A super-high multi-tower connected structure system and construction method thereof

By using cantilevered horns and dampers in the ultra-high multi-tower joint structure, combined with damping energy-consuming parts and automatic positioning locking mechanism, the problems of lateral movement of the core cylinder and limited construction height are solved, achieving high efficiency and safety The construction process has improved the technical level of construction.

CN118727939BActive Publication Date: 2024-11-05SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411231685.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-11-05
Estimated Expiration
2044-09-04

AI Technical Summary

Technical Problem

In the construction of ultra-high multi-tower joint structures, the core cylinder is prone to lateral displacement and the independent construction height is limited, resulting in low construction efficiency and inconvenience.

Method used

The cantilevered corbels and dampers are arranged between multiple core cylinders, and the positioning and buffering of the truss layer is achieved through damping energy-consuming parts. Combined with the automatic positioning locking mechanism and mechanized construction methods, the multi-layer steel structure is constructed synchronously and quickly.

Benefits of technology

It significantly improves construction efficiency, enhances structural stability and safety, reduces construction errors, improves installation accuracy, and reduces costs, and promotes technological progress in the field of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727939B_ABST
    Figure CN118727939B_ABST
Patent Text Reader

Abstract

The present invention belongs to the field of building construction, and relates to an ultra-high multi-tower connected structure system and a construction method thereof, wherein a plurality of truss layers are arranged between a plurality of core tubes, a cantilevered corbel is arranged on one side of the plurality of core tubes close to each other, a plurality of dampers are arranged on the top of the cantilevered corbel, the tops of the plurality of dampers are fixedly connected to the bottoms of the corresponding truss layers, a plurality of damping energy absorbing parts are installed on one side of the core tube, and the plurality of damping energy absorbing parts are used to position the truss layer; the truss layer comprises a plurality of groups of I-shaped steels, each group of I-shaped steels has two I-shaped steels and are symmetrically arranged, a same support plate is fixedly connected between the two I-shaped steels, and a plurality of first support frames and a plurality of second support frames are respectively arranged between the plurality of support plates; the problem that the core tube is prone to lateral displacement and the independent construction height of the core tube is limited in the current construction process of the ultra-high multi-tower connected structure is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of building construction and relates to an ultra-high multi-tower connected structural system and a construction method thereof. Background Art

[0002] The super-high multi-tower connected structure is generally equipped with multiple steel truss layers along the height, and each truss layer is equipped with multiple steel structures above or below. The truss layer supports the upper multi-layer steel structure or hangs the lower multi-layer steel structure. The traditional construction process and method are as follows:

[0003] 1) First, gradually construct each core tube structure and install the bottom truss layer;

[0004] 2) Set up a temporary support structure on the bottom truss layer, then install the multi-layer steel structure and the second truss layer, and gradually unload the temporary support structure;

[0005] 3) Install the truss layer and the upper steel structure in sequence, set up the temporary support structure, install the multi-layer structure, install the truss layer, and then unload;

[0006] 4) From bottom to top, use temporary support structures to gradually install truss layers and multi-layer steel structures, unload, etc.

[0007] However, this construction process still has the following defects:

[0008] 1. The construction of multi-layer steel structures at the truss level is cumbersome and time-consuming, and the core tube structure cannot be constructed quickly and independently due to the lack of lateral constraints at the truss level, resulting in low overall construction efficiency and limiting the independent construction height of multiple core tubes;

[0009] 2. During construction and hoisting, the truss layers between the core tubes are prone to mutual squeezing, resulting in lateral displacement of the core tube, which is inconvenient to use. Summary of the invention

[0010] In view of this, the present invention provides an ultra-high multi-tower connected structure system and a construction method thereof in order to solve the problems that the core tube is prone to lateral displacement and the independent construction height of the core tube is limited during the construction of the ultra-high multi-tower connected structure.

