A pipeline foundation pit support structure and construction method thereof
By using a fastening mechanism of a telescopic connector and threaded column drive slider in the pipeline foundation pit, combined with the sink drainage structure, the deformation collapse caused by the lack of support in the middle of the steel plate and the water accumulation corrosion caused by the lack of tight fit is solved, and the problem of water accumulation is achieved. The stability and drainage effect of the inner wall of the foundation pit.
Patent Information
- Application Number
- CN202411114656.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-08-14
AI Technical Summary
In the construction of pipeline foundation pits, the steel plate is prone to deform and collapse due to the lack of middle support, and the stainless steel plate does not fit closely with the inner wall of the foundation pit, resulting in water accumulation and corrosion problems on the outside.
The pipe foundation pit support structure including a baffle, a support mechanism and a fastening mechanism is adopted. The slider is driven by a retractable connecting body and threaded column to adjust the fit between the baffle and the inner wall of the foundation pit to ensure the stability of the baffle. A sink and drain pipe are also installed at the bottom of the baffle to remove the accumulated water.
It effectively avoids deformation and collapse of the baffle and corrosion of the outside water accumulation, ensuring the stability and drainage effect of the inner wall of the foundation pit.
Smart Images

Figure CN118621805B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of foundation pit support, and more specifically, to a pipeline foundation pit support structure and a construction method thereof. Background Art
[0002] In order to avoid the collapse of the inner wall of the foundation pit during the construction of the pipeline foundation pit, a support structure is set up inside the foundation pit for protection. After searching, the Chinese patent announcement number CN112392053B discloses a pipeline foundation pit support structure and a construction method thereof. Although the structure is provided with a drainage component for sucking muddy water in the foundation pit, and a support mechanism for improving the support effect of steel sheet piles is provided in the foundation pit, which is beneficial to the support effect of the sewage pipe foundation pit, the steel plate is usually long, and it is far from enough to support it only by steel sheet piles. The area in the middle of the steel plate that is not supported by the steel sheet piles will cause the middle of the steel plate to bend and deform under external pressure, which may cause the steel plate to collapse and cause safety hazards;
[0003] After searching, the Chinese patent publication number CN216948343U discloses a pipeline foundation pit support structure for soft soil areas. Although the support improves the support effect of the foundation pit support in soft soil areas, the stainless steel plate is not pressed during installation, which leads to the inability to fit tightly with the inner wall of the foundation pit, resulting in a gap between the inner wall of the foundation pit and the stainless steel plate, which causes ground water to flow into the gap and gather, easily causing water accumulation, which in turn leads to water seepage on the inner side of the support and long-term water corrosion on the outer side of the steel plate. Summary of the invention
[0004] The present invention provides a pipeline foundation pit support structure and a construction method thereof, which solves the problems in the background technology that the middle of the foundation pit steel plate lacks support and is prone to deformation and collapse, and that water is prone to accumulate on the outer side of the steel plate.
[0005] According to one aspect of the present invention, there is provided a pipeline foundation pit support structure, comprising a baffle, a supporting mechanism and a fastening mechanism, wherein the baffle is arranged around the inner edge of the foundation pit, and supporting piles are pre-buried at the inner bottom of the foundation pit, and the fastening mechanism is installed on the upper part of the supporting piles, and the supporting piles are multiple and arranged relatively at intervals, and the fastening mechanism comprises a column and a connecting seat, the column is connected to the connecting seat by a retractable connecting body, and the connecting seat is connected to the baffle, and the distance between the baffle and the column can be adjusted by controlling the extension and retraction of the connecting body, and a steel beam is welded on the top of the column, one side of the supporting mechanism is mounted on the steel beam, and the other side of the supporting mechanism is fixed to the baffle.
[0006] In this embodiment, by adjusting the expansion and contraction of the connector, the distance between the connector seat and the baffle can be controlled, that is, the force exerted by the soil inside the foundation pit on the baffle can be changed, thereby avoiding the problem of the baffle being deformed or collapsed due to excessive force.
[0007] Preferably, based on the above scheme, the connecting body includes a top block, a connecting arm and a slider, the top block is fixed on the column, one end of the connecting arm is hinged to the top block, the other end of the connecting arm is hinged to the slider, a sliding groove is provided on the inner side surface of the connecting seat, the slider is adapted to the sliding groove, a threaded column is passed through the slider, and the top of the threaded column is connected to a driving body.
