A digital engineering management method and system based on BIM technology
Through BIM technology and Lagrangian multiplication calculation, real-time adjustment of project resource allocation and optimization of equipment management are solved, and the problems of resource allocation lag and equipment management defects in digital engineering management are improved, and project management efficiency and equipment life are improved.
Patent Information
- Application Number
- CN202411117805.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-08-15
AI Technical Summary
The existing digital engineering management methods are difficult to reflect project changes in real time, resulting in lagging resource allocation decisions, dispersed information lead to high complexity and error rates, and equipment management lacks effective performance decay monitoring, which increases project cost and time risks.
Using a digital engineering management method based on BIM technology, by extracting resource requirements and information in real time from the BIM model, adjusting resource allocation using Lagrangian multiplier calculation, iterative optimization, simulation and analysis of resource configuration impact, and monitoring based on equipment performance attenuation Data development and maintenance plan.
It realizes targeted and adaptive resource allocation, ensures balanced resource allocation, reduces the risks of waste and delays, improves project management efficiency and prediction accuracy, and extends the service life of equipment.
Smart Images

Figure CN118644056B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of engineering project management, and in particular to a digital engineering management method and system based on BIM technology. Background Art
[0002] Engineering project management involves the overall management and monitoring of engineering projects to ensure that tasks at each stage are completed smoothly according to established plans, specifications and standards. By defining project goals, organizing project resources, executing project plans, monitoring project progress and evaluating project performance, it is possible to reasonably coordinate personnel, resources, time and funds to achieve project goals and requirements, and facilitate timely adjustment of management strategies and methods.
[0003] Among them, the digital engineering management method involves the use of digital technology to optimize the engineering project management process. The purpose is to improve the transparency and efficiency of project management by providing real-time data, enhancing decision support and improving communication. Digital methods can track project progress more accurately, make project information more integrated and automated, and provide project managers with more accurate and immediate information processing capabilities.
[0004] Although existing digital engineering management methods rely on periodic data updates and processing, it is difficult to fully reflect project changes in real time, resulting in delayed resource allocation decisions and inability to respond to emergencies immediately. In addition, project information is in a relatively scattered state, which increases the complexity and error rate of data processing. This fragmented information management often leads to uneven resource utilization and inefficiency, and may cause cost increases and project delays. In terms of equipment management, the lack of effective performance degradation monitoring and maintenance plans often causes equipment failures or premature replacements, increasing the operating costs and time risks of the project. Summary of the invention
[0005] The purpose of the present invention is to solve the shortcomings of the prior art and to propose a digital engineering management method and system based on BIM technology.
[0006] In order to achieve the above object, the present invention adopts the following technical solution: a digital engineering management method based on BIM technology, comprising the following steps:
[0007] S1: Extract the resource requirements and current resource information of the engineering project from the BIM model in real time, identify the insufficient or excessive problems in resource allocation, apply Lagrange multipliers to calculate and adjust resource allocation, match project requirements, and generate an initial resource allocation model;
[0008] S2: Using the initial resource allocation model, iterative adjustments are made based on the current progress and resource consumption of the engineering projects provided in the BIM model until resource allocation is balanced in each engineering project, generating optimized resource information;
[0009] S3: Simulate and analyze the project progress through optimized resource information, analyze the impact of current resource configuration on the project progress, evaluate the effect of each resource configuration, and generate resource allocation evaluation results;
[0010] S4: Based on the resource allocation assessment results, analyze the usage history of key construction equipment in the project and its performance degradation monitoring data. According to the data and the progress of the project, select the maintenance or replacement time of the equipment, and sort them according to the maintenance urgency to obtain the project equipment management information.
