A construction progress management method and system based on BIM

Through the BIM-based construction progress management method, combined with work efficiency and resource parameters, the construction plan is adjusted in real time, and the lag and inaccurate problems of traditional construction progress management methods are solved, achieving more efficient construction management and risk control.

CN118521161BActive Publication Date: 2024-11-12CHINA POWER CONSTR MUNICIPAL CONSTR GRP SHANDONG ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410971455.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-12
Estimated Expiration
2044-07-19

AI Technical Summary

Technical Problem

Traditional construction progress management methods rely on manual recording, and data updates are lagging, making it difficult to reflect the construction site situation in real time, and failing to fully consider the impact of work efficiency and resource parameters, resulting in insufficient management.

Method used

Using BIM-based construction progress management method, by establishing a BIM model, real-time acquisition and extraction of construction site images, combining work efficiency and resource parameters for progress evaluation, adjusting construction plans, and optimizing resource allocation and construction processes.

Benefits of technology

More precise construction progress management has been achieved, reducing rework and delays, improving construction efficiency, identifying potential risks in advance, and ensuring that the project is completed on time and in quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118521161B_ABST
    Figure CN118521161B_ABST
Patent Text Reader

Abstract

The present application provides a construction progress management method and system based on BIM, which relates to the technical field of construction progress management. The management method includes the steps of modeling, planning, model optimization, construction progress evaluation, adjustment of construction plan and early warning. The management system includes a modeling module, a planning module, a construction progress evaluation module, a judgment module and a construction plan adjustment module. The present application can identify potential risk factors in advance and formulate corresponding response measures through in-depth analysis of construction progress deviations and their influencing factors, thereby effectively reducing project risks.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of construction progress management, and in particular to a construction progress management method and system based on BIM. Background Art

[0002] In the traditional construction industry, construction progress management has always been a key link in project management, directly related to the cost, quality and delivery time of the project. However, traditional construction progress management methods have many limitations, such as reliance on manual records, delayed data updates, and difficulty in reflecting the construction site situation in real time. These problems not only increase the difficulty of management, but also reduce management efficiency, making it difficult to adapt to the increasingly complex and rapidly changing needs of modern construction projects.

[0003] In order to overcome the shortcomings of traditional methods, the construction industry has begun to explore and apply new technologies to improve the level of construction progress management. Among them, Building Information Modeling (BIM) technology has gradually become an important tool for construction progress management due to its powerful information integration and visualization capabilities. BIM technology integrates the entire life cycle information of a building, such as design, construction, operation and maintenance, into one model through digital means, providing unprecedented data support and decision-making basis for project management.

[0004] A Chinese invention patent with a publication date of January 5, 2024 and publication number CN117350682A discloses a BIM-based construction progress management method and system, the method comprising: constructing a three-dimensional BIM model of a standard building; obtaining construction progress analysis results; obtaining multiple sets of finishing site images; performing material reuse progress analysis to obtain multiple material reuse progress analysis results; obtaining multiple usage demand analysis results; combining multiple material reuse progress analysis results and multiple usage demand analysis results to calculate multiple material progress analysis results; performing weighted correction calculations on the construction progress analysis results to obtain corrected construction progress analysis results, and generating a construction progress management plan.

[0005] However, in the construction progress, construction materials are part of the resource parameters. If only the impact of construction materials on the construction progress is considered, the obtained construction progress management plan is not accurate. In the actual construction process, the factors affecting the construction progress also include work efficiency parameters and other resource parameters such as people and equipment. In order to improve the accuracy of construction progress management, it is necessary to provide a construction progress management plan that can consider both work efficiency parameters and resource parameters. Summary of the invention

[0006] In order to take into account the impact of both work efficiency parameters and resource parameters on construction progress management, the present application provides a BIM-based construction progress management method and system.

[0007] In the first aspect, the present invention provides a construction progress management method based on BIM, which adopts the following technical solution:

[0008] A construction progress management method based on BIM, comprising the following steps:

[0009] Modeling: Building BIM models;

[0010] Make a plan: Based on the BIM model, combined with the project goals and construction period, make the first construction plan;

[0011] Construction progress assessment: including collecting construction images, extracting construction progress, retrieving construction plans, obtaining construction progress deviations and the first judgment step;

[0012] Collecting construction images: Collecting the current construction site image, recording it as the first image, and obtaining the current construction data;

[0013] Extracting construction progress: extracting the current construction progress based on the first image and the current construction data;

[0014] Retrieve the construction plan: In the BIM model, retrieve the current corresponding first construction plan progress and record it as the second construction plan;

[0015] Obtain construction progress deviation: Compare and analyze the current construction progress and the second construction plan to obtain the construction progress deviation;

[0016] First judgment: judging whether the construction progress deviation is greater than a preset construction progress deviation threshold, if so, executing the step of adjusting the construction plan; if not, executing the step of collecting construction images after an interval of time t;

[0017] Adjust the construction plan: including obtaining influencing factors, second judgment, third judgment, first adjustment and second adjustment steps;

[0018] Obtain influencing factors: Obtain influencing factors of construction progress deviation by analyzing the deviation of construction progress;

[0019] Second judgment: judging whether the influencing factor is an ergonomic parameter, if so, executing the first adjustment step; if not, executing the third judgment step;

[0020] Third judgment: judging whether the influencing factor is a resource parameter, if so, executing the second adjustment step; if not, continuing to construct according to the first construction plan;

[0021] First adjustment: Evaluate the first construction plan, obtain and adjust the construction links whose efficiency is lower than the preset threshold;

[0022] Second adjustment: adjust the first construction plan according to resource parameters to obtain the third construction plan.

[0023] By adopting the above technical solution, this application establishes a BIM model, so that the construction team can understand the design intent and engineering details more accurately, and reduce rework and delays caused by misunderstandings or poor communication. By collecting and extracting the construction progress in real time, managers can quickly grasp the actual progress of the project, adjust the plan in time, and ensure that the construction activities are carried out as planned. When it is found that the deviation of the construction progress is caused by resource parameters (including insufficient resources or unreasonable allocation), in order to ensure that the key construction links are supported by sufficient resources, this application adjusts the construction plan according to the resource parameters through the second adjustment step to achieve optimal allocation of resources, reduce waste, and improve overall construction efficiency. When it is found that the deviation of the construction progress is caused by the work efficiency parameter, this application will evaluate the first construction plan, obtain the construction link with work efficiency lower than the preset threshold, and make adjustments, so as to achieve a reasonable arrangement of the construction process or construction link. Through in-depth analysis of the deviation of the construction progress and its influencing factors, potential risk factors can be identified in advance, and corresponding countermeasures can be formulated to effectively reduce the risk of the project. By real-time monitoring of the construction progress, managers can respond to emergencies quickly and reduce the impact of emergencies on the overall progress of the project.

