A high-safety split-level cantilevered balcony structure and its assembly and use method
By adopting the design of adapters and drainage channels in the cantilevered balcony structure, self-locking and rainwater drainage are achieved, which solves the problems of inconvenient assembly and safety risks, and improves transportation efficiency and safety of use.
Patent Information
- Application Number
- CN202411087890.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-08-09
AI Technical Summary
The existing prefabricated cantilevered balcony structure occupies a large space during assembly and is inconvenient to transport, and it is easy to slip due to gravity during the hoisting process, resulting in a high risk of safety accidents.
It uses multiple assembled concrete slabs spliced end to end, realizes self-locking processing through adapters, uses the T-shaped structure of movable sliders and connectors to ensure splicing stability, and realizes rainwater drainage through drainage channels and movable blocking plates. Reduce balcony load.
It improves assembly efficiency, avoids falling accidents during hoisting, enhances the safety of balcony installation and use, and reduces the load and health risks of the balcony.
Smart Images

Figure CN118601136B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a staggered-layer cantilevered balcony structure, in particular to a high-safety staggered-layer cantilevered balcony structure applied in the cantilevered balcony field and an assembling and using method thereof. Background Art
[0002] In recent years, staggered cantilevered balconies have become a selling point for many developers. The so-called staggered cantilevered balconies mean that the balconies on the odd-numbered floors and the even-numbered floors are not on the same vertical line, and there is a misalignment in the design. This makes the building facade more varied, and also allows the owners to enjoy a larger balcony space and more sunshine. Since cantilevered balconies are mostly prefabricated structures, hoisting operations are often used in assembly.
[0003] The specification of Chinese patent CN202122956240.7 discloses an assembled cantilever beam balcony structure. The application realizes the fixing or disassembly effect of the table top and the baffle by clamping the second plug rod into the second plug hole or separating it from the second plug hole, which has the effect of facilitating the disassembly and recycling of the baffle.
[0004] Existing prefabricated cantilever balcony structures usually use an integrated structure during assembly, and the overall space occupied during transportation is large, which is not conducive to efficient transportation. In addition, some prefabricated balconies are designed for interlocking and plug-in operations, but since the interlocking and plug-in position is a single sliding plug-in, during the hoisting process, in order to prevent the assembled assembly structure from sliding due to gravity and causing safety accidents, multi-point bundling and hoisting are required, making the hoisting work more cumbersome. Summary of the invention
[0005] In view of the above-mentioned prior art, the technical problem to be solved by the present invention is to provide a cantilever balcony structure so that it can achieve convenient and effective self-locking processing during assembly, avoid accidents of falling objects during lifting, and ensure lifting safety.
[0006] In order to solve the above problems, the present invention provides a high-safety staggered cantilever balcony structure, including a balcony bottom plate installed on the surface of a wall, a plurality of assembled concrete slabs spliced end to end are fixed on the top of the balcony bottom plate, and engaging grooves are provided on both side surfaces of the assembled concrete slabs, and two adjacent assembled concrete slabs are spliced by an adapter, and the adapter is formed by two adapter units connected by a movable shaft, and the adapter unit includes a vertical column with a cross-section of an isosceles right triangle, and equal-length plug-ins are arranged on one side surface of the vertical column, and the plug-ins and the engaging grooves have the same cross-section width, and movable sliders are symmetrically arranged on the surface of the plug-in, and the movable sliders are connected to the ends of the plug-in surface through shaft rods, and the height value of the movable slider is greater than the cross-sectional width value of the plug-in, and the inner wall of the engaging groove is provided with symmetrically arranged arc grooves, and the cross-sectional length value of the arc groove projected in the vertical direction is the same as the length value of the movable slider in the horizontal state, and a sealing block is inserted into the interior of the engaging groove, and the internal thread of the sealing block is connected to a screw, and the tail end of the screw extends into the movable slider in the horizontally placed state.
[0007] In the above-mentioned high-safety staggered cantilever balcony structure, the use of adapters can achieve effective interlocking and self-locking processing, avoid accidents of falling objects during the hoisting process, and ensure the safety of the hoisting.
