Electric cement plug injection tool
Through the design of electric cement injection plug tools, the use of motors to drive valves and timing equipment solves the problem of early solidification of cement, achieves precise cement injection at preset positions and time points, improves construction efficiency and safety, and reduces costs. .
Patent Information
- Application Number
- CN202310341140.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the existing cement injection technology, cement is easy to solidify prematurely under heat and pressure, resulting in low construction efficiency and high cost, and it is difficult to accurately control the solidification time and ash amount.
Design an electric cement injection tool that preloads cement slurry downhole and uses a motor to drive the valve to control the outflow of cement slurry. It combines with timing equipment to achieve precise adjustment and delayed power supply to ensure that the cement solidifies at the preset position and time.
It realizes cement injection at preset positions and time points, avoids early solidification of cement, improves construction efficiency and safety, reduces costs, and accurately controls the amount of ash.
Smart Images

Figure CN118728307A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of drilling and completion engineering, and in particular to an electric cementing plug tool. Background Art
[0002] In the downhole operation of oil fields, cementing is a very important process measure. Every year, hundreds of wells in oil fields need to be squeezed and plugged to seal the oil layer, water layer or other stratified operations, so as to achieve the purpose of sealing the tested oil layer and returning to the new layer for oil testing, plugging non-target layers, finding leaks and sealing, and upper casing pressure testing.
[0003] In the prior art, circulating cementing is the most common cementing method in oil fields. It is to pump the prepared cement slurry into the well and circulate it to the predetermined position, and then solidify it to form a plug. This method requires a pump truck, but the amount of cement squeezed and the time are not well controlled, and it is very easy to cause the "flagpole" phenomenon, that is, the cement solidifies prematurely under heat and pressure, causing the oil pipe to be unable to be pulled out, affecting the success rate of construction, and thus leading to the problems of slow timeliness and high cost; another wire pouring method is to use tools such as pouring ash barrels to make the cement slurry flow out through electric current blasting or impact to form a plug, but it is only suitable for layers with low plugging requirements and small ash plug thickness. Therefore, it is necessary to study a cementing tool with fast timeliness, avoiding cement solidification of the pipe column, high safety factor and low cost. Summary of the invention
[0004] The embodiment of the present invention provides an electric cement plug tool, which at least partially solves the technical problem in the prior art that the time of the cement injection process is difficult to control, resulting in premature solidification, and achieves the technical effect of injecting cement at a preset position and at a preset time while ensuring that the cement does not solidify prematurely.
[0005] In the first aspect, in order to solve the above technical problems, the embodiments of the present invention provide the following technical solutions:
[0006] An electric cement plugging tool, comprising:
[0007] An outer shell and a valve, an inner shell, a transmission mechanism and a power source arranged in the outer shell;
[0008] The outer shell includes a cement slurry loading part and a cement slurry flowing part, the inner shell is arranged in the cement slurry flowing part, and a mud passing space is arranged between the inner shell and the outer shell;
[0009] The flow of cement slurry is controlled by the valve between the cement slurry loading part and the mud passing space;
[0010] The transmission mechanism and the power source are arranged in the inner shell. The transmission mechanism drives the valve to open and close under the drive of the power source. The power source responds to the start signal sent by the timing device.
[0011] Optionally, the transmission mechanism includes a screw connected to the output shaft of the motor in the power source and a nut adapted to the screw; the screw is rotatably connected to the inner shell; the nut moves along a guide groove provided in the inner shell, and the nut is connected to the piston of the valve.
[0012] Optionally, one or more planetary gear sets for increasing torque are provided between the lead screw and the motor output shaft.
[0013] Optionally, the piston includes a connecting part and a sealing part which are connected to each other, the connecting part is connected to the nut, and the sealing part abuts against the inner wall of the outer shell; the sealing part is made of metal, a sealing ring is provided on the side wall of the sealing part, and the sealing part is sealed and abuts against the inner wall of the outer shell through the sealing part.
[0014] Optionally, the inner shell and the outer shell are coaxially arranged, and the mud passing space is cylindrical.
[0015] Optionally, the valve further comprises a boss disposed on the outer shell, and the boss is in sealing contact with the piston.