[0024] Optionally, after executing the planning step and before executing the construction progress evaluation step, the method further includes:

[0025] Get time nodes: Get the time periods corresponding to each construction link in the first construction plan, and get the time nodes when the current construction link starts and ends;

[0026] First model optimization: add time nodes to the BIM model to obtain a new BIM model.

[0027] By adopting the above technical scheme, the present application can further refine the construction plan by obtaining the time period corresponding to each construction link and the specific time node of the current construction link in the first construction plan, clarify the start and end time of each construction link, and ensure the orderly progress of the construction activities. After adding the time node in the BIM model, the construction plan becomes more specific and intuitive, which helps the construction team to better understand and execute the plan, reduce delays and errors caused by unclear plans, and the BIM model with time nodes not only contains spatial information, but also contains time information, so that the model can more comprehensively reflect the actual situation of the project, and provide richer data support for construction progress evaluation and other decisions. After adding the time node in the BIM model, the construction progress evaluation can be carried out more accurately and efficiently. By comparing the actual construction progress with the planned progress in the BIM model, deviations can be found in time and corresponding adjustment measures can be taken. If it is found that the construction progress deviation is large, the construction progress needs to be adjusted, especially when the time node needs to be adjusted, the optimized BIM model can provide more detailed and accurate data support to help managers quickly formulate adjustment plans and implement them.

[0028] Optionally, after executing the first model optimization step and before executing the construction progress evaluation step, the method further includes:

[0029] Second, model optimization: including building a hierarchical structure, format conversion, lightweight processing, and model reconstruction steps;

[0030] Building a hierarchical structure: including data partitioning and frustum reduction steps;

[0031] Data partitioning: The BIM model obtained in the first model optimization step is divided into multiple tiles with different accuracy levels;

[0032] View frustum clipping: According to the camera's viewing angle and distance, determine the tile that can be seen from the current viewing angle, recorded as the first tile;

[0033] Format conversion: extract the geometric information of the first tile in the IFC file, and obtain the 3D Tiles file by reconstructing and changing the format of the data;

[0034] Lightweight processing: Use the Draco compression algorithm to lightweight the geometric data in the 3D Tiles file;

[0035] Model reconstruction: including file loading, object access, fourth judgment, first information extraction, LOD level determination and tile rendering steps;

[0036] File loading: Use the Three.js library to load lightweight 3D Tiles files;

[0037] Access objects: Access each object in the 3D Tiles file;

[0038] Fourth judgment: for each object, judging whether there is additional information, if yes, extracting BIM attributes from the additional information, if no, executing the first information extraction step;

[0039] First information extraction: extract the BIM attribute information of each object in the 3D Tiles file;

[0040] Determine the LOD level: Set the LOD level according to the camera's viewing angle and distance;

[0041] Tile rendering: Render the first tile based on the LOD level and BIM attribute information.

[0042] By adopting the above technical solution, this application uses the Three.js library to load the lightweight 3D Tiles file, and through the steps of accessing objects, the fourth judgment, the first information extraction, etc., the attribute information of the BIM model is completely retained. Specifically, for each object in the 3D Tiles file, it is first determined whether there is additional information. If so, the BIM attribute is extracted from the additional information; if not, the BIM attribute information is extracted from the 3D Tiles file through an information extraction step. Finally, the LOD (Levels of Detail) level is set according to the camera's viewing angle and distance, and the first tile is rendered in combination with the BIM attribute information, realizing real-time interaction and smooth rendering of the BIM model. While retaining the key information of the BIM model, the efficient loading and smooth rendering of the BIM model are realized through steps such as data division, cone cutting, format conversion, lightweight processing and model reconstruction, providing strong technical support for the widespread application of BIM technology.

[0043] Optionally, after executing the step of collecting construction images and before executing the step of extracting construction progress, the method further includes:

[0044] Image processing: including image preprocessing and image selection steps;

[0045] Image preprocessing: cleaning the first image to obtain the second image, wherein the cleaning operation includes: denoising, enhancing image contrast, adjusting image brightness, and adjusting image color;

[0046] Image selection: screen the second image to obtain a third image, and use the third image as a new construction site image.

[0047] By adopting the above technical solution, the present application performs a preprocessing operation on the first image, which can effectively improve the quality of the first image, thereby obtaining a clearer and more accurate second image. After the first image is preprocessed, the second image is screened to remove blurry, repeated or irrelevant second images to obtain a third image, and the most valuable third image is retained as a new construction site image, which helps to reduce data redundancy and improve the efficiency of subsequent processing and analysis.

[0048] Optionally, after executing the image selection step and before executing the construction progress extraction step, the method further includes:

[0049] Image recognition: using computer vision technology to recognize construction elements in the third image, the construction elements including: completed construction links, storage locations of construction equipment, and stacking conditions of construction materials;

[0050] Progress quantification: Quantify the current construction progress according to the construction elements, obtain quantitative indicators, and use the quantitative indicators as the new current construction data.

[0051] By adopting the above technical solution, computer vision technology is used to identify construction elements in the third image (i.e., high-quality construction site images after preprocessing and selection), such as completed construction links, storage locations of construction equipment, and stacking of construction materials. This application can automatically and quickly extract key information from complex images, reducing the subjectivity and errors of manual judgment. According to the results of image recognition, the current construction progress is quantified to obtain specific quantitative indicators, including the percentage of completed construction links, the efficiency of construction equipment, the consumption of construction materials, etc., providing managers with more objective and specific construction progress evaluation results. Through quantitative indicators, managers can more clearly understand the actual situation of the construction progress, timely discover potential problems and delay risks, and thus formulate more reasonable construction plans and resource allocation plans to optimize construction decisions. This application combines image recognition technology and BIM models to realize intelligent monitoring and evaluation of construction progress, providing managers with more timely and accurate decision support.

