High-power V2G charging pile based on direct-current bus and control method thereof
Through the high-power V2G charging pile based on the DC bus, combined with the intelligent scheduling of unidirectional DC/DC and bidirectional DC/DC modules, the problem of high cost of V2G charging piles and overdraft of battery cycles is solved, and efficient energy transmission and grid balance are achieved. , improving the stability and sustainability of the power grid.
Patent Information
- Application Number
- CN202410832886.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-26
- Publication Date
- 2024-10-01
AI Technical Summary
The bidirectional DC/DC modules used in existing V2G charging piles are high in cost and low in efficiency. Overdraft of new energy vehicle battery cycles results in low utilization of V2G functions and affects the balance of the power grid.
Using a high-power V2G charging stack based on the DC bus, combined with intelligent dispatching of unidirectional DC/DC and bidirectional DC/DC modules, through real-time monitoring and multi-vehicle dispatch management units, module allocation and energy transmission are optimized, reducing the number of modules and improving the system efficiency, and support renewable energy access.
It reduces equipment and operating costs, improves the flexibility and efficiency of energy use, enhances the stability and sustainability of the power grid, improves the utilization of V2G functions, and is suitable for a variety of environments.
Smart Images

Figure CN118722307A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of new energy vehicle charging stacks, and in particular to a high-power V2G charging stack based on a direct current bus and a control method thereof. Background Art
[0002] With the development of the new energy vehicle industry, the number of new energy vehicles in my country is increasing day by day, and the demand for charging new energy vehicles is also increasing. The large number of vehicle loads and daily life, industrial and other electricity consumption put a heavy burden on the power grid, especially the power grid during peak hours. In addition to being a load, the batteries of new energy vehicles can also be used as energy storage devices to transmit energy to the power grid to alleviate the pressure on the power grid during peak hours. In this context, V2G technology has been widely used, and at the same time, several problems that need to be solved have been highlighted in the practical application of the technology:
[0003] (1) The bidirectional DC / DC modules used in V2G charging piles are expensive and have poor economic efficiency.
[0004] Compared with unidirectional DC / DC modules, the topological structure of bidirectional DC / DC modules that realize V2G functions determines that it will use more expensive components, and more costs will be invested in device selection. At the same time, the control method of bidirectional DC / DC is more complicated, and more resources will be invested in the design of the control circuit, including investment in hardware devices and more R&D investment. In addition, due to its topological structure and device selection, bidirectional DC / DC is bound to have more self-loss than unidirectional DC / DC modules, and there will be a certain gap in conversion efficiency. Under the current demand for high-power fast charging, the economic benefits of using a large number of bidirectional DC / DC modules to build a high-power charging pile in terms of cost and efficiency are not high.
[0005] (2) Overdrawing the number of battery cycles for new energy vehicles remains a major challenge for the commercialization of V2G technology.
[0006] The life span of electric vehicle batteries makes owners of new energy vehicles reluctant to use the V2G function of charging piles, which makes the utilization rate of the V2G function of charging piles low. The actual benefits of V2G are not particularly objective, and it is difficult to achieve vehicle-grid balance by this alone. Summary of the invention
[0007] In view of the deficiencies in the above-mentioned prior art, the present invention provides a high-power V2G charging stack based on a DC bus and a control method thereof, which can support intelligent scheduling of bidirectional DC / DC and unidirectional DC / DC modules, and can effectively reduce the number and use of modules in traditional V2G systems, thereby reducing costs and improving system efficiency.
