Winter loading and spring welding construction method for large-span ultra-wide continuous steel box girder bridge in large-temperature-difference environment

By adopting the ‘winter welding and spring welding’ construction method on the long-span steel structure box girder bridge, the problems of welding quality and construction period in environments with large temperature differences were solved, efficient and low-cost construction was achieved, and project quality and energy saving were ensured.

CN118720338APending Publication Date: 2024-10-01POWERCHINA MUNICIPAL CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410784126.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-18
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

Large-span steel structure box girder bridges are constructed in an environment with large temperature differences, especially low temperatures in winter and high temperatures in summer, which pose great challenges to welding quality and construction period, resulting in increased construction difficulty, extended construction period, high energy consumption, and difficulty in ensuring welding quality.

Method used

Adopting the 'winter clothing and spring welding' construction method, the steel box beams are assembled in winter, the assembly parameters and gap control are adjusted, and welding is carried out in spring, through fixed spot welding in time periods, batch welding, cross welding and welding Inspection and other steps should be taken to optimize the construction process, reduce weld repairs, and avoid large-area welding preheating and post-weld insulation.

Benefits of technology

It ensures the quality and safety of the project, reduces energy consumption and weld defects, improves work efficiency, reduces construction costs, and achieves green and energy-saving construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118720338A_ABST
    Figure CN118720338A_ABST
Patent Text Reader

Abstract

The invention provides a construction method for winter loading and spring welding of a large-span ultra-wide continuous steel box girder bridge in a large-temperature-difference environment. Winter assembly comprises the following steps that S11, girder sections are positioned, and a supporting system is strengthened; s12, beam section gap control; s13, plate stacking, fixing, preheating and heat preservation are conducted; s14, mounting and positioning closure sections at the two ends; according to the thermal expansion and cold contraction amount and thermodynamic simulation analysis under the full-bridge unconstrained condition, the distance between the end box girder and the bridge abutment is determined in combination with the temperature range when the closure section is installed; spring welding comprises the following steps that S21, fixed spot welding is conducted in different periods; s22, welding is conducted pairwise according to batches; s23, welding a cross-shaped welding seam; s24, welding the test section; s25, weld joint gap inspection and coping are conducted before welding; s26, welding is started; and S27, welding inspection is conducted. According to the method, weld joint repair is reduced, and engineering quality safety is ensured; large-area welding preheating and post-welding heat preservation work are avoided, and huge energy consumption is reduced; the working efficiency is improved, energy, manpower and material resources are saved, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of building construction, and in particular relates to a winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment. Background Art

[0002] The large-span steel box girder bridge has a large amount of work and is located in a hilly area. The construction spans winter and the temperature difference is large. The temperature difference throughout the year exceeds 55°C, which has a great impact on the steel structure construction. In particular, the temperature difference on the surface of the steel structure at the construction site can reach more than 70°C, which poses a great challenge to the linear control, closure and welding quality of the steel bridge assembly;

[0003] The on-site installation and welding construction of the bridge spanned all four seasons of the year. The temperature in summer reached over 35°C, and the surface temperature of the steel structure reached over 50°C. The lowest temperature in winter reached minus 20°C, and the surface temperature of the steel structure was below minus 22°C. The temperature difference was greater than 70°C. Due to the harsh outdoor working environment in winter, the temperature environment no longer meets the welding requirements for low-alloy steel structures. Moreover, the bridge is located in an open area, more than 13 meters away from the river surface, and the wind speed in winter exceeds level 5. According to conventional engineering construction methods, similar steel structure construction in this area is in the "winter break period", that is, work is suspended in winter; but the project is on a tight schedule. If work is suspended in winter, it will directly affect the progress of other related projects, which will have a great impact.

[0004] Therefore, how to ensure the construction period and quality under the natural conditions of the area is an urgent problem to be solved. Summary of the invention

[0005] In view of this, the present invention aims to propose a winter installation and spring welding construction method for a large-span and ultra-wide continuous steel box girder bridge under a large temperature difference environment, adjust the construction process procedures, installation group parameters, time period and stage positioning and other measures to control assembly and welding technical indicators, optimize the construction process, adopt the "winter installation, spring welding" construction method, reduce weld rework, ensure the quality and safety of the project; avoid large-area welding preheating and post-weld insulation work, reduce huge energy consumption; improve work efficiency, save energy and manpower and material resources, and reduce construction costs.

[0006] To achieve the above object, the technical solution of the present invention is achieved as follows:

[0007] Winter installation and spring welding construction method for large-span ultra-wide continuous steel box girder bridges in large temperature difference environments: assemble the steel box girders in winter and weld them in spring;

[0008] The winter assembly includes the following steps:

[0009] S11, beam segment positioning and strengthening support system; add support pads and reinforcement plates at the bottom of the steel box beam to ensure that the bottom of the steel box beam is closely combined with the adjustment pier pad;

[0010] S12, beam section gap control: the gap between two steel box beams is controlled within 10mm-40mm;

[0011] S13, preheating and heat preservation of the fixed yard plate; the circumferential seam in the length direction is not fixed and connected, and the longitudinal seam in the width direction is reinforced with the yard plate, and the yard plate is welded to the top of the steel box girder; before installing the yard plate, the surrounding area is preheated with a flame, and then the yard plate is fixed by spot welding, and the preheating and welding are completed continuously, and the yard plate is insulated after welding with rock wool;

[0012] S14. Installation and positioning of the joint sections at both ends; based on the thermal expansion and contraction of the entire bridge under unconstrained conditions and thermodynamic simulation analysis, combined with the temperature range during the installation of the joint sections, determine the distance between the end box girder and the abutment.

[0013] Spring welding includes the following steps:

[0014] S21, spot welding in different time periods: fix the top plate in the morning, fix the bottom plate in the afternoon, and assemble the positioning web in the evening;

[0015] S22, welding in batches in pairs to form even-numbered segments of 2, 4, 6, and so on, and welding them into a whole;

[0016] S23, cross weld welding, for the cross welds of the top and bottom plates that intersect each other longitudinally and transversely, the longitudinal welds shall be welded continuously first, and after the non-destructive testing is qualified, the overall circumferential weld shall be welded;

[0017] S24, test section welding: select any half width of the section for welding test, and conduct welding test in the order of vertical seam first, then transverse seam and then overhead welding;

[0018] S25. Inspection and grinding of weld gap before welding;

[0019] S26, start welding;

[0020] S27. Welding inspection.

