Assembled reinforced concrete dense-rib shear wall and building thereof
Through dense rib structure and indirect overlap technology, the hidden grouting and steel bar positioning perforation problems of horizontal joint connection of prefabricated concrete shear walls are solved, and efficient and reliable on-site construction is achieved, reducing costs and difficulty, and improving the overall performance.
Patent Information
- Application Number
- CN202411018974.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-29
AI Technical Summary
The horizontal joint connection method of the existing prefabricated concrete shear walls has problems such as difficult to supervise the quality of concealed grouting construction, high precision of positioning and perforation of steel bars, high construction difficulty and high cost, which affects the overall performance of the structure.
Prefabricated reinforced concrete shear walls with dense rib structures, through the design of prefabricated walls and concealed beam mold shells, use plug-in structures, anchor plates and restrained stirrups to achieve indirect overlap of steel bars, cancel the concealed grouting project, and use casting in place Construction methods, simplify on-site construction steps.
The construction quality of horizontal joints and on-site connection efficiency are improved, the construction difficulty and cost are reduced, the construction quality of steel bar joints is ensured, the problem of scrap parts and rib breakage is reduced, and the construction efficiency and overall performance are improved.
Smart Images

Figure CN118531928B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction, and in particular to an assembled reinforced concrete dense-rib shear wall and a building thereof. Background Art
[0002] Prefabricated buildings have a wide range of applications and are used in residential buildings, bridge projects, subway stations, stadiums, and many other aspects. Compared with traditional structures, prefabricated concrete shear wall structures have the advantages of saving labor costs, reducing noise and dust pollution at the construction site, shortening construction period, better product quality control, high production efficiency, and high material utilization.
[0003] However, there are horizontal and vertical joints between the prefabricated shear wall units, which connect the prefabricated components into a whole, so that the entire structure has sufficient bearing capacity, stiffness and ductility, as well as the ability to resist earthquakes, accidental loads and wind loads. Therefore, the mechanical properties of the joints have a crucial impact on the overall performance of the structure. Whether the force is reasonable and the construction is convenient is the key to the prefabricated concrete shear wall technology.
[0004] At present, the main connection methods for horizontal joints of prefabricated concrete shear walls at home and abroad are: sleeve grouting, constrained slurry anchor, sleeve extrusion, etc. Studies have shown that the performance of sleeve grouting, constrained slurry anchor, etc. can meet the requirements of "equivalent to cast-in-place". However, both technologies have obvious disadvantages, which are mainly manifested as follows: 1. Concealed grouting construction is required, and the grouting quality cannot be directly supervised. At the same time, there is a lack of efficient tools and means to detect grouting defects, which will cause major grouting construction quality risks, adversely affect the performance of horizontal joints, and ultimately affect the overall performance of the prefabricated shear wall structure; 2. The processing accuracy requirements for prefabricated reinforced concrete shear walls are high. If the position of the steel bars deviates slightly, it will be difficult for the on-site steel bars to penetrate into the sleeve live slurry anchor holes. At the same time, due to the large number of shear wall steel bars and the high-altitude operation, the precision of on-site construction is extremely high. Inserting dozens or even dozens of steel bars into the prefabricated reinforced concrete shear wall steel sleeve at the same time is like threading a needle with several tons of weight in the air, which causes a series of specific problems and implementation costs such as high labor costs for professional teams, high cost of measures, waste parts, broken steel bars, etc. 3. The self-weight of prefabricated shear wall components is large, and hoisting is inconvenient, which makes on-site installation and connection difficult.
[0005] In view of the shortcomings and deficiencies of the existing prefabricated shear wall structure, it is necessary to propose a new type of prefabricated shear wall structure, in which the steel bars adopt an efficient connection method and the shear wall adopts a dense-rib structure, which improves the efficiency of on-site lifting connection and the construction quality of horizontal joints, and has good adaptability to my country's construction environment. Summary of the invention
[0006] The object of the present invention is to provide an assembled reinforced concrete multi-rib shear wall and a building thereof, so as to solve at least one of the above-mentioned technical problems existing in the prior art.