[0011] In order to achieve the above object, the present invention provides the following technical solutions:

[0012] An ultra-high multi-tower connected structural system, comprising:

[0013] Multiple core tubes, multiple truss layers are arranged between the multiple core tubes, cantilevered corbels are arranged on the sides of the multiple core tubes close to each other, multiple dampers are arranged on the tops of the cantilevered corbels, the tops of the multiple dampers are fixedly connected to the bottoms of the corresponding truss layers, and multiple damping energy absorbing parts are installed on one side of the core tube, and the multiple damping energy absorbing parts are used to position the truss layers;

[0014] The truss layer includes multiple groups of I-shaped steels, each group of I-shaped steels has two in number and are symmetrically arranged, a same support plate is fixedly connected between the two I-shaped steels, and multiple first support frames and multiple second support frames are respectively arranged between the multiple support plates.

[0015] Furthermore, the damping energy-absorbing component includes an installation main board, a plurality of embedded bolts are embedded on one side of the core tube, and four corners of the installation main board are provided with clearance grooves, and an inner wall of one side of the clearance groove is provided with an installation hole, which is used in conjunction with the embedded bolts, and a fixing nut is provided on the outer wall thread sleeve of the embedded bolts.

[0016] Furthermore, the damping energy-absorbing component also includes an auxiliary mounting plate, which is arranged parallel to the main mounting plate. One side of the main mounting plate is fixedly connected with two symmetrically arranged positioning rods, and one side of the auxiliary mounting plate is provided with two symmetrically arranged positioning grooves, and the positioning rods are slidably connected inside the positioning grooves.

[0017] Furthermore, a rectangular box is slidably connected to one side of the auxiliary installation plate, and a side protrusion is slidably connected to the inner wall of one side of the rectangular box, two symmetrically arranged second springs are fixedly connected between one side of the side protrusion and the inner wall of one side of the rectangular box, a rectangular groove is provided on the top of the side protrusion, and the same sliding bar is slidably connected between the inner walls on both sides of the rectangular groove, and the same compression spring is fixedly connected between the bottom of the sliding bar and the bottom inner wall of the rectangular groove, a strip hole is provided on the top of the rectangular box, and the strip hole is used in conjunction with the sliding bar, and a fixing bar is fixedly connected to the top inner wall of the auxiliary installation plate, and the fixing bar is used in conjunction with the strip hole.

[0018] Furthermore, a first rack is fixedly connected to one side of the rectangular box, a gear is rotatably connected to the bottom inner wall of the auxiliary mounting plate, the first rack is meshed with the gear, a front protrusion is slidably connected to the top inner wall of the auxiliary mounting plate, a second rack is fixedly connected to one side of the front protrusion, the second rack is meshed with the gear, and the same group of buffer components for buffering are arranged between the front protrusion and the mounting main board.

[0019] Furthermore, the buffer assembly includes a plurality of first springs fixedly connected between the front protrusion and the inner wall of one side of the mounting auxiliary plate, the top of the mounting auxiliary plate is fixedly connected with a second fixed block, the top of the mounting main board is fixedly connected with a first fixed block, one side of the first fixed block is rotatably connected with an adjustment screw, and the adjustment screw thread passes through the second fixed block.

[0020] Furthermore, the buffer assembly includes a second T-slot opened on one side of the front protrusion, a first T-slot opened on one side of the main board installation, a connecting hole opened on one side of the auxiliary board installation, a first T-block clamped inside the second T-slot, a second T-block clamped inside the first T-slot, a round hole opened inside the second T-block, a sleeve fixedly connected to one side of the second T-block, an inner rod slidingly penetrated inside the sleeve, one end of the inner rod fixedly connected to one side of the first T-block, two symmetrically arranged third springs fixedly connected between the first T-block and the second T-block, and an operating block fixedly connected to one side of the sleeve.

