A high-precision intelligent lifting equipment and construction method for steel structure corridor
By using booms and friction blocks to prevent rotation in steel structure corridor hoisting equipment, combined with multiple hangers and electric hoists, and real-time detection of shaking sensors, the problem of shaking during the hoisting process of steel structure corridors is solved and high-level Precision and high safety hoisting effect.
Patent Information
- Application Number
- CN202411020168.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-29
AI Technical Summary
Steel structure corridors are prone to shaking during the hoisting process, which poses a major safety hazard. Common single-hook cranes still cannot effectively solve the shaking problem after improvements, and are not safe enough.
Design a high-precision intelligent hoisting equipment that uses booms instead of traditional slings, sets friction blocks close to hanging balls to prevent relative rotation of the hangers, uses multiple hangers and electric hoists for suspension, and combines real-time detection and adjustment with sway sensors. Ensure smooth lifting and lowering.
It achieves stable lifting and lowering of steel structure corridors, avoids shaking, significantly improves safety and intelligence, and adapts to steel structure corridors of different sizes to ensure high-precision hoisting construction.
Smart Images

Figure CN118545612B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and in particular to high-precision intelligent hoisting equipment and a construction method for a steel structure corridor. Background Art
[0002] At present, the installation and construction of steel structure corridors generally adopt common single-hook cranes for hoisting. Due to the large size and heavy weight of steel structure corridors, the steel structure corridors are prone to violent shaking when the single-hook crane lifts the steel structure corridors (that is, during the process of the steel structure corridors being lifted off the ground), which is very dangerous. Moreover, during the process of horizontal transportation after the steel structure corridors are lifted, the steel structure corridors are suspended in the air by only a single-hook lifting rope, which makes it difficult to avoid the shaking of the steel structure corridors, posing a great safety hazard. After the steel structure corridors are transported to their place and lowered to the ground for installation, there is still a risk of violent shaking of the steel structure corridors. Therefore, common single-hook cranes have many shortcomings in the installation and construction of steel structure corridors.
[0003] Based on this, technicians in this field have made improvements to the common single-hook crane, such as increasing the number of hooks and lifting ropes, setting up lifting mechanisms, etc. These improvements can alleviate the problem of shaking of the steel structure corridor during lifting and transportation to a certain extent, such as shown in patents with publication numbers CN221070648U and CN219860119U. However, the above-mentioned improved cranes essentially still lift the steel structure corridor through a single lifting rope, and the lifting mechanism and hooks set up still have the problem of swinging around the lifting rope, which is not safe enough. Summary of the invention
[0004] The main purpose of the invention is to propose a high-precision intelligent lifting equipment and construction method for a steel structure corridor, aiming to solve the problem that the current steel structure corridor is easy to shake during the lifting process, is very dangerous and has low safety.
[0005] In order to solve the above problems, the present invention proposes a high-precision intelligent lifting equipment for a steel structure corridor, comprising a crane, the crane having a telescopic arm, a suspension rod being arranged at the far end of the telescopic arm, the upper end of the suspension rod being rotatably connected with the telescopic arm, a hanging ball being fixedly installed at the lower end of the suspension rod, a mounting plate being suspended on the hanging ball, the mounting plate being hinged with the hanging ball, a plurality of hangers being installed on the mounting plate, an electric hoist being horizontally slidably installed on the hanger, and a lifting rope being wound around the electric hoist;
[0006] A lifting device and a shaking sensor are fixedly mounted on the mounting plate. The lifting device is connected to a friction block. The friction block can be pressed against the hanging ball under the push of the lifting device, thereby preventing the hanging ball and the mounting plate from rotating relative to each other.
[0007] In one embodiment, an annular groove coaxial with the suspension rod is provided on the outer surface of the hanging ball, a liquid storage hole is provided inside the suspension rod, the upper end of the liquid storage hole extends to the upper end surface of the suspension rod, and a liquid outlet hole connected to the bottom of the liquid storage hole is provided at the lower end of the side of the suspension rod, and the lubricating liquid in the liquid storage hole flows out of the liquid outlet hole and falls onto the outer surface of the hanging ball, and the lubricating liquid flows downward along the outer surface of the hanging ball into the annular groove;
[0008] A plurality of arc grooves concentric with the hanging ball are arranged on the outer surface of the hanging ball, the upper ends of the arc grooves are communicated with the annular grooves, and the lower ends of the arc grooves extend to the connection between the mounting plate and the hanging ball.