[0007] In order to solve the above technical problems, the present invention provides an assembled reinforced concrete multi-rib shear wall, comprising a wall body and a concealed beam formwork that are prefabricated together;
[0008] Vertical steel bars are vertically arranged in the wall, and the vertical steel bars include an upper connecting portion extending upward from the top surface of the wall and extending into the concealed beam formwork;
[0009] The concealed beam formwork is provided with a connecting opening, and the bottom of the wall is provided with a plug-in structure;
[0010] When two upper and lower adjacent prefabricated shear walls are butt-jointed, the bottom plug-in structure of the upper prefabricated shear wall is inserted into the connecting opening at the top of the lower prefabricated shear wall to achieve a fixed connection between the two.
[0011] Furthermore, the plug-in structure is an outwardly extending steel bar extending outwardly from the bottom surface of the wall body. The outwardly extending steel bar of the upper prefabricated shear wall is inserted into the connecting opening of the lower prefabricated shear wall. After pouring concrete or injecting slurry, the upper and lower prefabricated shear walls are fixedly connected.
[0012] Furthermore, a plurality of the upper connecting parts are arranged at intervals around the connecting opening to increase the connection strength of the connecting opening.
[0013] Furthermore, a plurality of the upper connecting parts are arranged in the cavity of the connecting opening. When two adjacent upper and lower prefabricated shear walls are butt-jointed, the protruding steel bars of the upper prefabricated shear wall are inserted into the connecting opening and overlap with the upper connecting parts around the connecting opening of the lower prefabricated shear wall and in the cavity.
[0014] Furthermore, restraining stirrups are provided around the connecting opening and the periphery of the upper connecting portion.
[0015] The restraining stirrups can be square stirrups, circular stirrups or spiral stirrups, etc. Multiple restraining stirrups are arranged at intervals in the height direction, and the spacing can be designed according to the actual project. The spacing between the restraining stirrups can be 40mm~100mm, which can provide a strong restraint effect for the steel bar connection.
[0016] Furthermore, one or more anchoring plates are provided on the upper connecting portion.
[0017] Furthermore, one or more anchor plates are provided on the protruding steel bars.
[0018] When multiple anchor plates are provided, the area of the anchor plates can be reduced, which facilitates construction; the shape of the anchor plates can be square, round, oval, etc.; the anchor plates are connected to the upper connecting part and the protruding steel bars by welding or threading.
[0019] Furthermore, hidden beam longitudinal reinforcement and hidden beam stirrups are pre-embedded in the hidden beam formwork.
[0020] Preferably, the hidden beam longitudinal reinforcement includes protruding portions extending out of the left and right sides of the hidden beam formwork, which are used to be connected to the frame beam longitudinal reinforcement.
[0021] Preferably, the lower end of the vertical steel bar extends out of the lower connecting portion of the bottom surface of the wall to form the protruding steel bar.
[0022] Of course, the protruding steel bars can also be connecting steel bars set up for independent vertical steel bars.
[0023] Furthermore, the wall is a dense-rib wall with a plurality of holes formed therein, thereby reducing the weight of the prefabricated wall components.
[0024] The holes are in the shape of square, rectangular, oval, circular or the like.
[0025] Furthermore, the holes are filled with lightweight prefabricated blocks, such as autoclaved aerated concrete blocks, etc., and the dense-rib opening area may not be filled to form a through hole.
[0026] Wherein, the thickness of the hidden beam formwork is equal to or greater than the thickness of the wall. The height of the hidden beam formwork is equal to the designed height of the frame beam.
[0027] Furthermore, the cavity outside the connecting opening in the concealed beam formwork is pre-filled with concrete.
[0028] The concealed beam formwork is poured with concrete during prefabrication, and a connection opening is reserved for connecting the upper and lower prefabricated shear walls during construction.
[0029] Of course, the concealed beam formwork may not be pre-filled with cement, and concrete may be poured during construction.
[0030] Furthermore, the bottom surface of the wall and the left and right sides of the hidden beam formwork are roughened. Specifically, roughening or key grooves can be adopted to enhance the bonding effect.
[0031] The length of the upper connection part is more than 10 times the diameter of the vertical steel bar. The size of the anchor plate can be designed according to the actual project conditions. Generally, the area of the anchor plate can be more than 6 times the cross-sectional area of the connected steel bar.
[0032] Due to the provision of anchor plates and restrained stirrups, the height of the indirect lap section of the steel bars in this application is significantly reduced compared to the steel bar lap length specified in the "Concrete Structure Design Code", and the height of the grouting section is also reduced, which can improve on-site construction efficiency.
