Laser positioning construction method for water stop joint of drainage vertical pipe

Through the laser positioning construction method, the laser level is used to accurately align the water stop joints in the building, which solves the problem of large installation errors in the existing technology and improves the installation accuracy and construction efficiency of the water stop joints in multi-story buildings.

CN118728081APending Publication Date: 2024-10-01CHINA HUASHI ENTERPRISES CO LTD (SICHUAN)

Patent Information

Application Number
CN202411031318.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The existing technology uses the ruler measuring method and the artificial plumb line method in construction, resulting in large installation errors in the drainage riser water stop joints, affecting the installation accuracy.

Method used

Using the laser positioning construction method, a laser level is used to install the water stop on the first floor as a benchmark. The cross intersection line of the laser level is used to open holes on the upper floor and fix the water stop to ensure the accurate alignment of each water stop. .

Benefits of technology

It improves the installation accuracy of water stop joints in multi-story buildings and ensures accurate docking of drainage risers. It is simple and efficient to operate and convenient to construct.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118728081A_ABST
    Figure CN118728081A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of building construction, and particularly relates to a laser positioning construction method for a water stop joint of a drainage vertical pipe. Comprising the steps that S1, a plurality of water stop joints in rows are installed on a formwork of a first floor slab, and floor slab concrete is poured; s2, enabling laser emitted from the bottom of the laser level gauge to be aligned with the central position of one water stop section, placing the laser level gauge on the water stop section, and leveling the laser level gauge; s3, the laser level gauge upwards emits a cross line and irradiates the template of the adjacent upper floor slab, and the template of the adjacent upper floor slab is holed; s4, repeating the steps S2 to S3; s5, straight lines connected with the multiple open holes are drawn on the formwork faces of the adjacent upper floor slabs, then vertical lines, passing through the open holes, of the straight lines are drawn, round holes in the four positioning lug plates on the periphery of the bottom of the water stop joint are aligned with one cross intersecting line, and the water stop joint and the formwork are fixed; floor slab concrete is poured; and S6, repeating the steps S2 to S5. And the mounting precision of the water stopping section in the multi-story building can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and in particular relates to a laser positioning construction method for a water stop joint of a drainage riser. Background Art

[0002] Drainage risers in civil buildings are usually made of polyvinyl chloride. Two adjacent drainage risers are installed by docking through water stop joints, and the water stop joints are pre-buried in the floor slab. Before pouring the floor slab concrete, the water stop joints are fixed on the floor slab formwork. During construction, it should be ensured that multiple water stop parts on the same floor are in a row, and the water stop joints on the lower floor slab are aligned with the corresponding water stop joints on the upper floor slab.

[0003] At present, the reserved installation and positioning of drainage plastic pipe water stoppers are generally based on the ruler measurement method and the manual plumb line method. Due to the large actual error of the building structure formwork, the cumulative error of these two methods during the construction process is too large. If the maximum allowable deviation value of the drainage riser installation is exceeded, the subsequent drainage riser installation will be seriously affected. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a laser positioning construction method for a drainage riser water stop joint, which can improve the installation accuracy of the water stop joint in a multi-story building.

[0005] The technical solution adopted by the present invention to solve the technical problem is: a laser positioning construction method for a drainage riser water stop joint, comprising the steps of:

[0006] S1, install multiple water stop joints in a row on the formwork of the first floor slab according to the design requirements as the installation reference; then pour the floor slab concrete;

[0007] S2, after the concrete reaches the demolding strength, align the laser emitted from the bottom of the laser level with the center position of one of the water stop joints, and place the laser level on the water stop joint, and level the laser level itself by placing a pad under the water stop joint and using the spirit level of the laser level;

[0008] S3, a laser level emits cross-intersecting lines upward and illuminates the template of the adjacent upper floor slab, the intersection of the cross-intersecting lines is used as the opening position, and a hole opener is used to open a hole in the template of the adjacent upper floor slab;

[0009] S4, repeating steps S2 to S3 until the number of openings on the template of the adjacent upper floor slab is equal to the number of water stop joints on the first floor slab;

[0010] S5, draw a straight line connecting multiple openings on the template surface of the adjacent upper floor slab, then draw a perpendicular line through each opening on the straight line, place the water stop on the template surface, align the circular holes on the four positioning ear plates on the outer periphery of the bottom of the water stop with one of the cross intersections, and then fix the water stop to the template by screws and positioning ear plates; after the water stop at each cross intersection is installed, pour the floor slab concrete;

[0011] S6, repeating steps S2 to S5 until the construction of multiple water stop joints in a row on each floor slab is completed.

[0012] Furthermore, in the steps S1 and S5, before pouring concrete, a removable cover plate is provided on the water stop joint to prevent concrete from falling in.

[0013] Furthermore, the hole opener in step S3 is a hand electric drill.

[0014] Furthermore, the cushion block in step S2 is a wedge-shaped block.

[0015] Compared with the prior art, the invention has the following beneficial effects: the invention provides a laser positioning construction method for a water stop joint of a drainage riser, which can improve the installation accuracy of the water stop joint in a multi-story building, further ensure the installation accuracy of the drainage riser, and has the advantages of high efficiency, simple operation, convenient construction, and easy implementation. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure of the present invention;

[0017] Figure 2 It is a schematic diagram of the position of the water stop node and the drawn cross intersection line in the present invention;

[0018] Figure numerals: 1-template; 2-water stop joint; 201-positioning ear plate; 3-laser level; 4-pad; 5-opening. DETAILED DESCRIPTION

[0019] The present invention is further described below in conjunction with the accompanying drawings and embodiments.