[0008] The specific technical solutions are as follows:
[0009] In a first aspect, a high-power V2G charging stack based on a DC bus is provided, comprising:
[0010] DC bus, used to connect the charging terminal and the energy system to maintain a stable voltage output;
[0011] Charging gun, an interface for charging the vehicle;
[0012] The unidirectional DC / DC module is used to connect the DC bus to the charging gun in one direction and has a one-to-one correspondence with the charging gun;
[0013] A bidirectional DC / DC module is used for bidirectional conversion between the DC bus and the charging gun; one bidirectional DC / DC module corresponds to multiple charging guns, and a first switch is provided between the bidirectional DC / DC module and the charging gun; adjacent charging guns are connected via a second switch;
[0014] Real-time monitoring module, which monitors the battery status, charging and discharging requirements and grid conditions of each vehicle in real time; and
[0015] The multi-vehicle dispatching management unit is used to coordinate the charging and discharging operations of multiple vehicles. It obtains the vehicle's power status, user demand and grid status according to the real-time monitoring module, assigns different priorities and performs charging and discharging operations on the vehicles according to the priority level.
[0016] When the vehicle is charging, the multi-vehicle scheduling management unit dynamically schedules the allocation of unidirectional DC / DC modules and bidirectional DC / DC modules according to the data sent by the real-time monitoring module. The priority of scheduling the unidirectional DC / DC module is higher than that of the bidirectional DC / DC module. The first switch and the second switch are controlled to be closed to form the allocation of the unidirectional DC / DC module and the bidirectional DC / DC module. When the vehicle transmits energy to the power grid, the multi-vehicle scheduling management unit dynamically schedules the bidirectional DC / DC module according to the data sent by the real-time monitoring module. The first switch and the second switch are controlled to be closed to form the allocation of the bidirectional DC / DC module. Finally, the energy of the vehicle is transmitted to the power grid through DC / AC.
[0017] Furthermore, in the above scheme, the multi-vehicle dispatch management unit sets an emergency discharge priority to ensure that the power grid can quickly obtain energy in an emergency.
[0018] In the above solution, the DC bus AC / DC module is connected to an AC power grid.
[0019] The above solution further includes a renewable energy access interface connected to the DC bus, and the access interface is connected to the photovoltaic module and the MPPT module, the energy storage battery and the PCS module.
[0020] Furthermore, in the above solution, when the vehicle is charging, the real-time monitoring module and energy management strategy are used to preferentially use the renewable energy access interface to access the DC bus for charging.
[0021] Furthermore, in the above solution, the unidirectional DC / DC module can be replaced by a bidirectional DC / DC module.
[0022] In a second aspect, a control method for a high-power V2G charging stack based on a DC bus is provided, comprising:
[0023] When the vehicle is connected to the charging pile, the real-time monitoring module obtains the vehicle's battery status and charging and discharging requirements;
[0024] The multi-vehicle dispatch management unit assigns initial priorities to the vehicles and determines whether to perform charging or discharging operations;
[0025] The real-time monitoring module monitors the battery status and grid load of the vehicle in real time. The multi-vehicle dispatching management unit dynamically adjusts the allocation of bidirectional DC / DC and unidirectional DC / DC modules based on the real-time data of the real-time monitoring module.
[0026] During the real-time monitoring of the charging and discharging process of each vehicle, the priority and charging and discharging power of each vehicle are dynamically adjusted through the load balancing algorithm to balance the power output of each vehicle to avoid overloading of a single vehicle.
[0027] In the above scheme, the load balancing algorithm steps include:
[0028] 1) Vehicle weight calculation: The weight is calculated based on the vehicle's priority and battery status. The formula is as follows:
[0029]
[0030] Among them, Wi is the power weight of vehicle i, Pi is the priority of vehicle i, Ei is the current power of vehicle i, and Emax is the maximum power of vehicle i;
[0031] 2) Total power calculation: Calculate the total available power Ptotal of the system;
[0032] Vehicle power allocation: Allocate the charging and discharging power Pi of each vehicle according to the weight Wi. The formula is as follows:
[0033]
[0034] Where N is the number of electric vehicles;
[0035] Actual allowable power:
[0036] When i=1, P 1 Is it greater than the required power P of vehicle A? A需, if it is less than, the power output to vehicle A is limited to P 1 And ΔP 1 =0;
[0037] If it is greater than, the limited power of vehicle A is the required power P A需 , and calculate ΔP 1 .
