Construction method of photovoltaic support in Gobi desert area
By optimizing the grouping of construction personnel and division of work in the Gobi Desert, combined with mechanical transportation, the problems of low efficiency and difficulty in the construction of photovoltaic brackets were solved, and efficient and low-cost construction results were achieved.
Patent Information
- Application Number
- CN202410776766.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-17
- Publication Date
- 2024-10-01
AI Technical Summary
The construction efficiency of photovoltaic brackets in the Gobi Desert is low, the cycle is long, the operational skills of the construction workers are high, and the construction is difficult. The terrain is rugged and the site is uneven, which increases the difficulty of construction.
By optimizing the grouping of construction workers, the processes are divided into three categories: A, B, and C. According to the skill level and quantity division, the columns and hoop supports are assembled in a centralized manner and the materials are distributed to each photovoltaic string. This reduces high-altitude operations and uses mechanical transportation to improve Material transfer efficiency, reducing material loss and transportation costs.
It improves construction efficiency, reduces the skill requirements for operators, shortens the construction cycle, reduces the risk of high-altitude operations and material loss, reduces construction costs, and improves the overall construction efficiency and work efficiency.
Smart Images

Figure CN118739980A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of photovoltaic construction, and in particular to a construction method of a photovoltaic bracket in a Gobi desert area. Background Art
[0002] With the needs of national development and the improvement of industry technology, the construction of photovoltaic power stations in the western Gobi Desert region is a new trend under the guidance of current policies. At present, the installation of common photovoltaic bracket components in China is to fix photovoltaic panels by welding or mechanically fixing stainless steel brackets on concrete foundations (single or double piles). The conventional construction sequence of photovoltaic bracket and component installation is: installation of reinforcement pads → installation of clamps, front and rear columns → installation of oblique longitudinal bars, horizontal and longitudinal bars → installation of longitudinal beams and diagonal braces → installation of purlin support plates → installation of purlins and purlin connectors and bracket leveling → installation of flange tie bars → installation of tie rods between beams → installation of photovoltaic components → installation of tie rods between columns → inspection and final tightening of bolts.
[0003] In the installation process of existing photovoltaic brackets, all components are completely constructed by operators on site from bottom to top for the entire photovoltaic string. This method has high requirements for the flatness of the site, the construction is relatively scattered, there are many high-altitude operations, and the operating skills of the construction workers are high. In addition, the work efficiency is low, the cycle is long, and the component loss rate is high. In addition, due to the remote location and difficult transportation in the Gobi Desert area, it is not conducive to the short-term large-scale organization of personnel for rapid construction. In addition, the rugged terrain, uneven site, and large slope greatly increase the difficulty of photovoltaic on-site construction. Therefore, it is necessary to provide a construction method for photovoltaic brackets in the Gobi Desert area, which can solve the problems of low construction efficiency, long cycle, high requirements for the operating skills of construction workers, and high construction difficulty of photovoltaic brackets in the Gobi Desert area in the prior art. Summary of the invention
[0004] The purpose of the present invention is to provide a construction method for photovoltaic brackets in Gobi desert areas, which can solve the problems of low construction efficiency, long construction period, high operating skill requirements for construction workers and great construction difficulty of photovoltaic brackets in Gobi desert areas in the prior art.
[0005] The present invention is achieved in that:
[0006] A method for constructing a photovoltaic support in a Gobi desert area comprises the following steps:
[0007] Step 1: Optimize the grouping of construction workers according to the construction process;
[0008] Step 2: Select a site near the construction area of the photovoltaic modules and level it as the centralized assembly site for the construction area;
[0009] Step 3: The personnel in the optimized grouping centrally assemble the column-hoop support parts at the centralized assembly location;
[0010] Step 4: The personnel in the optimized group will distribute the centrally assembled column-hoop supports and other bracket materials to each photovoltaic string;
[0011] Step 5: The personnel in the optimized group assemble the column-hoop support and other support materials on the ground at each photovoltaic string to form a column-hoop-longitudinal beam-diagonal brace component;
[0012] Step 6: The personnel in the optimized group install the column-hoop-longitudinal beam-diagonal brace components on the pipe piles at each photovoltaic string;
[0013] Step 7: The personnel in the optimized group shall install the purlins and purlin connectors and level the brackets at each photovoltaic string;
[0014] Step 8: The personnel in the optimized group install the flange tie bars at each photovoltaic string;
[0015] Step 9: The personnel in the optimized group install the tie rods between beams at each photovoltaic string;
[0016] Step 10: The optimized group of personnel installs photovoltaic modules at each photovoltaic string;
[0017] Step 11: The personnel in the optimized group install the column tie rods at each photovoltaic string;
[0018] Step 12: The personnel in the optimized group will inspect the entire photovoltaic bracket and tighten the bolts at each photovoltaic string.
