Low-carbon plan scheduling method for ship segmented coating

By establishing a multi-objective mathematical model and an improved artificial bee colony algorithm, the ship segmented painting schedule is optimized, which solves the problems of energy saving and carbon emissions, realizes a low-carbon schedule for ship segmented painting, and ensures time , workload and carbon emissions balance.

CN118735146AActive Publication Date: 2024-10-01SHANGHAI JIAOTONG UNIV

Patent Information

Application Number
CN202310333991.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-01
Estimated Expiration
2043-03-30

AI Technical Summary

Technical Problem

There are challenges in energy conservation and carbon emissions in ship segmented painting. It is difficult to effectively optimize production schedules with existing technology to reduce energy consumption and carbon emissions. At the same time, human resource allocation issues need to be considered.

Method used

Establish a multi-objective mathematical model, adopt an improved artificial bee colony algorithm that mixes greedy random adaptive search algorithm and variable neighborhood search algorithm, express the planning and scheduling results through a three-dimensional coding method, optimize the process sequence, team allocation and personnel allocation to ensure the maximum Minimization of makespan, unbalanced workload and carbon emissions.

Benefits of technology

Obtaining an approximately optimal solution within a reasonable time improves the efficiency and effectiveness of the ship's segmented painting schedule and achieves a two-week schedule that comprehensively considers completion time, workload and carbon emissions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735146A_ABST
    Figure CN118735146A_ABST
Patent Text Reader

Abstract

The invention discloses a plan scheduling method for ship segmented coating, which considers the problem of low-carbon ship segmented coating plan scheduling of electric energy consumed by VOCs waste gas treatment equipment and carbon emission brought by LNG gas, considers the constraint of human resources, and establishes a multi-schedule plan scheduling model comprising two tasks of sand washing and spraying. An improved artificial bee colony algorithm is provided to effectively obtain an approximate optimal solution within reasonable time, and a three-dimensional coding solution scheme mechanism is designed based on a model. The greedy random adaptive search algorithm and the variable neighborhood search algorithm are mixed in the algorithm, so that the search efficiency of the algorithm is improved, and the method can be well used for the ship segmented coating plan scheduling problem.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of shipbuilding, and in particular to a low-carbon planning and scheduling method for ship section painting. Background Art

[0002] How to reduce environmental pollution and achieve green manufacturing has become one of the urgent problems to be solved in modern manufacturing. Planning is a key link in the manufacturing system, and production planning and scheduling is an effective way to save energy in the manufacturing industry. By selecting different workshops or machines and optimizing the production planning sequence, energy saving can be achieved without increasing additional energy consumption. More and more scholars are committed to the study of energy saving in production planning and scheduling, and have achieved many results.

[0003] Ship painting is a labor-intensive production system. Compared with the classic scheduling problem, the scheduling problem of ship section painting needs to consider the allocation of human resources. At the same time, with the advancement of green ship technology and concepts, VOCs treatment equipment is the main energy-consuming equipment in the ship painting production process. The electricity consumed by its operation and LNG gas have become the main sources of carbon emissions in painting operations. Therefore, it is of great practical significance to study the scheduling problem of low-carbon ship section painting. Summary of the invention

[0004] The present invention provides a low-carbon planning and scheduling method for ship block painting, which can quickly obtain a two-week planning and scheduling arrangement that comprehensively considers the three goals of completion time, unbalanced workload and carbon emissions.

[0005] In order to achieve the above objectives, the present invention provides a low-carbon planning and scheduling method for ship section painting, which comprises:

[0006] Establish a multi-objective mathematical model for ship section painting scheduling with regard to maximum completion time, unbalanced workload and carbon emissions;

[0007] The planning and scheduling results are represented by a three-dimensional coding method including process sequence vector, team allocation vector and personnel allocation vector.

[0008] The improved artificial bee colony algorithm which mixed greedy random adaptive search algorithm and variable neighborhood search algorithm was used to solve the mathematical model of multi-objective ship section painting planning and scheduling to obtain the final planning and scheduling result.

