Construction method for installing all-in-one machine through tunnel secondary lining reinforcing mesh and arch frame

Through the mechanized construction method of the tunnel's secondary lining steel mesh and the arch installation integrated machine, the problems of low efficiency and poor quality of steel bar binding in tunnel construction are solved, the precise and rapid installation of steel bars is achieved, and the construction safety and quality are improved.

CN118728430APending Publication Date: 2024-10-01CHINA RAILWAY FIRST GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410985257.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In tunnel construction, the binding of steel bars in the existing technology requires manual binding on site one by one, resulting in long construction time, low efficiency, poor quality, safety hazards, and a lack of steel mesh sheets installed in sheets.

Method used

The construction method of tunnel secondary lining steel mesh and arch installation integrated machine is adopted. The steel mesh is connected through pins and pin sleeves. The arch installation integrated machine with multi-section hydraulic telescopic arm is used for mechanized installation to ensure the precise position of the steel mesh. and quick installation.

Benefits of technology

It improves the degree of mechanization of steel bar installation, saves labor, avoids the pollution problem of steel bars being dragged on the tunnel floor, ensures installation accuracy and quality, and solves the problem of difficult control of steel bar offset and concrete protective layer thickness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118728430A_ABST
    Figure CN118728430A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for installing an all-in-one machine through tunnel secondary lining reinforcing mesh pieces and an arch frame, and belongs to the technical field of tunnel mechanical construction. The two ends of a reinforcing mesh top arch are each rotationally connected with a reinforcing mesh side arch, and the two reinforcing mesh side arches are in lap joint with each other and movably connected together; the reinforcing mesh top arch is supported by the main arm and moved to a to-be-constructed area, and the tunnel secondary lining reinforcing mesh is lifted to a proper position through the main arm; and the movable connection between the two reinforcing mesh side arches is removed, the left auxiliary arm and the right auxiliary arm are in lap joint with the two reinforcing mesh side arches correspondingly and stretch outwards, the reinforcing mesh top arch and the two reinforcing mesh side arches are tightly attached to the inner wall of the tunnel, the tunnel secondary lining reinforcing mesh is manually fixed, and installation is completed. The device has the advantages that the mechanization degree is high, labor is saved, the problems that the reinforcing steel bars are dragged on the tunnel ground and are prone to being polluted by oil stains, muddy water and the like are solved, the reinforcing steel bar installation precision and quality are guaranteed, and the reinforcing steel bars can be rapidly installed in pieces.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of mechanized tunnel construction, and more specifically relates to a construction method using a tunnel secondary lining steel mesh and an arch frame installation integrated machine. Background Art

[0002] A tunnel is an engineering structure buried in the ground, and is a form of human use of underground space. Tunnels can be classified according to different standards, such as purpose, geological conditions, buried depth, location, etc. The main functions of tunnels include transportation, water conservancy, municipal administration, mining, etc. Tunnels can be used for three-dimensional transportation, crossing mountains and ridges, underground passages, crossing rivers and seas, pipeline transportation, underground cables, water conservancy projects, etc. Tunnels can be underground passages or located underground. In addition, tunnels can also be divided into different types according to the size of their cross-sectional areas, such as very small section tunnels, small section tunnels, medium section tunnels, large section tunnels and extra-large section tunnels. In tunnel construction, in order to ensure the firmness and reliability of the tunnel, it is often necessary to tie steel bars on the inner wall surface of the tunnel and use concrete for pouring. In the prior art, the steel bars can only be tied on site with the help of a steel mesh trolley, and the steel bars are tied one by one manually on site; the construction time is long and the efficiency is low; the construction quality is poor, the shape and position of the steel mesh cannot be guaranteed, and the thickness of the concrete protective layer cannot be ensured; there are many construction workers on site, and there are great safety hazards; the prior art lacks a steel mesh that can be installed in pieces. Therefore, how to provide a tunnel secondary lining steel mesh and arch frame installation all-in-one machine is a problem that technicians in this field urgently need to solve. Summary of the invention

[0003] In view of this, the present invention provides a construction method using a tunnel secondary lining steel mesh and an arch frame installation integrated machine, which has the advantages of high degree of mechanization, saving labor, avoiding the problem of steel bars being dragged on the tunnel ground and easily contaminated by oil stains, mud and water, etc., ensuring the accuracy and quality of steel bar installation, and the steel bars can be installed quickly in pieces.