[0008] As a further improvement of the present application, the waist length of the vertical column section is the same as the cross-sectional width of the assembled concrete slab, and the vertical column is of the same height as the assembled concrete slab.
[0009] As a further improvement of the present application, the two connectors of the adapter are arranged horizontally in the initial state, and the two connectors are arranged vertically when two assembled concrete slabs are vertically spliced.
[0010] As a further improvement of the present application, the cross-sectional length value of the engaging groove is the sum of the cross-sectional length value of the connector and the thickness value of the movable slider, and the thickness of the sealing block is the same as the thickness value of the movable slider in the horizontal state.
[0011] As another improvement of the present application, the interiors of the two vertical columns in the adapter are both provided with drainage grooves with a semicircular cross-section, and the inner wall of the drainage groove is installed with a movable blocking plate with a diameter the same as the inner diameter of the drainage groove through a reset shaft.
[0012] As another improvement supplement of the present application, a monitoring unit is installed on the surface of the movable blocking plate, and the monitoring unit includes a flow sensor for determining whether the drainage trough is in a drainage state and an inclination sensor for determining the inclination state of the movable blocking plate, and an alarm electrically connected to the flow sensor and the inclination sensor is installed on the surface of the wall.
[0013] As another improved supplement of the present application, the drainage groove is arranged obliquely, and one end of the drainage groove facing the wall is higher than the other end.
[0014] A method for assembling and using a high-safety split-level cantilevered balcony structure comprises the following steps:
[0015] S1, preliminary installation, connecting the assembled concrete slab with built-in steel bars to the surface of the wall;
[0016] S2, assembly, the horizontally spliced assembled concrete panels are buckled into the fitting grooves through the plug-in parts, and when the horizontal splicing is completed and the two assembled concrete panels are vertically spliced, one of the vertical columns in the adapter is rotated 180 degrees to form a state where the two plug-in parts are perpendicular to each other and then plugged in;
[0017] S3, locking process, after the plug-in piece is inserted into the fitting groove, the movable slider is turned 90 degrees, and after sliding into the arc groove in a horizontal state, the sealing block is buckled on the movable slider in a horizontal state, and the sealing block and the movable slider are locked with a screw;
[0018] S4, filling the gap between the two vertical columns in the adapter, and then hoisting the assembled concrete slabs formed by assembling and locking the multiple assembled concrete slabs to the surface of the balcony bottom plate for fixed connection;
[0019] S5. During heavy rainfall, rainwater accumulated on the surface of the balcony floor is discharged through the gutter, reducing the load on the overall balcony structure.
[0020] To sum up, by using adapters, it is possible to control the manufacturing cost of the balcony without changing the structure of the assembled concrete slabs and by rotating one of the vertical columns 180 degrees after completing the horizontal splicing of the assembled concrete slabs, so that the two originally horizontally arranged connectors become vertically arranged, and the vertical splicing at the corners can be smoothly performed, which can improve the problem of low transportation efficiency caused by the integrated prefabricated balcony. In addition, after the splicing is completed, the change in the placement state of the movable slider is utilized to form a T-shaped structure with the connector, making it difficult to pull out horizontally, and after the sealing block and the movable slider are threadedly locked, the longitudinal pullout of the movable slider is prevented, so that the overall connection stability of the fence structure after splicing is enhanced. In the subsequent lifting process, there is no need to strengthen the lifting bundling, which also reduces the possibility of falling accidents and improves the safety of balcony installation. In addition, during the use of the balcony, the drainage trough and the movable blocking plate are used to flexibly drain the water, reduce the balcony load, and ensure the safety and sanitation of the balcony. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 This is a schematic diagram of the overall structure of the first implementation method of the present application;
[0022] Figure 2 This is a schematic diagram of the structure of the adapter according to the first embodiment of the present application;
[0023] Figure 3This is a schematic diagram of the process of rotating the plug-in block 180 degrees in the first embodiment of the present application;
[0024] Figure 4 This is a schematic diagram of the installation of the arc groove and the sealing block in the first embodiment of the present application;
[0025] Figure 5 This is a schematic structural diagram of an arc groove and a movable slider in the first embodiment of the present application;
[0026] Figure 6 This is a schematic diagram of the movable slider in the first embodiment of the present application changing from a vertical state to a horizontal state;
[0027] Figure 7 This is a structural diagram of multiple assembled concrete panels spliced together on the surface of a wall in the first embodiment of the present application;
[0028] Figure 8 This is a structural diagram of a movable plug and a drainage trough in the second embodiment of the present application;
[0029] Fig. 9 This is a schematic diagram of the drainage process of the second embodiment of the present application;
[0030] Fig.10 This is a cross-sectional view of the drainage groove of the second embodiment of the present application.
