A bridge deck widening structure and construction method suitable for existing bridge structures

Through the fastening connection and positioning mechanism of prefabricated plates and prefabricated support structures, combined with the casting of light aggregate UHPC, the problem of disturbance and insufficient bearing capacity of the existing bridge deck widening structure on existing bridges is solved, and the structural Self-stabilization and load-bearing capacity are improved.

CN118547571BActive Publication Date: 2024-11-15HUNAN PROVINCIAL COMM PLANNING SURVEY & DESIGN INST CO LTD
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202410994048.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2024-11-15
Estimated Expiration
2044-07-24

AI Technical Summary

Technical Problem

The existing bridge deck widening structure causes great disturbances to the existing bridge structure during construction, and cannot solve the problem of insufficient bearing capacity at the same time. The conventional expansion structure has a single function, which increases the engineering cost.

Method used

Prefabricated plates and prefabricated support structures are used to connect the prefabricated plates to the web and flange ends of the existing bridge by fastening the connecting rods and pre-positioning mechanisms to form a self-stabilizing structure. Prefabricated plates are used as templates during construction and cast Light aggregate UHPC structural layer to enhance longitudinal and lateral load-bearing capacity.

Benefits of technology

It reduces construction disturbances, simplifies construction technology, improves the integrity and safety redundancy of the structure, reduces the bending moment at the root of the flange, and achieves bridge deck widening and structural reinforcement while improving load-bearing capacity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118547571B_ABST
    Figure CN118547571B_ABST
Patent Text Reader

Abstract

The present invention provides a bridge deck widening structure and construction method applicable to an existing bridge structure, including an existing bridge, a precast plate, a connection assembly, and a plurality of precast support structures arranged at intervals along the bridge direction, each precast support structure including a precast T-shaped rib, an inner lining plate, and a fastening connecting rod, the precast T-shaped rib including a web connecting end and a cantilever widened end, the inner lining plate, the web of the existing bridge, and the web connecting end are connected to each other through a fastening connecting rod, the cantilever widened end is connected to the flange end of the existing bridge through a connection assembly, a pre-positioning mechanism is formed at the cantilever widened end, the pre-positioning mechanism has a pre-positioning groove, and the precast plate is supported in the pre-positioning groove. In this way, a large number of reinforcement processes are saved by the connection method of the fastening connecting rod, and the disturbance to the existing structure is small; the structure remains self-stable during the construction process, and the time of hoisting cross operation is reduced; after the structural layer is poured, it participates in the force as a part of the existing bridge as a whole, greatly improving the longitudinal and lateral bearing capacity of the existing structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridges, and in particular to a bridge deck widening structure and a construction method suitable for an existing bridge structure. Background Art

[0002] Traditional bridge deck widening structures in the prior art usually require a large amount of embedded reinforcement during construction, which is complex to construct and causes great disturbance to the existing structure. Considering that some bridges have been in service for a long time and have accumulated a lot of defects, such widening structures and construction methods will cause further damage to the existing structure. In addition, the conventional expansion structure has a relatively single function and can only solve the problem of widening the deck of existing bridges. It cannot solve the problem of insufficient bearing capacity of some bridges due to expansion, increased dead load and defects of the structure itself. Other reinforcement measures need to be taken, which increases the project cost.

[0003] In view of this, it is necessary to propose a bridge deck widening structure suitable for existing bridge structures to solve or at least alleviate the above-mentioned defects. Summary of the invention

[0004] The main purpose of the present invention is to provide a bridge deck widening structure suitable for existing bridge structures, so as to solve the problem that the bridge deck widening structure in the prior art has a large disturbance to the existing structure and cannot simultaneously meet the requirements of strengthening the existing structure.

[0005] To achieve the above-mentioned object, the present invention provides a bridge deck widening structure applicable to an existing bridge structure, comprising an existing bridge, a prefabricated plate, a connection assembly, and two prefabricated support units arranged on the outer side of the web of the existing bridge in a transverse direction of the bridge, each of the prefabricated support units comprising a plurality of prefabricated support structures arranged at intervals in the longitudinal direction of the bridge; wherein:

[0006] Each of the prefabricated supporting structures includes a prefabricated T-shaped rib, an inner lining plate and a fastening connecting rod, wherein the prefabricated T-shaped rib includes a web connecting end and a cantilevered widened end, wherein a plurality of screw holes arranged at intervals along the web of the existing bridge are reserved, the inner lining plate is provided with through holes corresponding to the screw holes, and the web connecting end is provided with connecting holes corresponding to the screw holes, and the fastening connecting rod passes through the through holes, the screw holes and the connecting holes in sequence and extends into the web connecting end to fix the inner lining plate, the web of the existing bridge and the web connecting end to each other; the cantilevered widened end is connected to the flange end of the existing bridge through the connecting assembly to form a self-stabilizing structure;

[0007] A pre-positioning mechanism is protruded upward on the cantilevered widened end, and the pre-positioning mechanism has pre-positioning grooves on both sides along the longitudinal direction of the bridge for positioning the prefabricated board in the longitudinal and transverse directions of the bridge. The two ends of the prefabricated board are respectively supported in the pre-positioning grooves between two adjacent prefabricated supporting structures.

[0008] Preferably, the pre-positioning mechanism comprises an outwardly protruding block, a shear-resistant mounting block and a prefabricated anchor block, all of which are arranged on the cantilever widened end; the outwardly protruding block and the prefabricated anchor block are respectively arranged at both ends of the shear-resistant mounting block along the transverse direction of the bridge, and the prefabricated anchor block is arranged away from the flange end of the existing bridge;

[0009] The protruding block and the prefabricated anchor block are both the same width as the prefabricated T-shaped rib, and the width of the shear-resistant mounting block is smaller than the width of the prefabricated T-shaped rib. The shear-resistant mounting block is arranged in the middle of the prefabricated T-shaped rib so that the pre-positioning groove is formed between the protruding block, the shear-resistant mounting block and the prefabricated anchor block.

[0010] Preferably, the web of the existing bridge is provided with a first shear key groove and a second shear key groove on both inner and outer sides, respectively, wherein a first shear key protrusion corresponding to the first shear key groove is formed outwardly on a side wall surface of the inner lining plate close to the web, and the first shear key protrusion is embedded in the first shear key groove;

[0011] A second shear key protrusion corresponding to the second shear key groove is formed outwardly on a side wall surface of the web connecting end close to the web, and the second shear key protrusion is embedded in the second shear key groove;

[0012] Structural adhesive is provided between the first shear key groove and the first shear key protrusion, and between the second shear key groove and the second shear key protrusion.

