Intelligent supervision method and equipment for aluminum veneer production
By acquiring and analyzing aluminum panel production information, controlling the feeding device and monitoring production response events on the production line, the problem of difficult production strategy adjustment in traditional automated aluminum panel production lines has been solved, achieving efficient intelligent supervision and cost optimization.
Patent Information
- Application Number
- CN202411163177.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2044-08-23
AI Technical Summary
Traditional automated aluminum panel production lines rely on manual supervision, making it difficult to quickly adjust production strategies, resulting in production delays and increased costs.
By acquiring aluminum panel production information, analyzing production cycle time, controlling the feeding device to feed materials, and monitoring in real time whether material waiting or material accumulation events occur on the production line, a response mechanism is implemented to quickly identify and handle production response events.
It improved production efficiency and product quality, optimized cost control, and enabled intelligent monitoring of the automated aluminum veneer production line.
Smart Images

Figure CN118672227B_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of aluminum veneer production, and in particular, relates to an intelligent supervision method and equipment for aluminum veneer production. Background Art
[0002] With the development of automation and intelligence in the manufacturing industry, the production of aluminum veneers has gradually become automated. The automated production line of aluminum veneers usually includes automated equipment for different processes and automatic conveying devices to form an automated production line, which greatly reduces manpower.
[0003] However, in traditional aluminum veneer automated production lines, the supervision method often relies on regular manual inspections. When production problems occur, it is difficult to quickly adjust the production strategy, resulting in production delays and increased costs. Summary of the invention
[0004] The embodiments of the present application provide an intelligent supervision method and device for aluminum veneer production, which can solve the problem that it is difficult to quickly adjust the production strategy in the traditional aluminum veneer automated production line, resulting in production delays and increased costs.
[0005] In a first aspect, an embodiment of the present application provides an intelligent supervision method for aluminum veneer production, comprising:
[0006] Acquire aluminum veneer production information; wherein the aluminum veneer production information is used to reflect the production model and production line of the aluminum veneer;
[0007] Analyze the aluminum veneer production information to determine the production rhythm; wherein the production rhythm is used to reflect the production efficiency of the production line;
[0008] Controlling the feeding device to feed materials according to the production rhythm;
[0009] Monitor whether a production response event occurs on the production line; wherein the production response event includes a waiting event and a stacking event. The waiting event is used to reflect that the aluminum veneer production equipment has not produced and processed the aluminum veneer to be processed within a first preset time, and the stacking event is used to reflect that the loading area of the aluminum veneer production equipment has accumulated more than a preset number of aluminum veneers to be processed within a second preset time;
[0010] If the production response event occurs, a response mechanism is executed based on the production response event.
[0011] The above technical solutions in the embodiments of the present application have at least the following technical effects:
[0012] The intelligent supervision method for aluminum veneer production provided by the present application obtains the production model and aluminum veneer production information of the production line for reflecting the aluminum veneer; then analyzes based on the aluminum veneer production information to determine the production efficiency and production rhythm for reflecting the production line; and then controls the feeding device to feed according to the production rhythm, which can improve the matching of raw material supply with the demand of the production line, reduce excessive or insufficient feeding, and thus maintain the continuity and efficiency of the aluminum veneer production line. In the production process, real-time supervision of whether the production line occurs, including a waiting event for reflecting that the aluminum veneer production equipment has not produced and processed the aluminum veneer within the first preset time, and a production response event for reflecting that the feeding area of the aluminum veneer production equipment accumulates more than a preset number of aluminum veneers to be processed within the second preset time; if a production response event occurs, a response mechanism is executed based on the production response event. The method can quickly identify production response events such as waiting and stacking, take timely measures, reduce production interruptions or waste of resources, not only improve production efficiency and product quality, but also optimize cost control, and realize the intelligent supervision process of the aluminum veneer automated production line.
[0013] In a possible implementation manner of the first aspect, if the production response event occurs, executing a response mechanism based on the production response event includes:
[0014] If the production response event occurs, then obtain the equipment information where the production response event occurs; wherein the equipment information is used to reflect the aluminum single plate production equipment related to the production response event;
[0015] A response mechanism is executed based on the production response event and the device information.
[0016] In a possible implementation manner of the first aspect, executing a response mechanism based on the production response event and the device information includes:
[0017] Acquire the location information of the equipment information; wherein the location information is used to reflect the aluminum veneer production process of the aluminum veneer production equipment where the waiting event occurs;
[0018] Obtaining bottleneck process information; wherein the bottleneck process information is used to reflect the aluminum veneer production process with the smallest production capacity of the production line and the corresponding aluminum veneer production equipment;
[0019] A response mechanism is executed based on the production response event, the location information and the bottleneck process information.
[0020] In a possible implementation manner of the first aspect, executing a response mechanism based on the production response event, the location information, and the bottleneck process information includes:
[0021] When the production response event is the waiting event, determining a first relative position of the aluminum veneer production process reflected by the position information and the aluminum veneer production process reflected by the bottleneck process information;
[0022] If the aluminum veneer production process reflected by the first relative position matches the aluminum veneer production process reflected by the bottleneck process information, an equipment performance degradation warning is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the bottleneck process information is controlled to shut down.
