A smart operation and maintenance system for substations
Through the substation smart operation and maintenance system, big data and artificial intelligence technology are used for real-time monitoring and intelligent analysis, which solves the problems of high cost and low fault diagnosis efficiency of traditional operation and maintenance methods, and achieves active operation and maintenance of equipment and accuracy of fault handling. and efficiency improvement.
Patent Information
- Application Number
- CN202410981595.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-07-22
AI Technical Summary
Traditional substation operation and maintenance methods are costly and difficult to accurately determine the cause of faults, resulting in equipment that may be over-maintained or under-maintained, resulting in low efficiency. They also rely on experienced operation and maintenance personnel, and it is difficult for inexperienced personnel to accurately diagnose faults.
A smart substation operation and maintenance system is designed, including a data collection and preprocessing module, an equipment operation and maintenance knowledge graph building module, a dynamic alarm threshold calculation module, a maintenance time prediction module and a fault cause identification module, using big data and artificial intelligence technology. Real-time monitoring and intelligent analysis, by building equipment operation and maintenance knowledge maps, dynamically calculating alarm thresholds, predicting maintenance time and identifying fault causes.
It realizes active operation and maintenance of substation equipment, reduces operation and maintenance costs, improves the accuracy and efficiency of fault diagnosis, reduces systematic false alarms caused by environmental changes, and provides flexible operation and maintenance plans and targeted faults. treatment plan.
Smart Images

Figure CN118523503B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of substation management, and in particular to an intelligent operation and maintenance system for a substation. Background Art
[0002] Substation intelligent operation and maintenance technology refers to the technology that uses technical means such as big data and artificial intelligence to conduct real-time monitoring and intelligent analysis of the operating status of the substation.
[0003] Traditional operation and maintenance methods mainly rely on regular maintenance and post-maintenance models. Although regular maintenance ensures the regular maintenance of equipment, it is difficult to accurately capture the real-time operating status of the equipment, which often leads to wasteful over-maintenance of the equipment or hidden dangers of insufficient maintenance. Post-maintenance is only carried out after the equipment fails, which not only interrupts the normal operation of the substation, but also may increase additional maintenance costs due to delayed processing. In addition, when equipment failure occurs, traditional operation and maintenance methods usually rely only on the personal experience of the operation and maintenance personnel to determine the cause of the failure. This method is inefficient and highly dependent on experienced operation and maintenance personnel. For inexperienced operation and maintenance personnel, they may find it difficult to accurately diagnose the fault, resulting in repeated failures or unsatisfactory maintenance results. Summary of the invention
[0004] In view of this, the present invention aims to provide a smart operation and maintenance system for a substation, aiming to solve the problem that traditional operation and maintenance methods are high in cost and difficult to determine the cause of failures.
[0005] A substation intelligent operation and maintenance system, comprising:
[0006] Data collection and preprocessing module: collects equipment status data and equipment operation and maintenance documents and performs preprocessing to obtain preprocessed equipment status data and equipment operation and maintenance documents; the equipment includes cooling pipelines, transformers, current transformers and voltage transformers;
[0007] Equipment operation and maintenance knowledge graph construction module: constructs the equipment operation and maintenance knowledge graph based on the pre-processed equipment operation and maintenance documents;
[0008] Dynamic alarm threshold calculation module: Combines all equipment states, performs baseline state modeling, and calculates the upper and lower limits of the dynamic alarm threshold;
[0009] Maintenance time prediction module: If the equipment status is normal, the next maintenance time is predicted based on the pre-processed equipment status data;
[0010] Fault cause identification module: If the equipment status is abnormal, the fault cause is identified by combining the equipment operation and maintenance knowledge graph with the pre-processed equipment status data.
[0011] Furthermore, the operation steps of the data collection and preprocessing module include:
[0012] S11: Collect equipment status data and equipment operation and maintenance documents in the substation and perform pre-processing;
[0013] The equipment operation and maintenance document includes the equipment name, component name, fault type, fault cause, fault phenomenon, fault identification method, and fault handling record;
[0014] S12: For numerical data, missing values are filled using mean filling method;
[0015] S13: For text data, the HanLP tool is used to segment words and remove stop words; the full name of the HanLP tool is Chinese Character Language Processing Tool.
