High-water-level operation pipe network rain and sewage mixed connection point positioning algorithm based on uncertainty method

By applying the uncertainty method in the drainage pipe network, the pipe network model and probability distribution are established, which solves the problem of insufficient positioning accuracy of rainwater and sewage mixing junctions during high water level operation, and achieves more efficient and accurate mixing junction positioning and probability analysis. .

CN118733952AInactive Publication Date: 2024-10-01TIANJIN UNIV

Patent Information

Application Number
CN202410794848.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-19
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology is difficult to accurately locate the rainwater and sewage mixed junctions in the drainage pipe network under high water level operation conditions. In particular, the positioning accuracy is affected by the density of monitoring points, and traditional methods are costly or inefficient.

Method used

An algorithm for locating rainwater and sewage mixed joints in high water level operating pipe networks based on uncertainty method is adopted. Monitoring points are arranged in the study area, a pipe network model is established, a priori probability distribution of mixing parameters is generated, plans are randomly generated, and posterior statistical analysis is performed Probability distribution, and then determine the mixing situation.

Benefits of technology

It improves the positioning accuracy of rain and sewage mixed junctions, can calculate the mixing probability of all inspection wells through partial monitoring point data, quantitatively determine the number and location of mixed junctions, and reduces detection costs and time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118733952A_ABST
    Figure CN118733952A_ABST
Patent Text Reader

Abstract

The invention discloses a high-water-level operation pipe network rainwater and sewage mixed joint positioning algorithm based on an uncertainty method. The method comprises the following steps: S1, arranging a plurality of monitoring points in a rainwater pipe network in a research area, and obtaining a plurality of indication indexes based on the plurality of monitoring points; s2, establishing a pipe network model b based on related information and mixed connection parameters of the rainwater pipe network in the research area; s3, operating the pipe network model b to obtain an operation result, and comparing the result with an actually measured indication index value to obtain a current mixed connection scheme and a current operation result of which the coincidence degree meets a judgment condition; s4, circularly executing the steps S2-S3 to obtain a plurality of mixed connection schemes; performing statistical analysis on the plurality of mixed connection schemes to obtain posterior probability distribution of different mixed connection parameter values in the drainage pipe network; and S5, based on the posterior probability distribution of different mixed connection parameter values, determining the mixed connection condition to obtain a determination result.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of rainwater-sewage mixed connection investigation and diagnosis in drainage pipe networks, and in particular to an algorithm for locating rainwater-sewage mixed connection points in high-water-level operation pipe networks based on an uncertainty method. Background Art

[0002] The operation status of the drainage network is directly related to the city's environmental quality and the quality of life of residents. Due to historical reasons, different construction standards, and improper management and maintenance, the problem of rainwater and sewage mixing in the drainage network has become increasingly prominent, especially when operating at high water levels. This not only increases the pressure on the drainage network, but may also cause sewage to be directly discharged into the water, causing environmental pollution.

[0003] Traditional methods for locating rainwater-sewage mixing points mainly rely on manual inspections, CCTV detection, and water quality characteristic factor methods. Although manual inspections are intuitive, they are inefficient and limited by the experience and skill level of the staff; although CCTV detection can accurately locate mixing points, it requires placing cameras in the pipes, which is complicated and costly to operate. In addition, for drainage networks operating at high water levels, CCTV detection costs are relatively high; the water quality characteristic factor method measures certain characteristic parameters in sewage, such as COD, ammonia nitrogen, total phosphorus, isotopes, etc., to infer the water quality characteristics of external water, and judge whether there are rainwater-sewage mixing points in the pipe network based on this. It does not require direct physical inspection of the pipes, is easy to operate, and has relatively low costs. However, the positioning accuracy of the water quality characteristic factor method for mixing points is affected by the density of the monitoring point layout, and can only infer the mixing situation between two monitoring points or in their upstream pipes. The positioning accuracy is insufficient and cannot be accurate to a certain section of the pipe or a certain pipe well. Summary of the invention

[0004] In order to solve the above technical problems, the present invention proposes a high water level operation pipe network rainwater and sewage mixing point positioning algorithm based on uncertainty method to solve the above problems existing in the prior art.

