Building maintenance and updating method and device based on BIM
The BIM-based building maintenance and update method solves the problems of project node conflicts and safety hazards in traditional project management methods, improves the efficiency and safety of building maintenance and update, and ensures the safety of building users and constructors.
Patent Information
- Application Number
- CN202411147975.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-21
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-08-21
AI Technical Summary
Existing building maintenance and renewal project management methods are mostly traditional multi-point, manual management, which leads to project node conflicts, low efficiency, and potential safety hazards, affecting the safety of building users and constructors.
The BIM-based building maintenance update method is used to obtain collaborative design demand information, generate maintenance task information, and adjust task information according to task execution conditions to ensure the accuracy and efficiency of task execution and reduce project node conflicts.
It improves the execution efficiency and accuracy of building maintenance and update projects, reduces the incidence of project node conflicts, and ensures the safety of life and property of building users and constructors.
Smart Images

Figure CN118674232B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of BIM technology, and in particular to a BIM-based building maintenance and updating method and device. Background Art
[0002] With the continuous development of society, more and more early buildings have become old buildings. In order to make the old buildings continue to play a role, the work of maintaining and renovating old buildings has become particularly important.
[0003] However, for building maintenance and renovation projects, in addition to executing actual engineering operations, project management is also particularly important. Efficient project management can improve the execution efficiency of building maintenance and renovation projects. However, practice has found that the existing technology mostly adopts traditional multi-point, manual management methods for project management, that is, each work group of the building maintenance and renovation project manages the engineering operations of its work group at a single point. In this way, there will be conflicts in engineering nodes when cross-operations between work groups, which not only affects the execution efficiency of the building maintenance and renovation project, but also has certain safety hazards, which is not conducive to protecting the life and property safety of the users of the maintained buildings, nor is it conducive to protecting the life and property safety of the construction workers.
[0004] It can be seen that it is particularly important to propose a technical solution to improve the efficiency of building maintenance and renewal. Summary of the invention
[0005] The present invention provides a building maintenance and updating method and device based on BIM, which can improve the building maintenance and updating efficiency.
[0006] In order to solve the above technical problems, the first aspect of the present invention discloses a BIM-based building maintenance and updating method, the method comprising:
[0007] Obtain collaborative design requirements information;
[0008] Generate first maintenance task information according to the collaborative design requirement information and the preset BIM model;
[0009] Determine whether the first maintenance task information satisfies the task execution condition corresponding to the collaborative design requirement information. When it is determined that the first maintenance task information does not satisfy the task execution condition, adjust the first maintenance task information according to the task execution condition to obtain second maintenance task information. The first maintenance task information or the second maintenance task information is used to indicate the execution of a building maintenance and renovation project. The collaborative design requirement information is determined based on the project engineering information of the building maintenance and renovation project.
[0010] As an optional implementation, in the first aspect of the present invention, the building maintenance and renewal project includes at least one professional group, the collaborative design requirement information includes collaborative design requirement sub-information of each professional group, and the generating of the first maintenance task information according to the collaborative design requirement information and the preset BIM model includes:
[0011] For each of the professional groups, determining the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information of the professional group and the preset BIM model;
[0012] The first maintenance task information is generated according to all the maintenance task sub-information.
[0013] As an optional implementation, in the first aspect of the present invention, the preset BIM model includes at least one BIM professional sub-model, and each professional group has at least one corresponding BIM professional sub-model; for each professional group, determining the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information and the preset BIM model of the professional group includes:
[0014] For each of the BIM professional sub-models, according to the collaborative design requirement sub-information of the professional group and the BIM professional sub-model, determine the professional task sub-information of the professional group corresponding to the BIM professional sub-model; according to the preset task execution process model, judge whether there are at least two target professional task sub-information that meet the preset conflict condition among all the professional task sub-information of the professional group; when it is judged that there are at least two target professional task sub-information among all the professional task sub-information of the professional group, adjust each of the target professional task sub-information according to the preset task execution process model, and re-trigger the execution of the operation of judging whether there are at least two target professional task sub-information that meet the preset conflict condition among all the professional task sub-information of the professional group according to the preset task execution process model;
[0015] When it is determined that at least two of the target professional task sub-information do not exist in all the professional task sub-information of the professional group, the maintenance task sub-information of the professional group is determined based on all the professional task sub-information.
[0016] As an optional implementation manner, in the first aspect of the present invention, the determining whether the first maintenance task information satisfies the task execution condition corresponding to the collaborative design requirement information includes:
[0017] Determine, according to the first maintenance task information, at least one target area of the building maintenance and renewal project and an expected maintenance effect of each of the target areas;
[0018] For each of the target areas, current status information of the target area is obtained; based on the current status information, whether the target area meets the area configuration condition of the expected maintenance effect is determined; when it is determined that the target area does not meet the area configuration condition of the expected maintenance effect, determining that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information;
[0019] And, adjusting the first maintenance task information according to the task execution condition to obtain the second maintenance task information includes:
[0020] Obtaining the preset protection priority of the target area;
[0021] Determine whether the preset protection priority is greater than or equal to a protection priority threshold, and when it is determined that the preset protection priority is greater than or equal to the protection priority threshold, determine at least one associated area of the target area; adjust the target area and all the associated areas according to the expected maintenance effect to adjust the first maintenance task information to obtain second maintenance task information;
[0022] When it is determined that the preset protection priority is less than the protection priority threshold, the target area is adjusted according to the expected maintenance effect to adjust the first maintenance task information to obtain second maintenance task information.
[0023] As an optional implementation, in the first aspect of the present invention, the current status information includes at least one status information of regional area information, regional volume information, regional material layout information, regional temperature information, regional humidity information, regional particulate matter distribution information, regional gas distribution information, regional noise distribution information, regional wind speed information, regional wind direction information, regional light source information, regional object information, regional image information, regional audio information, regional target distribution information, and regional associated area information;
[0024] And, judging whether the target area meets the area configuration condition of the expected maintenance effect according to the current state information includes:
[0025] Analyzing the current configuration information of the target area according to the current state information;
[0026] generating simulation control parameters according to the expected maintenance effect;
[0027] generating desired configuration information of the target area according to the simulation control parameter and the first maintenance task information;
[0028] Generate a simulated maintenance effect of the target area according to the expected configuration information and the current configuration information;
[0029] It is determined whether the simulated maintenance effect matches the expected maintenance effect. When it is determined that the simulated maintenance effect does not match the expected maintenance effect, it is determined that the target area does not meet the area configuration condition of the expected maintenance effect.
[0030] As an optional implementation manner, in the first aspect of the present invention, before obtaining the collaborative design requirement information, the method further includes:
[0031] Obtaining the project engineering information of the building maintenance and renovation project;
[0032] Analyze at least one target item of the building maintenance and renovation project according to the project engineering information and the preset BIM model, each of the target items having a corresponding preset priority value;
[0033] For each of the target items, according to the target item and the corresponding preset priority value, calculate the current priority value of the target item; determine whether the current priority value is greater than or equal to the preset priority threshold, and when it is determined that the current priority value is greater than or equal to the preset priority threshold, determine the target item as a key item;
[0034] And, the obtaining of collaborative design requirement information includes:
[0035] Based on all the key items, the collaborative design requirement information is determined.