[0016] Furthermore, the step of processing the device status data includes:
[0017] S111: using the standard deviation method, identifying abnormal values of the equipment status data, and removing the identified abnormal values;
[0018] S112: The data after the outliers are removed is standardized using a Z-score method to obtain preprocessed device status data.
[0019] Furthermore, the operation steps of the equipment operation and maintenance knowledge graph construction module include:
[0020] S21: Perform named entity recognition on the preprocessed equipment operation and maintenance documents and create new nodes in the knowledge graph;
[0021] S22: For each named entity, perform relationship extraction and attribute extraction based on the pre-processed equipment operation and maintenance documents;
[0022] S23: Based on the extracted named entities, attributes, and relationships, a knowledge graph is constructed using MangoDB, where MangoDB is a database based on distributed file storage;
[0023] S24: For the constructed knowledge graph, eliminate redundant information, merge duplicate nodes, and obtain the equipment operation and maintenance knowledge graph; the knowledge graph contains node information and adjacency information, wherein the node information includes the named entity name, attribute, and relationship, and the adjacency information includes the adjacency matrix between nodes;
[0024] In the knowledge graph, the natural language descriptions in the equipment operation and maintenance documents are structured and mapped to nodes, attributes, and relationships in the knowledge graph, providing a data basis for subsequent analysis and reasoning of equipment failures and their treatment methods;
[0025] Furthermore, the operation steps of the dynamic alarm threshold calculation module include:
[0026] S31: Combine all equipment status data to perform benchmark status modeling and obtain a status benchmark value sequence. The calculation method is:
[0027]
[0028] in, is the reference state value sequence at the current time t, For fully connected network operation, is a gated recurrent unit operation, is the baseline state value sequence of the previous moment, is the preprocessed data vector of all device states at the current moment, and t is the index of the first moment;
[0029] S32: Output the upper and lower limits of the dynamic alarm threshold according to the state reference value sequence. The calculation method is:
[0030]
[0031]
[0032] in, is the upper limit of the dynamic alarm threshold at the current time t, is the lower limit of the dynamic alarm threshold at the current time t, For the first long short-term memory network operation, For the second long short-term memory network operation, is the upper limit of the dynamic alarm threshold at the previous moment, It is the lower limit of the dynamic alarm threshold at the previous moment;
[0033] The second long short-term memory network has the same network structure as the first long short-term memory network, but uses different parameter initialization methods; the first long short-term memory network uses random parameter initialization, and the second long short-term memory network uses the Xavier method for parameter initialization; wherein the Xavier method is also called Xavier initialization, which is a common method for initializing neural network weights, and the goal is to make each neuron keep the variance of input and output as equal as possible during the forward propagation process, so as to avoid the problem of gradient vanishing or gradient exploding in deep networks;
[0034] The baseline state modeling uses a gated recurrent unit to combine the state data of all devices to generate a baseline state value sequence, and combined with the calculation of dynamic thresholds, it can maintain accurate monitoring of the state of individual devices when the overall environment changes;
[0035] Compared with the traditional alarm method based on fixed thresholds, the present invention can calculate dynamic alarm thresholds according to the real-time changes in equipment status. In particular, when other modules are in normal status, anomalies can be identified by dynamically adjusting the upper and lower limits, reducing systematic false alarms caused by normal environmental changes, making the substation operation and maintenance system more accurate and flexible.
[0036] Furthermore, the maintenance time prediction module includes constructing a maintenance time prediction model to predict the next maintenance time based on the preprocessed equipment status data and the previous maintenance time; using the Monte Carlo simulation method to generate a sample set through the output and error distribution of multiple prediction models, sorting the sample set, and calculating the confidence interval of the next maintenance time.