[0023] In a possible implementation manner of the first aspect, executing a response mechanism based on the production response event, the location information, and the bottleneck process information further includes:
[0024] If the aluminum veneer production process reflected by the first relative position does not match the aluminum veneer production process reflected by the bottleneck process information, then the difference between the first production capacity of the aluminum veneer production process reflected by the first relative position and the second production capacity in the bottleneck process information is calculated to obtain the capacity difference;
[0025] comparing the capacity difference with a preset threshold;
[0026] If the production capacity difference is less than the preset threshold, an early warning of equipment performance degradation is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the position information is controlled to shut down for maintenance.
[0027] In a possible implementation manner of the first aspect, executing a response mechanism based on the production response event, the location information, and the bottleneck process information further includes:
[0028] If the production capacity difference is greater than or equal to the preset threshold, the aluminum single plate production equipment is controlled to continue production.
[0029] In a possible implementation manner of the first aspect, executing a response mechanism based on the production response event, the location information, and the bottleneck process information includes:
[0030] When the production response event is the stockpiling event, determining a second relative position of the aluminum veneer production process reflected by the position information and the aluminum veneer production process reflected by the bottleneck process information;
[0031] If the aluminum veneer production process reflected by the second relative position matches the aluminum veneer production process reflected by the bottleneck process information, the stacking quantity of the stacking event is obtained;
[0032] Analyze the stacking quantity and the preset quantity to obtain a beat adjustment amount;
[0033] Adjusting the production rhythm based on the rhythm adjustment amount to obtain a temporary production rhythm;
[0034] The loading device is controlled to load materials according to the temporary production rhythm.
[0035] In a possible implementation manner of the first aspect, executing a response mechanism based on the production response event, the location information, and the bottleneck process information further includes:
[0036] If the aluminum veneer production process reflected by the second relative position does not match the aluminum veneer production process reflected by the bottleneck process information, an equipment failure warning is issued based on the position information, and the production line is shut down for maintenance.
[0037] In a second aspect, the embodiment of the present application provides an intelligent supervision system for aluminum veneer production, including:
[0038] An acquisition module is used to acquire the production information of the aluminum veneer; wherein the production information of the aluminum veneer is used to reflect the production model and production line of the aluminum veneer;
[0039] An analysis module, used to analyze the aluminum veneer production information and determine the production rhythm; wherein the production rhythm is used to reflect the production efficiency of the production line;
[0040] A control module, used for controlling a feeding device to feed materials according to the production rhythm;
[0041] A supervision module is used to supervise whether a production response event occurs on the production line; wherein the production response event includes a waiting event and a stacking event, wherein the waiting event is used to reflect that the aluminum veneer production equipment has not produced and processed the aluminum veneer to be processed within a first preset time, and the stacking event is used to reflect that the loading area of the aluminum veneer production equipment has accumulated more than a preset number of aluminum veneers to be processed within a second preset time;
[0042] An execution module is used to execute a response mechanism based on the production response event if the production response event occurs.
[0043] In the third aspect, an embodiment of the present application provides an intelligent supervision device for the production of aluminum veneer, comprising a feeding device, a production device and a control device, wherein the control device is electrically connected to the melting device, the extrusion device and the cooling device, and the control device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements any one of the methods described in the first aspect when executing the computer program.
[0044] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method described in any one of the above-mentioned first aspects is implemented.
[0045] In the fifth aspect, an embodiment of the present application provides a computer program product. When the computer program product is run on an intelligent supervision device for aluminum veneer production, the intelligent supervision device for aluminum veneer production enables the intelligent supervision device for aluminum veneer production to execute the intelligent supervision method for aluminum veneer production described in any one of the above-mentioned first aspects.
[0046] It can be understood that the beneficial effects of the second to fifth aspects mentioned above can be found in the relevant description of the first aspect mentioned above, and will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0048] Figure 1 It is a flow chart of the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application;
[0049] Figure 2 It is a schematic diagram of the implementation process of step S500 in the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application;
[0050] Figure 3 It is a schematic diagram of the implementation process of step S520 in the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application;
[0051] Figure 4 This is one of the implementation flow diagrams of step S523 in the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application;
[0052] Figure 5 This is the second implementation flow diagram of step S523 in the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application;
[0053] Figure 6 It is a structural schematic diagram of the intelligent supervision system for aluminum veneer production provided in the embodiment of the present application;
[0054] Figure 7 It is a structural schematic diagram of the control device of the intelligent monitoring equipment for aluminum veneer production provided in the embodiment of the present application. DETAILED DESCRIPTION
[0055] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.
[0056] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, wholes, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or combinations thereof.
[0057] It should also be understood that the term “and / or” used in the specification and appended claims refers to any and all possible combinations of one or more of the associated listed items, and includes these combinations.
[0058] As used in the specification and appended claims of this application, the term "if" can be interpreted as "when" or "uponce" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" can be interpreted as meaning "uponce it is determined" or "in response to determining" or "uponce [described condition or event] is detected" or "in response to detecting [described condition or event]", depending on the context.
[0059] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.
[0060] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.
[0061] With the development of automation and intelligence in the manufacturing industry, the production of aluminum veneers has gradually become automated. The automated production line of aluminum veneers usually includes automated equipment for different processes and automatic conveying devices to form an automated production line, which greatly reduces manpower.
[0062] However, in traditional aluminum veneer automated production lines, the supervision method often relies on regular manual inspections. When production problems occur, it is difficult to quickly adjust the production strategy, resulting in production delays and increased costs.