[0013] Preferably, the connection assembly comprises a transverse prestressed steel strand, and the prefabricated anchor block is provided with a prefabricated channel, wherein:

[0014] One end of the transverse prestressed steel bundle extends into the flange end connected to the existing bridge, and the other end of the transverse prestressed steel bundle extends along the transverse direction of the bridge toward the cantilevered widened end and extends into the prefabricated channel fixed to the prefabricated anchor block.

[0015] Preferably, the connection assembly further comprises a plurality of shear steel bars spaced apart in the transverse direction of the bridge, the bottom of the shear steel bars being embedded in the shear mounting block, and the top of the shear steel bars extending upward from the bottom to form a closed loop.

[0016] Preferably, the web of the existing bridge is an inclined web, and the web connecting end of the prefabricated T-shaped rib is arranged to match the web and be inclined.

[0017] Preferably, the connecting assembly also includes a plurality of transverse structural steel bars arranged at intervals along the longitudinal direction of the bridge, one end of the transverse structural steel bar is overlapped with the existing steel bar at the flange end of the existing bridge, and the other end of the transverse structural steel bar extends outward along the transverse direction of the bridge and is cantilevered.

[0018] The present application also provides a construction method for a bridge deck widening structure applicable to an existing bridge structure, which is applied to the bridge deck widening structure applicable to the existing bridge structure as described above, and specifically comprises the steps of:

[0019] S1, pre-treating an existing bridge so that the load-bearing components of the existing bridge are exposed to form a bridge to be repaired; wherein the load-bearing components include transverse prestressed arrangement strips and existing steel bars at the flange ends of the existing bridge;

[0020] S2, installing a prefabricated support structure on the bridge to be repaired, pre-assembling the prefabricated support structure on the bridge to be repaired and making it self-stabilizing to form a blank beam to be widened, and a plurality of the prefabricated support structures are arranged at intervals on the lateral side of the bridge to be repaired along the longitudinal direction of the bridge; wherein the first end of each of the prefabricated support structures is fixedly connected to one side of the bridge to be repaired, and the second end of the prefabricated support structure extends outward from the first end along the transverse direction of the bridge and is cantilevered;

[0021] S3, hoisting the prefabricated panels onto the blank beam to be widened and pre-positioning them, the prefabricated panels are arranged in the pre-positioning grooves between two adjacent prefabricated support structures, and a plurality of the prefabricated panels are combined on the prefabricated support structures to form an integral widened blank;

[0022] S4, pouring a lightweight aggregate UHPC structural layer on the widened preform and the existing bridge deck structural layer to form a widened bridge.

[0023] Preferably, the step S2 specifically comprises the steps of:

[0024] S21, processing the web of the existing bridge so that a first shear key groove and a second shear key groove are respectively opened on both sides of the web, and screw holes are opened on the web; wherein the screw holes are arranged through the width direction of the web, and structural adhesive is applied to the first shear key groove and the second shear key groove;

[0025] S22, hoisting the inner lining plate and the prefabricated T-shaped rib to the target installation position respectively; wherein the existing bridge is a box girder, the inner lining plate is located in the box chamber inside the web, and the prefabricated T-shaped rib is located outside the web;

[0026] S23, by tightening the connecting rod, sequentially passing through the through hole, the screw hole, and the connecting hole and extending into the web connecting end of the prefabricated T-shaped rib, the inner lining plate, the web and the web connecting end of the prefabricated T-shaped rib are sequentially fixedly connected, and the first shear key protrusion is correspondingly clamped in the first shear key groove, and the second shear key protrusion is correspondingly clamped in the second shear key groove;

[0027] S24, installing a transverse prestressed steel bundle in the transverse prestressed arrangement strip, anchoring one end of the transverse prestressed steel bundle in a prefabricated hole of a prefabricated anchor block, and tensioning the transverse prestressed steel bundle once, so that the prefabricated T-shaped rib forms a self-stabilizing structure;

[0028] S25, repeating steps S21 to S24 to arrange a plurality of the prefabricated support structures at intervals along the longitudinal direction of the bridge to form the blank beam to be widened with self-stabilizing capability.

[0029] Preferably, the step S3 further includes the following steps:

[0030] S31, laying transverse structural steel bars using the prefabricated plate as a template, and overlapping one end of the transverse structural steel bars with the existing steel bars at the flange end of the existing bridge;

[0031] S32, using the precast panel as a template to cast a lightweight aggregate UHPC structural layer on the widened preform;

[0032] S33, the transverse prestressed steel tendons are tensioned twice to the designed tension control stress.

[0033] Compared with the prior art, the present invention has the following beneficial effects:

[0034] The present invention provides a bridge deck widening structure and construction method applicable to an existing bridge structure, comprising an existing bridge, a precast panel, a connection assembly and a plurality of precast supporting structures arranged at intervals along the direction of the bridge, each precast supporting structure comprising a precast T-shaped rib, an inner lining plate and a fastening connecting rod, the precast T-shaped rib comprising a web connecting end and a cantilevered widened end, the inner lining plate, the web of the existing bridge and the web connecting end are interconnected by a fastening connecting rod, the cantilevered widened end is connected to the flange end of the existing bridge by a connection assembly, a pre-positioning mechanism is formed on the cantilevered widened end protruding upward, the pre-positioning mechanism has pre-positioning grooves on both sides along the direction of the bridge, and the precast panel is supported in the pre-positioning grooves. In this way, the connection method of tightening the connecting rods eliminates the construction process of a large number of embedded steel bars required for conventional reinforcement structures, which has little disturbance to the existing structure, simple construction process and reliable quality; combined with the connection components, the structure can remain self-stabilized during the construction process, reducing the time of temporary lifting and cross-operation and the additional structural measures generated thereby, and further simplifying the construction process; adjacent prefabricated support structures are connected as a whole through prefabricated panels, which are used as templates during the construction process. After the lightweight aggregate UHPC is poured, it participates in the load as a part of the structure as a whole, realizing the combination of permanent and temporary, which can greatly enhance the longitudinal and lateral bearing capacity of the structure and improve the structural integrity; further, the force mode of the flange end of the existing bridge is transformed from cantilever beam force to equivalent continuous beam force, which increases the bridge deck width while reducing the bending moment at the root of the flange. Combined with the inner lining plate reinforcement structure set at the web of the existing bridge, the safety redundancy of the structure is greatly improved; and most of the structures can be prefabricated in the factory, which takes up less time on site, improves the convenience and economy of construction, and is more conducive to construction quality control. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.