[0033] Furthermore, a grouting port and a grouting outlet are provided on the side wall of the connecting opening; the grouting port is provided at the bottom of the side wall of the connecting opening, and the grouting outlet is provided at the top of the side wall of the connecting opening.
[0034] After the prefabricated shear wall is hoisted in place, the extended steel bars of the upper prefabricated shear wall are inserted into the connection opening of the lower prefabricated shear wall, and grout is poured into the connection opening through the grouting port until the grout overflows from the grouting port. The grouting is stopped and the grouting port and the grouting port are blocked with a plug. After the grouting is completed, the horizontal joint connection between the two adjacent prefabricated shear walls is completed.
[0035] The second aspect of the present application discloses a building using the above-mentioned assembled reinforced concrete multi-rib shear wall, which also includes a prefabricated composite floor slab;
[0036] The two upper and lower adjacent precast shear walls are arranged at intervals, and the bottom protruding steel bars of the upper precast shear wall are inserted into the connecting openings at the top of the lower precast shear wall; the edge of the precast composite floor slab is inserted into the interval between the two upper and lower adjacent precast shear walls and overlapped on the hidden beam formwork of the lower precast shear wall, and concrete is poured into the interval to form a post-cast joint, while the two upper and lower adjacent precast shear walls and the precast composite floor slab are fixedly connected.
[0037] Furthermore, the extended portion of the steel bars embedded in the prefabricated composite floor slab is inserted between the protruding steel bars and is indirectly overlapped and connected to the protruding steel bars.
[0038] By adopting the above technical solution, the present invention has the following beneficial effects:
[0039] The present invention provides an assembled reinforced concrete dense-rib shear wall and a building thereof, which realizes efficient connection of prefabricated shear walls; adopts a cast-in-place construction method, eliminates the hidden sleeve grouting and constrained grouting works, is intuitive to operate, and is easy to inspect for quality, and can effectively ensure the construction quality of steel bar joints; eliminates the construction steps of on-site steel bar positioning and punching, improves the construction error tolerance, reduces the construction difficulty, and improves the construction efficiency.
[0040] The invention has the following beneficial effects:
[0041] 1. The novel assembled reinforced concrete shear wall horizontal joint structure proposed in the present invention can realize the efficient connection of assembled shear wall units, and has the characteristics of high degree of factory prefabrication and less on-site wet work.
[0042] 2. Compared with the existing technology, the connection of the horizontal joints of the new prefabricated reinforced concrete shear wall adopts the cast-in-place construction method, which eliminates the hidden grouting project and can effectively ensure the construction quality of the steel bar connection at the horizontal joints.
[0043] 3. The cast-in-place construction method is adopted on site, which does not require additional grouting materials and professional grouting workers, saving on-site construction costs.
[0044] 4. Compared with the existing technology, the connection of the horizontal joints of the new prefabricated reinforced concrete shear wall does not require the construction steps of on-site steel bar positioning holes. The vertical connection of the prefabricated shear wall unit uses indirect steel bar lap joints as the basic structural form, which improves the construction error tolerance and improves the construction efficiency.
[0045] 5. The basic structural form of indirect lap joint of steel bars is a very mature steel bar connection method with mature on-site construction experience. The construction quality can be well guaranteed, and a series of specific problems such as waste parts and broken bars are also improved, which not only improves construction efficiency but also reduces construction costs.
[0046] 6. The prefabricated wall adopts a dense rib layout. The dense rib opening area can significantly reduce the weight of the prefabricated wall, facilitate the hoisting of the prefabricated wall and the on-site alignment connection, and improve the construction connection efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0048] Figure 1 A three-dimensional diagram of a prefabricated shear wall provided in Example 1 of the present invention;
[0049] Figure 2 for Figure 1 The schematic diagram of the internal structure of the prefabricated shear wall hidden beam formwork shown;
[0050] Figure 3 It is a partial stereoscopic diagram of two upper and lower connected prefabricated shear walls in Example 1 of the present invention;
[0051] Figure 4 This is a schematic diagram of the connection structure of the upper and lower prefabricated shear walls in Example 1;
[0052] Figure 5 This is a three-dimensional diagram when the width and thickness of the hidden beam formwork in Example 1 are greater than the wall;
[0053] Figure 6 A three-dimensional diagram of a prefabricated shear wall provided in Example 2 of the present invention;
[0054] Figure 7 A three-dimensional diagram of the spacing arrangement of two upper and lower adjacent prefabricated shear walls in a building provided in Example 2 of the present invention;
[0055] Figure 8 A schematic diagram of the connection structure between the prefabricated shear wall and the prefabricated composite floor slab provided in Example 2 of the present invention;
[0056] Fig. 9 for Figure 8 A partial enlarged view of the middle part;
[0057] Fig.10 This is a schematic structural diagram of the prefabricated shear wall provided in Example 3;
[0058] Fig.11 This is a schematic structural diagram of the prefabricated shear wall provided in Example 4;
[0059] Fig.12 This is a schematic diagram of the structure of the prefabricated shear wall provided in Example 5;
[0060] Fig.13 This is a schematic diagram of the connection structure of the upper and lower prefabricated shear walls in Example 5;
[0061] Fig.14 is a three-dimensional diagram of a C-shaped steel block in Example 5;
[0062] Fig.15 A partial diagram of another connection structure of the upper and lower prefabricated shear walls in Example 5;
[0063] Fig.16 This is a top view of another implementation of the C-shaped steel block in Example 5.