[0037] The operation steps of the maintenance time prediction module include:
[0038] S41: Build a maintenance time prediction model to predict the next maintenance time based on the preprocessed equipment status data and the last maintenance time. The calculation method is:
[0039]
[0040]
[0041]
[0042]
[0043]
[0044] in, is the original time series feature at the current time t, is the original time series feature of the previous moment, is the vector obtained by concatenating the preprocessed equipment status data and the last maintenance time. is the context vector at the current time t, is the attention weight of time k for time t, is the original time series feature at time k, k is the index of the second time, To take the exponential operation of a natural constant, is the attention score of time k for time t, is the attention score of moment j for moment t, j is the index of the third moment, is the hyperbolic tangent function operation, is the first parameter matrix, is the second parameter matrix, is the first bias vector, is the predicted value of the next maintenance time, is the third parameter matrix, is the second bias vector;
[0045] S42: Monte Carlo simulation method is used to calculate the confidence interval of the next maintenance time. The calculation method is:
[0046] Generate samples by predicting the output and error distribution of the model, calculated as:
[0047]
[0048]
[0049] in, is the predicted value of the next maintenance time of the nth sample, n is the sample index, is the error distribution of the nth sample, is the normal distribution of the sample, is the sample mean, is the sample variance;
[0050] Perform multiple simulations to obtain a sample set ,in is the sample set, M is the number of samples;
[0051] Sort the sample set and calculate the upper and lower bounds of the confidence interval based on the confidence level. The calculation method is:
[0052]
[0053]
[0054] in, is the upper bound of the confidence interval, is the lower bound of the confidence interval, and c is the significance level;
[0055] Traditional methods usually estimate maintenance time based on simple statistical models, such as linear regression or time interval prediction based on fixed periods, which is difficult to capture the complex dynamic changes of equipment data. The present invention adds an attention mechanism on the basis of the gated recurrent unit to integrate historical and current information, analyze the importance of data at different times, and make the maintenance time prediction more accurate. In addition, after predicting the maintenance time, the present invention introduces the Monte Carlo simulation method to calculate the confidence interval and quantify the uncertainty of the prediction results, which not only provides specific time nodes, but also provides time ranges, making the operation and maintenance plan more flexible.
[0056] Furthermore, the fault cause identification module extracts key fault features from the status data of the abnormal equipment, generates a fault text description, and combines the equipment operation and maintenance knowledge graph to identify the fault cause and fault handling suggestions.
[0057] The operation steps of the fault cause identification module include:
[0058] S51: Extract key fault features from the status data of abnormal equipment, and the calculation method is:
[0059]
[0060] in, is the key fault feature at the current moment, It is a multi-scale convolutional long short-term memory network operation. is the key fault feature of the previous moment, is the preprocessed abnormal device status data vector at the current moment;
[0061] S52: Generate a fault text description based on the extracted key fault features. The calculation method is:
[0062]
[0063] in, is the generated fault text description, For the bidirectional autoregressive model operation, It is the concatenation vector of key fault type and fault description;
[0064] S53: Based on the generated fault text description and combined with the equipment operation and maintenance knowledge graph, the fault cause is identified. The calculation method is:
[0065]
[0066] in, is the representation vector of the equipment operation and maintenance knowledge graph, For graph neural network operations, It is the node information of the equipment operation and maintenance knowledge graph. is the adjacency matrix between nodes;
[0067] S54: searching the fault handling records for a matching historical fault handling record according to the identified fault cause, and generating a fault handling suggestion according to the matched historical fault handling record;
[0068] Compared with traditional methods, traditional fault feature extraction methods are usually based on simple rules or statistical methods, lack multi-scale analysis capabilities, and are difficult to capture complex fault modes. When generating fault descriptions, they rely on manual generation, are prone to subjective bias, and are inefficient. The present invention uses a multi-scale convolutional long short-term memory network to extract key fault features, captures fault features on different time scales from multi-scale convolutions, and better characterizes the complexity of abnormal states. A bidirectional autoregressive model is used to automatically generate fault text descriptions, which reduces the uncertainty and delay of manual descriptions and improves the accuracy of descriptions. In addition, the present invention combines graph neural networks and equipment operation and maintenance knowledge graphs, uses the relationship information between graph structures and nodes to identify fault causes, uses historical fault processing records in the knowledge graph, and combines current fault features to generate fault processing suggestions to ensure that the processing plan is more targeted, which not only improves the effectiveness of current fault processing, but also provides data support for future operation and maintenance, and improves the efficiency of smart operation and maintenance of substations.