[0011] As a further solution of the present invention, the acquisition step of identifying the problem of insufficient or excessive resource allocation is specifically:
[0012] S111: Extract the resource requirements and current resource information of the project from the BIM model in real time using the formula:
[0013] and ;
[0014] Calculate the total amount of demand for each type of resource and the current available ;
[0015] in, represents the demand of the jth project for the i-th type of resources, is the weight of the jth item, represents the supply of the i-th resource from the k-th source, is the reliability coefficient of the kth source, and Respectively represent the upper limits of the number of projects and the number of resource sources;
[0016] S112: Based on the total amount of each type of resource required and the current available , using the formula:
[0017] ;
[0018] Calculate the difference between the demand and supply of the project and get the difference between the demand and supply of the i-th resource ;
[0019] in, is the urgency coefficient of resource category i;
[0020] S113: Based on the difference between the demand and supply of the i-th resource , using the formula:
[0021] ;
[0022] Get the absolute value of the total difference .
[0023] As a further solution of the present invention, the step of obtaining the initial resource allocation model is specifically as follows:
[0024] S121: According to the absolute value of the total difference , using the formula:
[0025] ;
[0026] Get the initial value of the Lagrange multiplier ;
[0027] in, Represents a small positive number that prevents division by zero, is the adjustment coefficient, is the secondary adjustment coefficient;
[0028] S122: Using the initial value of the Lagrange multiplier The allocation for each resource category is adjusted using the formula:
[0029] ;
[0030] Calculate the new allocation of each resource and get the adjusted available amount of the i-th resource ;
[0031] in, is the difference weighting factor;
[0032] S123: Based on the adjusted available amount of the i-th resource , construct the initial resource allocation model, using the formula:
[0033] ;
[0034] Calculate the total value of resource allocation under the current parameter settings ;
[0035] in, represents the value coefficient of the i-th type of resources, Represents the cost coefficient of the resource.
[0036] As a further solution of the present invention, the step of obtaining the optimized resource information is specifically as follows:
[0037] S211: Total value allocated according to the resource , using the formula:
[0038] ;
[0039] Calculate the current time The remaining amount of resources ;
[0040] in, Indicates the current time The resource consumption, is the secondary adjustment coefficient, is the square root adjustment coefficient;
[0041] S212: According to the current time The remaining amount of resources And the current project progress, using the formula:
[0042] ;
[0043] Compute resource deviation ratio , get optimized resource information;
[0044] in, Indicates the amount of resources that should be consumed according to the project progress. is the resource deviation adjustment factor.
[0045] As a further solution of the present invention, the step of obtaining the resource allocation evaluation result is specifically:
[0046] S311: Based on the deviation ratio of the resource , using the formula:
[0047] ;
[0048] Calculating simulation time Project progress status ;
[0049] in, For resource availability, is the weight of resource availability, is the sensitivity coefficient of simulation progress, To adjust The nonlinear coefficient of the effect;
[0050] S312: According to the simulation time Project progress status , using the formula:
[0051] ;
[0052] Calculate each time Resource allocation ;
[0053] in, To target project progress, is the sensitivity coefficient of the assessment;
[0054] S313: According to each time Resource allocation , using the formula:
[0055] ;
[0056] Integrate evaluation information of all resource allocations , and obtain the resource allocation evaluation result.
[0057] As a further solution of the present invention, the step of obtaining the maintenance or replacement time of the selected equipment is specifically as follows:
[0058] S411: Collect the usage history and performance degradation monitoring data of key construction equipment from the project data, and evaluate the allocation of all resources according to the evaluation information. , using the formula:
[0059] ;
[0060] Calculate engineering equipment in time Performance degradation metric under ;
[0061] in, represents a measure of the degradation of device performance, Indicates the cumulative usage time of the device. Indicates the use intensity adjustment coefficient, represents the normalization coefficient;
[0062] S412: According to the engineering equipment at time Performance degradation metric under , using the formula:
[0063] ;
[0064] Calculate the time interval for the next maintenance or replacement of engineering equipment ;
[0065] in, represents the performance degradation threshold, A tolerance factor that indicates performance degradation.