[0019] In the step 1, all personnel are divided into three categories: A, B, and C. Among them, they are arranged from high to low in terms of skill level, as A, B, and C, and from large to small in terms of number of personnel, as C, A, and B.
[0020] In the step 1 described above, the Class A personnel have high requirements on the work skill level and a large number of personnel. They are mainly responsible for the two key processes of "installation of purlins, purlin connectors and bracket leveling" and "installation of photovoltaic modules". According to the actual height, position deviation and verticality deviation of the pipe piles, the bracket installation height, purlin flatness and longitudinal beam angle are adjusted to make the bracket reach a state where the photovoltaic modules can be installed flatly. The installation of the photovoltaic modules is completed after the flange tie rods and inter-beam tie rods are installed.
[0021] In the step 1 described above, the skill level requirement for Class B personnel is moderate and the number of personnel is small. They are mainly responsible for the four processes of "flange tie rod installation", "inter-beam tie rod installation", "inter-column tie rod installation" and "inspection and final tightening of bolts".
[0022] In the above-mentioned step 1, the operating skill level requirement for Class C personnel is low and the number of personnel is the largest. They are mainly responsible for "installation of reinforced pads", "installation of clamps, front and rear columns", "installation of diagonal longitudinal bars, horizontal and longitudinal bars", "bulk materials", "installation of purlin support plates", "installation of longitudinal beams, front diagonal braces, and rear diagonal braces", and "connection of brackets and pipe piles".
[0023] In step 2, the principles for selecting the centralized assembly site are: 1) close to the roadside to facilitate the transportation and loading and unloading of materials; 2) located in the center of the construction area to facilitate the distribution of assembled components to the sides of each photovoltaic string; 3)
[0024] In the step 3, all the centralized assembly processes at the centralized assembly location are completed by Category C personnel.
[0025] The step 4 is completed by Class C personnel, who use a combination of forklifts, mountain crawler transport vehicles, mountain crawler dump trucks, truck cranes, truck cranes, and excavators to quickly spread the column-hoop supports and other support materials next to each photovoltaic string.
[0026] The steps 5 and 6 are all completed by Category C personnel.
[0027] The steps 7 and 10 are all completed by Category A personnel, and the steps 8, 9, 11 and 12 are all completed by Category B personnel.
[0028] Compared with the prior art, the present invention has the following beneficial effects:
[0029] 1. The present invention classifies construction workers according to their skill levels and reasonably simplifies a large number of construction processes based on the skill level requirements, so that the installation of photovoltaic brackets is transformed from complex construction content to large-scale assembly line operations with simpler processes. Each group of personnel is only responsible for their own process, which reduces the skill requirements for operators and facilitates the rapid construction of large-scale personnel in a short period of time, greatly improving the overall construction efficiency. The improvement in work efficiency is particularly obvious for large-scale photovoltaic construction projects, and it is also helpful to help alleviate social employment problems.
[0030] 2. The present invention assembles some components together and then distributes them to each photovoltaic string. In the traditional method, each string requires 183 components of various types and 390 sets of bolt assemblies, while the present invention requires 108 components of various types and 195 sets of bolt assemblies, which greatly shortens the distribution time, reduces material transportation and loss, reduces construction costs, improves overall construction efficiency, and ensures the construction period.
[0031] 3. The present invention transforms scattered construction on slopes into centralized construction on a flat site by assembling them in a centralized manner on a flat site and then distributing the materials to the sides of each photovoltaic string. This greatly improves the overall construction efficiency, minimizes high-altitude operations, reduces the difficulty of on-site construction and the incidence of high-altitude safety accidents, and reduces the content of welding and fire operations on the construction site, which is beneficial to protecting the ecological environment.