[0063] To solve the above problems, the embodiment of the present application provides an intelligent supervision method and equipment for aluminum veneer production. In the method, by obtaining the production model and production line aluminum veneer production information for reflecting the aluminum veneer; then analyzing based on the aluminum veneer production information, determining the production efficiency and production rhythm for reflecting the production line; and then controlling the feeding device to feed according to the production rhythm, it is possible to improve the matching of raw material supply with the demand of the production line, reduce excessive or insufficient feeding, and thus maintain the continuity and efficiency of the aluminum veneer production line. In the production process, real-time supervision of whether the production line occurs, including a waiting event for reflecting that the aluminum veneer production equipment has not produced and processed the aluminum veneer to be processed within the first preset time, and a production response event for reflecting that the feeding area of the aluminum veneer production equipment has accumulated more than a preset number of aluminum veneers to be processed within the second preset time; if a production response event occurs, a response mechanism is executed based on the production response event. The method can quickly identify production response events such as waiting and stacking, take timely measures, reduce production interruptions or waste of resources, not only improve production efficiency and product quality, but also optimize cost control, and realize the intelligent supervision process of the aluminum veneer automated production line.
[0064] The intelligent supervision method for aluminum veneer production provided in the embodiment of the present application can be applied to intelligent supervision equipment for aluminum veneer production. At this time, the intelligent supervision equipment for aluminum veneer production is the executor of the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application. The embodiment of the present application does not impose any restrictions on the specific type of intelligent supervision equipment for aluminum veneer production.
[0065] For example, the intelligent supervision equipment for aluminum veneer production may include a feeding device, a production device and a control device, and the control device is electrically connected to the feeding device and the production device. The feeding device is used to feed the original aluminum plate into the production device. The feeding device can be a manipulator, an automatic guided vehicle (AGV), a lifting conveyor, etc., but is not limited to this. The production device is connected to the output end of the feeding device, and is used to process and produce the original aluminum plate, such as cutting, cleaning, punching, folding, spraying, polishing, etc. The production device includes a cutting device, a folding device, a cleaning device, a spraying device, a punching device and a polishing device. The cutting device is connected to the output end of the feeding device, and is used to cut the original aluminum plate into the required size and shape. The cutting device can be a CNC shearing machine, a laser cutting machine, etc. The cleaning device is connected to the output end of the cutting device, and is used to clean the aluminum veneer. The cleaning device can be an ultrasonic cleaning machine, a spray cleaning machine, etc. The punching device is connected to the output end of the cleaning device, and is used to make holes on the aluminum veneer to facilitate installation or design requirements. The punching device can be a laser punching machine, a CNC punching machine, etc. The folding device is connected to the output end of the punching device, and is used to bend the edge of the aluminum veneer to form the required structural shape and increase its strength and aesthetics. The folding device can be a CNC folding machine, a servo motor driven folding machine, etc. The spraying device is connected to the output end of the folding device, and is used to apply paint on the surface of the aluminum veneer to provide a protective layer and aesthetic effect. The spraying device can be an air sprayer, an airless sprayer, etc. The polishing device is connected to the output end of the spraying device, and is used to improve the gloss and flatness of the surface of the aluminum veneer and improve its appearance quality. The polishing device can be an automatic mechanical polishing machine, an electrolytic polishing machine, etc. The various devices in the production device can be connected by a conveyor belt, or the materials can be circulated by a manipulator, etc., but are not limited to this. The input end of each device in the production device is provided with a loading area, and the output end of each device in the production device is provided with a unloading area. The loading area is used to place the aluminum veneer processed in the previous process, and the unloading area is used to place the aluminum veneer processed in this process. In production, all or part of the devices in the production device can be involved in production according to the needs of the process. The control system monitors and controls the entire loading process and the production process.
[0066] In order to better understand the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application, the specific implementation process of the intelligent supervision method for aluminum veneer production provided in the embodiment of the present application is exemplarily introduced below.
[0067] Figure 1 A schematic flow chart of an intelligent supervision method for aluminum veneer production provided in an embodiment of the present application is shown, and the intelligent supervision method for aluminum veneer production includes:
[0068] S100, obtaining aluminum veneer production information; wherein the aluminum veneer production information is used to reflect the production model and production line of the aluminum veneer.
[0069] It is understandable that the aluminum veneer production information can be manually input by humans, obtained through the MES system, ERP system, or obtained by scanning RFID tags to identify the batch of aluminum veneers, etc., but not limited to these.
[0070] S200, analyzing the aluminum veneer production information to determine the production rhythm; wherein the production rhythm is used to reflect the production efficiency of the production line.
[0071] It is understandable that different types of aluminum veneers may be produced on different production lines, and the models and specifications of the various devices used in the production devices of different production lines may also be different. The production rhythm can be determined by finding the average production time and fluctuation range through the production data of the same or similar products on the same line in the past; the bottleneck process on the production line can also be identified according to the aluminum veneer model and the various production devices on the production line, that is, the process with the lowest production capacity when producing the aluminum veneer of this model, and the production rhythm of the entire production line can be determined according to the production efficiency of the bottleneck process, etc., but not limited to this. Among them, the production efficiency of the bottleneck process reflects the time required for the bottleneck process to process an aluminum veneer, and the production rhythm of the entire production line reflects the time interval between processing and loading of the entire production line. Exemplarily, the processes of the aluminum veneer production line include cleaning, punching, spraying and polishing. The production efficiency of each process is 3s / piece for cleaning, 4s / piece for punching, 8s / piece for spraying and 10s / piece for polishing. The bottleneck process is the polishing process. Due to factors such as aging equipment and transmission efficiency, the production rhythm of the entire production line can be determined at around 10s, that is, the feeding device feeds the material every 10s or so, which can be 8-11s, 9-12s, and so on.