[0038] ΔP 1 =P 1 -P A需
[0039] Determine P2+ΔP 1 Is it greater than the required power P of vehicle B? B需 , if it is less than, the power output to vehicle B is limited to P2 and ΔP 2 =0;
[0040] If it is greater than, the limited power of vehicle B is the required power P B需 , and calculate ΔP 2 ;
[0041] ΔP 2 =P 2 +ΔP 1 -P B需
[0042] And so on, all vehicles are allocated overpower in turn;
[0043] 3) The number of power modules to be switched is allocated according to the actual allowed power, the priority and the rated power of a single power module rounded up, and the power modules are unidirectional DC / DC modules and bidirectional DC / DC modules;
[0044] 4) Perform feasibility optimization on the allocated modules according to the switching structure of the power modules and the discharge priority strategy.
[0045] In the above scheme, step 4) further comprises:
[0046] If the number of power modules allocated for switching is greater than the modules that can be switched on the charging line of this charging vehicle, the modules that can be switched are used; if the number of power modules allocated for switching is less than the modules that can be switched on the vehicle charging line, check whether the modules that can be switched are in an idle state. If they are in an idle state and the sum of the rated powers of the power modules allocated for switching is less than the power required by the vehicle, the idle modules are switched on to the charging line of the vehicle in sequence until the sum of the rated powers of the modules switched on the charging line of the vehicle is greater than the power required by the vehicle.
[0047] Compared with the prior art, the present invention has the following beneficial effects:
[0048] The DC bus-based charging stack of the present invention connects all charging terminals and energy systems, maintains a stable voltage output, and optimizes energy transmission efficiency. The intelligent scheduling of bidirectional DC / DC modules and unidirectional DC / DC modules can achieve optimal energy distribution according to the needs of the power grid and electric vehicles. The charging stack design includes an interface that allows photovoltaic power generation and energy storage systems to be directly connected to the DC bus, using electricity generated by renewable energy and releasing stored electricity during peak demand periods. The system reduces dependence on separate V2G modules and reduces equipment and operating costs through more efficient energy scheduling.
[0049] The V2G charging stack of the present invention not only improves the flexibility and efficiency of energy use, but also enhances the stability and sustainability of the power grid by supporting the integration of renewable energy. It is suitable for a variety of environments such as urban public charging stations, residential areas and commercial facilities, and is expected to play an important role in promoting the development of smart grids and green transportation.
[0050] The implementation of the present invention helps to achieve both economic and environmental benefits of electric vehicle charging infrastructure, and provides an efficient technical solution for the future development of electric vehicles and smart grids. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] Figure 1 It is a schematic diagram of the functional architecture of the system of the present invention;
[0052] Figure 2 It is a schematic diagram of the switching structure of the unidirectional DC / DC module and the bidirectional DC / DC module of the charging stack. DETAILED DESCRIPTION
[0053] The following is a further detailed description of the embodiments of the invention in conjunction with the accompanying drawings to make the objectives, technical solutions and technical effects of the invention more clearly presented.
[0054] like Figure 1 As shown, the present invention proposes a high-power V2G charging stack based on a DC bus, including a DC bus, a charging gun, a unidirectional DC / DC module, a bidirectional DC / DC module, a real-time monitoring module and a multi-vehicle scheduling management unit.
[0055] The DC bus is used to connect the charging terminal and the energy system to maintain a stable voltage output. The charging gun is an interface for vehicle charging. The unidirectional DC / DC module is used to connect the DC bus to the charging gun in one direction, and corresponds to the charging gun one-to-one. The bidirectional DC / DC module is used for bidirectional conversion between the DC bus and the charging gun; one bidirectional DC / DC module corresponds to multiple charging guns, and a first switch is provided between the bidirectional DC / DC module and the charging gun; adjacent charging guns are connected by a second switch.
[0056] The real-time monitoring module is used to monitor the battery status, charging and discharging requirements and power grid conditions of each vehicle in real time.