[0009] A further improvement of the present invention is that in the process of solving the multi-objective ship segment painting plan scheduling mathematical model, the minimum maximum completion time, the minimum unbalanced workload and the minimum carbon emission are the solution objectives.

[0010] A further improvement of the present invention is that the constraints of the multi-objective ship segment painting plan scheduling mathematical model include:

[0011] Each process can and can only be managed by one team;

[0012] The sum of the specific number of workers assigned to each team is less than the total number of workers;

[0013] Priority relationship constraints between processes;

[0014] The previous and next processes in the same section must wait for at least the lower limit of the drying time of the previous process;

[0015] The start day of a segment and the completion day of the last process must be within the time window given for the segment.

[0016] A further improvement of the present invention is that: in the process sequence vector, each element is a process number, and the position of the element in the process sequence vector represents the execution order of the corresponding process;

[0017] The elements of the team allocation vector correspond to the process sequence vector one by one, and each element represents the corresponding team of the corresponding process in the process sequence vector;

[0018] Each element in the personnel allocation vector represents a team, and the value of the element represents the actual number of workers in the team.

[0019] A further improvement of the present invention is that the improved artificial bee colony algorithm includes an initialization phase, a hiring phase, a following phase and a reconnaissance phase.

[0020] A further improvement of the present invention is that a greedy random adaptive search algorithm is used in the initialization phase of the improved artificial bee colony algorithm, which specifically includes:

[0021] First, randomly generate multiple groups of personnel allocation vectors and corresponding process sequence vectors; check each group of vectors, and if they do not meet the constraints, adjust the vectors to meet the constraints;

[0022] For each group of vectors, one is selected from the three solution objectives. According to the selected solution objective, the team assignment vector of the group of vectors is constructed through the greedy random adaptive algorithm. If the constructed team assignment vector does not meet the constraints, the team assignment vector is adjusted to meet the constraints and the corresponding solution is obtained. Finally, each solution is optimized through neighborhood search.

[0023] A further improvement of the present invention is that in the employed bee stage of the improved artificial bee colony algorithm, a crossover operator between solutions is used to enhance the diversity of population search.

[0024] A further improvement of the present invention is that in the following bee stage of the improved artificial bee colony algorithm, a VNS method is used to perform neighborhood search to improve the local search capability.

[0025] The further improvement of the present invention is that in the scout bee stage of the improved artificial bee colony algorithm, new solutions are freely found through greedy random adaptive search. The scheme of the present invention has the following technical effects: the method can effectively obtain an approximate optimal solution within a reasonable time, and a three-dimensional coded solution mechanism is designed based on the model. The greedy random adaptive search algorithm and the variable neighborhood search algorithm are mixed in the algorithm, which increases the search efficiency of the algorithm and can be better used for the ship segment painting plan scheduling problem.

[0026] The concept, specific structure and technical effects of the present invention will be further described below in conjunction with the accompanying drawings to fully understand the purpose, characteristics and effects of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 is a flow chart of the algorithm of the present invention;

[0028] Figure 2 This is the LNG gas consumption variation curve during the spraying process;

[0029] Figure 3 A schematic diagram of a three-dimensional vector representation method for scheduling results;

[0030] Figure 4 It is a schematic diagram of the disassembly, reorganization and mutation in the employment stage;

[0031] Figure 5 These are the eight neighborhood search operators included in VNS in three dimensions.

[0032] Figure 6 It is a Gantt chart of scheduling results. DETAILED DESCRIPTION

[0033] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the following embodiments and features in the embodiments can be combined with each other without conflict.

[0034] It should be noted that the illustrations provided in the following embodiments are only used to illustrate the basic concept of the present invention in a schematic manner, and thus the illustrations only show components related to the present invention rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed arbitrarily, and the component layout may also be more complicated.

[0035] While some exemplary embodiments of the present invention have been described for the purpose of illustration, it should be understood that the present invention may be implemented in other ways not specifically shown in the drawings.

