Passenger ship power station control system and control method
Through the combination of the intelligent power management system and the alarm module, it automatically matches the fuel consumption rate curve of the generator set and handles the load excess situation, solving the problem of inefficiency caused by the difference in power demand of the passenger ship power station, and improving energy utilization efficiency and system reliability.
Patent Information
- Application Number
- CN202410755134.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2024-10-01
AI Technical Summary
The power demand of passenger ship power stations varies greatly at different time periods, making it difficult for the engines to maintain operation at the optimal efficiency point, resulting in low efficiency of the power station and waste of fuel.
Adopt an intelligent power management system to calculate load demand through preset data, automatically match the fuel consumption rate curve of the generator set, and activate the alarm module and non-important load trip processing when the load exceeds the range, optimizing the operating status and power distribution of the generator set .
It improves energy utilization efficiency, enhances system reliability and security, realizes intelligent management, reduces operating costs, and facilitates maintenance and expansion.
Smart Images

Figure CN118739323A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of electric control technology, and in particular to a passenger ship power station control system and control method. Background Art
[0002] On conventional civilian merchant ships, offshore engineering ships and passenger ships, the ship power station control system consists of engines, generators, switchboards and power management systems. Under normal working conditions, after the engine group drives the generator to generate electricity, the generated electricity is distributed to various equipment users through the distribution network composed of the switchboard. The control and distribution during this period are managed by the power management system.
[0003] At present, engines with fixed fuel consumption rate curve characteristics are usually used as prime movers in passenger ship power stations to drive generators to generate electricity, which is then distributed to users such as ship propulsion and air conditioning. Unlike conventional bulk cargo ships and container ships, there are more types of electrical users on passenger ships, and the power demand varies greatly in different time periods. Therefore, in the actual operation of the power station, the actual demand load may deviate greatly from the design load in some periods and working conditions, and it is difficult for the engine to maintain operation at or near the optimal efficiency point, resulting in low power station efficiency and fuel waste. Summary of the invention
[0004] In view of this, an embodiment of the present application provides a passenger ship power station control system and a control method, which can improve energy utilization efficiency.
[0005] The technical solution of the embodiment of the present application is implemented as follows:
[0006] In a first aspect, an embodiment of the present application provides a passenger ship power station control system, the passenger ship power station control system comprising:
[0007] a generator set consisting of an engine and a generator, a first switchboard, at least one load line and a power management system;
[0008] The output end of the generator set is connected to the input end of the switchboard, and the output end of the first switchboard is respectively connected to the input end of the at least one load line;
[0009] The generator set includes at least one fuel consumption rate curve, and the power management system is used to selectively adjust the fuel consumption rate curve of the generator set;
[0010] When the power management system is in operation, a target fuel consumption rate curve is selected from the at least one fuel consumption rate curve to meet the load demand of the passenger ship.
[0011] In a possible implementation manner, the at least one load line includes: a first load line and a second load line;
[0012] The first load circuit includes a propulsion transformer, a propulsion inverter and a propulsion motor;
[0013] The second load circuit includes a daily transformer and a second distribution board, and the distribution voltage of the second distribution board is lower than the distribution voltage of the first distribution board;
[0014] The output end of the first distribution board is connected to the input end of the propulsion transformer and the input end of the daily transformer respectively; the output end of the propulsion transformer is connected to the input end of the propulsion inverter, and the output end of the propulsion inverter is connected to the input end of the propulsion motor; the output end of the daily transformer is connected to the input end of the second distribution board.
[0015] In a possible implementation manner, the number of the generator sets is at least 4, and each generator set consists of 1 engine and 1 generator.
[0016] In a possible implementation, the first distribution board includes a front distribution board and a rear distribution board, the output ends of at least some of the generator sets are connected to the input ends of the front distribution board, and the output ends of the remaining generator sets are connected to the input ends of the rear distribution board; the front distribution board and the rear distribution board are connected via a connecting switch to form a distribution network.
[0017] In a possible implementation, the passenger ship power station control system further includes: an intelligent power management system;
[0018] The intelligent power management system is used to calculate and process the load demand of the passenger ship based on preset data, and automatically match the fuel consumption rate curve of the generator set according to the calculated load demand. The preset data includes the target route, the expected speed of the voyage entry, the hotel's estimated power and reserved power.