[0036] As an optional implementation manner, in the first aspect of the present invention, determining the collaborative design requirement information according to all the key items includes:
[0037] For each of the key items, determining at least one associated item of the key item among all the target items according to the project engineering information and the key item;
[0038] For each of the associated items, determining an associated value between the associated item and the key item;
[0039] According to the association value of the association item and the current priority value of the association item, judging whether the association item satisfies a preset supplementary maintenance condition, and when judging that the association item satisfies the preset supplementary maintenance condition, determining the association item as a supplementary key item;
[0040] The collaborative design requirement information is determined based on all the key items and all the supplementary key items.
[0041] The second aspect of the present invention discloses a BIM-based building maintenance and updating device, the device comprising:
[0042] The first acquisition module is used to acquire collaborative design requirement information;
[0043] A generating module, configured to generate first maintenance task information according to the collaborative design requirement information and a preset BIM model;
[0044] A first judgment module, used to judge whether the first maintenance task information meets the task execution condition corresponding to the collaborative design requirement information;
[0045] An adjustment module is used to adjust the first maintenance task information according to the task execution condition to obtain second maintenance task information when the first judgment module determines that the first maintenance task information does not meet the task execution condition. The first maintenance task information or the second maintenance task information is used to indicate the execution of the building maintenance and renewal project, and the collaborative design requirement information is determined based on the project engineering information of the building maintenance and renewal project.
[0046] As an optional implementation, in the second aspect of the present invention, the building maintenance and renewal project includes at least one professional group, the collaborative design requirement information includes collaborative design requirement sub-information of each professional group, and the generation module generates the first maintenance task information according to the collaborative design requirement information and the preset BIM model in a specific manner including:
[0047] For each of the professional groups, determining the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information of the professional group and the preset BIM model;
[0048] The first maintenance task information is generated according to all the maintenance task sub-information.
[0049] As an optional implementation, in the second aspect of the present invention, the preset BIM model includes at least one BIM professional sub-model, and each professional group has at least one corresponding BIM professional sub-model; for each professional group, the generation module determines the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information and the preset BIM model of the professional group. The specific manner includes:
[0050] For each of the BIM professional sub-models, according to the collaborative design requirement sub-information of the professional group and the BIM professional sub-model, determine the professional task sub-information of the professional group corresponding to the BIM professional sub-model; according to the preset task execution process model, judge whether there are at least two target professional task sub-information that meet the preset conflict condition among all the professional task sub-information of the professional group; when it is judged that there are at least two target professional task sub-information among all the professional task sub-information of the professional group, adjust each of the target professional task sub-information according to the preset task execution process model, and re-trigger the execution of the operation of judging whether there are at least two target professional task sub-information that meet the preset conflict condition among all the professional task sub-information of the professional group according to the preset task execution process model;
[0051] When it is determined that at least two of the target professional task sub-information do not exist in all the professional task sub-information of the professional group, the maintenance task sub-information of the professional group is determined based on all the professional task sub-information.
[0052] As an optional implementation manner, in the second aspect of the present invention, the specific manner in which the first judgment module judges whether the first maintenance task information satisfies the task execution condition corresponding to the collaborative design requirement information includes:
[0053] Determine, according to the first maintenance task information, at least one target area of the building maintenance and renewal project and an expected maintenance effect of each of the target areas;
[0054] For each of the target areas, current status information of the target area is obtained; based on the current status information, whether the target area meets the area configuration condition of the expected maintenance effect is determined; when it is determined that the target area does not meet the area configuration condition of the expected maintenance effect, determining that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information;
[0055] Furthermore, the adjustment module adjusts the first maintenance task information according to the task execution condition to obtain the second maintenance task information in a specific manner including:
[0056] Obtaining the preset protection priority of the target area;
[0057] Determine whether the preset protection priority is greater than or equal to a protection priority threshold, and when it is determined that the preset protection priority is greater than or equal to the protection priority threshold, determine at least one associated area of the target area; adjust the target area and all the associated areas according to the expected maintenance effect to adjust the first maintenance task information to obtain second maintenance task information;
[0058] When it is determined that the preset protection priority is less than the protection priority threshold, the target area is adjusted according to the expected maintenance effect to adjust the first maintenance task information to obtain second maintenance task information.
[0059] As an optional implementation, in the second aspect of the present invention, the current status information includes at least one status information of regional area information, regional volume information, regional material layout information, regional temperature information, regional humidity information, regional particulate matter distribution information, regional gas distribution information, regional noise distribution information, regional wind speed information, regional wind direction information, regional light source information, regional object information, regional image information, regional audio information, regional target distribution information, and regional associated area information;
[0060] And, the first judgment module judges whether the target area meets the area configuration condition of the expected maintenance effect according to the current state information in a specific manner including:
[0061] Analyzing the current configuration information of the target area according to the current state information;
[0062] generating simulation control parameters according to the expected maintenance effect;
[0063] generating desired configuration information of the target area according to the simulation control parameter and the first maintenance task information;
[0064] Generate a simulated maintenance effect of the target area according to the expected configuration information and the current configuration information;
[0065] It is determined whether the simulated maintenance effect matches the expected maintenance effect. When it is determined that the simulated maintenance effect does not match the expected maintenance effect, it is determined that the target area does not meet the area configuration condition of the expected maintenance effect.
[0066] As an optional implementation, in the second aspect of the present invention, the device further includes:
[0067] A second acquisition module is used to acquire the project engineering information of the building maintenance and renewal project before the first acquisition module acquires the collaborative design requirement information;
[0068] An analysis module, used to analyze at least one target item of the building maintenance and renovation project according to the project engineering information and a preset BIM model, each of the target items having a corresponding preset priority value;
[0069] A calculation module, configured to calculate, for each of the target items, a current priority value of the target item according to the target item and the corresponding preset priority value;
[0070] A second judgment module is used to judge whether the current priority value is greater than or equal to a preset priority threshold;
[0071] a determination module, configured to determine the target item as a key item when the second determination module determines that the current priority value is greater than or equal to the preset priority threshold;
[0072] And, the specific manner in which the first acquisition module acquires the collaborative design requirement information includes:
[0073] Based on all the key items, the collaborative design requirement information is determined.
[0074] As an optional implementation, in the second aspect of the present invention, the specific manner in which the first acquisition module determines the collaborative design requirement information according to all the key items includes:
[0075] For each of the key items, determining at least one associated item of the key item among all the target items according to the project engineering information and the key item;
[0076] For each of the associated items, determining an associated value between the associated item and the key item;
[0077] According to the association value of the association item and the current priority value of the association item, judging whether the association item satisfies a preset supplementary maintenance condition, and when judging that the association item satisfies the preset supplementary maintenance condition, determining the association item as a supplementary key item;
[0078] The collaborative design requirement information is determined based on all the key items and all the supplementary key items.