[0052] Optionally, after executing the progress quantification step and before executing the construction progress extraction step, the following step may be further included:

[0053] Get the planned construction time: Calculate the total duration T of the first construction plan progress. The calculation model is as follows:

[0054] ;

[0055] Among them, Q is the total construction volume, R is the total resource input, and S is the unit work efficiency;

[0056] First mapping: Map the current construction data to the first construction plan to obtain the construction duration corresponding to the current construction data in the first construction plan. , recorded as the first duration;

[0057] First calculation: calculate the first proportion of the first duration in the total duration , the calculation model is as follows:

[0058] .

[0059] By adopting the above technical solution, this application calculates the total duration T of the first construction plan (i.e., the planned construction time of the entire project), providing a benchmark for subsequent progress evaluation. By comparing the difference between the actual construction progress and the planned construction time, the speed of the construction progress can be evaluated, providing a basis for decision-making for managers. By mapping the current construction data to the first construction plan, the position of the current construction status in the plan can be accurately located. Through the mapping relationship, the current construction data can be compared with the planned construction data to find the differences and deviations between the two. This comparison helps to timely discover potential problems and risks, and provides a basis for subsequent adjustments and optimizations. By calculating the first proportion of the first duration in the total duration, the completion of the current construction progress can be quantified. The first proportion can intuitively reflect the speed and completion of the construction progress. According to the proportion, managers can determine whether it is necessary to adjust the construction strategy, increase resource investment, or optimize the construction process, etc., to ensure that the construction project proceeds smoothly as planned.

[0060] Optionally, after executing the step of extracting the construction progress and before executing the step of retrieving the construction plan, the following steps may be further included:

[0061] Second calculation: Get the construction duration of the second construction plan , recorded as the second duration;

[0062] Third calculation: calculate the second proportion of the second duration in the total duration , the calculation model is as follows:

[0063] .

[0064] By adopting the above-mentioned technical solution, the present application obtains the construction duration of the second plan through the second calculation step, and obtains the second proportion of the second duration in the total duration through the third calculation step, quantifies the progress of the second construction plan relative to the entire construction project, and obtains the proportion of the second construction plan corresponding to the current time in the first construction plan to the total duration of the entire first construction plan.

[0065] Optionally, in the step of obtaining the construction progress deviation, by comparing the first proportion and the second proportion , and obtain the construction progress deviation.

[0066] By adopting the above technical solution, this application compares the values ​​of the first proportion (the proportion of the current construction data in the total duration) and the second proportion (the proportion of the second construction plan in the total duration), and can accurately obtain the deviation of the construction progress. This application maps the current construction progress to the first construction plan, calculates the proportion of the duration in the first construction plan in the total duration, and obtains the first proportion; and in the first construction plan, the current time should correspond to the construction duration of the second construction plan (the second duration), calculates the proportion of the second duration in the total duration, and obtains the second proportion; this application maps the current construction progress and the planned construction progress to the first construction plan, uses the first construction plan as a unified reference framework, and places the actual construction progress and the expected construction progress plan on the same timeline for comparison, so that the comparison result is more accurate and obvious.

[0067] Optionally, after executing the first determination step and before executing the construction plan adjustment step, the method further includes:

[0068] Early warning: When the construction progress deviation is greater than the preset construction progress deviation threshold, an early warning will be issued for the lagging construction link.

[0069] By adopting the above technical solution, this application sets up an early warning mechanism, which can immediately detect problems when there are significant deviations in the construction progress. By establishing an early warning threshold and issuing an early warning when the deviation exceeds the threshold, managers can manage and control this risk more systematically. The enhancement of this risk management capability helps to improve the overall stability and reliability of the construction project.

[0070] In a second aspect, the present invention provides a BIM-based construction progress management system, which adopts the following technical solution:

[0071] A BIM-based construction progress management system includes the following steps:

[0072] Modeling module, used to build BIM models;

[0073] Planning module, used to formulate construction plans for projects;

[0074] The construction progress assessment module is used to collect the current construction site image, extract the current construction data based on the current construction site image, and obtain the current construction progress; compare the current construction progress with the progress of the construction plan to obtain the construction progress deviation;

[0075] A judgment module, which is in communication with the construction progress assessment module and is used to determine whether to adjust the construction plan;

[0076] Construction plan adjustment module: includes a first adjustment unit and a second adjustment unit, which are used to analyze the construction progress deviation and obtain the influencing factors; when the influencing factors are work efficiency parameters, the first adjustment unit obtains and adjusts the construction links whose work efficiency is lower than the preset threshold by evaluating the construction plan; when the influencing factors are resource parameters, the second adjustment unit adjusts the construction plan according to the resource parameters.

[0077] By adopting the above technical solution, the construction progress evaluation module of the present application obtains the current construction site image in real time, and uses image recognition technology to extract the current construction data. The current construction data is compared with the construction plan progress, and the construction progress deviation can be calculated quickly and accurately. The construction progress evaluation module provides strong support for timely discovery of construction progress problems. The judgment module intelligently judges whether the construction plan needs to be adjusted based on the results of the construction progress evaluation. This judgment is based on preset rules or algorithms, and can comprehensively consider the size of the construction progress deviation, the scope of influence, and the overall progress requirements of the project, so as to make reasonable decisions. When the judgment module decides that the construction plan needs to be adjusted, the construction plan adjustment module will play a role. The module includes a first adjustment unit and a second adjustment unit, which are adjusted for different types of influencing factors respectively. The first adjustment unit adjusts the work efficiency parameters, and proposes improvement measures and adjusts the plan by evaluating the construction links with low work efficiency in the construction plan. This helps to improve construction efficiency and reduce time delays. The second adjustment unit adjusts the resource parameters, and adjusts the construction plan according to the actual situation of the resource parameters (such as insufficient material supply, shortage of personnel, etc.), which helps to optimize resource allocation and ensure the smooth progress of the construction project. This system integrates a series of functional modules and realizes the refined management of construction projects through close collaboration of BIM modeling, construction plan formulation, construction progress evaluation, judgment and adjustment. This can not only improve construction efficiency and quality, but also reduce construction risks and ensure that the project is completed on time and with quality.

