A asphalt adding device for prebaked anode production
By designing asphalt addition devices in the production of prebaked anodes, the use of microconical plates to extend the residence time, the electric heating plate insulation and the vibration motor to avoid solidification, the problems of asphalt DC and heat loss are solved, and the production efficiency and product quality are improved.
Patent Information
- Application Number
- CN202411207959.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-08-30
AI Technical Summary
During the production process of pre-baked anode, asphalt is prone to be superfluous in DC flow when added, or the output speed is reduced and the heat loss is too much, resulting in solidification, affecting production efficiency.
A bitumen addition device for pre-baked anode production is designed, including components such as retention chambers, insulation chambers, vibration motors, servo motors and multi-layer microconical plates. The asphalt residence time is extended through the microconical plates, and the electric heating plates provide insulation and vibration motors. Avoid sticking and agitating rod to reduce solidification, ensuring that the asphalt remains liquid and outputs stably.
It effectively avoids asphalt accumulation and premature condensation, extends the addition time, improves production efficiency and product quality, and ensures stable and uniform output of asphalt.
Smart Images

Figure CN118723634B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of prebaked anode production equipment, and in particular to an asphalt adding device for prebaked anode production. Background Art
[0002] Prebaked anode is a product made of petroleum coke as the main raw material and coal tar pitch as a binder, which is prepared through a series of process engineering. It is finally used as the "heart" for aluminum smelting in the aluminum electrolysis production process. Therefore, the demand for anode carbon blocks is also increasing day by day. The asphalt raw material in the prebaked anode production process is solid under normal conditions. It needs to be heated to liquid before mixing with petroleum coke so that the asphalt can fill the open pores of the petroleum coke and fully cover the petroleum coke particles. However, when adding existing asphalt, the asphalt direct current is often too fast, resulting in the added asphalt being accumulated in one place in the production bin, which greatly affects the working efficiency of the prebaked anode. When the output speed is reduced, the asphalt often loses too much heat, causing the asphalt to solidify. At the same time, during the production process, therefore, we propose an asphalt adding device for prebaked anode production to solve the above-mentioned problems. Summary of the invention
[0003] The purpose of the present invention is to solve the shortcomings existing in the background technology and to propose an asphalt adding device for prebaked anode production.
[0004] In order to achieve the above purpose, the technical solution adopted by the present invention is: an asphalt adding device for prebaked anode production, including a production feeding device, the production feeding device includes a mounting frame, a retention bin is installed at the lower front end of the mounting frame, a feed port is installed at the top of the retention bin, a mounting ring is installed at the lower outer periphery of the retention bin, a pump body is installed at the top of the mounting ring, a plurality of extraction pipes are installed at the input end of the pump body, the ends of the extraction pipes away from the pump body all penetrate the wall of the insulation bin, a plurality of discharge pipes are installed at the output end of the pump body, and two discharge pipes are arranged on the outer periphery of each discharge pipe. A discharge port, the pump body is used to use the extraction pipe to extract the hotter asphalt at the inner edge of the insulation bin and transmit it to the interior of the retention bin through the discharge pipe, the bottom of the discharge port passes through the wall of the retention bin, the bottom of the retention bin is provided with an insulation bin, the bottom of the insulation bin is fixedly connected with a discharge pipe, the retention bin, the insulation bin and both ends of the discharge pipe are fixedly connected with a fixing frame, a vibration motor is installed in the middle of the fixing frame, a connecting frame is provided on one side of the vibration motor, and the end of the connecting frame away from the vibration motor is in contact with the outer walls of the retention bin, the insulation bin and the discharge pipe respectively.
[0005] Preferably, the mounting frame is installed on one side of the slide frame through a walking frame, the slide frame is arranged on the upper front and rear sides of the top frame, and the top frame is installed on the outside of the production warehouse.
[0006] Preferably, a servo motor is installed on the top of the mounting frame, a rotating shaft is fixedly connected to the bottom driving end of the servo motor, and evenly distributed guide plates are fixedly connected to the lower part of the outer periphery of the rotating shaft.