[0021] Furthermore, in step S12 of winter assembly, clearance control is performed on positions above 60000 mm span, wherein:

[0022] When the temperature is -0℃ to 10℃, the length is 60000mm to 70000mm, and the gap between the pairs is 10 to 20mm; when the length is 70000 to 80000mm, the gap between the pairs is 20 to 30mm; when the length is more than 80000mm, the gap between the pairs is 35mm; when the temperature is -10℃ to 20℃, the length within 70000mm is installed;

[0023] Length 70000~80000mm, gap between pairs 15~25mm; length 80000mm~90000mm, gap between pairs 25~35mm; length above 90000mm, gap between pairs 40mm.

[0024] 3. The winter-spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment according to claim 1 is characterized in that: in the spring welding step S22:

[0025] The longitudinal seams of each longitudinal section are first welded to form a whole section. The circumferential seams between sections are welded according to 4-6 sections per span. After the welding of each span is completed, the butt welds reserved between spans are welded, and finally the welding of the entire bridge is completed.

[0026] Furthermore, in step S23, the longitudinal weld is more than 200 mm away from the circumferential weld; during welding, the welds at the intersection are cleaned by carbon arc gouging, the groove is ground to be the same as the groove of the circumferential weld, and then the single circumferential weld is continuously welded.

[0027] Furthermore, in step S25, the welding gap is controlled between 6 mm and 15 mm.

[0028] Furthermore, in step S26, process control is performed during the welding process, which specifically includes the following steps:

[0029] 1) Before welding, use a grinder to grind the weld area to a glossy finish, remove oil, rust or other impurities, and ensure that the transition between plates of different thicknesses is smooth;

[0030] 2) Before using welding materials, dry them according to the instructions; take out the dried welding materials as needed and keep them dry during use; dry them again if they are left at room temperature for more than 4 hours; repeat the drying process no more than twice; when operating in the open air overnight, the welding materials must be properly stored and are not allowed to be stored in the open air. They must be kept at a constant temperature in a low-temperature oven, otherwise they must be dried again before use the next day.

[0031] 3) During the welding process, ensure consistent fusion, penetration and flatness. The weld surface should be well-formed and have a smooth transition with the parent material. The butt weld must be fully penetrated and the welding heat energy can be adjusted so that the welding fusion zone is between 5% and 10%;

[0032] 4) Each welding position shall be welded strictly according to the process parameters of the welding process assessment, and the welding process shall be recorded;

[0033] 5) When welding the butt welds of the bridge deck top plate using CO2 gas shielded welding, the maximum wind speed in the welding operation area shall not exceed 8m / s, and the wind speed for gas shielded arc welding shall not exceed 2m / s.

[0034] Further, in step S27, after welding is completed for more than 24 hours, 100% of the Class I and Class II welds are subjected to UT testing, 10% of the butt welds and 100% of the cross welds are subjected to RT testing, and the welds are subjected to MT testing according to the specification requirements.

[0035] Compared with the prior art, the winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment described in the present invention has the following advantages:

[0036] (1) The winter installation and spring welding construction method of a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment of the present invention ensures the quality and safety of the project; avoids large-area welding preheating and post-weld insulation work, and reduces huge energy consumption; improves work efficiency, saves energy and manpower and material resources, and reduces construction costs.

[0037] (2) The winter-spring welding construction method for a large-span, ultra-wide continuous steel box girder bridge under a large temperature difference environment of the present invention reduces batch low-temperature welding work, effectively reduces the probability of weld defects, improves the first-time welding pass rate, reduces weld repair by 6%, and ensures welding quality and the overall quality of the project. The application of this technology has greatly reduced energy consumption, reduced hazardous waste emissions, and achieved green and energy-saving construction. At the same time, it has been promoted and applied in subsequent projects with the same natural conditions, and has also achieved the same effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the accompanying drawings:

[0039] Figure 1 A schematic diagram of the overall geometric model of a bridge according to an embodiment of the present invention;

[0040] Figure 2 A schematic diagram of an overall finite element model of a bridge according to an embodiment of the present invention;

[0041] Figure 3 A schematic diagram of a weld geometry model according to an embodiment of the present invention;

[0042] Figure 4 A schematic diagram of a finite element model of a weld according to an embodiment of the present invention;

[0043] Figure 5 This is a schematic diagram of the weld gap of a steel box girder at room temperature (20° C.) according to an embodiment of the present invention;

[0044] Figure 6 This is a schematic diagram of the change of the weld gap at -20°C according to an embodiment of the present invention;

[0045] Figure 7This is a schematic diagram of the change of the weld gap at 15°C according to an embodiment of the present invention;

[0046] Figure 8 This is a schematic diagram of the change of the weld gap at 50°C according to an embodiment of the present invention;

[0047] Fig. 9 This is a schematic diagram of the stress deformation of the weld at -20°C according to an embodiment of the present invention;

[0048] Fig.10 This is a schematic diagram of the stress deformation of the weld at 15°C according to an embodiment of the present invention;

[0049] Fig.11 This is a schematic diagram of the stress deformation of the weld at 50°C according to an embodiment of the present invention;

[0050] Fig.12 This is a schematic diagram of weld strain distribution at -20°C according to an embodiment of the present invention;

[0051] Fig.13 This is a schematic diagram of weld strain distribution at 15°C according to an embodiment of the present invention;

[0052] Fig.14 This is a schematic diagram of the change of the weld gap at 50°C according to an embodiment of the present invention;

[0053] Fig.15 This is a schematic diagram of weld stress distribution at -20°C according to an embodiment of the present invention;

[0054] Fig.16 This is a schematic diagram of weld stress distribution at 15°C according to an embodiment of the present invention;

[0055] Fig.17 This is a schematic diagram of weld stress distribution at 50°C according to an embodiment of the present invention;

[0056] Fig.18 This is a schematic diagram of a support system according to an embodiment of the present invention;

[0057] Fig.19 It is a schematic diagram of the steel box girder sections according to an embodiment of the present invention;

[0058] Fig. 20 This is a schematic diagram of the steel box girder structure described in an embodiment of the present invention.

[0059] Description of reference numerals: DETAILED DESCRIPTION

[0060] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments may be combined with each other.

[0061] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and the like are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first", "second", and the like may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0062] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances.

[0063] The present invention will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.