[0069] Compared with the prior art, the advantages of the present invention are:
[0070] (1) In terms of the overall solution, the present invention uses equipment status data and equipment operation and maintenance documents to establish a substation intelligent operation and maintenance system, thereby realizing active operation and maintenance of substation equipment. At the same time, combined with historical fault handling records, an equipment operation and maintenance knowledge graph is established and fault causes are identified, so that inexperienced operation and maintenance personnel can also diagnose faults, thereby improving the level of intelligent operation and maintenance of substations and reducing substation operation and maintenance costs.
[0071] (2) In terms of algorithm improvement, the present invention adds an attention mechanism based on the recurrent gating unit, which improves the model's sensitivity to changes in device status and its ability to grasp the overall situation. At the same time, before generating the fault description, a multi-scale convolutional long short-term memory network is used to extract key fault features to better characterize the complexity of the abnormal state.
[0072] (3) In terms of operation and maintenance flexibility, after the present invention makes a prediction of the next operation and maintenance time, it uses the Monte Carlo method to simulate the prediction results and calculate the confidence interval to quantify the uncertainty of the prediction results, which not only provides the time node of the next operation and maintenance, but also provides the time range.
[0073] (4) The present invention proposes a method for calculating the dynamic alarm threshold. First, the baseline state is modeled based on the status of all equipment. Second, the dynamic alarm threshold is calculated based on the baseline state and the real-time changes in the equipment status. This method can maintain accurate monitoring of the status of individual equipment when the overall environment changes, reduce systematic false alarms caused by normal environmental changes, and make the substation operation and maintenance system more accurate and flexible. BRIEF DESCRIPTION OF THE DRAWINGS
[0074] Figure 1 A schematic diagram of the algorithm flow for calculating the dynamic alarm threshold provided by the present invention;
[0075] Figure 2 A schematic diagram of the algorithm flow for operation and maintenance time prediction provided by the present invention. DETAILED DESCRIPTION
[0076] The present invention is further described below in conjunction with the accompanying drawings, but the present invention is not limited in any way. Any changes or substitutions made based on the teachings of the present invention belong to the protection scope of the present invention.
[0077] Embodiment 1: A smart operation and maintenance system for a substation, including a data collection and preprocessing module, an equipment operation and maintenance knowledge graph construction module, a dynamic alarm threshold calculation module, a maintenance time prediction module, and a fault cause identification module. The details are as follows:
[0078] Data collection and preprocessing module: collects equipment status data and equipment operation and maintenance documents and performs preprocessing to obtain preprocessed equipment status data and equipment operation and maintenance documents; the equipment includes cooling pipelines, transformers, current transformers and voltage transformers; its operation steps include:
[0079] S1: Collect equipment status data and equipment operation and maintenance documents and perform preprocessing to obtain preprocessed equipment status data and equipment operation and maintenance documents;
[0080] S11: collecting equipment status data and equipment operation and maintenance documents in the substation, wherein the equipment operation and maintenance documents include equipment name, component name, fault type, fault cause, fault phenomenon, fault identification method, and fault handling record; the equipment includes cooling pipelines, transformers, current transformers, and voltage transformers;
[0081] Taking the cooling pipeline as an example, the equipment status data includes:
[0082] Pressure data: real-time pressure value of cooling pipeline, historical pressure change curve, etc.
[0083] Flow data: real-time flow value of cooling pipeline, historical flow change curve, etc.
[0084] Temperature data: Temperature values of the cooling line and all its surroundings, used to analyze cooling effects.
[0085] Energy consumption data: Energy consumption data of the cooling system, used to evaluate cooling efficiency.
[0086] S111: using the standard deviation method, identifying abnormal values of the equipment status data, and removing the identified abnormal values;
[0087] S112: After removing the outliers, the data is standardized using a Z-score method to obtain preprocessed device status data;
[0088] S12: For numerical data, missing values are filled using mean filling method;
[0089] S13: For text data, the HanLP tool is used to segment words and remove stop words; the full name of the HanLP tool is Chinese Character Language Processing Tool.