[0021] A construction method for a super-high multi-tower connected structural system specifically comprises the following steps:

[0022] S1. Multiple core tubes are constructed simultaneously and quickly, followed by the construction of multiple truss layers at appropriate intervals until the entire structure is capped, creating multiple working surfaces based on the corresponding truss layers;

[0023] S11, after the truss layer is hoisted to a suitable height, one side of the truss layer contacts one side of the front protrusion, thereby squeezing the first spring, the front protrusion drives the second rack to move laterally, the second rack drives the gear to rotate, the gear drives the first rack to move laterally, and the first rack drives the rectangular box to move laterally;

[0024] S12. When the I-shaped steels on both sides of the truss layer move to a suitable height, the side protrusions move laterally under the elastic force of the second spring and are inserted into the inside of the I-shaped steel to prevent the I-shaped steel from continuing to rise, thereby positioning the truss layer. The side protrusions on the other side are also inserted into the other side of the I-shaped steel to brake the truss layer.

[0025] S13. Workers install cantilevered corbels at appropriate locations and install dampers on the top of the cantilevered corbels. The top of the damper is installed at the bottom of the truss layer to buffer the longitudinal displacement of the truss layer.

[0026] S2. Multi-layer steel structures are constructed simultaneously above each truss layer, so that the multi-layer steel structures that fill the gaps inside the truss layer can also be constructed quickly.

[0027] The ultra-high multi-tower connected structural system disclosed in the present invention has the following advantages:

[0028] 1. Improve construction efficiency: By quickly and synchronously constructing multiple core tubes and truss layers, the construction period is significantly shortened and the overall construction speed is improved. Multi-layer steel structures are simultaneously constructed above the truss layer, supplemented by temporary support and unloading strategies, which enables rapid filling of multi-layer steel structures and further improves construction efficiency. The overall lifting process is used to construct the middle truss layer, which reduces the number of hoisting times and installation time, and improves construction efficiency.

[0029] 2. Enhanced structural stability and safety: The automatic positioning and locking mechanism after the truss layer is hoisted (such as the engagement of the front protrusions, side protrusions and I-shaped steel) ensures the accuracy and stability of the truss layer installation and prevents safety hazards caused by inadequate hoisting. The installation of cantilevered corbels and dampers effectively buffers the possible longitudinal displacement of the truss layer and enhances the seismic resistance and safety of the structure.

[0030] 3. Improve construction flexibility and maintainability: Two convenient disassembly methods are designed for the removal of multiple damping energy-absorbing parts 4. The auxiliary mounting plate can be reset and disassembled by adjusting the screw rod, or the auxiliary mounting plate and the main mounting plate can be quickly separated by pulling the operating block, which improves the flexibility of the construction process. Damping energy-absorbing parts and other components can be reused, which reduces the construction cost and facilitates subsequent maintenance and replacement.

[0031] 4. Reduce construction errors and improve accuracy: The mechanized positioning and locking mechanism reduces the errors caused by human operation and improves the accuracy and reliability of installation. The design of precision components such as sliding bars and fixing bars ensures precise control of the truss layer during lifting and positioning.

[0032] 5. Promote technological innovation and industrial upgrading: It integrates a number of innovative technologies, such as overall lifting technology, automatic positioning and locking mechanism, etc., which has promoted technological progress and industrial upgrading in the field of construction. The efficient and safe construction methods provide important technical reference and reference for future super-high-rise buildings, complex structural projects, etc. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be described in detail below in conjunction with the accompanying drawings, wherein:

[0034] Figure 1 A schematic diagram of an ultra-high multi-tower connected structural system and a construction method thereof proposed by the present invention at an early stage of construction;

[0035] Figure 2 A schematic diagram of a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention at a later stage of construction;

[0036] Figure 3 A three-dimensional structural schematic diagram of a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0037] Figure 4 A schematic diagram of the three-dimensional structure of the truss layer in a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0038] Figure 5 A three-dimensional structural schematic diagram of a core tube and a damper in a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0039] Figure 6 A three-dimensional structural schematic diagram of installing a main plate and installing an auxiliary plate in a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0040] Figure 7 It is a schematic diagram of the exploded structure of installing the main plate and installing the auxiliary plate in a super-high multi-tower connected structure system and a construction method thereof proposed by the present invention;