[0007] Preferably, a rotating frame is provided inside the discharge pipe, and the rotating frame is fixedly connected to the lower middle part of the outer circumference of the rotating shaft, and the rotating frame is rotatably connected to the inside of the discharge pipe.
[0008] Preferably, a stirring rod is fixedly connected to the middle and upper part of the outer circumference of the rotating shaft, and the stirring rod is arranged in the middle part of the heat preservation bin, and an electric heating plate is arranged inside the wall of the heat preservation bin.
[0009] Preferably, a plurality of micro-cone plates are installed inside the retention bin, a plurality of openings are opened on the outer side of the middle of the micro-cone plates, the distribution position of the openings on each micro-cone plate is different, and a plurality of guide rollers are arranged on the top of the micro-cone plates.
[0010] Preferably, a material guide plate is installed at the bottom of the retention bin, and a material discharge port is installed in the middle of the bottom end of the material guide plate.
[0011] Preferably, the guide rollers are provided with evenly distributed guide edges at their peripheries, the guide rollers are rotatably connected to the peripheries of fixed shafts, the fixed shafts are fixedly connected to the upper and middle parts of the peripheries of rotating shafts, the rotating shafts penetrate the micro-cone plates, and the micro-cone plates are rotatably connected to the rotating shafts.
[0012] Preferably, the micro-cone plates are all configured to be inverted cones with high sides and low sides, the guide rollers are all kept horizontal with the micro-cone plates, and the bottoms of the guide rollers are in contact with the tops of the micro-cone plates.
[0013] Preferably, a delivery pipe is installed in the middle of the front slide through a walking frame, a feed pump is connected to the top of the delivery pipe, and the other end of the delivery pipe faces the feed inlet.
[0014] Compared with the prior art, the present invention has the following beneficial effects:
[0015] 1. People can first use a delivery pump to introduce liquid asphalt into the feed port so that the liquid asphalt can enter the retention bin. A plurality of micro-cone plates are arranged inside the retention bin. The micro-cone plates are arranged in an inverted cone shape with a high outside and a low inside. While not affecting the discharge of asphalt, the micro-cone plates can effectively extend the residence time of liquid asphalt inside the retention bin, thereby effectively avoiding the situation where the added asphalt is accumulated in one place in the production bin due to too fast direct flow of asphalt, so that the asphalt can have an appropriate addition time, which is convenient for material distribution.
[0016] 2. The servo motor can drive the rotating shaft to rotate. After the asphalt falls on the micro-cone plate, the rotation of the rotating shaft can drive the guide roller and the bottom micro-cone plate to rotate relative to each other using the fixed shaft. At the same time, the guide edges arranged on the guide roller can guide the liquid asphalt accumulated on the micro-cone plate, so that the asphalt can fall through the opening to the next layer of micro-cone plate. The cooperation of multiple layers of micro-cone plates and multiple groups of guide rollers can greatly extend the time of asphalt in the detention bin and avoid asphalt solidification, which is beneficial to the pre-trained anode production work.
[0017] 3. The electric heating plate inside the insulation bin can provide an insulation environment during the process of adding asphalt to avoid heat loss of asphalt, so that the asphalt can remain in liquid state, which is conducive to the continuous addition and feeding of asphalt. At the same time, during the rotation of the shaft, it will drive the external fixed stirring rod to rotate synchronously. The stirring rod can continuously stir the asphalt inside the insulation bin to further reduce the possibility of asphalt solidification. At the same time, the stirring rod is symmetrically designed, two in a group, in a "V" shape, so that during the stirring process, a downward rotation force can be applied to the asphalt at all times, so that the asphalt can maintain a stable output state, which is conducive to the stable discharge of asphalt.
[0018] 4. During the discharge of asphalt, the pump body on the mounting ring can be used to extract the hotter asphalt from the inner edge of the insulation bin through the extraction pipe and transfer it to the inside of the retention bin, so that it can be mixed with the asphalt inside the retention bin, so that the asphalt inside the retention bin can be supplemented with heat, thereby preventing the asphalt from solidifying early.
