Underground drilling blowout-prevention and overrun-prevention device with self-cleaning function and underground drilling blowout-prevention and overrun-prevention method
By integrating the blowout preventer body, automatic slag removal system, intelligent control center and intelligent pipeline self-cleaning system into the underground drilling blowout prevention and over-limit device, the risk of gas blowout accidents during drilling of high gas outburst coal seams is solved, and the Real-time monitoring and automatic response improve gas drainage efficiency and mine safety production.
Patent Information
- Application Number
- CN202410931634.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-10-08
AI Technical Summary
The existing downhole drilling blowout and over-limit prevention device lacks real-time gas status monitoring and automated response mechanisms during the drilling process of high gas and outburst coal seams, resulting in an increased risk of gas blowout accidents, low drainage efficiency, and high cleaning costs. Restricting mine safety production.
A device including a blowout prevention body, an automatic slag removal system, an intelligent control center and an intelligent pipeline self-cleaning system is designed to achieve real-time monitoring, automatic response and intelligent adjustment through multi-parameter gas monitoring, automatic gas drainage and pipeline self-cleaning. , reduce gas concentration and prevent gas accumulation and blowhole accidents.
It achieves real-time monitoring and automatic response of gas concentration, reduces the risk of gas blowhole accidents, improves gas drainage efficiency, reduces manual intervention and cleaning workload, and improves mine safety production levels.
Smart Images

Figure CN118745874A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an underground drilling blowout prevention and overrun prevention device and method with a self-cleaning function, which is suitable for preventing and controlling large-scale gas blowout accidents during gas extraction in drilling holes in high-gas and protruding coal seams, and belongs to the technical field of mine gas disaster prevention and control. Background Art
[0002] The occurrence of gas disasters seriously affects the safe production of coal mines. Gas extraction is a fundamental technology to solve gas disasters in mines. However, as the depth of coal seam mining increases, the gas pressure in the coal seam increases and the coal quality becomes soft. Therefore, during the drilling process in the coal seam, under the action of high gas pressure, gas and coal powder are quickly and massively sprayed from the drill hole into the mining space, causing gas over-limit accidents. In severe cases, the sprayed coal powder can also cause harm to workers.
[0003] In response to the drilling blowout accident in high-gas coal seams, the current blowout prevention device has the following problems: 1. There is a lack of real-time monitoring of the gas status (gas concentration, pressure and temperature) during the drilling process. In addition, there is a lack of effective early warning and rapid response mechanism for gas over-limit on site, making it difficult to issue an alarm in time at the early stage of gas blowout, resulting in an increased risk of gas accumulation, explosion and blowout accidents; 2. Traditional blowout prevention devices usually rely on manual operation and lack an automated rapid response mechanism. In an emergency, such as when a gas blowout occurs, a delay in manual operation may cause a large amount of gas to flow into the mining face, increasing safety risks; 3. When extracting over-limit gas during the drilling process, fixed parameters are often used for extraction, and there is a lack of the ability to intelligently and dynamically adjust the extraction parameters based on real-time monitoring data. This results in the inability to achieve the optimal extraction effect under different gas conditions; 4. The blowout preventer is generally equipped with multiple valves and various sensors. A large amount of coal powder or coal slime will pass through the blowout preventer during the water drilling / air drilling process. Over time, there may be too much mud residue at the valve, resulting in the valve not being able to open normally or the sensor probe being blocked by coal slime and unable to monitor the parameters in the blowout preventer normally. Manual cleaning has high maintenance costs, and untimely and incomplete cleaning effects will significantly affect the continuity and efficiency of gas extraction and blowout preventer devices, limiting the improvement of mine safety production levels; 5. The existing mine gas management system has low integration, and the level of automation and intelligence is not high: the slag removal, dust removal, gas monitoring and early warning extraction, and blowout preventer pipeline system cleaning during the drilling process involve a lot of manual intervention, which not only increases the labor intensity, but also increases the risk of operational errors, limiting the improvement of mine safety production levels.
[0004] The above problems not only affect the efficiency and effect of gas extraction, but also increase the risk of mine safety production. Therefore, how to provide a new device and method that can effectively solve the above problems is the research and development direction of the present invention. Summary of the invention
[0005] In view of the problems existing in the above-mentioned prior art, the present invention provides a downhole drilling blowout prevention and overrun prevention device and method with a self-cleaning function, which can effectively solve the above-mentioned problems.
[0006] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: an underground drilling blowout prevention and overrun prevention device with self-cleaning function, including a blowout prevention body, an automatic slag removal system, an intelligent control center, an intelligent gas monitoring and early warning extraction system and an intelligent pipeline self-cleaning system;
[0007] The blowout prevention body is fixed on the bracket, and includes a tee, a slag discharge funnel and a box body; the tee is a hollow tube with openings at both ends and a slag discharge port at its side, one end of the tee is pushed into the coal seam, and the other end and the slag discharge port are outside the drill hole, and the slag discharge port is sealed and connected to the box body inlet through a flexible sealing hose; the slag discharge funnel is installed at the lower part of the box body, and the upper port of the slag discharge funnel is connected to the inside of the box body, which is used to collect coal slag generated by drilling; the upper part of the box body is provided with a box body air outlet;
[0008] The automatic slag removal system is used to automatically collect and discharge the coal slag generated during the drilling process. The automatic slag removal system includes a slag discharge valve, a coal slag automatic conveying mechanism and a coal slag collection area. The slag discharge valve is installed at the lower port of the slag discharge funnel and is used to control the opening and closing of the lower port of the slag discharge funnel; the coal slag automatic conveying mechanism is located below the lower port of the slag discharge funnel and is used to receive the coal slag discharged by the slag discharge funnel and convey it to the coal slag collection area;
[0009] The intelligent gas monitoring and early warning extraction system includes a gas multi-parameter monitoring unit and a gas extraction actuator. The gas multi-parameter monitoring unit is installed in a box body and is used to monitor the gas concentration, pressure and temperature inside the box body in real time during the drilling process; the gas extraction actuator includes a gas extraction valve, a gas extraction pump and an extracted gas storage device; the gas extraction valve is installed at the air outlet of the box body and is used to control the opening and closing of the air outlet of the box body; the inlet of the gas extraction pump is connected to the air outlet of the box body through a pipeline, and the outlet of the gas extraction pump is connected to the extracted gas storage device through a pipeline, so as to transport the gas in the box body to the extracted gas storage device for collection;
[0010] The intelligent pipeline self-cleaning system includes multiple pipeline self-cleaning multi-parameter monitoring units and self-cleaning execution devices, wherein the multiple pipeline self-cleaning multi-parameter monitoring units are respectively arranged inside the box, at the box inlet, at the box outlet and at the lower port of the slag discharge funnel; each pipeline self-cleaning multi-parameter monitoring unit collects images, gas pressure and gas flow around its own position in real time to monitor the coal slime blockage inside the pipeline and the coal slime accumulation in the box in real time; and after feeding back to the intelligent control center for analysis and processing, the intelligent control center controls the self-cleaning execution device to realize the cleaning of each position;
[0011] The intelligent control center is connected to the gas multi-parameter monitoring unit through a data transmission line, which is used to receive the gas concentration, pressure and temperature change data in the downhole drilling process in real time, and adjust the opening and closing of the gas extraction valve and the power of the gas extraction pump after analysis and processing. At the same time, the intelligent control center obtains the coal slag accumulation inside the box body according to the images around the respective positions fed back by the pipeline self-cleaning multi-parameter monitoring unit, and adjusts the opening and closing of the slag discharge valve and the transportation speed of the coal slag automatic conveying mechanism after analysis and processing to meet the gas extraction and slag removal and drainage needs.