[0019] In a possible implementation, the passenger ship power station control system further includes: an alarm module;
[0020] The alarm module is used to detect the current load and issue an alarm when the current load exceeds the load requirement.
[0021] In a second aspect, an embodiment of the present application further provides a passenger ship, which is equipped with a passenger ship power station control system as described in any one of the first aspects.
[0022] In a third aspect, an embodiment of the present application further provides an electrical device, wherein the electrical device is equipped with a passenger ship power station control system as described in any one of the first aspects.
[0023] In a fourth aspect, an embodiment of the present application further provides a passenger ship power station control method, the passenger ship power station control method comprising:
[0024] In response to input of preset data, a recommended fuel consumption rate curve of the passenger ship power station control system is determined by a heuristic algorithm, wherein the preset data includes at least one of a target route, an expected speed for voyage entry, an estimated power of the hotel, and a reserved power;
[0025] The corresponding recommended fuel consumption rate curve is activated through an intelligent power management system. If the load demand meets the power range allowed by the recommended fuel consumption rate curve, a strategy instruction is determined based on the recommended fuel consumption rate curve, and the strategy instruction is applied to the power management system.
[0026] In a possible implementation manner, the passenger ship power station control method further includes:
[0027] If the load demand does not meet the power range allowed by the recommended fuel consumption rate curve, the alarm module is activated and the non-important load is tripped, wherein the non-important load is preset based on the power demand.
[0028] The embodiments of the present application have the following beneficial effects:
[0029] (1) Improve energy efficiency: Through the intelligent power management system, the system can accurately calculate the load demand based on the preset data and automatically match the fuel consumption rate curve of the generator set. This precise matching helps to optimize the operating efficiency of the generator set, reduce unnecessary energy consumption, and thus improve the overall energy efficiency.
[0030] (2) Enhanced system reliability: The system adopts a redundant design, including the configuration of multiple generator sets and switchboards, as well as the flexibility of the tie switch. This design ensures that even if some generator sets or switchboards fail, the system can still maintain power supply through the deployment of the tie switch, greatly improving the reliability of the system.
[0031] (3) Improve system safety: The addition of the alarm module enables the system to monitor the current load situation in real time and issue an alarm when the load exceeds the preset demand. This helps to promptly detect and handle abnormal situations in the power system, avoid potential safety hazards, and improve the safety of the entire system.
[0032] (4) Intelligent management: The application of intelligent power management system realizes intelligent management of power stations, which can automatically adjust the operating status and fuel consumption rate curve of generator sets without human intervention. This not only reduces operating costs, but also improves the automation level and operating efficiency of the system.
[0033] (5) Easy to maintain and expand: The modular design of the system makes each part relatively independent, which is easy to maintain and replace. At the same time, the system has good scalability and can add generator sets or load lines as needed to meet the needs of passenger ships of different sizes. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0035] Figure 1 It is a schematic diagram of a passenger ship power station control system provided in an embodiment of the present application;
[0036] Figure 2 It is a schematic diagram of a passenger ship power station control method provided in an embodiment of the present application. DETAILED DESCRIPTION
[0037] To make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. It should be understood that the drawings in the present application only serve the purpose of explanation and description and are not used to limit the scope of protection of the present application. In addition, it should be understood that the schematic drawings are not drawn in real proportion. The flowchart used in this application shows the operations implemented according to some embodiments of the present application. It should be understood that the operations of the flowchart can be implemented out of sequence, and the steps without logical context can be reversed in order or implemented simultaneously. In addition, those skilled in the art can add one or more other operations to the flowchart under the guidance of the content of the present application, or remove one or more operations from the flowchart.
[0038] In the following description, reference is made to “some embodiments”, which describe a subset of all possible embodiments, but it will be understood that “some embodiments” may be the same subset or different subsets of all possible embodiments and may be combined with each other without conflict.
[0039] In addition, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various configurations. Therefore, the following detailed description of the embodiments of the present application provided in the drawings is not intended to limit the scope of the application claimed for protection, but merely represents the selected embodiments of the present application. Based on the embodiments of the present application, all other embodiments obtained by those skilled in the art without making creative work belong to the scope of protection of the present application.