[0057] The multi-vehicle dispatching management unit is used to coordinate the charging and discharging operations of multiple vehicles. It obtains the vehicle's power status, user demand and grid status according to the real-time monitoring module, assigns different priorities and performs charging and discharging operations on the vehicles according to the priority level.
[0058] When the vehicle is charging, the multi-vehicle scheduling management unit dynamically schedules the allocation of unidirectional DC / DC modules and bidirectional DC / DC modules according to the data sent by the real-time monitoring module. The priority of scheduling the unidirectional DC / DC module is higher than that of the bidirectional DC / DC module. The first switch and the second switch are controlled to be closed to form the allocation of the unidirectional DC / DC module and the bidirectional DC / DC module. When the vehicle transmits energy to the power grid, the multi-vehicle scheduling management unit dynamically schedules the bidirectional DC / DC module according to the data sent by the real-time monitoring module. The first switch and the second switch are controlled to be closed to form the allocation of the bidirectional DC / DC module. Finally, the energy of the vehicle is transmitted to the power grid through DC / AC.
[0059] Among them, the unidirectional DC / DC module and the bidirectional DC / DC module are the power modules of the charging stack, specifically the power conversion module. The first switch and the second switch etc. constitute the switching structure of the unidirectional DC / DC module and the bidirectional DC / DC module, which are used to allocate the corresponding number of power modules of the vehicle, that is, the corresponding number of unidirectional DC / DC modules and bidirectional DC / DC modules.
[0060] like Figure 1 As shown, the dotted box is the charging stack based on the DC bus proposed in this patent. Due to its special structure based on the DC bus, the functions of the traditional AC / DC and DC / DC integrated charging modules are separated, and AC / DC and DC / DC conversion are performed separately. The rectification and power factor correction functions after the AC grid input are completed by a high-power AC / DC module, and its output part is connected to the DC bus. At the same time, the DC bus also supports the connection of the photovoltaic module MPPT module and the energy storage battery PCS module. The DC bus needs to pass through the charging module, that is, the DC / DC module, to the vehicle end.
[0061] The charging stack proposed in the present invention includes multiple bidirectional DC / DC modules and multiple unidirectional DC / DC modules, and the specific number ratio is based on comprehensive consideration of usage requirements and costs. The bidirectional DC / DC module can be switched to any charging gun output port of the charging stack, so that the v2g function can be realized no matter which port the charging pile is used. Figure 2 shown.
[0062] For economic reasons, the number of bidirectional DC / DC modules used is small. The proposed charging pile has a structure that can switch limited bidirectional DC / DC modules to any vehicle charging gun port. These bidirectional DC / DC modules can be intelligently scheduled through a unified multi-vehicle scheduling management unit. Usually only unidirectional DC / DC modules work during charging. When the power demand is higher, more unidirectional DC / DC modules or even bidirectional DC / DC modules will be scheduled to participate in charging; but when the power demand is met, bidirectional DC / DC modules will be used as little as possible or used less to ensure the normal use of V2G functions.
[0063] When transmitting energy from the vehicle to the grid, the bidirectional DC / DC module will be scheduled according to the vehicle's discharge power. A single or multiple vehicles can transmit energy to the DC bus through one or more bidirectional DC / DC modules, and then the high-power DC / AC will transmit the vehicle's energy to the grid.
[0064] When all bidirectional DC / DC modules are fully loaded, subsequent vehicles will not be able to discharge to the grid. In addition, the charging pile can also replace the unidirectional DC / DC module with a bidirectional DC / DC module to achieve a smooth upgrade of the charging pile, improve the charging and discharging power of V2G, and reduce the difficulty and cost of charging pile transformation.
[0065] In addition, the charging stack proposed by the present invention also includes an interface for the energy storage system and an access interface for photovoltaic components, as well as related MPPT modules and PCS functional modules. In addition to the vehicle-to-grid, it also supports energy flow in all directions, from photovoltaics to the grid or vehicle, and from the energy storage system to the grid or vehicle, to achieve the integrated use of the power system, and at the same time relieve the pressure on the grid from multiple angles.