[0072] S300, controlling the loading device to load materials according to the production rhythm.
[0073] It can be understood that the feeding speed of the feeding device is consistent with the production rhythm, which can ensure the continuous and efficient operation of the production line.
[0074] S400, monitor whether a production response event occurs on the production line; wherein, production response events include waiting events and stacking events. The waiting events are used to reflect that the aluminum veneer production equipment has not produced and processed the aluminum veneer to be processed within the first preset time, and the stacking events are used to reflect that the loading area of the aluminum veneer production equipment has accumulated more than a preset number of aluminum veneers to be processed within the second preset time.
[0075] It can be understood that the occurrence of the waiting event indicates that there is a shortage of materials in a certain link of the production line, which causes the production equipment to be unable to receive the aluminum veneer to be processed within the first preset time, thereby causing the unplanned idle operation of the production equipment. This idle operation not only wastes electricity and human resources, but also interrupts the continuity of the production process, and may cause a chain reaction in subsequent processes. For example, other equipment on the production line also needs to wait or slow down the production rhythm until the material is replenished. The occurrence of the stacking event refers to the accumulation of more than a preset number of aluminum veneers to be processed in the loading area or a certain link of the production line within the second preset time. This situation is usually caused by the processing speed of a part of the production line being lower than the upstream supply speed, or the consumption speed of the downstream slowing down, resulting in a backlog of materials at a certain point. The production response event can be obtained by installing a camera or other imaging device at the input and output ports of each aluminum veneer production equipment, or by setting a sensor (such as a weight sensor, an infrared sensor, etc.) at the input and output ports of each aluminum veneer production equipment to obtain the production response event, and so on, but not limited to this.
[0076] The first preset time, the second preset time and the preset quantity are both preset values. Each aluminum veneer production equipment on the aluminum veneer production line corresponds to a first preset time and a second preset time. The first preset time, the second preset time and the preset quantity can be manually set based on previous production experience, the production rhythm of the production line and the production capacity of each aluminum veneer production equipment, or can be obtained from the aluminum veneer production database, etc., but not limited to this. The aluminum veneer production database refers to a database containing aluminum veneer production information and the corresponding first preset time and second preset time of each aluminum veneer production equipment. These data can be obtained through laboratory experiments, on-site measurements and monitoring, and previous experience. After obtaining, the collected data is sorted, classified and archived, useful information and rules are extracted, and the relevant data is saved in the database to form an aluminum veneer production database.
[0077] S500: If a production response event occurs, a response mechanism is executed based on the production response event.
[0078] It can be understood that the response mechanism refers to a series of predefined actions taken when a production response event occurs. The response mechanism can be set manually or obtained from the aluminum veneer production database, etc., but is not limited to this. The response mechanism includes adjusting the production rhythm, emergency maintenance, notifying relevant personnel, etc.
[0079] With this arrangement, when there is a material waiting event or material piling event during the production process, the production line can give timely feedback and optimize actions, reducing the impact on the production efficiency and cost waste of aluminum veneers. At the same time, it ensures product quality and delivery time, and enhances the market competitiveness of the enterprise.
[0080] As an optional embodiment of this application, please refer to Figure 2 In step S500, if a production response event occurs, a response mechanism is executed based on the production response event, including:
[0081] S510: If a production response event occurs, obtain the equipment information where the production response event occurs; wherein the equipment information is used to reflect the aluminum veneer production equipment related to the production response event.
[0082] It can be understood that the corresponding aluminum veneer equipment name can be obtained by obtaining the occurrence location or process of the production response event, and then the aluminum veneer equipment name can be matched with the data in the aluminum veneer database to obtain the corresponding equipment information; the corresponding equipment information can also be directly obtained through sensors or imaging devices, etc., but not limited to this.
[0083] S520, executing a response mechanism based on the production response event and the device information.
[0084] It can be understood that different production response events correspond to different response mechanisms.
[0085] With this setup, by quickly identifying production response events and locating specific equipment, timely measures can be taken to reduce production line downtime, avoid production delays, reduce scrap and additional costs caused by production interruptions, and avoid unnecessary equipment idling or overuse, thereby reducing production costs.
[0086] In one possible implementation, see Figure 3 In step S520, a response mechanism is executed based on the production response event and the device information, including:
[0087] S521, obtaining location information of equipment information; wherein the location information is used to reflect the aluminum veneer production process of the aluminum veneer production equipment where the waiting event occurs.
[0088] It can be understood that the corresponding aluminum veneer equipment name can be obtained by obtaining the occurrence process of the production response event, and then the aluminum veneer equipment name can be matched with the data in the aluminum veneer database to obtain the corresponding location information; the corresponding location information can also be directly obtained through sensors or imaging devices, etc., but not limited to this.
[0089] S522, obtaining bottleneck process information; wherein the bottleneck process information is used to reflect the aluminum veneer production process with the smallest production capacity of the production line and the corresponding aluminum veneer production equipment.