[0079] The third aspect of the present invention discloses another BIM-based building maintenance and updating device, the device comprising:
[0080] A memory storing executable program code;
[0081] a processor coupled to the memory;
[0082] The processor calls the executable program code stored in the memory to execute the BIM-based building maintenance and updating method disclosed in the first aspect of the present invention.
[0083] The fourth aspect of the present invention discloses a computer storage medium, which stores computer instructions. When the computer instructions are called, they are used to execute the BIM-based building maintenance and updating method disclosed in the first aspect of the present invention.
[0084] Compared with the prior art, the embodiments of the present invention have the following beneficial effects:
[0085] In the embodiment of the present invention, collaborative design requirement information is obtained; first maintenance task information is generated according to the collaborative design requirement information and the preset BIM model; it is determined whether the first maintenance task information meets the task execution condition corresponding to the collaborative design requirement information, and when it is determined that the first maintenance task information does not meet the task execution condition, the first maintenance task information is adjusted according to the task execution condition to obtain the second maintenance task information, and the first maintenance task information or the second maintenance task information is used to indicate the execution of the building maintenance and renewal project, and the collaborative design requirement information is determined according to the project engineering information of the building maintenance and renewal project. It can be seen that the implementation of the present invention can generate the first maintenance task information for indicating the execution of the building maintenance and renewal project according to the acquired collaborative design requirement information and the preset BIM model, improve the generation accuracy of the first maintenance task information, and when it is determined that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information, the first maintenance task information is adjusted according to the task execution condition to obtain the new second maintenance task information for indicating the execution of the building maintenance and renewal project, which can improve the efficiency of the building maintenance and renewal while ensuring the accuracy of the building maintenance and renewal, reduce the occurrence of engineering node conflicts during the execution of the building maintenance and renewal project, and is conducive to protecting the life and property safety of the users of the maintained building and the life and property safety of the constructors. BRIEF DESCRIPTION OF THE DRAWINGS
[0086] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0087] Figure 1 It is a flow chart of a BIM-based building maintenance and updating method disclosed in an embodiment of the present invention;
[0088] Figure 2 It is a flowchart of another BIM-based building maintenance and updating method disclosed in an embodiment of the present invention;
[0089] Figure 3 It is a structural schematic diagram of a BIM-based building maintenance and updating device disclosed in an embodiment of the present invention;
[0090] Figure 4 It is a structural schematic diagram of another BIM-based building maintenance and updating device disclosed in an embodiment of the present invention;
[0091] Figure 5 It is a structural schematic diagram of another BIM-based building maintenance and renewal device disclosed in an embodiment of the present invention. DETAILED DESCRIPTION
[0092] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0093] The terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish different objects rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, device, product or end including a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units inherent to these processes, methods, products or ends.
[0094] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0095] The present invention discloses a method and device for building maintenance and updating based on BIM, which can generate first maintenance task information for indicating the execution of building maintenance and updating projects according to the acquired collaborative design requirement information and the preset BIM model, improve the generation accuracy of the first maintenance task information, and when it is judged that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information, adjust the first maintenance task information according to the task execution condition to obtain new second maintenance task information for indicating the execution of building maintenance and updating projects, while ensuring the accuracy of building maintenance and updating, improve the efficiency of building maintenance and updating, reduce the occurrence of engineering node conflicts during the execution of building maintenance and updating projects, and help to protect the life and property safety of users of the maintained buildings and the life and property safety of constructors. The following are detailed descriptions.
[0096] Embodiment 1
[0097] See also Figure 1 , Figure 1 1 is a flow chart of a BIM-based building maintenance and updating method disclosed in an embodiment of the present invention. Figure 1The described BIM-based building maintenance and update method can be applied to building maintenance equipment, such as building maintenance and update systems, building management systems, etc. It can also be applied to intelligent devices associated with building maintenance equipment, such as: intelligent devices that have a communication electrical connection / electromagnetic connection / wireless connection relationship with building maintenance equipment, and the intelligent devices include but are not limited to one or more of cloud devices, edge computing devices, relay devices, base station devices, urban management devices, intelligent network devices, energy-saving devices, and safety protection devices, which are not limited in the embodiments of the present invention. Figure 1 As shown, the BIM-based building maintenance and updating method may include the following operations:
[0098] 101. Obtain collaborative design requirement information.
[0099] In the embodiment of the present invention, the above-mentioned collaborative design requirement information is used to represent the collaborative design information for the current building maintenance and renewal project requirements that all work groups in the building maintenance and renewal project need to execute.
[0100] 102. Generate first maintenance task information according to the collaborative design requirement information and the preset BIM model.
[0101] In the embodiment of the present invention, the above-mentioned BIM model is fully called Building Information Modeling model.
[0102] 103. Determine whether the first maintenance task information satisfies a task execution condition corresponding to the collaborative design requirement information.
[0103] 104. When it is determined that the first maintenance task information does not meet the task execution conditions, the first maintenance task information is adjusted according to the task execution conditions to obtain the second maintenance task information. The first maintenance task information or the second maintenance task information is used to indicate the execution of the building maintenance and renewal project. The collaborative design requirement information is determined based on the project engineering information of the building maintenance and renewal project.
[0104] It should be noted that the building maintenance and renovation project in the embodiment of the present invention can represent a specific engineering operation or an engineering project. When it is an engineering project, the building maintenance and renovation project includes the above-mentioned operation group, and there is no ambiguity here.
[0105] In an embodiment of the present invention, as an optional implementation, when it is determined that the first maintenance task information does not meet the task execution conditions, the specific engineering operations of the above-mentioned building maintenance and renewal project can be directly instructed to be executed through the first maintenance task information.
[0106] In the embodiment of the present invention, further optionally, in the process of executing specific engineering operations in the building maintenance and renovation project, the specific operations of step 101 to step 104 may be continuously and cyclically executed.
[0107] It can be seen that the implementation of the embodiment of the present invention can generate first maintenance task information for indicating the execution of a building maintenance and renewal project according to the acquired collaborative design requirement information and the preset BIM model, thereby improving the generation accuracy of the first maintenance task information, and when it is determined that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information, the first maintenance task information is adjusted according to the task execution condition to obtain new second maintenance task information for indicating the execution of a building maintenance and renewal project. This can improve the efficiency of building maintenance and renewal while ensuring the accuracy of building maintenance and renewal, reduce the occurrence of project node conflicts during the execution of building maintenance and renewal projects, and is beneficial to protecting the life and property safety of users of the maintained buildings and the life and property safety of constructors.