[0078] In summary, the present application includes at least one of the following beneficial technical effects:

[0079] 1. This application establishes a BIM model, so that the construction team can understand the design intent and engineering details more accurately, and reduce rework and delays caused by misunderstandings or poor communication. By collecting and extracting the construction progress in real time, managers can quickly grasp the actual progress of the project, adjust the plan in time, and ensure that the construction activities proceed as planned. When it is found that the deviation of the construction progress is caused by resource parameters (including insufficient resources or unreasonable allocation), in order to ensure that the key construction links are supported by sufficient resources, the construction plan is adjusted according to the resource parameters through the second adjustment step to achieve optimal allocation of resources, reduce waste, and improve overall construction efficiency. When it is found that the deviation of the construction progress is caused by the work efficiency parameter, this application will evaluate the first construction plan, obtain the construction links with work efficiency lower than the preset threshold, and make adjustments, so as to achieve a reasonable arrangement of the construction process or construction links. Through in-depth analysis of the deviation of the construction progress and its influencing factors, potential risk factors can be identified in advance, and corresponding countermeasures can be formulated to effectively reduce project risks. By monitoring the construction progress in real time, managers can respond to emergencies quickly and reduce their impact on the overall progress of the project.

[0080] 2. This application uses the Three.js library to load the lightweight 3D Tiles file, and through the steps of accessing objects, the fourth judgment, and the first information extraction, the attribute information of the BIM model is completely retained. Specifically, for each object in the 3D Tiles file, it is first determined whether there is additional information. If so, the BIM attributes are extracted from the additional information; if not, the BIM attribute information is extracted from the 3D Tiles file through the first information extraction step. Finally, the LOD (Levels of Detail) level is set according to the camera's viewing angle and distance, and the first tile is rendered in combination with the BIM attribute information, realizing real-time interaction and smooth rendering of the BIM model. While retaining the key information of the BIM model, through the steps of data division, cone cutting, format conversion, lightweight processing and model reconstruction, the efficient loading and smooth rendering of the BIM model are realized, providing strong technical support for the widespread application of BIM technology.

[0081] 3. This application compares the values ​​of the first proportion (the proportion of the current construction data in the total duration) and the second proportion (the proportion of the second construction plan in the total duration), and can accurately obtain the deviation of the construction progress. This application maps the current construction progress to the first construction plan, calculates the proportion of the duration in the first construction plan in the total duration, and obtains the first proportion; and in the first construction plan, the current time should correspond to the construction duration of the second construction plan (the second duration), calculates the proportion of the second duration in the total duration, and obtains the second proportion; This application maps the current construction progress and the planned construction progress to the first construction plan, uses the first construction plan as a unified reference framework, and places the actual construction progress and the expected construction progress plan on the same timeline for comparison, so that the comparison result is more accurate and obvious.

[0082] 4. The construction progress assessment module of the present application obtains the current construction site image in real time and extracts the current construction data using image recognition technology. The current construction data is compared with the construction plan progress, and the construction progress deviation can be calculated quickly and accurately. The construction progress assessment module provides strong support for timely discovery of construction progress problems. The judgment module intelligently judges whether the construction plan needs to be adjusted based on the results of the construction progress assessment. This judgment is based on preset rules or algorithms, and can comprehensively consider the size of the construction progress deviation, the scope of influence, and the overall progress requirements of the project, so as to make reasonable decisions. When the judgment module decides that the construction plan needs to be adjusted, the construction plan adjustment module will play a role. The module includes a first adjustment unit and a second adjustment unit, which are adjusted for different types of influencing factors respectively. The first adjustment unit adjusts the work efficiency parameters, and proposes improvement measures and adjusts the plan by evaluating the construction links with low work efficiency in the construction plan. This helps to improve construction efficiency and reduce time delays. The second adjustment unit adjusts the resource parameters and adjusts the construction plan according to the actual situation of the resource parameters (such as insufficient material supply, shortage of personnel, etc.), which helps to optimize resource allocation and ensure the smooth progress of the construction project. This system integrates a series of functional modules and realizes the refined management of construction projects through close collaboration of BIM modeling, construction plan formulation, construction progress evaluation, judgment and adjustment. This can not only improve construction efficiency and quality, but also reduce construction risks and ensure that the project is completed on time and with quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0083] Figure 1 is a flow chart of Example 1 of the present application;

[0084] Figure 2 is a flow chart of the model optimization step S3 of Example 1 of the present application;

[0085] Figure 3is a flowchart of the construction progress assessment step S4 of Example 1 of the present application;

[0086] Figure 4 is a flowchart of step S6 of adjusting the construction plan in Example 1 of the present application;

[0087] Figure 5 It is a structural diagram of Example 2 of the present application. DETAILED DESCRIPTION

[0088] The following combination Figures 1 to 5 This application is described in further detail.

[0089] Embodiment 1: This embodiment discloses a construction progress management method based on BIM, referring to Figure 1 The management method includes: a modeling step S1, a plan making step S2, a model optimization step S3, a construction progress evaluation step S4, an early warning S5, and a construction plan adjustment step S6. First, a BIM model of the current construction project is established, and then a first construction plan is made, and then the BIM model is optimized, and then the current construction progress and the second construction plan are compared to determine whether the construction plan needs to be adjusted. If so, it is further determined whether the factors affecting the construction progress are work efficiency factors, resource factors, or other factors. If it is a work efficiency factor, the first construction plan is evaluated, and the construction links whose efficiency is lower than the preset threshold are adjusted. If it is a resource parameter, the first construction plan is adjusted according to the resource parameter. If it is other factors, the subsequent construction is continued according to the first construction plan. This embodiment also issues an early warning for the construction link whose construction progress deviation is greater than the preset construction progress deviation threshold.

[0090] This embodiment includes the following steps:

[0091] S1 Modeling: Establish a BIM model based on the current project plan and information (covering the structure, electrical, mechanical, piping and other systems of the target building), and the BIM model contains detailed design information and component properties.

[0092] S2 Plan making: Based on the BIM model, combined with the project objectives and construction period, a detailed first construction plan is made. In the first construction plan, the construction tasks, time arrangements and resource requirements of each construction link are clearly defined to ensure the rationality and feasibility of the first construction plan.

[0093] like Figure 2 As shown, the model optimization step S3 includes a time node acquisition step S31, a first model optimization step S32 and a second model optimization step S33.