[0090] It is understandable that the bottleneck process information can be manually input or obtained from the aluminum veneer database, etc., but not limited to this. The bottleneck process refers to the process with the lowest production capacity in the production line, which usually determines the upper limit of the production efficiency of the entire production line.
[0091] S523, executing a response mechanism based on the production response event, location information and bottleneck process information.
[0092] With this arrangement, when a production response event occurs, the corresponding response mechanism is determined through the correlation between the location information and the bottleneck process information, so that targeted measures can be taken quickly to reduce the production interruption time. At the same time, the overall efficiency of the production line and the particularity of the bottleneck process are taken into account to ensure the continuity and efficiency of production activities. This response mechanism based on location information and bottleneck process information improves the adaptive ability and intelligence level of the production system.
[0093] In one possible implementation, see Figure 4 In step S523, a response mechanism is executed based on the production response event, the location information and the bottleneck process information, including:
[0094] S523a, when the production response event is a waiting event, determine the first relative position of the aluminum veneer production process reflected by the position information and the aluminum veneer production process reflected by the bottleneck process information.
[0095] It can be understood that the production sequence can be obtained by sorting the production order of the aluminum veneer through each process in the production line, and then comparing the sequence position of the aluminum veneer production process where the waiting event occurred in the production sequence with the sequence position of the bottleneck process in the production sequence reflected in the bottleneck process information, so as to obtain the first relative position; the first relative position can also be obtained by comparing the first position of the production line where the aluminum veneer production process where the waiting event occurred is located with the second position of the production line where the bottleneck process is located, and so on, but not limited to this.
[0096] S524a, if the aluminum veneer production process reflected by the first relative position matches the aluminum veneer production process reflected by the bottleneck process information, an equipment performance degradation warning is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the bottleneck process information is controlled to shut down.
[0097] It can be understood that matching means that the aluminum veneer production equipment where the waiting event occurred is consistent with the aluminum veneer production equipment of the bottleneck process, that is, the aluminum veneer production equipment of the bottleneck process has a waiting event. When a waiting event occurs in the bottleneck process, it means that the production capacity of a process before the bottleneck process is less than the capacity of the bottleneck process. At this time, an early warning will be immediately issued to the production management personnel, indicating that the equipment performance may decline and require emergency treatment. The early warning can be issued through indicator lights or voice broadcasts, etc., but not limited to these. In order to avoid piling of materials in the previous process, the aluminum veneer production equipment before the aluminum veneer production equipment reflected in the bottleneck process information is controlled to shut down.
[0098] Such settings and the implementation of an early warning mechanism can enhance the real-time and accuracy of production management, improve the adaptability of the production system, and enhance the sophistication of production management. Controlling equipment shutdown before the bottleneck process can avoid overproduction, reduce material stacking in the previous process, and prevent excessive accumulation of semi-finished products or raw materials, thereby avoiding waste of resources.
[0099] In one possible implementation, see Figure 4 In step S523, a response mechanism is executed based on the production response event, the location information and the bottleneck process information, and further includes:
[0100] S524A, if the aluminum veneer production process reflected by the first relative position does not match the aluminum veneer production process reflected by the bottleneck process information, then calculate the difference between the first production capacity of the aluminum veneer production process reflected by the first relative position and the second production capacity in the bottleneck process information to obtain the capacity difference.
[0101] It can be understood that mismatch means that the aluminum veneer production equipment where the waiting event occurs is not the aluminum veneer production equipment corresponding to the bottleneck process. The first production capacity and the second production capacity can be input manually or obtained from the aluminum veneer production database, etc., but not limited to this.
[0102] S525A, compares the capacity difference with a preset threshold.
[0103] It can be understood that the preset threshold is a pre-set value, which can be set manually, or by inputting the aluminum veneer production information and the corresponding aluminum veneer production equipment into the learning model, outputting the corresponding preset threshold, etc., but not limited thereto. The learning model is trained with multiple sets of training data, and each set of training data in the multiple sets of training data includes the aluminum veneer production information and the corresponding aluminum veneer production equipment and the preset threshold.
[0104] S526A, if the production capacity difference is less than a preset threshold, an equipment performance degradation warning is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the position information is controlled to shut down for maintenance.
[0105] It can be understood that when the capacity difference is less than the preset threshold, it means that although the current waiting event does not occur in the bottleneck process, the capacity of this process is close to the capacity of the bottleneck process. In this case, the aluminum veneer production equipment has a waiting event, which means that the capacity of one or more aluminum veneer production equipment in the previous process has been significantly reduced, and the production efficiency of the entire production line has been affected. By issuing an early warning, the production management personnel or maintenance team is notified that the performance of the aluminum veneer production equipment on the current production line may have declined and needs to be inspected and maintained to prevent further capacity loss. At the same time, in order to avoid excessive backlog of materials on the production line, especially to avoid too many semi-finished products before the problem equipment, the equipment before the equipment is controlled to shut down. Doing so can reduce unnecessary production waste and leave time for the maintenance team to deal with equipment problems.
[0106] In one possible implementation, see Figure 4 In step S523, a response mechanism is executed based on the production response event, the location information and the bottleneck process information, and further includes:
[0107] S526a, if the production capacity difference is greater than or equal to the preset threshold, the aluminum single plate production equipment is controlled to continue production.