[0036] like Figure 1 As shown, an embodiment of the present invention provides a low-carbon planning and scheduling method for ship section painting, comprising:

[0037] The problem is defined as follows: in the ship section painting scheduling problem, the ship section must complete the first process of the sandblasting process by the sandblasting team, and then the spraying team will complete the subsequent processes of the spraying process. The section may have 2-5 spraying processes depending on the needs. The different numbers of workers assigned to the team will affect the team's operation rate, and the arrangement of the process sequence will also affect the workload of different teams. At the same time, when the spraying process is carried out every day, the VOCs waste gas treatment equipment must be turned on to treat the waste gas generated during the spraying process. For this reason, the present invention proposes a multi-objective mathematical model that comprehensively considers the maximum completion time, team workload balance and total carbon emissions.

[0038] The symbols and explanations of the numbers, sets, parameters and decision variables used in this model are shown in Table 1.

[0039] The three solution goals in the mathematical model are as follows:

[0040] (1) Completion time, expressed as follows:

[0041]

[0042] The completion time formula indicates that the solution goal 1 is to minimize the total completion time of all plans. All planned days before the last day are uniformly regarded as the maximum working time DH for calculation regardless of the actual completion time.

[0043] Table 1 Symbols in mathematical models

[0044]

[0045] (2) The imbalance of team work is expressed as follows:

[0046]

[0047]

[0048]

[0049] The formula for the unbalanced workload of the team indicates that the solution to goal 2 is to minimize the difference between the workload of each team and the average workload of the team to balance the overall workload. First, the average working hours of workers in each team are calculated as the workload of the team, and then the average of the workload of all teams is calculated to obtain the unbalanced workload.

[0050] (3) Total carbon emissions

[0051] The carbon emissions in the ship section painting production operation mainly come from the energy consumption of the VOCs waste gas treatment equipment in the spray workshop. The energy consumption includes electricity consumption and LNG gas consumption. The electricity consumption power is constant by default when the VOCs waste gas treatment equipment is turned on. The LNG gas consumption can be divided into three stages: the start stage, the stable stage and the end stage.

[0052] LNG gas consumption changes such as Figure 2 As shown, the red line indicates the start phase, the green line indicates the stable phase, and the blue line indicates the end phase. The start phase starts with the spraying operation, and the LNG gas combustion consumption rate increases as the VOCs gas concentration increases; the LNG gas consumption is constant in the stable phase; the end phase begins when all spraying tasks are completed on the day, and the VOCs waste gas treatment equipment continues to operate for a period of time. The LNG gas consumption rate first decreases and then becomes constant at the basic consumption rate, and finally the equipment is shut down and waits to be started when the spraying operation begins the next day.

[0053] The calculation formula for carbon emissions is as follows:

[0054] Min f3=ε·Q E +σ·Q LNG

[0055]

[0056]

[0057] The carbon emission formula indicates that the solution to goal 3 is to minimize the sum of carbon emissions from electricity consumption and carbon emissions from gas consumption. Based on the carbon emissions per kilowatt-hour of electricity consumption, e is generally set to 0.7559, and based on the carbon emissions per cubic meter of LNG gas combustion, σ is generally set to 2.1650. The total electricity consumption and the total cubic meters of LNG gas consumption are calculated separately and then added together. In this model, w is set according to the actual situation. E =20,w LNG1 =15,w LNG2 =30.

[0058] The constraints included in the mathematical model are as follows:

[0059] Each process can and can only be handled by one team, and the sandblasting process is the responsibility of the sandblasting team, and the spraying process is the responsibility of the spraying team. The constraint formula is as follows:

[0060]

[0061]

[0062]

[0063] The sum of the specific number of workers assigned to each team is less than the total number of workers. The constraint formula is as follows:

[0064]

[0065]

[0066] The actual time of the process in the model is obtained by dividing the total budgeted working hours of the process by the number of people in the team responsible for the process. The constraint formula is as follows:

[0067]