[0066] As a further solution of the present invention, the step of obtaining the engineering equipment management information is specifically as follows:
[0067] S421: according to the time interval for the next maintenance or replacement of the engineering equipment , using the formula:
[0068] ;
[0069] Calculating the Engineering Equipment Maintenance Urgency Index ;
[0070] in, Indicates the operating time of the equipment since the last maintenance. represents the critical running time, Indicates adjustment right The sensitivity of the impact, Indicates the time buffer value, represents the base of natural logarithms;
[0071] S422: According to the engineering equipment maintenance emergency index , using the formula:
[0072] ;
[0073] Determine the maintenance priority of engineering equipment ;
[0074] in, represents the adjustment factor, Indicates the offset;
[0075] S423: According to the maintenance priority of the engineering equipment , using the formula:
[0076] ;
[0077] Get the maintenance demand index of the entire equipment pool at a given point in time , get engineering equipment management information;
[0078] in, Indicates the progress of the project. Indicates the device The attribute value of Represents the weight factor.
[0079] A digital engineering management system based on BIM technology, the digital engineering management system based on BIM technology is used to execute the digital engineering management method based on BIM technology, the system comprises:
[0080] The demand analysis module extracts the resource demand and existing resource status of each project from BIM data, analyzes areas of insufficient or excessive resources, uses Lagrange multipliers to adjust resource quantities, and generates resource demand and available resource data;
[0081] The resource allocation module uses the resource demand and available resource data to quantitatively adjust each type of resource, optimize resource allocation efficiency, and generate an initial resource allocation model;
[0082] The real-time adjustment module monitors the progress of the engineering project and the resource consumption status, dynamically adjusts the resource allocation based on the initial resource allocation model, updates the resource configuration in real time, and generates optimized resource information;
[0083] The schedule simulation module uses the optimized resource information to perform schedule simulation of the engineering project, analyze the impact of various resource configurations on the project schedule, evaluate the efficiency of the resource configuration plan, and generate resource allocation evaluation results;
[0084] The equipment management module analyzes the usage data and performance monitoring records of key equipment in the project based on the resource allocation evaluation results, formulates equipment maintenance or replacement plans, and generates project equipment management information.
[0085] Compared with the prior art, the advantages and positive effects of the present invention are:
[0086] In the present invention, resource allocation is adjusted by Lagrange multipliers, making resource allocation more targeted and adaptable, and dynamically matching changing project requirements. In addition, the iterative adjustment process ensures that resource allocation is balanced in various engineering projects, reducing the risk of resource waste and project delays. By simulating and analyzing the impact of current resource allocation on project progress, the accuracy of prediction and support for decision-making are enhanced, making project management more efficient. Finally, the maintenance or replacement plan for key construction equipment is formulated to ensure the optimal performance of the equipment and extend its service life. BRIEF DESCRIPTION OF THE DRAWINGS
[0087] Figure 1 It is a schematic diagram of the workflow of the present invention;
[0088] Figure 2 A flow chart of the steps for obtaining the method of identifying under- or over-allocation of resources for the present invention;
[0089] Figure 3 A flowchart of the steps for obtaining the initial resource allocation model of the present invention;
[0090] Figure 4 A flow chart of the steps for obtaining resource information optimized for the present invention;
[0091] Figure 5A flowchart of the steps for obtaining resource allocation evaluation results of the present invention;
[0092] Figure 6 A flow chart of the steps for obtaining the maintenance or replacement time of the selected equipment of the present invention;
[0093] Figure 7 The figure is a flow chart of the steps for obtaining engineering equipment management information of the present invention. DETAILED DESCRIPTION
[0094] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0095] In the description of the present invention, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, in the description of the present invention, "multiple" means two or more, unless otherwise clearly and specifically defined.