[0016] Optionally, the cross section of the boss is trapezoidal.
[0017] Optionally, the cement slurry loading part includes a plurality of one or more identical loading cylinders, and two adjacent loading cylinders are threadedly sealed and connected via a connecting joint.
[0018] Optionally, the power source includes a motor disposed in the inner shell and a power source electrically connected to the motor.
[0019] Optionally, a lifting ring is provided on one end of the cement slurry loading part close to the wellhead.
[0020] One or more technical solutions provided in the embodiments of the present invention have at least the following technical effects or advantages:
[0021] By loading the mud into the cement slurry loading part in advance, the use of mud pumps is reduced, and the motor is used to drive the valve to open and close to complete the power control, so that the staff does not need to use other methods to inject mud from the wellhead. The timing device is used to control the power supply of the motor, so that the mud can be discharged according to the required time. In addition, since the mud is loaded into the cement slurry loading part in advance, the amount of ash can be accurately adjusted in advance, and it is not easy to solidify in a closed environment. In this way, cement injection operations can be carried out at a preset position and preset time point without premature solidification of cement. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0023] Figure 1 A schematic structural diagram of an electric cement plugging tool provided by the present invention;
[0024] Figure 2 A flow chart of a process corresponding to the electric cement plug tool provided by the present invention;
[0025] Figure 3 It is a structural schematic diagram of the transmission mechanism and the valve in the present invention;
[0026] Figure 4 It is a structural schematic diagram of the transmission mechanism in the present invention;
[0027] Figure 5 It is a schematic structural diagram of the cement slurry loading part in the present invention.
[0028] Figure numerals: 1. outer shell; 11. cement slurry loading part; 111. loading cylinder; 112. connecting joint; 12. cement slurry flowing part; 2. valve; 21. piston; 211. sealing ring; 212. sealing member; 213. connecting member; 22. boss; 3. inner shell; 4. transmission mechanism; 41. screw; 42. nut; 43. guide groove; 44. planetary gear set; 5. power source; 6. mud passing space. DETAILED DESCRIPTION
[0029] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0030] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0032] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "disposed" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0033] It should be understood that the embodiments of the present invention and the specific features in the embodiments are detailed descriptions of the technical solutions of the present application, rather than limitations of the technical solutions of the present application. In the absence of conflict, the embodiments of the present application and the technical features in the embodiments may be combined with each other.
[0034] The embodiment of the present invention provides an electric cement plugging tool to solve the above technical problems. The overall idea is as follows:
[0035] By loading the mud into the cement slurry loading part in advance, the use of mud pumps is reduced, and the motor is used to drive the valve to open and close to complete the power control, so that the staff does not need to use other methods to inject mud from the wellhead. The timing device is used to control the power supply of the motor, so that the mud can be discharged according to the required time. In addition, since the mud is loaded into the cement slurry loading part in advance, the amount of ash can be accurately adjusted in advance, and it is not easy to solidify in a closed environment. In this way, cement injection operations can be carried out at a preset position and preset time point without premature solidification of cement.
[0036] In an embodiment of the present invention, there is provided Figure 1 An electric cement plugging tool shown in the figure comprises: an outer shell 1 and a valve 2, an inner shell 3, a transmission mechanism 4 and a power source 5 arranged in the outer shell 1; the outer shell 1 comprises a cement slurry loading part 11 and a cement slurry flowing part 12, the inner shell 3 is arranged in the cement slurry flowing part 12, and a mud passing space 6 is provided between the inner shell 3 and the outer shell 1; the flow of cement slurry between the cement slurry loading part 11 and the mud passing space 6 is controlled by the valve 2; the transmission mechanism 4 and the power source 5 are arranged in the inner shell 3, and the transmission mechanism 4 drives the valve 2 to open and close under the drive of the power source 5; the power source 5 responds to the start signal sent by the timing device.