[0019] 5. Vibration waves can be generated by the operation of the vibration motor, and the vibration waves can be transmitted to the retention bin, insulation bin and discharge pipe wall through the connecting frame and the fixing frame. The working frequencies of the vibration motors are different, which makes the vibration frequencies of the retention bin, insulation bin and discharge pipe different. In addition, the materials of the connecting frame and the fixing frame are different, so that the asphalt can receive continuous vibration waves of different frequencies during transmission, which can effectively prevent the asphalt from excessively adhering to the inner wall of the equipment and is beneficial to the addition of asphalt.
[0020] 6. When asphalt is output, the rotating rack at the lower part of the outer periphery of the rotating shaft can clean the inside of the discharge pipe to avoid sticking to the wall during discharge and achieve smooth discharge. At the same time, the spiral shape of the rotating rack can effectively increase the speed of asphalt discharge, so that the asphalt can be smooth and unobstructed during final output. The rotating shaft can also guide the asphalt so that it can flow down along the rotating shaft and fall into the production bin to complete the addition work. The guide plate at the end of the rotating shaft can divide the downstream asphalt into multiple portions so that the asphalt can be scattered more evenly into the production bin, thereby effectively reducing the subsequent mixing time and helping to improve the production efficiency of pre-trained anodes and the final product effect.
[0021] 7. In actual production, people can control the slide to descend so that the end of the rotating shaft can be directly inserted into the material inside the production bin. The guide plate on the rotating shaft can be used to guide the asphalt and discharge it, and at the same time, the asphalt can be mixed with other materials to achieve rapid addition, thereby further improving production efficiency while taking into account both actual output effect and product quality, which is conducive to actual use. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is a schematic diagram of the front three-dimensional structure of a pitch adding device for prebaked anode production according to the present invention;
[0023] Figure 2 It is a schematic diagram of a partial structure of a pitch adding device for prebaked anode production according to the present invention from a top view;
[0024] Figure 3 It is a partial structural schematic diagram of the retention bin and the heat preservation bin of a bitumen adding device for prebaked anode production of the present invention;
[0025] Figure 4 It is a partial structural schematic diagram of a pump body of an asphalt adding device for prebaked anode production according to the present invention;
[0026] Figure 5 This is a schematic diagram of the internal structure of a heat preservation bin and a discharge pipe of an asphalt adding device for prebaked anode production according to the present invention;
[0027] Figure 6 It is a schematic diagram of the partial structure in the retention bin of a pitch adding device for prebaked anode production of the present invention;
[0028] Figure 7 This is a schematic diagram of the local structure of the micro-cone plate of an asphalt adding device for prebaked anode production according to the present invention.
[0029] 1. Production feeding device; 101. Top frame; 102. Slide; 103. Conveying pipe; 104. Servo motor; 105. Production bin; 106. Guide plate; 107. Fixed frame; 108. Insulation bin; 109. Discharge pipe; 110. Pump body; 111. Mounting frame; 112. Feed inlet; 113. Connecting frame; 114. Vibration motor; 115. Rotating shaft; 116. Extraction pipe; 117. Mounting ring; 118. Discharge pipe; 119. Retention bin; 120. Discharge outlet; 121. Rotating frame; 122. Agitator; 123. Feed outlet; 124. Guide plate; 125. Micro-cone plate; 126. Guide edge; 127. Opening; 128. Heating plate; 129. Guide roller; 130. Fixed shaft. DETAILED DESCRIPTION
[0030] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art may think of other obvious variations.