[0041] Figure 8 A three-dimensional structural schematic diagram of installing auxiliary plates in a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0042] Fig. 9 A schematic diagram of the three-dimensional structure of a rectangular box in a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0043] Fig.10 It is a schematic diagram of the exploded structure of a rectangular box and side protrusions in a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0044] Fig.11 A three-dimensional structural schematic diagram of a first T-shaped block and a second T-shaped block in an ultra-high multi-tower connected structural system and a construction method thereof proposed by the present invention;

[0045] Fig.12 The diagram is a schematic diagram of the exploded structure of the first T-block and the second T-block in a super-high multi-tower connected structural system and a construction method thereof proposed by the present invention.

[0046] In the figure: 1, core tube; 2, truss layer; 201, support plate; 202, I-shaped steel; 203, first support frame; 204, second support frame; 3, cantilevered corbel; 4, damping energy dissipation part; 401, installation main board; 402, first fixing block; 403, adjustment screw; 404, installation auxiliary plate; 405, side convex block; 406, front convex block; 407, first spring; 408, embedded bolt; 409, fixing nut; 410, clearance groove; 411, installation hole; 412, positioning rod; 413, positioning groove; 41 4. Second fixed block; 415. Second spring; 416. Rectangular box; 417. First rack; 418. Gear; 419. Second rack; 420. Fixed bar; 421. Compression spring; 422. Sliding bar; 423. Rectangular groove; 424. Bar hole; 425. First T-block; 426. Sleeve; 427. Second T-block; 428. Third spring; 429. Connecting hole; 430. First T-slot; 431. Round hole; 432. Operating block; 433. Inner rod; 434. Second T-slot; 5. Damper. DETAILED DESCRIPTION

[0047] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the illustrations provided in the following embodiments only illustrate the basic concept of the present invention in a schematic manner, and the following embodiments and features in the embodiments can be combined with each other without conflict.

[0048] Embodiment 1

[0049] Reference Figure 1-10 A super-high multi-tower connected structural system, wherein multiple truss layers 2 are arranged between multiple core tubes 1, and a cantilevered corbel 3 is arranged on the side where the multiple core tubes 1 are close to each other. A plurality of dampers 5 are arranged on the top of the cantilevered corbel 3, and the tops of the plurality of dampers 5 are fixedly connected to the bottom of the corresponding truss layer 2. A plurality of damping energy absorbing parts 4 are installed on one side of the core tube 1, and the plurality of damping energy absorbing parts 4 are used to position the truss layer 2. At this time, workers can install the cantilevered corbel 3 at a suitable position, and install the damper 5 on the top of the cantilevered corbel 3. The top of the damper 5 is installed at the bottom of the truss layer 2 to buffer the longitudinal displacement generated by the truss layer 2. At this time, the plurality of damping energy absorbing parts 4 can be removed and moved to the installation position of the next truss layer 2 for repeated use.

[0050] The damping energy absorbing component 4 includes a mounting main board 401, a plurality of embedded bolts 408 are embedded on one side of the core tube 1, and four corners of the mounting main board 401 are provided with clearance grooves 410, and an inner wall of one side of the clearance groove 410 is provided with a mounting hole 411, and the mounting hole 411 is used in conjunction with the embedded bolts 408, and a fixing nut 409 is threadedly sleeved on the outer wall of the embedded bolt 408. The damping energy absorbing component 4 also includes a mounting auxiliary plate 404, and the mounting auxiliary plate 404 is arranged parallel to the mounting main board 401, and one side of the mounting main board 401 is fixedly connected with two symmetrically arranged positioning rods 412, and one side of the mounting auxiliary plate 404 is provided with two symmetrically arranged positioning grooves 413, and the positioning rod 412 is slidably connected to the inside of the positioning groove 413;