[0012] Furthermore, the gas multi-parameter monitoring unit includes an air pressure sensor, a methane gas concentration sensor and a temperature sensor; wherein the air pressure sensor is used to monitor the pressure of methane gas in the blowout preventer body in real time; the methane gas concentration sensor is used to monitor the concentration of methane gas in the blowout preventer body in real time; and the temperature sensor is used to monitor the temperature in the blowout preventer body in real time.
[0013] Furthermore, the pipeline self-cleaning multi-parameter monitoring unit includes an image sensor, a gas pressure sensor and a gas flow sensor, which are respectively used to collect image data, gas pressure and gas flow at the location in real time to reflect the coal slime blockage situation at each location.
[0014] Furthermore, the self-cleaning execution device includes a plurality of self-cleaning nozzles, a self-cleaning fluid pulsating injection pump, a self-cleaning water source, a self-cleaning gas source and a heater; the plurality of self-cleaning nozzles are respectively installed inside the box, at the box inlet, at the box outlet and at the lower port of the slag discharge funnel, the self-cleaning water source and the self-cleaning gas source are both connected to the inlet of the self-cleaning fluid pulsating injection pump, the outlet of the self-cleaning fluid pulsating injection pump is connected to each self-cleaning nozzle through the heater, the self-cleaning fluid pulsating injection pump is used to pump the water of the self-cleaning water source or the gas of the self-cleaning gas source to each self-cleaning nozzle to spray out and clean the surroundings; the heater is used to heat the passing gas or water.
[0015] Furthermore, the intelligent control center has an audible and visual alarm function. When it detects that the gas concentration, temperature and pressure exceed the preset warning threshold, it automatically triggers the audible and visual alarm to promptly notify the underground workers to take risk avoidance measures.
[0016] Furthermore, the automatic coal slag conveying mechanism is a belt conveyor.
[0017] The working method of the underground drilling blowout and overrun prevention device with self-cleaning function comprises the following specific steps:
[0018] Step 1: Install the tee pipe and assemble the anti-blowout hole drilling device: According to the design plan of pre-extraction drilling for gas in high-gas and protruding coal seams, first use a drilling rig to push one end of the tee pipe into the coal seam according to the angle and direction of the gas pre-extraction drilling design, and the other end of the tee pipe and the slag discharge port are outside the borehole. The underground drilling anti-blowout and anti-overrun device is assembled next to the area to be drilled;
[0019] Step 2: Start the intelligent gas monitoring, early warning and extraction system and the intelligent pipeline self-cleaning system: After the three-way pipe and the drilling blowout prevention hole device are installed in place, start the intelligent gas monitoring, early warning and extraction system. The gas multi-parameter monitoring unit monitors the gas concentration, pressure and temperature data of the underground drilling area in real time, and feeds back to the intelligent control center; at the same time, start the intelligent pipeline self-cleaning system. The pipeline self-cleaning multi-parameter monitoring units at different locations use their own image sensors, gas pressure sensors and gas flow sensors to collect the image data, gas pressure and gas flow of the location in real time and feed them back to the intelligent control center. After analysis and processing, the intelligent control center obtains the coal slime blockage situation at each location;
[0020] Step 3: Drilling for pre-gas extraction: Start the drilling rig and adjust the angle and direction of the drill rod so that the drill rod passes through both ends of the tee pipe and drills into the coal seam. During the drilling process, the intelligent gas monitoring and early warning extraction system will continuously monitor the gas concentration, pressure and temperature, while the intelligent pipeline self-cleaning system will monitor the coal slime blockage at various locations of the box.
[0021] Step 4: Automatic slag discharge process during drilling construction: Drill cuttings, coal slag and dust generated during the normal drilling process of gas pre-extraction drilling are discharged through the slag discharge port of the three-way pipe, and then enter the box through the box inlet of the blowout prevention body; the intelligent control center receives the data fed back by the pipeline self-cleaning multi-parameter monitoring unit at different positions, and the intelligent control center processes the data to realize real-time analysis of the changes in the coal slag accumulation inside the box during the underground drilling process. When the coal slag accumulation inside the box reaches the preset coal slag accumulation threshold, the intelligent control center generates a trigger instruction and sends it to the automatic slag removal system to control the slag discharge valve to open for slag discharge, and then the coal slag accumulation inside the box is fed back in real time through the self-cleaning multi-parameter monitoring unit arranged inside the box. The intelligent control center dynamically adjusts the slag discharge strategy according to the feedback information until the intelligent control center evaluates that the coal slag inside the box is empty, and then generates a trigger instruction and sends it to the automatic slag removal system to close the slag discharge mode;
[0022] Step 5. Intelligent gas warning and extraction: The intelligent control center compares the preset gas concentration safety threshold, temperature threshold, gas pressure safety threshold and real-time monitoring data, and conducts a comprehensive assessment of the gas status, so as to identify potential gas accumulation, gas explosion and blowout phenomenon in advance, and realize real-time analysis of gas temperature and pressure status during underground drilling. According to whether the monitoring data exceeds the safety threshold, it intelligently identifies and judges abnormal changes in gas concentration inside the borehole, potential blowout phenomenon and gas explosion hazards; when the real-time monitored gas concentration, temperature and pressure exceed their respective safety thresholds, the intelligent control center automatically triggers the sound and light alarm, and promptly notifies the underground workers to take risk avoidance measures; at the same time, the intelligent control center controls the opening of The gas extraction valve is closed, the slag discharge valve is closed, and the automatic coal slag conveying mechanism is stopped; the deep learning model intelligently matches the gas overlimit degree according to the real-time monitoring data to dynamically adjust the underground gas extraction parameters to the optimal extraction parameters, and adjusts the gas extraction pump to start gas extraction at the corresponding power. A large amount of ejected gas enters the extraction gas storage device for collection, thereby reducing the gas concentration generated by the spray hole and preventing gas accumulation; the gas multi-parameter monitoring unit provides real-time feedback on the gas extraction situation inside the blowout prevention body until the monitored gas concentration, pressure and temperature are all less than their respective safety thresholds. The intelligent control center automatically switches the gas extraction valve and the slag discharge valve, so that the blowout prevention body quickly switches from the gas extraction mode to the slag discharge mode, and continues normal underground drilling operations;
[0023] Step 6: Intelligent self-cleaning of pipelines: The intelligent control center receives data from the pipeline self-cleaning multi-parameter monitoring unit, uses a deep learning algorithm to evaluate the coal slime blockage inside the pipeline, and intelligently matches the most appropriate self-cleaning strategy; the intelligent control center generates and sends a trigger instruction to the self-cleaning execution device based on the matched self-cleaning strategy, and the self-cleaning execution device cleans the gas extraction pipeline; while the self-cleaning execution device is working, the pipeline self-cleaning multi-parameter monitoring unit continuously monitors the self-cleaning process and provides real-time feedback to ensure the accuracy and effectiveness of the cleaning operation; the intelligent control center dynamically adjusts the cleaning strategy and parameters based on the feedback information until the pipeline blockage is evaluated to completely meet the conditions that do not require self-cleaning, and the self-cleaning mode is intelligently turned off;
[0024] Step 7, drill withdrawal: operate the drilling rig to withdraw the drill rod, and repeat the gas intelligent early warning and extraction and intelligent slag removal processes of steps 4 and 5 during the drill withdrawal process. After the drill is withdrawn, the three-way pipe is taken out from the gas pre-extraction borehole, and the gas pre-extraction borehole is sealed and connected to the gas extraction branch pipeline to continue gas extraction, thereby completing the construction of the gas pre-extraction borehole to prevent blowout.