[0040] In the following description, the terms "first\second\third" involved are merely used to distinguish similar objects and do not represent a specific ordering of the objects. It can be understood that "first\second\third" can be interchanged with a specific order or sequence where permitted, so that the embodiments of the present application described herein can be implemented in an order other than that illustrated or described herein.
[0041] It should be noted that the term "comprising" will be used in the embodiments of the present application to indicate the existence of the features declared thereafter, but does not exclude the addition of other features.
[0042] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein are for the purpose of describing the embodiments of this application and are not intended to limit this application.
[0043] See also Figure 1 , Figure 1 is a schematic diagram of a passenger ship power station control system provided in an embodiment of the present application, such as Figure 1 As shown, the passenger ship power station control system includes:
[0044] A generator set consisting of an engine 1 and a generator 2, a first switchboard 3, at least one load line and a power management system 9;
[0045] The output end of the generator set is connected to the input end of the switchboard, and the output end of the first switchboard 3 is respectively connected to the input end of the at least one load line;
[0046] The generator set comprises at least one fuel consumption rate curve, and the power management system 9 is used to selectively adjust the fuel consumption rate curve of the generator set;
[0047] When the power management system 9 is in operation, a target fuel consumption rate curve is selected from the at least one fuel consumption rate curve to meet the load demand of the passenger ship.
[0048] The generator set is the core part of the whole system, which consists of engine 1 and generator 2. Engine 1 drives generator 2 to generate electricity to meet various power needs of the passenger ship. The generator set has at least one fuel consumption rate curve, which means that the fuel consumption rate of the generator set will be different under different workloads.
[0049] The first switchboard 3 is a key component of the power system, which is used to receive the electric energy of the generator set and distribute it to various load lines.
[0050] Load lines carry electrical energy from the switchboard to the various electrical consumers on board the ship, such as lighting, air conditioning, kitchen equipment, etc. The number and capacity of these load lines depend on the specific needs and design of the ship.
[0051] The power management system 9 is the intelligent part of the system, which is responsible for adjusting the operating state of the generator set according to the load demand of the passenger ship. The user can manually select the most suitable one from multiple fuel consumption rate curves of the generator set through the power management system 9 to minimize fuel consumption and improve energy utilization efficiency while meeting the load demand.
[0052] Since there are multiple fuel consumption rate curves in this system, the power management system 9 can select the most suitable operating curve according to different load conditions, thereby ensuring the stable operation of the generator set and optimizing fuel consumption. By optimizing fuel consumption, this system can reduce the operating cost of the passenger ship and improve energy utilization efficiency, which is in line with the current green, low-carbon and environmentally friendly development concept. In general, the passenger ship power station control system can ensure the stable operation of the passenger ship under various load conditions, optimize fuel consumption and reduce operating costs.
[0053] In a possible implementation manner, the at least one load line includes: a first load line and a second load line;
[0054] The first load circuit includes a propulsion transformer 4, a propulsion frequency converter 5 and a propulsion motor 6;
[0055] The second load circuit includes a daily transformer 8 and a second distribution board 7, wherein the distribution voltage of the second distribution board 7 is lower than the distribution voltage of the first distribution board 3;
[0056] The output end of the first distribution board 3 is connected to the input end of the propulsion transformer 4 and the input end of the daily transformer 8 respectively; the output end of the propulsion transformer 4 is connected to the input end of the propulsion inverter 5, and the output end of the propulsion inverter 5 is connected to the input end of the propulsion motor 6; the output end of the daily transformer 8 is connected to the input end of the second distribution board 7.
[0057] The first switchboard 3 serves as a main switchboard, and its output end is directly connected to two main load lines, namely the first load line and the second load line.
[0058] The propulsion transformer 4 is responsible for converting the voltage output by the first switchboard 3 into the voltage required by the propulsion system.
[0059] The propulsion inverter 5 receives the power from the propulsion transformer 4 and converts it into the frequency and voltage required by the propulsion motor 6 to control the rotation speed and direction of the propulsion motor 6 .
[0060] The propulsion motor 6 receives the electric power from the propulsion inverter 5 and converts it into mechanical energy to drive the propulsion system of the ship.