[0094] S31 Obtaining time nodes: Obtaining the time periods corresponding to the various construction links in the first construction plan, and obtaining the time nodes corresponding to the start and end of the current construction link.

[0095] First, comprehensively review the overall schedule of the project, including all listed construction links and their dependencies. Secondly, clarify the specific content, scope and objectives of each construction link to ensure the accuracy of the time nodes. Thirdly, extract the start date and expected end date of each construction link from the first construction plan one by one. These start date and expected end date information may be presented in the form of calendar date, working days or relative time (such as the Xth day from the start of the project). Finally, when analyzing the time nodes, it is also necessary to consider the buffer time (such as project delay risk buffer) and floating time (time flexibility between tasks) that may be included in the first construction plan to ensure the flexibility and feasibility of the project construction.

[0096] S32 first model optimization: after obtaining detailed time node information in the time node obtaining step S31, the time node information is integrated into the BIM model (building information model) to create a 4D dynamic BIM model integrating the time dimension.

[0097] First, the time node data obtained in the step S31 of obtaining the time node is sorted into a format recognizable by the BIM software, such as a CSV file or a database entry. Secondly, use BIM software (such as Revit, Navisworks, BIM 360, etc.) to open or create a BIM model of the project, import the time node data into the BIM model through the API or built-in function of the software, and assign the corresponding start time and end time to each construction link. Thirdly, set the timeline in the BIM model to ensure that the time nodes can be clearly displayed along the timeline. The timeline is set to calendar date, working day or relative time format according to project needs. Thirdly, use the dynamic simulation function of the BIM software to display the progress of the construction link over time, including simulating the material entry, equipment installation, personnel deployment, etc. during the construction process, to help the project team better understand the project progress and potential risks. Thirdly, the administrator can more easily discover potential conflicts between construction links (such as resource conflicts, space conflicts, etc.) by adding a 4D dynamic BIM model with a time dimension. Once a conflict is found, the project team can directly adjust and optimize it in the BIM model to reduce changes on the construction site and delays in the construction progress. Finally, a BIM model report containing time node information is generated, including a schedule diagram, timeline view, etc., for the project team and stakeholders to review and discuss.

[0098] The second model optimization step S33 includes a hierarchical structure construction step S331, a format conversion step S332, a lightweight processing step S333 and a model reconstruction step S334.

[0099] The step S331 of constructing a hierarchical structure includes a data division step S3311 and a frustum reduction step S3312.

[0100] S3311 Data division: Divide the BIM model obtained in the first model optimization step S32 into multiple tiles, and assign different LOD (Level of Detail) levels to each tile. Each tile represents a part of the BIM model and has different levels of accuracy. These tiles can dynamically load and display different parts of the model according to the user's current perspective and the level of detail that needs to be loaded. When the user moves the perspective or changes the zoom level, the system dynamically loads new tiles and unloads tiles that are no longer needed to maintain effective use of memory, thereby improving performance and user experience.

[0101] In order to improve the loading speed, the tiles that the user has recently visited can be stored in the local cache. When the user visits these tiles again, they can be read directly from the cache without re-downloading.

[0102] S3312 View frustum culling: Based on the camera's view angle and distance, determine the tile that can be seen from the current view angle, recorded as the first tile. View frustum culling is an optimization technique that reduces the amount of model data that needs to be rendered, because only the part within the camera's field of view will be loaded and rendered.

[0103] In this embodiment, the frustum clipping step S3312 uses the octree spatial index method to remove invisible tiles according to the viewpoint and only draw the first tile, specifically: by constructing a cube area, which is the minimum range containing all tiles, the cube is divided into eight equal-sized first cubes along three different directions of the cube (in principle, the center of gravity of the cube is used as the origin of the coordinate system, each coordinate axis is parallel to the corresponding edge of the cube, and the cube is divided along the direction of the three coordinate axes). Then, the division is continued in each first cube until the number of first tiles contained in each divided cube is less than the preset tile number threshold, and the division is stopped. Then, the corresponding relationship between each cube and the first tile is established through the MORTON code. When the user views the BIM model of the project from a certain perspective, the corresponding first tile is retrieved through the cube for display.

[0104] S332 format conversion: Extract the geometric information of the first tile in the IFC (Industry Foundation Classes) file, and convert it into 3D Tiles format by reconstructing and changing the format of the data (using CGAL, PCL, etc. to convert the geometric information into a triangle mesh, because 3D Tiles mainly supports mesh-based geometric representation). 3D Tiles is an open standard designed for web maps and 3D models, which supports efficient data transmission and rendering.

[0105] S333 lightweight processing: Use the Draco (Dynamic Range Adaptive COdec) compression algorithm to compress the geometric data in the 3DTiles file (lightweight processing). The Draco compression algorithm is an efficient open source geometry compression library that can significantly reduce the size of the model file while maintaining high-quality visual effects, which is especially important for network transmission and client rendering.

[0106] The model reconstruction step S334 includes a file loading step S3341, an object access step S3342, a fourth judgment step S3343, a first information extraction step S3344, a LOD level determination step S3345 and a tile rendering step S3346.

[0107] S3341 file loading: Use the Three.js library (a popular JavaScript 3D library) to load lightweight 3D Tiles files.

[0108] S3342 Access Objects: Traverse each object in the 3D Tiles file for subsequent information extraction and rendering.

[0109] S3343 Fourth judgment: For each object, determine whether there is additional information (by checking the specific attributes of each object, or the associated attribute set to determine whether there is additional information). If so, extract the BIM attributes from the additional information. If not, execute the first information extraction step S3344.

[0110] S3344 First information extraction: Extract the BIM attribute information of each object in the 3D Tiles file. The BIM attribute information includes: material, size, manufacturer data, etc.

[0111] S3345 Determine the LOD level: dynamically set the detail level of the BIM model according to the camera's viewing angle and distance. When the camera is far away from the BIM model, a lower LOD level can be used to reduce the complexity of rendering and improve performance; when the camera is close to the BIM model, a higher LOD level is used to display more details. In this embodiment, the correspondence between the BIM model and the LOD level is shown in Table 1. For each additional LOD level, the BIM model adds new content on the original basis.

