A construction method and launching method of a high-center-of-gravity, low-stability dock door
By designing the inverted T-dock door segments without margin size and adding welding shrinkage, combining CNC cutting and prefabricated triangle horse plate to adjust the verticality, the problem of low welding shrinkage and stability during construction and drainage is solved, and the problem of low welding shrinkage and stability during construction and drainage is achieved. Efficient construction and safe launch.
Patent Information
- Application Number
- CN202211557683.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-06
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2042-12-06
AI Technical Summary
During the construction and drainage process, the inverted T-dock door has problems such as welding and receiving shrinkage, resulting in reduced segmentation, difficult adjustment of closing position, and low stability, resulting in long construction cycle, high cost and high risk of overturning.
By designing the dock door segments without margin size and adding welding to receive shrinkage, the components are accurately processed using CNC cutting and semi-automatic bevel machines, the prefabricated triangle horse plate adjusts the verticality of the segments, and using four-sided cables and slowness when draining the water Tow to reduce the risk of capsizing.
It improves the accuracy of segmented construction, shortens the construction cycle, reduces costs, and effectively avoids the risk of overturning T-dock doors during the launch process.
Smart Images

Figure CN115781192B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of dock door construction, and in particular to a construction method and a launching method of a dock door with a high center of gravity and low stability. Background Art
[0002] As the main place for ship manufacturing and maintenance, the dock is an important and indispensable facility in the shipyard. The dock has a dock room and a dock port. The dock room is used to place ships, and the dock port is used to enter and exit ships. The dock door is the water retaining door of the dock, which plays an important role in isolating seawater and facilitating the construction of the ship's steel structure after the final assembly and launching. The pontoon dock door refers to a box-shaped dock door equipped with a water pump and a water inlet valve that can be pressurized in both directions, and the floating, sinking, opening and closing of the door are controlled by the injection and discharge of water. The primary function of the pontoon dock door is to retain water. When it is placed in the working position of the dock port and contacts the dock body, it can be watertight, separating the water area from the dock room, and creating basic environmental conditions for shipbuilding and ship repair.
[0003] Conventional pontoon dock gates are rectangular steel box structures. As the country vigorously develops offshore and coastal projects, pontoon dock gates have gradually evolved from small to large and ultra-large in the early days. The rectangular steel box structure dock gates are large in size, occupy a large space in the dock, are heavy, require a lot of plates, have a long construction period, are high in cost, and are inconvenient to transport. Therefore, an inverted T-shaped dock gate was designed. Figure 1 As shown, the cross section of the main area in the middle of the inverted T-shaped dock door is in an inverted T shape. The inverted T-shaped dock door has two sections, namely the first section 1 and the second section 2. The second section 2 is composed of a horizontal section and a vertical section. The horizontal section is located above the vertical section, so that the second section 2 is a wide upper and narrow lower structure. The second section 2 is connected to the upper end surface of the first section 1. Compared with the conventional rectangular steel box dock door, the inverted T-shaped dock door has the basic water-retaining function of the dock door, and has the advantages of small size, small space occupied in the dock, light weight, small amount of plate material, short construction period, low cost and convenient transportation.
[0004] However, the following problems still exist when the inverted T-type dock door is built in the dock and launched into the water after completion:
[0005] (1) During the construction of the dock gate, full penetration welding accounts for a large proportion of welding, and the remaining welds are mostly groove welding. When welding in sections, shrinkage will occur, resulting in a reduction in the original volume of the sections. To address this problem, the conventional solution is to leave section compensation and carrying margin. Although this method can ensure that the sections will not shrink to the standard requirements during construction, it will eventually lead to the carrying sections being too large, requiring secondary marking and cutting, which increases the difficulty of meeting the precision requirements for section construction and increases the construction period and cost.
[0006] (2) The contact area between the second section 2 and the first section 1 is small, and there are only two closing seams when closing with the first section 1. It is difficult to adjust the fixed position of the closing point. In addition, due to the high overall height of the dock door, any slight tilt of the second section 2 during hoisting will affect the verticality of the dock door and increase the accuracy deviation. Therefore, the verticality of the second section 2 when closing is particularly important. At present, the conventional method for closing sections is to use process support auxiliary support welding. This method will waste a lot of diagonal bracing materials and cannot correct the verticality of the second section 2.
[0007] (3) After the dock gate is built in the dry dock, it needs to be launched into the water and moved to the destination waters. It is usually moved by towing by a tugboat. The inverted T-type dock gate has the characteristics of high center of gravity and low stability due to its special inverted T-shaped structure. If the towing method is improper during the movement, it is very easy to cause the inverted T-type dock gate to tilt seriously and capsize.
[0008] Therefore, the present invention proposes a construction method and a launching method of a high-center-of-gravity, low-stability dock door to solve the above-mentioned problems. Summary of the invention
[0009] The technical problem to be solved by the present invention is to provide a construction method and a launching method for a high-center-of-gravity, low-stability dock gate. By means of the provided construction method, the accuracy of segment construction is improved, the construction period and cost are reduced, the difficulty of adjusting the fixed position of the segments when they are closed is reduced, and verticality correction is achieved when the segments are closed. In addition, by means of the provided launching method, the problem that the inverted T-shaped dock gate, due to its special structural characteristics, has the characteristics of a high center of gravity and low stability, which easily causes the inverted T-shaped dock gate to tilt severely and overturn when moving, is solved.
