A method for optimizing the operation of distribution stations taking train load scheduling into account
Through the African wild dog algorithm, the operation of trains is optimized, combined with the power grid power supply and energy storage power supply mode, the problems of train operation cost regulation and electricity price differences are solved, and the reduction of train operation costs and the economic improvement of distribution stations are achieved.
Patent Information
- Application Number
- CN202410480911.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-22
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-04-22
AI Technical Summary
The existing technology lacks macro-control of train operating costs, and the electricity price differences in different periods under the conditions of the power market have not been effectively utilized, resulting in the economic regulation potential of the optimized operation of power distribution stations being not fully tapped.
Adopt the power grid power supply and energy storage power supply mode, optimize the operating costs of trains through the African wild dog algorithm, consider the power traction and electricity price issues under the conditions of the power market, use the energy storage device to recover braking energy consumption, and combine the transformer loss to perform reasonable scheduling to optimize Trains run at a speed to reduce costs.
It has achieved the reduction of train operating costs, improved the economy and computing power utilization of power distribution stations, and reduced transformer losses and information load transfer costs through real-time data processing and electricity price scheduling.
Smart Images

Figure CN118554460B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of intelligent control, and in particular relates to a distribution station optimization operation method taking train load scheduling into consideration. Background Art
[0002] With the rapid economic development, the urban population is increasing, the urbanization process is accelerating, the traffic is becoming increasingly congested, and the global energy consumption is also increasing. Trains have the characteristics of large transportation volume, high environmental friendliness, high density, punctuality, comfort, safety and reliability. The existing technology lacks macro-control of its computing power. Reasonable use of its computing power can greatly reduce the operating costs of trains and substations; secondly, under the conditions of the power market, there are large differences in electricity prices at different times, and reasonable power load distribution control is rarely considered. The economic control potential for optimizing the operation of substations is huge. Summary of the invention
[0003] The present invention considers that the power source of the distribution station is mainly the power supply of the power grid, supplemented by the energy storage power supply mode. The main research idea is: under normal operating conditions, the train load shows obvious intermittent and regularity, and the train operation cost is strongly related to the power market price in the time dimension. This patent decouples the train operation cost from the market price, and optimizes the train operation on the premise of first ensuring the energy consumption of the traction train, so as to reduce the train operation cost. The optimization operation strategy considers the following factors: 1. Power traction and electricity price issues in different periods under power market conditions. 2. For the information load detected during the operation of the train, the information load is transferred, and the distribution station processes the detection data. While the train arrives on time, the optimal operating speed curve is fed back to the train considering the delay constraint and the market electricity price. 3. For the braking energy consumption of the train, the energy storage device is used for recovery, and the market electricity price and the segmented characteristics of the target site are considered to reasonably dispatch the energy storage power. 4. While optimizing the train operation, the loss of the contact network power supply transformer is considered, and the cost of the train-distribution station is reduced from the two aspects of the train operation status and transformer loss.
[0004] The technical solution of the present invention is:
[0005] A method for optimizing the operation of a power distribution station taking into account train load scheduling comprises the following steps:
[0006] S1. Taking the lowest train operation cost as the objective function, the train load operation is optimized, which is composed of train operation cost, information load transfer cost, various loss costs, etc. The specific objective function is expressed as follows:
[0007] MinZ=f1+f2+f3
[0008] f3=f 3,1 +f 3,2
[0009] Where Z is the total system operation cost; the size of Z is determined by the transformer, line loss, train operation and distribution center, f1 is the energy cost of all trains, f2 is the server operation cost, and f 3,1 represents the loss cost of transformer operation, f 3,2 Indicates the loss cost of line operation;
[0010] S2. The improved African wild dog algorithm is used to optimize the objective function in all aspects; each individual in f1, f2, and f3 represents a wild dog operator, and the population size of wild dogs is determined by the actual operating system. An adaptive decreasing energy control factor E1 is added to the three iterative behaviors of siege, pursuit, and scavenging. The expression is as follows:
[0011]
[0012] Where m and n are constraint parameters, T is the upper limit of iteration, and r is the number of iterations.
[0013] Preferably, in step S1, the total energy consumption of train i during operation is f1 i , expressed as follows:
[0014]
[0015]
[0016]
[0017] Where: f1 is the energy cost of all trains, C1 represents the train set, is the electricity price at the tth moment of train i’s operation, is the power consumption of train i at the tth moment, is the electricity price for charging energy storage with regenerative braking energy at time t during the operation of train i, E is the power released by the energy storage device at the tth moment during the operation of train i; reg,i,t represents the braking energy consumption of the i-th train at time t; ξ is the energy recovery efficiency; M is the train mass; ν t is the train speed at time t; β is the braking system efficiency during the braking process.