[0061] The daily transformer 8 is connected to the first switchboard 3 to convert the voltage of the main switchboard into the voltage required for daily life and operation.
[0062] The second switchboard 7 has a distribution voltage lower than that of the first switchboard 3. It receives power from the daily transformer 8 and distributes it to various daily electrical equipment on the passenger ship, such as lighting, air conditioning, kitchen equipment, etc.
[0063] Through the first distribution board 3 and the second distribution board 7, the system realizes the hierarchical distribution of electricity, which not only meets the needs of the propulsion system for high voltage and high current, but also meets the needs of daily electrical equipment for low voltage and low current. At the same time, the design of hierarchical distribution also increases the reliability of the system. Even if a part fails, other parts can continue to operate.
[0064] In a possible implementation manner, the number of the generator sets is at least 4, and each generator set is composed of an engine 1 and a generator 2 .
[0065] The system includes at least 4 generator sets, each of which consists of an engine 1 and a generator 2. These generator sets jointly provide power for the passenger ship, ensuring that power demand can be met in various situations. The configuration of at least 4 generator sets provides a redundant design to ensure high reliability of the system. Even if some generator sets fail or are maintained, other generator sets can continue to provide power for the passenger ship.
[0066] In a possible implementation, the first distribution board 3 includes a front distribution board and a rear distribution board, the output ends of at least some of the generator sets are connected to the input ends of the front distribution board, and the output ends of the remaining generator sets are connected to the input ends of the rear distribution board; the front distribution board and the rear distribution board are connected via a connecting switch to form a distribution network.
[0067] The front switchboard is part of the power distribution network, and its input end is connected to the output end of at least some of the generator sets. The front switchboard is responsible for receiving and distributing the power from these generator sets. The rear switchboard is also part of the power distribution network, and its input end is connected to the output end of the remaining generator sets. The rear switchboard is responsible for receiving and distributing the power from these generator sets.
[0068] The tie switch connects the front distribution board and the rear distribution board, allowing the mutual supplement and deployment of electricity when needed. This increases the flexibility and reliability of the system.
[0069] The system provides high redundancy and flexibility through the configuration of the front and rear distribution boards, as well as the flexibility of the tie switch. Even if some generator sets or distribution boards fail, the system can still maintain power supply through the deployment of the tie switch. The configuration of the front and rear distribution boards makes system maintenance more convenient. When maintaining or replacing a certain part, the tie switch can be used to isolate other parts to reduce the impact on the entire system.
[0070] In a possible implementation manner, the passenger ship power station control system further includes: an intelligent power management system 10;
[0071] The intelligent power management system 10 is used to calculate and process the load demand of the passenger ship based on preset data, and automatically match the fuel consumption rate curve of the generator set according to the calculated load demand. The preset data includes the target route, the expected speed of the voyage entry, the hotel estimated power and the reserved power.
[0072] The intelligent power management system 10 can calculate the load demand of the passenger ship according to the preset data and automatically match the fuel consumption rate curve of the generator set. This system greatly improves the efficiency and accuracy of power station management and provides a strong guarantee for the safe and efficient operation of the passenger ship.
[0073] The intelligent power management system 10 first collects preset data, including the target route, the expected speed of the voyage entry, the hotel's estimated power and reserved power, etc. These data are the basis for calculating the load demand.
[0074] Based on the collected preset data, the intelligent power management system 10 uses an algorithm to calculate the load demand of the passenger ship. This process takes into account a variety of factors, such as range, speed, hotel power demand, etc., to ensure the accuracy of the calculation results. According to the calculated load demand, the intelligent power management system 10 automatically selects the most appropriate curve from the fuel consumption rate curve of the generator set. This helps to reduce fuel consumption and improve energy efficiency while meeting the load demand. During the voyage, the intelligent power management system 10 will monitor the load situation in real time and automatically adjust the operating status and fuel consumption rate curve of the generator set as needed. This dynamic adjustment ensures the stability and efficiency of the power supply.