[0064] Reference numerals:
[0065] 100-precast shear wall; 101-precast shear wall above; 102-precast shear wall below; 103-post-cast strip; 110-wall; 111-hole; 120-hidden beam formwork; 121-hidden beam longitudinal reinforcement; 121a-extending end; 122-connecting opening; 123-hidden beam stirrups; 124-grouting port; 125-grouting port; 126-out-of-surface reinforcement; 127-installation window; 130-vertical reinforcement; 131-upper connection part; 132-anchor plate; 133-restraint stirrups; 134-extending steel bars; 132a-first anchor plate; 132b-second anchor plate; 132c-third anchor plate; 132d-fourth anchor plate; 140-C-shaped steel block; 141-upper connecting plate; 142-lower connecting plate; 143-middle connecting plate; 144-opening groove; 144a-straight groove; 144b-oblique groove; 200-prefabricated composite floor; 201-extending part. DETAILED DESCRIPTION
[0066] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0067] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0068] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0069] The present invention is further explained below in conjunction with specific implementation modes.
[0070] Example 1
[0071] like Figure 1-4As shown, the present embodiment provides an assembled reinforced concrete multi-rib shear wall 100, comprising a wall body 110 and a concealed beam formwork 120 that are prefabricated together;
[0072] A vertical steel bar 130 is vertically arranged in the wall 110, and the vertical steel bar 130 includes an upper connecting portion 131 extending upward from the top surface of the wall 110 and extending into the hidden beam formwork 120;
[0073] The hidden beam formwork 120 is preferably a box structure made of reinforced concrete material, and a connecting opening 122 is provided on the hidden beam formwork 120, and a plug-in structure is provided at the bottom of the wall 110; when two adjacent prefabricated shear walls 100 are connected, the bottom plug-in structure of the upper prefabricated shear wall 101 is inserted into the connecting opening 122 at the top of the lower prefabricated shear wall 102 to achieve a fixed connection between the two.
[0074] In this embodiment, the plug-in structure is an extended steel bar 134 extending out from the bottom surface of the wall 110. The extended steel bar 134 of the upper prefabricated shear wall 101 is inserted into the connecting opening 122 of the lower prefabricated shear wall 102. After pouring concrete or injecting slurry, the upper and lower prefabricated shear walls 100 are fixedly connected.
[0075] Preferably, the lower end of the vertical steel bar 130 extends out of the lower connection portion of the bottom surface of the wall 110 to form the protruding steel bar 134. Of course, the protruding steel bar 134 can also be a connecting steel bar provided for the independent vertical steel bar 130.
[0076] A plurality of upper connecting parts 131 are arranged at intervals around the connecting opening 122 to increase the connection strength of the connecting opening 122. Constraint stirrups 133 are arranged around the connecting opening 122 and the upper connecting part 131. The constrained stirrups 133 can be square stirrups, circular stirrups or spiral stirrups, etc. A plurality of constrained stirrups 133 are arranged at intervals in the height direction, and the spacing can be designed according to the actual project. The spacing of the constrained stirrups 133 can be 40 mm to 100 mm, which can provide a strong constraint effect for the steel bar connection.
