Seam-drawing structure formwork and seam-drawing construction method
By designing the seamed structural formwork with reserved steel bars and slots, the problem of insufficient connection tightness and load-bearing effect of the existing seamed panels in the construction of building exterior walls was solved, achieving efficient connection strength and construction efficiency, and avoiding Increased cracking and subsequent repair costs.
Patent Information
- Application Number
- CN202411032591.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the construction of building exterior walls, the hollow cavity structure of the existing seamed panels results in poor concrete pouring and insufficient wall strength. Moreover, the steel bars at the connecting parts are easy to detach, making it impossible to ensure the tightness of the connection and the load-bearing effect.
Design a seam structural formwork, including seam panels spaced along the Made of PVC or wooden materials, the card slot can be optionally curved and equipped with an anti-slip structure to achieve high connection tightness.
It improves the connection strength of the connecting parts, avoids cracking, ensures the load-bearing effect of the wall, improves construction efficiency and overall connection strength, and reduces later repair costs.
Smart Images

Figure CN118728059A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a seam-drawing structure template and a seam-drawing construction method. Background Art
[0002] At present, during the construction of building exterior walls, more and more projects are taking advantage of the advantages of aluminum formwork construction to deepen the original secondary masonry brick walls into cast-in-place concrete filling walls. This construction method realizes the one-time casting of the entire exterior wall.
[0003] However, in the actual construction process, the seismic resistance of the joints is poor, and cracks are prone to occur, which affects the overall strength of the building and easily increases the cost of later repairs. Most of the seam-drawn panels disclosed in the prior art are hollow cavity structures, which have the problems of poor concrete pouring and insufficient wall strength. At the same time, the steel bars at the joints are easily separated from the concrete, and the connection tightness of the joints cannot be ensured, nor can the load-bearing effect of the wall be guaranteed. Summary of the invention
[0004] The invention aims to provide a seam-drawing structure template and a seam-drawing construction method, which can ensure the connection strength of the joint and have a higher connection tightness.
[0005] To achieve this object, the present invention adopts the following technical solutions:
[0006] On the one hand, a seam structure template is provided, which is used to connect a first wall and a second wall, wherein a plurality of reserved steel bars are protruded from one side of the first wall and the second wall facing each other;
[0007] The seam structure template comprises two seam plates spaced apart along the X direction, a channel for pouring concrete is arranged between the two seam plates, a plurality of slots are arranged on one side of the two seam plates away from each other, the plurality of slots are spaced apart along the Y direction, and each of the slots extends along the Z direction;
[0008] The seam plate is arranged between the first wall and the second wall, and the plurality of reserved steel bars are clamped in the plurality of clamping grooves in a one-to-one correspondence;
[0009] The X direction, the Y direction and the Z direction are perpendicular to each other.
[0010] As an optional solution for the seam structure template, the slot is arc-shaped.
[0011] As an optional solution for the seam-stretching structure template, an anti-slip structure is provided in the slot.
[0012] As an optional solution for the seam-stretching structure template, the seam-stretching plate is made of PVC or wood.
[0013] As an optional solution for the seam structure template, the two seam plates are both of an integrally formed design.
[0014] On the other hand, a method for seam construction is provided, which adopts any of the seam structure templates described above, comprising the following steps:
[0015] S1: tying the main structural steel bars of the first wall and the second wall;
[0016] S2: placing the seam plate between the first wall and the second wall, and clamping the plurality of reserved steel bars in the plurality of clamping grooves in a one-to-one correspondence;
[0017] S3: pouring concrete.