[0032] 4. Through the optimization of personnel and processes, the overall construction efficiency of the present invention can reach more than 0.50 strings per person per day, and the overall labor cost optimization efficiency can reach 16%, which has a good cost reduction and efficiency improvement effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a flow chart of the construction method of the photovoltaic support in the Gobi desert area of the present invention;
[0034] Figure 2 It is a schematic diagram of the assembly of the column-hoop support member in the construction method of the photovoltaic support in the Gobi desert area of the present invention;
[0035] Figure 3 It is a schematic diagram of the assembly of the column-hoop-longitudinal beam-diagonal bracing components in the construction method of the photovoltaic support in the Gobi desert area of the present invention;
[0036] Figure 4 It is a schematic diagram of the installation of the column-hoop-longitudinal beam-diagonal bracing member on the final screwed pipe pile in the construction method of the Gobi desert region photovoltaic support of the present invention;
[0037] Figure 5 It is a schematic diagram of the installation of purlins in the construction method of the photovoltaic support in the Gobi desert area of the present invention;
[0038] Figure 6 It is a schematic diagram of the installation of flange braces in the construction method of the photovoltaic support in the Gobi desert area of the present invention;
[0039] Figure 7 It is a schematic diagram of installing the tie rods between beams in the construction method of the photovoltaic support in the Gobi desert area of the present invention;
[0040] Figure 8 It is a schematic diagram of the installation of column tie rods in the construction method of the Gobi desert region photovoltaic support of the present invention.
[0041] In the figure, 101 is a reinforcing pad, 102 is a front column, 103 is a rear column, 104 is an oblique longitudinal bar, 105 is a horizontal and longitudinal bar, 106 is a clamp one, 107 is a clamp two, 201 is a purlin support plate, 202 is a longitudinal beam, 203 is a front oblique brace, 204 is a rear oblique brace, 3 is a pipe pile, 4 is a purlin, 5 is a flange brace, 6 is a brace between beams, 7 is a column tie rod, and 8 is a photovoltaic module. DETAILED DESCRIPTION
[0042] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0043] The present invention is based on the traditional photovoltaic module construction process, that is, the installation of reinforcement pads → installation of clamps and front and rear columns → installation of oblique longitudinal bars and horizontal and vertical bars → installation of longitudinal beams and diagonal braces → installation of purlin support plates → installation of purlins and purlin connectors and bracket leveling → installation of flange tie bars → installation of tie rods between beams → installation of photovoltaic modules → installation of tie rods between columns → inspection and final tightening of bolts, and optimization of construction personnel and processes. The traditional process of bulk assembly of parts next to the photovoltaic string is optimized as follows: the installation of reinforcement pads, clamps, installation of front and rear columns, installation of oblique longitudinal bars and horizontal and vertical bars, installation of longitudinal beams and diagonal braces, installation of longitudinal beams and diagonal braces, and installation of purlin support plates are first assembled on the ground, and then scattered to the photovoltaic string for installation, so as to reduce the difficulty of construction and improve the construction efficiency.
[0044] Please see attached Figure 1 , a construction method of a photovoltaic support in a Gobi desert area, comprising the following steps:
[0045] Step 1: Optimize the grouping of construction workers according to the construction process.
[0046] Specifically, all personnel are divided into three categories: A, B, and C. Among them, they are arranged from high to low in terms of skill level as A, B, and C, and from many to few in terms of number as C, A, and B.
[0047] Class A personnel have high requirements for work skill levels and a large number of personnel. They are mainly responsible for the two key processes of "installation of purlins, purlin connectors and bracket leveling" and "installation of photovoltaic modules". The focus is on adjusting the bracket installation height, purlin flatness, longitudinal beam angle and other parameters according to the actual height, position deviation and verticality deviation of the pipe piles, so that the bracket can reach a state where photovoltaic modules can be installed flatly, and the installation of photovoltaic modules can be completed after the flange tie rods and inter-beam tie rods are installed.
[0048] The skill level requirements for Class B personnel are moderate and the number of personnel is relatively small. They are mainly responsible for four processes: "flange tie rod installation", "inter-beam tie rod installation", "inter-column tie rod installation" and "inspection and final tightening of bolts".
[0049] Category C personnel have lower skill level requirements and the largest number of personnel. They are mainly responsible for processes such as "reinforcement pad installation", "hoops, front and rear column installation", "diagonal and longitudinal bars, horizontal and longitudinal bars installation", "bulk materials", "purlin support plate installation", "longitudinal beams, front diagonal braces, rear diagonal braces installation", and "bracket and pipe pile connection". These processes are relatively simple, do not require high-altitude work, and most of the processes do not require high physical strength, so they are suitable for women and workers with relatively low skill qualities.