[0075] The intelligent power management system 10 realizes the intelligent management of power plants by automatically collecting data, calculating load requirements and matching fuel consumption rate curves. This greatly reduces the need for manual intervention and improves management efficiency. Based on the calculation and processing of the algorithm, the intelligent power management system 10 can accurately calculate the load requirements and select the most appropriate fuel consumption rate curve. This helps to ensure the stability and efficiency of power supply. The intelligent power management system 10 can automatically adjust the operating status and fuel consumption rate curve of the generator set according to the preset data and real-time load conditions. This flexibility enables the system to adapt to various navigation conditions and load changes. By optimizing the operating status of the generator set and selecting the appropriate fuel consumption rate curve, the intelligent power management system 10 helps to reduce fuel consumption and emissions, which is in line with the green, low-carbon and environmentally friendly development concept.
[0076] In a possible implementation, the passenger ship power station control system further includes: an alarm module;
[0077] The alarm module is used to detect the current load and issue an alarm when the current load exceeds the load requirement.
[0078] The alarm module obtains the data of the current load in real time through sensors or other monitoring devices. These data may include parameters such as current, voltage, and power, reflecting the current operating status of the power system. The alarm module compares the current load with the preset load demand. The load demand is calculated based on factors such as the passenger ship's sailing plan, the hotel's estimated power, and the reserved power. If the current load exceeds the preset load demand, the alarm module will immediately trigger the alarm mechanism. The alarm form may include sound alarms, flashing lights, display screen prompts, etc., so that the operator can quickly notice the abnormal situation. The alarm module also records and stores relevant information of the alarm event, such as the time of occurrence, current load value, alarm type, etc. This information can be used for subsequent analysis and troubleshooting to help optimize the operation and maintenance of the system.
[0079] In summary, the embodiments of the present application have the following beneficial effects:
[0080] (1) Improve energy efficiency: Through the intelligent power management system, the system can accurately calculate the load demand based on the preset data and automatically match the fuel consumption rate curve of the generator set. This precise matching helps to optimize the operating efficiency of the generator set, reduce unnecessary energy consumption, and thus improve the overall energy efficiency.
[0081] (2) Enhanced system reliability: The system adopts a redundant design, including the configuration of multiple generator sets and switchboards, as well as the flexibility of the tie switch. This design ensures that even if some generator sets or switchboards fail, the system can still maintain power supply through the deployment of the tie switch, greatly improving the reliability of the system.
[0082] (3) Improve system safety: The addition of the alarm module enables the system to monitor the current load situation in real time and issue an alarm when the load exceeds the preset demand. This helps to promptly detect and handle abnormal situations in the power system, avoid potential safety hazards, and improve the safety of the entire system.
[0083] (4) Intelligent management: The application of intelligent power management system realizes intelligent management of power stations, which can automatically adjust the operating status and fuel consumption rate curve of generator sets without human intervention. This not only reduces operating costs, but also improves the automation level and operating efficiency of the system.
[0084] (5) Easy to maintain and expand: The modular design of the system makes each part relatively independent, which is easy to maintain and replace. At the same time, the system has good scalability and can add generator sets or load lines as needed to meet the needs of passenger ships of different sizes.
[0085] An embodiment of the present application also provides a passenger ship, which is equipped with the passenger ship power station control system described in any one of the above embodiments.
[0086] An embodiment of the present application also provides an electrical device, which is equipped with the passenger ship power station control system described in any of the above embodiments.
[0087] See also Figure 2 , Figure 2 : is a schematic diagram of a passenger ship power station control method provided in an embodiment of the present application. The embodiment of the present application also provides a passenger ship power station control method, and the passenger ship power station control method includes:
[0088] In response to input of preset data, a recommended fuel consumption rate curve of the passenger ship power station control system is determined by a heuristic algorithm, wherein the preset data includes at least one of a target route, an expected speed for voyage entry, an estimated power of the hotel, and a reserved power;
[0089] The corresponding recommended fuel consumption rate curve is activated through an intelligent power management system. If the load demand meets the power range allowed by the recommended fuel consumption rate curve, a strategy instruction is determined based on the recommended fuel consumption rate curve, and the strategy instruction is applied to the power management system.
[0090] The preset data is the basis of this method, which includes key information such as target route, expected speed of voyage entry, hotel estimated power and reserved power. This information provides the necessary background information for the system to more accurately predict and calculate load demand.