[0005] To achieve the above object, the present invention provides a high water level operation pipe network rainwater and sewage mixing point positioning algorithm based on uncertainty method, comprising:

[0006] S1. Arrange a number of monitoring points in the rainwater pipe network in the study area and obtain a number of indicator indicators based on the monitoring points;

[0007] S2. Establishing a pipe network model b based on the relevant information and mixing parameters of the rainwater pipe network in the study area;

[0008] S3, running the pipe network model b to obtain an operation result, and comparing the result with the actual measured indicator value to obtain the current hybrid connection scheme and the current operation result whose compliance degree meets the judgment condition;

[0009] S4, looping through S2-S3 to obtain a number of hybrid schemes; performing statistical analysis on the hybrid schemes to obtain a posterior probability distribution of different hybrid parameter values ​​in the drainage network;

[0010] S5. Determine the mixing situation based on the posterior probability distribution of the different mixing parameter values ​​to obtain a determination result.

[0011] Optionally, a number of monitoring points are arranged in the stormwater pipe network of the study area with a density of 50%.

[0012] Optionally, some of the indicator indicators include but are not limited to isotopes, COD, ammonia nitrogen, total phosphorus and mixing rate calculated using water quality characteristic factors.

[0013] Optionally, the process of establishing the pipe network model b based on the relevant information and hybrid parameters of the rainwater pipe network in the study area includes:

[0014] Establishing a pipe network model a based on the relevant information of the rainwater pipe network in the study area;

[0015] Set a prior probability distribution for each mixing parameter;

[0016] Randomly generating a pipe network hybrid scheme including different hybrid parameters based on the prior probability distribution;

[0017] A pipeline network model b is established based on the pipeline network hybrid solution and the pipeline network model a.

[0018] Optionally, the relevant information of the rainwater pipe network in the study area includes but is not limited to the drainage pipe network length, pipe diameter, pipe bottom elevation, well bottom elevation, well depth, and pipe connection relationship.

[0019] Optionally, the establishment platform of the pipe network model a is SWMM.

[0020] Optionally, the different mixing parameters include but are not limited to the number of inlets, the number of outlets, the inlet locations, the outlet locations, the total mixing volume and the inflow volume of each inlet.

[0021] Optionally, the prior probability distribution of different hybrid parameters is a normal distribution or a discrete probability distribution.

[0022] Optionally, the process of determining the mixing situation based on the posterior probability distribution of different mixing parameter values ​​includes:

[0023] For the mixing parameters whose probability distribution is normal distribution, the normal distribution mean of the mixing parameters is used as the mixing value; wherein the mixing parameters whose probability distribution is normal distribution include: the number of inlets, the number of outlets, the total mixing amount and the inflow amount of each inlet;

[0024] For the mixing parameters whose probability distribution is a discrete probability distribution, a probability baseline for determining potential mixing points is set, and points whose probability corresponding to the mixing parameters is greater than the probability baseline are determined as potential mixing points; among them, the mixing parameters whose probability distribution is a discrete probability distribution include inlet points and outlet points.

[0025] Compared with the prior art, the present invention has the following advantages and technical effects:

[0026] The method for locating rainwater-sewage mixing points in a drainage network operating at a high water level based on an uncertainty algorithm proposed in the present invention solves the problem that the positioning accuracy of mixing points by the water quality characteristic factor method in the existing rainwater-sewage mixing diagnosis technology is affected by the density of monitoring point layout. Compared with the water quality characteristic factor method used alone, the algorithm has a higher positioning accuracy for mixing points, and the mixing probability of all drainage network inspection wells can be calculated through partial monitoring point data without the need for full sampling and detection. At the same time, the method can also obtain the probability of all inspection wells being mixed inlets and mixed outlets, and can quantitatively determine the number of mixing points, the location of potential mixing points, and their corresponding mixing amounts. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] The drawings constituting a part of the present application are used to provide a further understanding of the present application. The illustrative embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:

[0028] Figure 1 A technical roadmap of a high-water-level operation pipe network rainwater-sewage mixing point positioning algorithm based on an uncertainty method according to an embodiment of the present invention;

[0029] Figure 2 It is a SWMM pipe network model diagram of a high water level rainwater pipe network in an embodiment of the present invention;

[0030] Figure 3 The distribution of inlet probability and the inlet probability baseline diagram in the algorithm calculation result of the embodiment of the present invention;

[0031] Figure 4 The figure shows the distribution of outflow probability and the outflow probability baseline diagram in the algorithm calculation result of the embodiment of the present invention. DETAILED DESCRIPTION