[0010] In order to solve the first technical problem, the technical solution of the present invention is: a method for constructing a high-center-of-gravity, low-stability dock door, the innovation of which is that the high-center-of-gravity, low-stability dock door is constructed in a dock, and the construction method comprises the following steps:
[0011] Step 1, dock door size design;
[0012] Step 1-1, complete the design of the dock door section without margin dimensions;
[0013] Step 1-2, adding welding shrinkage to the size of the dock door segments without margin to form a dock door size processing drawing;
[0014] Step 2: Component production;
[0015] Step 2-1, preparation before cutting, leveling and straightening the plates used for dock door segmentation, and testing the CNC cutting machine for trial cutting accuracy. The cutting error of the CNC cutting machine is 1mm;
[0016] Step 2-2, cutting and testing, using a CNC cutting machine to cut the plate into components, measuring the components to obtain the actual dimensions, and comparing them with the dock door dimension processing drawings;
[0017] Step 2-3, management after unloading, the components are placed in the corresponding trays, and the components are beveled using a semi-automatic beveling machine to obtain reference plates, transverse components, longitudinal components and bulk parts;
[0018] Step 3, segment welding;
[0019] Step 3-1, tire frame production, according to the tire frame drawing, the tire frame is produced, the tire frame center line, auxiliary lines and seam lines are marked on the tire frame, the horizontal plane is found by using a laser theodolite, and a mark is made on the fulcrum as a reference plane for measuring the height of the tire frame;
[0020] Step 3-2, base plate tire installation;
[0021] Step 3-3, marking and inspection, marking the center line of the reference plate and the assembly lines of the longitudinal components and transverse components on the reference plate, and the marking error of the assembly line is less than 2mm;
[0022] Step 3-4: Position the components on the tire, assemble the longitudinal components first, and then assemble the transverse components;
[0023] Step 3-5, adding process support;
[0024] Step 3-6, install the bulk parts;
[0025] Step 3-7, welding, welding can only be carried out after all components are assembled;
[0026] Step 3-8, segment completion accuracy measurement, the measurement items include segment length, width, height, verticality and segment horizontality;
[0027] Step 3-9, removing the mold, obtaining the first segment and the second segment;
[0028] Step 4, closing the sections;
[0029] Step 4-1, prefabricate the horse plates, symmetrically weld two rows of triangular horse plates on the upper end surface of the first segment, the bottom sides of the triangular horse plates are welded to the first segment, the sides of the two symmetrical triangular horse plates close to each other are vertical sides, the verticality of the vertical sides is consistent with the verticality requirement of the second segment, the two symmetrical triangular horse plates cooperate with the first segment to form a second segment accommodating groove with two right-angled edges, and the distance between two adjacent triangular horse plates in each row of triangular horse plates is 1m;
[0030] Step 4-2, preparation before lifting, install cement piers on both sides of the first section in the width direction, install hand chain hoists on the cement piers, install lifting lug shackle groups on both sides of the second section in the width direction, and connect the wire rope of the hand chain hoist to the lifting lug shackle group on the same side;
[0031] Step 4-3, hoisting the second segment, after hoisting the second segment just above the second segment receiving slot by using a crane, lowering the second segment gradually into the second segment receiving slot, during the lowering process, use the hand chain hoists on both sides to adjust the verticality of the second segment, and use the crane to move the position of the second segment in the second segment receiving slot until the second segment is completely placed in the second segment receiving slot, and the placement position is consistent with the required closing position;
[0032] Step 4-4, closing welding, welding the closing seams between the second segment and the triangular plate, and between the second segment and the first segment;
[0033] Step 5: Install the water-stopping device.
[0034] Furthermore, the method of adding welding shrinkage in step 1-2 is to add 1.0 mm of welding shrinkage for every 2000 mm of no-residue dimension in the long axis direction of the dock door, and to add 0.5 mm of welding shrinkage for every 550 mm of no-residue dimension in both the width direction and the vertical direction of the dock door.
[0035] Furthermore, the welding in steps 3-7 follows the following principles:
[0036] N1, when the member intersects the plate joint, when there are both butt joints and corner joints, the following should be followed:
[0037] Weld the butt joints first, then the fillet joints;
[0038] Weld the end seams of the panels first, then the side seams of the panels;
[0039] For corner seams, weld the vertical corner seams first, then weld the flat corner seams;
[0040] The circular weld adopts symmetrical welding;
[0041] For welds with a length of more than 2m, the segmented back-welding method or the skip welding method is used to reduce welding deformation;
[0042] N2, When welding longitudinal and transverse members, the following should be followed:
[0043] Weld from the middle to the surrounding areas;
[0044] First weld the butt joints and corner joints between components, then weld the bottom;
[0045] Welding is performed symmetrically by an even number of welders, or by a single welder with left-right symmetry around the center of the component;
[0046] The reinforcement ribs around the opening are welded last;
[0047] N3, when welding the joints of internal components during segmented forming welding, the following should be followed:
[0048] Weld the butt joints first, then the fillet joints;
[0049] For butt joints, flat butt welding should be performed first, then horizontal butt welding, and finally vertical butt welding;
[0050] The joints with grooves are welded first, and the joints without grooves are welded later;
[0051] For corner joints, the vertical corner joints should be welded first, and then the flat corner joints.
[0052] Furthermore, the installation of the water-stopping device in step 5 includes the following steps:
[0053] Step 5-1, preparation before installation. The water stop device includes an adjustment pad, a pressure block, a water stop rubber strip, a stainless steel pressure plate, a bolt and nut assembly, and a bolt hole cover. Before installing the water stop device, the overall assembly of the dock door should be completed, the anti-corrosion layer treatment work should be completed, the adjustment pad should be completed, the size measurement should be qualified, there should be no obvious deformation, and the installation position of the water stop device should be determined;
[0054] Step 5-2, install the adjustment pad. According to the design requirements, select the adjustment pad of corresponding thickness, lay it flat and fit it at the required installation position on the dock door, and use welding rods to weld and fix the adjustment pad. The adjustment pad should be installed flat and without burrs, and the joints should be polished flat without obvious protrusions. The overall flatness of the adjustment pad should not exceed 3mm;
[0055] Step 5-3, drilling, the drilling holes include a first bolt hole for installing the pressure block and a second bolt hole for installing the water-stop rubber strip, the deviation of the center distance between two adjacent bolt holes is no more than 1mm, and there is no cumulative deviation, the two ends of the bolt holes are chamfered 45°, and there are no burrs;
[0056] Step 5-4, install the pressure blocks. Personnel on both sides install two rows of pressure blocks simultaneously, use bolt and nut assemblies for pre-tightening, check whether the straightness and parallelism of the pressure blocks after installation meet the requirements of the drawings, check whether the water-stopping conditions of the bolt holes after the pressure blocks are installed meet the requirements, and adjust the upper plane of the pressure blocks in time to meet the requirements of the drawings.