[0018] Preferably, in step S1, the server energy consumption is regulated by adjusting the number of working servers, and the server power consumption model is as follows:
[0019] P 2,t =P w n t +P h (N t )
[0020] Where, P 2,t is the total energy consumption of the server at time t, P w is the power consumption of the working server, P h is the energy consumption of dormant servers, N is the total number of servers, n t is the number of working servers at time t;
[0021] After the server energy consumption model is established, the server operating cost can be obtained:
[0022]
[0023] Where f2 is the server operation cost.
[0024] Preferably, in step S1, the transformer operation loss cost is calculated by function f 3,1 It is represented as follows:
[0025]
[0026] When the rated current I1 on the high-voltage side flows through the double-winding transformer, the rated load loss generated in the time period t is P 3,t , assuming the equivalent resistance of the transformer is r T , satisfying the following relationship:
[0027]
[0028] Preferably, in step S1, within time period t, the line operation loss cost is calculated using function f 3,2 It is represented as follows:
[0029]
[0030] During the period t, the line operation power loss is expressed by function P 4,t It is represented as follows:
[0031]
[0032] I ab,t represents the current of the branch of the distribution station (ab) during the period t. By controlling the running status of the train cluster, the line loss is controlled. ab represents the resistance of the branch, and C2 represents the branch set of the distribution substation.
[0033] Preferably, in step S1, the power supply for daily operation of the power distribution station comes from the power grid and the energy storage device, and the energy balance equation of the power distribution station is constrained as follows:
[0034]
[0035] Pg,i,t ≤P max (17)
[0036]
[0037] Where, P g,i,t is the exchange power between distribution station i and the grid at time t, P max is the maximum exchange power between the distribution station and the power grid, is the maximum discharge power of the energy storage device at time t;
[0038] Data processing delay constraints:
[0039]
[0040] Where: i,t is the total amount of data tasks arriving at data center i at time t; μ is the service rate of the working server for data tasks; T Φ Delay bound for data processing;
[0041] The speed climbing constraints under the train acceleration state are as follows:
[0042] V up t+1,min <V t <V up t+1,max (20)
[0043] Where V t is the train speed at time t; V up t-1,min 、V up t-1,max They are the minimum and maximum running speeds of the train at the next moment respectively;
[0044] Train speed braking constraints:
[0045] When arriving at the target station or encountering an emergency, the train will actively brake to reduce its running speed. The speed constraints when the train brakes are as follows:
[0046] V down t-1,min <V t <V down t+1,max (twenty one)
[0047] Where V down t-1,min 、V down t-1,maxare the minimum and maximum running speeds at the next moment when the train brakes. Preferably, in step S2, the improved African wild dog algorithm is used to comprehensively optimize the objective function, and each individual in f1, f2, and f3 is sequentially encoded. represents the i-th individual in the d-dimensional space in the encoding, that is, the position of the i-th wild dog in the d-dimensional space,
[0048] Mobbing behavior:
[0049]
[0050] In the formula, represents the new position of the i-th wild dog in the d-dimensional space; Ψ is a uniform random number in [-2,2]; represents the optimal position of the i-th wild dog in d-dimensional space;
[0051]
[0052] In the formula, Λ represents the number of wild dogs, represents the position of the kth wild dog in d-dimensional space, f i d Represents the position of the i-th wild dog in d-dimensional space.
[0053] Preferably, in step S2, the pursuit behavior:
[0054]
[0055] In the formula, c is a uniform random number in [-1,1]; is a random individual in the wild dog population, j≠i.
[0056] Preferably, in step S2, the scavenging behavior is:
[0057]
[0058] Survival Behavior:
[0059] The three behaviors of the population, namely, siege, hunting, and scavenging, will eventually be screened and eliminated through survival behavior. The survival probability of the three behaviors in the i-th iteration is sr i for:
[0060]
[0061]
[0062]
[0063] In the formula, are two random individuals in the population, represents the updated position after the adaptive decreasing energy control factor is adopted; best(F(X)) is the set of population solutions with the highest fitness, F(X i ) is the i-th group of population solutions, worst(F(X)) is the group of population solutions with the lowest fitness, and ε represents the allowable error range.
[0064] Compared with the prior art, the present invention has the following beneficial effects:
[0065] This patent starts with information load, considers the real-time data detected during train operation, and calculates the most suitable speed curve for train operation. Train operation has strict time and mileage constraints. Using only the train's internal computer to process the detection data will inevitably lead to delays, making the train operation cost less than optimal. This patent innovatively proposes an optimized operation strategy for collaborative distribution stations, using the powerful computing power of distribution stations to process complex train information and complete information scheduling between trains and distribution stations.