[0036] Figure 1 A schematic elevational cross-sectional view of the overall structure of an embodiment of the present invention;

[0037] Figure 2 is a three-dimensional schematic diagram of a prefabricated support unit in one embodiment of the present invention;

[0038] Figure 3 is a three-dimensional schematic diagram of a prefabricated support structure in one embodiment of the present invention;

[0039] Figure 4 A horizontal cross-sectional schematic diagram of the overall structure in one embodiment of the present invention;

[0040] Figure 5 It is a schematic diagram of the outer side of the overall structure in one embodiment of the present invention;

[0041] Figure 6 It is a schematic diagram of the inner side of the overall structure in one embodiment of the present invention;

[0042] The purpose, features and advantages of the present invention will be further described with reference to the accompanying drawings in conjunction with the embodiments.

[0043] Description of Figure Numbers:

[0044] 10. Prefabricated support structure; 110. Prefabricated T-shaped rib; 111. Web connection end; 112. Cantilever widened end; 113. Connection hole; 114. Second shear key protrusion; 120. Lining plate; 121. First shear key protrusion; 130. Fastening connecting rod; 140. Pre-positioning mechanism; 141. Pre-positioning groove; 142. External convex block; 143. Shear mounting block; 144. Prefabricated anchor block; 1441 , prefabricated channel; 20, connection assembly; 210, transverse prestressed steel strand; 220, shear reinforcement; 230, transverse structural reinforcement; 30, prefabricated plate; 310, lap boss; 40, existing bridge; 410, web; 411, first shear key groove; 412, second shear key groove; 420, flange end; 430, load-bearing member; 431, existing reinforcement; 440, lightweight aggregate UHPC structural layer. DETAILED DESCRIPTION

[0045] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.

[0046] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0047] It should be noted that all directional indications (such as up, down, left, right, front, back, etc.) in the embodiments of the present invention are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0048] In addition, the descriptions of "first", "second", etc. in the present invention are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0049] Please refer to the attached Figure 1-6 In one embodiment of the present invention, a bridge deck widening structure suitable for an existing bridge 40 structure is provided, comprising an existing bridge 40, a prefabricated plate 30, a connecting assembly 20, and two prefabricated support units arranged relatively on the outside of the web 410 of the existing bridge 40 along the transverse bridge direction, each of the prefabricated support units comprising a plurality of prefabricated support structures 10 arranged at intervals along the longitudinal bridge direction. First of all, it should be noted that the longitudinal bridge direction in the present application refers to the extension direction along the existing bridge 40, and the transverse bridge direction refers to the width direction along the existing bridge 40; and the traditional bridge deck widening structure in the prior art usually requires a large number of embedded steel bars during construction, the construction is complex and has a large disturbance to the existing structure. Considering that some bridges have been in service for a long time and have accumulated a large number of diseases, such a widening structure and construction method will cause further damage to the existing structure; in addition, the conventional expansion structure has a relatively single function and can only solve the problem of widening the bridge deck of the existing bridge. For some bridges, the problem of insufficient bearing capacity caused by the expansion of the capacity, the increase of the dead load and the disease of the structure itself cannot be solved at the same time, and other reinforcement measures need to be taken, which increases the project cost. This application solves the above-mentioned defects in the prior art by providing a bridge deck widening structure and construction method applicable to existing bridge structures. The details are as follows:

[0050] Each of the prefabricated supporting structures 10 includes a prefabricated T-shaped rib 110, an inner lining plate 120 and a fastening connecting rod 130, wherein the prefabricated T-shaped rib 110 includes a web connecting end 111 and a cantilevered widened end 112, wherein a plurality of screw holes arranged at intervals along the web 410 of the existing bridge 40 are reserved, the inner lining plate 120 is provided with through holes corresponding to the screw holes, and the web connecting end 111 is provided with connecting holes 113 corresponding to the screw holes, and the fastening connecting rod 130 passes through the through holes, the screw holes and the connecting holes 113 in sequence and extends into the web connecting end 111 to fix the inner lining plate 120, the web 410 of the existing bridge 40 and the web connecting end 111 to each other; the cantilevered widened end 112 is connected to the flange end 420 of the existing bridge 40 through the connecting assembly 20 to form a self-stabilizing structure.

[0051] Specifically, the bridge deck widening structure in the present application includes an existing bridge 40, a prefabricated plate 30, a connecting assembly 20 and two prefabricated support units. The existing bridge 40 is used as a widening object, and the prefabricated support units are used as widening structures. Therefore, in order to ensure that the widening of both sides of the existing bridge 40 is consistent, the two prefabricated support units are relatively arranged on the outside of the web 410 of the existing bridge 40 along the transverse direction of the bridge; further, each of the prefabricated support units includes a plurality of prefabricated support structures 10 arranged at intervals along the longitudinal direction of the bridge to ensure widening along the longitudinal direction of the bridge. The range is consistent, and the multiple prefabricated supporting structures 10 are combined through the prefabricated panels 30, and the prefabricated panels 30 are not only used as templates during the construction process, but also can participate in the load as a part of the structure after the structural layer is poured, so as to realize permanent and temporary combination and greatly enhance the longitudinal and transverse bearing capacity of the structure; and the connecting components 20 are used to further improve the connection stability of the prefabricated supporting structure 10, so that the prefabricated supporting structure 10 can form a self-stabilizing structure through the connecting components 20 during the construction process, thereby reducing the temporary lifting and cross-operation time during construction.

[0052] Each of the prefabricated support structures 10 includes a prefabricated T-shaped rib 110, an inner lining plate 120 and a fastening connecting rod 130. The prefabricated T-shaped rib 110 is the main load-bearing connection widening structure. Its cross-sectional form adopts the T-shaped rib method. The T-shaped cross-section has the advantages of strong load-bearing capacity, light weight and easy construction. It is usually composed of a wing plate and a rib plate. The wing plate can be used for connection as a connection part, and the rib plate is used as the main load-bearing part; further, the prefabricated T-shaped rib 110 includes a web connecting rod The web connecting end 111 and the cantilevered widened end 112, the web connecting end 111 is used to connect with the existing bridge 40, so as to fix the entire prefabricated support structure 10 to the outer side of the web 410 of the existing bridge 40, and the cantilevered widened end 112 serves as the widened part of the entire widened structure. Preferably, in the present application, the height of the rib plate part of the prefabricated T-shaped rib 110 gradually decreases toward the cantilevered widened end 112 to reduce the deadweight of the cantilevered widened end 112. For details, please refer to the attached Figure 1 .