[0090] Equipment operation and maintenance knowledge graph construction module: constructs the equipment operation and maintenance knowledge graph based on the preprocessed equipment operation and maintenance documents; its operation steps include:
[0091] S2: Build the equipment operation and maintenance knowledge graph based on the preprocessed equipment operation and maintenance documents;
[0092] S21: Perform named entity recognition on the preprocessed equipment operation and maintenance documents and create new nodes in the knowledge graph;
[0093] S22: For each named entity, perform relationship extraction and attribute extraction based on the pre-processed equipment operation and maintenance documents;
[0094] S23: Based on the extracted named entities, attributes, and relationships, a knowledge graph is constructed using MangoDB, where MangoDB is a database based on distributed file storage;
[0095] S24: For the constructed knowledge graph, eliminate redundant information, merge duplicate nodes, and obtain the equipment operation and maintenance knowledge graph; the knowledge graph contains node information and adjacency information, wherein the node information includes the named entity name, attribute, and relationship, and the adjacency information includes the adjacency matrix between nodes;
[0096] In the knowledge graph, the natural language descriptions in the equipment operation and maintenance documents are structured and mapped to nodes, attributes, and relationships in the knowledge graph, providing a data basis for subsequent analysis and reasoning of equipment failures and their treatment methods;
[0097] For example,
[0098] Node information:
[0099] Named Entity Name:
[0100] Equipment: Cooling system
[0101] Components: Cooling lines
[0102] Fault type: Leakage
[0103] property:
[0104] Cooling line: {pressure: 0.5 MPa, flow rate: 2 L / min, temperature: 25°C}
[0105] Fault type: Leakage {Fault cause: Pipeline aging, Fault phenomenon: Pressure drop, Fault identification method: Pressure monitoring}
[0106] relation:
[0107] The cooling system includes cooling lines
[0108] Cooling line leaks
[0109] The leak was caused by aging pipelines.
[0110] A leak will show up as a sudden drop in pressure.
[0111] Dynamic alarm threshold calculation module: Combines all device states, performs baseline state modeling, and calculates the upper and lower limits of the dynamic alarm threshold; its operation steps include:
[0112] S3: Combine all device states to model the baseline state and calculate the upper and lower limits of the dynamic alarm threshold, such as Figure 1 As shown;
[0113] S31: Combine all equipment status data to perform benchmark status modeling and obtain a status benchmark value sequence. The calculation method is:
[0114]
[0115] in, is the reference state value sequence at the current time t, For fully connected network operation, is a gated recurrent unit operation, is the baseline state value sequence of the previous moment, is the preprocessed data vector of all device states at the current moment, and t is the index of the first moment;
[0116] S32: Output the upper and lower limits of the dynamic alarm threshold according to the state reference value sequence. The calculation method is:
[0117]
[0118]
[0119] in, is the upper limit of the dynamic alarm threshold at the current time t, is the lower limit of the dynamic alarm threshold at the current time t, For the first long short-term memory network operation, For the second long short-term memory network operation, is the upper limit of the dynamic alarm threshold at the previous moment, It is the lower limit of the dynamic alarm threshold at the previous moment;
[0120] The first long short-term memory network operation and the second long short-term memory network operation are characterized in that the second long short-term memory network has the same network structure as the first long short-term memory network, but uses different parameter initialization methods; the first long short-term memory network uses random parameter initialization, and the second long short-term memory network uses the Xavier method for parameter initialization; wherein the Xavier method is also called Xavier initialization, which is a common method for initializing neural network weights, and the goal is to make each neuron keep the variance of the input and output as equal as possible during the forward propagation process, thereby avoiding the problem of gradient disappearance or gradient explosion in deep networks;
[0121] The baseline state modeling uses a gated recurrent unit to combine the state data of all devices to generate a baseline state value sequence, and combined with the calculation of dynamic thresholds, it can maintain accurate monitoring of the state of individual devices when the overall environment changes;
[0122] Compared with the traditional alarm method based on fixed thresholds, the present invention can calculate dynamic alarm thresholds according to the real-time changes in equipment status. In particular, when other modules are in normal status, anomalies can be identified by dynamically adjusting the upper and lower limits, reducing systematic false alarms caused by normal environmental changes, making the substation operation and maintenance system more accurate and flexible.