[0066] The overhead line is powered by a distribution station, which uses real-time electricity prices for billing. The cost of electricity will vary slightly depending on the time when the train uses electricity. Taking into account the train operation plan and energy consumption, the detection data is integrated to ensure that the train arrives at the station on time. At the same time, the distribution station calculates the optimal operating speed of the train. The operating loss of the transformer is modeled, and the objective function is to minimize the train load-distribution station operating cost, and the optimal scheduling strategy between the two is sought. While planning the train speed, the transformer loss that supplies power to the train is taken into account, and changes in the train's operating status will also affect the transformer loss. The train load is a load with a higher execution priority, but there is still some load that can be reduced in terms of the train's operating status and transformer loss. This patent combines market electricity prices, comprehensively considers both the train and the distribution station, and uniformly dispatches the entire system to further reduce operating costs and improve the economy of the system.
[0067] The braking loss during the operation of the train can be recovered through the energy storage device. This article considers 90% of the average braking energy consumption of the train as the maximum capacity of the energy storage device, aiming to maximize the recovery of braking energy consumption. After the storage device stores a certain amount of electrical energy, it chooses to supply power to the train when the electricity price is high according to the real-time electricity price and operation plan, so as to further reduce the operating cost of the train-distribution station. This patent focuses on the macro and micro states of the train operation, reasonably controls the transfer of the train's information load, and improves the computing power utilization of the distribution station by transferring the information load.
[0068] In terms of algorithms, improvements are made to the algorithm search speed and convergence accuracy. The patented algorithm uses a staged attenuation algorithm to solve the target, increases the algorithm search area in the early stage of iteration, ensures the diversity of the population, and improves the convergence speed; and improves the search accuracy in the later stage of iteration to ensure the convergence accuracy of the algorithm. BRIEF DESCRIPTION OF THE DRAWINGS
[0069] Figure 1 This is a simplified diagram of the train operation curve and energy consumption.
[0070] Figure 2 The graph shows the relationship between two energy consumption and speed for the same distance.
[0071] Figure 3 This is the algorithm flow chart.
[0072] Figure 4 Overall system block diagram. DETAILED DESCRIPTION
[0073] The present invention is described in detail below in conjunction with specific embodiments. The following embodiments will help those skilled in the art to further understand the present invention, but are not intended to limit the present invention in any form. It should be noted that, for those of ordinary skill in the art, several changes and improvements can also be made without departing from the concept of the present invention. These all belong to the protection scope of the present invention.
[0074] A method for optimizing the operation of a power distribution station taking into account train load scheduling comprises the following steps:
[0075] S1. Taking the lowest train operation cost as the objective function, the train load operation is optimized, which is composed of train operation cost, information load transfer cost, various loss costs, etc. The specific objective function is expressed as follows:
[0076] MinZ=f1+f2+f3
[0077] f3=f 3,1 +f 3,2
[0078] Where Z is the total system operation cost; the size of Z is determined by the transformer, line loss, train operation and distribution center, f1 is the energy cost of all trains, f2 is the server operation cost, and f 3,1 represents the loss cost of transformer operation, f 3,2 Indicates the loss cost of line operation;
[0079] S2. The improved African wild dog algorithm is used to optimize the objective function in all aspects; each individual in f1, f2, and f3 represents a wild dog operator, and the population size of wild dogs is determined by the actual operating system. An adaptive decreasing energy control factor E1 is added to the three iterative behaviors of siege, pursuit, and scavenging. The expression is as follows:
[0080]
[0081] Where m and n are constraint parameters, T is the upper limit of iteration, and r is the number of iterations.
[0082] (1) Train-distribution station optimization operation strategy
[0083] ① Train operation cost modeling
[0084] In this patent, the traction train load mainly considers the power load and air-conditioning load in the train. The train power load is mainly used for traction of the train. In order to ensure safe and reliable operation, the train regenerative braking optimization energy consumption technology involving the distribution station energy storage is considered; the train air-conditioning load is mainly used for the indoor ambient temperature, and its energy consumption will also be optimized and regulated.
[0085] The total energy consumption of train i during operation is f1 i , expressed as follows:
[0086]
[0087] Where: f1 is the energy cost of all trains, C1 represents the train set, is the electricity price at the tth moment of train i’s operation, is the power consumption of train i at the tth moment, is the electricity price for charging energy storage with regenerative braking energy at time t during the operation of train i, It is the power released by the energy storage device at the tth moment during the operation of train i.
[0088] ②Train dynamic load modeling
[0089] The energy required by the train during operation is mainly provided by the power supply network, and the train energy consumption can be calculated as shown in formula (2).
[0090] E i,t =E z,i,t +E aux,i,t -E reg,i,t (2)
[0091] Where: E i,t is the total energy consumption of the i-th train at time t; E z,t,i is the traction energy consumption of the i-th train at time t; E aux,i,t is the auxiliary energy consumption of the i-th train at time t; E reg,i,t is the braking energy consumption of the i-th train at time t.