[0037] It should be noted that, since the diameter of the well is generally small in the usual cementing operation, it is not suitable for large objects to enter, so the diameter of the outer shell 1 is set according to the size of the pipe used in the existing cementing operation. At the same time, in order not to increase the diameter of the outer shell 1, the inner shell 3 is set to place the power source 5 and the transmission mechanism 4. In the prior art, cement solidifies in advance under heat and pressure, and the pressure is largely generated by falling from a high altitude when injected by a cement pump. Therefore, this embodiment adopts a cement slurry loading part 11 to put the stirred cement in advance, so that the quantity can be set according to the pressure to avoid premature solidification. In addition to being used to install the inner shell 3, the setting of the cement slurry flow part 12 also uses the mud space 6 between the inner shell 3 and the outer shell 1 to discharge the fluid, that is, cement slurry. The valve 2 is set to seal the cement slurry loading part 11, so as to control whether the mud is discharged. Since the cement plug tool is used for underground operations, it needs to be opened underground for cementing operations. The timing device is thus set to control the power source 5, based on the time when the cement plug tool reaches the specified position, so as to achieve cement injection at the preset position and preset time without premature solidification of cement. It should be noted that this embodiment is only illustrated by the example of cement slurry, and is also applicable to other fluids with the same principle.
[0038] like Figure 2 As shown, the specific implementation process is:
[0039] Step S101, according to the pre-calculated required fluid volume, a corresponding amount of fluid is loaded into the cement slurry loading part 11 of the cement plug injection tool;
[0040] Step S102, based on the determined injection fluid position, manually setting the start time of fluid injection through a timing device in the cement plugging tool;
[0041] Step S103, using a cable retractable vehicle to lower the cement plug tool to the fluid injection position, and perform depth calibration;
[0042] Step S104, when the start time is reached, the programmable logic control in the cement plug tool responds to the start signal sent by the timing device, controls the motor in the cement plug tool to open the valve 2, and releases the fluid from the cement plug tool;
[0043] Step S105, after all fluid injection operations are completed, the cement plugging tool is recovered by the cable retractable vehicle.
[0044] It should be noted that the process in this embodiment, in addition to being applied to the cement plug tool in this embodiment, can also be applied to other types of cement plug tools, for example: containing a power source 5 whose start and stop are controlled by a timing device, and the power source 5 controls the opening and closing of the valve 2, thereby completing the discharge or limiting function of the cement slurry, which can be applicable to the process in this embodiment.
[0045] In detail, the above-mentioned step of performing depth calibration also includes: calculating the useful length of the cable according to the number of rotations of the reel on the cable reel-up vehicle; summing the used length and the length of the cement plug tool to obtain the calculated depth of the injected fluid position, and performing depth calibration based on the calculated depth.
[0046] It should be noted that during underground operations, since it is necessary to calibrate and confirm whether the cementing plug tool has reached the specified position, a reference object is needed to measure the descent distance of the cementing plug tool. Because the cable enters the underground synchronously with the cementing plug tool, the position of the cementing plug tool can be directly obtained based on the cable length, the length or height of the cementing plug tool itself, and this can be used as the basis for calibration.
[0047] In detail, the above-mentioned step of setting the start time of fluid injection also includes: based on the determined fluid injection position, measuring the distance from the fluid injection position to the wellhead; calculating the first time when the cement plug tool arrives at the fluid injection position according to the distance and the cable reel-and-reel speed; and using the first time as the start time and manually inputting it into the timing device.
[0048] It should be noted that for timing, the shortest time should be the time for the cementing plug tool to reach the specified position. The shortest time can be obtained by dividing the distance from the injection fluid position to the wellhead by the speed of the cable lowering. Setting the manual input timing time allows the staff to check the time based on experience and improve the accuracy of the cementing operation.
[0049] In detail, the step of taking the first time as the start time also includes: setting a waiting time, taking the sum of the waiting time and the first time as the start time, and manually inputting it into the timing device.
[0050] It should be noted that if the shortest time is used, all work must be prepared before the cement plug tool can be placed below. However, emergencies cannot be dealt with in a timely manner. Therefore, a waiting time is set to give the staff sufficient time to check, thereby ensuring the stable operation of the cementing work.