[0096] See also Figure 1 The present invention provides a technical solution: a digital engineering management method based on BIM technology, comprising the following steps:
[0097] S1: Extract the resource requirements and current resource information of the engineering project from the BIM model in real time, identify the insufficient or excessive problems in resource allocation, apply Lagrange multipliers to calculate and adjust resource allocation, match project requirements, and generate an initial resource allocation model;
[0098] S2: Using the initial resource allocation model, iterative adjustments are made based on the current progress and resource consumption of the engineering projects provided in the BIM model until resource allocation is balanced in each engineering project, generating optimized resource information;
[0099] S3: Simulate and analyze the project progress through optimized resource information, analyze the impact of current resource configuration on the project progress, evaluate the effect of each resource configuration, and generate resource allocation evaluation results;
[0100] S4: Based on the resource allocation assessment results, analyze the usage history of key construction equipment in the project and its performance degradation monitoring data, select the maintenance or replacement time of the equipment based on the data and the progress of the project, and sort them according to the maintenance urgency to obtain the project equipment management information;
[0101] The initial resource allocation model includes the human resource allocation, material allocation plan and equipment utilization schedule of the engineering project. The optimized resource information includes the adjusted human resource distribution, material utilization adjustment measures and equipment operation efficiency data. The resource allocation evaluation results include the cost-benefit analysis, time saving estimation and risk analysis of the resource allocation optimization plan. The engineering equipment management information includes the optimization plan of the equipment maintenance cycle, the priority ranking of equipment replacement and the prediction of equipment performance degradation.
[0102] See also Figure 2 ,The acquisition steps to identify the problem of insufficient or excessive resource allocation are as follows:
[0103] S111: Extract the resource requirements and current resource information of the project from the BIM model in real time using the formula:
[0104] and ;
[0105] Calculate the total amount of demand for each type of resource and the current available ;
[0106] in, represents the demand of the jth project for the i-th type of resources, is the weight of the jth project, which affects the calculation of resource demand. represents the supply of the i-th resource from the k-th source, is the reliability coefficient of the kth source, adjusting the weight of the supply, and Respectively represent the upper limits of the number of projects and the number of resource sources;
[0107] S112: Based on the total demand for each type of resource and the current available , using the formula:
[0108] ;
[0109] Calculate the difference between the demand and supply of the project and get the difference between the demand and supply of the i-th resource ;
[0110] in, is the urgency coefficient of resource category i, which is used to adjust the sensitivity in the variance calculation. This coefficient considers the impact of the criticality of the resource in the allocation priority;
[0111] S113: Based on the difference between the demand and supply of the i-th resource , using the formula:
[0112] ;
[0113] Get the absolute value of the total difference ;
[0114] Among them, the larger A value of indicates a resource allocation problem.
[0115] The calculation process is as follows:
[0116] The baseline value is set to 50 to distinguish whether resources are in excess or insufficient. If it is greater than 50, it is considered that there is a serious problem in resource allocation; If it is less than or equal to 50, the resource allocation is considered reasonable.
[0117] For the formula:
[0118] and ;
[0119] Assumptions: Projects 1 and 2 require 100 and 150 units of resource 1 respectively.
[0120] Project Weight .
[0121] Resource source 1 provides 200 units, source 2 provides 100 units, and source 3 provides 50 units.
[0122] Reliability coefficient .
[0123] Total computing resource requirements :
[0124] ;
[0125] Compute the current amount of available resources :
[0126] ;
[0127] For the formula:
[0128] ;
[0129] Example and derivation assuming urgency coefficient .
[0130] Computing resource differences :
[0131] ;
[0132] For the formula:
[0133] ;
[0134] Summarize resource differences:
[0135] ;
[0136] Due to the calculated The value is 40, which is lower than the benchmark value , indicating that the resource allocation is basically reasonable, and there is no serious problem of insufficient or excessive resources. Therefore, the resource allocation effect is good and can meet the needs of the project without causing obvious waste or shortage.
[0137] See also Figure 3 , the specific steps for obtaining the initial resource allocation model are:
[0138] S121: Based on the absolute value of the total difference , using the formula:
[0139] ;
[0140] Get the initial value of the Lagrange multiplier ;
[0141] in, Represents a small positive number that prevents division by zero, is the adjustment factor used to maintain the calculation baseline, is the secondary adjustment coefficient;
[0142] S122: Using initial values of Lagrange multipliers The allocation for each resource category is adjusted using the formula:
[0143] ;
[0144] Calculate the new allocation of each resource and get the adjusted available amount of the i-th resource ;
[0145] in, A weighting factor for differences that increases adjustment sensitivity to extreme differences;
[0146] S123: Based on the adjusted available quantity of the i-th resource , construct the initial resource allocation model, using the formula:
[0147] ;
[0148] Calculate the total value of resource allocation under the current parameter settings ;
[0149] in, Represents the value coefficient of the i-th type of resource, which is used to evaluate the importance of the resource in the project. Represents the cost coefficient of a resource and is used to adjust the cost-benefit balance of resource allocation.