[0050] The three categories of personnel, A, B, and C, perform assembly line operations in their respective areas in proportion. By increasing the work content of category C personnel, category A and B personnel, especially category A personnel, have more time to engage in operations requiring high skills, and each group of personnel only performs the contents of their own process, thereby improving overall construction efficiency, reducing labor costs, and alleviating the pressure on the demand for highly skilled construction personnel.
[0051] Construction workers must be certified before they can take up their posts. We must strengthen the quality awareness education and technical training of site management and workers, strictly enforce the site management system and production discipline, and pay attention to strengthening incentives and communication during the process. The team leader should be responsible for guiding workers to carry out construction in a standardized and safe manner, and at the same time be responsible for the management of the construction process and answering related questions. If there are any questions, they should contact the project department management personnel in a timely manner. The installers must go through the technical briefing of the project department before they can install. During installation, they must strictly follow the technical briefing and strictly control the quality during the installation process to ensure that no parts are missed or missing.
[0052] Step 2: Select a site near the construction area of the PV panels and level it as the centralized assembly site for the construction area.
[0053] Since the construction site of the Gobi Desert PV project is huge, the terrain is complex, the terrain is constantly undulating, and there are many types and quantities of materials for the support construction, if all components are assembled separately next to each PV string, the materials will be scattered, easy to lose, and have a high loss rate. At the same time, due to the uneven site, the installation efficiency is low. A site is selected near the construction area of the PV module for leveling as the centralized assembly site of the construction area, which is used to transform the scattered construction of some slopes into centralized construction on a flat site, which is convenient for the centralized stacking of materials and reduces transportation and loss. The efficiency of centralized assembly on a flat site is higher than that of scattered installation on a slope, which is conducive to reducing the difficulty of construction.
[0054] The centralized assembly site is mainly used for centralized assembly of column-clamp supports, which are then distributed to the side of each photovoltaic string, transforming scattered construction on slopes into centralized construction on flat sites.
[0055] The principles for selecting a centralized assembly site are: ① Close to the roadside to facilitate the transportation and loading and unloading of materials. ② Located in the center of the construction area to facilitate the distribution of assembled components to the side of each photovoltaic string. ③ The original ground of the site is relatively flat to reduce the cost of site leveling.
[0056] Step 3: Personnel in optimized groups centrally assemble column-hoop supports at a centralized assembly location.
[0057] Based on the existing construction procedures, the installation of components such as "reinforced pads", "hoops, front and rear columns", "oblique longitudinal bars, horizontal and longitudinal bars" is optimized from scattered installation on the Gobi Desert slope to centralized assembly on a flat site, and the centralized assembled parts are then dispersed to each photovoltaic string, thereby solving the problem of inefficiency caused by uneven site and scattered construction, reducing the number of loose materials and on-site spare parts, and improving overall construction efficiency.
[0058] All centralized assembly processes at the centralized assembly location are completed by Class C personnel. After assembly, the materials are distributed to each photovoltaic string for the next step of construction.
[0059] Taking a photovoltaic project in the west as an example, the centralized assembly of the off-site leveling site for each photovoltaic string includes: 10 reinforcement pads 1, 15 reinforcement pads 2, 10 reinforcement pads 3, 5 front columns, 5 rear columns, 10 oblique longitudinal bars, 5 horizontal longitudinal bars, 10 clamp accessories 1, 10 clamp accessories 2, and 95 sets of bolt assemblies of various models, totaling 80 components and 95 sets of bolt assemblies of various types. The assembled column-clamp support parts, a total of 5 sets of column-clamp support parts for each photovoltaic string.
[0060] Among them, the specifications of the reinforcement plate 1 are: 180*40*3, carbon steel grade 8.8, hot-dip galvanized, the average thickness of the zinc layer ≥50μm, and the local thickness ≥40μm. The specifications of the reinforcement plate 2 are: 110*40*3, carbon steel grade 8.8, hot-dip galvanized, the average thickness of the zinc layer ≥50μm, and the local thickness ≥40μm. The specifications of the reinforcement plate 3 are: 145*40*3, carbon steel grade 8.8, hot-dip galvanized, the average thickness of the zinc layer ≥50μm, and the local thickness ≥40μm.
[0061] The specifications of the front column 102 are: C90*50*15*2.0*L1575, S350GD+ZM275. The specifications of the rear column 103 are: C70*50*15*2.0*L1848, S350GD+ZM275. The specifications of the clamp 1 are: R151*680*100*5.0(Φ300*432), S420GD+ZM275. The specifications of the clamp 2 are: R151*500*100*5.0(Φ300*432), S420GD+ZM275.