[0051] Those skilled in the art will appreciate that the process provided by the embodiments of the present invention may be a method, a system, or a computer program product. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0052] Furthermore, if Figure 3 and Figure 4 As shown, the transmission mechanism 4 includes a lead screw 41 connected to the output shaft of the motor in the power source 5 and a nut 42 adapted to the lead screw 41; the lead screw 41 is rotationally connected to the inner shell 3; the nut 42 moves along a guide groove 43 provided in the inner shell 3, and the nut 42 is connected to the piston 21 of the valve 2.
[0053] It should be noted that since the cement slurry is loaded into the cement slurry loading part 11 in advance, its heavy weight will cause the general valve 2 to be squeezed back after sealing, resulting in cement slurry leakage. Therefore, the screw 41 transmission method is adopted, and the screw 41 and the nut 42 have the self-locking property to complete the sealing of the cement slurry loading part 11, and when the piston 21 is not damaged, the problem of the piston 21 being squeezed back by the pressure of the cement slurry is avoided. The sealing performance is improved.
[0054] Furthermore, if Figure 4 As shown, one or more planetary gear sets 44 for increasing torque are also provided between the lead screw 41 and the motor output shaft.
[0055] It should be noted that, due to the volume limitation of the cementing plug tool housing 1, a large motor cannot be placed, so the planetary gear set 44 is used to reduce speed, thereby increasing the torque. At the same time, due to the structure of the multiple planetary gear sets 44, they are arranged in a superimposed manner along the axial direction of the motor output shaft, and the cementing plug tool housing 1 pipeline is also cylindrical, so while increasing the torque, it can be well adapted to the pipeline, improving the adaptability.
[0056] Furthermore, if Figure 3 As shown, the piston 21 includes a connecting member 213 and a sealing member 212 that are connected to each other. The connecting member 213 is connected to the nut 42, and the sealing member 212 abuts against the inner wall of the housing 1. The sealing member 212 is made of metal, and a sealing ring 211 is provided on the side wall of the sealing member 212. The sealing member 212 abuts against the inner wall of the housing 1 through the sealing member 212.
[0057] It should be noted that since the piston 21 is in direct contact with the cement slurry in the cement slurry loading part 11, it needs to withstand a relatively large pressure. If it is made of materials such as rubber, it cannot bear the pressure. If a layer of rubber is directly put on the entire piston 21, the rubber in contact with the cement slurry will be damaged very quickly and will fall off easily. Therefore, using a metal material for the seal 212 of the piston 21 can increase the bearing capacity of the cement slurry. However, there will still be a certain gap between the metal material and the outer shell 1, which will cause the cement slurry to leak. Therefore, a sealing ring 211 is provided on the side wall of the seal 212 to ensure the sealing. In this way, the service life and sealing of the piston 21 are improved.
[0058] Furthermore, if Figure 1 , Figure 3 and Figure 4 As shown, the inner shell 3 is coaxially arranged with the outer shell 1, and the mud passing space 6 is cylindrical.
[0059] It should be noted that the inner shell 3 and the outer shell 1 are coaxially arranged, mainly to place the piston 21 at the center so that it can be fully stressed and avoid stress on one side of the piston 21, which may cause the piston 21 to break, thereby ensuring the stability of the seal.
[0060] Furthermore, if Figure 3 As shown, the valve 2 further comprises a boss 22 disposed on the housing 1 , and the boss 22 is in sealing contact with the piston 21 .
[0061] It should be noted that if the edge of the piston 21 directly contacts the flat inner wall of the housing 1, due to space limitations, the supporting screw 41 can only support the center of the piston 21, and the edge part cannot be effectively supported, thereby reducing the service life. Therefore, the boss 22 is provided on the housing 1, so that the radius of the connecting member 213 of the piston 21 can be reduced by a certain amount, thereby improving the bearing capacity of the piston 21 and indirectly improving the service life of the piston 21.
[0062] Furthermore, if Figure 3 As shown, the cross section of the boss 22 is trapezoidal.
[0063] It should be noted that if the boss 22 is directly set at a right angle, mud will remain at the connection between the boss 22 and the shell 1, and after solidification over a long period of time, it will easily extend outward, thereby causing blockage. Therefore, a boss 22 with a trapezoidal cross-section is used, and the trapezoidal slope is used to allow cement slurry to flow out as much as possible to avoid blockage.