[0091] Heuristic algorithm is a method that can find an approximate solution to a problem in a limited time based on existing experience and knowledge. Here, it uses preset data as input, combines historical data and experience, and determines the recommended fuel consumption curve that best meets current conditions through calculation and analysis.
[0092] The intelligent power management system is the core part of the power plant control system, which is responsible for managing and adjusting the operating status of the generator set. After receiving the recommended fuel consumption rate curve, the intelligent power management system will activate the corresponding curve and make fine adjustments based on the actual situation of the system to ensure that the generator set operates in the optimal state.
[0093] After the recommended fuel consumption rate curve is activated, the system will monitor the load demand in real time and compare it with the power range allowed by the recommended fuel consumption rate curve. If the load demand meets the range, the system will determine the strategy instructions based on the recommended fuel consumption rate curve, which will be directly used to control the operating status of the generator set.
[0094] Based on the determined strategic instructions, the intelligent power management system adjusts the speed, power output and other parameters of the generator set to ensure that they match the recommended fuel consumption curve. This precise control helps improve the operating efficiency of the generator set, reduce unnecessary energy consumption, and extend the service life of the equipment.
[0095] The passenger ship power station control method realizes the optimized management of the power station control system through intelligent decision-making and precise control. It can not only improve the operating efficiency of the system and reduce energy consumption, but also ensure the stability and reliability of power supply, providing a strong guarantee for the safe navigation of passenger ships.
[0096] In a possible implementation manner, the passenger ship power station control method further includes:
[0097] If the load demand does not meet the power range allowed by the recommended fuel consumption rate curve, the alarm module is activated and the non-critical load is tripped, wherein the non-critical load is preset based on the power demand. In the power system, loads are usually divided into critical loads and non-critical loads. Critical loads refer to those equipment and services that are essential for the safe navigation of the ship, such as navigation, communication, emergency lighting, etc. Non-critical loads include some equipment and services that are not essential for the normal operation of the ship, such as entertainment facilities, air conditioning systems, etc.
[0098] When the load demand exceeds the power range of the recommended fuel consumption rate curve, the system will first trip the non-critical loads. This means that the system will shut down or reduce the power supply of some non-critical equipment to reduce the burden on the power system. This treatment method can reduce the power demand without affecting the safe navigation of the ship, so that the system can return to the power range of the recommended fuel consumption rate curve.
[0099] While performing the non-critical load tripping process, the system will activate the alarm module. The alarm module is an important component of the power station control system, which is used to issue an alarm when an abnormal situation occurs in the power system to remind the operator to pay attention and take corresponding measures.
[0100] In this case, the alarm module will send out an audible and visual alarm signal and may display relevant fault information or system status. This helps operators quickly understand the current power system status and make correct decisions.
[0101] By tripping non-critical loads and activating the alarm module, the passenger ship power station control method can ensure that when the load in the power system exceeds the power range allowed by the recommended fuel consumption rate curve, it can respond quickly and effectively and ensure the safe navigation of the ship. At the same time, this processing method can also reduce energy consumption to a certain extent and improve the operating efficiency of the power station control system.
[0102] The above passenger ship power station control method has the following beneficial effects:
[0103] (1) Improve energy efficiency: Through the intelligent power management system, the system can accurately calculate the load demand based on the preset data and automatically match the fuel consumption rate curve of the generator set. This precise matching helps to optimize the operating efficiency of the generator set, reduce unnecessary energy consumption, and thus improve the overall energy efficiency.
[0104] (2) Enhanced system reliability: The system adopts a redundant design, including the configuration of multiple generator sets and switchboards, as well as the flexibility of the tie switch. This design ensures that even if some generator sets or switchboards fail, the system can still maintain power supply through the deployment of the tie switch, greatly improving the reliability of the system.
[0105] (3) Improve system safety: The addition of the alarm module enables the system to monitor the current load situation in real time and issue an alarm when the load exceeds the preset demand. This helps to promptly detect and handle abnormal situations in the power system, avoid potential safety hazards, and improve the safety of the entire system.
[0106] (4) Intelligent management: The application of intelligent power management system realizes intelligent management of power stations, which can automatically adjust the operating status and fuel consumption rate curve of generator sets without human intervention. This not only reduces operating costs, but also improves the automation level and operating efficiency of the system.