[0009] In one embodiment, the mounting plate comprises:
[0010] The upper mounting plate is horizontally arranged and is provided with a hanging hole, wherein the hanging hole is a through hole, the upper mounting plate is hung on the hanging ball through the hanging hole, the hole wall of the hanging hole is in close contact with the outer surface of the upper hemisphere of the hanging ball, and the lower end of the arc groove is located in the hanging hole;
[0011] A lower mounting plate is located below the upper mounting plate and is parallel to the upper mounting plate, and the lifting device and the sway sensor are mounted on the lower mounting plate;
[0012] A plurality of connecting rods, the upper and lower ends of which are fixedly connected to the upper mounting plate and the lower mounting plate;
[0013] A plurality of mounting shafts are vertically arranged through the upper mounting plate and the lower mounting plate, and are rotatably connected with the upper mounting plate and the lower mounting plate, and each mounting shaft is fixedly connected with a hanger;
[0014] Motor 1 is fixedly connected to the upper mounting plate, and the motor 1 is drivingly connected to the mounting shaft to drive the mounting shaft to rotate.
[0015] In one embodiment, a guide rod is vertically fixedly installed on the lower mounting plate, a lifting seat is vertically slidably installed on the guide rod, a second motor is installed on the lifting seat, an output shaft of the second motor is fixedly connected to the friction block, the second motor is used to drive the friction block to rotate around the vertical axis, the lifting device is connected to the lifting seat, and is used to drive the lifting seat to slide vertically, and the second motor and the hanging ball are coaxial.
[0016] In one embodiment, there are four installation shafts, which are respectively arranged at two ends of the installation plate, and the two installation shafts located at the same end of the installation plate are connected through external gear meshing transmission.
[0017] In one embodiment, a linear motor is provided on the hanger, and the electric hoist is installed on the linear motor.
[0018] In addition, the present invention also proposes a high-precision intelligent hoisting construction method for a steel structure corridor, which uses the aforementioned high-precision intelligent hoisting equipment for a steel structure corridor to perform the following steps:
[0019] According to the size of the steel structure corridor, the motor is controlled to drive the installation shaft to rotate and deploy multiple hangers;
[0020] According to the size of the steel structure corridor, the linear motor is controlled to drive the electric hoist to move to the suspension position;
[0021] Control the electric hoist to unfold the lifting rope and connect the lower end of the lifting rope to the steel structure corridor;
[0022] Control all the electric hoists to retract the hoisting ropes and hoist the steel structure corridor steadily;
[0023] After the steel structure corridor leaves the ground, control the crane to transport the steel structure corridor. After the steel structure corridor is transported to the installation location, control the electric hoist to unfold the lifting rope and steadily lower the steel structure corridor to the installation location.
[0024] During the process of controlling the crane to transport the steel structure corridor, the shaking sensor detects in real time whether the mounting plate is shaking. If shaking of the mounting plate is detected, the lifting device is controlled to push the friction block upward to fit the hanging ball to prevent the mounting plate from rotating relative to the hanging ball.
[0025] In one embodiment, all electric hoists are evenly distributed at various locations directly above the steel structure corridor.
[0026] In one embodiment, after the lower end of the suspension rope is connected to the steel structure corridor, the suspension rope is inclined and forms a straight line, and two adjacent suspension ropes form an inverted figure eight shape.
[0027] In one embodiment, after the steel structure corridor is transported to the installation position, if the orientation of the steel structure corridor is incorrect, the second motor is started to drive the friction block to rotate, and at the same time the lifting device is controlled to push the friction block upward to contact the hanging ball, and then the mounting plate is driven to rotate around the vertical axis of the hanging ball to adjust the orientation of the steel structure corridor. After the orientation of the steel structure corridor is adjusted to the right position, the electric hoist is controlled to unfold the lifting rope to smoothly lower the steel structure corridor to the installation position.