[0032] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0033] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0034] Embodiment 1

[0035] like Figure 1 As shown, in this embodiment, a high-water-level operation pipe network rainwater-sewage mixing point positioning algorithm based on an uncertainty method is provided, including the following steps: a certain density of monitoring points are arranged in the rainwater pipe network in the study area; a number of indicator values ​​of each monitoring point are obtained; a drainage pipe network model a is established on a computer; a priori probability distribution of mixing parameters is set; a pipe network mixing scheme containing different mixing parameters is randomly generated according to the prior probability; the mixing scheme is generalized into the established pipe network model a to obtain the pipe network model b; the pipe network model b is run on a computer; the indicator value of each monitoring point in the running result of the pipe network model b is compared with the indicator value obtained by actual measurement; the mixing scheme and its running results whose compliance degree meets the judgment conditions are recorded; the mixing parameters in the recorded mixing scheme are statistically analyzed to obtain the posterior probability distribution of different mixing parameter values ​​in the drainage pipe network; the mixing situation is judged according to the probability distribution values ​​of different mixing parameter values. In view of the problem that the positioning accuracy of the mixing point of the water quality characteristic factor method in the existing rainwater-sewage mixing diagnosis technology is affected by the density of the monitoring point layout, the present invention proposes a rainwater-sewage mixing point positioning algorithm for high-water-level operation pipe networks based on uncertainty methods. This method applies two uncertainty methods, Monte Carlo and Bayesian, and presents the determination of the amount of rainwater-sewage mixing and the mixing points in the drainage network in the form of a posterior probability distribution. Compared with the use of the water quality characteristic factor method alone, the algorithm has higher positioning accuracy for the mixing points, and the mixing probability of all drainage network inspection wells can be calculated through partial monitoring point data without the need for full sampling and detection. At the same time, the method can also obtain the probability of all inspection wells as mixing inlets and mixing outlets, and can quantitatively determine the number of mixing points, the location of potential mixing points and their corresponding mixing amounts. Specifically, it includes the following steps:

[0036] Step 1: Set up a certain density of monitoring points in the drainage network of the study area; the density of monitoring points set up in the drainage network of the study area is 50%.

[0037] Step 2: Obtain several indicator values ​​for each monitoring point; several indicator values ​​include water quality characteristic factors such as isotopes, COD, ammonia nitrogen, total phosphorus, or the mixing rate calculated using a certain water quality characteristic factor.

[0038] The process of obtaining a number of indicator indicators at each monitoring point includes: selecting one or more indicator indicators; sampling each monitoring point to obtain one or more indicator indicator values ​​in the water sample of the monitoring point.

[0039] Step 3: Generalize the relevant information of the drainage network in the study area and establish a SWMM network model a on the computer; the relevant information of the drainage network in the study area includes the drainage network pipe length, pipe diameter, pipe bottom elevation, well bottom elevation, well depth, pipeline connection relationship, etc.

[0040] Step 3: Set a priori probability distribution for each mixing parameter; different mixing parameters include the number of inlets, the number of outlets, the inlet locations, the outlet locations, the total mixing volume, and the inflow volume of each inlet.

[0041] Step 4: randomly generate a pipe network hybrid scheme containing different hybrid parameters according to a priori probability;

[0042] Step 5: Generalize the hybrid scheme into the established pipe network model a to obtain a new SWMM pipe network model b;

[0043] Step 6: Run the pipe network model b on the computer;

[0044] Step 7: Compare the indicator value of each monitoring point in the operation result of the pipe network model b with the indicator value obtained by actual measurement, and use the total relative error less than a given value to determine the degree of conformity with the actual situation;

[0045] Step 8: Record the hybrid schemes whose total relative error is less than a given value and their operation results;

[0046] Step 9: After a certain number of recorded schemes are met, statistical analysis is performed on the mixed parameters in the recorded mixed schemes to obtain the posterior probability distribution of different mixed parameter values ​​in the drainage network.

[0047] Step 10: Determine the mixing situation according to the probability distribution values ​​of different mixing parameter values.