[0068] Each process has a start time and end time constraint. At the same time, each process must be completed within the maximum working time of the day. The priority relationship constraints between different processes are as follows:

[0069]

[0070]

[0071]

[0072]

[0073] The time sequence constraints at the workstations must be considered between the processes that the team is responsible for on the day. The constraint formula is as follows:

[0074]

[0075]

[0076]

[0077] The previous and next processes in the same segment must wait for at least the lower limit of the drying time of the previous process. The constraint formula is as follows:

[0078]

[0079] The starting day of a segment and the completion day of the last process must be within the time window given by the segment. The constraint formula is as follows:

[0080]

[0081]

[0082] An improved artificial bee colony algorithm (IABC) is proposed. The artificial bee colony algorithm (ABC) is a swarm intelligence optimization algorithm that simulates the honey-collecting mechanism of bees to solve multi-dimensional complex optimization problems. In the ABC algorithm, the location of each nectar source represents a feasible solution. Artificial bee colonies are divided into three categories: employed bees, follower bees, and scout bees. Employed bees will look for new nectar sources based on the nectar source information that has been discovered, follower bees will search around the nectar source based on the nectar source information shared by employed bees, and scout bees will freely search for new and valuable nectar sources through random search methods. Based on the idea of ​​the artificial bee colony algorithm, the present invention proposes an improved artificial bee colony algorithm, which is as follows:

[0083] In the initialization stage, a three-dimensional coding method is designed to generate an initial population with stable quality through the initialization strategy of Greedy Random Adaptive Search (GRASP). In the employed bee stage, the crossover operator between nectar sources is used to enhance the diversity of population search. In the follower bee stage, an effective variable neighborhood search (VNS) algorithm is designed to improve the local search ability of IABC. In the scout bee stage, the GRASP method is used to freely search for new nectar sources, which increases the globality of the search while preventing the bees from falling into a blind and random state. The algorithm flow chart is shown in the figure below. Figure 1 shown.

[0084] A three-dimensional coding method was designed. The three sub-problems involved in planning and scheduling: process scheduling, team arrangement and worker allocation. The determination of the three sub-problems can guarantee a unique solution. In order to effectively arrange computing resources, corresponding three-dimensional coding methods were designed for the three sub-problems based on the characteristics of the problem. The feasible solution code of SBPSP consists of three vectors: process sequence vector (PV), team allocation vector (GV) and personnel allocation vector (WV). The number of each element in PV is the process number, indicating the time relationship between all processes; the number of each element in GV is the team number, and the position of each element corresponds to the process number of the sequence to which the position belongs; the number of each element in WV is the actual number of workers in the team, and the position of each element corresponds to the team number of the sequence to which the position belongs. PV Figure 3 An example of a three-bit encoding method of the solution is shown.

[0085] In the initialization stage, a GRASP algorithm (greedy random adaptive search algorithm) is designed. First, WV and PV are randomly generated, and then the process that violates the process priority constraint is adjusted to after its predecessor process according to the model constraints, so as to adjust the PV to the PV that can find a feasible solution. At the same time, a target is randomly selected with medium probability among the three solution targets. One-third of the initial population adopts the search strategy of minimum completion time, one-third of the initial population adopts the search strategy of minimum job imbalance, and one-third of the initial population adopts the search strategy of minimum carbon emission. According to the selected target, the algorithm constructs GV through a greedy random adaptive algorithm, and finally finds a feasible solution that meets the constraints by adjusting GV. Finally, the solution found is optimized through neighborhood search. The search operator used in neighborhood search optimization is detailed in the VNS method of the follow-up bee stage.

[0086] In the hired bee stage, hired bees have to search among the discovered nectar sources in an attempt to find better nectar sources. Based on the three-dimensional coding method, a combination method between the solved codes is designed. For GV and PV, two different solution combination methods are proposed in combination with the characteristics of the problem, so as to improve the efficiency of hired bee search. At the same time, a mutation operator is introduced to WV to improve the search effectiveness of the algorithm, and hired bee searches are performed in these three dimensions. An example of a combination of GV (CGV), a combination of PV (CPV), and a variation of WV (MWV) is shown in Figure 1. Figure 4 shown.