[0008] In this embodiment, the threaded column is driven to rotate by the action of the driving body. When the threaded column rotates, it can drive the slider to slide on the surface of one side of the connecting seat, so that the slider can support the top block through the connecting arm, so that the connecting seat is moved backward by the reaction force, and the connecting seat can drive the baffle to fit the inner wall of the foundation pit, which is beneficial to avoid water accumulation in the gap outside the baffle and cause corrosion of the baffle. The driving body can be a manually driven wrench or an electrically driven motor.
[0009] Preferably, based on the above solution, there are two connecting arms, and the two connecting arms are respectively hinged to the top block, and the other ends of the two connecting arms are respectively connected to the two sliding blocks.
[0010] In this embodiment, in order to ensure smooth movement, each connector of the present invention includes two connecting arms. When the threaded column rotates, the threaded column engages with the thread on the slider, pulling the slider to move in the slide groove to change the angle between the connecting arm and the column, thereby changing the distance between the connecting seat and the column, and adjusting the distance between the baffle on the connecting seat and the foundation pit.
[0011] Preferably, based on the above solution, at least two groups of connectors are spaced apart on the same threaded column, and grooves for engaging the baffle are provided on both sides of the connecting seat.
[0012] In this embodiment, the baffle can be fixed by the groove adapted by the baffle, and at the same time, through the design of multiple connectors, it can be ensured that when the threaded column rotates, the upper and lower baffles are subjected to more uniform force.
[0013] Preferably, based on the above scheme, it also includes a drainage structure, which includes a water trough welded to one side of the bottom of the baffle, the top of the water trough is rotatably connected to the cover plate by a hinge, there is a gap between one side of the cover plate and the top edge of the water trough, and one side of the top of the water trough is sloped, and one side of the water trough is connected to a drain pipe.
[0014] In this embodiment, the accumulated water inside the foundation pit can flow into the water tank through the gap on one side of the top of the water tank, which is conducive to timely discharge of the accumulated water inside the foundation pit. Opening the top cover is conducive to cleaning the mud and dirt inside the water tank.
[0015] Preferably, based on the above solution, the baffles are arranged to form an even-numbered polygon, and the steel beams are fixed on the columns corresponding to the baffles on the opposite sides.
[0016] Preferably, on the basis of the above scheme, adjustment holes arranged at intervals are provided on the steel beam, and the support structure includes a support arm and an adjustment block, the adjustment block is mounted on the steel beam, connecting ear plates are provided on both sides of the adjustment block, one end of the support arm is hinged to the connecting ear plate, and the other end of the support arm is fixedly connected to the baffle.
[0017] In this embodiment, by loosening the adjusting bolt, the adjusting block can slide outside the steel beam, so that the connecting plates at one end of the supporting arms on both sides of the steel beam can be close to the middle part of the baffle, which is conducive to adjusting the supporting position of the supporting arm on the baffle.
[0018] Preferably, based on the above solution, the adjustment block and the steel beam are fixed by bolts passing through the adjustment hole.
[0019] The present invention also provides a pipeline foundation pit support construction method, comprising the following steps:
[0020] Step A1, excavating a pre-buried pit for burying support piles at the bottom of the foundation pit, burying fixed support piles, fixing the bottom of the column to the support piles, and ensuring that the spacing between adjacent columns is the width of the baffle during installation;
[0021] Step A2, insert the baffle into the grooves on both sides of the connection seat, bury the water tank at the bottom of one side of the baffle into the ground, make the top of the water tank lower than the horizontal plane of the bottom of the foundation pit, and connect the drainage pipe connected to the inside of the water tank to the external mud pump;
[0022] Step A3, controlling the expansion and contraction of the connector, adjusting the distance between the baffle and the inner edge of the foundation pit, controlling the external force acting on the baffle, and after the adjustment is completed, welding adjacent baffles and welding multiple ribs at intervals from top to bottom.
[0023] Preferably, based on the above solution, after the adjustment of step A3 is completed, the following is further included:
[0024] A steel beam is installed between the columns on opposite sides, an adjustment block is sleeved on the steel beam, one end of the support arm is fixed to the baffle, and the adjustment block is pushed to move on the steel beam, so that the support arm, the baffle and the steel beam form a triangular stable support.
[0025] A pipeline foundation pit support structure of the present invention, through the rotation of a threaded column, the threaded column can drive a slider to slide on the surface of one side of the base while rotating, so that the slider can support the top block through the connecting arm, so that the base is moved backward by the reaction force, and the base can drive the baffle to fit with the inner wall of the foundation pit, which is beneficial to avoid water accumulation in the gap outside the baffle.