[0004] In order to achieve the above object, the present invention adopts the following technical solution:

[0005] A construction method using a tunnel secondary lining steel mesh and an arch frame installation integrated machine comprises the following steps:

[0006] S1. First, the two ends of the steel mesh top arch are rotated and connected to a steel mesh side arch through a pin and a pin sleeve to form a tunnel secondary lining steel mesh, and the two steel mesh side arches are rotated inward to overlap each other, so that the two steel mesh side arches are movably connected;

[0007] S2, then lift the top arch of the steel mesh by the main arm of the arch frame installation machine, move the tunnel secondary lining steel mesh to the area to be constructed, and raise the tunnel secondary lining steel mesh to a suitable position by raising the main arm;

[0008] S3, releasing the movable connection between the two steel mesh side arches, using the left auxiliary arm and the right auxiliary arm to overlap the two steel mesh side arches respectively, and stretching them outwards, so that the two steel mesh side arches are fully unfolded around the steel mesh top arch;

[0009] S4. Adjust the positions of the main arm, left auxiliary arm and right auxiliary arm so that the top arch of the steel mesh and the two side arches of the steel mesh are close to the inner wall of the tunnel. Fix the secondary lining steel mesh of the tunnel manually to complete the installation.

[0010] Furthermore, the arch frame installation integrated machine is an engineering construction vehicle, and the main arm, left auxiliary arm and right auxiliary arm are all rotatably connected to the arch frame installation integrated machine.

[0011] Furthermore, the main arm, the left auxiliary arm and the right auxiliary arm are all multi-section hydraulic telescopic arms.

[0012] The beneficial effects of the present invention are:

[0013] 1. The implementation of the present invention solves the problem that the installation of the secondary lining steel bars is not mechanized to a high degree and the installation is labor-intensive.

[0014] 2. The implementation of the present invention solves the problem that when installing steel bars manually, the steel bars are dragged on the tunnel floor and are easily contaminated by oil stains, muddy water, etc.

[0015] 3. The implementation of the present invention solves the problem that the accuracy and quality of steel bar installation cannot be guaranteed. During construction, quality and safety problems such as steel bar deviation, poor steel bar skeleton connection effect, inadequate control of the spacing between the upper and lower steel bar meshes, overall unevenness of the upper mesh and difficulty in controlling the thickness of the concrete cover, and overall deviation of the main steel bars or large spacing deviation often occur.

[0016] 4. The implementation of the present invention solves the problem that the tunnel waterproofing board is easily burned during on-site welding of the secondary lining steel bars.

[0017] 5. The implementation of the present invention solves the problem that the number of lining stirrups is difficult to ensure due to the concrete pouring process. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0019] Figure 1 It is a bottom schematic diagram of the fully unfolded top arch and side arch of the steel mesh of the present invention.

[0020] Figure 2 It is a schematic diagram of the transportation of the steel mesh top arch and the steel mesh side arch of the present invention.

[0021] Figure 3 It is a side schematic diagram of the fully unfolded top arch and side arch of the steel mesh of the present invention.

[0022] Among them, in the figure:

[0023] 1- Steel mesh top arch; 2- Steel mesh side arch; 3- Main arm; 4- Left auxiliary arm; 5- Right auxiliary arm. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0025] Please see attached Figure 1-3 The present invention provides a construction method using a tunnel secondary lining steel mesh and an arch frame installation integrated machine, comprising the following steps:

[0026] S1. First, the two ends of the steel mesh top arch 1 are rotated and connected to a steel mesh side arch 2 through a pin and a pin sleeve to form a tunnel second lining steel mesh, and the two steel mesh side arches 2 are rotated inward to overlap each other, so that the two steel mesh side arches 2 are movably connected;

[0027] S2, then lift the steel mesh top arch 1 through the main arm 3 on the arch frame installation integrated machine, move the tunnel secondary lining steel mesh to the area to be constructed, and raise the tunnel secondary lining steel mesh to a suitable position by raising the main arm 3;

[0028] S3, release the movable connection between the two steel mesh side arches 2, use the left auxiliary arm 4 and the right auxiliary arm 5 to overlap the two steel mesh side arches 2 respectively, and stretch them outwards, so that the two steel mesh side arches 2 are fully unfolded around the steel mesh top arch 1;

[0029] S4. Adjust the positions of the main arm 3, the left auxiliary arm 4 and the right auxiliary arm 5 so that the steel mesh top arch 1 and the two steel mesh side arches 2 are close to the inner wall of the tunnel, and manually fix the tunnel secondary lining steel mesh to complete the installation.