[0107] (5) Easy to maintain and expand: The modular design of the system makes each part relatively independent, which is easy to maintain and replace. At the same time, the system has good scalability and can add generator sets or load lines as needed to meet the needs of passenger ships of different sizes.
Claims
1. A passenger ship power station control system, characterized in that: The passenger ship power station control system comprises: a generator set consisting of an engine and a generator, a first switchboard, at least one load line and a power management system; The output end of the generator set is connected to the input end of the switchboard, and the output end of the first switchboard is respectively connected to the input end of the at least one load line; The generator set includes at least one fuel consumption rate curve, and the power management system is used to selectively adjust the fuel consumption rate curve of the generator set; When the power management system is in operation, a target fuel consumption rate curve is selected from the at least one fuel consumption rate curve to meet the load demand of the passenger ship.
2. The passenger ship power station control system according to claim 1, characterized in that: The at least one load line comprises: a first load line and a second load line; The first load circuit includes a propulsion transformer, a propulsion inverter and a propulsion motor; The second load circuit includes a daily transformer and a second distribution board, and the distribution voltage of the second distribution board is lower than the distribution voltage of the first distribution board; The output end of the first distribution board is connected to the input end of the propulsion transformer and the input end of the daily transformer respectively; the output end of the propulsion transformer is connected to the input end of the propulsion inverter, and the output end of the propulsion inverter is connected to the input end of the propulsion motor; the output end of the daily transformer is connected to the input end of the second distribution board.
3. The passenger ship power station control system according to claim 1, characterized in that: The number of the generator sets is at least 4, and each generator set consists of 1 engine and 1 generator.
4. The passenger ship power station control system according to claim 3, characterized in that: The first distribution board includes a front distribution board and a rear distribution board, the output ends of at least some of the generator sets are connected to the input ends of the front distribution board, and the output ends of the remaining generator sets are connected to the input ends of the rear distribution board; the front distribution board and the rear distribution board are connected through a connecting switch to form a distribution network.
5. The passenger ship power station control system according to claim 1, characterized in that: The passenger ship power station control system also includes: an intelligent power management system; The intelligent power management system is used to calculate and process the load demand of the passenger ship based on preset data, and automatically match the fuel consumption rate curve of the generator set according to the calculated load demand. The preset data includes the target route, the expected speed of the voyage entry, the hotel's estimated power and reserved power.
6. The passenger ship power station control system according to claim 1, characterized in that: The passenger ship power station control system also includes: an alarm module; The alarm module is used to detect the current load and issue an alarm when the current load exceeds the load requirement.
7. A passenger ship, characterized in that: The passenger ship is equipped with a passenger ship power station control system as described in any one of claims 1 to 6.
8. An electrical device, characterized in that: The electrical equipment is equipped with a passenger ship power station control system as described in any one of claims 1 to 6.
9. A passenger ship power station control method, characterized in that: The passenger ship power station control method comprises: In response to input of preset data, a recommended fuel consumption rate curve of the passenger ship power station control system is determined by a heuristic algorithm, wherein the preset data includes at least one of a target route, an expected speed for voyage entry, an estimated power of the hotel, and a reserved power; The corresponding recommended fuel consumption rate curve is activated through an intelligent power management system. If the load demand meets the power range allowed by the recommended fuel consumption rate curve, a strategy instruction is determined based on the recommended fuel consumption rate curve, and the strategy instruction is applied to the power management system.
10. The passenger ship power station control method according to claim 9, characterized in that: The passenger ship power station control method further includes: If the load demand does not meet the power range allowed by the recommended fuel consumption rate curve, the alarm module is activated and the non-important load is tripped, wherein the non-important load is preset based on the power demand.
Citation Information
Patent Citations
Method for economizing fuel by adjusting control parameters of engine to adapt to running conditions of vehicle
CN101776021A
Ship energy consumption and carbon emission monitoring system based on Internet of Things
CN115277743A
Control method of electric propulsion ship power station based on speed-adjustable diesel generating set
CN115459336A
Electricity-electricity hybrid ship direct current comprehensive power system and control method
CN115498622A
Control System And Method For Improving Fuel Economy
US20070272216A1