[0051] The truss layer 2 includes multiple groups of I-shaped steels 202, each group of I-shaped steels 202 has two and are symmetrically arranged, the same support plate 201 is fixedly connected between the two I-shaped steels 202, multiple first support frames 203 and multiple second support frames 204 are respectively arranged between the multiple support plates 201, because the fixing strip 420 is located inside the strip hole 424, the side protrusion 405 cannot fully rebound at this time, and one side of the side protrusion 405 always conflicts with one side of the fixing strip 420, thereby preventing the truss layer 2 from conflicting with the side protrusion 405 when it is not hoisted in place, and as the rectangular box 416 is gradually moved out, the fixing strip 420 is separated from the inside of the strip hole 424, and the side protrusion 405 moves to one side of the I-shaped steel 202;

[0052] A first rack 417 is fixedly connected to one side of the rectangular box 416, and a gear 418 is rotatably connected to the bottom inner wall of the auxiliary mounting plate 404. The first rack 417 and the gear 418 are meshed. A front protrusion 406 is slidably connected to the top inner wall of the auxiliary mounting plate 404. A second rack 419 is fixedly connected to one side of the front protrusion 406. The second rack 419 is meshed with the gear 418. After the truss layer 2 is hoisted to a suitable height, one side of the truss layer 2 is in contact with the front The first spring 407 is pressed against one side of the protrusion 406, and the front protrusion 406 drives the second rack 419 to move horizontally, the second rack 419 drives the gear 418 to rotate, the gear 418 drives the first rack 417 to move horizontally, and the first rack 417 drives the rectangular box 416 to move horizontally. When the I-shaped steel 202 moves to a suitable height, the side protrusion 405 moves horizontally under the elastic force of the second spring 415 and is stuck in the I-shaped steel 202. The inside of the I-shaped steel 202 is prevented from continuing to rise and the truss layer 2 is positioned. At this time, the sliding bar 422 moves to the bottom of the strip hole 424, and the sliding bar 422 moves vertically upward under the elastic force of the compression spring 421 and is stuck in the inside of the strip hole 424. At this time, the side protrusion 405 is in a braking state, and the side protrusion 405 on the other side is also stuck in the other side of the I-shaped steel 202. At this time, the truss layer 2 can be braked, and the same group of buffer components for buffering are provided between the front protrusion 406 and the mounting main board 401. The buffer component includes a plurality of first springs 407 fixedly connected between the front protrusion 406 and the inner wall of one side of the mounting auxiliary plate 404, the top of the mounting auxiliary plate 404 is fixedly connected to the second fixing block 414, the top of the mounting main board 401 is fixedly connected to the first fixing block 402, and one side of the first fixing block 402 is rotatably connected to an adjusting screw 403, and the adjusting screw 403 threadably passes through the second fixing block 414.

[0053] When it is necessary to remove the mounting auxiliary plate 404, by rotating the adjusting screw 403, the adjusting screw 403 drives the mounting auxiliary plate 404 as a whole to move closer to the mounting main board 401, thereby leaving a rebound space for the front protrusion 406. At this time, the front protrusion 406 rebounds under the elastic force of the first spring 407, thereby driving the rectangular box 416 to retract. During the retraction of the rectangular box 416, since the top of one side of the sliding bar 422 is inclined, the fixing bar 420 can push the sliding bar 422 to the inside of the rectangular groove 423. At this time, the side protrusion 405 can be moved horizontally to complete the resetting of the side protrusion 405. After removing multiple fixing nuts 409, the mounting main board 401 and the mounting auxiliary plate 404 are taken out as a whole.