[0031] Description of the numbers in the figure:
[0032] 001. Wall; 1. Assembled concrete slab; 2. Balcony bottom plate; 11. Fitting groove; 3. Adapter; 31. Vertical column; 32. Movable slider; 33. Connector; 4. Sealing block; 5. Arc groove; 6. Drainage trough; 7. Movable blocking plate. DETAILED DESCRIPTION
[0033] Two implementation modes of the present application are described in detail below with reference to the accompanying drawings.
[0034] The first implementation method:
[0035] Figure 1-2 and Figure 4A high-safety split-level cantilevered balcony structure is shown, comprising a balcony bottom plate 2 installed on the surface of a wall 001, a plurality of assembled concrete slabs 1 spliced end to end are fixed on the top of the balcony bottom plate 2, both sides of the assembled concrete slabs 1 are provided with engaging grooves 11, two adjacent assembled concrete slabs 1 are spliced by an adapter 3, the adapter 3 is formed by two adapter units connected by a movable shaft, and the adapter unit includes a vertical column 31 with a cross-section of an isosceles right triangle, and a plug-in 33 of equal length is arranged on one side surface of the vertical column 31, and the plug-in 33 and the engaging groove 11 are connected. The cross-section of the connector 33 is equal in width, and the movable slider 32 is symmetrically arranged on the surface of the connector 33, and the movable slider 32 is connected to the end of the surface of the connector 33 through a shaft rod, and the height of the movable slider 32 is greater than the cross-sectional width of the connector 33. The inner wall of the fitting groove 11 is provided with symmetrically arranged arc grooves 5, and the cross-sectional length of the arc groove 5 projected in the vertical direction is the same as the length of the movable slider 32 in the horizontal state. The interior of the fitting groove 11 is plugged with a sealing block 4, and the internal thread of the sealing block 4 is connected with a screw, and the tail end of the screw extends into the movable slider 32 in the horizontal state;
[0036] In the initial state, the two plug-in components 33 of the adapter 3 are arranged horizontally. When two assembled concrete slabs 1 are vertically spliced, the two plug-in components 33 are arranged vertically.
[0037] Specifically, when assembling the semi-enclosed balcony, first fix the balcony bottom plate 2 on the surface of the wall 001, and then splice a plurality of assembled concrete slabs 1 into a fence structure according to the size of the balcony bottom plate 2. When assembling, horizontal splicing needs to be performed first, and two assembled concrete slabs 1 are inserted into the fitting groove 11 through the plug-in piece 33 on the surface of the adapter 3, and then vertical splicing is performed at the corner. It is necessary to rotate one of the vertical columns 31 180 degrees so that the originally horizontally placed plug-in piece 33 becomes a vertical arrangement, so that the corresponding vertical splicing (such as Figure 3 As shown), and there is no need to change the surface structure design of the assembled concrete slab 1. During transportation, multiple assembled concrete slabs 1 can be efficiently stacked and transported to ensure transportation efficiency. At the same time, when prefabricating the assembled concrete slab 1, it is also more convenient, and there is no need to open grooves and protrusions on different planes to adapt to corner splicing operations;
[0038] Figure 5-7It is shown that after the interlocking and plugging is completed, since the movable slider 32 is at a position close to the end of the surface of the connector 33, and thus relatively close to the end of the interlocking groove 11, it is convenient to flip the movable slider 32 in the vertical state into a horizontal state and move in the arc groove 5, and then put the sealing block 4 into the interlocking groove 11, and use a screw to complete the locking of the sealing block 4 and the movable slider 32. Since the cross-sectional length value of the movable slider 32 in the horizontal state is greater than the cross-sectional width value of the connector 33, a T-shaped structure can be formed to prevent the adapter 3 from being laterally pulled out of the interlocking groove 11. In addition, since the movable slider 32 is limited by the cross-sectional length of the arc groove 5 in the arc groove 5 after being locked with the sealing block 4, it cannot be moved up, and then the locking processing in the horizontal and vertical directions is realized, so that the multiple assembled concrete slabs 1 after splicing are in a relatively stable connection relationship. Therefore, during hoisting, there is no need to adopt a multi-point bundling design, which simplifies the selection of hoisting points during hoisting and avoids falling accidents during hoisting, thereby ensuring hoisting safety.