[0108] In the embodiment of the present invention, as an optional implementation, the above-mentioned building maintenance and renewal project includes at least one professional group. Optionally, the above-mentioned professional group can represent an engineering team, a subcontracting team, a responsible group, etc., similar to the above-mentioned work group. The collaborative design requirement information includes the collaborative design requirement sub-information of each professional group. The above-mentioned generation of the first maintenance task information according to the collaborative design requirement information and the preset BIM model may include the following operations:
[0109] For each professional group, the maintenance task sub-information of the professional group is determined according to the collaborative design requirement sub-information of the professional group and the preset BIM model.
[0110] Generate first maintenance task information according to all maintenance task sub-information.
[0111] It can be seen that the implementation of this optional embodiment can determine the maintenance task sub-information of each professional group based on the collaborative design requirement sub-information and the preset BIM model of each professional group, improve the accuracy of determining the maintenance task sub-information, and generate the first maintenance task information through comprehensive sorting based on all the maintenance task sub-information, thereby improving the generation accuracy of the first maintenance task information, which is conducive to the preliminary integration of the maintenance task sub-information of all professional groups and is conducive to improving the efficiency of building maintenance and updating.
[0112] In this optional embodiment, as an optional implementation, the above-mentioned preset BIM model includes at least one BIM professional sub-model, and each professional group has at least one corresponding BIM professional sub-model; for each professional group, determining the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information of the professional group and the preset BIM model may include the following operations:
[0113] For each BIM professional sub-model, the professional task sub-information of the professional group corresponding to the BIM professional sub-model is determined according to the collaborative design requirement sub-information of the professional group and the BIM professional sub-model; according to the preset task execution process model, it is judged whether there are at least two target professional task sub-information that meet the preset conflict conditions among all the professional task sub-information of the professional group; when it is judged that there are at least two target professional task sub-information among all the professional task sub-information of the professional group, each target professional task sub-information is adjusted according to the preset task execution process model, and the operation of judging whether there are at least two target professional task sub-information that meet the preset conflict conditions among all the professional task sub-information of the professional group according to the preset task execution process model is re-triggered.
[0114] When it is determined that at least two target professional task sub-information do not exist in all the professional task sub-information of the professional group, the maintenance task sub-information of the professional group is determined based on all the professional task sub-information.
[0115] In this optional embodiment, optionally, the above-mentioned BIM professional sub-model may include but is not limited to a BIM sub-model for early project planning, a BIM sub-model for the design stage, a BIM sub-model for the construction stage, and a BIM sub-model for the operation and maintenance stage. Specifically, it may also include BIM sub-models for at least one scenario such as site, building, structure, machinery, electrical, maintenance and update, structural components, exterior protection components, interior components, kitchen and bathroom components, equipment components, intelligent components, and community supporting components.
[0116] In this optional embodiment, further optionally, the above-mentioned preset conflict conditions include at least one of time node conflict, conflict between prior execution and subsequent execution steps, operator conflict, material usage conflict, operation area conflict, construction accident, account node conflict, etc.
[0117] It can be seen that the implementation of this optional embodiment can further determine the professional task sub-information of each professional group corresponding to each BIM professional sub-model based on the collaborative design requirement sub-information of each professional group and each BIM professional sub-model, thereby realizing the determination of many-to-many professional task sub-information and improving the accuracy of the determination of professional task sub-information. Furthermore, when there are at least two target professional task sub-information in all the professional task sub-information of each professional group, each target professional task sub-information is adjusted according to the preset task execution process model, and the operation of re-triggering the execution according to the preset task execution process model to determine whether there are at least two target professional task sub-information that meet the preset conflict conditions in all the professional task sub-information of the professional group can be further improved. The accuracy of the determination of the professional task sub-information of the building maintenance and renewal project is beneficial to improving the maintenance task sub-information of each professional group, thereby reducing the determination conflict rate of the maintenance task sub-information from the basic stage and at the internal level of each professional group, which is beneficial to improving the efficiency of building maintenance and renewal, and improving the generation accuracy of the first maintenance task information from all professional group levels in the later stage, thereby further improving the efficiency of building maintenance and renewal.
[0118] In the embodiment of the present invention, as another optional implementation, before obtaining the collaborative design requirement information, the method may further include the following operations:
[0119] Get project information for building maintenance and renovation projects.
[0120] According to the project engineering information and the preset BIM model, at least one target item of the building maintenance and renovation project is analyzed, and each target item has a corresponding preset priority value.
[0121] For each target item, the current priority value of the target item is calculated based on the target item and the corresponding preset priority value; it is determined whether the current priority value is greater than or equal to the preset priority threshold. When it is determined that the current priority value is greater than or equal to the preset priority threshold, the target item is determined as a key item.
[0122] And, obtaining collaborative design requirement information may include the following operations:
[0123] Determine collaborative design requirement information based on all key items.
[0124] In this optional embodiment, the above-mentioned professional group executes the above-mentioned target items.
[0125] It can be seen that the implementation of this optional embodiment can analyze at least one target item of the building maintenance and renovation project through the acquired project engineering information and the preset BIM model of the building maintenance and renovation project, and for each target item, calculate the current priority value of the target item according to the target item and the corresponding preset priority value, and when it is judged that the current priority value is greater than or equal to the preset priority threshold, the target item is determined as a key item, thereby improving the accuracy of determining the key items, and thereby determining the collaborative design requirement information based on all key items, thereby improving the accuracy of determining the collaborative design requirement information, and being able to improve the accuracy of building maintenance and renewal from the source.
[0126] In this optional embodiment, as an optional implementation mode, the above-mentioned determining the collaborative design requirement information according to all key items may include the following operations:
[0127] For each key item, at least one associated item of the key item among all target items is determined based on the project engineering information and the key item.
[0128] For each association term, an association value between the association term and the key term is determined.
[0129] According to the association value of the association item and the current priority value of the association item, it is determined whether the association item meets the preset supplementary maintenance condition. When it is determined that the association item meets the preset supplementary maintenance condition, the association item is determined as a supplementary key item.
[0130] Determine collaborative design requirement information based on all key items and all supplementary key items.
[0131] It can be seen that the implementation of this optional embodiment can also determine all the key items of all building maintenance and renovation projects, and combine the project engineering information of the building maintenance and renovation projects. For each key item, it is possible to determine at least one associated item of the key item in all target items. For each associated item, determine the association value between the associated item and the key item. According to the association value of the associated item and the current priority value of the associated item, judge whether the associated item meets the preset supplementary maintenance condition. When the judgment result is yes, determine the associated item as a supplementary key item, thereby improving the accuracy of determining the supplementary key items, thereby further improving the accuracy of determining the collaborative design requirement information.