[0053] Preferably, the web connecting end 111 is connected to the web 410 by means of a fastening connecting rod 130. The fastening connecting rod 130 can be a connecting piece that is easy to construct and has high strength, such as a high-strength bolt. This connection method eliminates the construction process of a large number of embedded bars required for conventional reinforcement structures, and only requires a small number of screw holes to be pre-drilled on the web 410. This causes less disturbance to the existing structure (the web 410 of the existing bridge 40), and the construction process is simple and the construction quality is reliable. It should be noted that the inner lining plate 120 is used as an internal overlap during connection to match the connection stability of the high-strength bolts on the inside, avoid loosening during connection, and prevent one end of the high-strength bolt from directly contacting the web 410 during connection, thereby reducing damage to the web 410. It can also be used as an external reinforcement measure for the web 410 to increase the thickness of the web. Before the construction connection is carried out, a hole needs to be opened on the inner lining plate 120. There is a through hole corresponding to the screw hole, and a connecting hole 113 corresponding to the screw hole is opened at the web connecting end 111. The corresponding setting here means that the through hole, the screw hole and the connecting hole 113 have the same aperture and are coaxially arranged to facilitate the penetration of the fastening connecting rod 130. Opening it in advance can reduce the construction hoisting time and simplify the process; the cantilevered widened end 112 is connected to the flange end 420 of the existing bridge 40 through the connecting component 20, so that the entire prefabricated support structure 10 can maintain self-stability during the construction process after the connection, and the temporary hoisting time and the additional structural measures generated thereby are simultaneously reduced, and the construction process is further simplified; in this way, the web 410 of the existing bridge 40 is simultaneously reinforced while the flange is widened, thereby avoiding the structural safety problem caused by the substantial increase in the force on the web 410 due to the expansion.

[0054] A pre-positioning mechanism 140 is protruded upward on the cantilevered widened end 112, and the pre-positioning mechanism 140 has pre-positioning grooves 141 on both sides along the longitudinal direction of the bridge for positioning the precast panel 30 in the longitudinal and transverse directions of the bridge. The two ends of the precast panel 30 are respectively supported in the pre-positioning grooves 141 between two adjacent precast supporting structures 10.

[0055] In detail, the pre-positioning mechanism 140 is used to form a pre-positioning groove 141 for positioning the prefabricated panel 30 so that the prefabricated panel 30 can be overlapped. The pre-positioning groove 141 can also limit the prefabricated panel 30 in the transverse direction and the longitudinal direction to ensure the stable connection of the prefabricated panel 30. The pre-positioning groove 141 is relatively distributed on both sides of the pre-positioning mechanism 140 along the longitudinal direction, so that the pre-positioning grooves 141 between the two adjacent prefabricated support structures 10 can be combined with the spacing space to form a limiting installation for the installation of the prefabricated panel 30. The prefabricated panel 30 has a space for installation, and both ends of the prefabricated panel 30 are respectively set in the pre-positioning groove 141 between the two adjacent prefabricated supporting structures 10, so that the two adjacent prefabricated supporting structures 10 are connected as a whole, and participate in the force bearing together with the structure after the construction is completed, thereby strengthening the integrity of the structure; the flange force bearing mode of the existing bridge 40 can also be converted from cantilever beam force bearing to continuous beam force bearing, thereby increasing the bridge deck width and reducing the bending moment at the root of the flange, thereby improving the safety redundancy of the structure, and having a relatively broad application prospect.

[0056] As a preferred embodiment of the present invention, the pre-positioning mechanism 140 includes an outer protruding block 142, a shear mounting block 143 and a prefabricated anchor block 144, all of which are arranged on the cantilevered widened end 112; the outer protruding block 142 and the prefabricated anchor block 144 are respectively arranged at both ends of the shear mounting block 143 along the transverse direction of the bridge, and the prefabricated anchor block 144 is arranged away from the flange end 420 of the existing bridge 40; the outer protruding block 142 and the prefabricated anchor block 144 are both the same width as the prefabricated T-shaped rib 110, and the width of the shear mounting block 143 is smaller than the width of the prefabricated T-shaped rib 110, and the shear mounting block 143 is arranged in the middle of the prefabricated T-shaped rib 110, so that the outer protruding block 142, the shear mounting block 143 and the prefabricated anchor block 144 are surrounded by the pre-positioning groove 141.

[0057] It should be noted that the pre-positioning mechanism 140 includes an outer protruding block 142, a shear-resistant mounting block 143 and a prefabricated anchor block 144, all of which are arranged on the cantilever widened end 112. The outer protruding block 142 is used to abut against the flange end 420 of the existing bridge 40 to serve as the starting part of the cantilever widened end 112; and the shear-resistant mounting block 143 is used to arrange the shear steel bars 220 in advance to improve the shear resistance of the cantilever widened end 112 during subsequent construction and connection, and enhance the integrity. , which extends along the transverse direction of the bridge; the prefabricated anchor block 144 is used for anchoring the transverse prestressed steel bundle 210, thereby strengthening the connection between the cantilevered widened end 112 and the existing bridge 40. Therefore, in order to ensure that the entire cantilevered widened end 112 is subjected to uniform force, the prefabricated anchor block 144 needs to be arranged away from the flange end 420 of the existing bridge 40, so that the transverse prestressed steel bundle 210 passes through the entire cantilevered widened end 112 and maintains force after pouring the concrete of the structural layer 440.

[0058] Among them, the outer protruding block 142 and the prefabricated anchor block 144 are both the same width as the prefabricated T-shaped rib 110, so as to facilitate processing during prefabrication. Since the shear-resistant mounting block 143 is arranged between the outer protruding block 142 and the prefabricated anchor block 144, the width of the shear-resistant mounting block 143 is smaller than the width of the prefabricated T-shaped rib 110, so that the pre-positioning mechanism 140 formed by the three thereof is in an "I" shape arranged along the transverse bridge direction, and the grooves on both sides of the "I" shape are the pre-positioning grooves 141, that is, the outer protruding block 142, the shear-resistant mounting block 143 and the prefabricated anchor block 144 are surrounded to form the pre-positioning groove 141. For details, please refer to the attached Figure 3 .