[0150] The calculation process is as follows:
[0151] For the formula:
[0152] ;
[0153] Assumed parameters: , , ;
[0154] ;
[0155] The initial value of the Lagrange multiplier is shown, which will be used to adjust the resource allocation to balance resource surplus and shortage.
[0156] For the formula:
[0157] ;
[0158] Assumed parameters: ;
[0159] ;
[0160] The results show a slight decrease in the adjusted resource volume, reflecting a small adjustment to the resource surplus.
[0161] For the formula:
[0162] ;
[0163] Assumed parameters: .
[0164] ;
[0165] The ideal resource volume is assumed to be , the final calculation result , which is slightly lower than the benchmark value, indicating that the resource allocation is close to the ideal state, but slightly insufficient. After adjustment using the Lagrange multiplier, the resource allocation is close to optimization, but may still need fine-tuning to fully meet the project needs.
[0166] See also Figure 4 , the steps for obtaining optimized resource information are as follows:
[0167] S211: Total value based on resource allocation , using the formula:
[0168] ;
[0169] Calculate the current time The remaining amount of resources ;
[0170] in, Indicates the current time Resource consumption, obtain data from real-time monitoring, is the secondary adjustment coefficient, which is used to reflect the impact of accelerated resource consumption. It is the square root adjustment coefficient, which is used to smooth the impact of sudden consumption increase;
[0171] S212: According to the current time The remaining amount of resources And the current project progress, using the formula:
[0172] ;
[0173] Compute resource deviation ratio , get optimized resource information;
[0174] in, Indicates the amount of resources that should be consumed according to the project progress, calculated based on the project plan and real-time progress. is the resource deviation adjustment factor.
[0175] The calculation process is as follows:
[0176] For the formula:
[0177] ;
[0178] Assumed parameters: .
[0179] Assuming the current time Resource consumption under For 40:
[0180] ;
[0181] ;
[0182] ;
[0183] Indicates the remaining amount of current resources under given parameters and consumption.
[0184] For the formula:
[0185] ;
[0186] Assumed parameters: .
[0187] ;
[0188] ;
[0189] ;
[0190] ;
[0191] result Indicates the deviation ratio of current resource consumption relative to the expected value.
[0192] Assume that the baseline value is 300, which indicates the ideal resource consumption. Compared with , the display resources are saved, but close to reasonable consumption. A positive value of indicates that resource consumption is slightly less than planned and that slight adjustments may be needed to ensure full utilization of resources.
[0193] See also Figure 5 , the specific steps for obtaining the resource allocation evaluation results are:
[0194] S311: Deviation ratio according to resources , using the formula:
[0195] ;
[0196] Calculating simulation time Project progress status ;
[0197] in, For resource availability, is the weight of resource availability, is the sensitivity coefficient of simulation progress, To adjust The nonlinear coefficient of the effect;
[0198] S312: According to simulation time Project progress status , using the formula:
[0199] ;
[0200] Calculate each time Resource allocation ;
[0201] in, To target project progress, is the sensitivity coefficient of the assessment;
[0202] S313: According to each time Resource allocation , using the formula:
[0203] ;
[0204] Integrate evaluation information of all resource allocations , and obtain the resource allocation evaluation result.
[0205] The calculation process is as follows;
[0206] Assumed parameters: , , , .
[0207] For the formula:
[0208] ;
[0209] result:
[0210] ;
[0211] ;
[0212] ;
[0213] Assumed parameters: , .
[0214] For the formula:
[0215] ;
[0216] result:
[0217] ;
[0218] ;
[0219] ;
[0220] For the formula:
[0221] ;
[0222] Since there is only one time, .