[0132] Embodiment 2
[0133] See also Figure 2 , Figure 2 1 is a flow chart of another BIM-based building maintenance and update method disclosed in an embodiment of the present invention. Figure 2The described BIM-based building maintenance and update method can be applied to building maintenance equipment, such as building maintenance and update systems, building management systems, etc. It can also be applied to intelligent devices associated with building maintenance equipment, such as: intelligent devices that have a communication electrical connection / electromagnetic connection / wireless connection relationship with building maintenance equipment, and the intelligent devices include but are not limited to one or more of cloud devices, edge computing devices, relay devices, base station devices, urban management devices, intelligent network devices, energy-saving devices, and safety protection devices, which are not limited in the embodiments of the present invention. Figure 2 As shown, the BIM-based building maintenance and updating method may include the following operations:
[0134] 201. Obtain collaborative design requirement information.
[0135] 202. Generate first maintenance task information according to the collaborative design requirement information and the preset BIM model.
[0136] 203. Determine at least one target area of the building maintenance and renewal project and an expected maintenance effect of each target area according to the first maintenance task information.
[0137] In the embodiment of the present invention, optionally, the expected maintenance effect is determined after determining a first simulated maintenance effect that simulates the first maintenance task information based on the first maintenance task information.
[0138] Further, optionally, after determining the above-mentioned first simulated maintenance effect, it is also possible to determine whether the first simulated maintenance effect matches the expected maintenance effect, and when the judgment result is no, further fine-tune the above-mentioned first maintenance task information based on the expected maintenance effect.
[0139] Therefore, in the subsequent steps 204, 205, 206 and 207, the first maintenance task information based on is the first maintenance task information after fine-tuning.
[0140] 204. For each target area, obtain current status information of the target area.
[0141] 205. Determine, based on the current status information, whether the target area meets the area configuration condition for the expected maintenance effect.
[0142] 206. When it is determined that the target area does not satisfy the area configuration condition of the expected maintenance effect, it is determined that the first maintenance task information does not satisfy the task execution condition corresponding to the collaborative design requirement information.
[0143] 207. When it is determined that the first maintenance task information does not meet the task execution conditions, the first maintenance task information is adjusted according to the task execution conditions to obtain the second maintenance task information. The first maintenance task information or the second maintenance task information is used to indicate the execution of the building maintenance and renewal project. The collaborative design requirement information is determined based on the project engineering information of the building maintenance and renewal project.
[0144] In the embodiment of the present invention, for the supplementary explanation of step 201, step 202 and step 207, please refer to the supplementary explanation of step 101, step 102 and step 104 in the first embodiment, and the embodiment of the present invention will not repeat them any more.
[0145] It can be seen that the implementation of the embodiment of the present invention can, after obtaining the first maintenance task information, determine at least one target area of the building maintenance and renewal project and the expected maintenance effect of each target area, as well as the current status information of each target area, to determine whether the target area meets the area configuration conditions for the expected maintenance effect, so that when the judgment result is no, it is determined that the first maintenance task information does not meet the task execution conditions corresponding to the collaborative design requirement information, thereby improving the accuracy and executability of determining that the first maintenance task information does not meet the task execution conditions corresponding to the collaborative design requirement information, which is conducive to further improving the accuracy of determining the second maintenance information, and is conducive to improving the building maintenance and renewal efficiency and update accuracy.
[0146] In the embodiment of the present invention, as an optional implementation mode, the above-mentioned adjusting the first maintenance task information according to the task execution condition to obtain the second maintenance task information may include the following operations:
[0147] Get the preset protection priority of the target area.
[0148] Determine whether the preset protection priority is greater than or equal to the protection priority threshold. When it is determined that the preset protection priority is greater than or equal to the protection priority threshold, determine at least one associated area of the target area; according to the expected maintenance effect, adjust the target area and all associated areas to adjust the first maintenance task information to obtain the second maintenance task information.
[0149] When it is determined that the preset protection priority is less than the protection priority threshold, the target area is adjusted according to the expected maintenance effect to adjust the first maintenance task information to obtain the second maintenance task information.
[0150] It can be seen that the implementation of this optional embodiment can determine whether to collaboratively adjust the first maintenance task information through at least one associated area to obtain the second maintenance task information by judging whether the preset protection priority of the target area is greater than or equal to the protection priority threshold, after determining that the target area does not meet the area configuration conditions for the expected maintenance effect and that the first maintenance task information does not meet the task execution conditions corresponding to the collaborative design requirement information. This can further improve the accuracy of building maintenance and updating on the basis of improving the efficiency of building maintenance and updating.
[0151] In an embodiment of the present invention, as another optional implementation, the above-mentioned current status information includes at least one status information of regional area information, regional volume information, regional material layout information, regional temperature information, regional humidity information, regional particulate matter distribution information, regional gas distribution information, regional noise distribution information, regional wind speed information, regional wind direction information, regional light source information, regional object information, regional image information, regional audio information, regional target distribution information, and regional associated area information;
[0152] Furthermore, judging whether the target area meets the area configuration condition of the expected maintenance effect according to the current state information may include the following operations:
[0153] According to the current status information, analyze the current configuration information of the target area.
[0154] Generate simulation control parameters based on the expected maintenance effect.
[0155] The desired configuration information of the target area is generated according to the simulation control parameters and the first maintenance task information.
[0156] A simulated maintenance effect of the target area is generated according to the expected configuration information and the current configuration information.
[0157] It is determined whether the simulated maintenance effect matches the expected maintenance effect. When it is determined that the simulated maintenance effect does not match the expected maintenance effect, it is determined that the target area does not meet the area configuration condition of the expected maintenance effect.
[0158] It can be seen that the implementation of this optional embodiment can analyze the current configuration information of the target area based on at least one state information of the target area mentioned above, generate simulation control parameters of the expected maintenance effect based on the expected maintenance effect, and then generate the expected configuration information of the target area based on the simulation control parameters and the first maintenance task information, and generate the second simulated maintenance effect under the expected maintenance effect of the target area by combining the expected configuration information and the current configuration information. When it is judged that the second simulated maintenance effect does not match the expected simulated maintenance effect, it is determined that the target area does not meet the area configuration condition of the expected maintenance effect. The second simulated maintenance effect is used to distinguish it from the first simulated maintenance effect mentioned above in the embodiment of the present invention, and the specific name in the claims shall prevail. It can be seen that the accuracy of determining the area configuration condition that the target area does not meet the expected maintenance effect can be improved, which is conducive to further improving the accuracy and executability of determining that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information, which is conducive to further improving the accuracy of determining the second maintenance information, and is conducive to improving the efficiency and accuracy of building maintenance updates.
[0159] Embodiment 3
[0160] See also Figure 3 , Figure 3 : is a structural diagram of a BIM-based building maintenance and updating device disclosed in an embodiment of the present invention. Figure 3 The described BIM-based building maintenance and renewal device can be used in building maintenance equipment, such as building maintenance and renewal systems, building management systems, etc. It can also be applied to intelligent devices associated with building maintenance equipment, such as: intelligent devices that have a communication electrical connection / electromagnetic connection / wireless connection relationship with building maintenance equipment, and the intelligent devices include but are not limited to one or more of cloud devices, edge computing devices, relay devices, base station devices, urban management devices, intelligent network devices, energy-saving devices, and safety protection devices, which are not limited in the embodiments of the present invention. Figure 3 As shown, the BIM-based building maintenance and updating device may include:
[0161] The first acquisition module 301 is used to acquire collaborative design requirement information.