[0057] Step 5-5, install the waterproof rubber strip and the stainless steel pressure plate, place the waterproof rubber strip on the floor where the installation surface is located, trim the position of the waterproof rubber strip, ensure that the force of each section of the waterproof rubber strip is even, ensure that the elasticity and size of the waterproof rubber strip meet the installation conditions, mark and punch the waterproof rubber strip, install the waterproof rubber strip and the stainless steel pressure plate, use the bolt and nut assembly for pre-tightening, adjust the tightness of the waterproof rubber strip, and adjust the straightness and flatness of the waterproof surface of the waterproof rubber strip to meet the requirements of the drawing;
[0058] Step 5-6, tighten all bolt and nut assemblies, check that the straightness and flatness of the pressure block and water-stop rubber strip after tightening meet the requirements of the drawing, and install the bolt hole cover at the pressure block;
[0059] Steps 5-7: Inspection after installation. Inspection items include:
[0060] (1) Check whether the pressure block has cracks or defects;
[0061] (2) Check whether the water-stop rubber strip has cracks or defects, and focus on checking whether the right-angle joints have damage or unevenness;
[0062] (3) Check that the assembly flatness deviation of the pressure block is no more than ±1mm / 1m and no more than ±3mm / 30m;
[0063] (4) Check that the flatness deviation of the water-stop surface of the water-stop rubber strip is not greater than ±1mm / 1m and not greater than ±3mm / 30m;
[0064] (5) Check that the bolt hole covers at the pressure block are intact and without any gaps.
[0065] Further, the water-stop device comprises an adjusting pad, a pressure-bearing block, a water-stop rubber strip, a stainless steel pressure plate, a bolt and nut assembly and a bolt hole cover;
[0066] The dock door is provided with a groove for installing a water-stop device, and a water-stop device is provided at each relative position on the side of the groove;
[0067] The adjusting pad is installed on the side of the groove, the waterproof rubber strip and the pressure block are both fitted on the side of the adjusting pad away from the dock door, the pressure block has two and is symmetrically arranged on both sides of the waterproof rubber strip, and the pressure block is provided with an assembly groove;
[0068] The pressure-bearing block, the adjusting pad and the dock door cooperate to form a first bolt hole that matches the bolt and nut assembly, the first bolt hole is located in the assembly groove, and the pressure-bearing block is fixedly connected to the adjusting pad by assembling the bolt and nut assembly in the first bolt hole, and the bolt hole cover is clamped at the opening of the assembly groove to form a closed space in the assembly groove;
[0069] The water-stop rubber strip, the adjusting pad and the dock door cooperate to form a second bolt hole that matches the bolt and nut assembly. The bolt and nut assembly is assembled in the second bolt hole to fix the water-stop rubber strip on the adjusting pad. The stainless steel pressure plate is arranged on the side of the water-stop rubber strip away from the adjusting pad and is sleeved on the bolt of the bolt and nut assembly. The stainless steel pressure plate is pressed against the water-stop rubber strip by tightening the bolt and nut assembly.
[0070] A method for constructing and launching a high-center-of-gravity, low-stability dock door, the launching method comprising the following steps:
[0071] Step S1: Selecting the launching time: after the dock door is built in the dock, the launching time is selected according to the water depth requirement in the dock when the dock door is launched and the tide table;
[0072] Step S2, preparatory work before water filling, installing functional equipment on the dock door, closing all dock door ballast water tank subdivision valves, temporarily filling the ballast water tank with water to the required height, and testing whether the wind force before leaving the dock meets the ship inclination test specifications;
[0073] Step S3, cable the dock door. To prevent the dock door from colliding with the dock wall due to the influence of water flow and to ensure the stability of the dock door, the dock door and the mooring equipment on both sides of the dock are cabled in advance before releasing the water;
[0074] Step S4, the dock door is floated, water is released into the dock, the draft of the dock door is always observed and the state of the dock door is observed to see whether it is floating, and the position of the dock door is adjusted through the mooring equipment to prevent the dock door from colliding with the dock wall;
[0075] Step S5, the dock gate is undocking. After the tide stabilizes, four tugboats are organized to tow the dock gate. Before towing, the four tugboats are tied with cables at the four corners of the dock gate, and the mooring equipment cables between the dock gate and both sides of the dock are released. When towing, the tugboats first move longitudinally to the middle of the dock, then move laterally to leave the dock and move to the destination.
[0076] Furthermore, in step S3, the dock door cable follows the figure eight cable principle, that is, the angle of the cable mooring is an outward figure eight or an inward figure eight.
[0077] Further, in step S4, the dock door is floated, water is released into the dock, the draft of the dock door is constantly observed, and the state of the dock door is observed to see whether it is floating, and the position of the dock door is adjusted through the mooring equipment to prevent the dock door from colliding with the dock wall, and the long axis direction of the dock door is directed toward the dock exit;
[0078] Furthermore, the longitudinal movement is movement along the width direction of the dock door, and the lateral movement is movement along the long axis direction of the dock door.
[0079] Furthermore, the mooring equipment includes three winches and a traction trolley, wherein two winches are installed on one side of the dock wall, and another winch and traction trolley are arranged on the other side of the dock wall, and the winches and traction trolley are respectively connected to the dock door through cables.
[0080] The advantages of the present invention are:
[0081] The invention provides a construction method and launching method of a high-center-of-gravity, low-stability dock door. The construction method uses welding shrinkage to replace segment compensation and carrying margin to compensate for the shrinkage generated during welding, so that the segments obtained by welding meet the accuracy requirements, and no secondary marking and cutting is required, thereby improving the construction accuracy, and finally achieving segmented margin-free construction, realizing segmented margin-free closing, shortening the dock door construction period, and reducing the construction cost; and before the segments are closed, a triangular horse plate is prefabricated at the closing seam, and a second segment accommodating groove with two right-angled edges is formed by the triangular horse plate. When the second segment is lowered and closed, the verticality of the second segment is adjusted by the cooperation of a hand winch, a cement pier, and a lifting eye shackle group. Since the verticality of the two side edges of the second segment accommodating groove is consistent with the verticality requirement of the second segment, after the second segment is lowered into the second segment accommodating groove, the triangular horse plates on both sides can correct the verticality of the second segment, and the closing position of the second segment is adjusted by moving in the second segment accommodating groove, thereby reducing the difficulty of adjusting the closing position of the segment.
