sewage treatment system based on the intelligent sewage treatment method according to any one of claims 1 to 3, characterized in that: include, The regional division module is used to collect sewage treatment data in various areas of the city and divide them into standard areas and areas to be optimized; Data analysis module, used to predict changes in water quality parameters and formulate sewage treatment measures based on water quality data of each area to be optimized; The comparison and adjustment module is used to compare the differences in sewage treatment processes between the area to be optimized and the standard area after the implementation of adjustment measures and formulate adjustment measures for sewage treatment; Energy recovery module, used to recover the energy generated in the sewage treatment process in real time and use the energy for sewage equipment to achieve energy self-supply and select the best energy according to cost-effectiveness at different energy demand stages; The visualization module is used to integrate the sewage treatment data of each region and visualize the data to form a comprehensive sewage data view.

5. A computer device comprising: A memory and a processor; the memory stores a computer program, wherein the processor implements the steps of the intelligent sewage treatment method according to any one of claims 1 to 3 when executing the computer program.

6. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the intelligent sewage treatment method described in any one of claims 1 to 3 are implemented.

Citation Information

Cited By

  • Industrial equipment monitoring management system and method based on cloud management platform

    CN120509989A

  • An industrial equipment monitoring management system and method based on a cloud management platform

    CN120509989B