[0026] A pipeline foundation pit supporting structure of the present invention, when being installed, after the two ends of the steel beam are fixed, the adjusting bolts are loosened to allow the adjusting block to slide outside the steel beam, so that the connecting plates at one end of the supporting arms on both sides of the steel beam can be connected and fixed to the portion of the baffle near the middle, and then the adjusting block is fixed to the hole groove on the surface of the steel beam by the adjusting bolts, so that the middle part of the baffle can be supported by the supporting arms on both sides of the steel beam, which is beneficial to prevent the middle part of the baffle from being squeezed by external force and causing deformation and collapse.
[0027] On the other hand, the present invention provides ground piles at the bottom of the column, and the support is pre-buried in the ground during installation, which is beneficial to improving the stability and firmness of the column. At the same time, by providing a support ring on the outside of the support, it is beneficial to improve the supporting surface of the ground pile underground, thereby helping to further improve the firmness of the ground pile.
[0028] This solves the problem of the lack of support in the middle of the foundation pit steel plate causing easy deformation and collapse, as well as the problem of water accumulation on the outside of the steel plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0030] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0031] Figure 2 It is a structural schematic diagram of the fastening mechanism of the present invention;
[0032] Figure 3 This is a schematic diagram of the cross-sectional structure of the connecting seat of the present invention;
[0033] Figure 4 It is a structural schematic diagram of the drainage structure of the present invention;
[0034] Figure 5 It is a schematic diagram of the supporting mechanism structure of the present invention;
[0035] Figure 6 This is a schematic diagram of the connecting arm structure of the present invention;
[0036] Figure 7 It is a schematic diagram of the top view structure of the present invention.
[0037] Description of Figure Numbers:
[0038] In the figure, 1. baffle; 2. supporting pile; 201. ground pile; 202. supporting ring; 3. drainage structure; 301. gutter; 302. hinge; 303. cover plate; 304. drain pipe; 4. supporting mechanism; 401. steel beam; 402. adjusting block; 403. adjusting bolt; 404. supporting arm; 405. connecting plate; 5. fastening mechanism; 501. connecting seat; 502. column; 503. wrench; 504. connecting rod; 505. base; 506. connecting arm; 507. top block; 508. slider; 509. threaded column; 6. rib plate. DETAILED DESCRIPTION
[0039] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0040] It should be understood that when used in this specification and the appended claims, the term "comprising" indicates the presence of described features, integers, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or collections.
[0041] In order to simplify the drawings, only the parts related to the present invention are schematically shown in each figure, and they do not represent the actual structure of the product. In addition, in order to simplify the drawings and facilitate understanding, in some figures, only one of the parts with the same structure or function is schematically drawn or marked. In this article, "one" not only means "only one", but also means "more than one".
[0042] It should be further understood that the term “and / or” used in the specification and appended claims refers to any combination and all possible combinations of one or more of the associated listed items, and includes these combinations.
[0043] In the embodiments shown in the drawings, the indications of directions (such as up, down, left, right, front and back) used to explain the structure and movement of the various components of the present invention are not absolute but relative. These descriptions are appropriate when these components are in the positions shown in the drawings. If the descriptions of the positions of these components change, the indications of these directions also change accordingly.
[0044] In addition, in the description of the present application, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.
[0045] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the specific implementation methods of the present invention will be described below with reference to the accompanying drawings. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings and other implementation methods can be obtained based on these drawings without creative work.
[0046] See also Figure 1 , and combined with Figure 2 and Figure 3 As shown, a pipeline foundation pit support structure of the present invention includes a baffle 1, a supporting mechanism 4 and a fastening mechanism 5. The baffle 1 is arranged around the inner edge side of the foundation pit, and a supporting pile 2 is pre-buried at the inner bottom of the foundation pit. The fastening mechanism 5 is installed on the upper part of the supporting pile 2. The supporting pile 2 is multiple and arranged relatively at intervals. The fastening mechanism 5 includes a column 502 and a connecting seat 501. The column 502 is connected to the connecting seat 501 through a retractable connecting body. The connecting seat 501 is connected to the baffle 1. The distance between the baffle 1 and the column 502 can be adjusted by controlling the telescopic connection of the connecting body. A steel beam 401 is welded on the top of the column 502. One side of the supporting mechanism 4 is mounted on the steel beam 401, and the other side of the supporting mechanism 4 is fixed to the baffle 1.