[0123] Maintenance time prediction module: If the equipment status is normal, the next maintenance time is predicted based on the preprocessed equipment status data; its operation steps include:
[0124] S4: If the equipment status is normal, the next maintenance time is predicted based on the preprocessed equipment status data, such as Figure 2 As shown;
[0125] S41: Build a maintenance time prediction model to predict the next maintenance time based on the preprocessed equipment status data and the last maintenance time. The calculation method is:
[0126]
[0127]
[0128]
[0129]
[0130]
[0131] in, is the original time series feature at the current time t, is the original time series feature of the previous moment, is the vector obtained by concatenating the preprocessed equipment status data and the last maintenance time. is the context vector at the current time t, is the attention weight of time k for time t, is the original time series feature at time k, k is the index of the second time, To take the exponential operation of a natural constant, is the attention score of time k for time t, is the attention score of moment j for moment t, j is the index of the third moment, is the hyperbolic tangent function operation, is the first parameter matrix, is the second parameter matrix, is the first bias vector, is the predicted value of the next maintenance time, is the third parameter matrix, is the second bias vector;
[0132] S42: Monte Carlo simulation method is used to calculate the confidence interval of the next maintenance time. The calculation method is:
[0133] Generate samples by predicting the output and error distribution of the model, calculated as:
[0134]
[0135]
[0136] in, is the predicted value of the next maintenance time of the nth sample, n is the sample index, is the error distribution of the nth sample, is the normal distribution of the sample, is the sample mean, is the sample variance;
[0137] Perform multiple simulations to obtain a sample set ,in is the sample set, M is the number of samples;
[0138] Sort the sample set and calculate the upper and lower bounds of the confidence interval based on the confidence level. The calculation method is:
[0139]
[0140]
[0141] in, is the upper bound of the confidence interval, is the lower bound of the confidence interval, and c is the significance level;
[0142] Traditional methods usually estimate maintenance time based on simple statistical models, such as linear regression or time interval prediction based on fixed periods, which is difficult to capture the complex dynamic changes of equipment data. The present invention adds an attention mechanism on the basis of the gated recurrent unit to integrate historical and current information, analyze the importance of data at different times, and make the maintenance time prediction more accurate. In addition, after predicting the maintenance time, the present invention introduces the Monte Carlo simulation method to calculate the confidence interval and quantify the uncertainty of the prediction results, which not only provides specific time nodes, but also provides time ranges, making the operation and maintenance plan more flexible.
[0143] For example:
[0144]
[0145] After sorting these sample data, if we calculate:
[0146] The value at the 2.5% position is 5.3 months (lower bound)
[0147] The value at the 97.5% position is 6.8 months (upper limit)
[0148] At a 95% confidence level, there is a 95% probability that the next maintenance time will be between 5.3 months and 6.8 months.
[0149] Fault cause identification module: If the equipment status is abnormal, the fault cause is identified by combining the equipment operation and maintenance knowledge graph with the pre-processed equipment status data. The operation steps include:
[0150] S5: If the equipment status is abnormal, the cause of the fault is identified by combining the equipment operation and maintenance knowledge graph with the pre-processed equipment status data;
[0151] S51: Extract key fault features from the status data of abnormal equipment, and the calculation method is:
[0152]
[0153] in, is the key fault feature at the current moment, It is a multi-scale convolutional long short-term memory network operation. is the key fault feature of the previous moment, is the preprocessed abnormal device status data vector at the current moment;
[0154] S52: Generate a fault text description based on the extracted key fault features. The calculation method is:
[0155]
[0156] in, is the generated fault text description, For the bidirectional autoregressive model operation, It is the concatenation vector of key fault type and fault description;
[0157] For example:
[0158] Description: "A sudden pressure rise was detected with a rate of change of"
[0159] Description: "An abnormal fluctuation frequency was found, the frequency is"
[0160] Description: "An outlier was detected, data point is";
[0161] S53: Based on the generated fault text description and combined with the equipment operation and maintenance knowledge graph, the fault cause is identified. The calculation method is:
[0162]
[0163] in, is the representation vector of the equipment operation and maintenance knowledge graph, For graph neural network operations, It is the node information of the equipment operation and maintenance knowledge graph. is the adjacency matrix between nodes;
[0164] S54: searching the fault handling records for a matching historical fault handling record according to the identified fault cause, and generating a fault handling suggestion according to the matched historical fault handling record;
[0165] Compared with traditional methods, traditional fault feature extraction methods are usually based on simple rules or statistical methods, lack multi-scale analysis capabilities, and are difficult to capture complex fault modes. When generating fault descriptions, they rely on manual generation, are prone to subjective bias, and are inefficient. The present invention uses a multi-scale convolutional long short-term memory network to extract key fault features, captures fault features on different time scales from multi-scale convolutions, and better characterizes the complexity of abnormal states. A bidirectional autoregressive model is used to automatically generate fault text descriptions, which reduces the uncertainty and delay of manual descriptions and improves the accuracy of descriptions. In addition, the present invention combines graph neural networks and equipment operation and maintenance knowledge graphs, uses the relationship information between graph structures and nodes to identify fault causes, uses historical fault processing records in the knowledge graph, and combines current fault features to generate fault processing suggestions to ensure that the processing plan is more targeted, which not only improves the effectiveness of current fault processing, but also provides data support for future operation and maintenance, and improves the efficiency of smart operation and maintenance of substations.