[0064] The patent of this invention studies a construction method that comprehensively considers the relationship between the assembly and welding construction procedures and process parameters of large-span bridges due to factors such as large temperature differences and low-temperature welding that cannot meet regulatory requirements, and optimizes the implementation of assembly and welding processes;

[0065] Take Jinzhong Xiaohe Bridge as an example:

[0066] The Xiaohe Bridge is 57.6 meters wide, the widest bridge of its kind in China. The bridge is 360 meters long, divided into 6 spans, with a maximum span of 90 meters and a maximum box beam height of 3.2 meters. The steel structure of the entire bridge weighs about 13,600 tons, and the material used is Q345qD low-alloy bridge steel. The left and right box beams and the middle cross beam are divided into more than 500 sections, with the widest section being 3.3 meters, the longest being 17.5 meters, and the heaviest being 44.1 tons.

[0067] Welding in a low-temperature environment has always been a difficult problem to solve in the steel structure industry. Generally, when the ambient temperature is lower than the standard, overall preheating and insulation measures or local preheating and insulation can be taken for small and medium-sized components. However, the Xiaohe Bridge is large in size: the width of the left and right box bodies is 46 meters (excluding the pedestrian bridges at both ends), and the maximum span is 90 meters; the construction environment is harsh: the bottom of the box beam is more than 13 meters from the ground, and the heat dissipation rate is fast; the box body is 3.2 meters high, and the partitions and ribs in the box body are crisscrossed, and the welding space is closed and narrow; the welding work surfaces are numerous and complex: the welding volume in a single box section can reach more than 1,000 meters, including horizontal, vertical, horizontal, and vertical multi-directional welding. It is extremely difficult to preheat and insulate according to the conventional method, and the quality of the welds during the welding process is difficult to guarantee;

[0068] Research plan ideas:

[0069] First, carry out low-temperature welding tests as usual: first, freeze the test piece and preheat the welding and insulation near the weld to check whether the welding of the test piece meets the requirements; second, cool down the local area of ​​the box, preheat the welding and insulation of the weld to check whether the weld meets the requirements; third, seal the box and divide it into multiple separate spaces for preheating welding and insulation to check whether the weld meets the requirements.

[0070] Second, break the routine, research and innovate new assembly and welding modes, and keep the work going in winter while ensuring the quality and safety of welding to ensure the construction period: according to the thermal expansion and contraction characteristics of steel structures, combined with the specific dimensions of the beams, analyze the stress, deformation and expansion parameters of the beams under various temperature conditions, study the various parameters and support methods of the winter box beam assembly, and when the spring comes, the temperature rises, and the ambient temperature is suitable for welding operations, review and calibrate the technical parameter indicators of the assembly, and formulate a reasonable welding process for welding. That is, the method of low-temperature assembly in winter and welding at a suitable temperature in spring when the temperature rises.

[0071] By comparing the quality of the above two modes and taking into account energy consumption and construction benefits, a reasonable construction method is determined;

[0072] Before construction, simulation verification is required to find a suitable construction plan. The specific construction method simulation verification steps are as follows:

[0073] 1. Low temperature welding test analysis

[0074] 1. Laboratory simulation of low temperature welding and rapid cooling test after welding

[0075] (1) According to the thickness of the box girder steel plate, select a group of 16mm and 25mm plates, and make a standard

[0076] Welding procedure test specimens;

[0077] (2) Place the test piece in the freezer of a refrigerator to simulate the welding test in a test room. Keep the test piece warm for 2 hours after it reaches -18°C;

[0078] (3) Take out the test piece and place it in the welding area. Use flame preheating to preheat the area within 50 mm on both sides of the weld to above 20°C, and use a laser temperature meter to measure;

[0079] (4) Draft welding procedure and design welding parameters;

[0080] (5) Welding shall be performed by welders who meet the qualification requirements according to the process parameters.

[0081] The welding parameters are shown in Table 1 below:

[0082]

[0083] (6) After welding, wrap the specimen with asbestos to keep it warm, put it in the refrigerator, and cool it quickly after welding for more than 2 hours;

[0084] (7) 24 hours after the test plate is welded, the weld is subjected to 100% ultrasonic flaw detection, Class B inspection, and Class I is qualified;

[0085] (8) Conduct tensile, bending and impact tests on the welded specimens;

[0086] 1) Test plate sampling: The mechanical properties test sampling standard shall be based on GB2649-89.

[0087] 2) Test items, standards and methods are shown in Table 2 below.

[0088]

[0089]

[0090] 2. Cool down the local area of ​​the box and then preheat and weld;

[0091] (1) Local cooling of the box

[0092] Prefabricated ice blocks are used to cool the weld within 2 meters to below -5°C, meeting the welding technology requirements for low-temperature welding tests.

[0093] (2) Preheating welding

[0094] There are two general ways to preheat local welding: flame preheating and industrial heating blanket preheating. Industrial heating blankets are mostly used for flat welds. Since this project involves more vertical welding, horizontal welding, and overhead welding, only flame preheating was used in the test. The preheating and welding process is measured with a laser thermometer, and welding is performed after the temperature meets the requirements.

[0095] The welding parameters are the same as those in Table 1. Rock wool is used for insulation after welding. Because it is difficult to cool down the local area in this test and mechanical property tests cannot be performed after welding, only non-destructive testing can be performed on the weld to verify the weld. After testing, local cracks were found in the weld on the outside of the box, so this method is not suitable for winter welding construction.

[0096] 3. Seal the box and divide it into several separate spaces for preheating welding test;

[0097] The internal partitions of the box girder are crisscrossed, and only ¢600mm pedestrian holes are set at the main stress-bearing positions of the partitions, and square process holes are set at non-main stress-bearing positions; there are no holes in the web of the box room along the entire length of the bridge (except for the welding holes at the transverse stiffening ribs of the bottom plate);

[0098] The spacing between the partitions of the pedestrian holes is about 10000mm, and the spacing between the partitions of the process holes is about 3000mm. Since the spacing of 10000mm is too long and not conducive to preheating and heat preservation, the test is carried out within a length of 3000mm. The web spacing of the closed space of the test section is 4500mm, and the box beam height is 3200mm;

[0099] An industrial heater is used to preheat and insulate the enclosed space. The preheating environment temperature is designed to be around 20°C. Tests are conducted on three types of welds, including the vertical welds between partitions and the flat welds between partitions and bottom plates. Safety protection measures are taken during the test: First, vents are set on the top plate of the box beam, and special fans are used for ventilation to keep the people in the space safe; second, CO2 fire extinguishers are set inside the space to ensure fire safety; third, full-time safety personnel track and protect the entire process;

[0100] The test was carried out at the three types of welds, the groove and lining were treated as for the first type of welds, and the welding was carried out according to the welding parameters in Table 1;

[0101] After welding, keep warm for 2 hours and cool naturally. After 24 hours, conduct nondestructive testing on the weld. The internal quality of the weld is qualified. This test cannot be used to test the mechanical properties of the weld.