[0082] The launching method uses cables on all four sides of the dock gate when it floats, which ensures the stability of the dock gate during the floating process and avoids the collision of the dock wall during the floating movement. After the dock gate floats stably, four tugboats are used to move longitudinally to the middle of the dock, and then move horizontally to leave the dock and move to the destination. This movement process effectively avoids the oblique movement of the dock gate and reduces the risk of tilting and capsizing of the inverted T-shaped dock gate. BRIEF DESCRIPTION OF THE DRAWINGS
[0083] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0084] Figure 1 It is a schematic structural diagram of the high-center-of-gravity and low-stability dock door of the present invention.
[0085] Figure 2 It is a schematic diagram of the segmented closure construction of the high-center-of-gravity, low-stability dock door of the present invention.
[0086] Figure 3 It is a schematic structural diagram of the water stopping device of the present invention.
[0087] Figure 4 It is a schematic diagram of the mooring equipment cable of the dock door and the dock of the present invention. DETAILED DESCRIPTION
[0088] The following embodiments can enable those skilled in the art to more fully understand the present invention, but the present invention is not limited to the scope of the embodiments.
[0089] like Figure 1 As shown, the cross section of the main area in the middle of the inverted T-shaped dock door is in an inverted T shape. The inverted T-shaped dock door has two sections, namely the first section 1 and the second section 2. The second section 2 is composed of a horizontal section and a vertical section. The horizontal section is located above the vertical section, so that the second section 2 is a wide upper and narrow lower structure. The second section 2 is connected to the upper end surface of the first section 1. Compared with the conventional rectangular steel box dock door, the inverted T-shaped dock door has the basic water-retaining function of the dock door, and has the advantages of small size, small space occupied in the dock, light weight, small amount of plate material, short construction period, low cost and convenient transportation.
[0090] However, there are still the following problems when the inverted T-type dock door is built in the dock:
[0091] (1) During the construction of the dock gate, full penetration welding accounts for a large proportion of welding, and the remaining welds are mostly groove welding. When welding in sections, shrinkage will occur, resulting in a reduction in the original volume of the sections. To address this problem, the conventional solution is to leave section compensation and carrying margin. Although this method can ensure that the sections will not shrink to the standard requirements during construction, it will eventually lead to the carrying sections being too large, requiring secondary marking and cutting, which increases the difficulty of meeting the precision requirements for section construction and increases the construction period and cost.
[0092] (2) The contact area between the second section 2 and the first section 1 is small, and there are only two closing seams when closing with the first section 1. It is difficult to adjust the fixed position of the closing point. In addition, due to the high overall height of the dock door, any slight tilt of the second section 2 during hoisting will affect the verticality of the dock door and increase the accuracy deviation. Therefore, the verticality of the second section 2 when closing is particularly important. At present, the conventional method for closing sections is to use process support auxiliary support welding. This method will waste a lot of diagonal bracing materials and cannot correct the verticality of the second section 2.
[0093] To solve the above problems, the present invention provides a method for building a high-center-of-gravity, low-stability dock gate, which is built in a dock. The main body dimensions of the high-center-of-gravity, low-stability dock gate in this embodiment are 114.85 meters long, 12 meters wide, and 13.5 meters high. The deadweight of the steel structure is about 2,200 tons, the total weight after the fixed ballast blocks are installed is about 5,200 tons, and the draft depth is 8.35 meters.
[0094] The construction method of the high center of gravity and low stability dock door includes the following steps:
[0095] Step 1, dock door size design;
[0096] Step 1-1, complete the design of the dock door section without margin dimensions;
[0097] Step 1-2, adding welding shrinkage on the basis of the no-residue dimensions of the dock door sections to form the dock door dimension processing drawing. The method of adding welding shrinkage is to add 1.0mm welding shrinkage for every 2000mm no-residue dimensions in the long axis direction of the dock door, and add 0.5mm welding shrinkage for every 550mm no-residue dimensions in the width direction and vertical direction of the dock door;
[0098] Step 2: Component production;
[0099] Step 2-1, preparation before cutting, leveling and straightening the plates used for dock door segmentation, and testing the cutting accuracy of the CNC cutting machine. The cutting error of the CNC cutting machine is 1mm. The work can be started only after the cutting accuracy of the CNC cutting machine meets the requirements;
[0100] Step 2-2, cutting and testing, using a CNC cutting machine to cut the plate into components, measuring the components to obtain the actual size of the components, and comparing them with the dock door size processing drawings to check whether the actual size of the components is within the allowable error range of 1mm, and at the same time monitoring the cutting process of the CNC cutting machine;
[0101] Step 2-3, management after cutting, the components that have been cut and tested and qualified are placed in the corresponding pallets, and the components are beveled using a semi-automatic beveling machine to obtain reference plates, transverse components, longitudinal components and bulk parts.
[0102] After the components are completed, they should be stacked and shipped flat to prevent deformation due to their own weight, extrusion, etc.
[0103] Step 3, segment welding;
[0104] Step 3-1, tire frame production, according to the tire frame drawing, the tire frame is produced, the tire frame center line, auxiliary lines and seam lines are marked on the tire frame, the horizontal plane is found by using a laser theodolite, and a mark is made on the fulcrum as a reference plane for measuring the height of the tire frame;
[0105] Step 3-2, base plate tire installation;
[0106] Step 3-3, marking and inspection, marking the center line of the reference plate and the assembly lines of the longitudinal components and transverse components on the reference plate, and the marking error of the assembly line is less than 2mm;
[0107] Step 3-4: Position the components on the tire, assemble the longitudinal components first, and then assemble the transverse components;
[0108] Step 3-5, add process support to facilitate component positioning welding, prevent it from overturning, ensure the temporary strength of the component, and prevent deformation after welding;
[0109] Step 3-6, install the bulk parts;
[0110] Step 3-7, welding, welding can only be carried out after all components are assembled; in order to improve welding strength and welding efficiency and avoid deformation, the following principles should be followed during welding:
[0111] N1, when the member intersects the plate joint, when there are both butt joints and corner joints, the following should be followed:
[0112] Weld the butt joints first, then the fillet joints;
[0113] Weld the end seams of the panels first, then the side seams of the panels;
[0114] For corner seams, weld the vertical corner seams first, then weld the flat corner seams;
[0115] The circular weld adopts symmetrical welding;
[0116] For welds with a length of more than 2m, the segmented back-welding method or the skip welding method is used to reduce welding deformation;
[0117] N2, When welding longitudinal and transverse members, the following should be followed:
[0118] Weld from the middle to the surrounding areas;
[0119] First weld the butt joints and corner joints between components, then weld the bottom;
[0120] Welding is performed symmetrically by an even number of welders, or by a single welder with left-right symmetry around the center of the component;
[0121] The reinforcement ribs around the opening are welded last;
[0122] N3, when welding the joints of internal components during segmented forming welding, the following should be followed:
[0123] Weld the butt joints first, then the fillet joints;
[0124] For butt joints, flat butt welding should be performed first, then horizontal butt welding, and finally vertical butt welding;
[0125] The joints with grooves are welded first, and the joints without grooves are welded later;
[0126] For corner joints, the vertical corner joints should be welded first, and then the flat corner joints.