[0108] It can be understood that when the capacity difference is greater than or equal to the preset threshold, it means that the theoretical production capacity of the aluminum veneer production equipment where the waiting event occurred is significantly higher than the production capacity of the aluminum veneer production equipment corresponding to the bottleneck process. Although the aluminum veneer production equipment did not produce and process the aluminum veneer to be processed within the corresponding first preset time, the equipment will not be required to stop immediately, but will choose to continue production to give a certain amount of time for the material supply problem to be resolved.
[0109] By comparing the capacity difference with the preset threshold, the system can intelligently determine when emergency measures need to be taken and when to wait for natural recovery, thereby ensuring production efficiency while avoiding unnecessary production interruptions and waste of resources. This approach not only helps maintain the stable operation of the production line, but also improves production flexibility and reduces the negative impact of production response events.
[0110] In one possible implementation, see Figure 5 In step S523, a response mechanism is executed based on the production response event, the location information and the bottleneck process information, including:
[0111] S523b, when the production response event is a stockpiling event, determine the second relative position of the aluminum veneer production process reflected by the position information and the aluminum veneer production process reflected by the bottleneck process information.
[0112] It can be understood that the second relative position can be obtained by adopting a method similar to the method of obtaining the first relative position in step S523a.
[0113] S524b: If the aluminum veneer production process reflected by the second relative position matches the aluminum veneer production process reflected by the bottleneck process information, the stacking quantity of the stacking event is obtained.
[0114] It can be understood that when the aluminum veneer production process reflected by the second relative position matches the aluminum veneer production process reflected by the bottleneck process information, it means that a material stacking event has occurred in the aluminum veneer production equipment of the bottleneck process. This indicates that the actual production capacity of the bottleneck process is less than the theoretical production capacity. The amount of pushed materials can be obtained by a camera or other imaging device, or by a sensor (weight sensor, light sensor, etc.), etc., but is not limited thereto.
[0115] S525b, analyzing the stockpile quantity and the preset quantity to obtain a beat adjustment amount.
[0116] It can be understood that the preset number is a pre-set value, which can be set manually or obtained from the aluminum veneer production database, etc., but not limited to this. The corresponding beat adjustment amount can be obtained by matching the stockpiling quantity and the preset quantity in the aluminum veneer production database; the corresponding beat adjustment amount can also be output by inputting the stockpiling quantity, the preset quantity and the aluminum veneer production information into the learning model, and the corresponding beat adjustment amount is output, etc., but not limited to this. The aluminum veneer production database also includes the stockpiling quantity, the preset quantity and the corresponding beat adjustment amount. These data can be obtained through laboratory experiments, on-site measurements and monitoring, and previous experience. After obtaining, the collected data will be sorted, classified and archived, useful information and rules will be extracted, and the relevant data will be saved in the database to form an aluminum veneer production database. The learning model is trained with multiple sets of training data, and each set of training data in the multiple sets of training data includes aluminum veneer production information, stockpiling quantity, preset quantity and corresponding beat adjustment amount.
[0117] S526b, adjusting the production rhythm based on the rhythm adjustment amount to obtain a temporary production rhythm.
[0118] It can be understood that temporary production tact = production tact - tact adjustment. For example, if the production tact is 4 pieces / minute and the tact adjustment is 1 piece / minute, the temporary production tact is 3 pieces / minute (3=4-1), and so on.
[0119] S527b, controlling the loading device to load materials according to the temporary production rhythm.
[0120] It can be understood that adjusting the production rhythm to the temporary production rhythm avoids excessive material backlog, thereby solving the material stacking incident and maintaining the smooth operation of the production line.
[0121] In one possible implementation, see Figure 5 In step S523, a response mechanism is executed based on the production response event, the location information and the bottleneck process information, and further includes:
[0122] S524B, if the aluminum veneer production process reflected by the second relative position does not match the aluminum veneer production process reflected by the bottleneck process information, an equipment failure warning is issued based on the position information, and the production line is shut down for maintenance.
[0123] It can be understood that when the aluminum veneer production process reflected by the second relative position does not match the aluminum veneer production process reflected by the bottleneck process information, that is, the aluminum veneer production equipment where the stacking incident occurred is not the aluminum veneer production equipment of the bottleneck process, it means that the equipment in the non-bottleneck process may have encountered performance degradation or failure, resulting in its processing capacity being far below the expected level. Shutdown maintenance of the production line can prevent the problem from further deteriorating, avoid more extensive production interruptions, and reduce production losses.
[0124] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0125] Corresponding to the intelligent supervision method for aluminum veneer production described in the above embodiment, the embodiment of the present application also provides an intelligent supervision system for aluminum veneer production, and each module of the system can implement each step of the intelligent supervision method for aluminum veneer production. Figure 6 A structural block diagram of an intelligent supervision system for aluminum veneer production provided in an embodiment of the present application is shown. For ease of explanation, only the parts related to the embodiment of the present application are shown.
[0126] Reference Figure 6 , the aluminum veneer production intelligent supervision system includes:
[0127] The acquisition module is used to acquire the aluminum veneer production information; wherein the aluminum veneer production information is used to reflect the production model and production line of the aluminum veneer;
[0128] The analysis module is used to analyze the aluminum veneer production information and determine the production rhythm; wherein the production rhythm is used to reflect the production efficiency of the production line;
[0129] A control module is used to control the loading device to load materials according to the production rhythm;
[0130] A supervision module is used to supervise whether a production response event occurs on the production line; wherein the production response event includes a waiting event and a stacking event. The waiting event is used to reflect that the aluminum veneer production equipment has not produced and processed the aluminum veneer to be processed within a first preset time, and the stacking event is used to reflect that the loading area of the aluminum veneer production equipment has accumulated more than a preset number of aluminum veneers to be processed within a second preset time;
[0131] The execution module is used to execute a response mechanism based on the production response event if a production response event occurs.