[0047] When in use, the distance between the connecting seat 501 and the baffle 1 can be controlled by adjusting the extension and contraction of the connecting body, that is, the force exerted by the soil inside the foundation pit on the baffle 1 can be changed, thereby avoiding the problem of the baffle 1 being subjected to excessive force and causing it to deform or collapse. At the same time, combined with the supporting force of the steel beam 401, after being adjusted to a suitable position through the connecting body, the steel beams 401 between the baffles 1 on opposite sides can interact with each other to form an opposite force, thereby forming a stable support and ensuring the stability of the baffle 1.
[0048] Specifically, the connector of the present invention includes a top block 507, a connecting arm 506 and a slider 508. The top block 507 is fixed on the column 502. One end of the connecting arm 506 is hinged to the top block 507, and the other end of the connecting arm 506 is hinged to the slider 508. The inner side surface of the connecting seat 501 is provided with a slide groove, and the slider 508 is adapted to the slide groove. The slider 508 is penetrated with a threaded column 509, and the top of the threaded column 509 is connected to the driving body. For the specific structure, please refer to Figure 6 shown.
[0049] Among them, the driving body can be a wrench 503 or a motor. When the driving body applies a force on the threaded column 509, it drives the threaded column 509 to rotate, thereby utilizing the threaded force between the threaded column 509 and the slider 508 to drive the slider 508 to slide up and down on the slide groove on the connecting seat 501. Since the top block 507 and the column 502 are fixed to each other, and the connecting arm 506 is hinged to the top block 507, when the slider 508 moves up and down, the angle between the connecting arm 506 and the column 502 will change, thereby changing the distance between the connecting seat 501 and the column 502, driving the baffle 1 installed on the connecting seat 501 to move relative to each other, so as to change the force between the baffle 1 and the foundation pit, and avoid damage to the baffle 1 caused by excessive force.
[0050] In order to further improve the stability of the spacing adjustment between the baffle 1 and the column 502, each connector of the present invention has two connecting arms 506, and the two connecting arms 506 are respectively hinged to the top block 507, the top plate is welded to the column 502, and the other ends of the two connecting arms 506 are respectively connected to two sliders 508, and the threads in the two sliders 508 are designed to be opposite to each other, so that when the threaded column 509 rotates, the two sliders 508 move in opposite directions, so as to quickly adjust the angle between the baffle 1 and the column 502 and ensure the stability of its movement.
[0051] like Figure 2 As shown, at least two groups of spaced-apart connectors are spaced-apart on the same threaded column 509 of the present invention, and the number of connectors can be set according to the height of the baffle 1. Grooves for the baffle 1 to engage are provided on both sides of the connecting seat 501 to facilitate quick installation of the baffle 1.
[0052] In this embodiment, the baffle 1 can be fixed by the groove adapted by the baffle 1. At the same time, through the design of multiple connectors, it can be ensured that when the threaded column 509 rotates, the upper and lower baffles 1 are subjected to more uniform force.
[0053] In order to drain the accumulated water in the foundation pit in time, Figure 4 As shown, the present invention also includes a drainage structure 3, which includes a water trough 301 welded to one side of the bottom of the baffle 1, and the top of the water trough 301 is rotatably connected to the cover 303 through a hinge 302. There is a gap between one side of the cover 303 and the top edge of the water trough 301, and one side of the top of the water trough 301 is sloped, and one side of the water trough 301 is connected to the drain pipe 304.
[0054] When in use, the accumulated water inside the foundation pit can flow into the water tank 301 through the gap on one side of the top of the water tank 301, which is conducive to the timely discharge of the accumulated water inside the foundation pit through the drain pipe 304 and the mud pump on the ground. By opening the top cover 303, it is convenient to clean the mud inside the water tank 301.
[0055] The baffle 1 of the present invention is arranged to form an even polygon, and the steel beam 401 is fixed on the corresponding column 502 of the baffle 1 on the opposite side. Figure 1 and Figure 7 As shown, the baffle 1 of the present invention forms a foundation pit with a quadrilateral cross-section, there are three steel beams 401 and six supporting piles 2.
[0056] It should be noted that the present invention pre-buries ground piles 201 on one side of the baffle 1 close to the center of the foundation pit, and the ground piles 201 are connected to the support piles 2 via the support rings 202 to stabilize the support piles 2, so that the columns 502 and the foundation form an integrated stable structure.