[0092] The general train operation trajectory can be simplified into three stages. The train operation curve and energy consumption diagram are as follows: Figure 1 Stage 1: The train starts the traction stage, starting from rest and accelerating to the highest speed with maximum capacity. The traction energy consumption in this stage is E t1 ; Stage 2, the train is running at a constant speed. In this process, the traction force is equal to the train resistance to keep the train running at a constant speed. The traction energy consumption in this stage is E t2; Stage 3, the train braking and deceleration stage, gradually decelerating from the running speed until it stops. The feedback energy in this stage is E reg ; Auxiliary energy consumption E during the entire operation process aux Always existed.
[0093] Among them, the train braking power is higher than the traction power, but the braking feedback efficiency is lower than the traction power. Therefore, the train consumes energy during traction and feeds back energy during braking. The train potential energy change is not considered, and it is considered from the perspective of the kinetic energy of the whole vehicle. t1 With E reg The traction energy consumption and braking can be calculated according to the kinematic formula, which is as follows:
[0094]
[0095]
[0096]
[0097] Where: M is the mass of the train; v is the speed of the train; a, β are the traction efficiency and braking efficiency of the traction and braking processes.
[0098] During constant speed operation, the higher the constant speed of the train, the greater the power consumption of overcoming resistance, the shorter the running time, and the smaller the auxiliary energy consumption. Conversely, the lower the running speed, the smaller the power consumption of overcoming resistance, the longer the running time, and the greater the auxiliary energy consumption. Therefore, if the energy offset of the two stages of starting traction and braking deceleration is considered, the power here is not specific to a certain train, and only the train running loss formula is used to derive the train running energy consumption relationship. The total train running energy consumption is:
[0099]
[0100] Where E is the train running energy consumption, and traction energy consumption E t2 It is mainly to overcome the resistance and do work. From the above information, we can know that when the length of the train running section is constant, the energy consumption of overcoming the resistance is E. res It is related to the train speed level v. The higher the running speed, the greater the running resistance, the greater the traction required, and the higher the energy consumption. Train auxiliary energy consumption E aux It is related to the train running time. When the length of the train running section is constant, the higher the running speed v, the shorter the running time t, and the lower the auxiliary energy consumption; the lower the running speed v, the longer the running time t, and the higher the auxiliary energy consumption. The relationship curves of the two energy consumption and speed for the same distance are as follows: Figure 2 shown.
[0101] It can be seen that as the train speed increases, the auxiliary energy consumption decreases and the energy consumption for overcoming resistance increases; in the initial stage of the train start, the running speed is low and the train is in an accelerated state, and the energy consumption of this process is relatively high; in the middle stage of the train start, the energy consumption for overcoming resistance gradually exceeds the auxiliary energy consumption, and at this time the running speed level is approximately proportional to the energy consumption for overcoming resistance; at the end of the train start, the auxiliary energy consumption is low, and the main energy consumption is the energy consumption for overcoming resistance. At this time, the train can adjust the running speed according to the operation plan, running mileage, and running status to complete the running task.
[0102] A variety of sensors are installed inside and outside the train to detect information such as track slope, curves, terrain, outside temperature and weather. In the context of the Internet of Things, the data generated by each subsystem is integrated through multi-level information interconnection and fusion technology to achieve information convergence in lines, substations and higher areas. Focusing on processing these massive amounts of data can obtain the optimal operation strategy for the train, but there is currently a lack of the ability to process data in real time. Therefore, this patent proposes an IT load integration strategy. Considering that the computing power of the train's own computer is limited and the information processing speed often lags behind the actual situation of the train, this article proposes to transfer the train's IT information load to a distribution station with greater computing power. The distribution station provides computing power and calculates the optimal speed curve of the train based on the control object, and then feeds back to the train computer. The train uses automatic control to help the driver better track the speed curve.
[0103] ③ Train energy storage device modeling
[0104] The train will brake frequently when entering, leaving, or stopping at a station. The energy consumed in this process is recovered by the train energy storage device. The mathematical formula for energy recovery is as follows:
[0105]
[0106]
[0107] In the formula, E reg,i,t represents the braking energy consumption of the i-th train at time t; ξ is the energy recovery efficiency; ν t is the train speed at time t; to ensure optimal recovery of braking energy consumption, the maximum capacity of the energy storage device shall not exceed 90% of the total average braking energy consumption of the train operation, and the energy of the storage device shall terminate at 0 before the train stops running.