[0054] Embodiment 2

[0055] Reference Figure 1-12 The difference between the second embodiment and the first embodiment is that another buffer assembly of the same group for buffering is arranged between the front protrusion 406 and the mounting main board 401, and the buffer assembly includes a second T-slot 434 opened on one side of the front protrusion 406, a first T-slot 430 is opened on one side of the mounting main board 401, a connecting hole 429 is opened on one side of the mounting auxiliary plate 404, a first T-block 425 is clamped inside the second T-slot 434, a second T-block 427 is clamped inside the first T-slot 430, a round hole 431 is opened inside the second T-block 427, a sleeve 426 is fixedly connected to one side of the second T-block 427, an inner rod 433 is slidably penetrated inside the sleeve 426, one end of the inner rod 433 is fixedly connected to one side of the first T-block 425, two symmetrically arranged third springs 428 are fixedly connected between the first T-block 425 and the second T-block 427, and an operating block 432 is fixedly connected to one side of the sleeve 426.

[0056] When it is necessary to remove the mounting auxiliary plate 404, by pulling the operating block 432, the sleeve 426 drives the inner rod 433 to move horizontally, and then the entire first T-block 425 and the second T-block 427 are directly pulled out from the second T-slot 434 and the first T-slot 430. At this time, the mounting auxiliary plate 404 can be moved closer to the mounting main board 401 as a whole. The positioning of the positioning rod 412 and the positioning slot 413 is used to ensure the stability of the movement of the mounting auxiliary plate 404. After removing multiple fixing nuts 409, the mounting main board 401 and the mounting auxiliary plate 404 are taken out as a whole.

[0057] like Figure 1-2 A construction method of a super-high multi-tower connected structural system is shown, which specifically includes the following steps:

[0058] S1. Multiple core tubes 1 are constructed synchronously and quickly, followed by the rapid construction of multiple truss layers 2 at appropriate intervals until the entire structure is capped, creating multiple working surfaces based on the corresponding truss layers 2, taking 4 truss layers 2 as an example;

[0059] After the truss layer 2 is hoisted to a suitable height, one side of the truss layer 2 contacts one side of the front protrusion 406, thereby squeezing the first spring 407, and the front protrusion 406 drives the second rack 419 to move laterally, the second rack 419 drives the gear 418 to rotate, the gear 418 drives the first rack 417 to move laterally, and the first rack 417 drives the rectangular box 416 to move laterally;

[0060] Since the fixing strip 420 is located inside the strip hole 424, the side protrusion 405 cannot fully rebound at this time, and one side of the side protrusion 405 always conflicts with one side of the fixing strip 420, thereby preventing the truss layer 2 from conflicting with the side protrusion 405 when the truss layer 2 is not hoisted in place. As the rectangular box 416 is gradually moved out, the fixing strip 420 is separated from the inside of the strip hole 424, and the side protrusion 405 moves to one side of the I-shaped steel 202;

[0061] When the I-shaped steel 202 moves to a suitable height, the side protrusion 405 moves laterally under the elastic force of the second spring 415 and is inserted into the inside of the I-shaped steel 202 to prevent the I-shaped steel 202 from continuing to rise and position the truss layer 2. At this time, the sliding bar 422 moves to the bottom of the strip hole 424. The sliding bar 422 moves vertically upward under the elastic force of the compression spring 421 and is inserted into the inside of the strip hole 424. At this time, the side protrusion 405 is in a braking state, and the side protrusion 405 on the other side is also inserted into the other side of the I-shaped steel 202. At this time, the truss layer 2 can be braked;

[0062] At this time, the worker can install the cantilevered corbel 3 at a suitable position, and install the damper 5 on the top of the cantilevered corbel 3. The top of the damper 5 is installed at the bottom of the truss layer 2 to buffer the longitudinal displacement of the truss layer 2. After the truss layer 2 is installed, the multiple damping energy dissipating parts 4 can be removed and moved to the position where the next truss layer 2 is installed for repeated use.

[0063] The damping energy dissipation member 4 can be dismantled by adjusting the screw rod to reset and dismantle the auxiliary mounting plate 404 , or by pulling the operating block to quickly separate the auxiliary mounting plate 404 from the main mounting plate 401 .