[0112] Table 1 Correspondence between BIM model and LOD level

[0113]

[0114] In this embodiment, the correspondence between the camera distance and the LOD level is shown in Table 2. The camera distance refers to the minimum distance between the camera and the building in the BIM model, in meters.

[0115] Table 2 Correspondence between camera distance and LOD level

[0116]

[0117] S3346 Tile Rendering: Render the first tile by combining LOD level and BIM attribute information. The rendering process will take into account multiple factors such as lighting, shadows, textures, etc. to generate realistic 3D visual effects. Users will see the optimized and rendered BIM model on the screen, and provide relevant construction data in subsequent steps.

[0118] like Figure 3 As shown, the construction progress assessment step S4 includes a construction image acquisition step S401, an image processing step S402, an image recognition step S403, a progress quantification step S404, an acquisition of a planned construction time step S405, a first mapping step S406, a first calculation step S407, an extraction of a construction progress step S408, a second calculation step S409, a third calculation step S410, a construction plan retrieval step S411, an acquisition of a construction progress deviation step S412 and a first judgment step S413.

[0119] S401 collects construction images: uses drones, cameras and other equipment to collect images of the current construction site, records them as the first image, and simultaneously obtains current construction data, such as completed project volume, personnel attendance, etc.

[0120] The image processing step S402 includes an image preprocessing step S4021 and an image selection step S4022.

[0121] S4021 Image preprocessing: cleaning the first image to obtain a second image, wherein the cleaning operation includes: denoising, enhancing image contrast, adjusting image brightness, and adjusting image color.

[0122] S4022 Image selection: Screen out an image suitable for further analysis from the second image and record it as the third image.

[0123] S403 Image recognition: using computer vision technology to recognize construction elements in the third image to support quantification of construction progress, the construction elements include: completed construction links, storage locations of construction equipment, and stacking conditions of construction materials.

[0124] S404 Progress Quantification: Quantify the current construction progress according to the construction elements, obtain quantitative indicators, and use the quantitative indicators as new current construction data. The quantitative indicators include: the percentage of completed construction links, the efficiency of construction equipment, the consumption of construction materials, etc.

[0125] S405 Obtaining the planned construction time: Calculate the total duration T of the first construction plan progress. The calculation model is as follows:

[0126] ;

[0127] Among them, Q is the total construction volume, which is determined by statistical analysis based on the design drawings, bill of quantities, technical specifications and other documents of the project. R is the total resource input, which is set according to expert experience and obtained through statistical analysis. S is the unit work efficiency, which refers to the amount of work that can be completed by a unit resource (such as a worker or a machine) in a unit time (such as an hour or a day). It is set according to expert experience and obtained through statistical analysis.

[0128] According to the experience of experts, the total resource input R and unit work efficiency S are set. Taking "Project A: Medium-sized Residential Building" as an example, further explanation is given:

[0129] Setting of total resource input R:

[0130] Expert team formation: The project team first formed an expert team consisting of senior project managers, architects, engineers, cost control experts, etc.

[0131] Historical project analysis: The expert team referred to the company's past resource input data for projects of similar scale, including labor, machinery and equipment, materials, etc.

[0132] Labor: 500 workers, evenly distributed over the project period (assuming one year), which is about 15 workers per day (this is just an example; in actual projects, labor input will be adjusted dynamically based on construction progress and demand).

[0133] Mechanical equipment: 10 excavators, 20 transport vehicles, 5 tower cranes, etc. (the specific number depends on the project scale and construction requirements).

[0134] Materials: XX tons of steel, XX tons of cement, XX cubic meters of sand, etc. (the specific quantity needs to be calculated based on the design drawings and the bill of quantities).

[0135] Expert experience judgment: Based on historical project data, market research results and the experts' own experience, the team made a preliminary estimate of the resources required for this project. Taking into account the complexity of the project, the construction period requirements and potential risk factors, the expert team finally determined the total resource investment R, including the specific quantity of different types of resources required for each construction stage.

[0136] Setting of unit ergonomics S:

[0137] Task decomposition: The project team first breaks down the entire project into several specific construction tasks, such as foundation construction, main structure construction, decoration projects, etc.

[0138] Work efficiency evaluation: For each construction task, the team invited workers, team leaders or technicians with rich construction experience to conduct an evaluation. Based on their own experience, they estimated the amount of work that could be completed in a unit of time (such as a day or a week).

[0139] Statistical analysis: The team collected multiple evaluation results and conducted statistical analysis to eliminate the bias of individual evaluations and obtain a more accurate unit work efficiency S. This value reflects the amount of work that a worker or a machine can complete in a unit of time under specific conditions. For example: Based on expert experience and statistical analysis, the amount of work that a skilled concrete worker can complete in a day (calculated on an 8-hour work system) (i.e., unit work efficiency S) may be:

[0140] Pouring concrete: 20-25 cubic meters (this value fluctuates depending on factors such as the workers' technical level, construction environment, and project requirements).

[0141] Dynamic adjustment: Unit work efficiency S is not fixed. With the improvement of construction technology, the improvement of workers' skills and changes in external conditions (such as weather, material supply, etc.), the unit work efficiency may change. Therefore, the project team needs to continuously monitor the changes in unit work efficiency during the construction process and make dynamic adjustments based on actual conditions.

[0142] S406 First mapping: Mapping the current construction data to the first construction plan to obtain the construction duration corresponding to the current construction data in the first construction plan , recorded as the first duration.

[0143] S407 First calculation: Calculate the first proportion of the first duration in the total duration , the calculation model is as follows:

[0144] .

[0145] S408 Extracting construction progress: extracting the current construction progress based on the first image and the current construction data.

[0146] S409 Second calculation: obtaining the construction duration of the second construction plan , recorded as the second duration;

[0147] S410 Third calculation: calculating the second proportion of the second duration in the total duration , the calculation model is as follows:

[0148] .

[0149] S411 retrieves the construction plan: in the BIM model, retrieves the current progress of the first construction plan and records it as the second construction plan.

[0150] S412 obtains construction progress deviation: by comparing the first proportion and the second proportion The value of the construction progress deviation is obtained, and the calculation method is: Construction progress deviation = first proportion - The second largest proportion .

[0151] In other embodiments, in the step S412 of obtaining the construction progress deviation, a BIM analysis tool is used to compare and analyze the current construction progress and the second construction plan to obtain the construction progress deviation.