[0102] From the perspective of welding quality, this method can be implemented in principle. Since the preheating energy consumption of this experiment is relatively large, the energy consumption is measured and analyzed during the research process.

[0103] During the test, the highest ambient temperature was minus 2°C and the lowest was minus 8°C. It took 10 hours for the preheating space to reach 20°C, 6 hours for the actual welding test, and 2 hours for insulation. The entire preheating, welding and insulation time was 18 hours.

[0104] Comparison of theoretical heat consumption for space heating and energy consumption in actual test:

[0105] 1) Test space volume V = 3*3.2*4.5 = 43.2 (m 3 );

[0106] 2) 1m 3 The theoretical energy required to raise the air temperature by 1°C is: E1=1×1.29×1.003=1.2939 (kJ).

[0107] At standard atmospheric pressure: the specific gravity of air is 1.185kg / m^3; the specific heat of air is 1.003kJ / (kg·k),

[0108] The theoretical energy required for the entire space to rise in temperature by 1°C is: E2=43.2*1.2939=55.8952 (kJ).

[0109] Before heating, the average ambient temperature is -5°C, and the temperature is raised to 20°C, with a total temperature increase of 25°C. The theoretical energy required is E3=55.8952*25=1397.4 (kJ).

[0110] 1 kWh = 1 kilowatt-hour = 3600 kJ, so 1397.4 kJ ≈ 0.3881 kilowatt-hour.

[0111] Calculated based on a thermal efficiency of 90%, the theoretical energy required to raise the temperature of the enclosed space by 25°C is 0.3881 / 90% = 0.431 kWh.

[0112] The actual test used two 2kw-3kW automatic temperature-controlled heating fans, which worked for 18 hours and actually consumed about 40 degrees of electricity. The actual consumption was about 100 times the theoretical amount.

[0113] Through on-site inspection and analysis, the main reasons for the low thermal efficiency are: first, the thermal conductivity of the steel plate is high, and the heat is dissipated quickly; second, the bottom plate, web plate stiffening ribs and top plate U ribs are dense, and the heat dissipation through the welding holes is fast; third, the local climate is windy in winter with high wind speed. The bottom of the box girder is 13m above the ground, and the heat dissipation at the joint between the top and bottom plates is extremely fast;

[0114] Based on the above analysis, the test can be preheated inside a relatively closed cabin, so that the entire independent cabin reaches the required temperature of the welding environment, which is flexible and safe to move, and can be insulated and slowly cooled after welding, achieving certain results. However, the local winter lasts for a long time, with daily temperatures below minus 8°C for more than 16 hours, and the lowest temperature can reach below minus 20°C, resulting in a huge heat loss. If the box girder is fully insulated and sealed for welding, it is difficult to implement on site. Therefore, although the welding test results meet the requirements, if actual implementation is considered, huge costs will be invested, energy consumption is immeasurable, and there is still a certain risk to welding quality under low temperature conditions.

[0115] In addition, for large box girders, the test data cannot fully reflect the actual situation on site. If all box girders are preheated for welding and heat-insulated after welding, the heat loss during the heating process is extremely large, and heat-insulation after welding is difficult to carry out. In order to ensure the quality of the project, the assembly and welding processes are comprehensively considered, the construction cost is taken into account, the climate change law in Jinzhong is studied and analyzed, and the construction control method of "winter installation, spring welding" is innovated, that is, the "winter installation and spring welding" technology;

[0116] "Winter installation and spring welding" means that welding cannot be carried out in winter due to the low temperature. Measures can be taken to carry out installation and assembly, and the joints can be temporarily fixed. Welding can be carried out when the temperature becomes suitable in spring.

[0117] The patent of this invention is based on the thermal expansion and contraction characteristics of steel structures, combined with the specific dimensions of the beam body to study and analyze the stress, deformation and expansion parameters of the beam body in each temperature range, and innovate the various parameters and support methods of the winter box beam assembly. When the spring comes, the temperature rises, and the ambient temperature is suitable for welding operations, the installation technical parameter indicators of the assembly pair are reviewed and corrected, and a reasonable welding process is formulated for welding;

[0118] The verification process of “Construction method of winter installation and spring welding for large span and ultra-wide continuous steel box girder bridge under large temperature difference environment” is as follows;

[0119] 1. Establish a simulation model for finite element analysis:

[0120] (1) Basic principles of thermodynamic finite element analysis

[0121] The general three-dimensional heat transfer equation in thermodynamics can be expressed as:

[0122]

[0123] When the thermal conductivity λ is a constant, the Laplace operator is used Then the imported equation can be expressed by the operator as:

[0124]

[0125] Among them, the mathematical expression of the Laplace operator is:

[0126]

[0127] The temperature distribution of the steel plate structure can be calculated using the thermodynamic conduction equation.

[0128] During the calculation process, the initial temperature boundary conditions are set, the temperature of any point on the outer boundary of the material at each time and the convection coefficient between the object and the surrounding environment are given, and according to the Newton cooling formula, the surface heat transfer coefficient is used, and the boundary conditions can be expressed as follows:

[0129]

[0130] Where: T e is the temperature of the surrounding temperature field, and β is the convection heat transfer coefficient.

[0131] Through the boundary conditions of the material, the heat conduction equation can be solved to obtain the theoretical material temperature distribution.

[0132] Temperature changes in materials can cause thermal deformation of the structure. Thermal deformation is thermoelasticity. Like elasticity, when solving thermoelasticity problems, it is necessary to meet the basic assumptions of elasticity and abstract the material structure and properties into an ideal model as the object of theoretical analysis.