[0223] Assume the base value is Indicates the ideal resource evaluation effect. Calculation results Compare this result with the baseline value ,It can be seen that the resource assessment result is slightly higher than the ,ideal value, indicating that the resource allocation is slightly ,excessive or inefficient, and further adjustment may be needed to achieve the ,ideal project progress.
[0224] See also Figure 6 , the specific steps for obtaining the maintenance or replacement time of the selected equipment are:
[0225] S411: Collect the usage history and performance degradation monitoring data of key construction equipment from the project data, and evaluate the allocation of all resources based on the information , using the formula:
[0226] ;
[0227] Calculate engineering equipment in time Performance degradation metric under ;
[0228] in, represents a measure of the degradation of device performance, Indicates the cumulative usage time of the device, which is the total number of hours since the device was activated. Indicates the usage intensity adjustment coefficient, which adjusts the impact of historical usage time on performance degradation. represents the normalization coefficient used to adjust the scale of the attenuation metric;
[0229] S412: According to the engineering equipment at time Performance degradation metric under , using the formula:
[0230] ;
[0231] Calculate the time interval for the next maintenance or replacement of engineering equipment ;
[0232] in, Indicates the performance degradation threshold. When this value is reached, maintenance or replacement is recommended. A tolerance factor that indicates performance degradation.
[0233] The calculation process is as follows:
[0234] Assumed parameters: Hour, , .
[0235] For the formula:
[0236] ;
[0237] result:
[0238] ;
[0239] ;
[0240] ;
[0241] ;
[0242] ;
[0243] ;
[0244] Assumed parameters: , .
[0245] For the formula:
[0246] ;
[0247] result:
[0248] ;
[0249] ;
[0250] ;
[0251] Assume that the base value is 1.5, which represents the ideal maintenance interval in years. Calculation results This result is slightly higher than the baseline, indicating that the equipment's performance decays more slowly and may require less frequent maintenance.
[0252] See also Figure 7 ,The specific steps for obtaining engineering equipment management information are as follows:
[0253] S421: According to the time interval for the next maintenance or replacement of engineering equipment , using the formula:
[0254] ;
[0255] Calculating the Engineering Equipment Maintenance Urgency Index ;
[0256] in, Indicates the operating time of the equipment since the last maintenance. Indicates critical operating time, the equipment may need more frequent inspections, Indicates adjustment right The sensitivity of the impact Indicates the time buffer value, providing additional maintenance preparation time. If it is a negative value, it means that the equipment urgently needs maintenance; Represents the base of natural logarithms, used in exponential functions;
[0257] S422: According to the engineering equipment maintenance emergency index , using the formula:
[0258] ;
[0259] Determine the maintenance priority of engineering equipment ;
[0260] in, The closer the value is to 1, the higher the priority. Represents the adjustment factor, affecting right sensitivity, Indicates the offset, which adjusts the baseline of priority allocation;
[0261] S423: According to the maintenance priority of engineering equipment , using the formula:
[0262] ;
[0263] Get the maintenance demand index of the entire equipment pool at a given point in time , get engineering equipment management information;
[0264] in, Indicates the progress of the project. Indicates the device Attribute values, such as the importance or cost of the equipment, Represents a weighting factor, which is adjusted based on the importance of the device and the impact of its failure.
[0265] The calculation process is as follows:
[0266] Assumed parameters: Year, Year, , Year.
[0267] For the formula:
[0268] ;
[0269] result:
[0270] ;
[0271] ;
[0272] ;
[0273] ;
[0274] ;
[0275] ;
[0276] Assumed parameters: .
[0277] For the formula:
[0278] ;
[0279] result:
[0280] ;
[0281] ;
[0282] ;
[0283] ;
[0284] ;
[0285] Assumed parameters: .
[0286] For the formula:
[0287] ;
[0288] result:
[0289] ;
[0290] ;
[0291] ;
[0292] A baseline value of 0.5 is assumed, representing the expected average equipment management efficiency. It means that the project is doing better than average in resource management, indicating that resource allocation and maintenance plans are reasonable.