[0152] S413 First judgment: judge whether the construction progress deviation is greater than the preset construction progress deviation threshold. If so, execute the construction plan adjustment step S6; if not, execute the construction image acquisition step S401 after an interval t.

[0153] S5 warning: When the construction progress deviation is greater than the preset construction progress deviation threshold, a warning is issued for the lagging construction link.

[0154] like Figure 4 As shown, the construction plan adjustment step S6 includes an influencing factor acquisition step S61, an input step S62, a second judgment step S63, a third judgment step S64, a first adjustment step S65 and a second adjustment step S66.

[0155] S61 Obtaining influencing factors: Analyzing the construction progress deviation based on expert experience, and obtaining influencing factors of the construction progress deviation by analyzing the construction progress deviation, wherein the influencing factors include: work efficiency parameters, resource parameters and other parameters.

[0156] The analysis of construction progress deviation based on expert experience is further explained using "Project B: High-rise Residential Building" as an example:

[0157] Project B, a high-rise residential building construction project, was originally planned to complete the main structure construction and decoration works within two years and meet the delivery conditions. However, one and a half years into the project, it was found that the actual construction progress was seriously behind the planned progress and it was expected that it would not be completed on schedule. After forming an expert team, the construction deviation was analyzed and the following influencing factors were identified:

[0158] Ergonomic parameters:

[0159] Technical construction difficulties: During the construction of the high-rise main structure, technical difficulties such as difficulties in concrete pumping and low efficiency in steel bar tying were encountered, which slowed down the construction speed.

[0160] Insufficient skills of construction workers: Some newly joined construction workers are not familiar with high-rise building construction technology and safety regulations, which affects construction efficiency and quality.

[0161] Resource parameters:

[0162] Delay in material supply: Due to changes in market supply and demand, some key materials such as high-performance concrete and special steel are in short supply, resulting in delays in material arrival.

[0163] Frequent equipment failures: Construction machinery and equipment are aging and not maintained in a timely manner, resulting in frequent failures during the construction process, affecting the construction progress.

[0164] Other parameters:

[0165] Weather factors: The project site encountered multiple heavy rains and typhoons during the construction period, resulting in severe waterlogging at the construction site and making normal operations impossible.

[0166] S62 Input: Input the factors affecting the construction progress deviation into the system.

[0167] S63 second judgment: determine whether the influencing factor input in step S62 is a work efficiency parameter (such as worker skill level, construction method efficiency, etc., and quantitative indicators related to work efficiency). If so, execute the first adjustment step S65; if not, execute the third judgment step S64.

[0168] S64 The third judgment: Determine whether the influencing factors input in step S62 are resource parameters (such as material supply, equipment configuration, labor allocation, etc., and quantitative indicators related to resources). If so, execute the second adjustment step S66; if not, classify the influencing factors as other factors (such as weather, policy changes, etc.), and continue construction according to the first construction plan.

[0169] S65 First Adjustment: Evaluate the first construction plan, obtain and adjust the construction links whose efficiency is lower than the preset threshold. Analyze the reasons for the low efficiency of these links, which may be improper construction methods, insufficient worker skills, etc., take corresponding measures to improve the efficiency, such as improving construction methods, training workers, etc., recalculate the construction time according to the adjusted efficiency, and update the first construction plan.

[0170] S66 Second adjustment: Analyze whether the current resource allocation is reasonable based on the actual situation of resource parameters (such as material supply, equipment configuration, labor allocation, etc.). If it is found that the resource allocation is insufficient or unreasonable, formulate an adjustment plan, such as increasing material supply, deploying more equipment, reallocating labor, etc., modify the first construction plan according to the adjustment plan, and generate the third construction plan.

[0171] Ensure that the resource allocation in the third construction plan can meet the construction needs and complete the construction tasks within the specified time.

[0172] This application proposes a construction progress management method based on BIM, by integrating BIM modeling, planning, progress monitoring and dynamic adjustment. By constructing a sophisticated BIM model, comprehensive data support is provided for the project; then, a detailed construction plan is formulated based on the model information to ensure that all links are closely connected. During the construction process, on-site images are collected in real time to evaluate the current construction progress, and accurately compared with the planned progress in the BIM model to quickly identify construction progress deviations. Based on the analysis of construction progress deviations, this application automatically determines whether the construction plan needs to be adjusted, and intelligently selects the adjustment path: for work efficiency factors, optimize construction methods or improve workers' skills; for resource factors, dynamically allocate materials, equipment and manpower to ensure efficient use of resources. Through technology empowerment, this method realizes the refinement and intelligence of construction management, effectively improves the efficiency and flexibility of project execution, and injects new impetus into the sustainable development of the construction industry.

[0173] Example 2: This example discloses a BIM-based construction progress management system. Figure 5 , the management system comprises:

[0174] Modeling module, this module is responsible for creating and maintaining BIM models. BIM models are three-dimensional digital models that integrate all information of a building project, including structural design, building materials, construction progress, and other information.

[0175] The planning module is used to develop a detailed construction plan for the project based on the BIM model and project requirements.

[0176] The construction progress assessment module is used to extract the current construction data and obtain the current construction progress based on the current construction site image; compare the current construction progress with the construction plan progress in the BIM model, calculate and output the construction progress deviation, that is, the difference between the actual construction progress and the planned progress;

[0177] The judgment module is in communication with the construction progress evaluation module and is used to analyze whether the construction progress deviation exceeds a preset construction progress deviation threshold and determine whether the construction plan needs to be adjusted.

[0178] Construction progress adjustment module: includes a first adjustment unit and a second adjustment unit, which are used to analyze construction deviations and obtain influencing factors; when the influencing factor is a work efficiency parameter, the first adjustment unit evaluates the construction plan. This unit evaluates the work efficiency of each construction link in the construction plan, identifies and adjusts the construction links whose work efficiency is lower than the preset threshold, which may include improving construction methods, improving workers' skills, etc., and updates the construction plan to reflect the expected progress after the work efficiency adjustment; when the influencing factor is a resource parameter, the second adjustment unit adjusts the construction plan according to the resource parameter to ensure that resources are effectively utilized to meet construction needs.