[0077] More preferably, a plurality of the upper connecting parts 131 are provided in the cavity of the connecting opening 122. When two adjacent upper and lower prefabricated shear walls 100 are butt-jointed, the protruding steel bars 134 of the upper prefabricated shear wall 101 are inserted into the connecting opening 122 and overlapped with the upper connecting parts 131 around the connecting opening 122 of the lower prefabricated shear wall 102 and in the cavity.
[0078] More preferably, one or more anchor plates 132 are provided on the upper connection part 131. One or more anchor plates 132 are provided on the protruding steel bar 134. When multiple anchor plates 132 are provided, the area of the anchor plates 132 can be reduced, which is convenient for construction; the shape of the anchor plates 132 can be square, round, oval, etc.; the anchor plates 132 are connected to the upper connection part 131 and the protruding steel bar 134 by welding or threading.
[0079] Furthermore, hidden beam longitudinal reinforcement 121 and hidden beam stirrups 123 are pre-embedded in the hidden beam formwork 120. Preferably, the hidden beam longitudinal reinforcement 121 includes extended ends 121a extending out of the left and right sides of the hidden beam formwork 120 for connection with the frame beam longitudinal reinforcement.
[0080] In this embodiment, the wall 110 is a dense rib wall, and a plurality of holes 111 are formed on the wall 110. The holes 111 are in the shape of square, rectangular, oval, circular, etc. The holes 111 may be filled with lightweight prefabricated blocks, such as autoclaved aerated concrete blocks, etc., or may not be filled with the dense rib opening area to form a through hole.
[0081] The thickness of the hidden beam formwork 120 is equal to or greater than the thickness of the wall 110. The height of the hidden beam formwork 120 is equal to the designed height of the frame beam.
[0082] Furthermore, the cavity outside the connecting opening 122 in the concealed beam formwork 120 is pre-filled with concrete.
[0083] The hidden beam formwork 120 is a box structure with an opening on the top. When pouring concrete during construction, concrete is poured into the hidden beam formwork 120 to form a part of the cross beam. The cross beam and the prefabricated shear wall 100 form an integral structure.
[0084] Preferably, the bottom surface of the wall 110 and the left and right sides of the concealed beam formwork 120 are roughened. Specifically, roughening or key grooves can be used to enhance the bonding effect.
[0085] The length of the upper connection portion 131 is more than 10 times the diameter of the vertical steel bar 130. The size of the anchor plate 132 can be designed according to the actual project conditions. Generally, the area of the anchor plate 132 can be more than 6 times the cross-sectional area of the connected steel bar.
[0086] In specific applications, the left and right widths and thicknesses of the concealed beam formwork 120 may be the same as the widths and thicknesses of the wall 110, see Figure 5 As shown, the left and right widths and thicknesses of the concealed beam formwork 120 may also be greater than the width and thickness of the wall 110 , thereby meeting the beam design requirements of the application scenario.
[0087] Since the anchor plate 132 and the restraining stirrups 133 are provided in the present application, the height of the indirect lap section of the steel bars is significantly reduced compared to the steel bar lap length specified in the "Concrete Structure Design Code", and the height of the grouting section is also reduced, which can improve the on-site construction efficiency.
[0088] The present invention provides an assembled reinforced concrete multi-ribbed shear wall 100 and a building thereof, which realizes efficient connection of prefabricated shear walls 100; adopts a cast-in-place construction method, eliminates the hidden sleeve grouting and constrained grouting works, is intuitive to operate, and is easy to inspect for quality, and can effectively ensure the construction quality of steel bar joints; eliminates the construction steps of on-site steel bar positioning and punching, improves the construction error tolerance, reduces the construction difficulty, and improves the construction efficiency.
[0089] The invention has the following beneficial effects:
[0090] 1. The novel assembled reinforced concrete shear wall horizontal joint structure proposed in the present invention can realize the efficient connection of assembled shear wall units, and has the characteristics of high degree of factory prefabrication and less on-site wet work.
[0091] 2. Compared with the existing technology, the connection of the horizontal joints of the new prefabricated reinforced concrete shear wall adopts the cast-in-place construction method, which eliminates the hidden grouting project and can effectively ensure the construction quality of the steel bar connection at the horizontal joints.
[0092] 3. The cast-in-place construction method is adopted on site, which does not require additional grouting materials and professional grouting workers, saving on-site construction costs.
[0093] 4. Compared with the existing technology, the connection of the horizontal joints of the new prefabricated reinforced concrete shear wall does not require the construction steps of on-site steel bar positioning holes. The vertical connection of the prefabricated shear wall unit uses indirect steel bar lap joints as the basic structural form, which improves the construction error tolerance and improves the construction efficiency.