[0066] Based on the above solution, the present invention also discloses a control method for a high-power V2G charging stack based on a DC bus, comprising:
[0067] When the vehicle is connected to the charging pile, the real-time monitoring module obtains the vehicle's battery status and charging and discharging requirements;
[0068] The multi-vehicle dispatch management unit assigns initial priorities to the vehicles and determines whether to perform charging or discharging operations;
[0069] The real-time monitoring module monitors the battery status and grid load of the vehicle in real time. The multi-vehicle dispatching management unit dynamically adjusts the allocation of bidirectional DC / DC and unidirectional DC / DC modules based on the real-time data of the real-time monitoring module.
[0070] During the real-time monitoring of the charging and discharging process of each vehicle, the priority and charging and discharging power of each vehicle are dynamically adjusted through the load balancing algorithm to balance the power output of each vehicle to avoid overloading of a single vehicle.
[0071] The charging stack of the present invention dynamically manages the charging and discharging process of electric vehicles, supports direct access to photovoltaic and energy storage systems, and realizes smooth expansion of the photovoltaic storage and charging system; at the same time, the charging stack supports intelligent scheduling of bidirectional DC / DC modules and unidirectional DC / DC modules, adds a V2G implementation method on the basis of the basic charging function, and takes cost issues into consideration.
[0072] The adjustment strategy of the charging stack of the present invention is: different priorities are assigned according to the power status of the vehicle, user needs and power grid status. Vehicles with high priorities are given priority for charging and discharging operations. Emergency discharge priority is set to ensure that the power grid can quickly obtain energy in an emergency.
[0073] The control strategy of the charging stack of the present invention includes:
[0074] 1. Initial connection: (1) When a vehicle is connected to the charging pile, the real-time monitoring module obtains the battery status and charging and discharging requirements of the vehicle. (2) The multi-vehicle dispatch management unit assigns initial priority and determines whether to perform charging or discharging operations.
[0075] 2. Dynamic scheduling: (1) The multi-vehicle scheduling management unit monitors the battery status and grid load of the vehicles in real time, and dynamically adjusts the allocation of bidirectional DC / DC and unidirectional DC / DC modules through scheduling strategies. (2) According to the priority and real-time demand, the charging and discharging power of each vehicle is adjusted to ensure efficient use of system resources.
[0076] 3. Load balancing: (1) Real-time monitoring of the charging and discharging process of each vehicle, and balance the power output of each vehicle through the load balancing algorithm to avoid overloading of a single vehicle. (2) Dynamically adjust the priority and charging and discharging power of each vehicle to ensure that all vehicles meet their respective charging and discharging needs while efficiently utilizing system resources.
[0077] 4. Energy management: (1) Give priority to the use of renewable energy for charging, and optimize the utilization of photovoltaic power generation and energy storage systems through real-time monitoring modules and energy management strategies. (2) Realize the two-way flow of energy between photovoltaic and energy storage systems and vehicles, adjust the charging strategy according to the grid demand and the availability of renewable energy, and improve the overall efficiency of the system.
[0078] The above scheme is specifically developed with examples:
[0079] 1. Connect the vehicle to the charging station
[0080] If vehicles A, B, and C are connected to the charging piles respectively, the real-time monitoring module obtains the battery status and charging and discharging requirements of each vehicle. The battery status includes the power, voltage, and temperature, and the discharge requirements include the time and power required for charging or discharging.
[0081] The multi-vehicle dispatch management unit assigns initial priorities to vehicles A, B, and C according to the battery status and requirements of the vehicles. In this example, the priorities of vehicles A, B, and C are 1, 2, 3, ..., with 1 being the highest priority.
[0082] Threshold setting: Set the power threshold, such as charging to 80% is high power, and discharging to 20% is low power.
[0083] 2. Real-time monitoring and scheduling
[0084] Vehicle A needs to be charged quickly, if the power is less than 20% and the user needs it urgently, it is assigned the highest priority.