[0028] Beneficial effects: The high-precision intelligent lifting equipment for the steel structure corridor of the present application solves the problem of swinging during the lifting process of the steel structure corridor by setting a suspension rod instead of a traditional suspension rope and setting a friction block close to the hanging ball to prevent the hanger from rotating relative to the hanging ball. The hanger can be extended to adapt to steel structure corridors of different sizes. It has rich functions and good practicality. Electric hoists are set on multiple hangers to suspend the same steel structure corridor, ensuring that the steel structure corridor can be lifted and lowered smoothly to avoid shaking, and has high safety.
[0029] The high-precision intelligent lifting equipment for the steel structure corridor of the present application adopts a hinged connection form of the hanger and the hanging ball, so that the steel structure corridor can always remain stable during the lifting process and is not affected by the inclination of the telescopic arm, which is conducive to the realization of high-precision lifting construction. Moreover, during the lifting and transportation of the steel structure corridor, the shaking sensor detects in real time whether it is shaking. Once the violent shaking of the steel structure corridor is detected, the friction block and the hanging ball can be controlled in time to be pressed together, so that the hanger and the hanging ball are locked and fixed, and the shaking of the steel structure corridor can be quickly reduced and eliminated, which greatly improves the lifting safety of the steel structure corridor and has a high degree of intelligence. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0031] Figure 1 It is a top view of a high-precision intelligent lifting device for a steel structure corridor of the present invention;
[0032] Figure 2 yes Figure 1 AA section view in;
[0033] Figure 3 yes Figure 2 The enlarged view of the C part in FIG.
[0034] Figure 4 yes Figure 1 A magnified view of part B in FIG.
[0035] Figure 5 This is a schematic diagram of the hoisting of the steel structure corridor;
[0036] Figure 6 yes Figure 5 Top view of the .
[0037] The following are the descriptions of the reference numerals:
[0038] 1. Telescopic arm; 2. Suspension rod; 3. Liquid storage hole; 4. Hanging ball; 5. Annular groove; 6. Arc groove; 7. Liquid outlet hole; 8. Upper mounting plate; 9. Connecting rod; 10. Lower mounting plate; 11. Mounting shaft; 12. Motor 1; 13. Driven wheel; 14. Driving wheel; 15. Suspension bracket; 16. Pin; 17. Electric hoist; 18. Suspension rope; 19. Hanging hole; 20. Guide rod; 21. Lifting seat; 22. Lifting device; 23. Motor 2; 24. Friction block; 25. Steel structure corridor; 26. Linear motor; 27. Shake sensor. DETAILED DESCRIPTION
[0039] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0040] It should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0041] In the present invention, unless otherwise clearly specified and limited, the terms "connection", "fixation", etc. should be understood in a broad sense. For example, "fixation" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0042] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or a scheme that satisfies both A and B. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in the field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0043] The present invention proposes a high-precision intelligent lifting device for a steel structure corridor. The high-precision intelligent lifting device for the steel structure corridor solves the problem of swinging during the lifting process of the steel structure corridor 25 by arranging a suspension rod 2 instead of a traditional suspension rope and arranging a friction block 24 close to a hanging ball 4 to prevent the hanger 15 from rotating relative to the hanging ball 4. The hanger 15 is extendable to adapt to steel structure corridors 25 of different sizes. The device has rich functions and good practicality. Electric hoists 17 are arranged on multiple hangers 15 to suspend the same steel structure corridor 25, thereby ensuring that the steel structure corridor 25 can be lifted and lowered smoothly to avoid shaking, and the device has high safety.
[0044] In addition, the high-precision intelligent lifting equipment of the steel structure corridor adopts a hinged connection between the hanger 15 and the hanging ball 4, so that the steel structure corridor 25 can always remain stable during the lifting process and is not affected by the inclination of the telescopic arm 1, which is conducive to the realization of high-precision lifting construction. Moreover, during the lifting and transportation of the steel structure corridor 25, the shaking sensor 27 detects in real time whether it is shaking. Once it is detected that the steel structure corridor 25 is shaking violently, it can timely control the friction block 24 to press the hanging ball 4, so that the hanger 15 and the hanging ball 4 are locked and fixed, and the shaking of the steel structure corridor 25 is quickly reduced and eliminated, which greatly improves the lifting safety of the steel structure corridor 25 and has a high degree of intelligence.