[0039] After the assembled multiple assembled concrete slabs 1 are hoisted to the surface of the balcony bottom plate 2, the fence structure needs to be connected and fixed to the wall 001 and the surface of the balcony bottom plate 2 to complete the assembly and use of the corresponding semi-enclosed balcony.
[0040] The waist length of the cross section of the vertical column 31 is the same as the cross section width of the assembled concrete slab 1 , and the vertical column 31 is the same height as the assembled concrete slab 1 .
[0041] Specifically, during splicing, due to the cross-sectional dimensions of the vertical columns 31 and the assembled concrete slab 1 , the surface of the balcony after splicing is in a relatively flat state.
[0042] The cross-sectional length of the fitting groove 11 is the sum of the cross-sectional length of the connector 33 and the thickness of the movable slider 32 , and the thickness of the sealing block 4 is the same as the thickness of the movable slider 32 in the horizontal state.
[0043] Specifically, due to the size design of the sealing block 4 and the movable slider 32, after the movable slider 32 is turned over, the engaging groove 11 can be filled and blocked smoothly, so that the surface of the joint does not need to be filled later.
[0044] A method for assembling and using a high-safety split-level cantilevered balcony structure comprises the following steps:
[0045] S1, preliminary installation, connecting the assembled concrete slab 1 with built-in steel bars to the surface of the wall 001;
[0046] S2, assembly, the horizontally spliced assembled concrete panels 1 are buckled into the fitting grooves 11 through the plug-in parts 33, and when the horizontal splicing is completed and the two assembled concrete panels 1 are vertically spliced, one of the vertical columns 31 in the adapter 3 is rotated 180 degrees to form a state in which the two plug-in parts 33 are perpendicular to each other and then plugged in;
[0047] S3, locking process, after the plug-in 33 is inserted into the fitting groove 11, the movable slider 32 is turned 90 degrees, and after sliding into the arc groove 5 in a horizontal state, the sealing block 4 is buckled on the movable slider 32 in a horizontal state, and the sealing block 4 and the movable slider 32 are locked by a screw;
[0048] S4, filling the gap between the two vertical columns 31 in the adapter 3, and then hoisting the assembled concrete slabs 1 formed by assembling and locking the multiple assembled concrete slabs to the surface of the balcony bottom plate 2 for fixed connection;
[0049] S5. In heavy rainfall weather, rainwater accumulated on the surface of the balcony floor 2 is discharged through the drainage groove 6, reducing the load on the overall balcony structure.
[0050] The second implementation method:
[0051] Figure 8-Figure 10 It is shown that the two vertical columns 31 in the adapter 3 are both provided with a drainage groove 6 with a semicircular cross-section, and the inner wall of the drainage groove 6 is installed with a movable blocking plate 7 with the same diameter as the inner diameter of the drainage groove 6 through a reset shaft.
[0052] Specifically, after the installation of the spliced fence-type balcony is completed, the gap between the surfaces of the two vertical columns 31 in the adapter 3 needs to be filled and sealed with waterproof coating or waterproof cloth, thereby strengthening the sealing of the adapter 3 at the corner. When encountering heavy rainfall weather, rainwater will accumulate on the surface of the balcony bottom plate 2, resulting in an increase in the overall load of the balcony, which is not conducive to the safety of the cantilevered balcony. At this time, the accumulated rainwater can be discharged through the drainage groove 6 to reduce the overall load of the balcony, thereby protecting the safety of the balcony.