[0062] The specifications of the oblique and vertical strips are: C50*30*2.0*L710, S420GD+ZM275. The specifications of the horizontal and vertical strips are: C50*30*2.0*L490, S420GD+ZM275.
[0063] Each set of column-hoop support parts is installed as shown in the attached Figure 2 The specific installation points are as follows:
[0064] 1) Installation of reinforcement plate 101:
[0065] The reinforcing pads 101 on the front pillars 102 , the rear pillars 103 and the oblique longitudinal bars 104 are installed in advance, and the reinforcing pads 101 are fixed with an M8×25 hexagonal bolt assembly.
[0066] The specifications of the hexagonal bolt assembly M8×25 are: M8*25+2LFW+SW+NUT, carbon steel grade 8.8, hot-dip galvanized, the average thickness of the zinc layer ≥50μm, the local thickness ≥40μm, the quantity is 93.
[0067] 2) Installation of front column 102, rear column 103 and clamp
[0068] Select the front column 102 and the rear column 103 of corresponding length, fix the front column 102 and the rear column 103 on the clamp 106 and the clamp 2 107 respectively, and lock them with the M14*60 hexagonal bolt assembly for installing the clamp 106 and the clamp 2 107. During installation, pay attention to the C-shaped steel opening directions of the front column 102 and the rear column 103 to be the same.
[0069] The specifications of the M14*60 hexagonal bolt set are: M14*60+2LFW+SW+NUT, carbon steel grade 8.8, hot-dip galvanized, the average thickness of the zinc layer ≥50μm, the local thickness ≥40μm, the quantity is 30.
[0070] 3) Installation of oblique longitudinal strips 104 and horizontal longitudinal strips 105
[0071] The oblique longitudinal bars 104 and the horizontal longitudinal bars 105 are connected and fixed to the front column 102 and the rear column 103 by using M14*85 external hexagonal bolts, and all the bolt heads are kept in the same direction.
[0072] The specifications of the M14*85 hexagonal bolt set are: M14*85+2LFW+SW+NUT, carbon steel grade 8.8, hot-dip galvanized, the average thickness of the zinc layer ≥50μm, the local thickness ≥40μm, the quantity is 20.
[0073] Step 4: The personnel in the optimized group will distribute the centrally assembled column-clamp supports and other bracket materials to each photovoltaic string.
[0074] The step 4 is completed by Class C personnel, who distribute the assembled column-hoop supports and other bracket materials to each photovoltaic string. The materials distributed to each photovoltaic string include: 5 sets of column-hoop supports, 5 diagonal beams, 5 front diagonal braces, 5 rear diagonal braces, 8 purlins, 4 purlin connectors, 20 purlin support plates, 20 flange tie rods, 8 inter-beam tie rods, 28 photovoltaic modules and 295 sets of bolt assemblies of various models, totaling 108 components of various types and 295 sets of bolt assemblies of various types.
[0075] Preferably, according to the Gobi Desert terrain and temporary road conditions on site, a combination of machines such as forklifts, mountain crawler transporters, mountain crawler dump trucks, truck cranes, truck cranes, excavators, etc. can be used to quickly spread the column-hoop supports and other support materials next to each photovoltaic string.
[0076] Step 5: The personnel in the optimized group will assemble the column-hoop supports and other support materials on the ground at each photovoltaic string to form a column-hoop-longitudinal beam-diagonal bracing component.
[0077] Please see attached Figure 3 , the step 5 is all completed by Class C personnel. The specific ground assembly of the column-hoop-longitudinal beam-diagonal bracing components includes: using M10*30 bolt assemblies to connect the purlin support plate 201 with the longitudinal beam 202; using M14*35 bolt assemblies to connect the longitudinal beam 202 with the front column 102 and the rear column 103; using M14*60 bolt assemblies to connect the front diagonal brace 203, the rear diagonal brace 204 with the hoop 106 and the longitudinal beam 202; after the connection, do not tighten the bolts first to facilitate the subsequent overall leveling of the bracket.