[0108] (2) Modeling of power distribution station information load energy consumption
[0109] The data detected by the train is transferred to the power distribution station for processing, and the information of the power distribution station is centrally stored in the data center. The main energy consumption of the data center is IT information energy consumption and refrigeration equipment energy consumption. The ratio of data center energy consumption to IT energy consumption is one of the indicators for measuring the energy consumption of the data center. The closer the ratio is to 1, the better the energy consumption level of the data center. In the energy consumption of the data center, the energy consumption of IT equipment accounts for the largest proportion. This energy consumption is mainly generated in the process of servers storing and processing information loads. The information load borne by the server is positively correlated with the energy consumption of IT equipment.
[0110] ①Server power consumption model
[0111] The energy consumption of the server at the receiving end of the information load distribution station will increase. Considering the service quality requirements of the data center and the service life of the server, the server shutdown state is not considered because the server is running in real time. The server energy consumption is regulated by adjusting the number of working servers. The server power consumption model is as follows:
[0112] P 2,t =P w n t +P h (N t ) (8)
[0113] Where P 2,t is the total energy consumption of the server at time t, P w is the power consumption of the working server, P h is the energy consumption of dormant servers, N is the total number of servers, n t is the number of working servers at time t.
[0114] After the server energy consumption model is established, the server operating cost can be obtained:
[0115]
[0116] Where f2 is the server operation cost.
[0117] ② Loss cost modeling
[0118] The loss cost of the distribution station, this patent mainly considers the transformer loss cost and the line operation loss cost.
[0119] 1) Transformer loss cost
[0120] Transformer parameters are crucial for calculating losses during power supply and conducting economic operation analysis. These parameters are divided into two categories, namely rated parameters and technical parameters. Rated parameters represent the basic performance of the transformer, while technical parameters reflect the transformer's own losses. The rated parameters of the transformer include the rated capacity S (MVA), the rated voltages U1 (kV) and U2 (kV) on the high-voltage and low-voltage sides, and the rated currents I1 (kA) and I2 (kA). The relationship between them is:
[0121]
[0122] There are multiple transformers in the distribution station. As one of the main equipment in the distribution network, the power loss of the transformer is an important part of the distribution network loss (accounting for about 40% to 70% of the distribution network loss). Therefore, the economic operation of the transformer is very important for the operation optimization of the entire flexible interconnected distribution network. This patent only studies the operation loss of the transformer that supplies power to the train, and the load loss of the transformer belongs to the variable loss. First, we give the following definition: When the rated current I1 on the high-voltage side flows through the double-winding transformer, the rated load loss generated in the time period t is P 3,t , assuming the equivalent resistance of the transformer is r T , satisfying the following relationship:
[0123]
[0124] In the formula, I1 is a quantity that changes in real time according to the running status of the train. Therefore, the transformer loss can be controlled by controlling the running status of the train cluster.
[0125] Therefore, the transformer operating loss cost is given by the function f 3,1 It is represented as follows:
[0126]
[0127] Where: f 3,1 Represents the loss cost of transformer operation.
[0128] 2) Line operation loss cost
[0129] During the period t, the line operation power loss is expressed by function P 4,t It is represented as follows:
[0130]
[0131] In the time period t, the line operation loss cost is expressed by function f 3,2 It is represented as follows:
[0132]
[0133] Where: Iab,t represents the current of the branch of the distribution station (ab) during the period t. The line loss can be controlled by controlling the running status of the train cluster. ab represents the resistance of the branch, and C2 represents the branch set of the distribution substation.
[0134] The total loss of the distribution station is represented by f3 as follows:
[0135] f3=f 3,1 +f 3,2 (15)
[0136] Where: f 3,2 It represents the loss cost of line operation, and f3 is the sum of the loss of the substation transformer and the line.
[0137] (3) Constraints and objective functions
[0138] ①Energy constraint equation
[0139] The power supply for daily operation of the distribution station comes from the power grid and energy storage devices. The load power consumption mainly includes traction trains, various types of loads in the station, various losses, and discharge of energy storage devices. The energy balance equation constraints of the distribution station are as follows:
[0140]
[0141] P g,i,t ≤P max (17)
[0142]
[0143] Where, P g,i,t is the exchange power between distribution station i and the grid at time t, P max is the maximum exchange power between the distribution station and the power grid, is the maximum discharge power of the energy storage device at time t.
[0144] ②Data processing delay constraints:
[0145] In order to improve the coordinated dispatching effect between trains and power distribution stations, the data transmission delay between trains and power distribution stations needs to be reasonably controlled. It is ensured that when the delay reaches the maximum value, the data of the train real-time monitoring is transmitted to the power distribution station for processing in a timely manner, and the speed curve output by the power distribution station can accurately match the actual operation of the train.