[0094] 5. The basic structural form of indirect lap joint of steel bars is a very mature steel bar connection method with mature on-site construction experience. The construction quality can be well guaranteed, and a series of specific problems such as waste parts and broken bars are also improved, which not only improves construction efficiency but also reduces construction costs.
[0095] 6. The prefabricated wall 110 adopts a dense rib arrangement. The dense rib opening area can significantly reduce the weight of the prefabricated wall 110, facilitate the hoisting of the prefabricated wall 110 and the on-site alignment connection, and improve the construction connection efficiency.
[0096] Example 2
[0097] This embodiment 1 is basically the same as embodiment 1, except that:
[0098] See also Figure 6 As shown, the hidden beam formwork 120 is prefabricated as a beam structure with the wall 110. During prefabrication, concrete is poured into the hidden beam formwork 120 and a connection opening 122 is reserved. The hidden beam formwork 120 thus has the bearing capacity of the beam.
[0099] See also Figure 7 and 8 As shown, the second aspect of this embodiment discloses a building using the above-mentioned assembled reinforced concrete multi-rib shear wall 100. During construction, the protruding end 121a of the hidden beam longitudinal reinforcement 121 of the prefabricated shear wall 100 is fixedly connected to the longitudinal reinforcement of the frame beam of the building by welding or the like; the hidden beam formwork 120 and the frame beam then form an integrated crossbeam structure.
[0100] See also Figure 7 As shown, the two adjacent prefabricated shear walls 100 are arranged at intervals, and the bottom protruding steel bars 134 of the upper prefabricated shear wall 101 are inserted into the connecting opening 122 at the top of the lower prefabricated shear wall 102.
[0101] See also Figure 8 As shown, the building also includes a prefabricated composite floor 200; the edge of the prefabricated composite floor 200 is inserted into the gap between the upper prefabricated shear wall 101 and the lower prefabricated shear wall 102, and overlapped on the hidden beam formwork 120 of the lower prefabricated shear wall 102, see Fig. 9 As shown, the extension 210 of the floor reinforcement embedded in the prefabricated composite floor 200 is inserted between the protruding reinforcements 134 and is indirectly overlapped and connected to the protruding reinforcements 134. After pouring concrete into the interval, a post-cast strip 103 is formed, thereby simultaneously fixing and connecting the upper and lower adjacent prefabricated shear walls 101, the lower prefabricated shear walls 102 and the prefabricated composite floor 200, and the overall rigidity is greatly enhanced.
[0102] Example 3
[0103] This embodiment is basically the same as Embodiment 1, except that:
[0104] See also Fig.10 As shown, a grouting port 124 and a grouting outlet 125 are provided on the side wall of the hidden beam formwork 120 connected to the opening 122; the grouting port 124 is provided at the bottom of the side wall connected to the opening 122, and the grouting port 125 is provided at the top of the side wall connected to the opening 122.
[0105] After the prefabricated shear wall 100 is hoisted in place, the extended steel bars 134 of the upper prefabricated shear wall 101 are inserted into the connection opening 122 of the lower prefabricated shear wall 102, and grout is poured into the connection opening 122 through the grouting port 124 until the grout overflows from the grouting port 125, and the grouting is stopped, and the grouting port 124 and the grouting port 125 are blocked with a plug. After the grouting is completed, the horizontal joint connection between the two upper and lower adjacent prefabricated shear walls 100 is completed.
[0106] Compared with Example 1, this embodiment has less wet work on site, is easy to install, and has higher efficiency.
[0107] Example 4
[0108] This embodiment is basically the same as Embodiment 1, except that:
[0109] See also Fig.11 As shown, in this embodiment, out-of-plane reinforcement 126 can be arranged in the wall 110 and the hidden beam formwork 120. When the vertical reinforcement 130 between the upper prefabricated shear wall 101 and the lower prefabricated shear wall 102 is overlapped and connected, the vertical reinforcement 130 may be biased inward, resulting in a decrease in the out-of-plane stiffness and bearing capacity of the shear wall. The out-of-plane reinforcement 126 can improve the out-of-plane stiffness and bearing capacity of the connection section between the upper prefabricated shear wall 101 and the lower prefabricated shear wall 102. In order to meet the anchoring requirements of the out-of-plane reinforcement 126 in the hidden beam formwork 120, the out-of-plane reinforcement 126 can be bent 90° or 135° in the beam formwork.