[0078] The specifications of the front diagonal brace 203 are: C50*30*2.0*L1157, S420GD+ZM275, the quantity is 5. The specifications of the rear diagonal brace 204 are: C75*50*15*2.0*L2593, S420GD+ZM275, the quantity is 5. The specifications of the longitudinal beam are: C90*50*15*2.0*L4000, S420GD+ZM275, the quantity is 5. The specifications of the purlin support plate are: L100*63*6*50, Q235B hot-dip galvanized, the average thickness of the zinc layer is ≥50μm, the local thickness is ≥40μm, the quantity is 20.
[0079] Step 6: The personnel in the optimized group install the column-hoop-longitudinal beam-diagonal bracing components on the pipe piles at each PV string.
[0080] Please see attached Figure 4 , the step 6 is all completed by Class C personnel, and the specific operations include: installing the front column 102 and the rear column 103 on the pipe pile 3 through the clamp 1 106 and the clamp 2 107. After the installation, the front column 102 of the 5 sets of column-clamp-longitudinal beam-diagonal bracing components are in the same direction, the rear column 103 of the 5 sets of column-clamp-longitudinal beam-diagonal bracing components are in the same direction, and the direction of the longitudinal beam 202 is roughly perpendicular to the direction of the string, but the bolts are not tightened, so as to facilitate the subsequent overall leveling of the bracket.
[0081] Before installing the column-hoop-longitudinal beam-bracing components, the elevation and transverse axis of the pipe piles should be re-measured to verify that the tolerance between the pipe piles and the tolerance of the pile top plane height meet the design requirements. The tolerance between two adjacent pipe piles is ±20mm, and the tolerance of the pile top plane height is -10mm. If errors are found in the elevation and axis of the pipe piles, they should be corrected or adjusted in time to ensure that the subsequent installation process meets the requirements of the photovoltaic modules.
[0082] Step 7: The personnel in the optimized group will install the purlins and purlin connectors and perform bracket leveling construction at each PV string.
[0083] Please see attached Figure 5 , the step 7 is all completed by Class A personnel, and the specific operations include: by adjusting the height position relationship between the clamp 1 106, the clamp 2 107 and the pipe pile 3, the longitudinal beam 202 of the five sets of column-clamp-longitudinal beam-bracing components are made to be on the same plane; the inclination angle of the longitudinal beam 202 is checked and adjusted with an inclinometer to keep the inclination angle of the longitudinal beam 202 consistent with the designed installation angle, for example, 33°; the purlin 4 and the purlin connector (not shown in the figure) are connected to the longitudinal beam 202 of the five sets of column-clamp-longitudinal beam-bracing components by using an M10*30 bolt assembly; the installation holes of the front and rear purlins are located on a straight line, and the straight line forms an angle of 90° with the purlin 4; the bolt heads on one side of the purlin 4 and the purlin connector are installed downward to prevent the components from colliding with the bolts in strong winds to form a photovoltaic support structure; the photovoltaic support structure is leveled, and all bolts are tightened during the leveling process.
[0084] The specifications of the purlins are: C110*40*15*2.0*L8650, S420GD+ZM275, quantity 4, and C110*40*15*2.0*L9950, S420GD+ZM275, quantity 4. The specifications of the purlin connectors are: 118*43*3*300, Q235B hot-dip galvanized, average zinc layer thickness ≥50μm, local thickness ≥40μm, quantity 4.
[0085] Step 8: The optimized group of personnel will install the flange tie rods at each PV string.
[0086] Please see attached Figure 6 The step 8 is all completed by Class B personnel. Specifically, the flange brace 5 is connected between the purlins 4 using an M8*25 bolt assembly. The flange brace 5 must not be loose after installation, and all bolt heads are facing downward to facilitate the later installation of photovoltaic DC cables.
[0087] The flange braces 5 include straight braces vertically arranged between the purlins 4 and diagonal braces obliquely arranged between the purlins 4. The specifications of the straight braces are: L35*25*1.2*3864, S420GD+ZM275, the quantity is 4, and the specifications of the diagonal braces are: L35*25*1.2*2465, S420GD+ZM275, the quantity is 16.
[0088] Step 9: The personnel in the optimized group will install the tie rods between beams at each photovoltaic string.
[0089] Please see attached Figure 7 , the step 9 is all completed by Class B personnel. Specifically, the inter-beam tie rod 6 is installed and fixed between the longitudinal beams 202 using special fan-shaped gaskets and M10 bolt assemblies, and the inter-beam tie rod 6 is installed only on the adjacent longitudinal beams 202 of the first span and the adjacent longitudinal beams 202 of the last span.
[0090] The specifications of the inter-beam tie rod 6 are: M10*L4750 / 5200, S420GD+ZM275, and the quantity is 2 long and 2 short.