[0133] If the temperature inside the object changes to T, if the tiny length of each point is not constrained, positive strain will occur, and the concept of linear elastic expansion coefficient will appear. In isotropic materials, the expansion coefficient does not change with direction, so there is no shear stress. When there is an external constraint on the object, the free deformation of the object is constrained, and thermal stress is generated inside the object. The deformation equation of the object caused by this thermal stress is:

[0134]

[0135] Because the geometric relationship between deformation and displacement does not change due to different causes of deformation and displacement, when solving plane stress problems, the physical equation is:

[0136]

[0137] When solving plane strain problems, the physical equation is:

[0138]

[0139] To study the thermal deformation law of the structure, it is necessary to solve the above thermoelastic equation. When the temperature of the solid changes, since each point in the solid cannot change in the same proportion, any point in the solid will be constrained by the adjacent units of the point and cannot deform freely. When the solid is constrained by the outside world, any point in the solid will not be able to deform freely. This internal and external constraint of the solid causes it to generate certain stresses corresponding to the thermal deformation caused by the temperature change. In this case, the stress generated is thermal stress.

[0140] (2) Comparative analysis of thermal stress by finite element method

[0141] 1) Establishment of the overall model of bridge welded steel plate

[0142] According to the design dimensions of the bridge, a 1:1 geometric model is established and a finite element model is generated. The box girder is 3200mm high and 370000mm long. The width of the bridge is symmetrical and connected by discontinuous box girders with unequal spacing in the middle. Therefore, the width is calculated based on the width of a single solid box girder of 21000mm. A weld geometry model and a finite element model are established between the box girder steel plates that make up the bridge deck; Figure 1-Figure 4 As shown;

[0143] 2) Analysis of deformation of bridge body welded box girder steel plate

[0144] Thermal expansion coefficient of steel: Under unconstrained conditions, the deformation of the steel plate depends on the thermal expansion coefficient of the material itself. The thermal expansion coefficient of steel ranges from (10-20)×10-6 / ℃. The larger the coefficient, the greater the deformation after heating, and vice versa. The thermal expansion coefficient is not a constant, but changes slightly with temperature and increases with rising temperature. This project uses Q345qD, whose thermal expansion coefficient is 12×10-6 / ℃ for low alloy steel, which means that it expands by 0.012mm per meter per degree. Without considering the change with temperature, the expansion coefficient and the expansion per meter are considered as fixed values.

[0145] Taking the normal temperature of 20℃ as the benchmark, the thermal deformation generated at different temperatures, namely -20℃ in winter, 15℃ in spring and 50℃ in summer, is compared.

[0146] A. Maximum and minimum theoretical deformation under unconstrained conditions

[0147] In principle, the theoretical deformation refers to the uniform change of thermal expansion and contraction of the steel plate. It has nothing to do with the box girder structure and only needs to consider the length of the required position.

[0148] a. Width direction: The width of the box girder is 21000mm, the width of the top plate of the outermost segment box girder is 2500mm, and the distance between the outermost butt welds is 18500mm; the width of the top plate of the innermost segment box girder is 3200mm, and the distance between the closest butt welds is 3200mm. The deformation of the joints at different temperatures in the width direction is shown in Table 3.

[0149] Deformation table of longitudinal joints of box beams under unconstrained conditions

[0150]

[0151] b. Length direction: The total length of the bridge is 370 meters, and the spans are 55+55+60+90+55+55 (meters). The intersection of the 60-meter and 90-meter spans is taken as the origin, and calculations are made towards both ends. Taking the maximum length of a single section at the pier of 17.5 meters, and spans of 60 meters, 90 meters, 115 meters, 145 meters, and 180 meters as examples, the theoretical deformation is calculated as shown in Table 4 below;

[0152] Deformation table of transverse joints of box beams under unconstrained conditions

[0153]

[0154] Through analysis and comparison, it was found that at an extreme temperature difference of 70°C, the maximum deformation under unconstrained conditions was: 15.54mm for the longitudinal weld in the direction of the bridge width, and 151.2mm for the transverse weld in the direction of the bridge length.

[0155] Thermal stress analysis of welds under constrained conditions: Taking room temperature of 20℃ as the benchmark, compare the thermal deformation at different temperatures of -20℃ in winter, 15℃ in spring and 50℃ in summer. The coordinate direction is based on the intersection of 60m and 90m spans, and the length is calculated towards both ends. Analyze at the box girder length of 60000mm, the weld gap is 12mm, and the steel plate thickness is 20mm.

[0156] The temperature of -20℃ in winter, 15℃ in spring and 50℃ in summer was applied respectively. The thermal stress deformation of the weld was caused by applying different temperatures as shown in the figure. The temperature is based on 20℃. When the temperature decreases, the steel plate shrinks and the weld gap expands; when the temperature increases, the weld gap shrinks; Figure 5-8 As shown;

[0157] Finite element analysis joint deformation table at 60000mm under constraint conditions

[0158]

[0159] According to the weld deformation, the steel plate shrinks when the temperature is below 20℃, and the relative gap of the weld at -20℃ increases by 18.623mm; the relative gap of the weld at 15℃ increases by 3.11mm; the steel plate expands when the temperature is above 20℃, and the gap of the weld at 50℃ decreases by 11.55mm. Through analysis, it can be seen that when the extreme temperature difference is 70 degrees, the gap difference is 30.173mm, which exceeds the process parameter range of the weld gap (6-15mm for gasket welding gap). If the group is considered according to the 15℃ welding process gap in spring, the difference between the weld gap in winter and the gap in summer is 15.5mm, and the difference between the weld gap in winter and the gap in summer is 14.6mm, which is basically within the process parameter range within 60 meters.

[0160] It can be seen that if the winter installation and spring welding method is adopted, the weld gap problem caused by the contraction of low-temperature steel plates in winter and the expansion of steel plates in summer can be effectively reduced. At the same time, by calculating the thermal deformation of the box girder steel plates at temperatures such as winter, spring and summer, it not only provides a reference for determining the gap in the assembly process, but also provides a prerequisite for analyzing the stress of the weld, and infers the change of the gap at the splicing position of each segment by analogy;

[0161] 3) Bridge weld stress analysis

[0162] Due to the effect of thermal expansion and contraction, the weld position is squeezed and stretched by the steel plate, which can easily cause damage to the weld structure. By analyzing the thermal deformation displacement of the weld (changed to the displacement change described in the previous section), the displacement load is applied to the weld structure, and the influence of welding at different seasonal temperatures such as -20℃, 15℃, and 50℃ on the weld structure is analyzed;

[0163] A. Weld stress and deformation analysis, such as Figure 9-11 As shown,

[0164] That is, the gap difference between the weld gap when welding at a temperature of -20℃ and the gap caused by thermal expansion of the steel plate structure in summer, and the difference between the weld gap at 15℃ in spring and the weld gaps in winter and summer under the winter-spring welding technology, are added as displacement loads to the corresponding weld positions, and the displacement change data under the winter-spring welding technology is compared with that under the winter-spring welding technology;

[0165]

[0166] By comparison, it can be seen that the displacement changes are mainly concentrated near the edge of the weld. The maximum displacement of winter welding is twice the displacement produced by the winter-spring welding technology. Therefore, this technology greatly reduces the extrusion displacement of the weld and improves the safety of the weld.