[0025] Furthermore, in step four, the coal slag accumulation situation inside the box is determined, specifically: the image data fed back by the pipeline self-cleaning multi-parameter monitoring unit set in the box is analyzed, the coal slime accumulation height is determined, and the height is compared with the set threshold height. If it exceeds the threshold height, it is determined that slag discharge treatment is required, otherwise it is not required.
[0026] Furthermore, in step 5, the deep learning model intelligently matches the gas overlimit degree according to the real-time monitoring data and dynamically adjusts the underground gas extraction parameters to the optimal extraction parameters, specifically:
[0027] The deep learning algorithm is used in advance to obtain the gas extraction parameters corresponding to different gas concentrations, temperatures and pressure data for training. After training, a deep learning model is formed, and the monitoring data collected each time is input into the deep learning model. The deep learning model intelligently matches the degree of gas exceeding the limit and dynamically adjusts the underground gas extraction parameters to the optimal extraction parameters to ensure efficient gas extraction; the real-time monitoring data dynamically adjusts the underground gas extraction parameters: ① Optimal extraction flow rate: calculated according to the gas outburst rate, for every 0.1% increase in gas concentration, the extraction flow rate increases by 30L / min, and the maximum does not exceed 300L / min; ② Optimal extraction pressure: matched with the extraction flow rate, maintained below 0.8MPa; ③ Optimal extraction time: dynamically adjusted according to the monitoring data.
[0028] Furthermore, in step 6, a deep learning algorithm is used to evaluate the coal slime blockage inside the pipeline and intelligently match the most appropriate self-cleaning strategy and parameters, specifically:
[0029] The evaluation conditions are pre-set: no blockage, slight blockage, moderate blockage and severe blockage, and the image data, gas pressure and gas flow data corresponding to the above four evaluation conditions are set respectively, and the self-cleaning strategies corresponding to different evaluation conditions are determined at the same time: ① No blockage: no self-cleaning; ② Slight blockage: The intelligent control center controls the self-cleaning fluid pulsation injection pump to start, and connects it with the self-cleaning gas source. At this time, the self-cleaning fluid pulsation injection pump sprays gas through each self-cleaning nozzle in the form of high-pressure pulses to perform high-pressure pulse gas cleaning on the surrounding area; ③ Moderate blockage: The intelligent control center controls the self-cleaning fluid pulsation injection pump to start, and connects it with the self-cleaning water source. At this time, the self-cleaning fluid pulsation injection pump sprays water through each self-cleaning nozzle in the form of high-pressure pulses to perform high-pressure pulsating water jet cleaning on the surrounding area; ④ Severe blockage: The intelligent control center controls the self-cleaning fluid pulsation injection pump to start, and connects it with the self-cleaning water source. At this time, the self-cleaning fluid pulsation injection pump sprays water through each self-cleaning nozzle in the form of high-pressure pulses to perform high-pressure pulsating water jet cleaning on the surrounding area; The self-cleaning fluid pulsation injection pump and the heater are started by the core control, and are first connected to the self-cleaning gas source. At this time, the self-cleaning fluid pulsation injection pump passes the gas through the heater in a high-pressure pulse mode, and the heater heats the gas to form a high-temperature pulse gas, and sprays it through each self-cleaning nozzle to perform high-temperature and high-pressure pulse gas thermal cleaning on the surrounding area. After the set time, the connection with the self-cleaning gas source is disconnected, and the self-cleaning water source is connected at the same time. At this time, the self-cleaning fluid pulsation injection pump passes the water through the heater in a high-pressure pulse mode, and the heater heats the water to form a high-temperature pulse water jet, and sprays it through each self-cleaning nozzle to perform high-temperature and high-pressure pulsating water jet thermal cleaning on the surrounding area. After the set time, the connection with the self-cleaning water source is disconnected, and the self-cleaning gas source is connected at the same time, and the high-temperature and high-pressure pulse gas thermal cleaning is continued, and the two are continuously and alternately performed;
[0030] The deep learning algorithm is used to train the monitoring data and self-cleaning strategies corresponding to the four evaluation situations. After training, an evaluation model is formed. The monitoring data collected by the multi-parameter monitoring unit of the pipeline self-cleaning each time is input into the deep learning model to evaluate the evaluation situation corresponding to the monitoring data. The self-cleaning execution device is controlled according to the corresponding self-cleaning strategy according to the evaluation situation. When the pipeline is evaluated to be unblocked, the self-cleaning mode is intelligently turned off.
[0031] Compared with the prior art, the present invention combines the blowout prevention body, the automatic slag removal system, the intelligent control center, the intelligent gas monitoring and early warning extraction system and the intelligent pipeline self-cleaning system, and has the following advantages:
[0032] (1) The gas multi-parameter monitoring unit of the present invention uses high-precision sensors to monitor the gas concentration, pressure and temperature of underground drilling in real time. These key parameters are crucial for preventing gas explosions and blowout accidents. The intelligent control center uses deep learning algorithms to conduct real-time analysis and trend prediction of monitoring data, thereby intelligently identifying and judging abnormal changes in gas concentration inside the borehole, potential blowout phenomena and gas explosion hazards; when abnormal gas concentration or blowout risks are detected, the system can quickly issue an audible and visual alarm, and start the gas extraction system by controlling the opening and closing of the solenoid valve, thereby reducing the gas concentration in the shortest time and effectively preventing gas accumulation and blowout accidents.
[0033] (2) The present invention coordinates the control of the gas extraction valve and the slag discharge valve, so that the blowout prevention body can switch from the slag discharge mode to the gas extraction mode in a short time, realize rapid linkage, and effectively prevent gas over-limit: in the normal drilling process, the gas extraction valve is closed and the slag discharge valve is opened. At this time, the box of the blowout prevention body is connected to the automatic slag discharge mechanism and is in a cut-off state with the gas extraction pump. The coal slag generated by the drilling construction can be separated and collected separately in the box; gas extraction mode: the extraction valve is opened and the slag discharge valve is closed. At this time, the box of the blowout prevention body is cut off from the automatic slag discharge system and is in a connected state with the gas extraction pump. The gas extraction system extracts a large amount of ejected gas into the extraction gas storage device with the optimal gas extraction parameters, and a large amount of coal powder entering the box is settled in the slag discharge funnel, thereby realizing the separation and separate collection process of gas and coal powder at the time of the spray hole.
