Panel-free cast-in-place formwork for channel concrete breast wall with steel protective face and construction technology of panel-free cast-in-place formwork
By using the panel-less cast-in-place formwork and technology of the channel breast wall with steel protection in the construction of the channel breast wall, and using the steel protection as the formwork panel, the problem of increased construction difficulty and cost of the steel panel has been solved, and more efficient construction has been achieved. and lower cost construction results.
Patent Information
- Application Number
- CN202411036342.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-10-11
AI Technical Summary
In the construction of channel parapets, the weight of steel panels increases the difficulty and cost of formwork forming. Especially in long-span construction, it is difficult to effectively reduce the weight of formwork and construction complexity with existing technology.
The panelless cast-in-place formwork and construction technology of the concrete breast wall with steel protection channel are used. By using steel protection as the panel on one side of the breast wall formwork, the use of panels is reduced, the formwork structure and construction steps are optimized, and the overall weight and cost.
It simplifies the construction and construction process of the parapet formwork, reduces the cost, ensures the stability and flatness of the construction, reduces the loss of steel bars, and improves the strength and construction efficiency of the concrete.
Smart Images

Figure CN118756707A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a process for processing a channel breast wall, in particular to a panel-free cast-in-place formwork and a construction process for a channel concrete breast wall with a steel face. Background Art
[0002] The breast wall is the exposed superstructure of the wharf. The control of the leading edge and the top elevation of the breast wall are the key points. The construction of the breast wall currently uses a formwork frame, and the outside of the formwork frame will be covered with a layer of panels. In order to meet the construction strength, the panels are mostly made of steel. The steel panels themselves have a certain weight. In the construction of long-span breast walls, the use of panels is large, resulting in high overall quality after the formwork is formed, which increases the construction difficulty and also increases the construction cost.
[0003] In view of the above-mentioned defects, the designers have actively carried out research and innovation in order to create a panel-free cast-in-place formwork and construction process for the channel concrete breast wall with steel armor, so as to make it more valuable for industrial use. Summary of the Invention
[0004] In order to solve the above technical problems, the purpose of the present invention is to provide a panelless cast-in-place formwork and construction process for a waterway concrete breast wall with steel armor.
[0005] The present invention provides a panel-free construction process for a steel-faced channel concrete breast wall, the process comprising the following steps:
[0006] 1. Construction preparation, measurement and layout;
[0007] 2. Construction of cushion layer;
[0008] 3. Steel bar binding;
[0009] 4. Installation of platform formwork and protective surface;
[0010] 5. C30 cap concrete pouring;
[0011] 6. Installation of breast wall formwork and facing;
[0012] 7. C30 breast wall concrete pouring;
[0013] 8. Concrete maintenance;
[0014] In step one, measurement and laying out shall be carried out according to the requirements of the design drawings and the elevation control points to determine the elevation and axis position of the facing concrete, and earth excavation shall be carried out. The steel bar raw materials shall have a factory certificate and shall be put into use after passing the laboratory inspection. According to the bank protection section design drawing, the excavation boundary shall be delineated. The site shall be cleaned by using an excavator in conjunction with earth-moving transport vehicles to remove obstacles and silt within the excavation range, and a foundation pit excavation path shall be laid, and protection shall be provided between the excavation path and the foundation pit slope.
[0015] This panel-free construction process for the steel-faced channel concrete breast wall optimizes each step of the construction process through subdividing the construction process. In particular, the formwork is improved so that the water side of the breast wall formwork uses the formwork as a face protection, reducing the use of formwork and effectively lowering construction costs.
[0016] Furthermore, in step 2, the geology along the line is basically silty clay and silty clay. Therefore, when the foundation pit is excavated, a combination of open ditch drainage is adopted. A sump is set up in each construction trench section. During the construction period, drainage measures for the foundation pit are completed to prevent the revetment foundation pit from being disturbed and soaked by water during construction. During the construction of the foundation pit, a sump is set up at the bottom of the foundation pit, and drainage ditches are excavated around the bottom of the pit to allow water to flow into the sump, and then water is pumped out with a water pump. The foundation pit earthwork adopts the step excavation method. The specific stratification is determined according to the excavation depth of each revetment foundation pit. The earthwork is transported by dump trucks. The foundation pit soil transportation path adopts a slope ratio of 1:10 to connect to the slope top road. Backfill construction behind the wall can only be carried out when the concrete strength of the wall is greater than 80%. The backfill soil material must be clay with a better surface layer. It is strictly forbidden to use cultivated soil and silt soil for backfilling.