[0146]
[0147] Where: i,t is the total amount of data tasks arriving at data center i at time t; μ is the service rate of the working server for data tasks, which depends on the server performance; T ΦIt is the delay bound for data processing, and different types of data loads have different delay requirements.
[0148] ③Train speed climbing constraint
[0149] The speed climbing constraints under the train acceleration state are as follows:
[0150]
[0151] Where V t is the train speed at time t; V up t-1,min 、V up t-1,max They are the minimum and maximum running speeds of the train at the next moment respectively.
[0152] ④Train speed braking constraint
[0153] When arriving at the target station or encountering an emergency, the train reduces its running speed through active braking. The speed constraints during train braking are as follows.
[0154] V down t-1,min <V t <V down t+1,max (twenty one) Where V down t-1,min 、V down t-1,max They are the minimum and maximum running speeds at the next moment when the train brakes.
[0155] ⑤Objective function
[0156] This patent takes the lowest train operation cost as the objective function to optimize the train load operation, which is composed of train operation cost, information load transfer cost, various loss costs, etc. The specific objective function is expressed as follows:
[0157] MinZ=f1+f2+f3 (22)
[0158] In the formula, Z is the total cost of system operation; the size of Z is determined by transformer, line loss, train operation and distribution center. For the whole, blindly pursuing a certain item is slightly one-sided. Therefore, it is necessary to consider multi-faceted constraints and use appropriate intelligent algorithms to comprehensively optimize the goal.
[0159] (4) Improved intelligent solution algorithm
[0160] The African Wild Dog Algorithm is an optimization algorithm inspired by the behavior of African wild dog groups. It was created by Du Pengpeng and Xu Yida in 2014. This algorithm simulates four behaviors of African wild dog groups: siege, pursuit, scavenging, and survival. In the algorithm, siege, pursuit, and scavenging behaviors are mutually exclusive, while survival behavior determines the final solution. By randomly dividing the population into three categories and executing these three behaviors separately, the optimal position is finally determined by survival behavior. During the iteration process, iterative calculations of these three behaviors need to be performed simultaneously, making the algorithm more suitable for solving optimization problems. Figure 3 shown.
[0161] For f1: Encode the train cluster and calculate individual characteristics according to formulas (2)-(7). Individual characteristics include speed, energy consumption, and braking energy recovery in the current period. Enter the train operation constraints in the operation environment and control all individuals. Store each individual characteristic and calculate the train operation cost according to formula (1).
[0162] Regarding f2: Since the power distribution station server is running in real time, the server only has sleep state and power-on state. The system server is integrated according to formula (8). The server loss has a strong correlation with time. It is preferred to integrate the server cluster using matrix or series. The server operation cost is obtained according to formula (9). The power distribution station needs to process the information load transmitted by the train at all times, and then process the information and calculate the optimal running speed of the train according to the train energy consumption curve. Therefore, the server shutdown state is not considered in this patent.
[0163] Regarding f3: Transformer loss and line loss are strongly correlated with current, and the power required by the train is determined by the train speed. Although this patent will use f1, f2, and f3 to distinguish between train operation, distribution center loss, transformer, and line loss, f1, f2, and f3 are a whole in the general direction. The transformer and line current are highly variable. By dividing 24 hours into multiple time periods and monitoring the current size in each time period, the average current size of the transformer and line in the time period can be obtained, and this part of the loss can be calculated according to formulas (10)-(15).
[0164] According to formulas (16)-(21), multiple constraints are entered. f1, f2, and f3 are a continuous whole in terms of train operation. Once the constraints are established, the algorithm search area is determined. The African wild dog algorithm is used to search the multi-objective and multi-constrained area. Finally, the optimal solution of the algorithm is obtained by integrating the total objective function of formula (23). The physical data represented by the optimal solution of the algorithm is the optimal strategy considering the train-distribution station scheduling. Among the individuals contained in the above f1, f2, and f3, each individual represents a wild dog operator, and the population size of the wild dog is determined by the actual operation system. Each individual should follow the corresponding constraints. The initialization and iteration behavior of the wild dog strictly follow the improved African wild dog algorithm. The iteration behavior strictly follows the improved African wild dog algorithm, as shown in formulas (23)-(34). According to formula (22), the objective function is entered, and the optimal solution is finally obtained.
[0165] In the above process, there are multiple individuals in f1, f2, and f3. The objective function seeks the minimum value of the sum of f1, f2, and f3 while complying with the constraints. Sequentially encode each individual in f1, f2, and f3, using Represents the i-th individual in the code and updates the algorithm formula.
[0166] ①Besieging behavior
[0167]
[0168] In the formula, represents the new position of the i-th wild dog in the d-dimensional space, and Ψ is a uniform random number in [-2,2]; represents the optimal position of the i-th wild dog in d-dimensional space;
[0169]
[0170] In the formula, Λ represents the number of wild dogs, represents the position of the kth wild dog in d-dimensional space, f i d Represents the position of the i-th wild dog in d-dimensional space.