[0167] B. Weld stress and strain analysis, such as Figure 12-Figure 17 As shown;

[0168] Judging from the stress distribution and size caused by the temperature difference of thermal stress on the weld, when the weld structure is subjected to extrusion, the stress and strain are mainly concentrated near the weld surface. When winter welding is adopted, after summer, due to the rise in temperature, the weld structure is subjected to a larger extrusion effect, and the maximum strain is 9.235mm. The maximum stress of 124MPa exceeds the allowable stress of the weld structure, resulting in structural cracking of the weld. When the winter-installation-spring welding technology is adopted, the maximum strain of the weld in winter is 3.2mm, and the maximum strain in summer is 3.0mm, while the stresses are 63.8MPa and 61.3MPa respectively, and the stress is reduced to half of the original stress, which greatly reduces the thermal stress value caused by the temperature difference, improves the safety of the weld structure, and ensures the quality and service life of the project.

[0169] It can be seen from this that if the winter installation and spring welding method is adopted, the weld stress problem caused by the contraction of low-temperature steel plates in winter and the expansion of steel plates in summer can be effectively reduced.

[0170] Winter installation and spring welding construction method for large-span ultra-wide continuous steel box girder bridges in large temperature difference environments: assemble the steel box girders in winter and weld them in spring;

[0171] The winter assembly includes the following steps:

[0172] S11, beam segment positioning and strengthening support system; add support pads and reinforcement plates at the bottom of the steel box beam to ensure that the bottom of the steel box beam is closely combined with the adjustment pier pad;

[0173] The box girder installation adopts the in-situ bracket support system, such as Fig.18 As shown in the figure, the bottom plate of the box beam is connected to the main support of the lower column steel pipe by the temporary adjustment pier through the distribution beam. After the hoisting and installation positioning, if the welding is not timely, the support cannot be removed, which will cause local deformation of the beam section under the action of thermal expansion and contraction, and the beam section and the pier will have relative displacement;

[0174] The overall structure of the main bridge is divided into 24 sections along the length of the bridge. Each section is supported by multiple columns and adjustable piers. The specific structure is as follows: the main pipe of the box beam support adopts φ609×16, the connection system adopts Ⅰ14, the distribution beam adopts double-pieced I56b I-beam, and the top of the distribution beam is equipped with an adjustable pier pipe. In order to ensure the stability of the support, additional support pads and reinforcement plates are installed in winter to make the bottom of the beam and the adjustable pier pads tightly combined, so as to alleviate the local deformation of the beam section caused by thermal expansion and contraction after winter installation. The local damage to the bottom of the box beam caused by displacement, ensure the local support quality of the beam section.

[0175] S12, beam section gap control: the gap between two steel box beams is controlled within 10mm-40mm;

[0176] The Xiaohe Bridge is 370m long and has 6 spans. The two middle spans are 90m and 60m respectively, and the four spans at both ends are 55m each. The starting point is the intersection of the 90m span and the 60m span. The installation sequence is to proceed from this point to both ends, with lengths of 170m and 200m respectively. When winter assembly begins, the welding length at both ends reaches 60m.

[0177] One of the biggest challenges of winter installation is determining the assembly gap. According to theoretical research on the unconstrained state and finite element analysis, the maximum expansion and contraction deformation of the longitudinal welds in the width direction of the bridge is within the requirements of the welding process parameters. Therefore, during installation, the longitudinal welds are controlled according to the gaps required by the process parameters and the code plates are positioned. Due to the thermal expansion and contraction of the steel plates, the expansion and contraction of the transverse welds in the length direction of the bridge greatly exceeds the process assembly parameter range. Therefore, the research believes that during winter assembly, the transverse welds are not connected and the gaps are determined based on the principle of thermal expansion and contraction of unconstrained steel plates and finite element calculations. According to the position of the splicing seams from the origin and other conditions, and combined with the ambient temperature range during installation, the gaps of the splicing seams at each position are determined. When winter construction began, most of the 6000mm span and 90000mm span had been assembled, so only positions above 60000mm were considered for winter installation and spring welding;

[0178] When the temperature is -0℃ to 10℃, the length is 60000mm to 70000mm, and the gap between the pairs is 10 to 20mm; when the length is 70000 to 80000mm, the gap between the pairs is 20 to 30mm; when the length is more than 80000mm, the gap between the pairs is 35mm; when the temperature is -10℃ to 20℃, the length within 70000mm is installed;

[0179] Length 70000~80000mm, group gap 15~25mm; length 80000mm~90000mm, group gap 25~35mm; length above 90000mm, group gap 40mm, gap control table is as follows:

[0180]

[0181] S13. Fix the preheating and insulation of the code plates; the circumferential seams in the length direction are not fixed and connected, and the longitudinal seams in the width direction are reinforced with code plates, which are welded to the top of the steel box girder; before installing the code plates, the surrounding area is preheated with a flame and then the code plates are fixed by spot welding, and the preheating and welding are continued. Rock wool is used to insulate the code plates after welding; cracks are prevented in the code plate reinforcement welds, which affect the quality of the fixed welding installation.

[0182] S14. Installation and positioning of the joint sections at both ends; the main bridge of Xiaohe Bridge is divided into 6 spans, the lengths of each span are different, and the positioning of the joint sections of each span is different. The joint section of the middle span can be smoothly adjusted during the installation process. The joint section of the box girder at both ends of the abutment needs to be determined according to the thermal expansion and contraction of the whole bridge under unconstrained conditions and thermodynamic simulation analysis, combined with the temperature range during the installation of the joint section, to determine the distance between the end box girder and the abutment. Otherwise, if the installation gap is not properly controlled, it will affect the working length of the expansion joint, and even the box girder will conflict with the retaining wall after thermal expansion in summer;

[0183] For example, the Xiaohe Bridge is 370 meters long, with an extreme temperature of 40℃ in summer and minus 18℃ when the joint section is assembled in winter, with a temperature difference of 58℃. The thermal expansion coefficient of low-alloy steel is 12×10-6 / ℃, which means that the expansion is 0.012mm per meter per degree, and the total expansion is about 260mm. Therefore, according to the design drawings, the distance between the two ends of the box girder and the abutment needs to be adjusted by about 130mm.