[0017] The revetment pit utilizes a "pit dewatering + slope excavation" approach. Excavation and transportation are combined with backfill behind the wall, with appropriate allocation and transport of unusable spoil to a disposal area. The original ground elevation is 7.7-10.0m, the pit bottom elevation is 11.1m, and the excavation depth is 2.59-2.89m. The soil is relatively hard, not a deep pit, and no support is required. Excavation involves using an excavator to smooth the slope until it meets the design slope requirements. A minimum of 1m of working space and drainage ditch width is reserved around the pit bottom.
[0018] Furthermore, in step three, the steel bars are piled on a flat ground, padded with square wood underneath and completely covered with plastic film to prevent surface rust. The lap joints of the steel bars meet the requirements of the specifications and do not exceed 50% on the same section. To ensure the protective layer of the steel bars, shaped concrete pads are used to ensure that the steel bars are not exposed and to prevent the steel mesh from deformation.
[0019] The elevation difference between the bottom reinforcement and the upper reinforcement of the pedestal is 85cm. In order to ensure the thickness of the protective layer, it is necessary to increase the connecting reinforcement between the upper and lower reinforcement layers for fixation. The overall steel bar loss is too large. While ensuring the quality and safety of the steel bar installation, the loss is reduced as much as possible. Different overlapping methods are used for overlapping, and the actual disconnection is carried out according to the design dimensions of the drawings to reduce the loss.
[0020] Furthermore, in step four, the base template is divided into four parts at different heights and connected by angle steel.
[0021] Furthermore, in step six, the breast wall formwork is a universal formwork with a length of 9.88m. The front wall formwork also only has horizontal and vertical purlins, and the steel facing can be used as the panel.
[0022] Both the pedestal formwork and breast wall formwork use steel facing as panels, reducing the use of panels.
[0023] Furthermore, in steps 5 and 7, the structural concrete should be poured in layers, with each pouring thickness controlled at about 30 cm. When vibrating the upper layer of concrete, the vibrating rod should be inserted into the lower layer of concrete at the same time, and the top layer of concrete should be vibrated twice to avoid loose top phenomenon.
[0024] Concrete vibration is carried out using an inserted vibrating rod. The vibration points should be evenly distributed and follow the principle of fast insertion and slow withdrawal to ensure that no vibration is missed or over-vibrated.
[0025] When treating construction joints, the floating slurry, loose stones and weak concrete layers on the hardened concrete surface should be removed; before pouring, the old concrete surface should be moistened with water, but no water should be left on the concrete surface.
[0026] Furthermore, in step eight, after the concrete is poured, the cement gradually hardens under the action of hydration, and the hydration requires appropriate temperature and humidity to ensure that the concrete has suitable hardening conditions and its strength continues to increase.
[0027] After concrete is poured, the cement gradually hardens through hydration. Hydration requires appropriate temperature and humidity. To ensure suitable hardening conditions and continuous strength growth, concrete must be cured. Curing ensures that the cement is fully hydrated, ensuring the concrete's initial hardening. This prevents abnormal shrinkage, cracks, and other damage that can occur after concrete is formed due to exposure to sunlight, wind, or cold weather.
[0028] A cast-in-place formwork for a panel-free construction process of a channel concrete breast wall with a steel face, comprising a cap formwork and a breast wall formwork, wherein the breast wall formwork is placed on one side of the cap formwork;
[0029] The cap formwork consists of two side panels (one), a template (one with a panel), and a tail plate. Multiple sets of templates (one) are spliced together to form the water-facing surface, and multiple tail plates are spliced together to form the water-repelling surface. There are mounting beams on the outside of the templates (one) and the tail plates. Connecting rods (one) pass through the mounting beams on the outside of the end plates (one) and the tail plates and are locked with nuts.
[0030] The breast wall formwork includes two sets of front and rear mounting beams. Multiple sets of formwork 2 are spliced together to form the water-facing surface, and multiple sets of formwork 3 are spliced together to form the water-repelling surface. Connecting rod 2 passes through the mounting beams on the outside of formwork 2 and formwork 3 and is locked with nuts. There are side panels 2 at both ends of formwork 2 and formwork 3.