[0031] like Figure 1-Figure 7 The asphalt adding device for prebaked anode production shown in the figure comprises a production feeding device 1, the production feeding device 1 comprises a mounting frame 111, a retention bin 119 is mounted at the lower front end of the mounting frame 111, a feed port 112 is mounted at the top of the retention bin 119, a mounting ring 117 is mounted at the lower outer periphery of the retention bin 119, a pump body 110 is mounted at the top of the mounting ring 117, a plurality of extraction pipes 116 are mounted at the input end of the pump body 110, the ends of the extraction pipes 116 away from the pump body 110 all penetrate the wall of the heat preservation bin 108, a plurality of discharge pipes 118 are mounted at the output end of the pump body 110, two discharge ports 120 are arranged at the outer periphery of the discharge pipes 118, the pump body 110 is used to extract the hotter asphalt at the inner edge of the heat preservation bin 108 by means of the extraction pipes 116 and transmit it to the inside of the retention bin 119 through the discharge pipes 118, and the bottom ends of the discharge ports 120 all penetrate the wall of the retention bin 119;
[0032] Furthermore, in a specific implementation, during the process of asphalt discharge, the pump body 110 on the mounting ring 117 can use the extraction pipe 116 to extract the hotter asphalt from the inner edge of the insulation bin 108 and transfer it to the interior of the retention bin 119, so that it can be mixed with the asphalt inside the retention bin 119, so that the asphalt inside the retention bin 119 can be supplemented with heat, thereby preventing the asphalt from solidifying prematurely.
[0033] Among them, a heat preservation bin 108 is arranged at the bottom of the retention bin 119, a discharge pipe 109 is fixedly connected to the bottom of the heat preservation bin 108, and a fixing frame 107 is fixedly connected to both ends of the retention bin 119, the heat preservation bin 108 and the discharge pipe 109, a vibration motor 114 is installed in the middle of the fixing frame 107, and a connecting frame 113 is arranged on one side of the vibration motor 114, and one end of the connecting frame 113 away from the vibration motor 114 is in contact with the outer side walls of the retention bin 119, the heat preservation bin 108 and the discharge pipe 109 respectively;
[0034] Furthermore, in a specific implementation, vibration waves can be generated through the operation of the vibration motor 114, and the vibration waves can be transmitted to the walls of the retention bin 119, the insulation bin 108 and the discharge pipe 109 through the connecting frame 113 and the fixing frame 107. The operating frequencies of the vibration motors 114 are different, so that the vibration frequencies of the retention bin 119, the insulation bin 108 and the discharge pipe 109 are also different. In addition, the connecting frame 113 and the fixing frame 107 are made of different materials, so that the asphalt can receive continuous vibration waves of different frequencies during transmission, thereby effectively preventing the asphalt from excessively adhering to the inner wall of the equipment and facilitating the addition of asphalt.
[0035] Among them, the mounting frame 111 is installed on one side of the slide 102 through the traveling frame, the slide 102 is arranged on the upper part of the front and rear sides of the top frame 101, the top frame 101 is installed on the outside of the production warehouse 105, and a conveying pipe 103 is installed in the middle of the front slide 102 through the traveling frame. A feed pump is connected to the top of the conveying pipe 103, and the other end of the conveying pipe 103 faces the feed inlet 112;
[0036] Furthermore, in specific implementation, in actual use, people can first use a delivery pump to introduce liquid asphalt into the feed port 112, so that the liquid asphalt can enter the retention bin 119, and a plurality of micro-cone plates 125 are arranged inside the retention bin 119. The micro-cone plates 125 are arranged in an inverted cone shape with a high outside and a low inside. Without affecting the discharge of asphalt, the micro-cone plates 125 can effectively extend the residence time of liquid asphalt inside the retention bin 119, thereby effectively avoiding the situation where the asphalt flows too fast and the added asphalt is all accumulated in one place in the production bin 105, so that the asphalt can have an appropriate addition time, which is convenient for distribution.
[0037] Among them, a servo motor 104 is installed on the top of the mounting frame 111, and a rotating shaft 115 is fixedly connected to the bottom driving end of the servo motor 104. A uniformly distributed guide plate 106 is fixedly connected to the lower part of the outer periphery of the rotating shaft 115. A rotating frame 121 is arranged inside the discharge pipe 109. The rotating frames 121 are all fixedly connected to the middle and lower part of the outer periphery of the rotating shaft 115. The rotating frames 121 are all rotatably connected to the inside of the discharge pipe 109. A stirring rod 122 is fixedly connected to the middle and upper part of the outer periphery of the rotating shaft 115. The stirring rod 122 is arranged in the middle part of the heat preservation bin 108, and an electric heating plate 128 is arranged inside the wall of the heat preservation bin 108.