[0048] The process of determining the mixing situation according to the probability distribution values ​​of different mixing parameter values ​​includes: for mixing parameters with normal probability distribution, such as the number of inlets, the number of outflow outlets, the total mixing amount and the inflow amount of each inlet, the normal distribution mean is used as the mixing value; for mixing parameters with discrete probability distribution, such as the inlet point and the outflow point, a probability baseline for determining potential mixing points is set, and points with probability greater than the baseline value are determined as potential mixing points.

[0049] In view of the problem that the positioning accuracy of the mixing point of the water quality characteristic factor method in the existing rainwater-sewage mixing diagnosis technology is affected by the density of the monitoring point layout, the present invention proposes a rainwater-sewage mixing point positioning algorithm for high-water-level operation pipe networks based on uncertainty methods. The method applies two uncertainty methods, Monte Carlo and Bayesian, and presents the determination of the amount of rainwater-sewage mixing and the mixing points in the drainage network in the form of posterior probability distribution. Compared with the use of the water quality characteristic factor method alone, the algorithm has higher positioning accuracy for the mixing points, and can calculate the mixing probability of all drainage network inspection wells through partial monitoring point data without the need for full sampling and detection. At the same time, the method can also obtain the probability of all inspection wells as mixing inlets and mixing outlets, and can quantitatively determine the number of mixing points, the location of potential mixing points and their corresponding mixing amounts.

[0050] Embodiment 2

[0051] like Figure 2-Figure 4 As shown, this example takes a high-water-level rainwater pipe network as an example, and measures the sewage mixing volume and locates the mixing points of the rainwater pipe network, including: S1. Arrange a number of monitoring points in the rainwater pipe network in the study area and obtain a number of indicator indicators based on the monitoring points; S2. Establish a pipe network model b based on the relevant information and mixing parameters of the rainwater pipe network in the study area; S3. Run the pipe network model b to obtain the operation results, and compare the results with the actual measured indicator values ​​to obtain the current mixing scheme and the current operation results that meet the judgment conditions; S4. Execute S2-S3 in a loop to obtain a number of mixing schemes; perform statistical analysis on a number of mixing schemes to obtain the posterior probability distribution of different mixing parameter values ​​in the drainage pipe network; S5. Determine the mixing situation based on the posterior probability distribution of different mixing parameter values ​​to obtain the judgment result. The specific implementation process is as follows:

[0052] Step 1: Set up a certain density of monitoring points in the rainwater pipe network in the study area, and the monitoring points account for 45% of the total number of rainwater inspection wells;

[0053] Step 2: Obtain the sewage mixing rate of each monitoring point;

[0054] Step 3: Generalize the relationship between the length, diameter, bottom elevation, well bottom elevation, well depth, and pipe connection of the rainwater pipe network in the study area and establish a SWMM pipe network model on the computer, such as Figure 2 As shown;

[0055] Step 3: Set a priori probability distribution for each mixing parameter, using normal distribution or discrete probability distribution; different mixing parameters include the number of inlets, the number of outlets, the inlet locations, the outlet locations, the total mixing volume, and the inflow volume of each inlet.

[0056] Step 4: randomly generate a pipe network hybrid scheme containing different hybrid parameters according to a priori probability;

[0057] Step 5: Generalize the hybrid scheme into the established pipe network model a to obtain a new SWMM pipe network model b;

[0058] Step 6: Run SWMM pipe network model b;

[0059] Step 7: Compare the mixed connection rate of each monitoring point in the operation results of SWMM pipe network model b with the mixed connection rate obtained by actual measurement, and use the total relative error less than 0.5 as the judgment condition of the degree of compliance;

[0060] Step 8: Record the hybrid schemes with a total relative error less than 0.5 and their operation results;

[0061] Step 9: After 1000 recorded schemes are met, statistical analysis is performed on the mixed connection parameters in the recorded mixed connection schemes to obtain the posterior probability distribution of different mixed connection parameter values ​​in the drainage network.

[0062] Step 10: Determine the mixing situation according to the probability distribution values ​​of different mixing parameter values. The process of determining the mixing situation according to the probability distribution values ​​of different mixing parameter values ​​includes: for mixing parameters with normal probability distribution, such as the number of inlets, the number of outlets, the total mixing volume and the inflow volume of each inlet, the mean of the normal distribution is used as the mixing value; for mixing parameters with discrete probability distribution, such as the inlet point and the outflow point, the probability baseline for determining potential mixing points is set, and the points with probability greater than the baseline value are determined as potential mixing points.