[0034] (3) The intelligent pipeline self-cleaning system of the present invention can collect images, gas pressure and gas flux change data inside the pipeline through an integrated self-cleaning monitoring unit to comprehensively evaluate the coal slime blockage inside the gas extraction pipeline, and intelligently match the corresponding self-cleaning strategy according to the evaluation situation, and dynamically adjust the self-cleaning strategy according to the pipeline self-cleaning feedback situation, effectively clear the blockage in the pipeline, which not only reduces the workload of manual cleaning, but also avoids the reduction of gas extraction efficiency due to pipeline blockage. In addition, the system's adaptive adjustment, decision support, real-time feedback and remote communication functions make the cleaning process more efficient, accurate and reliable.
[0035] (4) The intelligent control center in the present invention can intelligently match the degree of gas overlimit according to real-time gas monitoring data and historical extraction results, and dynamically adjust gas extraction parameters such as extraction flow, pressure and temperature according to real-time feedback data of gas extraction status to achieve the best extraction effect. This intelligent matching technology not only improves the efficiency of gas extraction, but also reduces energy consumption, achieving efficient and energy-saving gas extraction.
[0036] (5) The entire system design of the present invention fully considers the needs of automation and intelligence. Through the integrated control system, the whole process of slag removal and dust removal, gas multi-parameter monitoring, early warning, extraction and pipeline self-cleaning during the drilling construction is realized. This automated and intelligent design not only improves the response speed and work efficiency of the system, but also reduces manual intervention and reduces the risk of human operational errors. Rapid gas extraction and pipeline self-cleaning effectively prevent the occurrence of gas accumulation and blowout accidents, ensuring the safety of miners and the stable production of mines. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0038] Figure 2 It is a work flow chart of the intelligent gas monitoring, early warning and extraction system in the present invention;
[0039] Figure 3 It is a working flow chart of the intelligent pipeline self-cleaning system in the present invention;
[0040] Figure 4 It is a structural schematic diagram of a gas multi-parameter monitoring unit in the present invention;
[0041] Figure 5 It is a structural schematic diagram of the pipeline self-cleaning multi-parameter monitoring unit in the present invention.
[0042] In the figure: 1-roof, 2-coal seam, 3-drill pipe, 4-tee pipe, 5-flange, 6-flexible sealing hose, 7-blowout prevention body, 8-slag discharge funnel, 9-slag discharge valve, 10-coal slag automatic conveying mechanism, 11-coal slag collection area, 12-intelligent control center, 13-gas multi-parameter monitoring unit, 13-1-temperature sensor, 13-2-pressure sensor, 13-3-methane gas concentration sensor, 14-data transmission line, 15-gas extraction valve, 16- -gas extraction pipeline, 17-gas extraction pump, 18-extracted gas storage device, 19-imported solenoid valve, 20-pipeline self-cleaning multi-parameter monitoring unit, 20-1-image sensor, 20-2-gas pressure sensor, 20-3-gas flow sensor, 21-self-cleaning nozzle, 22-self-cleaning fluid pulsation injection pump, 23-self-cleaning water source, 24-self-cleaning gas source, 25-heater, 26-pipeline conveying mechanism; 27-self-cleaning fluid conveying pipeline. DETAILED DESCRIPTION
[0043] The present invention will be further described below.
[0044] like Figure 1As shown, a downhole drilling blowout prevention and overrun prevention device with a self-cleaning function includes a blowout prevention body 7, an automatic slag removal system, an intelligent control center 12, an intelligent gas monitoring and early warning extraction system, and an intelligent pipeline self-cleaning system;
[0045] The blowout prevention body 7 is fixed on the bracket, and includes a tee pipe 4, a slag discharge funnel 8 and a box body; the tee pipe 4 is a hollow pipe with two ends open and a slag discharge port is provided on its side, one end of the tee pipe 4 is pushed into the coal seam 2, and the other end and the slag discharge port are outside the borehole, and the slag discharge port is sealed and connected to the box body inlet through a flexible sealing hose 6; the slag discharge funnel 8 is installed at the lower part of the box body, and the upper end of the slag discharge funnel 8 is connected to the inside of the box body, which is used to collect the coal slag generated by drilling; the upper part of the box body is provided with a box body air outlet;
[0046] The automatic slag removal system is used to automatically collect and discharge the coal slag generated during the drilling process. The automatic slag removal system includes a slag discharge valve 9, a coal slag automatic conveying mechanism 10 and a coal slag collection area 11. The slag discharge valve 9 is installed at the lower port of the slag discharge funnel 8 and is used to control the opening and closing of the lower port of the slag discharge funnel 8; the coal slag automatic conveying mechanism 10 is located below the lower port of the slag discharge funnel 8 and is used to receive the coal slag discharged by the slag discharge funnel 8 and convey it to the coal slag collection area 11;
[0047] The intelligent gas monitoring and early warning extraction system includes a gas multi-parameter monitoring unit 13 and a gas extraction actuator. The gas multi-parameter monitoring unit 13 is installed in a box body and is used to monitor the gas concentration, pressure and temperature inside the box body in real time during the drilling process. Figure 4 As shown, the gas multi-parameter monitoring unit 13 includes an air pressure sensor 13-2, a methane gas concentration sensor 13-3 and a temperature sensor 13-1; wherein the air pressure sensor 13-2 is used to monitor the pressure of methane gas in the blowout prevention body 7 in real time; the methane gas concentration sensor 13-3 is used to monitor the concentration of methane gas in the blowout prevention body 7 in real time; and the temperature sensor 13-1 is used to monitor the temperature in the blowout prevention body 7 in real time. The gas extraction actuator includes a gas extraction valve 15, a gas extraction pump 17 and an extracted gas storage device 18; the gas extraction valve 15 is installed at the gas outlet of the box body, and is used to control the opening and closing of the gas outlet of the box body; the inlet of the gas extraction pump 17 is connected to the gas outlet of the box body through a pipeline, and the outlet of the gas extraction pump 17 is connected to the extracted gas storage device 18 through a pipeline, and is used to transport the gas in the box body to the extracted gas storage device 18 for collection;
[0048] The intelligent pipeline self-cleaning system includes a plurality of pipeline self-cleaning multi-parameter monitoring units 20 and a self-cleaning execution device, wherein the plurality of pipeline self-cleaning multi-parameter monitoring units 20 are respectively arranged inside the box, at the box inlet, at the box outlet and at the lower port of the slag discharge funnel 8; Figure 5As shown, the pipeline self-cleaning multi-parameter monitoring unit 20 includes an image sensor 20-1, a gas pressure sensor 20-2 and a gas flow sensor 20-3, which are respectively used to collect image data, gas pressure and gas flow at the location in real time to reflect the coal slime blockage at each location; each pipeline self-cleaning multi-parameter monitoring unit 20 collects images, gas pressure and gas flow around its location in real time to monitor the coal slime blockage inside the pipeline and the coal slime accumulation in the box in real time; and feeds back to the intelligent control center 12 for analysis and processing, and the intelligent control center 12 controls the self-cleaning execution device to realize the cleaning of each location; the self-cleaning execution device includes multiple self-cleaning A washing nozzle 21, a self-cleaning fluid pulsating injection pump 22, a self-cleaning water source 23, a self-cleaning gas source 24 and a heater 25; a plurality of self-cleaning nozzles 21 are respectively installed inside the box, at the box inlet, at the box outlet and at the lower port of the slag discharge funnel 8, the self-cleaning water source 23 and the self-cleaning gas source 24 are both connected to the inlet of the self-cleaning fluid pulsating injection pump 22, and the outlet of the self-cleaning fluid pulsating injection pump 22 is connected to each self-cleaning nozzle 21 through the heater 25, and the self-cleaning fluid pulsating injection pump 22 is used to pump the water of the self-cleaning water source 23 or the gas of the self-cleaning gas source 24 to each self-cleaning nozzle 21 to spray and clean the surroundings; the heater 25 is used to heat the passing gas or water.