[0045] Specifically, in one embodiment of the invention, the high-precision intelligent lifting equipment for the steel structure corridor includes a crane having a telescopic arm 1, such as Figure 1 and Figure 2 As shown, the distal end of the telescopic arm 1 is rotatably connected to the upper end of the suspension rod 2 via a pin shaft, and the suspension rod 2 and the distal end of the telescopic arm 1 are rotatably connected with each other with a certain extrusion friction force. This design does not affect the lifting and retracting of the telescopic arm 1, and avoids the random shaking of the suspension rod 2. The so-called random shaking of the suspension rod 2 refers to the suspension rod 2 swinging back and forth around its upper end in an irregular and easy manner. The design that the upper end of the suspension rod 2 is rotatably connected to the distal end of the telescopic arm 1 via a pin shaft prevents the suspension rod 2 from swinging easily, because the suspension rod 2 and the distal end of the telescopic arm 1 are rotatably connected with each other with a certain extrusion friction force. The existence of this force prevents the suspension rod 2 from swaying at will, thereby realizing the smooth lifting of the steel structure corridor 25 with high safety.
[0046] In this embodiment, if Figure 1 and Figure 2 As shown, a hanging ball 4 is fixedly installed at the lower end of the suspension rod 2. Preferably, the hanging ball 4 and the suspension rod 2 are coaxial, and the diameter of the suspension rod 2 is smaller than the ball diameter of the hanging ball 4. This design makes it convenient for the installation plate to be hung on the hanging ball 4.
[0047] In this embodiment, a mounting plate is suspended on the hanging ball 4, and the mounting plate is hinged to the hanging ball 4. Specifically, Figure 1 and Figure 2As shown, the mounting plate includes: an upper mounting plate 8, a lower mounting plate 10, a plurality of connecting rods 9, a plurality of mounting shafts 11, and a motor 12. The upper mounting plate 8 is horizontally arranged and is provided with a hanging hole 19, which is a through hole. The upper mounting plate 8 is hung on the hanging ball 4 through the hanging hole 19. Figure 2 As shown, the hole wall of the hanging hole 19 is in close contact with the outer surface of the upper hemisphere of the hanging ball 4, and the hole wall of the hanging hole 19 and the outer surface of the upper hemisphere of the hanging ball 4 are slidably connected, thereby realizing the ball hinge connection between the upper mounting plate 8 and the hanging ball 4.
[0048] Further, such as Figure 1-Figure 4 As shown, the outer surface of the hanging ball 4 is provided with an annular groove 5 coaxial with the suspension rod 2, and the annular groove 5 is located on the outer surface of the upper hemisphere of the hanging ball 4. The suspension rod 2 is provided with a liquid storage hole 3 inside, and the upper end of the liquid storage hole 3 extends to the upper end surface of the suspension rod 2. With this design, lubricating liquid can be added to the liquid storage hole 3 from the upper end of the liquid storage hole 3, and the lower end of the side of the suspension rod 2 is provided with a liquid outlet hole 7 connected to the bottom of the liquid storage hole 3. Preferably, the liquid outlet hole 7 is an inclined hole, and the high end of the inclined hole is located at the bottom of the liquid storage hole 3. The lubricating liquid in the liquid storage hole 3 flows out from the liquid outlet hole 7 and falls on the outer surface of the hanging ball 4, and then the lubricating liquid flows downward along the outer surface of the hanging ball 4 into the annular groove 5. shaped groove 5, a plurality of arc grooves 6 concentric with the hanging ball 4 are arranged on the outer surface of the hanging ball 4, and preferably, the plurality of arc grooves 6 are evenly distributed on the outer surface of the upper hemisphere of the hanging ball 4, the upper end of the arc groove 6 is connected with the annular groove 5, and the lower end of the arc groove 6 extends to the connection between the mounting plate and the hanging ball 4, that is, the lower end of the arc groove 6 is located in the hanging hole 19. In this design, the lubricating fluid in the annular groove 5 flows into each arc groove 6, and the lubricating fluid flows into the hanging hole 19 through each arc groove 6 to lubricate the hole wall of the hanging hole 19 and the outer surface of the upper hemisphere of the hanging ball 4, thereby reducing the friction resistance of the hole wall of the hanging hole 19 and the outer surface of the upper hemisphere of the hanging ball 4 slidingly connected.