[0053] In addition, since the drainage trough 6 is symmetrically designed, the integrity of the splicing will not be affected after rotation. When draining water, the impact of rainwater will cause the movable blocking plate 7 to deflect, thereby allowing the water to be discharged smoothly. After the rainwater is drained, under the action of the reset shaft, the movable blocking plate 7 resumes the sealing treatment of the drainage trough 6, preventing external reptiles and other foreign objects from being transferred to the balcony through the drainage trough 6, thereby ensuring the hygiene and safety of the balcony. Compared with the design of the drain pipe, it can reduce costs and also reduce the odor problem of the drain pipe caused by the growth of bacteria in the moist corners of the drain pipe.
[0054] The drainage groove 6 is arranged obliquely, and one end of the drainage groove 6 facing the wall 001 is higher than the other end.
[0055] Specifically, the inclined design of the drainage trough 6 provides a more convenient way to discharge the accumulated rainwater, while also avoiding the problem of residual water in the drainage trough 6.
[0056] A monitoring unit is installed on the surface of the movable blocking plate 7, and the monitoring unit includes a flow sensor for determining whether the drainage trough 6 is in a drainage state and an inclination sensor for determining the inclination state of the movable blocking plate 7, and an alarm electrically connected to the flow sensor and the inclination sensor is installed on the surface of the wall 001.
[0057] Specifically, in the process of draining water through the gutter 6, as the water flows, some foreign matter carried in the water will be discharged together. Under normal circumstances, after the rainwater is discharged, under the action of the reset shaft, the movable plug 7 can be normally reset to achieve a blocking effect. However, if during the drainage process, the movable plug 7 and the inner wall of the gutter 6 are partially stuck, the reset of the movable plug 7 will be prevented. At this time, combined with the flow sensor, it is monitored that the inside of the gutter 6 is not in a drainage state, and the inclination sensor detects that the movable plug 7 is in a non-horizontal state. At this time, the alarm will be activated to remind the user that the reset of the movable plug 7 is abnormal. The user is required to use a rod-shaped object with a diameter smaller than the gutter 6 to reach into the gutter 6 to poke the movable plug 7, thereby releasing the restraining effect of the movable plug 7, allowing the movable plug 7 to be reset. After the movable plug 7 is reset, it can continue to be poked inward to achieve the effect of unblocking the inside of the gutter 6.
[0058] Different from the first embodiment, this embodiment improves the phenomenon of water accumulation during the use of the balcony, thereby reducing the load on the balcony, ensuring the safety of the balcony while also ensuring the hygiene and safety of the balcony.
[0059] In summary, the present application utilizes the adapter 3, and on the basis of not changing the structure of the assembled concrete slab 1 and thus controlling the manufacturing cost of the balcony, after completing the horizontal splicing of the assembled concrete slab 1, one of the vertical columns 31 is rotated 180 degrees, so that the two originally horizontally arranged connectors 33 become vertically arranged, and the vertical splicing at the corner is smoothly performed, which can improve the problem of low transportation efficiency caused by the integrated prefabricated balcony. In addition, after the splicing is completed, the change in the placement state of the movable slider 32 is utilized to form a T-shaped structure with the connector 33, making it difficult to pull it out horizontally, and after the sealing block 4 and the movable slider 32 are threadedly locked, the longitudinal pullout of the movable slider 32 is prevented, so that the overall connection stability of the fence structure after splicing is enhanced, and in the subsequent lifting process, there is no need to strengthen the lifting bundling, which also reduces the possibility of falling accidents and improves the safety of balcony installation. In addition, during the use of the balcony, the drainage trough 6 and the movable blocking plate 7 are used to flexibly drain water, reduce the balcony load, and ensure the safety and sanitation of the balcony.
[0060] In view of current practical needs, the above-mentioned implementation mode adopted in this application is not limited to the scope of protection. Various changes made within the knowledge scope of technical personnel in this field without departing from the concept of this application still fall within the scope of protection of the present invention.