[0091] Step 10: The optimized group of personnel installs PV modules at each PV string.
[0092] The step 10 is all completed by Class A personnel. Specifically, the standardized photovoltaic assembly 8 is fixed to the purlin 4 by means of stainless steel M8 hexagonal bolts, D-type washers, large flat washers, spring washers, and double nuts. The installation clearance of the photovoltaic assembly 8 is 20 mm, and the minimum height of the photovoltaic assembly 8 from the ground is not less than 1.5 m.
[0093] The specification of the spring washer is M10, carbon steel grade 8.8, hot-dip galvanized, the average thickness of the zinc layer is ≥50μm, the local thickness is ≥40μm, and the quantity is 16.
[0094] Step 11: The personnel in the optimized group will install the column tie rods at each PV string.
[0095] Please see attached Figure 8 , the step 11 is all completed by Class B personnel. Specifically, the column tie rod 7 is installed and fixed between adjacent rear columns 103 using a special fan-shaped gasket and an M10 bolt assembly. The column tie rod 7 must not be loose after installation. The column tie rod 7 is only installed between the adjacent rear columns 103 of the first span and the adjacent rear columns 103 of the last span to complete the installation of the entire photovoltaic bracket.
[0096] The specifications of the column tie rod 7 are: M10*L5800, S420GD+ZM275, and the quantity is 4. The specifications of the fan-shaped gasket are: R25*20*3, S350GD+ZM275, and the quantity is 16.
[0097] Step 12: The personnel in the optimized group will inspect the entire photovoltaic bracket and tighten the bolts at each photovoltaic string.
[0098] The step 12 is all completed by Class B personnel. After the entire photovoltaic bracket is installed, the entire photovoltaic bracket is inspected. The main inspection contents include: whether components are missing, whether the inclination angles of the front diagonal brace 203, the rear diagonal brace 204 and the photovoltaic assembly 8 meet the design requirements, whether the photovoltaic bracket as a whole is horizontal and vertical, neat and beautiful, whether the bolts are tightened reliably, and whether it meets the design specification requirements.
[0099] In the method of the present invention, the reinforcing pad 101 is installed, the clamp 106, the clamp 2 107, the front column 102, the rear column 103, the oblique longitudinal bar 104, the horizontal and longitudinal bar 105, the longitudinal beam 202, the front diagonal brace 203, the rear diagonal brace 204, the purlin support plate 201, the purlin 4, the purlin connector installation and the bracket leveling, the flange tie bar 5 installation, the beam tie rod 6 installation, the photovoltaic module 8 installation, the column tie rod 7 installation, inspection, and final tightening of the bolts, each step is carried out using the existing installation process and acceptance standards, in accordance with the "Photovoltaic Power Station Construction Code" (GB 50794-2012), "Photovoltaic Power Generation Project Acceptance Code" (GB / T 50796-2012), "Photovoltaic Power Generation Project Component and Bracket Installation Quality Assessment Standard" (NB / T 10320-2019), "Photovoltaic Power Generation Project Compliance and Production Acceptance Procedure" (NB / T 32036-2017), Xinjiang Power Grid New Energy Station and Supporting Energy Storage Grid Service Work Guidelines, etc. are used as the basis for quality control, which will not be repeated here.
[0100] The present invention can generate greater economic benefits by optimizing personnel and processes:
[0101] 1. In the conventional construction method, a group of 6 people construct each complete photovoltaic string one by one. On average, each group of people can construct 2.5 strings per day, that is, 0.42 strings per person per day. The overall construction efficiency of the present invention can reach more than 0.50 strings per person per day.
[0102] 2. Take a photovoltaic project in the west as an example: the project has 192 sub-arrays and 43,968 photovoltaic strings. The labor cost of the conventional construction method is 43,968 / 0.42*300=31.40 million yuan, while the labor cost of the present invention is 43,968 / 0.50*300=26.38 million yuan, saving a total of 5.02 million yuan. Take another photovoltaic project in the west as an example: the project has 160 sub-arrays and 16,320 photovoltaic strings. The labor cost of the conventional construction method is 16,320 / 0.42*300=11.65 million yuan, while the labor cost of the present invention is 16,320 / 0.50*300=9.79 million yuan, saving a total of 1.86 million yuan, and the overall labor cost optimization efficiency rate can reach 16%.