[0127] Step 3-8, segment completion accuracy measurement, the measurement items include segment length, width, height, verticality and segment horizontality;
[0128] Step 3-9, removing the mold, obtaining the first segment and the second segment;
[0129] Step 4, closing the sections;
[0130] Step 4-1, prefabricate the horse plates, symmetrically weld two rows of triangular horse plates 3 on the upper end surface of the first segment 1, the thickness of the triangular horse plates 3 is 20 mm, the distance between two adjacent triangular horse plates in each row of triangular horse plates 3 is 1 m, the bottom sides of the triangular horse plates 3 are welded to the first segment 1, the sides of the two symmetrical triangular horse plates 3 close to each other are vertical sides, the verticality of the vertical sides is consistent with the verticality requirement of the second segment 2, and the two symmetrical triangular horse plates 3 cooperate with the first segment 1 to form a second segment accommodating groove with two right-angled edges.
[0131] Step 4-2, preparation before lifting, place 50 tons of cement piers 5 on both sides of the width direction of the first section 1, such as Figure 2 As shown, a 5-ton hand chain hoist 4 is installed on each cement pier 5, and a lifting lug shackle group is installed on both sides of the width direction of the top of the second section 2. The lifting lug shackle group consists of a 10-ton lifting lug 7 and an 8.5-ton shackle 6. The lifting lug 7 is installed on the bottom surface of the horizontal section of the second section 2, and the shackle 6 is connected to the lifting lug 7. The steel wire rope of the hand chain hoist 4 is connected to the shackle 6 on the same side.
[0132] Step 4-3, hoisting the second segment, after hoisting the second segment 2 just above the second segment accommodating slot by using a crane, lowering the second segment 2 gradually into the second segment accommodating slot, during the lowering process, using the hand chain hoists 4 on both sides to adjust the verticality of the second segment 2, and using the crane to move the position of the second segment 2 in the second segment accommodating slot until the second segment 2 is completely placed in the second segment accommodating slot, and the placement position is consistent with the required closing position;
[0133] Step 4-4, closing welding, welding the closing seams between the second segment 2 and the triangular plate 3, and between the second segment 2 and the first segment 1;
[0134] Step 5: Install the water-stopping device.
[0135] The dock door is provided with a groove for installing a water stop device. Two sets of water stop devices are installed at relative positions on the sides of the groove. The water stop device includes an adjustment pad 11, a pressure block 13, a water stop rubber strip 14, a stainless steel pressure plate 15, a bolt and nut assembly 16 and a bolt hole cover 17. Figure 3As shown, the adjusting pad 11 is installed on the side of the groove, the waterproof rubber strip 14 and the pressure block 13 are both fitted and arranged on the side of the adjusting pad 11 away from the dock door, the pressure block 13 has two and symmetrically arranged on both sides of the waterproof rubber strip 14, and an assembly groove is opened on the pressure block 13; the pressure block 13, the adjusting pad 11 and the dock door are matched to open a first bolt hole matching the bolt and nut assembly 16, the first bolt hole is located in the assembly groove, and the bolt and nut assembly is assembled in the first bolt hole to fix the pressure block 13 on the adjusting pad 11, and the bolt hole cover 17 is engaged at the opening of the assembly groove to form a closed space in the assembly groove; the waterproof rubber strip 14, the adjusting pad 11 and the dock door are matched to open a second bolt hole matching the bolt and nut assembly, the second bolt holes are evenly distributed on both sides of the waterproof rubber strip, and the bolt and nut assembly 16 is assembled in the second bolt hole. The rubber strip 14 is fixedly connected to the adjusting pad 11, and the stainless steel pressure plate 15 is arranged on the side of the water-stop rubber strip 14 away from the adjusting pad 11, and is sleeved on the bolt of the bolt and nut assembly 16. The stainless steel pressure plate 15 is pressed against the water-stop rubber strip 14 by tightening the bolt and nut assembly 16; in this embodiment, the pressure block 13 adopts a special cross-section polymer material with high compressive strength and long corrosion resistance, and the water-stop rubber strip 14 adopts a hollow rubber strip; in addition, the water-stop device also includes a baffle 12, which is connected to the side of the adjusting pad 11 away from the dock door, and the side of the groove extends outwardly in a direction perpendicular to the side of the groove. The baffle cooperates with the adjusting pad 11 and the baffle 12 to form a limiting groove for installing the pressure block 13 and the water-stop rubber strip 14. The pressure block 13 and the water-stop rubber strip 14 are installed in the limiting groove, which improves the sealing effect of the water-stop device.
[0136] The installation of the water stop device has the following steps:
[0137] Step 5-1, preparation before installation. Before the installation of the water stop device, the overall assembly of the dock door should be completed, the anti-corrosion layer treatment work should be completed, the adjustment pad 11 should be completed, the size measurement should be qualified, there should be no obvious deformation, and the installation position of the water stop device should be determined;
[0138] Step 5-2, install the adjustment pad 11. According to the design requirements, select the adjustment pad 11 of corresponding thickness, lay it flat and fit it on the required installation position on the dock door, and use welding rods to weld and fix the adjustment pad 11. The adjustment pad 11 should be installed flat and free of defects such as burrs. The joints should be polished flat without obvious protrusions. The overall flatness of the adjustment pad should not be greater than 3mm. Determine the installation position of the baffle 12 according to the design requirements, and use welding rods to weld the baffle 12 to the adjustment pad 11;
[0139] Step 5-3, drilling, the drilling holes include a first bolt hole for installing the pressure block 13 and a second bolt hole for installing the waterproof rubber strip 14. The entire waterproof device contains a large number of bolt holes, the work is difficult, and the precision requirement is high. When drilling, the deviation of the center distance between two adjacent bolt holes is required to be no more than 1mm, and there is no cumulative deviation. The two ends of the bolt hole are chamfered at 45° and there are no burrs;
[0140] Step 5-4, install the pressure blocks 13. Personnel on both sides install two rows of pressure blocks 13 simultaneously, use the bolt and nut assemblies for pre-tightening, check whether the straightness and parallelism of the pressure blocks 13 after installation meet the requirements of the drawings, check whether the water-stopping conditions of the bolt holes of the pressure blocks 13 after installation meet the requirements, and adjust the upper plane of the pressure blocks 13 in time to meet the requirements of the drawings.