[0018] Beneficial effects of the present invention:
[0019] The present invention provides a seam-pulling structure template, which is used to connect a first wall and a second wall, and a plurality of reserved steel bars are convexly provided on the sides of the first wall and the second wall facing each other. The seam-pulling mechanism template includes two seam-pulling plates arranged at intervals along the X direction, a channel for pouring concrete is arranged between the two seam-pulling plates, and a plurality of slots are arranged on the sides of the two seam-pulling plates facing away from each other, and the plurality of slots are arranged at intervals along the Y direction, and each slot extends along the Z direction. The seam-pulling plates are arranged between the first wall and the second wall, and at the same time, a plurality of reserved steel bars are correspondingly arranged in the plurality of slots, so as to fix and connect the two seam-pulling plates with the reserved steel bars of the first wall and the second wall respectively. When the concrete is poured subsequently, the first wall and the second wall can be poured simultaneously, the construction efficiency can be improved, and the construction progress can be accelerated; at the same time, the connection strength between the steel bars at the joint and the wall can be ensured, the overall connection strength can be ensured, the subsequent cracking can be effectively avoided, and the load-bearing effect of the wall can be ensured. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is an overall schematic diagram of the seam structure template provided by the specific implementation example of the present invention;
[0021] Figure 2 It is a side view of a seam-pulling mechanism template provided in a specific embodiment of the present invention;
[0022] Figure 3 It is a schematic diagram of the use of the seam structure template provided in the specific implementation example of the present invention.
[0023] In the figure:
[0024] 100, first wall; 200, second wall; 300, reserved steel bars;
[0025] 1. Pull-on seam board; 11. Card slot;
[0026] 2. Channel. DETAILED DESCRIPTION
[0027] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0028] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0029] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0030] In the description of this embodiment, the terms "upper", "lower", "right", etc., directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
[0031] The technical solution of the present invention is further described below with reference to the accompanying drawings and through specific implementation methods.
[0032] like Figures 1 to 3As shown, the present embodiment provides a seam-drawing structure template, which is used to connect the first wall 100 and the second wall 200, and the first wall 100 and the second wall 200 are both provided with a plurality of reserved steel bars 300 on one side facing each other. The seam-drawing mechanism template includes two seam-drawing plates 1 spaced apart along the X direction, a channel 2 for pouring concrete is arranged between the two seam-drawing plates 1, and a plurality of slots 11 are provided on the side facing away from each other of the two seam-drawing plates 1, the plurality of slots 11 are spaced apart along the Y direction, and each slot 11 extends along the Z direction. The seam-drawing plates 1 are arranged between the first wall 100 and the second wall 200, and at the same time, the plurality of reserved steel bars 300 are correspondingly arranged in the plurality of slots 11 one by one, so as to fix the two seam-drawing plates 1 with the reserved steel bars 300 of the first wall 100 and the second wall 200, respectively. During the subsequent concrete pouring, the first wall 100 and the second wall 200 can be poured simultaneously, thereby improving construction efficiency and accelerating construction progress; at the same time, the connection strength between the steel bars at the joints and the wall can be ensured, thereby ensuring the overall connection strength, effectively avoiding possible subsequent cracking, and ensuring the load-bearing effect of the wall.
[0033] The X direction, the Y direction and the Z direction are perpendicular to each other.
[0034] For example, in this embodiment, the overall size of the seam structure template along the X direction is 200mm, the size of each seam plate 1 along the X direction is 50mm, and the width of the channel 2 enclosed between the two seam plates 1 is 100mm. The spacing between two adjacent slots 11 along the Y direction is 200mm, the size of each slot 11 along the X direction is 25mm, and the size along the Y direction is 10mm, and four slots 11 are provided on each seam plate 1; in other embodiments, the specific size of the seam structure template can be designed as needed, and the number of slots 11 can also be set as needed, which is not specifically limited here.
[0035] Optionally, the slot 11 is arc-shaped (not shown in the figure) to increase the contact area between the reserved steel bar 300 and the slot 11, improve the clamping stability of the seam plate 1 and the reserved steel bar 300, avoid the movement of the seam structure template, and ensure the stability of the fixation of the seam structure template.
[0036] Optionally, an anti-skid structure is provided in the slot 11. Specifically, the anti-skid structure is an anti-skid pad provided in the slot 11, such as a rubber pad, or the like; or the anti-skid structure is an anti-skid protrusion provided in the slot 11, and the anti-skid protrusion can be a dot-shaped protrusion or a pattern protrusion of any shape, and its function is to increase the contact friction between the slot 11 and the reserved steel bar 300, and prevent the seam plate 1 from moving. Its specific form refers to the prior art, and is not specifically limited in this embodiment, as long as it can play a role in increasing friction.