[0059] It is worth mentioning that it is necessary to ensure that the side of the prefabricated panel 30 close to the existing bridge 40 is in contact with the flange end 420 of the existing bridge 40, and the prefabricated panel 30 can be arranged in the pre-positioning groove 141 on both sides along the bridge. Therefore, overlapping protrusions 310 can be respectively protruded outward at both ends of the prefabricated panel 30 along the bridge direction, so that a notch groove will be formed at the corner position of the prefabricated panel 30, so that when the prefabricated panel 30 is laid, the overlapping protrusion 310 of the prefabricated panel 30 is arranged in the pre-positioning groove 141 (that is, overlapped on the cantilevered widened end 112), and the notch groove of the prefabricated panel 30 is matched with the protruding block 142. For details, please refer to the attached Figure 2 .

[0060] As a preferred embodiment of the present invention, the web 410 of the existing bridge 40 is provided with a first shear key groove 411 and a second shear key groove 412 on both sides thereof, wherein a first shear key protrusion 121 corresponding to the first shear key groove 411 is formed outwardly on a side wall surface of the inner lining plate 120 close to the web 410, and the first shear key protrusion 121 is embedded in the first shear key groove 411;

[0061] A second shear key protrusion 114 corresponding to the second shear key groove 412 is formed on a side wall surface of the web connecting end 111 close to the web 410, and the second shear key protrusion 114 is embedded in the second shear key groove 412;

[0062] Structural adhesive is disposed between the first shear key groove 411 and the first shear key protrusion 121 , and between the second shear key groove 412 and the second shear key protrusion 114 .

[0063] It should be noted that the shear resistance of the interface can be improved by setting a shear key at the web 410. Therefore, considering that the inner lining plate 120 and the prefabricated T-shaped rib 110 are respectively arranged on the inner and outer sides of the web 410 of the existing bridge 40, a first shear key groove 411 and a second shear key groove 412 are respectively opened on the inner and outer sides of the web 410 of the existing bridge 40. At the same time, when prefabricating the inner lining plate 120, a first shear key protrusion 121 corresponding to the first shear key groove 411 is prefabricated outward on the side wall surface of the inner lining plate 120 close to the web 410, so that the first shear key protrusion 121 and the first shear key groove 411 are embedded in each other. When connected, an interface shear key is formed between the inner lining plate 120 and the web 410; and when prefabricating the prefabricated T-shaped rib 110, a second shear key protrusion 114 corresponding to the second shear key groove 412 is prefabricated outwardly on the side wall surface of the web connecting end 111 of the prefabricated T-shaped rib 110 close to the web 410, so that the second shear key protrusion 114 and the second shear key groove 412 are embedded and connected with each other to form an interface shear key between the web connecting end 111 and the web 410; it is worth mentioning that the corresponding embedded structural dimensions are consistent here, and are coaxially arranged, and the arrangement of structural adhesive can be used to enhance the connectivity between interfaces.

[0064] As a preferred embodiment of the present invention, the connection assembly 20 includes a transverse prestressed steel strand 210, and a prefabricated channel 1441 is provided in the prefabricated anchor block 144, wherein:

[0065] One end of the transverse prestressed steel bundle 210 extends into the flange end 420 connected to the existing bridge 40 , and the other end of the transverse prestressed steel bundle 210 extends along the transverse direction of the bridge toward the cantilevered widened end 112 and extends into the prefabricated channel 1441 fixed to the prefabricated anchor block 144 .

[0066] It is worth noting that the transverse prestressed steel bundle 210 is used as a connector between the cantilever widened end 112 and the existing bridge 40, and is used as a force-bearing system. One end of the transverse prestressed steel bundle 210 directly extends into the flange end 420 of the existing bridge 40 (that is, in the transverse prestressed arrangement strip of the existing bridge 40). In this way, while widening, the structural transverse prestressed system of the existing bridge 40 can be reshaped, greatly improving the transverse bearing capacity of the enhanced structure. The other end of the transverse prestressed steel bundle 210 extends into the prefabricated channel 1441 fixed to the prefabricated anchor block 144, and forms a self-stabilizing structure after tensioning, thereby reducing the time of cross-operation of hoisting during construction, and can solve the bearing capacity problems of the existing bridge 40 caused by expansion and defects such as rust of the transverse prestressed anchor head and loosening of the transverse prestressed steel bundle 210, thereby ensuring the safe operation of the structure and improving the service life of the structure.

[0067] As a preferred embodiment of the present invention, the connecting assembly 20 also includes a plurality of shear steel bars 220 arranged at intervals along the transverse direction of the bridge, the bottom of the shear steel bars 220 is embedded in the shear mounting block 143, and the top of the shear steel bars 220 extends upward from the bottom to form a closed loop.

[0068] It is worth noting that the shear steel bars 220 are used to improve the structural shear strength at the cantilever widened end 112. They are arranged in advance in the shear mounting block 143, that is, when the prefabricated T-shaped rib 110 is prefabricated, the bottom of the shear steel bars 220 is embedded in the shear mounting block 143. In this way, after the entire prefabricated mounting structure is assembled and the structural layer 440 concrete is cast in place, they can participate in the force at the same time, thereby improving the integrity of the structure, and the closed loop setting can enhance the torsion and shear resistance.

[0069] Furthermore, the web 410 of the existing bridge 40 is an inclined web, and the web connecting end 111 of the prefabricated T-shaped rib 110 is matched with the web 410 and is arranged in an inclined shape.

[0070] It should be noted that in bridges with a larger deck width, a box girder form with a large cantilever inclined web is usually adopted. Different from a straight web, if the traditional widening structure is directly constructed, the entire construction process is more troublesome and the structural structure of the inclined web is greatly damaged. Therefore, the present application adopts a high-strength bolt connection form for the inclined web, which reduces the disturbance to the existing structure while simultaneously reinforcing the web 410. To facilitate construction and connection, the web connection end 111 of the prefabricated T-shaped rib 110 is also arranged to match the web 410 and is arranged in an inclined shape so that it can be flatly attached to the outside of the web 410 during connection. It is worth mentioning that the present application can also be applied to a box girder form with a straight web. At this time, the web connection end 111 of the prefabricated T-shaped rib 110 can be matched with the straight web and arranged to be vertically extended.