[0064] Furthermore, if Figure 5 As shown, the cement slurry loading part 11 includes a plurality of one or more identical loading cylinders 111 , and two adjacent loading cylinders 111 are threadedly sealed and connected via a connecting joint 112 .
[0065] It should be noted that since the cement slurry is loaded into the cement slurry loading part 11 in advance, there is a great limitation on the adjustment of the pre-loaded cement amount by setting a fixed loading cylinder 111. Therefore, a plurality of identical loading cylinders 111 are provided to increase the capacity of the cement slurry loading part 11 as needed, thereby improving the adaptability to different cement amounts.
[0066] Furthermore, the power source 5 includes a motor disposed in the inner shell 3 and a power source electrically connected to the motor.
[0067] It should be noted that since the inner shell 3 is arranged in the center of the outer shell 1, if an external power source is used, it needs to pass through the mud space 6 to be powered. The mud space 6 is a passage for cement slurry, and it is easy to cause damage to the circuit in a long-term collision. Therefore, the motor and the power source are both arranged in the inner shell 3, thereby improving the service life.
[0068] Furthermore, a lifting ring is provided on one end of the cement slurry loading part 11 close to the wellhead.
[0069] It should be noted that the purpose of the setting of the lifting ring is to hang the cable on the lifting ring when it is on the ground and to connect it reliably with the downhole tool string.
[0070] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.
[0071] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. An electric cement plugging tool, characterized in that: The tools include: An outer shell, and a valve, an inner shell, a transmission mechanism and a power source arranged in the outer shell; The outer shell includes a cement slurry loading part and a cement slurry flowing part, the inner shell is arranged in the cement slurry flowing part, and a mud passing space is provided between the inner shell and the outer shell; The valve is used to control the flow of cement slurry between the cement slurry loading part and the mud passage space; The transmission mechanism and the power source are arranged in the inner shell. The transmission mechanism drives the valve to open and close under the drive of the power source. The power source responds to the start signal sent by the timing device.
2. The electric cement plugging tool according to claim 1, characterized in that: The transmission mechanism includes a lead screw connected to the output shaft of the motor in the power source and a nut adapted to the lead screw; the lead screw is rotationally connected to the inner shell; the nut moves along a guide groove arranged in the inner shell, and the nut is connected to the piston of the valve.
3. The electric cement plugging tool according to claim 2, characterized in that: One or more planetary gear sets for increasing torque are also provided between the lead screw and the motor output shaft.
4. The electric cement plugging tool according to claim 2, characterized in that: The piston includes a connecting piece and a sealing piece which are connected to each other. The connecting piece is connected to the nut, and the sealing piece abuts against the inner wall of the outer shell. The sealing piece is made of metal, and a sealing ring is provided on the side wall of the sealing piece. The sealing piece abuts against the inner wall of the outer shell through the sealing piece.
5. The electric cement plugging tool according to claim 1, characterized in that: The inner shell and the outer shell are coaxially arranged, and the mud passage space is cylindrical.
6. The electric cement plugging tool according to claim 5, characterized in that: The valve further comprises a boss arranged on the housing, wherein the boss is in sealing contact with the piston.
7. The electric cement plugging tool according to claim 6, characterized in that: The cross section of the boss is trapezoidal.
8. The electric cement plugging tool according to claim 1, characterized in that: The cement slurry loading part includes a plurality of one or more identical loading cylinders, and two adjacent loading cylinders are threadedly sealed and connected via a connecting joint.
9. The electric cement plugging tool according to claim 1, characterized in that: The power source includes a motor disposed in the inner shell and a power source electrically connected to the motor.
10. The electric cement plugging tool according to claim 1, characterized in that: A lifting ring is arranged on one end of the cement slurry loading part close to the wellhead.
Citation Information
Patent Citations
Electromechanical ash pouring tool for oil and gas well
CN112196490A
Ash throwing tool for cable in oil pipe
CN114439413A
Multipurpose is unsettled throws an ash section of thick bamboo, grey instrument is thrown to plug formula and grey instrument is thrown to firing pin formula
CN208777947U
Novel cable ash pouring cylinder releaser
CN218407382U
Cementing plug system
US20200270964A1