Laser positioning construction method for water stop joint of drainage vertical pipe
Through the laser positioning construction method, the laser level is used to accurately align the water stop joints in the building, which solves the problem of large installation errors in the existing technology and improves the installation accuracy and construction efficiency of the water stop joints in multi-story buildings.
Patent Information
- Application Number
- CN202411031318.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-01
AI Technical Summary
The existing technology uses the ruler measuring method and the artificial plumb line method in construction, resulting in large installation errors in the drainage riser water stop joints, affecting the installation accuracy.
Using the laser positioning construction method, a laser level is used to install the water stop on the first floor as a benchmark. The cross intersection line of the laser level is used to open holes on the upper floor and fix the water stop to ensure the accurate alignment of each water stop. .
It improves the installation accuracy of water stop joints in multi-story buildings and ensures accurate docking of drainage risers. It is simple and efficient to operate and convenient to construct.
Smart Images

Figure CN118728081A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a laser positioning construction method for a water stop joint of a drainage riser. Background Art
[0002] Drainage risers in civil buildings are usually made of polyvinyl chloride. Two adjacent drainage risers are installed by docking through water stop joints, and the water stop joints are pre-buried in the floor slab. Before pouring the floor slab concrete, the water stop joints are fixed on the floor slab formwork. During construction, it should be ensured that multiple water stop parts on the same floor are in a row, and the water stop joints on the lower floor slab are aligned with the corresponding water stop joints on the upper floor slab.
[0003] At present, the reserved installation and positioning of drainage plastic pipe water stoppers are generally based on the ruler measurement method and the manual plumb line method. Due to the large actual error of the building structure formwork, the cumulative error of these two methods during the construction process is too large. If the maximum allowable deviation value of the drainage riser installation is exceeded, the subsequent drainage riser installation will be seriously affected. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a laser positioning construction method for a drainage riser water stop joint, which can improve the installation accuracy of the water stop joint in a multi-story building.
[0005] The technical solution adopted by the present invention to solve the technical problem is: a laser positioning construction method for a drainage riser water stop joint, comprising the steps of:
[0006] S1, install multiple water stop joints in a row on the formwork of the first floor slab according to the design requirements as the installation reference; then pour the floor slab concrete;
[0007] S2, after the concrete reaches the demolding strength, align the laser emitted from the bottom of the laser level with the center position of one of the water stop joints, and place the laser level on the water stop joint, and level the laser level itself by placing a pad under the water stop joint and using the spirit level of the laser level;
[0008] S3, a laser level emits cross-intersecting lines upward and illuminates the template of the adjacent upper floor slab, the intersection of the cross-intersecting lines is used as the opening position, and a hole opener is used to open a hole in the template of the adjacent upper floor slab;
[0009] S4, repeating steps S2 to S3 until the number of openings on the template of the adjacent upper floor slab is equal to the number of water stop joints on the first floor slab;
[0010] S5, draw a straight line connecting multiple openings on the template surface of the adjacent upper floor slab, then draw a perpendicular line through each opening on the straight line, place the water stop on the template surface, align the circular holes on the four positioning ear plates on the outer periphery of the bottom of the water stop with one of the cross intersections, and then fix the water stop to the template by screws and positioning ear plates; after the water stop at each cross intersection is installed, pour the floor slab concrete;
[0011] S6, repeating steps S2 to S5 until the construction of multiple water stop joints in a row on each floor slab is completed.
[0012] Furthermore, in the steps S1 and S5, before pouring concrete, a removable cover plate is provided on the water stop joint to prevent concrete from falling in.
[0013] Furthermore, the hole opener in step S3 is a hand electric drill.
[0014] Furthermore, the cushion block in step S2 is a wedge-shaped block.
[0015] Compared with the prior art, the invention has the following beneficial effects: the invention provides a laser positioning construction method for a water stop joint of a drainage riser, which can improve the installation accuracy of the water stop joint in a multi-story building, further ensure the installation accuracy of the drainage riser, and has the advantages of high efficiency, simple operation, convenient construction, and easy implementation. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the structure of the present invention;
[0017] Figure 2 It is a schematic diagram of the position of the water stop node and the drawn cross intersection line in the present invention;
[0018] Figure numerals: 1-template; 2-water stop joint; 201-positioning ear plate; 3-laser level; 4-pad; 5-opening. DETAILED DESCRIPTION
[0019] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0020] A laser positioning construction method for a drainage riser water stop joint comprises the following steps:
[0021] S1, according to the design requirements, install multiple water stop joints 2 in a row on the formwork 1 of the first floor slab as the installation reference; then pour the floor slab concrete.
[0022] Normally, the pouring elevation of the floor slab concrete is lower than the height of the water stop joint 2.