[0085] Vehicle B needs to discharge to the grid. If the power level is higher than 80% and the grid is at peak power consumption, it is assigned the second highest priority.
[0086] Vehicle C only needs slow charging, such as when the power level is around 40% and the user does not need to use it urgently, so it is assigned the lowest priority.
[0087] The multi-vehicle dispatch management unit dynamically allocates bidirectional DC / DC and unidirectional DC / DC modules according to the priority and real-time needs of each vehicle. For example:
[0088] Vehicle A is charged with unidirectional DC / DC modules first. When the unidirectional DC / DC modules that can be switched cannot meet the charging power required by vehicle A, some bidirectional DC / DC modules are called. If the current bidirectional DC / DC module is discharging, at least one bidirectional DC / DC module is kept discharging for fast charging.
[0089] Vehicle B uses a bidirectional DC / DC module to discharge to the grid.
[0090] Vehicle C uses a unidirectional DC / DC module for slow charging.
[0091] 3. Load balancing and optimization
[0092] The charging and discharging process of vehicles A, B, and C is monitored in real time. Through a load balancing algorithm that takes weights into account, the power output of each vehicle is balanced to avoid overloading of a single vehicle.
[0093] When the power level of vehicle A reaches the set threshold, such as 80%, its charging power is automatically reduced to prioritize the discharge needs of vehicle B and avoid excessive pressure on the power grid.
[0094] If the battery level of vehicle B drops to a set threshold, such as 50% discharge, the discharge power is automatically adjusted to ensure battery life and system stability.
[0095] 4. Energy Management
[0096] When photovoltaic power generation and energy storage systems are connected, renewable energy is used to charge vehicles A and C first. For example:
[0097] When photovoltaic power generation is sufficient during the day, the photovoltaic system directly provides charging power for vehicles A and C.
[0098] The energy storage system provides charging power for vehicles A and C at night or when photovoltaic power generation is insufficient.
[0099] In order to realize the two-way flow of energy between vehicle B and the power grid, the overall energy utilization of the system is optimized through energy management strategies. For example:
[0100] During the peak period of power consumption in the power grid, the electric energy of vehicle B is fed back to the power grid first to relieve the pressure on the power grid.
[0101] During the off-peak period of power consumption in the power grid, the discharge operation of vehicle B is reduced, and energy storage or charging for other vehicles is given priority.
[0102] Here is a load balancing algorithm that takes weight into account:
[0103] 1) Vehicle weight calculation: The weight is calculated based on the vehicle's priority and battery status. The formula is as follows:
[0104]
[0105] Among them, Wi is the power weight of vehicle i, Pi is the priority of vehicle i, Ei is the current power of vehicle i, and Emax is the maximum power of vehicle i;
[0106] 2) Total power calculation: Calculate the total available power Ptotal of the system;
[0107] Vehicle power allocation: Allocate the charging and discharging power Pi of each vehicle according to the weight Wi. The formula is as follows:
[0108]
[0109] Where N is the number of electric vehicles;
[0110] Actual allowable power:
[0111] When i=1, P 1 Is it greater than the required power P of vehicle A? A需 , if it is less than, the power output to vehicle A is limited to P 1 And ΔP 1 =0;
[0112] If it is greater than, the limited power of vehicle A is the required power P A需 , and calculate ΔP 1 .
[0113] ΔP 1 =P 1 -P A需
[0114] Determine P2+ΔP 1 Is it greater than the required power P of vehicle B? B需 , if it is less than, the power output to vehicle B is limited to P2 and ΔP 2 =0;
[0115] If it is greater than, the limited power of vehicle B is the required power P B需 , and calculate ΔP 2 ;
[0116] ΔP 2 =P 2 +ΔP 1 -P B需
[0117] And so on, all vehicles are allocated overpower in turn;
[0118] 3) The number of power modules to be switched is allocated according to the actual allowed power, the priority and the rated power of a single power module rounded up, and the power modules are unidirectional DC / DC modules and bidirectional DC / DC modules;
[0119] 4) Perform feasibility optimization on the allocated modules according to the switching structure of the power modules and the discharge priority strategy.