[0071] Furthermore, the connection assembly 20 also includes a plurality of transverse structural steel bars 230 arranged at intervals along the longitudinal direction of the bridge, one end of the transverse structural steel bar 230 is overlapped with the existing steel bar 431 of the flange end 420 of the existing bridge 40, and the other end of the transverse structural steel bar 230 extends outward along the transverse direction of the bridge and is cantilevered.

[0072] It should be understood that the transverse structural reinforcement 230 is used to improve the structural strength of the entire widened portion. It is connected to the existing reinforcement 431 at the flange end 420 of the existing bridge 40 and then connected as a whole after concrete pouring. The overlap of the transverse structural reinforcement 230 and the existing reinforcement 431 at the flange end 420 has a simple process, fast construction speed, and low requirements for construction accuracy.

[0073] The present application also provides a construction method for a bridge deck widening structure applicable to an existing bridge 40 structure, which is applied to the bridge deck widening structure applicable to the existing bridge 40 structure as described above, and specifically comprises the steps of:

[0074] S1, pre-treating the existing bridge 40 so that the load-bearing components 430 of the existing bridge 40 are exposed to form a bridge to be repaired; wherein the load-bearing components 430 include transverse prestressed arrangement strips (not shown) and existing steel bars 431 at the flange end 420 of the existing bridge 40; it should be understood that before widening, the structure of the existing bridge 40 needs to be pre-treated, including chiseling, excavation, etc., that is, chiseling the bridge deck pavement of the existing bridge 40, the concrete of the flange end 420, etc., so as to chisel out and expose the load-bearing components 430 in the original structure of the existing bridge 40, wherein the load-bearing components 430 include transverse prestressed arrangement strips and the existing bridge The existing steel bars 431 at the flange end 420 of the existing bridge 40, the transverse prestressed arrangement strip is used for arranging the transverse prestressed steel bundle 210 of the widened structure (prefabricated support structure 10), and the existing steel bars 431 at the flange end 420 of the existing bridge 40 are used for overlapping the transverse structural steel bars 230 of the widened structure (prefabricated support structure 10), so that the structure of the existing bridge 40 and the prefabricated support structure 10 are connected as a whole after pouring, and the steel bars and prestressed steel bundles improve the structural strength and bearing capacity; wherein, the width of the concrete of the flange end 420 of the existing bridge 40 is in the range of 20cm~30cm, which allows the existing steel bars 431 at the flange end 420 of the existing bridge 40 to leak out.

[0075] S2, installing a prefabricated support structure 10 on the bridge to be repaired, pre-assembling the prefabricated support structure 10 on the bridge to be repaired and making it have self-stabilizing ability to form a blank beam to be widened, and multiple prefabricated support structures 10 are arranged at intervals on the lateral side of the bridge to be repaired along the longitudinal direction of the bridge; wherein, the first end of each of the prefabricated support structures 10 is fixedly connected to one side of the bridge to be repaired, and the second end of the prefabricated support structure 10 extends outward from the first end along the transverse direction of the bridge and is cantilevered; it should be noted that the prefabricated support structure 10 is used to widen the support beam body, and can be processed in advance by prefabrication, and then installed by hoisting during construction. During assembly, it can form a self-stabilizing structure by partially tensioning the transverse prestressed steel bundle 210, which can reduce the time of cross-operation of hoisting, and at the same time reduce the additional structural measures required for hoisting, thereby simplifying the construction process.

[0076] S3, hoisting the prefabricated panels 30 onto the blank beam to be widened and pre-positioning them, the prefabricated panels 30 are arranged in the pre-positioning grooves 141 between two adjacent prefabricated support structures 10, and a plurality of the prefabricated panels 30 are combined on the prefabricated support structures 10 to form an integral widened blank;

[0077] S4, pouring a lightweight aggregate UHPC structural layer 440 on the widened blank to form a widened bridge; it is worth noting that the pre-positioning groove 141 between the two adjacent prefabricated support structures 10 can pre-position the prefabricated panel 30, that is, the two adjacent prefabricated support structures 10 are used as positioning constraints to ensure that the installation limit of the prefabricated panel 30 is accurate, and the arranged prefabricated panels 30 also connect the prefabricated support structures 10 arranged at intervals along the bridge direction as a whole, thereby enhancing the structural integrity, thereby forming an overall widened blank, so that after the lightweight aggregate UHPC structural layer 440 is finally poured, they can also be stressed together, and because of the relationship of being connected as a whole, the stress mode of the flange of the existing bridge 40 can also be converted from a cantilever beam to an equivalent continuous beam stress, while increasing the bridge deck width, reducing the bending moment at the root of the flange, and improving the safety redundancy of the structure.

[0078] Furthermore, the step S2 specifically includes the steps of:

[0079] S21, processing the web 410 of the existing bridge 40, so that the two sides of the web 410 are respectively provided with a first shear key groove 411 and a second shear key groove 412, and the web 410 is provided with a screw hole; wherein, the screw hole is arranged to penetrate along the width direction of the web 410; it can be understood that the screw hole (not shown in the figure) can be opened in the target position in advance, so as to facilitate direct penetration and installation during subsequent lifting; wherein, too many screw holes will lead to a decrease in the structural strength of the web 410, while too few screw holes may lead to unstable strength when the widened structure is connected. Therefore, in the present application as a preferred embodiment, the number of the screw holes can be set to six, specifically three groups, each group of the screw holes includes two screw holes arranged relatively along the width direction of the web 410, and the three groups of the screw holes are arranged at intervals along the extension direction of the web 410. For details, please refer to the attached Figure 6 Similarly, the first shear key groove 411 and the second shear key groove 412 can also be preset in the target position in advance to reduce on-site construction time.

[0080] It is worth mentioning that before lifting and assembling, the inner and outer interfaces of the web 410 need to be roughened. The roughening treatment can improve the adhesion between the interfaces and increase the degree of connection and fit. After the roughening treatment, structural adhesive can also be applied between the inner lining plate 120 and the web 410, and between the prefabricated T-shaped rib 110 and the web 410. The structural adhesive can be used to increase the adhesion between the interfaces to further improve the connection firmness. In a preferred embodiment, 2mm~3mm of structural adhesive is applied, and technical personnel in this field can choose according to actual needs.