[0038] Furthermore, in a specific implementation, the electric heating plate 128 inside the heat preservation bin 108 can provide a heat preservation environment during the process of adding asphalt, thereby preventing heat loss of the asphalt and allowing the asphalt to remain in a liquid state, which is beneficial to the continuous addition and feeding of asphalt. At the same time, during the rotation of the rotating shaft 115, the external fixed stirring rod 122 will be driven to rotate synchronously. The stirring rod 122 can continuously stir the asphalt inside the heat preservation bin 108, further reducing the possibility of asphalt solidification. At the same time, the stirring rod 122 is symmetrically designed, two in a group, in a "V" shape, so that during the stirring process, a downward force can be applied to the asphalt at all times, so that the asphalt can maintain a stable output state, which is beneficial to the stable discharge of asphalt.
[0039] Among them, a plurality of micro-cone plates 125 are installed inside the retention bin 119, and a plurality of openings 127 are opened on the outer side of the middle of the micro-cone plates 125. The distribution positions of the openings 127 on each micro-cone plate 125 are different. A plurality of guide rollers 129 are arranged on the top of the micro-cone plates 125. The micro-cone plates 125 are arranged in an inverted cone shape with high middle and low sides. The guide rollers 129 are kept level with the micro-cone plates 125. The bottoms of the guide rollers 129 are in contact with the tops of the micro-cone plates 125. The outer peripheries of the guide rollers 129 are arranged with evenly distributed guide edges 126. The guide rollers 129 are rotatably connected to the outer periphery of the fixed shaft 130. The fixed shaft 130 is fixedly connected to the middle and upper part of the outer periphery of the rotating shaft 115. The rotating shaft 115 penetrates the micro-cone plates 125. The micro-cone plates 125 are rotatably connected to the rotating shaft 115. A material guide plate 124 is installed at the bottom of the retention bin 119, and a material discharge port 123 is installed at the middle of the bottom end of the material guide plate 124.
[0040] Furthermore, in a specific implementation, the operation of the servo motor 104 can drive the rotating shaft 115 to rotate. After the asphalt falls onto the micro-cone plate 125, the rotation of the rotating shaft 115 can drive the guide roller 129 and the bottom micro-cone plate 125 to rotate relative to each other by utilizing the fixed shaft 130. At the same time, the guide edge 126 provided on the guide roller 129 can guide the liquid asphalt accumulated on the micro-cone plate 125, so that the asphalt can fall onto the next layer of micro-cone plate 125 through the opening 127. The cooperation of the multiple layers of micro-cone plates 125 and the multiple groups of guide rollers 129 can greatly extend the time of the asphalt in the detention bin 119 while preventing the asphalt from solidifying. At the same time, in some processes where other additives such as petroleum coke need to be added, the asphalt can be premixed, which is beneficial to the pre-trained anode production.