[0132] It should be noted that the information interaction, execution process and other contents between the above-mentioned modules are based on the same concept as the method embodiment of the present application. Their specific functions and technical effects can be found in the method embodiment part and will not be repeated here.
[0133] Those skilled in the art can clearly understand that, for the convenience and simplicity of description, only the division of the above modules is used as an example for illustration. In practical applications, the above functions can be assigned to different modules as needed, that is, the internal structure of the system can be divided into different modules to complete all or part of the functions described above. The modules in the embodiment can be integrated into a processing unit, or each module can exist physically alone, or two or more modules can be integrated into one unit. The above integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the modules are only for the convenience of distinguishing from each other, and are not used to limit the scope of protection of this application. The specific working process of the modules in the above system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.
[0134] The embodiment of the present application also provides an intelligent monitoring device for aluminum single plate production, including a feeding device, a production device and a control device, and the control device is electrically connected to the feeding device and the production device. Figure 7 This is a schematic diagram of the structure of a control device 6 provided in an embodiment of the present application. Figure 7 As shown, the control device 6 of this embodiment includes: at least one processor 60 ( Figure 7 Only one is shown), at least one memory 61 ( Figure 7 Only one is shown) and a computer program 62 stored in the at least one memory 61 and executable on the at least one processor 60. When the processor 60 executes the computer program 62, the control device 6 implements the steps in any of the above-mentioned embodiments of the intelligent supervision method for aluminum veneer production, or implements the functions of each module in the above-mentioned device embodiments.
[0135] Exemplarily, the computer program 62 may be divided into one or more modules / units, which are stored in the memory 61 and executed by the processor 60 to complete the present application. The one or more modules / units may be a series of computer program instruction segments capable of completing specific functions, which are used to describe the execution process of the computer program 62 in the control device 6.
[0136] The control device 6 may be a computing device such as a desktop computer, a notebook, a PDA, or a cloud server. The control device 6 may include, but is not limited to, a processor 60 and a memory 61. Those skilled in the art will appreciate that Figure 7 It is only an example of the control device 6 and does not constitute a limitation on the control device 6. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, it may also include input and output devices, network access devices, buses, etc.
[0137] The processor 60 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.
[0138] In some embodiments, the memory 61 may be an internal storage unit of the control device 6, such as a hard disk or memory of the control device 6. In other embodiments, the memory 61 may also be an external storage device of the control device 6, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the control device 6. Further, the memory 61 may also include both an internal storage unit and an external storage device of the control device 6. The memory 61 is used to store an operating system, an application program, a boot loader (BootLoader), data, and other programs, such as the program code of the computer program. The memory 61 may also be used to temporarily store data that has been output or is to be output.
[0139] An embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in any of the above method embodiments are implemented.
[0140] An embodiment of the present application provides a computer program product. When the computer program product is run on an intelligent supervision device for aluminum veneer production, the intelligent supervision device for aluminum veneer production implements the steps in any of the above-mentioned method embodiments.
[0141] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may at least include: any entity or device that can carry the computer program code to the intelligent supervision device for aluminum veneer production, recording medium, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, RandomAccess Memory), electric carrier signal, telecommunication signal and software distribution medium. For example, a USB flash drive, a mobile hard disk, a disk or an optical disk.
[0142] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0143] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0144] In the embodiments provided in the present application, it should be understood that the disclosed intelligent supervision equipment, system and method for aluminum veneer production can be implemented in other ways. For example, the above-described intelligent supervision system and equipment embodiments for aluminum veneer production are merely schematic. For example, the division of the modules is only a logical function division. There may be other division methods in actual implementation, such as multiple modules can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or modules, which can be electrical, mechanical or other forms.
[0145] The modules described as separate components may or may not be physically separated, and the components shown as modules may or may not be physical modules, that is, they may be located in one place or distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0146] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. An intelligent supervision method for aluminum veneer production, characterized in that: include: Acquire aluminum veneer production information; wherein, the aluminum veneer production information is used to reflect the production model and production line of the aluminum veneer; Analyzing the aluminum veneer production information to determine the production rhythm; wherein the production rhythm is used to reflect the production efficiency of the production line; Controlling the loading device to load materials according to the production rhythm; Monitor whether a production response event occurs on the production line; wherein the production response event includes a waiting event and a piling event. The waiting event is used to reflect that the aluminum veneer production equipment has not produced and processed the aluminum veneer to be processed within a first preset time, and the piling event is used to reflect that the loading area of the aluminum veneer production equipment has accumulated more than a preset number of aluminum veneers to be processed within a second preset time; If the production response event occurs, executing a response mechanism based on the production response event; If the production response event occurs, executing a response mechanism based on the production response event includes: If the production response event occurs, then obtain the equipment information where the production response event occurs; wherein the equipment information is used to reflect the aluminum single plate production equipment related to the production response event; executing a response mechanism based on the production response event and the device information; The executing a response mechanism based on the production response event and the device information includes: Acquire location information of the equipment information; wherein the location information is used to reflect the aluminum veneer production process of the aluminum veneer production equipment where the waiting event occurs; Obtaining bottleneck process information; wherein the bottleneck process information is used to reflect the aluminum veneer production process with the smallest production capacity of the production line and the corresponding aluminum veneer production equipment; executing a response mechanism based on the production response event, the location information, and the bottleneck process information; The executing a response mechanism based on the production response event, the location information, and the bottleneck process information includes: When the production response event is the waiting event, determining a first relative position of the aluminum veneer production process reflected by the position information and the aluminum veneer production process reflected by the bottleneck process information; If the aluminum veneer production process reflected by the first relative position matches the aluminum veneer production process reflected by the bottleneck process information, an equipment performance degradation warning is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the bottleneck process information is controlled to shut down; The executing a response mechanism based on the production response event, the location information and the bottleneck process information further includes: If the aluminum veneer production process reflected by the first relative position does not match the aluminum veneer production process reflected by the bottleneck process information, then calculating the difference between a first production capacity of the aluminum veneer production process reflected by the first relative position and a second production capacity in the bottleneck process information to obtain a capacity difference; comparing the production capacity difference with a preset threshold; If the production capacity difference is less than the preset threshold, an early warning of equipment performance degradation is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the position information is controlled to shut down for maintenance; If the production capacity difference is greater than or equal to the preset threshold, the aluminum single plate production equipment is controlled to continue production.