[0023] S2, after the concrete reaches the demolding strength, align the laser emitted from the bottom of the laser level 3 with the center position of one of the water stop joints 2, and place the laser level 3 on the water stop joint 2, by placing a pad 4 under the water stop joint 2 and using the spirit level of the laser level 3 itself to level the laser level 3.
[0024] S3, the laser level 3 emits cross-intersecting lines upward and illuminates the template 1 of the adjacent upper floor slab, the intersection of the cross-intersecting lines is used as the opening point 5, and a hole opener is used to open a hole in the template 1 of the adjacent upper floor slab.
[0025] S4, repeat steps S2 to S3 until the number of openings on the template 1 of the adjacent upper floor slab is equal to the number of water stop joints 2 on the first floor slab.
[0026] S5. Draw a straight line connecting multiple openings 5 on the board surface of the template 1 of the adjacent upper floor slab, and then draw a perpendicular line through each opening 5 on the straight line. Place the water stop 2 on the board surface of the template 1, align the circular holes on the four positioning ear plates 201 on the outer periphery of the bottom of the water stop 2 with one of the cross intersections, and then fix the water stop 2 to the template 1 by screws and the positioning ear plates 201. After the water stop 2 at each cross intersection is installed, pour the floor slab concrete.
[0027] like Figure 2 As shown, the circular holes on the four positioning ear plates 201 on the outer periphery of the bottom of the water stop joint 2 are aligned with one of the cross intersections to achieve cross positioning. When the circular holes on the four positioning ear plates 201 on the outer periphery of the bottom of the water stop joint 2 are aligned with one of the cross intersections, the opening 5 in the cross intersection is located at the center of the water stop joint 2.
[0028] S6, repeating steps S2 to S5 until the construction of multiple water stop joints 2 in a row on each floor slab is completed.
[0029] As a preferred embodiment, in the steps S1 and S5, before pouring concrete, a removable cover plate is provided on the water stop joint 2 to prevent concrete from falling in.
[0030] Preferably, the cover plate can be made of metal, wood, etc.
[0031] As a preferred embodiment, the hole opener in step S3 is a hand electric drill.
[0032] The cushion block 4 may be a flat cushion block. As a preferred embodiment, the cushion block 4 in step S2 is a wedge-shaped block.
[0033] The embodiments of the specific implementation are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. All equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A laser positioning construction method for a drainage riser water stop joint, characterized in that: Includes steps: S1, according to the design requirements, a plurality of water stop joints (2) are installed in a row on the formwork (1) of the first floor slab as an installation reference; and then the floor slab concrete is poured; S2, after the concrete reaches the demoulding strength, align the laser emitted from the bottom of the laser level (3) with the center position of one of the water stop joints (2), and place the laser level (3) on the water stop joint (2), and level the laser level (3) by placing a pad (4) under the water stop joint (2) and using the spirit level of the laser level (3); S3, the laser level (3) emits cross-intersecting lines upward and illuminates the template (1) of the adjacent upper floor, the intersection of the cross-intersecting lines is used as the opening position (5), and a hole is opened in the template (1) of the adjacent upper floor using a hole opener; S4, repeating steps S2 to S3 until the number of openings on the template (1) of the adjacent upper floor slab is equal to the number of water stop joints (2) on the first floor slab; S5, draw a straight line connecting a plurality of openings (5) on the board surface of the template (1) of the adjacent upper floor slab, then draw a perpendicular line through each opening (5) of the straight line, place the water stop (2) on the board surface of the template (1), align the circular holes on the four positioning ear plates (201) on the outer periphery of the bottom of the water stop (2) with one of the cross intersections, and then fix the water stop (2) to the template (1) by screws and the positioning ear plates (201); after the installation of each water stop (2) at the cross intersection is completed, pour the floor slab concrete; S6, repeating steps S2 to S5 until the construction of multiple water stop joints (2) in a row on each floor slab is completed.
2. A laser positioning construction method for a drainage riser water stop joint as claimed in claim 1, characterized in that: In the steps S1 and S5, before pouring concrete, a removable cover plate is provided on the water stop joint (2) to prevent concrete from falling in.
3. The laser positioning construction method for a drainage riser water stop joint according to claim 1, characterized in that: The hole opener in step S3 is a hand electric drill.
4. The laser positioning construction method for a drainage riser water stop joint according to claim 1, characterized in that: The cushion block (4) in step S2 is a wedge-shaped block.
Citation Information
Patent Citations
Water supply and drainage vertical stand pipe pre-buried sleeve infrared positioning system
CN212158612U
Cited By
Water stop joint positioning device and embedding method
CN121162027A