[0103] The above are only preferred embodiments of the present invention and are not intended to limit the scope of protection of the invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A method for constructing a photovoltaic support in a Gobi desert area, characterized by: The following steps are involved: Step 1: Optimize the grouping of construction workers according to the construction process; Step 2: Select a site near the construction area of the photovoltaic modules and level it as the centralized assembly site for the construction area; Step 3: The personnel in the optimized grouping centrally assemble the column-hoop support parts at the centralized assembly location; Step 4: The personnel in the optimized group will distribute the centrally assembled column-hoop supports and other bracket materials to each photovoltaic string; Step 5: The personnel in the optimized group assemble the column-hoop support and other support materials on the ground at each photovoltaic string to form a column-hoop-longitudinal beam-diagonal brace component; Step 6: The personnel in the optimized group install the column-hoop-longitudinal beam-diagonal brace components on the pipe piles at each photovoltaic string; Step 7: The personnel in the optimized group shall install the purlins and purlin connectors and level the brackets at each photovoltaic string; Step 8: The personnel in the optimized group install the flange tie bars at each photovoltaic string; Step 9: The personnel in the optimized group install the tie rods between beams at each photovoltaic string; Step 10: The optimized group of personnel installs photovoltaic modules at each photovoltaic string; Step 11: The personnel in the optimized group install the column tie rods at each photovoltaic string; Step 12: The personnel in the optimized group will inspect the entire photovoltaic bracket and tighten the bolts at each photovoltaic string.
2. The construction method of photovoltaic support in Gobi desert area according to claim 1 is characterized by: In the step 1, all personnel are divided into three categories: A, B, and C. Among them, they are arranged from high to low in terms of skill level, as A, B, and C, and from large to small in terms of number of personnel, as C, A, and B.
3. The construction method of the Gobi Desert photovoltaic support according to claim 2 is characterized by: In the step 1, the Class A personnel have high requirements on the working skill level and a large number of personnel. They are mainly responsible for the two key processes of "installation of purlins, purlin connectors and bracket leveling" and "installation of photovoltaic modules". According to the actual height, position deviation and verticality deviation of the pipe piles, the bracket installation height, purlin flatness and longitudinal beam angle are adjusted to make the bracket reach a state where the photovoltaic modules can be installed flatly. The installation of the photovoltaic modules is completed after the flange braces and inter-beam braces are installed.
4. The construction method of the Gobi Desert photovoltaic support according to claim 2 is characterized by: In the step 1, the skill level requirement for Class B personnel is moderate and the number of personnel is small. They are mainly responsible for the four processes of "flange tie rod installation", "inter-beam tie rod installation", "inter-column tie rod installation" and "inspection and final tightening of bolts".
5. The construction method of the Gobi Desert photovoltaic support according to claim 2 is characterized by: In the above-mentioned step 1, the operating skill level requirement for Category C personnel is low and the number of personnel is the largest. They are mainly responsible for "installation of reinforcing pads", "installation of clamps, front and rear columns", "installation of diagonal and longitudinal bars, horizontal and longitudinal bars", "bulk materials", "installation of purlin support plates", "installation of longitudinal beams, front diagonal braces, and rear diagonal braces", and "connection of brackets and pipe piles".
6. The construction method of photovoltaic support in Gobi desert area according to claim 1 is characterized by: In step 2, the principles for selecting the centralized assembly site are: ① close to the roadside to facilitate the transportation and loading and unloading of materials; ② located in the center of the construction area to facilitate the distribution of assembled components to the sides of each photovoltaic string; ③ the original ground of the site is flat to reduce the cost of site leveling.
7. The construction method of photovoltaic support in Gobi desert area according to claim 1 is characterized by: In the step 3, all the centralized assembly processes at the centralized assembly location are completed by Category C personnel.
8. The construction method of photovoltaic support in Gobi desert area according to claim 1 is characterized by: The step 4 is completed by Class C personnel, who use a combination of forklifts, mountain crawler transport vehicles, mountain crawler dump trucks, truck cranes, truck cranes, and excavators to quickly spread the column-hoop supports and other support materials next to each photovoltaic string.
9. The construction method of photovoltaic support in Gobi desert area according to claim 1 is characterized by: The steps 5 and 6 are all completed by Category C personnel.
10. The construction method of photovoltaic support in Gobi desert area according to claim 1, characterized in that: The steps 7 and 10 are all completed by Category A personnel, and the steps 8, 9, 11 and 12 are all completed by Category B personnel.