[0081] S22, hoisting the inner lining plate 120 and the prefabricated T-shaped rib 110 to the target installation position respectively; wherein the existing bridge 40 is a box girder, the inner lining plate 120 is located in the box chamber inside the web 410, and the prefabricated T-shaped rib 110 is located outside the web 410;

[0082] S23, by tightening the connecting rod 130, it passes through the through hole, the screw hole, the connecting hole 113 in sequence and extends into the web connecting end 111 of the prefabricated T-shaped rib 110, so as to fix the inner lining plate 120, the web 410 and the web connecting end 111 of the prefabricated T-shaped rib 110 in sequence, and the first shear key protrusion 121 is correspondingly clamped in the first shear key groove 411, and the second shear key protrusion 114 is correspondingly clamped in the second shear key groove 412; it should be noted that before installation, the components to be installed (inner lining plate 120, prefabricated T-shaped rib 110) are hoisted to their respective layout positions in advance by using a car crane or other means. For example, the inner lining plate 120 is located in the box chamber inside the web 410, and the prefabricated T-shaped rib 110 is located outside the web 410. Since the through holes, screw holes, and connecting holes 113 have been arranged in advance Well, at this time, it is only necessary to clamp the inner lining plate 120 and the prefabricated T-shaped rib 110 on both sides of the web 410 by tightening the connecting rod 130 (high-strength bolt). After assembly, the interface between the inner lining plate 120 and the web 410 fits together, and the first shear key protrusion 121 is correspondingly clamped in the first shear key groove 411 to form an inner shear key, and the web connecting end 111 of the prefabricated T-shaped rib 110 is also fitted with the interface of the web 410, and the second shear key protrusion 114 is correspondingly clamped in the second shear key groove 412 to form an outer shear key; in this way, the entire lifting process and installation process only need to pre-drill a small number of screw holes on the web 410, which has less disturbance to the existing structure and the construction process is relatively simple. It combines the advantage that most components can be prefabricated in the factory, which greatly improves the convenience and economy of construction.

[0083] S24, install the transverse prestressed steel bundle 210 in the transverse prestressed arrangement strip, and anchor one end of the transverse prestressed steel bundle 210 in the prefabricated channel 1441 of the prefabricated anchor block 144, and tension the transverse prestressed steel bundle 210 once, so that the prefabricated T-shaped rib 110 forms a self-stabilizing structure; it is worth noting that through the partial tensioning of the transverse prestress, the structure can have a self-stabilizing ability, reducing the temporary lifting time, so as to realize the widening of the bridge deck of the existing bridge 40, and at the same time, the existing transverse prestressed system of the existing bridge 40 can be reshaped, thereby greatly improving and enhancing the lateral bearing capacity of the structure.

[0084] S25, repeat steps S21~S24 to arrange multiple prefabricated support structures 10 at intervals along the direction of the bridge to form the blank beam to be widened with self-stabilizing ability; it can be understood that after assembling one prefabricated support structure 10, the next prefabricated support structure 10 can be assembled at a preset distance along the direction of the bridge, and after multiple prefabricated support structures 10 are assembled, the blank beam to be widened with self-stabilizing ability is formed, so as to facilitate the next step of lifting the prefabricated panel 30; in a preferred embodiment, the preset distance between the prefabricated support structures 10 along the direction of the bridge can be 300cm~400cm, and technical personnel in this field can choose according to actual needs.

[0085] Furthermore, the step S3 further includes the following steps:

[0086] S31, using the precast panel 30 as a template to lay transverse structural steel bars 230, and overlapping one end of the transverse structural steel bars 230 with the existing steel bars 431 of the flange end 420 of the existing bridge 40; it should be noted that the precast panel 30 can not only connect the spaced precast supporting structures 10 as a whole, but also be used as a template during the construction process. After the construction is completed, it participates in the force together with the structure to achieve permanent and temporary combination and template-free construction, thereby simplifying the construction process, speeding up the construction progress, and reducing the project cost; wherein, when overlapping, the overlap length usually needs to be ≥10d, where d refers to the diameter of the steel bar.

[0087] S32, using the precast panel 30 as a template to cast a lightweight aggregate UHPC structural layer 440 on the widened preform;

[0088] S33, performing secondary tensioning on the transverse prestressed steel tendons 210 to tension them to the designed tensioning control stress.

[0089] It can be understood that by pouring the lightweight aggregate UHPC structural layer 440 to achieve effective connection between all structures, they are connected together to bear the force, which greatly improves the longitudinal and lateral bearing capacity of the existing structure. During the pouring, the precast panels 30 that have been laid out can be used as templates for pouring, which simplifies the construction process, speeds up the construction progress, and realizes formwork-free construction. The transverse prestressed steel strands 210 can only increase the lateral bearing capacity of the entire main beam after secondary tensioning.

[0090] It is worth mentioning that the main structures in this application can be prefabricated in the factory, so it takes up less time on site, which improves the convenience and economy of construction, is more conducive to the control of construction quality, and has broad application prospects.

[0091] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A bridge deck widening structure applicable to an existing bridge structure, characterized in that: The invention comprises an existing bridge, a prefabricated plate, a connection assembly and two prefabricated support units arranged on the outer side of the web of the existing bridge in a transverse direction to each other, each of the prefabricated support units comprising a plurality of prefabricated support structures arranged at intervals in the longitudinal direction of the bridge; wherein: Each of the prefabricated supporting structures includes a prefabricated T-shaped rib, an inner lining plate and a fastening connecting rod, wherein the prefabricated T-shaped rib includes a web connecting end and a cantilevered widened end, wherein a plurality of screw holes arranged at intervals along its own extension direction are reserved on the web of the existing bridge, a through hole corresponding to the screw hole is provided on the inner lining plate, and a connecting hole corresponding to the screw hole is provided on the web connecting end, and the fastening connecting rod passes through the through hole, the screw hole and the connecting hole in sequence and extends into the web connecting end to fix the inner lining plate, the web of the existing bridge and the web connecting end to each other; the cantilevered widened end is connected to the flange end of the existing bridge through the connecting assembly to form a self-stabilizing structure; interface shear keys are formed between the inner lining plate and the web, and between the web connecting end and the web; A pre-positioning mechanism is formed on the cantilevered widened end, and the pre-positioning mechanism has pre-positioning grooves on both sides along the longitudinal direction of the bridge for positioning the prefabricated plate in the longitudinal direction and the transverse direction of the bridge. The two ends of the prefabricated plate are respectively supported in the pre-positioning grooves between two adjacent prefabricated support structures; The pre-positioning mechanism comprises an outwardly protruding block, a shearing mounting block and a prefabricated anchor block, all of which are arranged on the cantilevered widened end. The outwardly protruding block and the prefabricated anchor block are respectively arranged at both ends of the shearing mounting block along the transverse direction of the bridge, and the prefabricated anchor block is arranged away from the flange end of the existing bridge. The outwardly protruding block is used to abut against the flange end of the existing bridge to serve as the starting part of the cantilevered widened end. The outer convex block and the prefabricated anchor block are both the same width as the prefabricated T-shaped rib, and the width of the shear mounting block is smaller than the width of the prefabricated T-shaped rib. The shear mounting block is arranged in the middle of the prefabricated T-shaped rib, so that the outer convex block, the shear mounting block and the prefabricated anchor block are surrounded to form the pre-positioning groove; The connection assembly includes a plurality of shear steel bars spaced apart in the transverse direction of the bridge, the bottom of the shear steel bars is embedded in the shear mounting block, and the top of the shear steel bars extends upward from the bottom to form a closed loop.