[0171] ② Pursuit
[0172]
[0173] In the formula, c is a uniform random number in [-1,1]; is a random individual in the wild dog population, j≠i.
[0174] ③ Scavenging behavior
[0175]
[0176] ④Survival behavior
[0177] The three behaviors of the population, namely, siege, hunting, and scavenging, will eventually be screened and eliminated through survival behavior. The survival probability of the three behaviors in the i-th iteration is sr i for:
[0178]
[0179]
[0180] In the formula, are two random individuals in the population, represents the updated position after the adaptive decreasing energy control factor is adopted; best(F(X)) is the set of population solutions with the highest fitness, F(X i ) is the i-th group of population solutions, worst(F(X)) is the group of population solutions with the lowest fitness, and ε represents the allowable error range.
[0181] ⑤Algorithm flow and application
[0182] In the African wild dog algorithm, the probability of each wild dog choosing to attack, hunt, and scavenger is determined by P and Q. Generally, P = 0.5 and Q = 0.7. The specific process is as follows:
[0183] if(rand1<0.5and rand2<0.7) (29)
[0184] if(rand1<0.5and rand2≥0.7) (30)
[0185] if(rand1≥0.5) (31)
[0186] if(sr<0.3) (32)
[0187] Where rand1 and rand2 are both random numbers between 0 and 1, satisfying formulas (29) to (32). Wild dogs perform pursuit, scavenging, siege, and survival behaviors, respectively.
[0188] ⑤Algorithm improvement
[0189] In algorithm improvement, the search area should be increased in the early stage of algorithm iteration to increase the randomness and comprehensiveness of the early iteration of the algorithm; the integrity of the population should be preserved in the later stage of algorithm iteration to make the operator representative. The search model should follow: the population richness is at a high level in the early stage of iteration, and decreases with the progress of iteration until it approaches the minimum value in the later stage. Taking into account the lack of randomness of the search area of the African wild dog algorithm in the early stage, this patent improves this part by adding an adaptive decreasing energy control factor to the three iterative behaviors of siege, pursuit, and scavenging. The factor expression is as follows:
[0190]
[0191] m and n are constraint parameters, T is the upper limit of iteration, and r is the number of iterations;
[0192] Where: when n is 3, m is 5.2. The function graph shows an inverse S-shaped decrease. The slope is small at the beginning of the iteration. In the early stage of the iteration, E1 is used as a coefficient to multiply the three behaviors iteratively, which can improve the algorithm search range in the early stage of the algorithm; when n is 0.34 and m is 0.2, it is an S-shaped decrease. In the later stage of the iteration, E1 is multiplied by the three iterative behaviors, which can effectively ensure the iteration accuracy and improve the stability of the operator. The algorithm is set to iterate 200 times, and the 100th iteration is used as the dividing line to divide the early and late stages of the iteration. The iterative update formulas of the three behaviors are:
[0193]
[0194] Represents the updated position after adopting the adaptive decreasing energy control factor.
[0195] The overall system block diagram is as follows: Figure 4 As shown, the train is mainly powered by a distribution station, supplemented by energy storage devices. The information load generated by the train is transferred to the distribution station data center for processing. The data center considers market electricity prices, transformer and line losses, and the actual train operation losses to output the optimal operating speed curve. The objective function is to minimize the overall operating cost of the system, thereby improving the economy of the train-distribution station.
[0196] The above describes the specific embodiments of the present invention. It should be understood that the present invention is not limited to the above specific embodiments, and those skilled in the art can make various changes or modifications within the scope of the claims, which does not affect the essence of the present invention. In the absence of conflict, the embodiments of the present application and the features in the embodiments can be combined with each other arbitrarily.
Claims
1. A method for optimizing the operation of a power distribution station taking into account train load scheduling, characterized in that: The following steps are included: S1. Taking the lowest train operation cost as the objective function, the train load operation is optimized, which is composed of train operation cost, information load transfer cost, and various loss costs. The specific objective function is expressed as follows: MinZ=f1+f2+f3 <h2 style=";text-align:left;direction:ltr">f3=f<h2 style=";text-align:left;direction:ltr"> 3,1 <h2 style=";text-align:left;direction:ltr"> +f<h2 style=";text-align:left;direction:ltr"> 3,2 Where Z is the total system operation cost; the size of Z is determined by the transformer, line loss, train operation and distribution center, f1 is the energy cost of all trains, f2 is the server operation cost, and f 3,1 represents the loss cost of transformer operation, f 3,2 represents the loss cost of line operation; f1 is the energy cost of all trains, C1 represents the train set, is the electricity price at the tth moment of train i’s operation, is the power consumption of train i at the tth moment, is the electricity price for charging energy storage with regenerative braking energy at time t during the operation of train i, P is the power released by the energy storage device at the tth moment during the operation of train i; 2,t is the total energy consumption of the server at time t; S2. The improved African wild dog algorithm is used to optimize the objective function in all aspects; each individual in f1, f2, and f3 represents a wild dog operator, and the population size of wild dogs is determined by the actual operating system. An adaptive decreasing energy control factor E1 is added to the three iterative behaviors of siege, pursuit, and scavenging. The expression is as follows: In the formula, m and n are constraint parameters, T is the upper limit of iteration, and r is the number of iterations; Represents the updated position after adopting the adaptive decreasing energy control factor.