[0293] A digital engineering management system based on BIM technology, the digital engineering management system based on BIM technology is used to execute the digital engineering management method based on BIM technology, and the system includes:
[0294] The demand analysis module extracts the resource demand and existing resource status of each project from BIM data, analyzes areas of insufficient or excessive resources, uses Lagrange multipliers to adjust resource quantities, and generates resource demand and available resource data;
[0295] The resource allocation module uses resource demand and available resource data to make quantitative adjustments to each type of resource, optimize resource allocation efficiency, and generate an initial resource allocation model;
[0296] The real-time adjustment module monitors the progress of engineering projects and resource consumption, dynamically adjusts resource allocation based on the initial resource allocation model, updates resource configuration in real time, and generates optimized resource information;
[0297] The schedule simulation module uses optimized resource information to perform schedule simulation of engineering projects, analyze the impact of various resource configurations on project schedules, evaluate the efficiency of resource configuration plans, and generate resource allocation evaluation results;
[0298] The equipment management module analyzes the usage data and performance monitoring records of key equipment in the project based on the resource allocation assessment results, formulates equipment maintenance or replacement plans, and generates engineering equipment management information.
[0299] The above are only preferred embodiments of the present invention and are not intended to limit the present invention in other forms. Any technician familiar with the profession may use the technical contents disclosed above to change or modify them into equivalent embodiments with equivalent changes and apply them to other fields. However, any simple modification, equivalent change and modification made to the above embodiments based on the technical essence of the present invention without departing from the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.
Claims
1. A digital engineering management method based on BIM technology, characterized in that: The following steps are involved: Extract the resource requirements and current resource information of the engineering project from the BIM model in real time, identify the insufficient or excessive problems in resource allocation, apply Lagrange multipliers to calculate and adjust resource allocation, match project requirements, and generate an initial resource allocation model; The acquisition steps for identifying insufficient or excessive resource allocation problems are specifically as follows: Extract the resource requirements and current resource information of the project from the BIM model in real time using the formula: and ; Calculate the total amount of demand for each type of resource and the current available ; in, represents the demand of the jth project for the i-th type of resources, is the weight of the jth item, represents the supply of the i-th resource from the k-th source, is the reliability coefficient of the kth source, and Respectively represent the upper limits of the number of projects and the number of resource sources; According to the total demand for each type of resource and the current available , using the formula: ; Calculate the difference between the demand and supply of the project and get the difference between the demand and supply of the i-th resource ; in, is the urgency coefficient of resource category i; According to the difference between the demand and supply of the i-th resource , using the formula: ; Get the absolute value of the total difference ; The steps for obtaining the initial resource allocation model are specifically as follows: According to the absolute value of the total difference , using the formula: ; Get the initial value of the Lagrange multiplier ; in, Represents a small positive number that prevents zero from being divided, is the adjustment coefficient, is the secondary adjustment coefficient; Use the initial values of the Lagrange multipliers The allocation for each resource category is adjusted using the formula: ; Calculate the new allocation of each resource and get the adjusted available amount of the i-th resource ; in, is the difference weighting factor; Based on the adjusted available amount of the i-th resource , construct the initial resource allocation model, using the formula: ; Calculate the total value of resource allocation under the current parameter settings ; in, Represents the value coefficient of the i-th type of resource, which is used to evaluate the importance of the resource in the project. represents the cost coefficient of the resource; Using the initial resource allocation model, iterative adjustments are made according to the current progress and resource consumption of the engineering project provided in the BIM model until resource allocation is balanced in each engineering project, generating optimized resource information; The steps for obtaining the optimized resource information are specifically as follows: The total value allocated according to the resource , using the formula: ; Calculate the current time The remaining amount of resources ; in, Indicates the current time The resource consumption, is the secondary adjustment coefficient, which is used to reflect the impact of accelerated resource consumption. It is the square root adjustment coefficient, which is used to smooth the impact of sudden consumption increase; According to the current time The remaining amount of resources And the current project progress, using the formula: ; Compute resource deviation ratio , get optimized resource information; in, Indicates the amount of resources that should be consumed according to the project progress. is the resource deviation adjustment factor; Simulating and analyzing the project progress through the optimized resource information, analyzing the impact of the current resource configuration on the project progress, and evaluating the effect of each resource configuration to generate a resource allocation evaluation result; According to the resource allocation assessment results, the use history of key construction equipment in the project and its performance degradation monitoring data are analyzed. According to the data and the progress of the project, the maintenance or replacement time of the equipment is selected, and the equipment is sorted according to the maintenance urgency to obtain the project equipment management information.