[0041] Working principle:
[0042] In actual use, people can first use a delivery pump to introduce liquid asphalt into the feed port 112, so that the liquid asphalt can enter the retention bin 119. A plurality of micro-cone plates 125 are arranged inside the retention bin 119. The micro-cone plates 125 are arranged in an inverted cone shape with a high outside and a low inside. Without affecting the discharge of asphalt, the micro-cone plates 125 can effectively extend the residence time of liquid asphalt in the retention bin 119, thereby effectively avoiding the situation where the added asphalt is accumulated in one place in the production bin 105 due to excessive direct flow of asphalt, so that the asphalt can have an appropriate addition time, which is convenient for material distribution. In this process, the servo motor 104 can drive the rotating shaft 115 to rotate. After the asphalt falls on the micro-cone plates 125, the asphalt is discharged through the micro-cone plates 125. The rotation of the rotating shaft 115 can use the fixed shaft 130 to drive the guide roller 129 and the bottom micro-cone plate 125 to rotate relative to each other. At the same time, the guide edge 126 set on the guide roller 129 can guide the liquid asphalt accumulated on the micro-cone plate 125, so that the asphalt can fall onto the next layer of micro-cone plate 125 through the opening 127. The cooperation of multiple layers of micro-cone plates 125 and multiple groups of guide rollers 129 can greatly extend the time of asphalt in the detention bin 119 while avoiding asphalt solidification. At the same time, in some processes where other additives such as petroleum coke need to be added, it can be pre-mixed, which is beneficial to the pre-cultivation of anode production. The electric heating plate 128 inside the insulation bin 108 can provide an insulation environment during the process of adding asphalt to avoid asphalt heat. At the same time, during the rotation of the rotating shaft 115, the external fixed stirring rod 122 will be driven to rotate synchronously, and the asphalt inside the heat preservation bin 108 can be continuously stirred by the stirring rod 122, further reducing the possibility of asphalt solidification. At the same time, the stirring rod 122 is symmetrically designed, two by two in a group, in a "V" shape, so that during the stirring process, a downward rotation force can be applied to the asphalt at all times, so that the asphalt can maintain a stable output state, which is conducive to the stable discharge of asphalt. During the asphalt discharge process, the pump body 110 on the mounting ring 117 can use the extraction pipe 116 to extract the hotter asphalt on the inner edge of the heat preservation bin 108 and transmit it to the inside of the retention bin 119. Thereby, it can be mixed with the asphalt inside the retention bin 119, so that the asphalt inside the retention bin 119 can be supplemented with heat, thereby preventing the asphalt from solidifying early. At the same time, vibration waves can be generated by the operation of the vibration motor 114, and the vibration waves can be transmitted to the walls of the retention bin 119, the insulation bin 108 and the discharge pipe 109 through the connecting frame 113 and the fixing frame 107. The operating frequencies of the vibration motors 114 are different, so that the vibration frequencies of the retention bin 119, the insulation bin 108 and the discharge pipe 109 are also different. In addition, the materials of the connecting frame 113 and the fixing frame 107 are different, so that the asphalt can receive continuous vibration waves of different frequencies during transmission, thereby effectively preventing the asphalt from excessively adhering to the inner wall of the equipment, and facilitating the addition of asphalt.When the asphalt is discharged, the rotating frame 121 at the lower part of the outer periphery of the rotating shaft 115 can clean the inside of the discharge pipe 109 to avoid sticking to the wall during discharge and achieve smooth discharge. At the same time, the spiral shape of the rotating frame 121 can effectively increase the speed of asphalt discharge, so that the asphalt can be smoothly discharged at the final output, and the rotating shaft 115 can guide the asphalt so that the asphalt can flow down along the rotating shaft 115 and fall into the production bin 105 to complete the addition work. The guide plate 106 at the end of the rotating shaft 115 can divide the downstream asphalt into multiple portions, so that the asphalt can be more evenly distributed. Evenly scattered inside the production bin 105, which can effectively reduce the subsequent mixing time, which is beneficial to improving the production efficiency of the pre-cultured anode and the final product effect. At the same time, in actual use, people can control the slide 102 to descend, so that the end of the shaft 115 can be directly inserted into the material inside the production bin 105. The guide plate 106 on the shaft 115 can be used to guide the asphalt while mixing the asphalt with other materials to achieve rapid addition, further improving the production efficiency while taking into account the actual output effect and product quality, which is beneficial to actual use.
[0043] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.