2. A method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 1, characterized in that: In step S1, The calculation formula is: Where: E reg,i,t represents the braking energy consumption of the i-th train at time t; ξ is the energy recovery efficiency; M is the train mass; v t is the train speed at time t; β is the braking system efficiency during the braking process.
3. A method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 2, characterized in that: In step S1, the server energy consumption is regulated by adjusting the number of working servers. The server power consumption model is as follows: P 2,t =P w n t +P h (N-n t ) Where, P 2,t is the total energy consumption of the server at time t, P w is the power consumption of the working server, P h is the energy consumption of dormant servers, N is the total number of servers, n t is the number of working servers at time t.
4. A method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 3, characterized in that: In step S1, the transformer operating loss cost is calculated by function f 3,1 It is represented as follows: When the rated current I1 on the high-voltage side flows through the double-winding transformer, the rated load loss generated in the time period t is P 3,t , assuming the equivalent resistance of the transformer is r T , satisfying the following relationship:
5. A method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 4, characterized in that: In step S1, the line operation loss cost in time period t is calculated using function f 3,2 It is represented as follows: During the period t, the line operation power loss is expressed by function P 4,t It is represented as follows: I ab,t represents the current of the branch of the distribution station (ab) during the period t. By controlling the running status of the train cluster, the line loss is controlled. ab represents the resistance of the branch, and C2 represents the branch set of the distribution substation.
6. A method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 5, characterized in that: In step S1, the power supply for daily operation of the distribution station comes from the power grid and the energy storage device, and the energy balance equation of the distribution station is constrained as follows: P g,i,t ≤P max Where P g,i,t is the exchange power between distribution station i and the grid at time t, P max is the maximum exchange power between the distribution station and the power grid, is the maximum discharge power of the energy storage device at time t; Data processing delay constraints: Where: i,t is the total amount of data tasks arriving at data center i at time t, μ is the service rate of the working server for data tasks, T Φ Delay bound for data processing; The speed climbing constraints under the train acceleration state are as follows: V up t+1,min vV t <V up t+1,max Where V t is the train speed at time t; V up t-1,min 、V up t-1,max They are the minimum and maximum running speeds of the train at the next moment respectively; Train speed braking constraints: When arriving at the target station or encountering an emergency, the train will actively brake to reduce its running speed. The speed constraints when the train brakes are as follows: V down t-1,min <V t <V down t+1,max Where V down t-1,min 、V down t-1,max They are the minimum and maximum running speeds at the next moment when the train brakes.
7. The method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 1, characterized in that: In step S2, the improved African wild dog algorithm is used to optimize the objective function in all aspects, and each individual in f1, f2, and f3 is sequentially encoded. represents the i-th individual in the d-dimensional space in the encoding, that is, the position of the i-th wild dog in the d-dimensional space, Mobbing behavior: In the formula, represents the new position of the i-th wild dog in the d-dimensional space; Ψ is a uniform random number in [-2,2]; represents the optimal position of the i-th wild dog in d-dimensional space; In the formula, Λ represents the number of wild dogs, represents the position of the kth wild dog in d-dimensional space, f i d Represents the position of the i-th wild dog in d-dimensional space.
8. A method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 7, characterized in that: In step S2, the pursuit behavior: In the formula, c is a uniform random number in [-1,1]; is a random individual in the wild dog population, j≠i.
9. A method for optimizing the operation of a power distribution station taking train load scheduling into consideration according to claim 8, characterized in that: In step S2, scavenging behavior: Survival behavior: The three behaviors of the population, namely, siege, hunting, and scavenging, will eventually be screened and eliminated through survival behavior. The survival probability of the three behaviors in the i-th iteration is sr i for: In the formula, are two random individuals in the population, represents the updated position after the adaptive decreasing energy control factor is adopted; best(F(X)) is the set of population solutions with the highest fitness, F(X i ) is the i-th group of population solutions, worst(F(X)) is the group of population solutions with the lowest fitness, and ε represents the allowable error range.