[0162] The generating module 302 is used to generate first maintenance task information according to the collaborative design requirement information and the preset BIM model.
[0163] The first judgment module 303 is used to judge whether the first maintenance task information meets the task execution condition corresponding to the collaborative design requirement information.
[0164] The adjustment module 304 is used to adjust the first maintenance task information according to the task execution condition to obtain the second maintenance task information when the first judgment module 303 determines that the first maintenance task information does not meet the task execution condition. The first maintenance task information or the second maintenance task information is used to indicate the execution of the building maintenance and renewal project. The collaborative design requirement information is determined based on the project engineering information of the building maintenance and renewal project.
[0165] It can be seen that the implementation of the embodiment of the present invention can generate first maintenance task information for indicating the execution of a building maintenance and renewal project according to the acquired collaborative design requirement information and the preset BIM model, thereby improving the generation accuracy of the first maintenance task information, and when it is determined that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information, the first maintenance task information is adjusted according to the task execution condition to obtain new second maintenance task information for indicating the execution of a building maintenance and renewal project. This can improve the efficiency of building maintenance and renewal while ensuring the accuracy of building maintenance and renewal, reduce the occurrence of project node conflicts during the execution of building maintenance and renewal projects, and is beneficial to protecting the life and property safety of users of the maintained buildings and the life and property safety of constructors.
[0166] In the embodiment of the present invention, as an optional implementation, the building maintenance and renewal project includes at least one professional group, the collaborative design requirement information includes collaborative design requirement sub-information of each professional group, and the generation module 302 generates the first maintenance task information according to the collaborative design requirement information and the preset BIM model in a specific manner including:
[0167] For each professional group, the maintenance task sub-information of the professional group is determined according to the collaborative design requirement sub-information of the professional group and the preset BIM model.
[0168] Generate first maintenance task information according to all maintenance task sub-information.
[0169] It can be seen that the implementation of this optional embodiment can determine the maintenance task sub-information of each professional group based on the collaborative design requirement sub-information and the preset BIM model of each professional group, improve the accuracy of determining the maintenance task sub-information, and generate the first maintenance task information through comprehensive sorting based on all the maintenance task sub-information, thereby improving the generation accuracy of the first maintenance task information, which is conducive to the preliminary integration of the maintenance task sub-information of all professional groups and is conducive to improving the efficiency of building maintenance and updating.
[0170] In this optional embodiment, as an optional implementation, the above-mentioned preset BIM model includes at least one BIM professional sub-model, and each professional group has at least one corresponding BIM professional sub-model; for each professional group, the above-mentioned generation module 302 determines the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information of the professional group and the preset BIM model. The specific manner includes:
[0171] For each BIM professional sub-model, the professional task sub-information of the professional group corresponding to the BIM professional sub-model is determined according to the collaborative design requirement sub-information of the professional group and the BIM professional sub-model; according to the preset task execution process model, it is judged whether there are at least two target professional task sub-information that meet the preset conflict conditions among all the professional task sub-information of the professional group; when it is judged that there are at least two target professional task sub-information among all the professional task sub-information of the professional group, each target professional task sub-information is adjusted according to the preset task execution process model, and the operation of judging whether there are at least two target professional task sub-information that meet the preset conflict conditions among all the professional task sub-information of the professional group according to the preset task execution process model is re-triggered.
[0172] When it is determined that at least two target professional task sub-information do not exist in all the professional task sub-information of the professional group, the maintenance task sub-information of the professional group is determined based on all the professional task sub-information.
[0173] It can be seen that the implementation of this optional embodiment can further determine the professional task sub-information of each professional group corresponding to each BIM professional sub-model based on the collaborative design requirement sub-information of each professional group and each BIM professional sub-model, thereby realizing the determination of many-to-many professional task sub-information and improving the accuracy of the determination of professional task sub-information. Furthermore, when there are at least two target professional task sub-information in all the professional task sub-information of each professional group, each target professional task sub-information is adjusted according to the preset task execution process model, and the operation of re-triggering the execution according to the preset task execution process model to determine whether there are at least two target professional task sub-information that meet the preset conflict conditions in all the professional task sub-information of the professional group can be further improved. The accuracy of the determination of the professional task sub-information of the building maintenance and renewal project is beneficial to improving the maintenance task sub-information of each professional group, thereby reducing the determination conflict rate of the maintenance task sub-information from the basic stage and at the internal level of each professional group, which is beneficial to improving the efficiency of building maintenance and renewal, and improving the generation accuracy of the first maintenance task information from all professional group levels in the later stage, thereby further improving the efficiency of building maintenance and renewal.
[0174] In the embodiment of the present invention, as another optional implementation, the specific manner in which the first determination module 303 determines whether the first maintenance task information satisfies the task execution condition corresponding to the collaborative design requirement information includes:
[0175] At least one target area of the building maintenance and renewal project and an expected maintenance effect of each target area are determined according to the first maintenance task information.
[0176] For each target area, obtain the current status information of the target area; based on the current status information, determine whether the target area meets the area configuration conditions for the expected maintenance effect; when it is determined that the target area does not meet the area configuration conditions for the expected maintenance effect, determine that the first maintenance task information does not meet the task execution conditions corresponding to the collaborative design requirement information.
[0177] It can be seen that the implementation of the embodiment of the present invention can, after obtaining the first maintenance task information, determine at least one target area of the building maintenance and renewal project and the expected maintenance effect of each target area, as well as the current status information of each target area, to determine whether the target area meets the area configuration conditions for the expected maintenance effect, so that when the judgment result is no, it is determined that the first maintenance task information does not meet the task execution conditions corresponding to the collaborative design requirement information, thereby improving the accuracy and executability of determining that the first maintenance task information does not meet the task execution conditions corresponding to the collaborative design requirement information, which is conducive to further improving the accuracy of determining the second maintenance information, and is conducive to improving the building maintenance and renewal efficiency and update accuracy.
[0178] In this optional embodiment, as an optional implementation, the above adjustment module 304 adjusts the first maintenance task information according to the task execution condition, and the specific manner of obtaining the second maintenance task information includes:
[0179] Get the preset protection priority of the target area.
[0180] Determine whether the preset protection priority is greater than or equal to the protection priority threshold. When it is determined that the preset protection priority is greater than or equal to the protection priority threshold, determine at least one associated area of the target area; according to the expected maintenance effect, adjust the target area and all associated areas to adjust the first maintenance task information to obtain the second maintenance task information.
[0181] When it is determined that the preset protection priority is less than the protection priority threshold, the target area is adjusted according to the expected maintenance effect to adjust the first maintenance task information to obtain the second maintenance task information.