[0179] This application provides a BIM-based construction progress management system that integrates functions such as establishing a BIM model, formulating a construction plan, and evaluating and dynamically adjusting the construction progress. A detailed BIM model is established through the modeling module to provide an accurate information basis for the project. The planning module formulates a detailed construction plan based on the BIM model to ensure that the construction is carried out in an orderly manner. The construction progress evaluation module uses real-time construction image data to extract the current construction status and compare it with the planned progress in the BIM model to accurately calculate the construction progress deviation. The judgment module makes an intelligent decision whether to start the adjustment process based on the deviation. Once adjustment is required, the construction progress adjustment module immediately intervenes, which is divided into two adjustment paths: work efficiency parameters and resource parameters: if work efficiency is low, the construction method is optimized or the worker's skills are improved; if resources are insufficient, materials, equipment and manpower are reconfigured to ensure efficient use of resources. The entire system significantly improves construction efficiency and reduces the risk of delays through automated and intelligent management processes, providing strong support for construction projects.

[0180] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A construction progress management method based on BIM, characterized in that: include: Modeling: Building BIM models; Make a plan: Based on the BIM model, combined with the project goals and construction period, make the first construction plan; Get time nodes: Get the time periods corresponding to each construction link in the first construction plan, and get the start and end time nodes of the current construction link; First model optimization: add time nodes to the BIM model to obtain a new BIM model; Second, model optimization: including building a hierarchical structure, format conversion, lightweight processing, and model reconstruction steps; Building a hierarchical structure: including data partitioning and frustum reduction steps; Data partitioning: The BIM model obtained in the first model optimization step is divided into multiple tiles with different accuracy levels; View frustum clipping: According to the camera's viewing angle and distance, determine the tile that can be seen from the current viewing angle, recorded as the first tile; Format conversion: extract the geometric information of the first tile in the IFC file, and obtain the 3D Tiles file by reconstructing and changing the format of the data; Lightweight processing: Use the Draco compression algorithm to lightweight the geometric data in the 3D Tiles file; Model reconstruction: including file loading, object access, fourth judgment, first information extraction, LOD level determination and tile rendering steps; document Loading: Use the Three.js library to load the lightweight 3D Tiles file; Access objects: Access each object in the 3D Tiles file; Fourth judgment: for each object, judging whether there is additional information, if yes, extracting BIM attributes from the additional information, if no, executing the first information extraction step; First information extraction: extract the BIM attribute information of each object in the 3D Tiles file; Determine the LOD level: Set the LOD level according to the camera's viewing angle and distance; Tile rendering: Render the first tile based on the LOD level and BIM attribute information; Construction progress assessment: including collecting construction images, extracting construction progress, retrieving construction plans, obtaining construction progress deviations and the first judgment step; Collecting construction images: Collecting the current construction site image, recording it as the first image, and obtaining the current construction data; Image processing: including image preprocessing and image selection steps; Image preprocessing: cleaning the first image to obtain the second image, wherein the cleaning operation includes: denoising, enhancing image contrast, adjusting image brightness, and adjusting image color; Image selection: screening the second image to obtain a third image, and using the third image as a new construction site image; Image recognition: using computer vision technology to recognize construction elements in the third image, the construction elements including: completed construction links, storage locations of construction equipment, and stacking conditions of construction materials; Progress quantification: Quantify the current construction progress according to the construction elements, obtain quantitative indicators, and use the quantitative indicators as new current construction data; Get the planned construction time: Calculate the total duration T of the first construction plan progress. The calculation model is as follows: ; Among them, Q is the total construction volume, R is the total resource input, and S is the unit work efficiency; First mapping: Map the current construction data to the first construction plan to obtain the construction duration corresponding to the current construction data in the first construction plan. , recorded as the first duration; First calculation: calculate the first proportion of the first duration in the total duration , the calculation model is as follows: ; Extracting construction progress: extracting the current construction progress based on the first image and the current construction data; Second calculation: Get the construction duration of the second construction plan , recorded as the second duration; Third calculation: calculate the second proportion of the second duration in the total duration , the calculation model is as follows: ; Retrieve the construction plan: In the BIM model, retrieve the current corresponding first construction plan progress and record it as the second construction plan; Obtain construction progress deviation: Compare and analyze the current construction progress and the second construction plan to obtain the construction progress deviation; First judgment: judging whether the construction progress deviation is greater than a preset construction progress deviation threshold, if so, executing the step of adjusting the construction plan; if not, executing the step of collecting construction images after an interval of time t; Adjust the construction plan: including obtaining influencing factors, second judgment, third judgment, first adjustment and second adjustment steps; Obtain influencing factors: Obtain influencing factors of construction progress deviation by analyzing the deviation of construction progress; Second judgment: judging whether the influencing factor is an ergonomic parameter, if so, executing the first adjustment step; if not, executing the third judgment step; Third judgment: judging whether the influencing factor is a resource parameter, if so, executing the second adjustment step; if not, continuing to construct according to the first construction plan; First adjustment: Evaluate the first construction plan, obtain and adjust the construction links whose efficiency is lower than the preset threshold; Second adjustment: adjust the first construction plan according to resource parameters to obtain the third construction plan; In the step of obtaining the construction progress deviation, by comparing the first proportion and the second proportion , and obtain the construction progress deviation.

2. The BIM-based construction progress management method according to claim 1, characterized in that: After executing the first determination step and before executing the construction plan adjustment step, the method further includes: Early warning: When the construction progress deviation is greater than the preset construction progress deviation threshold, an early warning will be issued for the lagging construction link.

3. A BIM-based construction progress management system, the management system is applicable to the management method according to any one of claims 1-2, characterized in that: include: Modeling module, used to build BIM models; Planning module, used to formulate construction plans for projects; The construction progress assessment module is used to collect the current construction site image, extract the current construction data based on the current construction site image, and obtain the current construction progress; compare the current construction progress with the progress of the construction plan to obtain the construction progress deviation; A judgment module, which is in communication with the construction progress assessment module and is used to determine whether to adjust the construction plan; Construction plan adjustment module: includes a first adjustment unit and a second adjustment unit, which are used to analyze the construction progress deviation and obtain the influencing factors; when the influencing factors are work efficiency parameters, the first adjustment unit obtains and adjusts the construction links whose work efficiency is lower than the preset threshold by evaluating the construction plan; when the influencing factors are resource parameters, the second adjustment unit adjusts the construction plan according to the resource parameters.