[0049] In this embodiment, a plurality of hangers 15 are installed on the mounting plate, and an electric hoist 17 is horizontally slidably installed on the hanger 15. The sliding connection design of the electric hoist 17 is adapted to adapt to steel structure corridors 25 of different sizes. A lifting rope 18 is wound around the electric hoist 17, and the lower end of the lifting rope 18 can be connected to the steel structure corridor 25. The arrangement of multiple hangers 15 enables a steel structure corridor 25 to be connected to multiple lifting ropes 18. With this design, multiple lifting ropes 18 are evenly distributed on the steel structure corridor 25, and multiple lifting ropes 18 are lifted at the same time to achieve stable lifting of the steel structure corridor 25, thereby solving the problem of violent shaking caused by unstable center of gravity fluctuation during the process of lifting the steel structure corridor 25 off the ground. Electric hoists 17 are arranged on multiple hangers 15 to suspend the same steel structure corridor 25, thereby ensuring that the steel structure corridor 25 can be lifted and lowered smoothly to avoid shaking, and having high safety.
[0050] In this embodiment, a lifting device 22 and a shaking sensor 27 are fixedly installed on the mounting plate. The shaking sensor 27 is used to detect whether the mounting plate is shaking, thereby indirectly detecting whether the lifted steel structure corridor 25 is shaking during transportation. The lifting device 22 is connected to a friction block 24. The friction block 24 can be pressed against the hanging ball 4 under the push of the lifting device 22, thereby increasing the squeezing force between the hanging ball 4 and the hole wall of the hanging hole 19, and then increasing the static friction between the hanging ball 4 and the hole wall of the hanging hole 19, thereby preventing the hanging ball 4 and the mounting plate from rotating relative to each other, thereby realizing the locking and fixing connection between the hanging ball 4 and the mounting plate. With this design, when the shaking sensor 27 is moved, the hanging ball 4 and the mounting plate are locked. When the sensor 27 detects that the lifted steel structure corridor 25 shakes during transportation, the lifting device 22 immediately acts to push the friction block 24 close to the hanging ball 4, locks the hanging ball 4 and the mounting plate, and quickly reduces and eliminates the shaking of the steel structure corridor 25 to ensure the safety of the lifting of the steel structure corridor 25. During the transportation of the entire steel structure corridor 25, the shaking sensor 27 automatically detects whether the steel structure corridor 25 shakes in real time, and transmits the detection data to the controller, which automatically controls the action of the lifting device 22 according to the detection data, without the need for manual monitoring assistance, and has a high degree of automation and intelligence.
[0051] Specifically, Figure 2 As shown, the lower mounting plate 10 is located below the upper mounting plate 8 and is parallel to the upper mounting plate 8. The lifting device 22 and the sway sensor 27 are installed on the lower mounting plate 10. The upper and lower ends of the plurality of connecting rods 9 are fixedly connected to the upper mounting plate 8 and the lower mounting plate 10. The plurality of mounting shafts 11 vertically penetrate the upper mounting plate 8 and the lower mounting plate 10 and are rotatably connected to the upper mounting plate 8 and the lower mounting plate 10. Each mounting shaft 11 is fixedly connected to a hanger 15 by a pin 16. The rotation of 11 drives the hanger 15 connected thereto to rotate, the hanger 15 is provided with a linear motor 26, the electric hoist 17 is installed on the linear motor 26, the motor 12 is fixedly connected to the upper mounting plate 8, the motor 12 is transmission connected to the mounting shaft 11, and is used to drive the mounting shaft 11 to rotate, thereby driving the hanger 15 to rotate, and adjusting the position of the hanger 15 to adapt to steel structure corridors 25 of different sizes, thereby ensuring the smooth lifting of the steel structure corridor 25, with rich functions and good practicality.