[0063] The results show that the normal distribution mean of the total mixed inflow of the high water level operating rainwater pipe network is 144m3 / d, and the standard deviation is 40m3 / d; the normal distribution mean of the number of mixed inflow outlets is 7.27, and the standard deviation is 1.20; the normal distribution mean of the number of mixed outflow outlets is 9.40, and the standard deviation is 1.81; there are 17 potential mixed inflow outlets and 17 potential mixed outflow outlets, such as Figure 3 , Figure 4 As shown in the figure, there are two overlapping points between the potential mixed inflow and the potential mixed outflow, so there are 32 mixed points in the rainwater pipe network. The exploration results verify that among these 32 potential mixed points, the actual mixed points account for at least 47%.

[0064] The above are only preferred specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. An algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty methods, characterized in that: The following steps are involved: S1. Arrange a number of monitoring points in the rainwater pipe network in the study area and obtain a number of indicator indicators based on the monitoring points; S2. Establishing a pipe network model b based on the relevant information and mixing parameters of the rainwater pipe network in the study area; S3, running the pipe network model b to obtain an operation result, and comparing the result with the actual measured indicator value to obtain the current hybrid connection scheme and the current operation result whose compliance degree meets the judgment condition; S4, looping through S2-S3 to obtain a number of hybrid schemes; performing statistical analysis on the hybrid schemes to obtain a posterior probability distribution of different hybrid parameter values ​​in the drainage network; S5. Determine the mixing situation based on the posterior probability distribution of the different mixing parameter values ​​to obtain a determination result.

2. The algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty method according to claim 1 is characterized in that: The density of several monitoring points arranged in the rainwater pipe network in the study area is 50%.

3. The high water level operation pipe network rainwater and sewage mixing point positioning algorithm based on uncertainty method according to claim 1 is characterized in that: Some of the indicators include but are not limited to isotopes, COD, ammonia nitrogen, total phosphorus and mixing rate calculated using water quality characteristic factors.

4. The algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty method according to claim 1 is characterized in that: The process of establishing the pipe network model b based on the relevant information and hybrid parameters of the rainwater pipe network in the study area includes: Establishing a pipe network model a based on the relevant information of the rainwater pipe network in the study area; Set a prior probability distribution for each mixing parameter; Randomly generating a pipe network hybrid scheme including different hybrid parameters based on the prior probability distribution; A pipeline network model b is established based on the pipeline network hybrid solution and the pipeline network model a.

5. The algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty method according to claim 4 is characterized in that: The relevant information of the rainwater pipe network in the study area includes but is not limited to the length, diameter, bottom elevation, well bottom elevation, well depth and pipe connection relationship of the drainage network.

6. The algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty method according to claim 4 is characterized in that: The establishment platform of the pipe network model a is SWMM.

7. The algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty method according to claim 4 is characterized in that: The different mixing parameters include but are not limited to the number of inlets, the number of outlets, the positions of inlets, the positions of outlets, the total mixing volume and the inflow volume of each inlet.

8. The algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty method according to claim 4 is characterized in that: The prior probability distribution of different hybrid parameters is normal distribution or discrete probability distribution.

9. The algorithm for locating rainwater-sewage mixing points in high-water-level operation pipe networks based on uncertainty method according to claim 8 is characterized in that: The process of determining the mixing situation based on the posterior probability distribution of different mixing parameter values ​​includes: For the mixing parameters whose probability distribution is normal distribution, the normal distribution mean of the mixing parameters is used as the mixing value; wherein the mixing parameters whose probability distribution is normal distribution include: the number of inlets, the number of outlets, the total mixing amount and the inflow amount of each inlet; For the mixing parameters whose probability distribution is a discrete probability distribution, a probability baseline for determining potential mixing points is set, and points whose probability corresponding to the mixing parameters is greater than the probability baseline are determined as potential mixing points; among them, the mixing parameters whose probability distribution is a discrete probability distribution include inlet points and outlet points.

Citation Information

Patent Citations

  • A Bayesian statistical traceability method for discharging industrial waste water exceeding the standard of sewage pipe network

    CN108897964A

  • Drainage pipe network monitoring point arrangement method based on information entropy

    CN113836673A

Cited By

  • Method and system for positioning sewage mixing point of rainwater pipe network in high water level operation

    CN122904804A