[0037] Optionally, the seam-stretching plate 1 is made of PVC material or wooden material, and has good toughness, strong ductility and high impact resistance.
[0038] Optionally, the two seam-drawing plates 1 are both integrally formed, which is beneficial to simplifying the production process and improving production efficiency; at the same time, it can also effectively reduce processing costs and has good economy.
[0039] This embodiment also provides a method for seam pulling construction, using the seam pulling structure template described above, comprising the following steps:
[0040] S1: tying the main structural steel bars of the first wall 100 and the second wall 200;
[0041] The above steps, specifically in this embodiment, are to tie the main structural steel bars of the first wall 100 and the second wall 200, and reserve the reserved steel bars 300 for clamping with the seam plate 1;
[0042] S2: stacking the seam plate 1 on the end surface of the first wall 100 or the second wall 200, and clamping the plurality of reserved steel bars 300 in the plurality of clamping grooves 11 in a one-to-one correspondence;
[0043] The above steps, specifically in this embodiment, are as follows: the seam plate 1 is stacked on the end face of the first wall 100 or the second wall 200, and the outer edge of the seam plate 1 is aligned with the outer edge of the first wall 100 or the second wall 200, so that a channel 2 for pouring concrete is enclosed between the two seam plates 1; at the same time, a plurality of reserved steel bars 300 are clamped in a plurality of clamping grooves 11 in a one-to-one correspondence, so as to complete the clamping fixation of the reserved steel bars 300 and the seam plate 1;
[0044] Specifically, the first wall 100 and the second wall 200 can be distributed in a horizontal interval or in a vertical interval. In other words, the seam structure template can be used for a vertical seam structure or a horizontal seam structure. In addition, the seam structure template can also be used for a horizontal seam at the bottom of a beam, and has a wide range of applications and good versatility.
[0045] S3: pouring concrete.
[0046] In the above steps, specifically in this embodiment, the first wall 100 and the second wall 200 can be cast at the same time. The use of the seam structure template can ensure the compactness of the concrete casting and the connection strength between the first wall 100 and the second wall 200, and at the same time, it is conducive to improving the construction efficiency and speeding up the construction progress. In addition, the integrated insulation board can also be constructed as a whole, which is conducive to reducing the construction cost and speeding up the construction process.
[0047] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A seam-drawn structural template, used for connecting a first wall (100) and a second wall (200), wherein a plurality of reserved steel bars (300) are protruded from one side of the first wall (100) and the second wall (200) facing each other; It is characterized in that The seam-drawing structure template comprises two seam-drawing plates (1) arranged at intervals along the X direction, a channel (2) for pouring concrete is arranged between the two seam-drawing plates (1), a plurality of slots (11) are arranged on one side of the two seam-drawing plates (1) facing away from each other, the plurality of slots (11) are arranged at intervals along the Y direction, and each of the slots (11) extends along the Z direction; The seam-drawing plate (1) is arranged between the first wall (100) and the second wall (200), and the plurality of reserved steel bars (300) are clamped in the plurality of clamping grooves (11) in a one-to-one correspondence; The X direction, the Y direction and the Z direction are perpendicular to each other.
2. The seam structure template according to claim 1, characterized in that: The clamping slot (11) is arc-shaped.
3. The seam structure template according to claim 1, characterized in that: An anti-slip structure is arranged in the card slot (11).
4. The seam structure template according to claim 1, characterized in that: The seam-drawing plate (1) is made of PVC or wood.
5. The seam structure template according to claim 1, characterized in that: The two seam-drawing plates (1) are both of an integrally formed design.
6. A method for seam pulling construction, characterized in that: The method of using the seam structure template as described in any one of claims 1 to 5 above comprises the following steps: S1: tying the main structural steel bars of the first wall (100) and the second wall (200); S2: placing the seam-drawing plate (1) between the first wall (100) and the second wall (200), and clamping the plurality of reserved steel bars (300) in the plurality of clamping grooves (11) in a one-to-one correspondence; S3: pouring concrete.