[0182] It can be seen that the implementation of this optional embodiment can determine whether to collaboratively adjust the first maintenance task information through at least one associated area to obtain the second maintenance task information by judging whether the preset protection priority of the target area is greater than or equal to the protection priority threshold, after determining that the target area does not meet the area configuration conditions for the expected maintenance effect and that the first maintenance task information does not meet the task execution conditions corresponding to the collaborative design requirement information. This can further improve the accuracy of building maintenance and updating on the basis of improving the efficiency of building maintenance and updating.
[0183] In this optional embodiment, as another optional implementation, the above-mentioned current status information includes at least one status information of regional area information, regional volume information, regional material layout information, regional temperature information, regional humidity information, regional particulate matter distribution information, regional gas distribution information, regional noise distribution information, regional wind speed information, regional wind direction information, regional light source information, regional object information, regional image information, regional audio information, regional target distribution information, and regional associated area information;
[0184] Optionally, the first judgment module 303 judges whether the target area meets the area configuration condition of the expected maintenance effect according to the current state information in a specific manner including:
[0185] According to the current status information, analyze the current configuration information of the target area.
[0186] Generate simulation control parameters based on the expected maintenance effect.
[0187] The desired configuration information of the target area is generated according to the simulation control parameters and the first maintenance task information.
[0188] A simulated maintenance effect of the target area is generated according to the expected configuration information and the current configuration information.
[0189] It is determined whether the simulated maintenance effect matches the expected maintenance effect. When it is determined that the simulated maintenance effect does not match the expected maintenance effect, it is determined that the target area does not meet the area configuration condition of the expected maintenance effect.
[0190] It can be seen that the implementation of this optional embodiment can analyze the current configuration information of the target area based on at least one state information of the target area mentioned above, generate simulation control parameters of the expected maintenance effect based on the expected maintenance effect, and then generate the expected configuration information of the target area based on the simulation control parameters and the first maintenance task information, and generate the second simulated maintenance effect under the expected maintenance effect of the target area by combining the expected configuration information and the current configuration information. When it is judged that the second simulated maintenance effect does not match the expected simulated maintenance effect, it is determined that the target area does not meet the area configuration condition of the expected maintenance effect. The second simulated maintenance effect is used to distinguish it from the first simulated maintenance effect mentioned above in the embodiment of the present invention, and the specific name in the claims shall prevail. It can be seen that the accuracy of determining the area configuration condition that the target area does not meet the expected maintenance effect can be improved, which is conducive to further improving the accuracy and executability of determining that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information, which is conducive to further improving the accuracy of determining the second maintenance information, and is conducive to improving the efficiency and accuracy of building maintenance updates.
[0191] In an optional embodiment, if Figure 4 As shown, the device may also include:
[0192] The second acquisition module 305 is used to acquire project information of the building maintenance and renovation project before the first acquisition module 301 acquires the collaborative design requirement information.
[0193] The analysis module 306 is used to analyze at least one target item of the building maintenance and renovation project according to the project engineering information and the preset BIM model, and each target item has a corresponding preset priority value.
[0194] The calculation module 307 is used to calculate the current priority value of each target item according to the target item and the corresponding preset priority value.
[0195] The second determination module 308 is configured to determine whether the current priority value is greater than or equal to a preset priority threshold.
[0196] The determination module 309 is configured to determine the target item as a key item when the second determination module 308 determines that the current priority value is greater than or equal to a preset priority threshold.
[0197] Optionally, the specific manner in which the first acquisition module 301 acquires the collaborative design requirement information includes:
[0198] Determine collaborative design requirement information based on all key items.
[0199] It can be seen that the implementation of this optional embodiment can analyze at least one target item of the building maintenance and renovation project through the acquired project engineering information and the preset BIM model of the building maintenance and renovation project, and for each target item, calculate the current priority value of the target item according to the target item and the corresponding preset priority value, and when it is judged that the current priority value is greater than or equal to the preset priority threshold, the target item is determined as a key item, thereby improving the accuracy of determining the key items, and thereby determining the collaborative design requirement information based on all key items, thereby improving the accuracy of determining the collaborative design requirement information, and being able to improve the accuracy of building maintenance and renewal from the source.
[0200] In this optional embodiment, as an optional implementation, the specific manner in which the first acquisition module 301 determines the collaborative design requirement information according to all key items includes:
[0201] For each key item, at least one associated item of the key item among all target items is determined based on the project engineering information and the key item.
[0202] For each association term, an association value between the association term and the key term is determined.
[0203] According to the association value of the association item and the current priority value of the association item, it is determined whether the association item meets the preset supplementary maintenance condition. When it is determined that the association item meets the preset supplementary maintenance condition, the association item is determined as a supplementary key item.
[0204] Determine collaborative design requirement information based on all key items and all supplementary key items.
[0205] It can be seen that the implementation of this optional embodiment can also determine all the key items of all building maintenance and renovation projects, and combine the project engineering information of the building maintenance and renovation projects. For each key item, it is possible to determine at least one associated item of the key item in all target items. For each associated item, determine the association value between the associated item and the key item. According to the association value of the associated item and the current priority value of the associated item, judge whether the associated item meets the preset supplementary maintenance condition. When the judgment result is yes, determine the associated item as a supplementary key item, thereby improving the accuracy of determining the supplementary key items, thereby further improving the accuracy of determining the collaborative design requirement information.
[0206] Embodiment 4
[0207] See also Figure 5 , Figure 5 Schematic diagram of another BIM-based building maintenance and updating device disclosed in an embodiment of the present invention. Figure 5 As shown, the BIM-based building maintenance and updating device may include:
[0208] The memory 401 stores executable program codes.
[0209] A processor 402 is coupled to the memory 401 .
[0210] The processor 402 calls the executable program code stored in the memory 401 to execute the steps in the BIM-based building maintenance and updating method described in the first embodiment of the present invention or the second embodiment of the present invention.
[0211] Embodiment 5
[0212] An embodiment of the present invention discloses a computer storage medium, which stores computer instructions. When the computer instructions are called, they are used to execute the steps of the BIM-based building maintenance and updating method described in Embodiment 1 or Embodiment 2 of the present invention.
[0213] Embodiment 6
[0214] An embodiment of the present invention discloses a computer program product, which includes a non-transitory computer storage medium storing a computer program, and the computer program is operable to enable a computer to execute the steps in the BIM-based building maintenance and updating method described in Embodiment 1 or Embodiment 2.
[0215] The device embodiments described above are only illustrative, wherein the modules described as separate components may or may not be physically separated, and the components displayed as modules may or may not be physical modules, i.e., they may be located in one place, or they may be distributed on multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Those of ordinary skill in the art may understand and implement it without creative work.
[0216] Through the specific description of the above embodiments, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a necessary general hardware platform, and of course, can also be implemented by hardware. Based on such an understanding, the above technical solution can be essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, and the storage medium includes a read-only memory (ROM), a random access memory (RAM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), a one-time programmable read-only memory (OTPROM), an electronically erasable rewritable read-only memory (EEPROM), a compact disc (CD-ROM) or other optical disc storage, magnetic disk storage, magnetic tape storage, or any other computer-readable medium that can be used to carry or store data.