[0064] S2. Multi-layer steel structures can be constructed simultaneously on top of each truss layer 2 (temporary support needs to be added locally and then unloaded), and the multi-layer steel structures that fill the gaps inside the truss layer 2 can also be constructed quickly. Compared with traditional construction methods, the construction efficiency is high;

[0065] S3. When constructing a multi-layer truss layer 2, the bottom and the 4th to last truss layer 2 are constructed first. The middle 2-3 truss layers 2 can be hoisted as a whole by setting a lifting point on the 4th truss layer 2 to achieve rapid construction of the truss layer 2.

[0066] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution, which should be included in the scope of the claims of the present invention.

Claims

1. An ultra-high multi-tower connected structure system, It is characterized in that include: A plurality of core tubes (1), a plurality of truss layers (2) are arranged between the plurality of core tubes (1), a cantilevered corbel (3) is arranged on the side of the plurality of core tubes (1) close to each other, a plurality of dampers (5) are arranged on the top of the cantilevered corbel (3), the tops of the plurality of dampers (5) are fixedly connected to the bottom of the corresponding truss layer (2), a plurality of damping energy absorbing parts (4) are installed on one side of the core tube (1), and the plurality of damping energy absorbing parts (4) are used to position the truss layer (2); The truss layer (2) comprises a plurality of groups of I-shaped steels (202), each group of the I-shaped steels (202) comprises two I-shaped steels (202) and are symmetrically arranged, a same support plate (201) is fixedly connected between the two I-shaped steels (202), and a plurality of first support frames (203) and a plurality of second support frames (204) are respectively arranged between the plurality of support plates (201); The damping energy dissipation component (4) comprises a mounting main plate (401) and a mounting auxiliary plate (404); a plurality of embedded bolts (408) are embedded on one side of the core tube (1); four corners of the mounting main plate (401) are provided with clearance grooves (410); an inner wall of one side of the clearance groove (410) is provided with a mounting hole (411); the mounting hole (411) is used in conjunction with the embedded bolts (408); and a fixing nut (409) is threadedly sleeved on the outer wall of the embedded bolts (408); The auxiliary mounting plate (404) is arranged in parallel with the main mounting plate (401); one side of the main mounting plate (401) is fixedly connected with two symmetrically arranged positioning rods (412); one side of the auxiliary mounting plate (404) is provided with two symmetrically arranged positioning grooves (413); the positioning rods (412) are slidably connected inside the positioning grooves (413); one side of the auxiliary mounting plate (404) is slidably connected with a rectangular box (416); one side inner wall of the rectangular box (416) is slidably connected with a side protrusion (405); two symmetrically arranged second springs (415) are fixedly connected between one side of the side protrusion (405) and one side inner wall of the rectangular box (416); the rectangular box (416) is provided with a plurality of second springs (415) disposed on the inner wall of the rectangular box (416). A first rack (417) is fixedly connected to one side, a gear (418) is rotatably connected to the bottom inner wall of the auxiliary mounting plate (404), the first rack (417) and the gear (418) are meshed, a front protrusion (406) is slidably connected to the top inner wall of the auxiliary mounting plate (404), a second rack (419) is fixedly connected to one side of the front protrusion (406), the second rack (419) is meshed with the gear (418); after the I-shaped steel (202) on both sides of the truss layer (2) moves to a specified height, the side protrusion (405) moves laterally under the elastic force of the second spring (415) and is stuck in the interior of the I-shaped steel (202), so as to realize the positioning of the damping energy-absorbing component (4) on the truss layer (2); The same group of buffer components for buffering is arranged between the front protrusion (406) and the mounting mainboard (401).