Claims
1. A pitch adding device for prebaked anode production, comprising a production feeding device (1), characterized in that: The production feeding device (1) comprises a mounting frame (111), a retention bin (119) is mounted at the lower front end of the mounting frame (111), a feeding port (112) is mounted at the top of the retention bin (119), a mounting ring (117) is mounted at the lower outer periphery of the retention bin (119), a pump body (110) is mounted at the top of the mounting ring (117), a plurality of extraction pipes (116) are mounted at the input end of the pump body (110), the ends of the extraction pipes (116) away from the pump body (110) all penetrate the wall of the heat preservation bin (108), a plurality of discharge pipes (118) are mounted at the output end of the pump body (110), two discharge ports (120) are arranged at the outer periphery of the discharge pipes (118), and the pump body (110) is used to discharge the contents of the heat preservation bin (108) by means of the extraction pipes (116). The hotter asphalt at the edge is extracted and transmitted to the interior of the retention bin (119) through the discharge pipe (118). The bottom of the discharge port (120) penetrates the wall of the retention bin (119). A heat preservation bin (108) is provided at the bottom of the retention bin (119). A discharge pipe (109) is fixedly connected to the bottom of the heat preservation bin (108). A fixing frame (107) is fixedly connected to both ends of the retention bin (119), the heat preservation bin (108) and the discharge pipe (109). A vibration motor (114) is installed in the middle of the fixing frame (107). A connecting frame (113) is provided on one side of the vibration motor (114). The end of the connecting frame (113) away from the vibration motor (114) is in contact with the outer walls of the retention bin (119), the heat preservation bin (108) and the discharge pipe (109), respectively.
2. The asphalt adding device for prebaked anode production according to claim 1, characterized in that: The mounting frame (111) is mounted on one side of the slide (102) via a walking frame, the slide (102) is arranged on the upper front and rear sides of the top frame (101), and the top frame (101) is mounted on the outside of the production warehouse (105).
3. The asphalt adding device for prebaked anode production according to claim 1, characterized in that: A servo motor (104) is mounted on the top of the mounting frame (111), a rotating shaft (115) is fixedly connected to the bottom driving end of the servo motor (104), and evenly distributed guide plates (106) are fixedly connected to the lower periphery of the rotating shaft (115).
4. The asphalt adding device for prebaked anode production according to claim 3, characterized in that: A rotating frame (121) is provided inside the discharge pipe (109), and the rotating frame (121) is fixedly connected to the middle and lower part of the outer circumference of the rotating shaft (115). The rotating frame (121) is rotatably connected to the inside of the discharge pipe (109).
5. The asphalt adding device for prebaked anode production according to claim 4, characterized in that: A stirring rod (122) is fixedly connected to the middle upper portion of the outer circumference of the rotating shaft (115), and the stirring rod (122) is arranged in the middle portion of the heat preservation bin (108). An electric heating plate (128) is arranged inside the wall of the heat preservation bin (108).
6. The asphalt adding device for prebaked anode production according to claim 1, characterized in that: A plurality of micro-cone plates (125) are installed inside the retention bin (119), a plurality of openings (127) are provided on the outer sides of the middle parts of the micro-cone plates (125), the distribution positions of the openings (127) on each micro-cone plate (125) are different, and a plurality of guide rollers (129) are provided on the tops of the micro-cone plates (125).
7. The asphalt adding device for prebaked anode production according to claim 6, characterized in that: A material guide plate (124) is installed at the bottom of the retention bin (119), and a material discharge port (123) is installed at the middle of the bottom end of the material guide plate (124).
8. The asphalt adding device for prebaked anode production according to claim 7, characterized in that: The guide rollers (129) are provided with evenly distributed guide edges (126) on their peripheries, the guide rollers (129) are rotatably connected to the periphery of the fixed shafts (130), the fixed shafts (130) are fixedly connected to the middle and upper part of the periphery of the rotating shafts (115), the rotating shafts (115) penetrate the micro-cone plates (125), and the micro-cone plates (125) are rotatably connected to the rotating shafts (115).
9. The asphalt adding device for prebaked anode production according to claim 6, characterized in that: The micro-cone plates (125) are all arranged in an inverted cone shape with high sides and low sides, the guide rollers (129) are all kept horizontal with the micro-cone plates (125), and the bottoms of the guide rollers (129) are in contact with the tops of the micro-cone plates (125).
10. The asphalt adding device for prebaked anode production according to claim 2, characterized in that: A conveying pipe (103) is installed in the middle of the front slide (102) through a traveling frame, a feed pump is connected to the top of the conveying pipe (103), and the other end of the conveying pipe (103) faces the feed inlet (112).