2. The intelligent supervision method for aluminum veneer production according to claim 1, characterized in that: The executing a response mechanism based on the production response event, the location information, and the bottleneck process information includes: When the production response event is the stacking event, determining a second relative position of the aluminum veneer production process reflected by the position information and the aluminum veneer production process reflected by the bottleneck process information; If the aluminum veneer production process reflected by the second relative position matches the aluminum veneer production process reflected by the bottleneck process information, then obtaining the stacking quantity of the stacking event; Analyze the stacking quantity and the preset quantity to obtain a beat adjustment amount; Adjusting the production rhythm based on the rhythm adjustment amount to obtain a temporary production rhythm; The loading device is controlled to load materials according to the temporary production rhythm.
3. The intelligent supervision method for aluminum veneer production according to claim 2, characterized in that: The executing a response mechanism based on the production response event, the location information and the bottleneck process information further includes: If the aluminum veneer production process reflected by the second relative position does not match the aluminum veneer production process reflected by the bottleneck process information, an equipment failure warning is issued based on the position information, and the production line is shut down for maintenance.
4. An intelligent monitoring system for aluminum veneer production, characterized in that: include: An acquisition module is used to acquire aluminum veneer production information; wherein the aluminum veneer production information is used to reflect the production model and production line of the aluminum veneer; An analysis module, configured to analyze the aluminum veneer production information and determine a production rhythm; wherein the production rhythm is used to reflect the production efficiency of the production line; A control module, used for controlling the loading device to load materials according to the production rhythm; A monitoring module is configured to monitor whether a production response event occurs on the production line; wherein the production response event includes a waiting event and a piling event. The waiting event is used to reflect that the aluminum veneer production equipment has not produced and processed the aluminum veneer to be processed within a first preset time, and the piling event is used to reflect that the loading area of the aluminum veneer production equipment has accumulated more than a preset number of aluminum veneers to be processed within a second preset time. an execution module, configured to execute a response mechanism based on the production response event if the production response event occurs; The execution module is further configured to: If the production response event occurs, then obtain the equipment information where the production response event occurs; wherein the equipment information is used to reflect the aluminum single plate production equipment related to the production response event; executing a response mechanism based on the production response event and the device information; The executing a response mechanism based on the production response event and the device information includes: Acquire location information of the equipment information; wherein the location information is used to reflect the aluminum veneer production process of the aluminum veneer production equipment where the waiting event occurs; Obtaining bottleneck process information; wherein the bottleneck process information is used to reflect the aluminum veneer production process with the smallest production capacity of the production line and the corresponding aluminum veneer production equipment; executing a response mechanism based on the production response event, the location information, and the bottleneck process information; The executing a response mechanism based on the production response event, the location information, and the bottleneck process information includes: When the production response event is the waiting event, determining a first relative position of the aluminum veneer production process reflected by the position information and the aluminum veneer production process reflected by the bottleneck process information; If the aluminum veneer production process reflected by the first relative position matches the aluminum veneer production process reflected by the bottleneck process information, an equipment performance degradation warning is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the bottleneck process information is controlled to shut down; The executing a response mechanism based on the production response event, the location information and the bottleneck process information further includes: If the aluminum veneer production process reflected by the first relative position does not match the aluminum veneer production process reflected by the bottleneck process information, then calculating the difference between a first production capacity of the aluminum veneer production process reflected by the first relative position and a second production capacity in the bottleneck process information to obtain a capacity difference; comparing the production capacity difference with a preset threshold; If the production capacity difference is less than the preset threshold, an early warning of equipment performance degradation is issued, and the aluminum veneer production equipment before the aluminum veneer production equipment reflected by the position information is controlled to shut down for maintenance; If the production capacity difference is greater than or equal to the preset threshold, the aluminum single plate production equipment is controlled to continue production.
5. An intelligent monitoring device for aluminum veneer production, characterized in that: The method comprises a feeding device, a production device and a control device, wherein the control device is electrically connected to the feeding device and the production device, and the control device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, and when the processor executes the computer program, the method according to any one of claims 1 to 3 is implemented.