[0049] The intelligent control center 12 is connected to the gas multi-parameter monitoring unit 13 through a data transmission line 14, which is used to receive the gas concentration, pressure and temperature change data in the downhole drilling process in real time, and adjust the opening and closing of the gas extraction valve 15 and the power of the gas extraction pump 17 after analysis and processing. At the same time, the intelligent control center 12 obtains the coal slag accumulation inside the box body according to the image around the respective positions fed back by the pipeline self-cleaning multi-parameter monitoring unit 20, and adjusts the opening and closing of the slag discharge valve 9 and the transportation speed of the coal slag automatic conveying mechanism 10 after analysis and processing to meet the gas extraction and slag removal and drainage needs.
[0050] The above-mentioned image sensor 20-1 captures the real-time image inside the pipeline and transmits it to the intelligent control center 12. The intelligent control center 12 uses the well-known computer vision principle to identify the color, texture, shape and other characteristics of the coal slime, and compares it with the image data under the normal flow state, so as to determine the existence of coal slime blockage and its blockage degree (the blockage degree is determined as 0% to 100% according to the percentage of the blocked port area); in addition, in order to ensure the accuracy of determining the blockage situation, an auxiliary determination parameter is added, and the pressure change in the pipeline is measured by the gas pressure sensor 20-2. Coal slime blockage will cause gas flow obstruction, thereby causing local pressure rise. The intelligent control center 12 determines whether blockage occurs by identifying abnormal conditions of pressure data, such as pressure peak or sudden change of pressure gradient, and infers the degree and development trend of blockage by quantitatively analyzing the change characteristics of pressure gradient and pressure distribution; the gas flow sensor 20-3 measures the gas flow through the pipeline. Coal slime blockage will reduce the gas flow area, resulting in a decrease in gas flow. The intelligent control center 12 determines whether a blockage occurs by analyzing the time series of the flow data and finding abnormal conditions in the flow data, such as a downward trend in flow or a sudden change in flow, and infers the degree and development trend of the blockage by quantitatively analyzing the mean, variance, change gradient and time sensitivity of the flow data. These processes of determining whether a coal slime blockage occurs and the degree of the blockage are all implemented using existing algorithms and programs.
[0051] As an improvement of the present invention, the intelligent control center 12 has an audible and visual alarm function. When the gas concentration, temperature and pressure exceed the preset warning threshold, the audible and visual alarm is automatically triggered to promptly notify the underground workers to take risk avoidance measures. The coal slag automatic conveying mechanism 10 is a belt conveyor.
[0052] The working method of the underground drilling blowout and overrun prevention device with self-cleaning function comprises the following specific steps:
[0053] Step 1: Install the tee pipe and assemble the anti-blowout hole drilling device: According to the design scheme of pre-extraction drilling for gas in high-gas and protruding coal seams, first use a drilling rig to push one end of the tee pipe 4 into the coal seam 2 according to the angle and direction of the gas pre-extraction drilling design, and the other end of the tee pipe 4 and the slag discharge port are outside the borehole, and the underground drilling anti-blowout and anti-overrun device is assembled next to the area to be drilled;
[0054] Step 2, start the intelligent gas monitoring, early warning and extraction system and the intelligent pipeline self-cleaning system: after the three-way pipe 4 and the drilling anti-blowout hole device are installed in place, start the intelligent gas monitoring, early warning and extraction system, and the gas multi-parameter monitoring unit 13 monitors the gas concentration, pressure and temperature data of the underground drilling area in real time, and feeds back to the intelligent control center 12; at the same time, start the intelligent pipeline self-cleaning system, and the pipeline self-cleaning multi-parameter monitoring units 20 at different positions collect the image data, gas pressure and gas flow of the position in real time through their respective image sensors 20-1, gas pressure sensors 20-2 and gas flow sensors 20-3, and feed them back to the intelligent control center 12. After analysis and processing, the intelligent control center 12 obtains the coal slime blockage situation at each position;
[0055] Step 3: Drilling for pre-gas extraction: Start the drilling rig and adjust the angle and direction of the drill rod so that the drill rod passes through both ends of the tee pipe 4 and drills into the coal seam 2; during the drilling process, the intelligent gas monitoring and early warning extraction system will continuously monitor the gas concentration, pressure and temperature, while the intelligent pipeline self-cleaning system monitors the coal slime blockage at various positions of the box;
[0056] Step 4, automatic slag discharge process during drilling construction: the drilling cuttings, coal slag and dust generated during the normal drilling process of the gas pre-extraction drilling are discharged through the slag discharge port of the three-way pipe 4, and then enter the box through the box inlet of the blowout prevention body 7; the intelligent control center 12 receives the data fed back by the pipeline self-cleaning multi-parameter monitoring unit 20 at different positions, and the intelligent control center 12 processes the data to realize real-time analysis of the changes in the coal slag accumulation inside the box during the underground drilling process, specifically: the image data fed back by the pipeline self-cleaning multi-parameter monitoring unit 20 set in the box is analyzed to determine the height of the coal slime accumulation, and the height is The height is compared with the set threshold height. If it exceeds, it is determined that slag discharge is required, otherwise it is not required. When the coal slag accumulation in the box reaches the preset coal slag accumulation threshold, the intelligent control center 12 generates a trigger instruction and sends it to the automatic slag removal system to control the slag discharge valve 9 to open for slag discharge, and then the coal slag accumulation in the box is fed back in real time through the self-cleaning multi-parameter monitoring unit 20 arranged inside the box. The intelligent control center 12 dynamically adjusts the slag discharge strategy according to the feedback information until the intelligent control center 12 evaluates that the coal slag in the box is empty, and then generates a trigger instruction and sends it to the automatic slag removal system to close the slag discharge mode.