2. The ultra-high multi-tower connected structure system according to claim 1, It is characterized in that A rectangular groove (423) is provided at the top of the side protrusion (405); a sliding bar (422) is slidably connected between the inner walls on both sides of the rectangular groove (423); a compression spring (421) is fixedly connected between the bottom of the sliding bar (422) and the bottom inner wall of the rectangular groove (423); a strip hole (424) is provided at the top of the rectangular box (416); the strip hole (424) is used in conjunction with the sliding bar (422); a fixing bar (420) is fixedly connected to the inner wall at the top of the mounting auxiliary plate (404); the fixing bar (420) is used in conjunction with the strip hole (424).

3. The ultra-high multi-tower connected structure system according to claim 2, It is characterized in that The buffer assembly comprises a plurality of first springs (407) fixedly connected between a front protrusion (406) and an inner wall of one side of an auxiliary mounting plate (404); a second fixing block (414) is fixedly connected to the top of the auxiliary mounting plate (404); a first fixing block (402) is fixedly connected to the top of the main mounting plate (401); an adjusting screw (403) is rotatably connected to one side of the first fixing block (402); and a thread of the adjusting screw (403) passes through the second fixing block (414).

4. The ultra-high multi-tower connected structure system according to claim 2, It is characterized in that The buffer assembly comprises a second T-slot (434) provided on one side of the front protrusion (406); a first T-slot (430) is provided on one side of the mounting main plate (401); a connecting hole (429) is provided on one side of the mounting auxiliary plate (404); a first T-block (425) is clamped inside the second T-slot (434); a second T-block (427) is clamped inside the first T-slot (430); a round hole (431) is provided inside the second T-block (427); a sleeve (426) is fixedly connected to one side of the second T-block (427); an inner rod (433) is slidably penetrated inside the sleeve (426); one end of the inner rod (433) is fixedly connected to one side of the first T-block (425); two symmetrically arranged third springs (428) are fixedly connected between the first T-block (425) and the second T-block (427); and an operating block (432) is fixedly connected to one side of the sleeve (426).

5. A construction method for a super-high multi-tower connected structural system according to claim 3 or 4, It is characterized in that The specific steps include: S1. Multiple core tubes (1) are constructed simultaneously and quickly, followed by the construction of multiple truss layers (2) at appropriate intervals until the entire structure is capped, creating multiple working surfaces based on the corresponding truss layers (2); S11, after the truss layer (2) is hoisted to a suitable height, one side of the truss layer (2) contacts one side of the front protrusion (406), the front protrusion (406) drives the second rack (419) to move laterally, the second rack (419) drives the gear (418) to rotate, the gear (418) drives the first rack (417) to move laterally, and the first rack (417) drives the rectangular box (416) to move laterally; S12, when the I-shaped steels (202) on both sides of the truss layer (2) move to a suitable height, the side protrusions (405) move laterally under the elastic force of the second spring (415) and snap into the interior of the I-shaped steel (202) to prevent the I-shaped steel (202) from continuing to rise, thereby positioning the truss layer (2), and the side protrusions (405) on the other side are also snapped into the other side of the I-shaped steel (202) to brake the truss layer (2); S13, workers install the cantilevered corbel (3) at a suitable position and install a damper (5) on the top of the cantilevered corbel (3), wherein the top of the damper (5) is installed at the bottom of the truss layer (2) to buffer the longitudinal displacement of the truss layer (2); S2. Multi-layer steel structures are constructed simultaneously above each truss layer (2), so that the multi-layer steel structures that fill the gaps inside the truss layer (2) can also be quickly constructed.

Citation Information

Patent Citations

  • Fabricated truss concrete beam capable of being quickly replaced after earthquake

    CN112942681A

  • Energy-consuming type connected structure, connected building system and construction method

    CN113250315A

  • Prefabricated beam column building steel structure with anti-seismic function and construction method thereof

    CN114150907A

  • Upper steel truss and lower steel frame combined structure and construction method thereof

    CN117364914A

  • Aseismic control structure of connected buildings

    JP2008075318A