[0184] With the arrival of spring, the temperature is suitable and welding work can be carried out;

[0185] Spring welding includes the following steps:

[0186] S21, spot welding in different time periods: fix the top plate in the morning, fix the bottom plate in the afternoon, and assemble the positioning web in the evening;

[0187] Steel box girder structure Fig. 20 As shown;

[0188] Since the cross section of the beam section of this project reaches 3200mm, the top and bottom plates are affected by sunlight differently. Under normal circumstances, due to the influence of sunlight, the temperature of the top plate rises and gradually expands, while the bottom plate is not exposed to sunlight and is still the real-time temperature. The temperature is generally between 3pm and 6pm, and the temperature difference between the top and bottom plates can reach more than 15℃. Therefore, the temperature in the morning is relatively low, about 8-15℃, and the grouping and fixing are carried out under the condition of short-term sunlight and relatively small expansion; the temperature rises in the afternoon, and the temperature of the bottom plate rises accordingly, close to the temperature when the top plate is assembled in the morning, and the bottom plate is fixed at this time; the height of the web plate reaches 3200mm, and the gap above it changes with the temperature to form a small top and a large bottom, that is, the upper part expands faster than the lower part. Since the top plate has been fixed first, the upper expansion is constrained, and the middle of the web plate expands faster than the upper and lower ends. When the bottom plate is fixed, the web plate can be taken into account. In the evening, the temperature and the temperature of the beam body drop, the expansion naturally recovers, and the web plate is fixed.

[0189] Before welding, the circumferential seams of each segment need to be fixed and spot welded. When fixing, the gaps between the top plate, web plate and bottom plate of the box girder will have large differences, and uniform fixing does not meet the welding parameter requirements. Since the ambient temperature is only one of the factors affecting the thermal expansion and contraction deformation of the box girder, the influence of light in spring and summer is also a very important factor. The height of the box girder is 3.2m. The box girder panel is directly exposed to sunlight, the temperature rises suddenly, and the thermal expansion and elongation, while the bottom plate of the box girder is basically the ambient temperature, and the gap remains in place. As a result, the thermal expansion and contraction are different, resulting in a large difference in the upper and lower gaps, and it is impossible to uniformly spot weld and position; according to the linear expansion coefficient of the steel plate, the gap of the weld beam section is measured in different time periods, and the temperature change is used to fix the top plate in the morning, fix the bottom plate in the afternoon, and finally position the web plate, that is, the method of adjusting the fixation and spot welding in different time periods avoids the problem of gap differences in the splicing welds of the same segment, which can effectively ensure the welding quality and control the welding deformation.

[0190] S22. Weld in batches in pairs to form even-numbered segments of 2, 4, 6, and so on, which are welded together into a whole; first weld the longitudinal seams of each longitudinal segment to form a whole segment, and weld the circumferential seams between segments according to 4-6 segments per span. For example, after the longitudinal welds of the four segments A, B, C, and D are completed, the butt seams and circumferential seams of A and B are welded first, then the butt seams between C and D, and finally B and C are connected to avoid excessive thermal expansion and contraction of the overall steel box girder after being connected into pieces, which may cause the weld gap of the unwelded beam section to be too large or too small. After the welding of each span is completed, the butt welds reserved between spans are welded, and finally the welding of the entire bridge is completed.

[0191] S23. Cross weld welding: For the cross welds that intersect the top and bottom plates in the longitudinal and transverse directions, the longitudinal welds shall be welded continuously first. After the non-destructive testing is qualified, the overall circumferential welds shall be welded. The longitudinal weld shall be more than 200mm away from the circumferential weld. When welding, the welds at the intersection shall be cleaned by carbon arc gouging, and the groove shall be ground to be the same as the groove of the circumferential weld, and then the single circumferential weld shall be continuously welded to complete the process.

[0192] S24, test section welding: select any half width of the section for welding test, and conduct welding test in the order of vertical seam first, then transverse seam and then overhead welding;

[0193] There are 8 sections and 4 cabins in half width. Each cabin is welded by a team of 2 people. The order of welding is longitudinal seam first, then transverse seam, vertical seam first, then transverse seam, and then overhead welding. After the test section is qualified, subsequent batch welding is carried out, and fire extinguishers are placed in the cabin. When welding in the cabin, at least 2 welders are required in each cabin, and they should rest outside the cabin for half an hour every 2 hours. In order to ensure the personal safety of welders, a full-time contact person is set up.

[0194] S25. Inspection and grinding of weld gap before welding;

[0195] Preparation work before welding - grinding of welds and grooves is one of the necessary conditions for ensuring welding quality. Due to the influence of thermal expansion and contraction, the gap between beam sections changes dynamically. Before welding in spring, all weld gaps should be checked and ground, and the gap should be controlled at about 6 to 15 mm. The welds and surrounding areas should be completely ground to reveal the metallic luster, otherwise welding defects are likely to form during the welding process, which will affect the quality of the welds. In order to improve the quality of work, in addition to professional training and technical briefing for construction personnel, information technology is also used, and WeChat group training and communication management is adopted. At the same time, strict control is carried out during the construction process to ensure the quality of grinding before welding, providing a solid foundation for ensuring the overall quality of welding.

[0196] S26. Start welding. The steel structure welds of this project mainly include full-throttle bevel welds, partial-throttle bevel welds and ordinary fillet welds. The on-site Class I and Class II welds exceed 100,000 meters, of which 80% are in the box girder cabin. Except for the submerged arc automatic welding of the top plate cover welding outside the cabin, the rest are all welded by ceramic-lined flux-cored wire gas shielded welding, and the fillet welds are welded by double-sided flux-cored wire. The even number of welders on the left and right sides work simultaneously and symmetrically to ensure a uniform welding sequence. The key points of welding process control are as follows, including:

[0197] 1) Before welding, use a grinder to grind the weld area to a glossy finish, remove oil, rust or other impurities, and ensure that the transition between plates of different thicknesses is smooth;

[0198] 2) Before using welding materials, dry them according to the instructions; take out the dried welding materials as needed and keep them dry during use; dry them again if they are left at room temperature for more than 4 hours; repeat the drying process no more than twice; when operating in the open air overnight, the welding materials must be properly stored and are not allowed to be stored in the open air. They must be kept at a constant temperature in a low-temperature oven, otherwise they must be dried again before use the next day.