[0057] Step 5: Intelligent gas warning and extraction: Figure 2As shown, the intelligent control center 12 compares the preset gas concentration safety threshold, temperature threshold, gas pressure safety threshold and real-time monitoring data to conduct a comprehensive assessment of the gas state, so as to identify potential gas accumulation, gas explosion and blowout phenomenon in advance, and realize real-time analysis of the gas temperature and pressure state during the downhole drilling process. According to whether the monitoring data exceeds the safety threshold, the abnormal changes in the gas concentration inside the borehole, the potential blowout phenomenon and the hidden danger of gas explosion are intelligently identified and judged; when the real-time monitored gas concentration (safety threshold concentration is 1.0%), temperature (safety threshold: including cooling If the temperature (maximum temperature of liquid: 60°C; maximum temperature without coolant: 100°C) and pressure (safety threshold pressure: 1MPa) exceed their respective safety thresholds, the intelligent control center 12 automatically triggers an audible and visual alarm to promptly notify underground workers to take risk avoidance measures; at the same time, the intelligent control center 12 controls the opening of the gas extraction valve 15, the closing of the slag discharge valve 9, and the stopping of the automatic slag conveying mechanism 10; the deep learning model intelligently matches the degree of gas overlimit according to the real-time monitoring data and dynamically adjusts the underground gas extraction parameters to the optimal extraction parameters, and adjusts the gas extraction pump 17 to start gas extraction at the corresponding power, specifically:
[0058] In advance, deep learning algorithms (such as random forests or neural networks, support vector machines and neural networks, etc.) are used to obtain gas extraction parameters corresponding to different gas concentrations, temperatures and pressure data for training. After training, a deep learning model is formed, and the monitoring data collected each time is input into the deep learning model. The deep learning model intelligently matches the degree of gas exceeding the limit and dynamically adjusts the underground gas extraction parameters to the optimal extraction parameters to ensure efficient gas extraction; the real-time monitoring data dynamically adjusts the underground gas extraction parameters: ① Optimal extraction flow rate: calculated according to the gas outburst rate, the extraction flow rate increases by 30L / min for every 0.1% increase in gas concentration, and the maximum does not exceed 300L / min; ② Optimal extraction pressure: match the extraction flow rate and keep below 0.8MPa; ③ Optimal extraction time: dynamically adjusted according to monitoring data; a large amount of ejected gas enters the extraction gas storage device for collection, thereby reducing the gas concentration generated by the spray hole and preventing gas accumulation; the gas multi-parameter monitoring unit 13 provides real-time feedback on the gas extraction situation inside the blowout prevention body, until the monitored gas concentration, pressure and temperature are all less than their respective safety thresholds, the intelligent control center 12 automatically switches the gas extraction valve 15 and the slag discharge valve 9, so that the blowout prevention body 7 quickly switches from the gas extraction mode to the slag discharge mode, and continues the normal drilling operation underground;
[0059] Step 6: Intelligent self-cleaning of pipelines: Figure 3As shown, the evaluation conditions are pre-set: no blockage (i.e., the blockage degree is less than or equal to 5%), slight blockage (i.e., the blockage degree is greater than 5 and less than or equal to 30%), moderate blockage (i.e., the blockage degree is greater than 30 and less than or equal to 60%) and severe blockage (i.e., the blockage degree is greater than 60 and less than or equal to 100%), and the image data, gas pressure and gas flow data corresponding to the above four evaluation conditions are set respectively, and the self-cleaning strategies corresponding to different evaluation conditions are determined at the same time: ① No blockage: no self-cleaning; ② Slight blockage: The intelligent control center 12 controls the self-cleaning fluid pulsating injection pump 22 to start, and is connected to the self-cleaning gas source 24. At this time, the self-cleaning fluid pulsating injection pump 22 sprays gas through each self-cleaning nozzle 21 in the form of high-pressure pulses to perform high-pressure pulse gas cleaning on the surroundings; ③ Moderate blockage: The intelligent control center 12 controls the self-cleaning fluid pulsating injection pump 22 to start, and is connected to the self-cleaning water source 23. At this time, the self-cleaning fluid pulsating injection pump 22 sprays water through each self-cleaning nozzle 21 in the form of high-pressure pulses to clean the surroundings. The nozzle 21 sprays out high-pressure pulsating water jets to clean the surroundings; ④ Severe blockage: The intelligent control center 12 controls the self-cleaning fluid pulsating injection pump 22 and the heater 25 to start, and first connects with the self-cleaning gas source 24. At this time, the self-cleaning fluid pulsating injection pump 22 passes the gas through the heater 25 in a high-pressure pulse manner, and the heater 25 heats the gas to form a high-temperature pulse gas, and sprays through each self-cleaning nozzle 21 to perform high-temperature and high-pressure pulse gas thermal cleaning on the surroundings. After the set time, disconnect the connection with the self-cleaning gas source 24 and connect with the self-cleaning water source 23 at the same time. At this time, the self-cleaning fluid pulsating injection pump 22 passes the water through the heater 25 in a high-pressure pulse manner, and the heater 25 heats the water to form a high-temperature pulse water jet, and sprays through each self-cleaning nozzle 21 to perform high-temperature and high-pressure pulsating water jet thermal cleaning on the surroundings. After the set time, disconnect the connection with the self-cleaning water source 23 and connect with the self-cleaning gas source 24 at the same time, and continue to perform high-temperature and high-pressure pulse gas thermal cleaning, and the two are continuously performed alternately;
[0060] A deep learning algorithm (such as random forest or neural network, support vector machine and neural network, etc.) is used to train the monitoring data and self-cleaning strategies corresponding to the four evaluation situations. After training, an evaluation model is formed. The monitoring data collected by the pipeline self-cleaning multi-parameter monitoring unit each time is input into the deep learning model to evaluate the evaluation situation corresponding to the monitoring data. The self-cleaning execution device is controlled according to the corresponding self-cleaning strategy matched with the evaluation situation. While the self-cleaning execution device is working, the pipeline self-cleaning multi-parameter monitoring unit 20 continuously monitors the self-cleaning process and provides real-time feedback to ensure the accuracy and effectiveness of the cleaning operation. The intelligent control center 12 dynamically determines the evaluation situation and adjusts the self-cleaning strategy according to the feedback information until the pipeline blockage is assessed to be unblocked, and the self-cleaning mode is intelligently turned off.
[0061] Step 7, drill withdrawal: operate the drilling rig to withdraw the drill rod, and repeat the gas intelligent early warning and extraction and intelligent slag removal processes of steps 4 and 5 in the process of drill withdrawal. After drill withdrawal, take out the three-way pipe 4 from the gas pre-extraction borehole, seal the gas pre-extraction borehole and connect it to the gas extraction branch pipeline to continue gas extraction, thereby completing the construction of the gas pre-extraction borehole to prevent blowout.