[0087] In the following bee stage, the following bees search near the nectar source based on the nectar source information shared by the employed bees. The VNS method with strong search ability allows the employed bees to search more stably from the nectar source in its neighborhood, thereby ensuring that the nectar source can move in a better direction in each iteration. Based on the three-dimensional coding method, the present invention designs eight neighborhood search operators in the following bee stage. The VNS method uses these eight neighborhood search operators to perform neighborhood search in three dimensions: PV neighborhood search, GV neighborhood search, and PV neighborhood search. Figure 5 The eight neighborhood search operators included in VNS in three dimensions are shown. (a) to (d) are neighborhood searches for PV, including four types of PV neighborhood structure point exchange, PV neighborhood structure segment exchange, PV neighborhood structure insertion, and PV neighborhood structure flipping. (e) to (g) are neighborhood searches for GV, including three types of GV neighborhood structure partial exchange, GV neighborhood structure full exchange, and GV neighborhood structure change. The process of PV neighborhood structure reallocation is shown in (h), which allocates part of the flexible personnel of one team to another team within the feasible range.

[0088] In the scout bee stage, the scout bee calls the GRASP algorithm in each iteration to search for new nectar sources globally. If the scout bee finds a high-quality nectar source, it will be transformed into a follower bee to continue mining this nectar source. If a follower bee fails to find a new nectar source after Limit attempts in one iteration, it will temporarily transform into a scout bee to search globally and return to the follower bee identity at the beginning of the next iteration; if it fails to find a new nectar source in G_Limit iterations, it will be permanently transformed into a scout bee.

[0089] The algorithm will find an optimal non-dominated solution set, in which no two solutions are better than each other in each target dimension, which is called the Pareto front. A crowding distance judgment function is used, as shown in the following formula: 1 With f 2 Distance between:

[0090]

[0091] Each newly generated non-dominated solution is compared with the solution in the current Pareto front to decide whether to add this new solution. If the new non-dominated solution can dominate other solutions in the current Pareto front, these solutions are replaced and the new solution is inserted; if the new non-dominated solution cannot dominate other solutions in the Pareto front and the current Pareto front has reached the specified size, the Pareto front update operation is performed, and the calculation steps are as follows:

[0092] First, sort each target from small to large, count the maximum and minimum values ​​of the target, and normalize each target dimension and project it into the interval (0, 1); second, calculate the distance between any two solutions through the crowding distance judgment function; third, sort all solutions according to the crowding distance, and delete the solution with the smallest distance from the Pareto front.

[0093] The Gantt chart of a calculation result obtained by this algorithm is as follows: Figure 6 As shown in the figure, the time range of each planning and scheduling is about 13 days, which is in line with the current situation of the shipyard's two-week rolling planning and scheduling. Teams G1 and G2 belong to the sand team set G S , and teams G3 to G7 belong to the spraying team set G P At the beginning of the first day, the sandblasting team will first carry out the sandblasting operation. After a section has completed the sandblasting, the spraying team will immediately spray the section that has completed the sandblasting. It can be seen that the color and process blocks representing the same section are right after the sandblasting end time and next to the spraying start time.

[0094] The comparative analysis of this calculation example is shown in the following table. The present invention compares the IABC algorithm with NSGA-II, SS and ABC before improvement. The four algorithms are numerically tested on a total of 15 examples. Each example is run 10 times and the average of each evaluation index is taken. Three indicators are used in the evaluation of the algorithm results: mean ideal distance (MID), non-dominated solution dispersion (DNS) and inverse generation distance evaluation index (IGD). It can be seen that the IABC algorithm can be stably smaller than other algorithms in terms of MID and IGN, which means that the IABC algorithm has better solution performance.