[0031] This steel-armored channel concrete breast wall panel-free construction process uses a cast-in-place formwork, which can provide a new formwork structure for the construction process. The formwork structure adopts a formwork structure with a protective surface on the side facing the water. After splicing, no panels are required. The outside of the formwork is supported by multiple purlins, so that the steel protective surface and the steel purlins behind it have sufficient rigidity. After demoulding, the protective surface facing the water has a smooth appearance.
[0032] Through the above scheme, the present invention has at least the following advantages: this panelless construction process of the steel-faced channel concrete breast wall and the river breast wall manufactured by this process can effectively simplify the construction of the breast wall formwork through process adjustments, without the need for panels, and can ensure the stability of the formwork structure while reducing the overall weight of the formwork. After pouring, the breast wall meets the flatness requirements on the water side.
[0033] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention and implement it according to the contents of the specification, the following is a detailed description of the preferred embodiments of the present invention with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate a certain embodiment of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying any creative work.
[0035] Figure 1 It is a schematic diagram of the process steps of the present invention;
[0036] Figure 2 It is a structural schematic diagram of the breast wall formwork of the present invention;
[0037] Figure 3 It is a structural schematic diagram of the assembled pedestal and breast wall formwork of the present invention, wherein the rectangular structure at the lower end is the pedestal formwork, and the trapezoidal structure at the upper end is the breast wall formwork.
[0038] In the figure, 1 is side panel 1, 2 is template 1, 3 is tail panel, 4 is connecting rod 1, 5 is template 2, 6 is template 3, 7 is connecting rod 2, 8 is side panel 2. DETAILED DESCRIPTION
[0039] The following embodiments of the present invention are described in further detail with reference to the accompanying drawings and examples. The following examples are used to illustrate the present invention but are not intended to limit the scope of the present invention.
[0040] A panel-free construction process for a channel concrete breast wall with steel armor, the process comprising the following steps:
[0041] 1. Construction preparation, measurement and layout;
[0042] 2. Construction of cushion layer;
[0043] 3. Steel bar binding;
[0044] 4. Installation of platform formwork and protective surface;
[0045] 5. C30 cap concrete pouring;
[0046] 6. Installation of breast wall formwork and facing;
[0047] 7. C30 breast wall concrete pouring;
[0048] 8. Concrete maintenance;
[0049] This panel-free construction process for the steel-faced channel concrete breast wall adopts eight steps for breast wall processing. Apart from the foundation construction preparation, no panels are required during the fixed installation of the formwork protection of the pedestal and breast wall, which effectively reduces production costs. In each step, the pouring and curing of concrete can increase the strength of the breast wall.
[0050] In step one, the construction environment is measured. After the measurement is completed, the earth is excavated according to the construction requirements. The depth of the excavation is determined by the height of the breast wall. At the same time, the steel bar raw materials also need to be brought in and placed.
[0051] The steel bar raw materials have a factory certificate and are put into use after passing the laboratory inspection. The steel bars are stacked on a flat ground, padded with square wood underneath, and covered with plastic film to prevent the surface from rusting.
[0052] The steel bar lap joints shall comply with the specification requirements and shall not exceed 50% on the same section.
[0053] In order to ensure the protective layer of the steel bars, shaped concrete pads are used to ensure that the steel bars are not exposed and to prevent the steel mesh from deformation.
[0054] The foundation pit in this construction process adopts the "foundation pit dewatering + slope excavation" scheme. The excavation and transportation of earthwork is combined with backfilling behind the wall, and reasonable allocation is carried out. The unusable waste soil is transported to the waste soil area.
[0055] In areas with hard soil and not deep foundation pits, foundation pit support is not required. During foundation pit excavation, use an excavator to smooth the slope until it meets the design slope requirements. Reserve at least 1m of construction space and drainage ditch width around the pit bottom.
[0056] Delineate the excavation boundary according to the bank protection cross-section design. Site cleanup will be performed using an excavator and earthmoving vehicles to remove obstacles and silt within the excavation area. A temporary path will be laid to exit the foundation pit, ensuring protection between the temporary path and the foundation pit slope.
[0057] The geology along the line is basically silty clay and silty clay, so when excavating the foundation pit, open ditch drainage is used in combination, and a collection pit is set up in each construction trench section.