[0020] A laser positioning construction method for a drainage riser water stop joint comprises the following steps:

[0021] S1, according to the design requirements, install multiple water stop joints 2 in a row on the formwork 1 of the first floor slab as the installation reference; then pour the floor slab concrete.

[0022] Normally, the pouring elevation of the floor slab concrete is lower than the height of the water stop joint 2.

[0023] S2, after the concrete reaches the demolding strength, align the laser emitted from the bottom of the laser level 3 with the center position of one of the water stop joints 2, and place the laser level 3 on the water stop joint 2, by placing a pad 4 under the water stop joint 2 and using the spirit level of the laser level 3 itself to level the laser level 3.

[0024] S3, the laser level 3 emits cross-intersecting lines upward and illuminates the template 1 of the adjacent upper floor slab, the intersection of the cross-intersecting lines is used as the opening point 5, and a hole opener is used to open a hole in the template 1 of the adjacent upper floor slab.

[0025] S4, repeat steps S2 to S3 until the number of openings on the template 1 of the adjacent upper floor slab is equal to the number of water stop joints 2 on the first floor slab.

[0026] S5. Draw a straight line connecting multiple openings 5 ​​on the board surface of the template 1 of the adjacent upper floor slab, and then draw a perpendicular line through each opening 5 on the straight line. Place the water stop 2 on the board surface of the template 1, align the circular holes on the four positioning ear plates 201 on the outer periphery of the bottom of the water stop 2 with one of the cross intersections, and then fix the water stop 2 to the template 1 by screws and the positioning ear plates 201. After the water stop 2 at each cross intersection is installed, pour the floor slab concrete.

[0027] like Figure 2 As shown, the circular holes on the four positioning ear plates 201 on the outer periphery of the bottom of the water stop joint 2 are aligned with one of the cross intersections to achieve cross positioning. When the circular holes on the four positioning ear plates 201 on the outer periphery of the bottom of the water stop joint 2 are aligned with one of the cross intersections, the opening 5 in the cross intersection is located at the center of the water stop joint 2.

[0028] S6, repeating steps S2 to S5 until the construction of multiple water stop joints 2 in a row on each floor slab is completed.

[0029] As a preferred embodiment, in the steps S1 and S5, before pouring concrete, a removable cover plate is provided on the water stop joint 2 to prevent concrete from falling in.

[0030] Preferably, the cover plate can be made of metal, wood, etc.

[0031] As a preferred embodiment, the hole opener in step S3 is a hand electric drill.

[0032] The cushion block 4 may be a flat cushion block. As a preferred embodiment, the cushion block 4 in step S2 is a wedge-shaped block.

[0033] The embodiments of the specific implementation are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. All equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A laser positioning construction method for a drainage riser water stop joint, characterized in that: Includes steps: S1, according to the design requirements, a plurality of water stop joints (2) are installed in a row on the formwork (1) of the first floor slab as an installation reference; and then the floor slab concrete is poured; S2, after the concrete reaches the demoulding strength, align the laser emitted from the bottom of the laser level (3) with the center position of one of the water stop joints (2), and place the laser level (3) on the water stop joint (2), and level the laser level (3) by placing a pad (4) under the water stop joint (2) and using the spirit level of the laser level (3); S3, the laser level (3) emits cross-intersecting lines upward and illuminates the template (1) of the adjacent upper floor, the intersection of the cross-intersecting lines is used as the opening position (5), and a hole is opened in the template (1) of the adjacent upper floor using a hole opener; S4, repeating steps S2 to S3 until the number of openings on the template (1) of the adjacent upper floor slab is equal to the number of water stop joints (2) on the first floor slab; S5, draw a straight line connecting a plurality of openings (5) on the board surface of the template (1) of the adjacent upper floor slab, then draw a perpendicular line through each opening (5) of the straight line, place the water stop (2) on the board surface of the template (1), align the circular holes on the four positioning ear plates (201) on the outer periphery of the bottom of the water stop (2) with one of the cross intersections, and then fix the water stop (2) to the template (1) by screws and the positioning ear plates (201); after the installation of each water stop (2) at the cross intersection is completed, pour the floor slab concrete; S6, repeating steps S2 to S5 until the construction of multiple water stop joints (2) in a row on each floor slab is completed.

2. A laser positioning construction method for a drainage riser water stop joint as claimed in claim 1, characterized in that: In the steps S1 and S5, before pouring concrete, a removable cover plate is provided on the water stop joint (2) to prevent concrete from falling in.

3. The laser positioning construction method for a drainage riser water stop joint according to claim 1, characterized in that: The hole opener in step S3 is a hand electric drill.

4. The laser positioning construction method for a drainage riser water stop joint according to claim 1, characterized in that: The cushion block (4) in step S2 is a wedge-shaped block.

Citation Information

Patent Citations

  • Water supply and drainage vertical stand pipe pre-buried sleeve infrared positioning system

    CN212158612U

Cited By

  • Water stop joint positioning device and embedding method

    CN121162027A