[0095]

[0096] Although the embodiments disclosed in the present invention are as above, the above contents are only embodiments adopted for facilitating the understanding of the present invention and are not intended to limit the present invention. Any technician in the technical field to which the present invention belongs can make any modifications and changes in the form and details of the implementation without departing from the spirit and scope disclosed in the present invention, but the patent protection scope of the present invention shall still be subject to the scope defined in the attached claims.

Claims

1. A low-carbon planning and scheduling method for ship section painting, characterized in that include: Establish a multi-objective mathematical model for ship section painting scheduling based on maximum completion time, unbalanced workload and carbon emissions; The planning and scheduling results are represented by a three-dimensional coding method including process sequence vectors, team allocation vectors, and personnel allocation vectors; The improved artificial bee colony algorithm which mixed the greedy random adaptive search algorithm and the variable neighborhood search algorithm was used to solve the mathematical model of multi-objective ship section painting scheduling and obtain the final scheduling result.

2. A low-carbon planning and scheduling method for ship section painting according to claim 1, characterized in that In the process of solving the multi-objective ship section painting scheduling mathematical model, the solution objectives are to minimize the maximum completion time, minimize the unbalanced workload and minimize the carbon emissions.

3. A low-carbon planning and scheduling method for ship section painting according to claim 1, characterized in that: The constraints of the multi-objective ship section painting scheduling mathematical model include: Each process can and can only be managed by one team; The sum of the specific number of workers assigned to each team is less than the total number of workers; Priority relationship constraints between processes; The previous and next processes in the same section must wait for at least the lower limit of the drying time of the previous process; The start day of a segment and the completion day of the last process must be within the time window given for the segment.

4. A low-carbon planning and scheduling method for ship section painting according to claim 3, characterized in that: In the process sequence vector, each element is a process number, and the position of the element in the process sequence vector represents the execution order of the corresponding process; The elements of the team allocation vector correspond one-to-one to the process sequence vector, and each element represents the team corresponding to the corresponding process in the process sequence vector; Each element in the personnel allocation vector represents a team, and the value of the element represents the actual number of workers in the team.

5. A low-carbon planning and scheduling method for ship section painting according to claim 4, characterized in that: The improved artificial bee colony algorithm includes initialization phase, employment phase, following phase and reconnaissance phase.

6. A low-carbon planning and scheduling method for ship section painting according to claim 5, characterized in that: In the initialization phase of the improved artificial bee colony algorithm, a greedy random adaptive search algorithm is used, which specifically includes: First, multiple sets of personnel allocation vectors and corresponding process sequence vectors are randomly generated; each set of vectors is checked, and if they do not meet the constraints, the vectors are adjusted to meet the constraints; For each group of vectors, one of the three solution objectives is selected. According to the selected solution objective, the team assignment vector of the group of vectors is constructed through the greedy random adaptive algorithm. If the constructed team assignment vector does not meet the constraints, the team assignment vector is adjusted to make it meet the constraints and the corresponding solution is obtained. Finally, each solution is optimized through neighborhood search.

7. A low-carbon planning and scheduling method for ship section painting according to claim 5, characterized in that: In the employed bee stage of the improved artificial bee colony algorithm, the crossover operator between different solutions is used to enhance the diversity of population search.

8. A low-carbon planning and scheduling method for ship section painting according to claim 5, characterized in that: In the following bee stage of the improved artificial bee colony algorithm, the VNS method is used for neighborhood search to improve the local search capability.

9. A low-carbon planning and scheduling method for ship section painting according to claim 5, characterized in that: In the scout bee stage of the improved artificial bee colony algorithm, new solutions are freely found through greedy random adaptive search.

Citation Information

Patent Citations

  • Multi-target low-carbon flexible job shop scheduling method

    CN113780871A

  • Manufacturing industry intelligent production scheduling method based on deep learning

    CN113988674A

  • Optimizing apparatus, optimizing method, and storage medium

    US6651046B1

Cited By

  • Online resource allocation method and system based on multiplicative weight update

    CN120909763A

  • An online resource allocation method and system based on multiplicative weight update

    CN120909763B