[0058] During the construction period, drainage measures were implemented for the foundation trench to ensure that the revetment foundation pit was not disturbed or soaked by water during construction. A sump was set up at the bottom of the pit, and drainage ditches were excavated around the bottom to allow water to flow into the sump, which was then pumped out. Drainage was arranged using an open ditch and a sump. The open ditch was located on the waterside, with a cross-sectional dimension of 40cm×40cm. A sump of 60cm×60cm×60cm was arranged every 50m. Each sump was equipped with a 4-inch single-stage centrifugal clean water pump to ensure dry land construction for the revetment. To prevent rainwater from entering the foundation pit, a drainage ditch with a cross-sectional dimension of 40cm×40cm was excavated 1m outside the upper end of the pit to drain the rainwater into the local drainage system.
[0059] The excavation of the foundation pit is carried out using a stepped method, with the specific layers determined by the excavation depth of each type of revetment pit. The excavation is transported by dump trucks, and the excavation access road to the foundation pit has a slope of 1:10, connecting to the road at the top of the slope.
[0060] In order to ensure that the excavated soil is not soaked by rainwater and groundwater during the excavation process, the excavation adopts a block-by-block backward excavation operation. First, a drainage ditch is excavated to form a drainage ditch that is interconnected with the excavation trench. Soil seepage and surface water are introduced into the drainage ditch and discharged outside the foundation pit.
[0061] To prevent mechanical excavation from disturbing the existing foundation soil, a 30cm thick protective layer of soil must be reserved. Before excavating this protective layer, drainage ditches and sump pits should be deepened to prevent the foundation pit from being soaked by water. Excavation of this protective layer should be carried out in good weather. Once the excavation reaches the designed elevation, the foundation should be carefully protected from soaking. Reporting and subsequent construction should be organized promptly.
[0062] Backfill construction can only be carried out when the concrete strength of the wall is greater than 80%. The backfill soil material must be clay with good surface quality. It is strictly forbidden to use cultivated soil or silt soil for backfilling. The backfill construction process is as follows:
[0063] ① Before backfilling, the foundation pit must be cleaned of silt, accumulated water, etc., and reported to the supervising engineer for inspection and acceptance. Only after passing the inspection can the earth backfill be carried out.
[0064] ② Filling starts from the lower layer of the section, and the material is added layer by layer. The next layer of filling material is completed according to the specified parameters. Only after it is inspected and approved by the supervisor can new material be laid.
[0065] ③ The backfill soil shall be made of silty clay with good surface quality, which shall be compacted in layers with a layer thickness of no more than 30 cm.
[0066] ④ The backfill soil is directly backfilled and compacted by an excavator, and compacted near the wall with a frog-type rammer.
[0067] In step three, a processing site is provided for the placement of steel bars. A steel structure greenhouse is used and the steel bar raw material area, steel bar processing area, semi-finished product storage area, and finished product stacking area are arranged in accordance with standardized construction requirements.
[0068] The steel bars need to be stacked on a raised platform, more than 20 cm above the ground, and the lower support point should be based on the principle of ensuring that the steel bars do not deform.
[0069] (1) The steel bar protective layer shall be made of shaped high-strength mortar pads, and the thickness of the protective layer shall meet the design requirements. The number of pads on the bottom and side surfaces of the component shall be no less than 4 per m2 (the number per unit area shall be increased if the area is small to ensure accurate positioning of the steel bars), and the wire used to bind the pads and steel bars shall not extend into the protective layer;
[0070] (2) During the installation of steel bars, the designed reserved channels and embedded parts should be set in time, the setting positions should be correct, and the fixation should be firm;
[0071] (3) The tied steel frame must not be stepped on or heavy objects placed on it.
[0072] (4) The mesh or frame after welding must be stable and firm, and must not be loose or deformed during installation and pouring of concrete.
[0073] The pedestal formwork is 1m high and consists of four sections. The first section is 9.88m long and includes a 5mm-thick faceplate with 10 vertical purlins and 4 horizontal purlins. The two end cap forms are identical, 6.6m long and 1m high, with 60x20cm slots for the sheet piles, larger than the pile heads, to be sealed with steel plates later. The fourth section, 9.88m long, includes only horizontal and vertical purlins and no faceplate. Due to the design of the facing steel plate, this can be used as the faceplate. The four pedestal formwork sections are assembled using angle steel for easy demoulding.