[0057] like Figure 5 As shown, the steel beam 401 of the present invention is provided with adjustment holes arranged at intervals, and the supporting structure includes a support arm 404 and an adjustment block 402, the adjustment block 402 is mounted on the steel beam 401, and connecting ear plates are provided on both sides of the adjustment block 402, one end of the support arm 404 is hinged to the connecting ear plate, and the other end of the support arm 404 is connected to the baffle 1.
[0058] In this embodiment, by loosening the adjusting bolt 403, the adjusting block 402 can slide outside the steel beam 401, so that the connecting plate 405 at one end of the support arm 404 on both sides of the steel beam 401 can be close to the middle part of the baffle 1, which is conducive to adjusting the supporting position of the support arm 404 on the baffle 1.
[0059] It is worth noting that the adjustment block 402 of the present invention is fixed to the steel beam 401 by bolts passing through the adjustment holes, that is, the angle between the support arm 404 and the steel beam 401 can be adjusted by tightening the bolts.
[0060] Furthermore, the present invention also provides a plurality of elongated adjustment holes at intervals in the height direction of the column 502 , and a retractable connecting rod 504 is passed through the elongated adjustment hole, and one end of the connecting rod 504 is connected to the connecting seat 501 .
[0061] When the threaded column 509 rotates, the threaded column 509 can drive the slider 508 to slide on the surface of one side of the base 505, so that the slider 508 can support the top block 507 through the connecting arm 506, so that the base 505 will move backward due to the reaction force, and the base 505 can drive the baffle 1 to fit against the inner wall of the foundation pit, which is beneficial to avoid water accumulation in the gap outside the baffle 1.
[0062] The present invention also provides a pipeline foundation pit support construction method, comprising the following steps:
[0063] Step A1, excavating a pre-buried pit for burying the support piles 2 at the bottom of the foundation pit, burying the fixed support piles 2, fixing the bottom of the column 502 to the support piles 2, and ensuring that the spacing between adjacent columns 502 is the width of the baffle 1 during installation;
[0064] Step A2, insert the baffle plate 1 into the grooves on both sides of the connection seat 501, bury the water tank 301 at the bottom of one side of the baffle plate 1 into the ground, make the top of the water tank 301 lower than the horizontal plane of the bottom of the foundation pit, and connect the drainage pipe 304 connected to the inside of the water tank 301 to the external mud pump;
[0065] Step A3, control the expansion and contraction of the connector, adjust the distance between the baffle 1 and the inner edge surface of the foundation pit, control the external force acting on the baffle 1, and after the adjustment is completed, weld adjacent baffles 1 and weld multiple ribs 66 from top to bottom.
[0066] Furthermore, in order to ensure the stability of the connection between the baffles 1, after the adjustment in step A3 is completed, the present invention further includes:
[0067] A steel beam 401 is installed between the columns 502 on the opposite sides, an adjustment block 402 is sleeved on the steel beam 401, and one end of the support arm 404 is fixed to the baffle 1, pushing the adjustment block 402 to move on the steel beam 401, so that the support arm 404, the baffle 1 and the steel beam 401 form a triangular stable support.
[0068] A pipeline foundation pit support structure of the present invention, through the rotation of the threaded column 509, the threaded column 509 can drive the slider 508 to slide on the surface of one side of the base 505 while rotating, so that the slider 508 can support the top block 507 through the connecting arm 506, so that the base 505 will move backward due to the reaction force, and then the base 505 can drive the baffle 1 to fit with the inner wall of the foundation pit, which is beneficial to avoid water accumulation in the gap outside the baffle 1.
[0069] A pipeline foundation pit support structure of the present invention, when being installed, after the two ends of a steel beam 401 are fixed, the adjusting bolts 403 are loosened to allow the adjusting block 402 to slide outside the steel beam 401, so that the connecting plates 405 at one end of the supporting arms 404 on both sides of the steel beam 401 can be connected and fixed to the portion of the baffle 1 near the middle, and then the adjusting block 402 is fixed to the hole groove on the surface of the steel beam 401 by the adjusting bolts 403, so that the middle part of the baffle 1 can be supported by the supporting arms 404 on both sides of the steel beam 401, which is beneficial to prevent the middle part of the baffle 1 from being squeezed by external force and causing deformation and collapse.
[0070] On the other hand, the present invention provides ground piles 201 at the bottom of the columns 502. When the support is installed, the ground piles 201 are pre-buried underground, which helps to improve the stability and firmness of the columns 502. At the same time, by providing a support ring 202 on the outside of the support, the supporting surface of the ground piles 201 underground is improved, thereby helping to further improve the firmness of the ground piles 201.