2. The digital engineering management method based on BIM technology according to claim 1 is characterized in that: The steps for obtaining the resource allocation evaluation result are specifically as follows: According to the deviation ratio of the resource , using the formula: ; Calculating simulation time Project progress status ; in, For resource availability, is the weight of resource availability, is the sensitivity coefficient of simulation progress, To adjust The nonlinear coefficient of the effect; According to the simulation time Project progress status , using the formula: ; Calculate each time Resource allocation ; in, To target project progress, is the sensitivity coefficient of the assessment; According to each time Resource allocation , using the formula: ; Integrate evaluation information of all resource allocations , and obtain the resource allocation evaluation result.
3. The digital engineering management method based on BIM technology according to claim 2 is characterized in that: The steps for obtaining the maintenance or replacement time of the selected equipment are specifically as follows: Collect the usage history and performance degradation monitoring data of key construction equipment from the project data, and evaluate the allocation of all resources according to the information , using the formula: ; Calculate engineering equipment in time Performance degradation metric under ; in, represents a measure of the degradation of device performance, Indicates the cumulative usage time of the device. Indicates the use intensity adjustment coefficient, represents the normalization coefficient; According to the engineering equipment at time Performance degradation metric under , using the formula: ; Calculate the time interval for the next maintenance or replacement of engineering equipment ; in, represents the performance degradation threshold, A tolerance factor that indicates performance degradation.
4. The digital engineering management method based on BIM technology according to claim 3 is characterized in that: The steps for obtaining the engineering equipment management information are specifically as follows: According to the time interval for the next maintenance or replacement of the engineering equipment , using the formula: ; Calculating the Engineering Equipment Maintenance Urgency Index ; in, Indicates the operating time of the equipment since the last maintenance. represents the critical running time, Indicates adjustment right The sensitivity of the impact Indicates the time buffer value, represents the base of natural logarithms; According to the engineering equipment maintenance emergency index , using the formula: ; Determine the maintenance priority of engineering equipment ; in, represents the adjustment factor, Indicates the offset; According to the maintenance priority of the engineering equipment , using the formula: ; Get the maintenance demand index of the entire equipment pool at a given point in time , get engineering equipment management information; in, Indicates the progress of the project. Indicates the device The attribute value of Represents the weight factor.
5. A digital engineering management system based on BIM technology, characterized in that: According to the digital engineering management method based on BIM technology according to any one of claims 1 to 4, the system comprises: The demand analysis module extracts the resource demand and existing resource status of each project from BIM data, analyzes areas of insufficient or excessive resources, uses Lagrange multipliers to adjust resource quantities, and generates resource demand and available resource data; The resource allocation module uses the resource demand and available resource data to quantitatively adjust each type of resource, optimize resource allocation efficiency, and generate an initial resource allocation model; The real-time adjustment module monitors the progress of the engineering project and the resource consumption status, dynamically adjusts the resource allocation based on the initial resource allocation model, updates the resource configuration in real time, and generates optimized resource information; The schedule simulation module uses the optimized resource information to perform schedule simulation of the engineering project, analyze the impact of various resource configurations on the project schedule, evaluate the efficiency of the resource configuration plan, and generate resource allocation evaluation results; The equipment management module analyzes the usage data and performance monitoring records of key equipment in the project based on the resource allocation evaluation results, formulates equipment maintenance or replacement plans, and generates project equipment management information.