[0110] Example 5
[0111] This embodiment is basically the same as Embodiment 1, except that:
[0112] See also Figure 12-14 As shown, this embodiment further includes a C-shaped steel block 140, and the C-shaped steel block 140 includes an upper connecting plate 141, a middle connecting plate 143 and a lower connecting plate 142; the upper connecting plate 141 and the lower connecting plate 142 are respectively provided with an opening groove 144;
[0113] A first anchor plate 132a is provided at the end of the upper connection part 131 of the vertical reinforcement 130 of the prefabricated shear wall 100, and a second anchor plate 132b is provided at the end of the bottom protruding reinforcement 134 (preferably the lower connection part of the vertical reinforcement 130) of the prefabricated shear wall 100; an installation window 127 is opened on the outer side wall of the hidden beam formwork 120 of the prefabricated shear wall 100.
[0114] When the two adjacent prefabricated shear walls 100 are connected, the bottom protruding steel bars 134 of the upper prefabricated shear wall 101 are inserted into the connecting opening at the top of the lower prefabricated shear wall 102; the C-shaped steel block 140 is inserted into the connecting opening through the installation window 127, and the bottom protruding steel bars 134 of the upper prefabricated shear wall 101 are inserted into the open groove 144 on the upper connecting plate 141, and the second anchor plate 132b rests on the bottom surface of the upper connecting plate 141; the upper connecting part 131 of the vertical steel bars 130 of the lower prefabricated shear wall 102 is inserted into the open groove 144 on the lower connecting plate 142, and the first anchor plate 132a rests on the top surface of the lower connecting plate 142. That is, the outwardly extending steel bars 134 of the upper prefabricated shear wall 101 are connected through the second anchor plate 132b, the C-shaped steel block 140, the first anchor plate 132a and the vertical steel bars 130 of the lower prefabricated shear wall 102 to achieve direct transmission of tension.
[0115] Preferably, the opening grooves 144 on the upper connecting plate 141 and the lower connecting plate 142 are arranged relatively to each other up and down; more preferably, a plurality of opening grooves 144 are respectively provided on the upper connecting plate 141 and the lower connecting plate 142, so that the connection of several pairs of upper connecting parts 131 and protruding steel bars 134 can be realized at the same time.
[0116] See also Fig.15 As shown, preferably, a third anchor plate 132c arranged parallel to and spaced from the first anchor plate 132a is provided on the upper connection portion 131 of the vertical steel bar 130, and a fourth anchor plate 132d arranged parallel to and spaced from the second anchor plate 132b is provided on the end of the bottom outrigger steel bar 134 (preferably the lower connection portion of the vertical steel bar 130) of the prefabricated shear wall 100; the upper connection plate 141 is clamped between the second anchor plate 132b and the fourth anchor plate 132d, and the lower connection plate 142 is clamped between the first anchor plate 132a and the third anchor plate 132c. Thus, the C-shaped steel block 140 can realize the transmission of tension and pressure up and down.
[0117] After the C-shaped steel block 140 is inserted into the connection opening through the installation window 127, the middle connection plate 143 preferably covers the installation window 127 to prepare for the subsequent pouring of concrete into the hidden beam formwork 120 and prevent the concrete from flowing out of the connection opening.
[0118] See also Fig.16As shown, more preferably, the opening grooves 144 on the upper connecting plate 141 and the lower connecting plate 142 each include a straight groove 144a and one or more inclined grooves 144b; a plurality of bayonet holes are arranged at intervals on the side walls on the left and right sides of the inclined groove 144b; during the insertion of the C-shaped steel block 140 into the connecting opening through the installation window 127, a group of upper connecting parts 131 and the protruding steel bars 134 are respectively inserted into the straight grooves 144a on the lower connecting plate 142 and the upper connecting plate 141, and other groups of upper connecting parts 131 and the protruding steel bars 134 are respectively inserted into the bayonet holes in the inclined grooves 144b on the lower connecting plate 142 and the upper connecting plate 141; as the C-shaped steel block 140 is continuously inserted, the upper connecting part 131 and the protruding steel bars 134 abut against the side walls of the straight grooves 144a or the inclined grooves 144b, thereby increasing the transmission capacity of the lateral shear force between the upper prefabricated shear wall 101 and the lower prefabricated shear wall 102.