[0052] Preferably, Figure 1 and Figure 2 As shown, there are four mounting shafts 11, which are respectively arranged at the left and right ends of the mounting plate. The two mounting shafts 11 located at the same end of the mounting plate are connected through an external meshing transmission of a driven wheel 13, and the output shaft of the motor 12 is equipped with a driving wheel 14 meshing with the driven wheel 13.
[0053] The high-precision intelligent lifting equipment for the steel structure corridor of this embodiment adopts a hinged connection between the upper mounting plate 8 and the hanging ball 4, so that the steel structure corridor 25 can always remain stable during the lifting process, and is not affected by the inclination of the telescopic arm 1, which is conducive to the realization of high-precision lifting construction. For example, when the ground is uneven or the soil is soft, the crane will inevitably tilt slightly during the lifting and transportation of the steel structure corridor 25. At this time Figure 2 The vertical hanger 2 in the middle will tilt, while the articulated connection between the upper mounting plate 8 and the hanging ball 4 ensures that the upper mounting plate 8 remains horizontal when the hanger 2 tilts, that is, the steel structure corridor 25 can always remain stable and not tilted during the hoisting process, and is not affected by the inclination of the telescopic arm 1, which helps to achieve high-precision hoisting construction of the steel structure corridor 25. After the steel structure corridor 25 is transported to the installation position, the electric hoist 17 is controlled to unfold the hoisting rope 18, and the steel structure corridor 25 is steadily lowered to the installation position.
[0054] Further, such as Figure 2 As shown, a guide rod 20 is vertically fixedly installed on the lower mounting plate 10, and a lifting seat 21 is vertically slidably installed on the guide rod 20, and a motor 23 is installed on the lifting seat 21. The output shaft of the motor 23 is fixedly connected to the friction block 24, and the motor 23 is used to drive the friction block 24 to rotate around the vertical axis. The lifting device 22 is connected to the lifting seat 21, and is used to drive the lifting seat 21 to slide vertically. The motor 23 and the hanging ball 4 are coaxial. In this design, the motor 23 is started to drive the friction block 24 to rotate, and the lifting device 22 is controlled to push the friction block 24 to move up and contact with the hanging ball 4. The hanging ball 4 and the motor 23 can be used to reversely drive the mounting plate to rotate around the vertical axis of the hanging ball 4 to adjust the orientation of the steel structure corridor 25, which is convenient for the high-precision lifting construction of the steel structure corridor 25. After the orientation of the steel structure corridor 25 is adjusted to the right position, the electric hoist 17 is controlled to unfold the lifting rope 18, and the steel structure corridor 25 is smoothly lowered to the installation position.