2. The bridge deck widening structure applicable to an existing bridge structure according to claim 1, characterized in that: The web of the existing bridge is provided with a first shear key groove and a second shear key groove on both inner and outer sides, respectively, wherein a first shear key protrusion corresponding to the first shear key groove is formed outwardly on a side wall surface of the inner lining plate close to the web, and the first shear key protrusion is embedded in the first shear key groove; A second shear key protrusion corresponding to the second shear key groove is formed outwardly on a side wall surface of the web connecting end close to the web, and the second shear key protrusion is embedded in the second shear key groove; Structural adhesive is provided between the first shear key groove and the first shear key protrusion, and between the second shear key groove and the second shear key protrusion.

3. The bridge deck widening structure applicable to an existing bridge structure according to claim 1, characterized in that: The connection assembly includes a transverse prestressed steel strand, and a prefabricated channel is opened in the prefabricated anchor block, wherein: One end of the transverse prestressed steel bundle extends into the flange end connected to the existing bridge, and the other end of the transverse prestressed steel bundle extends along the transverse direction of the bridge toward the cantilevered widened end and extends into the prefabricated channel fixed to the prefabricated anchor block.

4. The bridge deck widening structure applicable to an existing bridge structure according to claim 1, characterized in that: The web of the existing bridge is an inclined web, and the web connecting end of the prefabricated T-shaped rib is arranged to match the web and be inclined.

5. The bridge deck widening structure applicable to an existing bridge structure according to claim 1, characterized in that: The connection assembly also includes a plurality of transverse structural steel bars arranged at intervals along the longitudinal direction of the bridge, one end of the transverse structural steel bar overlaps the existing steel bar at the flange end of the existing bridge, and the other end of the transverse structural steel bar extends outward along the transverse direction of the bridge and is cantilevered.

6. A construction method for a bridge deck widening structure applicable to an existing bridge structure, applied to the bridge deck widening structure applicable to an existing bridge structure as claimed in any one of claims 1 to 5, characterized in that: The specific steps include: S1, pre-treating an existing bridge so that the load-bearing components of the existing bridge are exposed to form a bridge to be repaired; wherein the load-bearing components include transverse prestressed arrangement strips and existing steel bars at the flange ends of the existing bridge; S2, installing a prefabricated support structure on the bridge to be repaired, pre-assembling the prefabricated support structure on the bridge to be repaired and making it self-stabilizing to form a blank beam to be widened, and a plurality of the prefabricated support structures are arranged at intervals on the lateral side of the bridge to be repaired along the longitudinal direction of the bridge; wherein the first end of each of the prefabricated support structures is fixedly connected to one side of the bridge to be repaired, and the second end of the prefabricated support structure extends outward from the first end along the transverse direction of the bridge and is cantilevered; S3, hoisting the prefabricated panels onto the blank beam to be widened and pre-positioning them, the prefabricated panels are arranged in the pre-positioning grooves between two adjacent prefabricated support structures, and a plurality of the prefabricated panels are combined on the prefabricated support structures to form an integral widened blank; S4, pouring a lightweight aggregate UHPC structural layer on the widened preform and the existing bridge deck structural layer to form a widened bridge.

7. The construction method for widening the bridge deck of an existing bridge structure according to claim 6, characterized in that: The step S2 specifically includes the following steps: S21, processing the web of the existing bridge so that a first shear key groove and a second shear key groove are respectively opened on both sides of the web, and screw holes are opened on the web; wherein the screw holes are arranged through the width direction of the web, and structural adhesive is applied to the first shear key groove and the second shear key groove; S22, hoisting the inner lining plate and the prefabricated T-shaped rib to the target installation position respectively; wherein the existing bridge is a box girder, the inner lining plate is located in the box chamber inside the web, and the prefabricated T-shaped rib is located outside the web; S23, by tightening the connecting rod, sequentially passing through the through hole, the screw hole, the connecting hole and extending into the web connecting end of the prefabricated T-shaped rib, so as to sequentially fix the inner lining plate, the web and the web connecting end of the prefabricated T-shaped rib, and the first shear key protrusion of the inner lining plate is correspondingly clamped in the first shear key groove, and the second shear key protrusion of the web connecting end is correspondingly clamped in the second shear key groove; S24, installing a transverse prestressed steel bundle in the transverse prestressed arrangement strip, anchoring one end of the transverse prestressed steel bundle in a prefabricated hole of a prefabricated anchor block, and tensioning the transverse prestressed steel bundle once, so that the prefabricated T-shaped rib forms a self-stabilizing structure; S25, repeating steps S21 to S24 to arrange a plurality of the prefabricated support structures at intervals along the longitudinal direction of the bridge to form the blank beam to be widened with self-stabilizing capability.

8. The construction method for widening the bridge deck of an existing bridge structure according to claim 6, characterized in that: The step S3 further includes the following steps: S31, laying transverse structural steel bars using the prefabricated plate as a template, and overlapping one end of the transverse structural steel bars with the existing steel bars at the flange end of the existing bridge; S32, using the precast panel as a template to cast a lightweight aggregate UHPC structural layer on the widened preform; S33, the transverse prestressed steel tendons are tensioned twice to the designed tension control stress.

Citation Information

Patent Citations

  • Steel cantilever combined bridge deck slab widening and reconstruction structure and construction method thereof

    CN106436591A

  • I-beam bridge deck slab construction method

    CN107217601A

  • Ultra-wide triangular truss type flange splicing concrete box girder and construction method thereof

    CN109930468A

  • Assembled-type dense rib beam floor system combination template and construction method

    CN110374321A

  • Steel reinforced concrete floor system and construction method thereof

    CN114351927A