[0119] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. An assembled reinforced concrete multi-rib shear wall, characterized in that: It includes a wall body and a concealed beam formwork shell that are prefabricated together; the wall body is a dense rib wall with a plurality of holes opened on the wall body; Vertical steel bars are vertically arranged in the wall, and the vertical steel bars include an upper connecting portion extending upward from the top surface of the wall and extending into the concealed beam formwork; The concealed beam formwork is provided with a connecting opening, and the bottom of the wall is provided with a plug-in structure; When two adjacent prefabricated shear walls are butt-jointed, the bottom plug-in structure of the upper prefabricated shear wall is inserted into the connecting opening at the top of the lower prefabricated shear wall to achieve a fixed connection between the two; The hidden beam formwork is pre-embedded with hidden beam longitudinal reinforcement and hidden beam stirrups; The dark beam longitudinal reinforcement includes an extension extending from the left and right sides of the dark beam formwork, which is used to connect with the frame beam longitudinal reinforcement; The plug-in structure is an outrigger extending from the bottom surface of the wall, and the outrigger of the upper prefabricated shear wall is inserted into the connecting opening of the lower prefabricated shear wall, and the upper and lower prefabricated shear walls are fixedly connected after pouring concrete or grout; It also includes a C-shaped steel block, which includes an upper connecting plate, a middle connecting plate and a lower connecting plate; the upper connecting plate and the lower connecting plate are respectively provided with an open groove; A first anchor plate is provided at the end of the upper connection portion of the vertical reinforcement of the prefabricated shear wall, and a second anchor plate is provided at the end of the bottom outrigger reinforcement of the prefabricated shear wall; an installation window is provided on the outer side wall of the hidden beam formwork of the prefabricated shear wall; When two adjacent prefabricated shear walls are connected, the bottom protruding steel bars of the upper prefabricated shear wall are inserted into the connecting opening at the top of the lower prefabricated shear wall; the C-shaped steel block is inserted into the connecting opening through the installation window, and the bottom protruding steel bars of the upper prefabricated shear wall are inserted into the opening groove on the upper connecting plate, and the second anchor plate rests on the bottom surface of the upper connecting plate; the upper connecting part of the vertical steel bars of the lower prefabricated shear wall is inserted into the opening groove on the lower connecting plate, and the first anchor plate rests on the top surface of the lower connecting plate; the protruding steel bars of the upper prefabricated shear wall are connected through the second anchor plate, the C-shaped steel block, the first anchor plate and the vertical steel bars of the lower prefabricated shear wall to realize direct transmission of tension.
2. The assembled reinforced concrete multi-ribbed shear wall according to claim 1, characterized in that: A plurality of upper connection parts are arranged at intervals around the connection opening to increase the connection strength of the connection opening.
3. The assembled reinforced concrete multi-ribbed shear wall according to claim 2, characterized in that: A plurality of upper connection parts are arranged in the cavity of the connecting opening. When two adjacent upper and lower prefabricated shear walls are butt-jointed, the protruding steel bars of the upper prefabricated shear wall are inserted into the connecting opening and overlapped with the upper connection parts around the connecting opening of the lower prefabricated shear wall and in the cavity.
4. The assembled reinforced concrete multi-ribbed shear wall according to claim 1, characterized in that: The connecting opening and the periphery of the upper connecting portion are provided with restraining stirrups.
5. The assembled reinforced concrete multi-ribbed shear wall according to claim 1, characterized in that: The lower end of the vertical steel bar extends out of the lower connecting portion of the bottom surface of the wall to form the protruding steel bar.
6. The assembled reinforced concrete multi-ribbed shear wall according to claim 1, characterized in that: The holes are filled with lightweight prefabricated building blocks.
7. A building using the assembled reinforced concrete multi-rib shear wall according to claim 1, further comprising a prefabricated composite floor slab; The two upper and lower adjacent precast shear walls are arranged at intervals, and the bottom protruding steel bars of the upper precast shear wall are inserted into the connecting openings at the top of the lower precast shear wall; the edge of the precast composite floor slab is inserted into the interval between the two upper and lower adjacent precast shear walls and overlapped on the hidden beam formwork of the lower precast shear wall, and concrete is poured into the interval to form a post-cast joint, while the two upper and lower adjacent precast shear walls and the precast composite floor slab are fixedly connected.