[0055] In addition, the present invention also proposes a high-precision intelligent hoisting construction method for a steel structure corridor, which uses the aforementioned high-precision intelligent hoisting equipment for a steel structure corridor to perform the following steps:
[0056] S1, according to the size of the steel structure corridor 25, the motor 12 is controlled to drive the installation shaft 11 to rotate and unfold multiple hangers 15, and then according to the size of the steel structure corridor 25, the linear motor 26 is controlled to drive the electric hoist 17 to move to the suspension position, such as Figure 5 and Figure 6 As shown, all the electric hoists 17 are evenly distributed at various places just above the steel structure corridor 25. The purpose of this design is to enable the subsequent lifting ropes 18 of multiple electric hoists 17 to stably lift the steel structure corridor 25, and to prevent the steel structure corridor 25 from being violently shaken due to unstable center of gravity fluctuations when it is lifted off the ground, thereby ensuring lifting safety;
[0057] S2, control the electric hoist 17 to unfold the suspension rope 18, and connect the lower end of the suspension rope 18 to the steel structure corridor 25. Preferably, as Figure 5 and Figure 6 As shown, after the lower end of the suspension rope 18 is connected to the steel structure corridor 25, the suspension rope 18 is inclined and in a straight line, and two adjacent suspension ropes 18 are in an inverted figure eight shape. This design is conducive to improving the stability of the suspension rope 18 suspending the steel structure corridor 25 and reducing the probability of the steel structure corridor 25 shaking relative to the suspension rope 18;
[0058] S3, control all the electric hoists 17 to move and retract the hoisting ropes 18 to lift the steel structure corridor 25 steadily, so that the steel structure corridor 25 does not shake violently due to the unstable center of gravity when being lifted off the ground, thereby ensuring the safety of lifting;
[0059] S4, after the steel structure corridor 25 leaves the ground, the crane is controlled to transport the steel structure corridor 25. After the steel structure corridor 25 is transported to the installation position, the electric hoist 17 is controlled to unfold the lifting rope 18, and the steel structure corridor 25 is smoothly lowered to the installation position. Specifically, in the process of controlling the crane to transport the steel structure corridor 25, the shaking sensor 27 detects in real time whether the installation plate is shaking. If the installation plate is detected to be shaking, the lifting device 22 is controlled to push the friction block 24 to move up and close to the hanging ball 4 to prevent the installation plate from rotating relative to the hanging ball 4, so as to avoid the shaking of the steel structure corridor 25 and ensure the safety of transportation. After the steel structure corridor 25 is transported to the installation position, the lifting device 22 drives the friction block 24 to move down and reset, and then the electric hoist 17 is controlled to unfold the lifting rope 18, and the steel structure corridor 25 is smoothly lowered to the installation position;
[0060] If it is found that the orientation of the steel structure corridor 25 is incorrect before the electric hoist 17 is controlled to unfold the lifting rope 18 to smoothly lower the steel structure corridor 25 to the installation position, the motor 23 is started to drive the friction block 24 to rotate, and the lifting device 22 is controlled to push the friction block 24 to move up and contact the hanging ball 4. With the help of the hanging ball 4 and the motor 23, the mounting plate is driven in reverse to rotate around the vertical axis of the hanging ball 4 to adjust the orientation of the steel structure corridor 25. After the orientation of the steel structure corridor 25 is adjusted to the right position, the electric hoist 17 is controlled to unfold the lifting rope 18 to smoothly lower the steel structure corridor 25 to the installation position, thereby realizing high-precision lifting construction of the steel structure corridor 25.
[0061] In this embodiment, the lifting device 22 is a cylinder, a hydraulic cylinder or a linear motor.
[0062] The above description is only a preferred embodiment of the present invention, and does not limit the patent scope of the present invention. All equivalent structural changes made by using the contents of the present invention specification and drawings under the inventive concept of the present invention, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present invention.
Claims
1. A high-precision intelligent lifting equipment for a steel structure corridor, comprising a crane having a telescopic arm, characterized in that: The distal end of the telescopic arm is rotatably connected to the upper end of the boom, a hanging ball is fixedly installed at the lower end of the boom, a mounting plate is suspended on the hanging ball, the mounting plate is hinged with the hanging ball, a plurality of hangers are installed on the mounting plate, an electric hoist is horizontally slidably installed on the hanger, and a hanging rope is wound around the electric hoist; A lifting device and a shaking sensor are fixedly mounted on the mounting plate, and the lifting device is connected to a friction block. The friction block can be pressed against the hanging ball under the push of the lifting device, thereby preventing the hanging ball and the mounting plate from rotating relative to each other; An annular groove coaxial with the suspension rod is arranged on the outer surface of the hanging ball, a liquid storage hole is arranged inside the suspension rod, the upper end of the liquid storage hole extends to the