[0166] For example:
[0167] Check the connection of the cooling pipeline to ensure that the pipeline is tightly connected without water leakage;
[0168] Check the cooling system's pumps, valves and other equipment to ensure they are operating normally;
[0169] Increase the coolant flow of the cooling system;
[0170] Reduce the pump working pressure of the cooling system;
[0171] Increase the cooling system water pump speed.
[0172] The present invention is particularly suitable for large-scale power substations with complex environments and a variety of equipment types. By comprehensively utilizing multi-source data, this solution can achieve comprehensive monitoring of equipment status, prediction of operation and maintenance events, and diagnosis of fault causes, greatly improving the reliability and operation and maintenance efficiency of the equipment.
[0173] It should be noted that the serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages and disadvantages of the embodiments. And the terms "including", "comprising" or any other variants thereof in this article are intended to cover non-exclusive inclusion, so that a process, device, article or method including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, device, article or method. In the absence of further restrictions, an element defined by the sentence "including a ..." does not exclude the presence of other identical elements in the process, device, article or method including the element.
[0174] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above-mentioned embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present invention is essentially or the part that contributes to the prior art can be embodied in the form of a software product, which is stored in a storage medium (such as ROM / RAM, magnetic disk, optical disk) as described above, and includes a number of instructions for a terminal device (which can be a mobile phone, a computer, a server, or a network device, etc.) to execute the methods described in each embodiment of the present invention.
[0175] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A substation intelligent operation and maintenance system, characterized in that: include: Data collection and preprocessing module: collects equipment status data and equipment operation and maintenance documents and performs preprocessing to obtain preprocessed equipment status data and equipment operation and maintenance documents; the equipment includes cooling pipelines, transformers, current transformers and voltage transformers; Equipment operation and maintenance knowledge graph construction module: constructs the equipment operation and maintenance knowledge graph based on the pre-processed equipment operation and maintenance documents; Dynamic alarm threshold calculation module: Combines all device states to perform baseline state modeling and calculates the upper and lower limits of the dynamic alarm threshold; The operation steps of the dynamic alarm threshold calculation module include: S31: Combine all equipment status data to perform benchmark status modeling and obtain a status benchmark value sequence. The calculation method is: , in, is the reference state value sequence at the current time t, For fully connected network operation, is a gated recurrent unit operation, is the baseline state value sequence of the previous moment, is the preprocessed data vector of all device states at the current moment, and t is the index of the first moment; S32: Output the upper and lower limits of the dynamic alarm threshold according to the state reference value sequence. The calculation method is: , , in, is the upper limit of the dynamic alarm threshold at the current time t, is the lower limit of the dynamic alarm threshold at the current time t, For the first long short-term memory network operation, For the second long short-term memory network operation, is the upper limit of the dynamic alarm threshold at the previous moment, It is the lower limit of the dynamic alarm threshold at the previous moment; The second long short-term memory network has the same network structure as the first long short-term memory network, but the first long short-term memory network uses random parameter initialization, and the second long short-term memory network uses the Xavier method for parameter initialization; Maintenance time prediction module: If the equipment status is normal, the next maintenance time is predicted based on the pre-processed equipment status data; The maintenance time prediction module includes constructing a maintenance time prediction model, predicting the next maintenance time according to the preprocessed equipment status data and the last maintenance time; using the Monte Carlo simulation method, generating a sample set through the output and error distribution of multiple prediction models, sorting the sample set, and calculating the confidence interval of the next maintenance time; The operation steps of the maintenance time prediction module include: S41: Build a maintenance time prediction model to predict the next maintenance time based on the preprocessed equipment status data and the last maintenance time. The calculation method is: , , , , , in, is the original time series feature at the current time t, is the original time series feature of the previous moment, is the vector obtained by concatenating the preprocessed equipment status data and the last maintenance time. is the context