[0062] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A downhole drilling blowout and overrun prevention device with self-cleaning function, It is characterized in that It includes blowout prevention body, automatic slag removal system, intelligent control center, intelligent gas monitoring and early warning extraction system and intelligent pipeline self-cleaning system; The blowout prevention body is fixed on the bracket, and includes a tee, a slag discharge funnel and a box body; the tee is a hollow tube with openings at both ends and a slag discharge port at its side, one end of the tee is pushed into the coal seam, and the other end and the slag discharge port are outside the drill hole, and the slag discharge port is sealed and connected to the box body inlet through a flexible sealing hose; the slag discharge funnel is installed at the lower part of the box body, and the upper port of the slag discharge funnel is connected to the inside of the box body, which is used to collect coal slag generated by drilling; the upper part of the box body is provided with a box body air outlet; The automatic slag removal system is used to automatically collect and discharge the coal slag generated during the drilling process. The automatic slag removal system includes a slag discharge valve, a coal slag automatic conveying mechanism and a coal slag collection area. The slag discharge valve is installed at the lower port of the slag discharge funnel and is used to control the opening and closing of the lower port of the slag discharge funnel; the coal slag automatic conveying mechanism is located below the lower port of the slag discharge funnel and is used to receive the coal slag discharged by the slag discharge funnel and convey it to the coal slag collection area; The intelligent gas monitoring and early warning extraction system includes a gas multi-parameter monitoring unit and a gas extraction actuator. The gas multi-parameter monitoring unit is installed in a box body and is used to monitor the gas concentration, pressure and temperature inside the box body in real time during the drilling process; the gas extraction actuator includes a gas extraction valve, a gas extraction pump and an extracted gas storage device; the gas extraction valve is installed at the air outlet of the box body and is used to control the opening and closing of the air outlet of the box body; the inlet of the gas extraction pump is connected to the air outlet of the box body through a pipeline, and the outlet of the gas extraction pump is connected to the extracted gas storage device through a pipeline, so as to transport the gas in the box body to the extracted gas storage device for collection; The intelligent pipeline self-cleaning system includes multiple pipeline self-cleaning multi-parameter monitoring units and self-cleaning execution devices, wherein the multiple pipeline self-cleaning multi-parameter monitoring units are respectively arranged inside the box, at the box inlet, at the box outlet and at the lower port of the slag discharge funnel; each pipeline self-cleaning multi-parameter monitoring unit collects images, gas pressure and gas flow around its own position in real time to monitor the coal slime blockage inside the pipeline and the coal slime accumulation in the box in real time; and after feeding back to the intelligent control center for analysis and processing, the intelligent control center controls the self-cleaning execution device to realize the cleaning of each position; The intelligent control center is connected to the gas multi-parameter monitoring unit through a data transmission line, which is used to receive the gas concentration, pressure and temperature change data in the downhole drilling process in real time, and adjust the opening and closing of the gas extraction valve and the power of the gas extraction pump after analysis and processing. At the same time, the intelligent control center obtains the coal slag accumulation inside the box body according to the images around the respective positions fed back by the pipeline self-cleaning multi-parameter monitoring unit, and adjusts the opening and closing of the slag discharge valve and the transportation speed of the coal slag automatic conveying mechanism after analysis and processing to meet the gas extraction and slag removal and drainage needs.
2. The downhole drilling blowout and overrun prevention device with self-cleaning function according to claim 1, It is characterized in that The gas multi-parameter monitoring unit includes an air pressure sensor, a methane gas concentration sensor and a temperature sensor; wherein the air pressure sensor is used to monitor the pressure of methane gas in the blowout prevention body in real time; the methane gas concentration sensor is used to monitor the concentration of methane gas in the blowout prevention body in real time; and the temperature sensor is used to monitor the temperature in the blowout prevention body in real time.
3. The downhole drilling blowout and overrun prevention device with self-cleaning function according to claim 1, It is characterized in that The pipeline self-cleaning multi-parameter monitoring unit includes an image sensor, a gas pressure sensor and a gas flow sensor, which are respectively used to collect image data, gas pressure and gas flow at the location in real time to reflect the coal slime blockage situation at each location.
4. The downhole drilling blowout and overrun prevention device with self-cleaning function according to claim 1, It is characterized in that The self-cleaning execution device includes multiple self-cleaning nozzles, a self-cleaning fluid pulsating injection pump, a self-cleaning water source, a self-cleaning gas source and a heater; the multiple self-cleaning nozzles are respectively installed inside the box, at the box inlet, at the box outlet and at the lower port of the slag discharge funnel, the self-cleaning water source and the self-cleaning gas source are both connected to the inlet of the self-cleaning fluid pulsating injection pump, the outlet of the self-cleaning fluid pulsating injection pump is connected to each self-cleaning nozzle through the heater, the self-cleaning fluid pulsating injection pump is used to pump the water of the self-cleaning water source or the gas of the self-cleaning gas source to each self-cleaning nozzle to spray and clean the surroundings; the heater is used to heat the passing gas or water.
5. The downhole drilling blowout and overrun prevention device with self-cleaning function according to claim 1, It is characterized in that The intelligent control center is equipped with sound and light alarm functions. When it detects that the gas concentration, temperature and pressure exceed the preset warning threshold, it automatically triggers the sound and light alarm to promptly notify the underground workers to take risk avoidance measures.
6. The downhole drilling blowout and overrun prevention device with self-cleaning function according to claim 1, It is characterized in that The automatic coal slag conveying mechanism is a belt conveyor.
7. A method for operating the downhole drilling blowout and overrun prevention device with self-cleaning function according to claim 1, It is characterized in that The specific steps are: Step 1: Install the tee pipe and assemble the anti-blowout hole drilling device: According to the design plan of pre-extraction drilling for gas in high-gas and protruding coal seams, first use a drilling rig to push one end of the tee pipe into the coal seam according to the angle and direction of the gas pre-extraction drilling design, and the other end of the tee pipe and the slag discharge port are outside the borehole. The underground drilling anti-blowout and anti-overrun device is assembled next to the area to be drilled; Step 2: Start the intelligent gas monitoring, early warning and extraction system and the intelligent pipeline self-cleaning system: After the three-way pipe and the drilling blowout prevention hole device are installed in place, start the intelligent gas monitoring, early warning and extraction system. The gas multi-parameter monitoring unit monitors the gas concentration, pressure and temperature data of the underground drilling area in real time, and feeds back to the intelligent control center; at the same time, start the intelligent pipeline self-cleaning system. The pipeline self-cleaning multi-parameter monitoring units at different locations use their own image sensors, gas pressure sensors and gas flow sensors to collect the image data, gas pressure and gas flow of the location in real time and feed them back to the intelligent control center. After analysis and processing, the intelligent control center obtains the coal slime blockage situation at each location; Step 3: Drilling for pre-gas extraction: Start the drilling rig and adjust the angle and direction of the drill rod so that the drill rod passes through both ends of the tee pipe and drills into the coal seam. During the drilling process, the intelligent gas monitoring and early warning extraction system will continuously monitor the gas concentration, pressure and temperature, while the intelligent pipeline self-cleaning system will monitor the coal slime blockage at various locations of the box. Step 4: Automatic slag discharge process during drilling construction: Drill cuttings, coal slag and dust generated during the normal drilling process of gas pre-extraction drilling are discharged through the slag discharge port of the three-way pipe, and then enter the box through the box inlet of the blowout prevention body; the intelligent control center receives the data fed back by the pipeline self-cleaning multi-parameter monitoring unit at different positions, and the intelligent control center processes the data to realize real-time analysis of the changes in the coal slag accumulation inside the box during the underground drilling process. When the coal slag accumulation inside the box reaches the preset coal slag accumulation threshold, the intelligent control center generates a trigger instruction and sends it to the automatic slag removal system to control the slag discharge valve to open for slag discharge, and then the coal slag