[0120] Among them, if the number of power modules allocated for switching is greater than the modules that can be switched on the charging line of this charging vehicle, the modules that can be switched are used; if the number of power modules allocated for switching is less than the modules that can be switched on the vehicle charging line, it is checked whether the modules that can be switched are in an idle state. If they are in an idle state and the sum of the rated powers of the power modules allocated for switching is less than the power required by the vehicle, the idle modules are switched on to the charging line of the vehicle in sequence until the sum of the rated powers of the modules switched on the charging line of the vehicle is greater than the power required by the vehicle.
[0121] Specifically, the switching is allocated through the first switch and the second switch; for example, when charging, the vehicle is initially fixedly allocated a unidirectional DC / DC module. If the number of power modules allocated for switching is greater than the modules that can be switched to the charging line of this charging vehicle, that is, the number of power modules cannot meet the demand, and the total number of unidirectional DC / DC modules or bidirectional DC / DC modules is insufficient, then the actual modules that can be switched are used. If the number of unidirectional DC / DC modules allocated for switching is less than the modules that can be switched to the charging line of the vehicle, that is, the number of power modules meets the demand, then check whether any of the unidirectional DC / DC modules or bidirectional DC / DC modules that can be switched is in an idle state. If it is in an idle state, and the sum of the rated powers of the power modules allocated for switching is less than the required power of the vehicle, then the idle unidirectional DC / DC modules or bidirectional DC / DC modules are switched to the charging line of the vehicle in sequence until the sum of the rated powers of the modules switched to the charging line of the vehicle is greater than the required power of the vehicle.
[0122] The above description is only a preferred feasible embodiment of the present invention and is not intended to limit the scope of the patent application of the present invention. All equivalent changes, equivalent substitutions or modified changes performed within the technical spirit and principles suggested by the present invention should be included in the scope of patent protection covered by the present invention.
Claims
1. A high-power V2G charging stack based on a DC bus, characterized in that: include: DC bus, used to connect the charging terminal and the energy system to maintain a stable voltage output; Charging gun, an interface for charging the vehicle; The unidirectional DC / DC module is used to connect the DC bus to the charging gun in one direction and has a one-to-one correspondence with the charging gun; A bidirectional DC / DC module is used for bidirectional conversion between the DC bus and the charging gun; one bidirectional DC / DC module corresponds to multiple charging guns, and a first switch is provided between the bidirectional DC / DC module and the charging gun; adjacent charging guns are connected via a second switch; Real-time monitoring module, which monitors the battery status, charging and discharging requirements and grid conditions of each vehicle in real time; and The multi-vehicle dispatching management unit is used to coordinate the charging and discharging operations of multiple vehicles. It obtains the vehicle's power status, user demand and grid status according to the real-time monitoring module, assigns different priorities and performs charging and discharging operations on the vehicles according to the priority level. When the vehicle is charging, the multi-vehicle scheduling management unit dynamically schedules the allocation of unidirectional DC / DC modules and bidirectional DC / DC modules according to the data sent by the real-time monitoring module. The priority of scheduling the unidirectional DC / DC module is higher than that of the bidirectional DC / DC module. The first switch and the second switch are controlled to be closed to form the allocation of the unidirectional DC / DC module and the bidirectional DC / DC module. When the vehicle transmits energy to the power grid, the multi-vehicle scheduling management unit dynamically schedules the bidirectional DC / DC module according to the data sent by the real-time monitoring module. The first switch and the second switch are controlled to be closed to form the allocation of the bidirectional DC / DC module. Finally, the energy of the vehicle is transmitted to the power grid through DC / AC.
2. A high-power V2G charging stack based on a DC bus according to claim 1, characterized in that: The multi-vehicle dispatch management unit sets emergency discharge priorities to ensure that the power grid can quickly obtain energy in emergency situations.