[0141] Step 5-5, install the waterproof rubber strip 14 and the stainless steel pressure plate 15, place the waterproof rubber strip 14 on the floor where the installation surface is located, trim the position of the waterproof rubber strip 14, ensure that the various sections of the waterproof rubber strip 14 are evenly stressed, ensure that the elasticity and size of the waterproof rubber strip 14 meet the installation conditions, mark and drill holes for the waterproof rubber strip 14, install the waterproof rubber strip 14 and the stainless steel pressure plate 15, use the bolt and nut assembly for pre-tightening, adjust the degree of compression of the waterproof rubber strip 14, and adjust the straightness and flatness of the waterproof surface of the waterproof rubber strip 14 to meet the requirements of the drawing;
[0142] Step 5-6, tighten all bolt and nut assemblies 16, check that the straightness and flatness of the tightened pressure block 13 and the waterproof rubber strip 14 meet the requirements of the drawing, and install the bolt hole cover 17 at the pressure block 13;
[0143] Steps 5-7: Inspection after installation. Inspection items include:
[0144] (1) Check whether the pressure block 13 has cracks or defects;
[0145] (2) Check whether the water-stop rubber strip 14 has cracks or defects, and focus on checking whether the right-angle joint has damage or unevenness;
[0146] (3) Check that the assembly flatness deviation of the pressure block 13 is not greater than ±1mm / 1m and not greater than ±3mm / 30m;
[0147] (4) Check that the flatness deviation of the water-stop surface of the water-stop rubber strip 14 is not greater than ±1mm / 1m and not greater than ±3mm / 30m;
[0148] (5) Check that the bolt hole covers 17 at the pressure block 13 are intact.
[0149] The above-mentioned construction method uses welding shrinkage to replace segment compensation and carrying allowance to compensate for the shrinkage generated during welding, so that the segments obtained by welding meet the accuracy requirements, without secondary marking and cutting, and improves the construction accuracy. Finally, the segmented zero-allowance construction is achieved, and the segmented zero-allowance closing is realized, which shortens the dock door construction period and reduces the construction cost; and before the segments are closed, a triangular horse plate is prefabricated at the closing seam, and a second segment accommodating groove with two right-angled edges is formed by the triangular horse plate. When the second segment is lowered and closed, the verticality of the second segment is adjusted by the hand winch, cement pier, and lifting eye shackle group. Since the verticality of the two sides of the second segment accommodating groove is consistent with the verticality requirement of the second segment, after the second segment is lowered into the second segment accommodating groove, the triangular horse plates on both sides can correct the verticality of the second segment, and the closing position of the second segment is adjusted by moving in the second segment accommodating groove, which reduces the difficulty of adjusting the closing position of the segment.
[0150] The following problems exist when the inverted T-type dock door is launched after it is built in the dock:
[0151] After the dock gate is built in the dry dock, due to the limitation of the water depth in the waters where the dock is located, the dock gate can only be launched after installing some ballast blocks. The remaining ballast blocks need to be launched and moved to the outfitting dock for installation. During the process of launching and moving the inverted T-type dock gate to the outfitting dock in the destination waters, it is usually moved by towing by a tugboat. The inverted T-type dock gate has the characteristics of high center of gravity and low stability due to its special inverted T-shaped structural characteristics. If the towing method is improper during the movement, it is very easy to cause the inverted T-type dock gate to tilt severely and capsize.
[0152] In order to solve the above problems, a launching method of a high-center-of-gravity, low-stability dock door is provided, and the launching method comprises the following steps:
[0153] Step S1: Selecting the launching time: after the dock gate is built in the dock, the launching time is selected according to the requirement that the water depth in the dock should be at least 9.8m when the dock gate is launched, and the tide table is used to refer to the launching time;
[0154] Step S2, preparation work before water filling, functional equipment is installed on the dock door, 1697 tons of fixed ballast blocks are installed in the dock door, all dock door ballast tank compartment valves are closed, the bottom surface of the dock door is used as the reference surface, the ballast tank is temporarily filled with water to the required height of 1250mm, and the wind force for undocking is tested. The undocking separation must comply with the ship inclination test specifications;
[0155] Step S3, the dock door is cabled. To prevent the dock door from being affected by the water flow and colliding with the dock wall and to ensure the stability of the dock door, the dock door and the mooring equipment on both sides of the dock are cabled in advance before releasing the water; Figure 4As shown, the mooring equipment includes three winches 8 and a traction trolley 18, wherein two winches 8 are installed on one side of the dock wall, and another winch and traction trolley 18 are arranged on the other side of the dock wall. The winches 8 and traction trolley 18 are respectively connected to the dock door through cables, and the dock door cable follows the figure eight cable principle, that is, the angle of the cable mooring is an outward or inward figure eight, so as to ensure the stability of the dock door during subsequent waterproofing and floating.
[0156] Step S4, the dock door floats, water is released into the dock, and the draft of the dock door is always observed and the state of the dock door is observed to see whether it is floating. At high tide, the water depth in the dock reaches 10.2m, and the dock door is fully floated. During the floating process, the position of the dock door is adjusted by the mooring equipment to avoid the dock door from colliding with the dock wall, and the long axis direction of the dock door is directed toward the dock exit 10;
[0157] Step S5, the dock gate is undocking. After the tide stabilizes, four tugboats are organized to tow the dock gate. Before towing, the four tugboats are tied with cables at the four corners of the dock gate, and the mooring equipment cables between the dock gate and both sides of the dock are released. When towing, the tugboats first move longitudinally (i.e. move along the width of the dock gate) to the middle of the dock, and then move transversely (i.e. move along the long axis of the dock gate) to leave the dock and move to the destination. During the entire towing process, the tugboats should move slowly and always observe the movement status of the dock gate to reduce the risk of the dock gate capsizing.