[0071] This solves the problem of the lack of support in the middle of the foundation pit steel plate causing easy deformation and collapse, as well as the problem of water accumulation on the outside of the steel plate.
[0072] Finally, the method of the present application is only a preferred implementation scheme and is not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A pipeline foundation pit support structure, characterized in that: It includes a baffle, a supporting mechanism and a fastening mechanism, the baffle is arranged around the inner edge of the foundation pit, and supporting piles are pre-buried at the inner bottom of the foundation pit. The fastening mechanism is installed on the upper part of the supporting piles. There are multiple supporting piles and they are arranged relatively at intervals. The fastening mechanism includes a column and a connecting seat. The column is connected to the connecting seat through a retractable connecting body, and the connecting seat is connected to the baffle. The distance between the baffle and the column can be adjusted by controlling the extension and retraction of the connecting body. A steel beam is welded on the top of the column, one side of the supporting mechanism is mounted on the steel beam, and the other side of the supporting mechanism is fixed to the baffle.
2. A pipeline foundation pit support structure according to claim 1, characterized in that: The connecting body includes a top block, a connecting arm and a slider, the top block is fixed on the column, one end of the connecting arm is hinged to the top block, and the other end of the connecting arm is hinged to the slider, the inner side surface of the connecting seat is provided with a slide groove, the slider is adapted to the slide groove, a threaded column is passed through the slider, and the top of the threaded column is connected to a driving body.
3. A pipeline foundation pit support structure as claimed in claim 2, characterized in that: There are two connecting arms, and the two connecting arms are respectively hinged to the top blocks, and the other ends of the two connecting arms are respectively connected to the two sliding blocks.
4. A pipeline foundation pit support structure as claimed in claim 2, characterized in that: At least two groups of connectors are arranged at intervals on the same threaded column, and grooves for the baffle to engage are arranged on both sides of the connecting seat.
5. A pipeline foundation pit support structure as claimed in claim 1, characterized in that: It also includes a drainage structure, which includes a water trough welded to one side of the bottom of the baffle, the top of the water trough is rotatably connected to the cover plate by a hinge, there is a gap between one side of the cover plate and the top edge of the water trough, and one side of the top of the water trough is sloped, and one side of the water trough is connected to a drainage pipe.
6. A pipeline foundation pit support structure according to claim 1, characterized in that: The baffles are arranged to form an even-numbered polygon, and the steel beams are fixed on the columns corresponding to the baffles on the opposite sides.
7. A pipeline foundation pit support structure as claimed in claim 6, characterized in that: The steel beam is provided with adjustment holes arranged at intervals, and the support mechanism includes a support arm and an adjustment block, the adjustment block is mounted on the steel beam, connecting ear plates are provided on both sides of the adjustment block, one end of the support arm is hinged to the connecting ear plate, and the other end of the support arm is fixed to the baffle.
8. A pipeline foundation pit support structure as claimed in claim 7, characterized in that: The adjusting block and the steel beam are fixed to each other by bolts passing through the adjusting hole.
9. A construction method for a pipeline foundation pit support structure as claimed in claim 7, characterized in that: The following steps are involved: Step A1, excavating a pre-buried pit for burying support piles at the bottom of the foundation pit, burying fixed support piles, fixing the bottom of the column to the support piles, and ensuring that the spacing between adjacent columns is the width of the baffle during installation; Step A2, insert the baffle into the grooves on both sides of the connection seat, bury the water tank at the bottom of one side of the baffle into the ground, make the top of the water tank lower than the horizontal plane of the bottom of the foundation pit, and connect the drainage pipe connected to the inside of the water tank to the external mud pump; Step A3, controlling the expansion and contraction of the connector, adjusting the distance between the baffle and the inner edge of the foundation pit, controlling the external force acting on the baffle, and after the adjustment is completed, welding adjacent baffles and welding multiple ribs at intervals from top to bottom.
10. The construction method of a pipeline foundation pit support structure according to claim 9, characterized in that: After the adjustment in step A3 is completed, the following steps are further included: A steel beam is installed between the columns on opposite sides, an adjustment block is sleeved on the steel beam, and one end of the support arm is fixed to the baffle plate, pushing the adjustment block to move on the steel beam, so that the support arm, the baffle plate and the steel beam form a triangular stable support.