upper end surface of the suspension rod, and a liquid outlet hole connected to the bottom of the liquid storage hole is arranged at the lower end of the side of the suspension rod, and the lubricating liquid in the liquid storage hole flows out from the liquid outlet hole and falls onto the outer surface of the hanging ball, and the lubricating liquid flows downward along the outer surface of the hanging ball into the annular groove; A plurality of arc grooves concentric with the hanging ball are arranged on the outer surface of the hanging ball, the upper ends of the arc grooves are connected with the annular grooves, and the lower ends of the arc grooves extend to the connection between the mounting plate and the hanging ball; The mounting plate comprises: The upper mounting plate is horizontally arranged and is provided with a hanging hole, wherein the hanging hole is a through hole, the upper mounting plate is hung on the hanging ball through the hanging hole, the hole wall of the hanging hole is in close contact with the outer surface of the upper hemisphere of the hanging ball, and the lower end of the arc groove is located in the hanging hole; A lower mounting plate is located below the upper mounting plate and is parallel to the upper mounting plate, and the lifting device and the sway sensor are mounted on the lower mounting plate; A plurality of connecting rods, the upper and lower ends of which are fixedly connected to the upper mounting plate and the lower mounting plate; A plurality of mounting shafts are vertically arranged through the upper mounting plate and the lower mounting plate, and are rotatably connected with the upper mounting plate and the lower mounting plate, and each mounting shaft is fixedly connected with a hanger; Motor 1 is fixedly connected to the upper mounting plate, and the motor 1 is drivingly connected to the mounting shaft to drive the mounting shaft to rotate; A guide rod is vertically fixedly installed on the lower mounting plate, a lifting seat is vertically slidably installed on the guide rod, a second motor is installed on the lifting seat, an output shaft of the second motor is fixedly connected to the friction block, the second motor is used to drive the friction block to rotate around the vertical axis, the lifting device is connected to the lifting seat, and is used to drive the lifting seat to slide vertically, and the second motor and the hanging ball are coaxial.
2. The high-precision intelligent lifting equipment for a steel structure corridor according to claim 1, characterized in that: There are four installation shafts, which are arranged at two ends of the installation plate. Two installation shafts located at the same end of the installation plate are connected through external gear meshing transmission.
3. The high-precision intelligent lifting equipment for a steel structure corridor according to claim 2, characterized in that: The hanger is provided with a linear motor, and the electric hoist is installed on the linear motor.
4. A high-precision intelligent hoisting construction method for a steel structure corridor, characterized in that: The following steps are performed using a high-precision intelligent lifting device for a steel structure corridor according to claim 3: According to the size of the steel structure corridor, the motor is controlled to drive the installation shaft to rotate and deploy multiple hangers; According to the size of the steel structure corridor, the linear motor is controlled to drive the electric hoist to move to the suspension position; Control the electric hoist to unfold the lifting rope and connect the lower end of the lifting rope to the steel structure corridor; Control all the electric hoists to retract the hoisting ropes and hoist the steel structure corridor steadily; After the steel structure corridor leaves the ground, control the crane to transport the steel structure corridor. After the steel structure corridor is transported to the installation location, control the electric hoist to unfold the lifting rope and steadily lower the steel structure corridor to the installation location. During the process of controlling the crane to transport the steel structure corridor, the shaking sensor detects in real time whether the mounting plate is shaking. If shaking of the mounting plate is detected, the lifting device is controlled to push the friction block upward to fit the hanging ball to prevent the mounting plate from rotating relative to the hanging ball.
5. A high-precision intelligent hoisting construction method for a steel structure corridor as claimed in claim 4, characterized in that: All electric hoists are evenly distributed above the steel structure corridor.
6. A high-precision intelligent hoisting construction method for a steel structure corridor as claimed in claim 4, characterized in that: After the lower end of the suspension rope is connected to the steel structure corridor, the suspension rope is inclined and forms a straight line, and two adjacent suspension ropes form an inverted figure eight shape.
7. A high-precision intelligent hoisting construction method for a steel structure corridor as claimed in claim 4, characterized in that: After the steel structure corridor is transported to the installation position, if the orientation of the steel structure corridor is incorrect, start motor 2 to drive the friction block to rotate, and at the same time control the lifting device to push the friction block upward to contact the hanging ball, and then drive the installation plate to rotate around the vertical axis of the hanging ball to adjust the orientation of the steel structure corridor. After the orientation of the steel structure corridor is adjusted to the right position, control the electric hoist to unfold the lifting rope and smoothly lower the steel structure corridor to the installation position.