[0158] In the above launching method, the dock gate is carried on four sides with cables when it floats, which ensures the stability of the dock gate during the floating process and avoids the collision of the dock wall during the floating movement. After the dock gate floats stably, four tugboats are used to move it longitudinally to the middle of the dock, and then move it laterally to leave the dock and move to the destination. This movement process effectively avoids the oblique movement of the dock gate and reduces the risk of tilting and capsizing of the inverted T-shaped dock gate.
[0159] Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A method for constructing a high-center-of-gravity, low-stability dock door. Features: The high-center-of-gravity, low-stability dock door is constructed in a dock, and the construction method comprises the following steps: Step 1, dock door size design; Step 1-1, complete the design of the dock door section without margin dimensions; Step 1-2, adding welding shrinkage to the size of the dock door segments without margin to form a dock door size processing drawing; Step 2: Component production; Step 2-1, preparation before cutting, leveling and straightening the plates used for dock door segmentation, and testing the CNC cutting machine for trial cutting accuracy. The cutting error of the CNC cutting machine is 1mm; Step 2-2, cutting and testing, using a CNC cutting machine to cut the plate into components, measuring the components to obtain the actual dimensions, and comparing them with the dock door dimension processing drawings; Step 2-3, management after unloading, the components are placed in the corresponding trays, and the components are beveled using a semi-automatic beveling machine to obtain reference plates, transverse components, longitudinal components and bulk parts; Step 3, segment welding; Step 3-1, tire frame production, according to the tire frame drawing, the tire frame is produced, the tire frame center line, auxiliary lines and seam lines are marked on the tire frame, the horizontal plane is found by using a laser theodolite, and a mark is made on the fulcrum as a reference plane for measuring the height of the tire frame; Step 3-2, base plate tire installation; Step 3-3, marking and inspection, marking the center line of the reference plate and the assembly lines of the longitudinal components and transverse components on the reference plate, and the marking error of the assembly line is less than 2mm; Step 3-4: Position the components on the tire, assemble the longitudinal components first, and then assemble the transverse components; Step 3-5, adding process support; Step 3-6, install the bulk parts; Step 3-7, welding, welding can only be carried out after all components are assembled; Step 3-8, segment completion accuracy measurement, the measurement items include segment length, width, height, verticality and segment horizontality; Step 3-9, removing the mold, obtaining the first segment and the second segment; Step 4, closing the sections; Step 4-1, prefabricate the horse plates, symmetrically weld two rows of triangular horse plates on the upper end surface of the first segment, the bottom sides of the triangular horse plates are welded to the first segment, the sides of the two symmetrical triangular horse plates close to each other are vertical sides, the verticality of the vertical sides is consistent with the verticality requirement of the second segment, the two symmetrical triangular horse plates cooperate with the first segment to form a second segment accommodating groove with two right-angled edges, and the distance between two adjacent triangular horse plates in each row of triangular horse plates is 1m; Step 4-2, preparation before lifting, install cement piers on both sides of the first section in the width direction, install hand chain hoists on the cement piers, install lifting lug shackle groups on both sides of the second section in the width direction, and connect the wire rope of the hand chain hoist to the lifting lug shackle group on the same side; Step 4-3, hoisting the second segment, after hoisting the second segment just above the second segment receiving slot by using a crane, lowering the second segment gradually into the second segment receiving slot, during the lowering process, use the hand chain hoists on both sides to adjust the verticality of the second segment, and use the crane to move the position of the second segment in the second segment receiving slot until the second segment is completely placed in the second segment receiving slot, and the placement position is consistent with the required closing position; Step 4-4, closing welding, welding the closing seams between the second segment and the triangular plate, and between the second segment and the first segment; Step 5: Install the water-stopping device.
2. The method for constructing a high-center-of-gravity, low-stability dock door according to claim 1, Features: The method of adding welding shrinkage in step 1-2 is to add 1.0mm of welding shrinkage for every 2000mm of no-residue dimension in the long axis direction of the dock door, and to add 0.5mm of welding shrinkage for every 550mm of no-residue dimension in the width and vertical directions of the dock door.
3. The method for constructing a high-center-of-gravity, low-stability dock door according to claim 1, Features: The welding in steps 3-7 follows the following principles: N1, when the member intersects the plate joint, when there are both butt joints and corner joints, the following should be followed: Weld the butt joints first, then the fillet joints; Weld the end seams of the panels first, then the side seams of the panels; For corner seams, weld the vertical corner seams first, then weld the flat corner seams; The circular weld adopts symmetrical welding; For welds with a length of more than 2m, the segmented back-welding method or the skip welding method is used to reduce welding deformation; N2, When welding longitudinal and transverse members, the following should be followed: Weld from the middle to the surrounding areas; First weld the butt joints and corner joints between components, then weld the bottom; Welding is performed symmetrically by an even number of welders, or by a single welder with left-right symmetry around the center of the component; The reinforcement ribs around the opening are welded last; N3, when welding the joints of internal components during segmented forming welding, the following should be followed: Weld the butt joints first, then the fillet joints; For butt joints, flat butt welding should be performed first, then horizontal butt welding, and finally vertical butt welding; The joints with grooves are welded first, and the joints without grooves are welded later; For corner joints, the vertical corner joints should be welded first, and then the flat corner joints.