vector at the current time t, is the attention weight of time k for time t, is the original time series feature at time k, k is the index of the second time, To take the exponential operation of a natural constant, is the attention score of time k for time t, is the attention score of moment j for moment t, j is the index of the third moment, is the hyperbolic tangent function operation, is the first parameter matrix, is the second parameter matrix, is the first bias vector, is the predicted value of the next maintenance time, is the third parameter matrix, is the second bias vector; S42: Monte Carlo simulation method is used to calculate the confidence interval of the next maintenance time. The calculation method is: Generate samples by predicting the output and error distribution of the model, calculated as: , , in, is the predicted value of the next maintenance time of the nth sample, n is the sample index, is the error distribution of the nth sample, is the normal distribution of the sample, is the sample mean, is the sample variance; Perform multiple simulations to obtain a sample set ,in is the sample set, M is the number of samples; Sort the sample set and calculate the upper and lower bounds of the confidence interval based on the confidence level. The calculation method is: , , in, is the upper bound of the confidence interval, is the lower bound of the confidence interval, c is the significance level, Fault cause identification module: If the equipment status is abnormal, the fault cause is identified by combining the equipment operation and maintenance knowledge graph and the pre-processed equipment status data; the fault cause identification module extracts key fault features from the status data of the abnormal equipment, generates a fault text description, and identifies the fault cause and fault handling suggestions by combining the equipment operation and maintenance knowledge graph; The operation steps of the fault cause identification module include: S51: Extract key fault features from the status data of abnormal equipment, and the calculation method is: , in, is the key fault feature at the current moment, It is a multi-scale convolutional long short-term memory network operation. is the key fault feature of the previous moment, is the preprocessed abnormal device status data vector at the current moment; S52: Generate a fault text description based on the extracted key fault features. The calculation method is: , in, is the generated fault text description, For the bidirectional autoregressive model operation, It is the concatenation vector of key fault type and fault description; S53: Based on the generated fault text description and combined with the equipment operation and maintenance knowledge graph, the fault cause is identified. The calculation method is: , in, is the representation vector of the equipment operation and maintenance knowledge graph, For graph neural network operations, It is the node information of the equipment operation and maintenance knowledge graph. is the adjacency matrix between nodes; S54: According to the identified fault cause, searching the fault handling records for a matching historical fault handling record, and generating a fault handling suggestion according to the matched historical fault handling record.
2. The intelligent operation and maintenance system for substation according to claim 1, characterized in that: The operation steps of the data collection and preprocessing module include: S11: Collect equipment status data and equipment operation and maintenance documents in the substation and perform pre-processing; The equipment operation and maintenance document includes the equipment name, component name, fault type, fault cause, fault phenomenon, fault identification method, and fault handling record; S12: For numerical data, missing values are filled using mean filling method; S13: For text data, the HanLP tool is used to perform word segmentation and remove stop words.
3. The intelligent operation and maintenance system for substation according to claim 2 is characterized in that: The processing steps of the device status data include: S111: using the standard deviation method, identifying abnormal values of the equipment status data, and removing the identified abnormal values; S112: The data after the outliers are removed is standardized using a Z-score method to obtain preprocessed device status data.
4. The substation intelligent operation and maintenance system according to claim 2 is characterized in that: The operation steps of the equipment operation and maintenance knowledge graph construction module include: S21: Perform named entity recognition on the preprocessed equipment operation and maintenance documents and create new nodes in the knowledge graph; S22: For each named entity, perform relationship extraction and attribute extraction based on the pre-processed equipment operation and maintenance documents; S23: Based on the extracted named entities, attributes, and relationships, MangoDB is used to build a knowledge graph; S24: For the constructed knowledge graph, eliminate redundant information, merge duplicate nodes, and obtain the equipment operation and maintenance knowledge graph; the knowledge graph contains node information and adjacency information, wherein the node information includes the named entity name, attributes, and relationships, and the adjacency information includes the adjacency matrix between nodes.