[0217] Finally, it should be noted that the BIM-based building maintenance and renewal method and device disclosed in the embodiment of the present invention only discloses the preferred embodiment of the present invention, which is only used to illustrate the technical solution of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, it should be understood by those skilled in the art that the technical solutions described in the aforementioned embodiments can still be modified, or some of the technical features therein can be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the present invention.
Claims
1. A BIM-based building maintenance and update method, It is characterized in that The method comprises: Obtain collaborative design requirements information; Generate first maintenance task information according to the collaborative design requirement information and the preset BIM model; Determine whether the first maintenance task information satisfies the task execution condition corresponding to the collaborative design requirement information. When it is determined that the first maintenance task information does not satisfy the task execution condition, adjust the first maintenance task information according to the task execution condition to obtain second maintenance task information. The first maintenance task information or the second maintenance task information is used to instruct the execution of a building maintenance and renewal project. The collaborative design requirement information is determined according to the project engineering information of the building maintenance and renewal project. Furthermore, the building maintenance and renewal project includes at least one professional group, the collaborative design requirement information includes collaborative design requirement sub-information of each professional group, and the generating of the first maintenance task information according to the collaborative design requirement information and the preset BIM model includes: For each of the professional groups, determining the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information of the professional group and the preset BIM model; Generate first maintenance task information according to all the maintenance task sub-information; Furthermore, the preset BIM model includes at least one BIM professional sub-model, and each professional group has at least one corresponding BIM professional sub-model; for each professional group, determining the maintenance task sub-information of the professional group according to the collaborative design requirement sub-information and the preset BIM model of the professional group includes: For each of the BIM professional sub-models, according to the collaborative design requirement sub-information of the professional group and the BIM professional sub-model, determine the professional task sub-information of the professional group corresponding to the BIM professional sub-model; according to the preset task execution process model, judge whether there are at least two target professional task sub-information that meet the preset conflict condition among all the professional task sub-information of the professional group; when it is judged that there are at least two target professional task sub-information among all the professional task sub-information of the professional group, adjust each of the target professional task sub-information according to the preset task execution process model, and re-trigger the execution of the operation of judging whether there are at least two target professional task sub-information that meet the preset conflict condition among all the professional task sub-information of the professional group according to the preset task execution process model; When it is determined that at least two of the target professional task sub-information do not exist in all the professional task sub-information of the professional group, the maintenance task sub-information of the professional group is determined based on all the professional task sub-information; And, the determining whether the first maintenance task information satisfies the task execution condition corresponding to the collaborative design requirement information includes: Determine, according to the first maintenance task information, at least one target area of the building maintenance and renewal project and an expected maintenance effect of each of the target areas; For each of the target areas, current status information of the target area is obtained; based on the current status information, whether the target area meets the area configuration condition of the expected maintenance effect is determined; when it is determined that the target area does not meet the area configuration condition of the expected maintenance effect, determining that the first maintenance task information does not meet the task execution condition corresponding to the collaborative design requirement information; And, adjusting the first maintenance task information according to the task execution condition to obtain the second maintenance task information includes: Obtaining the preset protection priority of the target area; Determine whether the preset protection priority is greater than or equal to a protection priority threshold, and when it is determined that the preset protection priority is greater than or equal to the protection priority threshold, determine at least one associated area of the target area; adjust the target area and all the associated areas according to the expected maintenance effect to adjust the first maintenance task information to obtain second maintenance task information; When it is determined that the preset protection priority is less than the protection priority threshold, the target area is adjusted according to the expected maintenance effect to adjust the first maintenance task information to obtain second maintenance task information; And, the current status information includes at least one status information of regional area information, regional volume information, regional material layout information, regional temperature information, regional humidity information, regional particle distribution information, regional gas distribution information, regional noise distribution information, regional wind speed information, regional wind direction information, regional light source information, regional object information, regional image information, regional audio information, regional target distribution information, and regional associated area information; and, judging whether the target area meets the regional configuration condition of the expected maintenance effect according to the current status information includes: Analyzing the current configuration information of the target area according to the current state information; generating simulation control parameters according to the expected maintenance effect; generating desired configuration information of the target area according to the simulation control parameter and the first maintenance task information; Generate a simulated maintenance effect of the target area according to the expected configuration information and the current configuration information; Determining whether the simulated maintenance effect matches the expected maintenance effect, and when it is determined that the simulated maintenance effect does not match the expected maintenance effect, determining that the target area does not meet the area configuration condition of the expected maintenance effect; Furthermore, before obtaining the collaborative design requirement information, the method further includes: Obtaining the project engineering information of the building maintenance and renovation project; Analyze at least one target item of the building maintenance and renovation project according to the project engineering information and the preset BIM model, each of the target items having a corresponding preset priority value; For each of the target items, according to the target item and the corresponding preset priority value, calculate the current priority value of the target item; determine whether the current priority value is greater than or equal to the preset priority threshold, and when it is determined that the current priority value is greater than or equal to the preset priority threshold, determine the target item as a key item; And, the obtaining of collaborative design requirement information includes: Determine collaborative design requirements based on all the key items; And, determining collaborative design requirement information based on all the key items includes: For each of the key items, determining at least one associated item of the key item among all the target items according to the project engineering information and the key item; For each of the associated items, determining an associated value between the associated item and the key item; According to the association value of the association item and the current priority value of the association item, judging whether the association item satisfies a preset supplementary maintenance condition, and when judging that the association item satisfies the preset supplementary maintenance condition, determining the association item as a supplementary key item; The collaborative design requirement information is determined based on all the key items and all the supplementary key items.
2. A BIM-based building maintenance and update device, It is characterized in that The device is used to execute the BIM-based building maintenance and updating method according to claim 1, and the device comprises: The first acquisition module is used to acquire collaborative design requirement information; A generating module, configured to generate first maintenance task information according to the collaborative design requirement information and a preset BIM model; A first judgment module, used to judge whether the first maintenance task information meets the task execution condition corresponding to the collaborative design requirement information; An adjustment module is used to adjust the first maintenance task information according to the task execution condition to obtain second maintenance task information when the first judgment module determines that the first maintenance task information does not meet the task execution condition. The first maintenance task information or the second maintenance task information is used to indicate the execution of the building maintenance and renewal project, and the collaborative design requirement information is determined based on the project engineering information of the building maintenance and renewal project.
3. A BIM-based building maintenance and update device, It is characterized in that The device comprises: A memory storing executable program code; a processor coupled to the memory; The processor calls the executable program code stored in the memory to execute the BIM-based building maintenance and updating method as claimed in claim 1.
4. A computer storage medium, It is characterized in that The computer storage medium stores computer instructions, which, when called, are used to execute the BIM-based building maintenance and updating method as claimed in claim 1.