[0030] The arch frame installation integrated machine is a construction vehicle, and the main arm 3, the left auxiliary arm 4 and the right auxiliary arm 5 are all rotatably connected to the arch frame installation integrated machine. A clamping mechanism can be installed on the main arm 3, the left auxiliary arm 4 and the right auxiliary arm 5 to clamp the steel mesh top arch 1 and the steel mesh side arch 2 to prevent the tunnel secondary lining steel mesh from sliding and shifting during the lifting process.

[0031] The main arm 3, the left auxiliary arm 4 and the right auxiliary arm 5 are all multi-section hydraulic telescopic arms, so as to shorten the vehicle length of the arch frame installation integrated machine while ensuring the lifting height.

[0032] The present invention has a simple structure and is easy to use. First, the two ends of the steel mesh top arch 1 are rotated to connect a steel mesh side arch 2 through a pin and a pin sleeve to form a tunnel secondary lining steel mesh, and the two steel mesh side arches 2 are rotated inward to overlap each other, so that the two steel mesh side arches 2 are movably connected; then the steel mesh top arch 1 is lifted by the main arm 3 on the arch frame installation integrated machine, and the tunnel secondary lining steel mesh is moved to the area to be constructed, and the tunnel secondary lining steel mesh is raised to a suitable position by raising the main arm 3; the active connection between the two steel mesh side arches 2 is released, and the left auxiliary arm 4 and the left auxiliary arm 4 are used to install the steel mesh top arch 1. The right auxiliary arm 5 is overlapped with the two steel mesh side arches 2 respectively and stretched outwards so that the two steel mesh side arches 2 are fully unfolded around the steel mesh top arch 1; the positions of the main arm 3, the left auxiliary arm 4 and the right auxiliary arm 5 are adjusted so that the steel mesh top arch 1 and the two steel mesh side arches 2 are close to the inner wall of the tunnel, and the tunnel secondary lining steel mesh is fixed manually to complete the installation. Therefore, the present invention has the advantages of high mechanization, labor saving, avoiding the problem that the steel bars are dragged on the tunnel ground and easily contaminated by oil stains, muddy water, etc., ensuring the accuracy and quality of the steel bar installation, and the steel bars can be quickly installed in pieces.

[0033] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.

[0034] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A construction method using a tunnel secondary lining steel mesh and an arch frame installation integrated machine, characterized in that: The following steps are involved: S1. First, the two ends of the steel mesh top arch (1) are rotated and connected to a steel mesh side arch (2) by means of a pin and a pin sleeve to form a tunnel secondary lining steel mesh, and the two steel mesh side arches (2) are rotated inwards to overlap each other, so that the two steel mesh side arches (2) are movably connected; S2, then lift the steel mesh top arch (1) by the main arm (3) on the arch frame installation integrated machine, move the tunnel secondary lining steel mesh to the area to be constructed, and raise the tunnel secondary lining steel mesh to a suitable position by raising the main arm (3); S3, releasing the movable connection between the two steel mesh side arches (2), using the left auxiliary arm (4) and the right auxiliary arm (5) to overlap the two steel mesh side arches (2) respectively, and stretching them outwards, so that the two steel mesh side arches (2) are fully unfolded around the steel mesh top arch (1); S4. Adjust the positions of the main arm (3), the left auxiliary arm (4) and the right auxiliary arm (5) so that the steel mesh top arch (1) and the two steel mesh side arches (2) are in close contact with the inner wall of the tunnel, and manually fix the tunnel secondary lining steel mesh to complete the installation.

2. A construction method using a tunnel secondary lining steel mesh and an arch frame installation integrated machine according to claim 1, characterized in that: The arch frame installation integrated machine is an engineering construction vehicle, and the main arm (3), the left auxiliary arm (4) and the right auxiliary arm (5) are all rotatably connected to the arch frame installation integrated machine.