3. The high-power V2G charging stack based on a DC bus according to claim 1 is characterized in that: The DC bus AC / DC module is connected to an AC power grid.
4. The high-power V2G charging stack based on a DC bus according to claim 1 is characterized in that: It also includes a renewable energy access interface connected to the DC bus, which connects photovoltaic panels and MPPT modules, energy storage batteries and PCS modules.
5. A high-power V2G charging stack based on a DC bus according to claim 4, characterized in that: When the vehicle is charging, the real-time monitoring module and energy management strategy are used to give priority to using the renewable energy access interface to access the DC bus for charging.
6. The high-power V2G charging stack based on a DC bus according to claim 1, characterized in that: The unidirectional DC / DC module can be detachably replaced by a bidirectional DC / DC module.
7. A control method for a high-power V2G charging stack based on a DC bus according to any one of claims 1 to 6, characterized in that: When the vehicle is connected to the charging pile, the real-time monitoring module obtains the vehicle's battery status and charging and discharging requirements; The multi-vehicle dispatch management unit assigns initial priorities to the vehicles and determines whether to perform charging or discharging operations; The real-time monitoring module monitors the battery status and grid load of the vehicle in real time. The multi-vehicle dispatching management unit dynamically adjusts the allocation of bidirectional DC / DC and unidirectional DC / DC modules based on the real-time data of the real-time monitoring module. During the real-time monitoring of the charging and discharging process of each vehicle, the priority and charging and discharging power of each vehicle are dynamically adjusted through the load balancing algorithm to balance the power output of each vehicle to avoid overloading of a single vehicle.
8. The control method of a high-power V2G charging stack based on a DC bus according to claim 7 is characterized in that: The load balancing algorithm steps include: 1) Vehicle weight calculation: The weight is calculated based on the vehicle's priority and battery status. The formula is as follows: Among them, Wi is the power weight of vehicle i, Pi is the priority of vehicle i, Ei is the current power of vehicle i, and Emax is the maximum power of vehicle i; 2) Total power calculation: Calculate the total available power Ptotal of the system; Vehicle power allocation: Allocate the charging and discharging power Pi of each vehicle according to the weight Wi. The formula is as follows: Where N is the number of electric vehicles; Actual allowable power: Determine if P1 is greater than the required power P of vehicle A when i=1 A需 , if it is less than, the power output to vehicle A is limited to P1 and ΔP1=0; If it is greater than, the limited power of vehicle A is the required power P A需 , and calculate ΔP1. ΔP1=P1-P A需 Determine whether P2+ΔP1 is greater than the required power P of vehicle B B需 , if it is less than, the power output to vehicle B is limited to P2 and ΔP2=0; If it is greater than, the limited power of vehicle B is the required power P B需 , and calculate ΔP2; ΔP2=P2+ΔP1-P B需 And so on, all vehicles are allocated overpower in turn; 3) The number of power modules to be switched is allocated according to the actual allowed power, the priority and the rated power of a single power module rounded up, and the power modules are unidirectional DC / DC modules and bidirectional DC / DC modules; 4) Perform feasibility optimization on the allocated modules according to the switching structure of the power modules and the discharge priority strategy.
9. The control method of a high-power V2G charging stack based on a DC bus according to claim 8, characterized in that: Step 4) includes: If the number of power modules allocated for switching is greater than the modules that can be switched on the charging line of this charging vehicle, the modules that can be switched are used; if the number of power modules allocated for switching is less than the modules that can be switched on the vehicle charging line, check whether the modules that can be switched are in an idle state. If they are in an idle state and the sum of the rated powers of the power modules allocated for switching is less than the power required by the vehicle, the idle modules are switched on to the charging line of the vehicle in sequence until the sum of the rated powers of the modules switched on the charging line of the vehicle is greater than the power required by the vehicle.
Citation Information
Cited By
Power distribution method, charging and discharging system, charging and discharging control unit and medium
CN119611145A
Power distribution method, charging and discharging system, charging and discharging control unit, and medium
CN119611145B
Charging management system and method
CN119872313A