Claims
1. A high-safety split-level cantilevered balcony structure, comprising a balcony bottom plate (2) installed on the surface of a wall (001), wherein a plurality of assembled concrete slabs (1) spliced end to end are fixed on the top of the balcony bottom plate (2). Features: Both side surfaces of the assembled concrete slab (1) are provided with engaging grooves (11), and two adjacent assembled concrete slabs (1) are spliced together via an adapter (3), wherein the adapter (3) is formed by connecting two adapter units via a movable shaft, and the adapter unit comprises a vertical column (31) having a cross-section of an isosceles right triangle, and a plug-in component (33) of equal length is arranged on a side surface of the vertical column (31), and the plug-in component (33) and the engaging groove (11) have the same cross-section width, and movable sliders (32) are symmetrically arranged on the surface of the plug-in component (33), and the movable sliders (32) is connected to the end of the surface of the plug-in component (33) through an axial rod, the height of the movable slider (32) is greater than the cross-sectional width of the plug-in component (33), the inner wall of the engaging groove (11) is provided with symmetrically arranged arc grooves (5), the cross-sectional length of the arc groove (5) projected in the vertical direction is the same as the length of the movable slider (32) in the horizontal state, the interior of the engaging groove (11) is plugged with a sealing block (4), and the internal thread of the sealing block (4) is connected with a screw, and the tail end of the screw extends into the movable slider (32) in the horizontal state.
2. A high-safety split-level cantilevered balcony structure according to claim 1, Features: The waist length of the cross section of the vertical column (31) is the same as the cross section width of the assembled concrete slab (1), and the vertical column (31) is of the same height as the assembled concrete slab (1).
3. A high-security split-level cantilevered balcony structure according to claim 1, Features: The two plug-in connectors (33) of the adapter (3) are arranged horizontally in an initial state, and the two plug-in connectors (33) are arranged vertically when two assembled concrete slabs (1) are vertically spliced.
4. A high-safety split-level cantilevered balcony structure according to claim 1, Features: The cross-sectional length value of the engaging groove (11) is the sum of the cross-sectional length value of the plug-in component (33) and the thickness value of the movable slider (32), and the thickness of the sealing block (4) is the same as the thickness value of the movable slider (32) in a horizontal state.
5. According to the high-security split-level cantilevered balcony structure of claim 1, Features: The two vertical columns (31) in the adapter (3) are each provided with a drainage groove (6) with a semicircular cross section, and a movable blocking plate (7) having a diameter identical to the inner diameter of the drainage groove (6) is installed on the inner wall of the drainage groove (6) via a reset shaft.
6. A high-safety split-level cantilevered balcony structure according to claim 5, Features: The drainage groove (6) is arranged obliquely, and one end of the drainage groove (6) facing the wall (001) is higher than the other end.
7. A high-safety split-level cantilevered balcony structure according to claim 5, Features: A monitoring unit is installed on the surface of the movable blocking plate (7), and the monitoring unit includes a flow sensor for determining whether the drainage groove (6) is in a drainage state and an inclination sensor for determining the inclination state of the movable blocking plate (7), and an alarm device electrically connected to the flow sensor and the inclination sensor is installed on the surface of the wall (001).
8. A method for assembling and using a high-safety split-level cantilevered balcony structure according to any one of claims 1 to 7, It is characterized in that The following steps are included: S1, preliminary installation, connecting the assembled concrete slab (1) with built-in steel bars to the surface of the wall (001); S2, assembling, the assembled concrete panels (1) to be horizontally spliced are buckled into the engaging grooves (11) through the plug-in parts (33), and when the horizontal splicing is completed and the two assembled concrete panels (1) are vertically spliced, one of the vertical columns (31) in the adapter (3) is rotated 180 degrees to form a state in which the two plug-in parts (33) are perpendicular to each other and then plugged in; S3, locking process, after the plug-in component (33) is inserted into the fitting groove (11), the movable slider (32) is moved to rotate 90 degrees, and after sliding into the arc groove (5) in a horizontal state, the sealing block (4) is buckled on the movable slider (32) in a horizontal state, and the sealing block (4) and the movable slider (32) are locked by a screw; S4, filling the gap between the surfaces of the two vertical columns (31) in the adapter (3), and then hoisting the assembled concrete slabs (1) formed by assembling and locking the multiple assembled concrete slabs to the surface of the balcony bottom plate (2) for fixed connection; S5. In heavy rainfall weather, rainwater accumulated on the surface of the balcony floor (2) is discharged through the drainage groove (6), thereby reducing the load on the entire balcony structure.