[0199] 3) During the welding process, ensure consistent fusion, penetration and flatness. The weld surface should be well-formed and have a smooth transition with the parent material. The butt weld must be fully penetrated and the welding heat energy can be adjusted so that the welding fusion zone is between 5% and 10%;

[0200] 4) Each welding position shall be welded strictly according to the process parameters of the welding process assessment, and the welding process shall be recorded;

[0201] 5) When welding the butt welds of the bridge deck top plate using CO2 gas shielded welding, the maximum wind speed in the welding operation area shall not exceed 8m / s, and the wind speed for gas shielded arc welding shall not exceed 2m / s.

[0202] S27, welding inspection: After each section is welded, self-inspection is qualified. More than 24 hours after welding is completed, 100% of Class I and Class II welds are tested by UT, 10% of butt welds and 100% of cross welds are tested by RT, and MT tests are performed on welds according to the specifications. After the test is qualified, a third-party professional non-destructive testing agency will conduct a random inspection of no less than 30% of the welds.

[0203] By studying and applying the "winter equipment and spring welding" construction method, the batch of low-temperature welding work has been reduced, the probability of weld defects has been effectively reduced, the first-time welding pass rate has been improved, and the weld rework has been reduced by 6%, ensuring the welding quality and the overall quality of the project. The application of this technology has greatly reduced energy consumption, reduced hazardous waste emissions, and achieved green and energy-saving construction.

[0204] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment, characterized by: The steel box girders are assembled in winter and welded in spring; The winter assembly includes the following steps: S11, beam segment positioning and strengthening support system; add support pads and reinforcement plates at the bottom of the steel box beam to ensure close integration of the bottom of the steel box beam and the adjustment pier pad; S12, beam section gap control: the gap between two steel box beams is controlled within 10mm-40mm; S13, preheating and heat preservation of the fixed yard plate; the circumferential seam in the length direction is not fixed and connected, and the longitudinal seam in the width direction is reinforced with the yard plate, and the yard plate is welded to the top of the steel box girder; before installing the yard plate, the surrounding area is preheated with a flame, and then the yard plate is fixed by spot welding, and the preheating and welding are completed continuously, and the yard plate is insulated after welding with rock wool; S14, installation and positioning of the joint sections at both ends; according to the thermal expansion and contraction under unconstrained conditions of the whole bridge and thermodynamic simulation analysis, combined with the temperature range during the installation of the joint sections, determine the distance between the end box girder and the abutment; Spring welding includes the following steps: S21, spot welding in different time periods: fix the top plate in the morning, fix the bottom plate in the afternoon, and assemble the positioning web in the evening; S22, welding in batches in pairs to form even-numbered segments of 2, 4, 6, and so on, and welding them into a whole; S23, cross weld welding, for the cross welds of the top and bottom plates that intersect vertically and horizontally, the longitudinal welds shall be welded continuously first, and after the non-destructive test is qualified, the overall circumferential weld shall be welded; S24, test section welding: select any half width of the section for welding test, and conduct welding test in the order of vertical seam first, then transverse seam and then overhead welding; S25. Inspection and grinding of weld gap before welding; S26, start welding; S27. Welding inspection.

2. The winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment according to claim 1 is characterized in that: In step S12 of winter assembly, clearance control is performed for positions above 60000 mm span, wherein: When the temperature is -0℃ to 10℃, the length is 60000mm to 70000mm, and the gap between the pairs is 10 to 20mm; when the length is 70000 to 80000mm, the gap between the pairs is 20 to 30mm; when the length is more than 80000mm, the gap between the pairs is 35mm; when the temperature is -10℃ to 20℃, the length within 70000mm is installed; Length 70000~80000mm, gap between pairs 15~25mm; length 80000mm~90000mm, gap between pairs 25~35mm; length above 90000mm, gap between pairs 40mm.

3. The winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment according to claim 1 is characterized in that: In step S22 of spring welding: The longitudinal seams of each longitudinal section are first welded to form a whole section. The circumferential seams between sections are welded according to 4-6 sections per span. After the welding of each span is completed, the butt welds reserved between spans are welded, and finally the welding of the entire bridge is completed.

4. The winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment according to claim 1, characterized in that: In step S23, the longitudinal weld is more than 200 mm away from the circumferential weld; during welding, the cross welds are cleaned by carbon arc gouging, the groove is ground to be the same as the circumferential groove, and then the single circumferential weld is continuously welded.

5. The winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment according to claim 1 is characterized in that: In step S25, the welding gap is controlled between 6 mm and 15 mm.

6. The winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment according to claim 1 is characterized in that: In step S26, process control is performed during the welding process, which specifically includes the following steps: 1) Before welding, use a grinder to grind the weld area to a glossy finish, remove oil, rust or other impurities, and ensure that the transition between plates of different thicknesses is smooth; 2) Before using welding materials, dry them according to the instructions; take out the dried welding materials as needed and keep them dry during use; dry them again if they are left at room temperature for more than 4 hours; repeat the drying process no more than twice; when operating in the open air overnight, the welding materials must be properly stored and not allowed to be stored in the open air. They must be kept at a constant temperature in a low-temperature oven, otherwise they must be dried again before use the next day; 3) During the welding process, ensure consistent fusion, penetration and flatness. The weld surface should be well-formed and have a smooth transition with the parent material. The butt weld must be fully penetrated and the welding heat energy can be adjusted so that the welding fusion zone is between 5% and 10%; 4) Each welding position shall be welded strictly according to the process parameters of the welding process assessment, and the welding process shall be recorded; 5) When welding the butt welds of the bridge deck top plate using CO2 gas shielded welding, the maximum wind speed in the welding operation area shall not exceed 8m / s, and the wind speed for gas shielded arc welding shall not exceed 2m / s.

7. The winter installation and spring welding construction method for a large-span ultra-wide continuous steel box girder bridge under a large temperature difference environment according to claim 1 is characterized in that: In step S27, after welding is completed for more than 24 hours, 100% of Class I and Class II welds are tested by UT, 10% of butt welds and 100% of cross welds are tested by RT, and MT tests are performed on welds according to specification requirements.