4. The method for constructing a high-center-of-gravity, low-stability dock door according to claim 1, Features: The installation of the water stop device in step 5 includes the following steps: Step 5-1, preparation before installation. The water stop device includes an adjustment pad, a pressure block, a water stop rubber strip, a stainless steel pressure plate, a bolt and nut assembly, and a bolt hole cover. Before installing the water stop device, the overall assembly of the dock door should be completed, the anti-corrosion layer treatment work should be completed, the adjustment pad should be completed, the size measurement should be qualified, there should be no obvious deformation, and the installation position of the water stop device should be determined; Step 5-2, install the adjustment pad. According to the design requirements, select the adjustment pad of corresponding thickness, lay it flat and fit it at the required installation position on the dock door, and use welding rods to weld and fix the adjustment pad. The adjustment pad should be installed flat and without burrs, and the joints should be polished flat without obvious protrusions. The overall flatness of the adjustment pad should not exceed 3mm; Step 5-3, drilling, the drilling holes include a first bolt hole for installing the pressure block and a second bolt hole for installing the water-stop rubber strip, the deviation of the center distance between two adjacent bolt holes is no more than 1mm, and there is no cumulative deviation, the two ends of the bolt holes are chamfered 45°, and there are no burrs; Step 5-4, install the pressure blocks. The personnel on both sides install two rows of pressure blocks simultaneously, use the bolt and nut assembly to pre-tighten, check whether the straightness and parallelism of the pressure blocks after installation meet the requirements of the drawings, check whether the water-stopping conditions of the bolt holes after the pressure blocks are installed meet the requirements, and adjust the upper plane of the pressure blocks in time to meet the requirements of the drawings; Step 5-5, install the waterproof rubber strip and the stainless steel pressure plate, place the waterproof rubber strip on the floor where the installation surface is located, trim the position of the waterproof rubber strip, ensure that the force of each section of the waterproof rubber strip is even, ensure that the elasticity and size of the waterproof rubber strip meet the installation conditions, mark and punch the waterproof rubber strip, install the waterproof rubber strip and the stainless steel pressure plate, use the bolt and nut assembly for pre-tightening, adjust the tightness of the waterproof rubber strip, and adjust the straightness and flatness of the waterproof surface of the waterproof rubber strip to meet the requirements of the drawing; Step 5-6, tighten all bolt and nut assemblies, check that the straightness and flatness of the pressure block and water-stop rubber strip after tightening meet the requirements of the drawing, and install the bolt hole cover at the pressure block; Steps 5-7: Inspection after installation. Inspection items include: (1) Check whether the pressure block has cracks or defects; (2) Check whether the water-stop rubber strip has cracks or defects, and focus on checking whether the right-angle joints have damage or unevenness; (3) Check that the assembly flatness deviation of the pressure block is no more than ±1mm / 1m and no more than ±3mm / 30m; (4) Check that the flatness deviation of the water-stop surface of the water-stop rubber strip is not greater than ±1mm / 1m and not greater than ±3mm / 30m; (5) Check that the bolt hole covers at the pressure block are intact and without any gaps.
5. The method for constructing a high-center-of-gravity, low-stability dock door according to claim 4, Features: The water-stop device comprises an adjusting pad, a pressure block, a water-stop rubber strip, a stainless steel pressure plate, a bolt and nut assembly and a bolt hole cover; The dock door is provided with a groove for installing a water-stop device, and a water-stop device is provided at each relative position on the side of the groove; The adjusting pad is installed on the side of the groove, the waterproof rubber strip and the pressure block are both fitted on the side of the adjusting pad away from the dock door, the pressure block has two and is symmetrically arranged on both sides of the waterproof rubber strip, and the pressure block is provided with an assembly groove; The pressure-bearing block, the adjusting pad and the dock door cooperate to form a first bolt hole that matches the bolt and nut assembly, the first bolt hole is located in the assembly groove, and the pressure-bearing block is fixedly connected to the adjusting pad by assembling the bolt and nut assembly in the first bolt hole, and the bolt hole cover is clamped at the opening of the assembly groove to form a closed space in the assembly groove; The water-stop rubber strip, the adjusting pad and the dock door cooperate to form a second bolt hole that matches the bolt and nut assembly. The bolt and nut assembly is assembled in the second bolt hole to fix the water-stop rubber strip on the adjusting pad. The stainless steel pressure plate is arranged on the side of the water-stop rubber strip away from the adjusting pad and is sleeved on the bolt of the bolt and nut assembly. The stainless steel pressure plate is pressed against the water-stop rubber strip by tightening the bolt and nut assembly.
6. A launching method, used for a high-center-of-gravity, low-stability dock gate constructed by the construction method of the high-center-of-gravity, low-stability dock gate according to claim 1, Features: The launching method comprises the following steps: Step S1: Selecting the launching time: after the dock door is built in the dock, the launching time is selected according to the water depth requirement in the dock when the dock door is launched and the tide table; Step S2, preparatory work before water filling, installing functional equipment on the dock door, closing all dock door ballast water tank subdivision valves, temporarily filling the ballast water tank with water to the required height, and testing whether the wind force before leaving the dock meets the ship inclination test specifications; Step S3, cable the dock door. To prevent the dock door from colliding with the dock wall due to the influence of water flow and to ensure the stability of the dock door, the dock door and the mooring equipment on both sides of the dock are cabled in advance before releasing the water; Step S4, the dock door is floated, water is released into the dock, the draft of the dock door is always observed and the state of the dock door is observed to see whether it is floating, and the position of the dock door is adjusted through the mooring equipment to prevent the dock door from colliding with the dock wall; Step S5, the dock gate is undocking. After the tide stabilizes, four tugboats are organized to tow the dock gate. Before towing, the four tugboats are tied with cables at the four corners of the dock gate, and the mooring equipment cables between the dock gate and both sides of the dock are released. When towing, the tugboats first move longitudinally to the middle of the dock, then move laterally to leave the dock and move to the destination.
7. The method for launching water according to claim 6, Features: In step S3, the dock door cable follows the figure eight cable principle, that is, the angle of the cable mooring is an outward or inward figure eight.
8. The method for launching water according to claim 6, Features: Step S4, the dock door is floated, water is released into the dock, the draft of the dock door is always observed and the state of the dock door is observed to see whether it is floating, the position of the dock door is adjusted by mooring equipment to avoid the dock door from colliding with the dock wall, and the long axis direction of the dock door is directed toward the dock exit; In step S5, the longitudinal movement is movement along the width direction of the dock door, and the lateral movement is movement along the long axis direction of the dock door.
9. The method for launching water according to claim 8, Features: The mooring equipment includes three winches and a traction trolley, wherein two winches are installed on one side of the dock wall, and another winch and traction trolley are arranged on the other side of the dock wall, and the winches and traction trolley are respectively connected to the dock door through cables.
Citation Information
Patent Citations
Joining method of dock gate
CN102101525A
Installation method of overlong twin-skeg structure segment and shaft bracket dock
CN102431626A
Process for sectionally putting up ship berths or docks
CN102582784A
Berth combination method in ship construction
CN102910255A
Ship total group erection method
CN109850066A