accumulation inside the box is fed back in real time through the self-cleaning multi-parameter monitoring unit arranged inside the box. The intelligent control center dynamically adjusts the slag discharge strategy according to the feedback information until the intelligent control center evaluates that the coal slag inside the box is empty, and then generates a trigger instruction and sends it to the automatic slag removal system to close the slag discharge mode; Step 5. Intelligent gas warning and extraction: The intelligent control center compares the preset gas concentration safety threshold, temperature threshold, gas pressure safety threshold and real-time monitoring data, and conducts a comprehensive assessment of the gas status, so as to identify potential gas accumulation, gas explosion and blowout phenomenon in advance, and realize real-time analysis of gas temperature and pressure status during underground drilling. According to whether the monitoring data exceeds the safety threshold, it intelligently identifies and judges abnormal changes in gas concentration inside the borehole, potential blowout phenomenon and gas explosion hazards; when the real-time monitored gas concentration, temperature and pressure exceed their respective safety thresholds, the intelligent control center automatically triggers the sound and light alarm, and promptly notifies the underground workers to take risk avoidance measures; at the same time, the intelligent control center controls the opening of The gas extraction valve is closed, the slag discharge valve is closed, and the automatic coal slag conveying mechanism is stopped; the deep learning model intelligently matches the gas overlimit degree according to the real-time monitoring data to dynamically adjust the underground gas extraction parameters to the optimal extraction parameters, and adjusts the gas extraction pump to start gas extraction at the corresponding power. A large amount of ejected gas enters the extraction gas storage device for collection, thereby reducing the gas concentration generated by the spray hole and preventing gas accumulation; the gas multi-parameter monitoring unit provides real-time feedback on the gas extraction situation inside the blowout prevention body until the monitored gas concentration, pressure and temperature are all less than their respective safety thresholds. The intelligent control center automatically switches the gas extraction valve and the slag discharge valve, so that the blowout prevention body quickly switches from the gas extraction mode to the slag discharge mode, and continues normal underground drilling operations; Step 6: Pipeline intelligent self-cleaning: The intelligent control center receives data from the pipeline self-cleaning multi-parameter monitoring unit, uses deep learning algorithms to evaluate the coal slime blockage inside the pipeline, and intelligently matches the most appropriate self-cleaning strategy; The intelligent control center generates and sends a trigger instruction to the self-cleaning execution device according to the matched self-cleaning strategy, and the self-cleaning execution device cleans the gas extraction pipeline. While the self-cleaning execution device is working, the pipeline self-cleaning multi-parameter monitoring unit continuously monitors the self-cleaning process and provides real-time feedback to ensure the accuracy and effectiveness of the cleaning operation. The intelligent control center dynamically determines the evaluation situation and adjusts the self-cleaning strategy according to the feedback information until the pipeline blockage situation is evaluated to completely meet the conditions that no self-cleaning is required, and the self-cleaning mode is intelligently turned off. Step 7, drill withdrawal: operate the drilling rig to withdraw the drill rod, and repeat the gas intelligent early warning and extraction and intelligent slag removal processes of steps 4 and 5 during the drill withdrawal process. After the drill is withdrawn, the three-way pipe is taken out from the gas pre-extraction borehole, and the gas pre-extraction borehole is sealed and connected to the gas extraction branch pipeline to continue gas extraction, thereby completing the construction of the gas pre-extraction borehole to prevent blowout.
8. The working method according to claim 7, It is characterized in that The coal slag accumulation situation inside the box body is determined in the step 4, specifically: the image data fed back by the pipeline self-cleaning multi-parameter monitoring unit set in the box body is analyzed to determine the coal slime accumulation height, and the height is compared with the set threshold height. If it exceeds, it is determined that slag discharge treatment is required, otherwise it is not required.
9. The working method according to claim 7, It is characterized in that In step 5, the deep learning model intelligently matches the gas overlimit degree according to the real-time monitoring data and dynamically adjusts the underground gas extraction parameters to the optimal extraction parameters, specifically: The deep learning algorithm is used in advance to obtain the gas extraction parameters corresponding to different gas concentrations, temperatures and pressure data for training. After training, a deep learning model is formed, and the monitoring data collected each time is input into the deep learning model. The deep learning model intelligently matches the degree of gas exceeding the limit and dynamically adjusts the underground gas extraction parameters to the optimal extraction parameters to ensure efficient gas extraction; the real-time monitoring data dynamically adjusts the underground gas extraction parameters: ① Optimal extraction flow rate: calculated according to the gas outburst rate, for every 0.1% increase in gas concentration, the extraction flow rate increases by 30L / min, and the maximum does not exceed 300L / min; ② Optimal extraction pressure: matched with the extraction flow rate, maintained below 0.8MPa; ③ Optimal extraction time: dynamically adjusted according to the monitoring data.
10. The working method according to claim 7, It is characterized in that In step 6, a deep learning algorithm is used to evaluate the coal slime blockage inside the pipeline and intelligently match the most appropriate self-cleaning strategy and parameters, specifically: The evaluation conditions are pre-set: no blockage, slight blockage, moderate blockage and severe blockage, and the image data, gas pressure and gas flow data corresponding to the above four evaluation conditions are set respectively, and the self-cleaning strategies corresponding to different evaluation conditions are determined at the same time: ① No blockage: no self-cleaning; ② Slight blockage: The intelligent control center controls the self-cleaning fluid pulsation injection pump to start, and connects it with the self-cleaning gas source. At this time, the self-cleaning fluid pulsation injection pump sprays gas through each self-cleaning nozzle in the form of high-pressure pulses to perform high-pressure pulse gas cleaning on the surrounding area; ③ Moderate blockage: The intelligent control center controls the self-cleaning fluid pulsation injection pump to start, and connects it with the self-cleaning water source. At this time, the self-cleaning fluid pulsation injection pump sprays water through each self-cleaning nozzle in the form of high-pressure pulses to perform high-pressure pulsating water jet cleaning on the surrounding area; ④ Severe blockage: The intelligent control center controls the self-cleaning fluid pulsation injection pump to start, and connects it with the self-cleaning water source. At this time, the self-cleaning fluid pulsation injection pump sprays water through each self-cleaning nozzle in the form of high-pressure pulses to perform high-pressure pulsating water jet cleaning on the surrounding area; The self-cleaning fluid pulsation injection pump and the heater are started by the core control, and are first connected to the self-cleaning gas source. At this time, the self-cleaning fluid pulsation injection pump passes the gas through the heater in a high-pressure pulse mode, and the heater heats the gas to form a high-temperature pulse gas, and sprays it through each self-cleaning nozzle to perform high-temperature and high-pressure pulse gas thermal cleaning on the surrounding area. After the set time, the connection with the self-cleaning gas source is disconnected, and the self-cleaning water source is connected at the same time. At this time, the self-cleaning fluid pulsation injection pump passes the water through the heater in a high-pressure pulse mode, and the heater heats the water to form a high-temperature pulse water jet, and sprays it through each self-cleaning nozzle to perform high-temperature and high-pressure pulsating water jet thermal cleaning on the surrounding area. After the set time, the connection with the self-cleaning water source is disconnected, and the self-cleaning gas source is connected at the same time, and the high-temperature and high-pressure pulse gas thermal cleaning is continued, and the two are continuously and alternately performed; The deep learning algorithm is used to train the monitoring data and self-cleaning strategies corresponding to the four evaluation situations. After training, an evaluation model is formed. The monitoring data collected by the multi-parameter monitoring unit of the pipeline self-cleaning each time is input into the deep learning model to evaluate the evaluation situation corresponding to the monitoring data. The self-cleaning execution device is controlled according to the corresponding self-cleaning strategy according to the evaluation situation. When the pipeline is evaluated to be unblocked, the self-cleaning mode is intelligently turned off.
Citation Information
Cited By
Volume-variable buffer pressure relief zero-overrun blowout prevention method for gas extraction drill hole
CN119244306A
Livestock manure pumping equipment operation monitoring method and system based on photovoltaic energy storage
CN119558548A
Deep soft coal body negative pressure caving and intelligent gas extraction control system and method
CN122383398A