[0074] The breast wall formwork is common to Structures I, II, and III, and is 9.88m long. Structure II differs from Structure I in having an additional "backpack" in the middle for mooring posts and hooks, so an additional "backpack" formwork is required for the breast wall. The front wall formwork also consists of only horizontal and vertical purlins, utilizing the designed steel facing as the panel. The end cap formwork for Structure II is common to Structure I and does not require a separate one. Structure III incorporates a step structure, and the rear wall formwork is 333mm taller than Structures I and II. A separate 333mm*9880mm movable joint formwork is constructed, allowing for easy use with different structures. A specially designed step-shaped formwork is installed on the breast wall formwork, allowing it to serve as a common formwork for Structures I, II, and III.
[0075] The template installation method is as follows:
[0076] a. Before installing the template, wipe off the dust on the template surface and apply the release agent evenly. Do not use waste oil instead of release agent.
[0077] b. The concrete residue at the joint should be removed and rinsed with water;
[0078] c. During the installation of the formwork, the embedded steel bars are straightened and the formwork tie bars are welded to the embedded steel bars. The upper edge of the formwork is fixed with steel pipes along the axis to ensure a smooth linear shape.
[0079] d. Template edge control: In order to avoid the local concrete veneer line shape not meeting the design requirements due to long-distance control, the principle of segmented straightening is adopted (basically straightening and laying out the line every 100 meters), and GPS is used to set the control points of the bank protection front line on the flat ground at both ends of the foundation trench behind the bank protection. During construction, the total station is used to penetrate the two end points to control the front line.
[0080] Elevation Control: To ensure the flatness and elevation of the bottom of the formwork during installation, the top elevation and external dimensions of the concrete cap are strictly controlled during concrete pouring to ensure a flat bottom during formwork installation. A level is used to control the formwork elevation and a clear mark is made on the formwork.
[0081] f. The template is installed in sections and intervals. After the adjacent templates are adjusted and straightened, they are spliced and tightened with screws.
[0082] g. Side formwork installation: The side formwork is also a steel formwork and is installed according to different mechanisms.
[0083] Leakage sealing: Double-sided foam adhesive is used to fill the joints of the formwork to ensure that the joints are leak-proof. Cement mortar should be applied to the gaps between the formwork and the masonry blocks to prevent leakage during the pouring of cement concrete due to loose adhesion.
[0084] iAfter the formwork is installed, its plane position, top elevation, and longitudinal and lateral stability should be inspected and accepted. The installed formwork should be firmly fixed to avoid displacement during concrete pouring.
[0085] The concrete work for steps five and seven needs to be done as follows:
[0086] 1. Inspection before concrete pouring
[0087] (1) Before pouring concrete, the interior of the formwork must be inspected. Holes left for draining flushing water and pouring concrete should be easily closed before and during pouring. All bolts, pipes, iron parts or other embedded parts should be fixed in the correct position before pouring concrete. No holes may be opened on any concrete formwork without the prior consent of the project supervisor. Concrete pouring can only begin after the project supervisor has inspected the installed formwork and obtained his consent.
[0088] (2) Before pouring concrete, clean out debris and dust from the cavity at the bottom of the formwork and apply a release agent to the formwork. However, the release agent must not be applied to the steel bars and other embedded parts. Before using the release agent, submit it to the project supervisor for inspection and approval.
[0089] (3) Before pouring concrete, after passing the self-inspection, report to the project supervisor for inspection of all formwork. The allowable deviation of formwork installation must comply with the requirements of relevant specifications.
[0090] (4) Before pouring concrete, relevant personnel including the concrete pump station should be organized to conduct a briefing. The contents of the briefing include: the name and characteristics of the structure, the quantity of concrete, the strength grade, the slump requirements, the pouring method, the pouring time, the interval time for concrete transportation, etc.
[0091] 2. Concrete pouring
[0092] (1) Structural concrete should be poured in layers, with each pouring thickness controlled at about 30 cm. When vibrating the upper layer of concrete, the vibrating rod should be inserted into the lower layer of concrete at the same time. The top layer of concrete should be vibrated twice to avoid loose top.
[0093] (2) Concrete vibration should be carried out using an inserted vibrating rod. The vibration points should be evenly distributed and follow the principle of fast insertion and slow withdrawal to ensure that no vibration is missed or exceeded.
[0094] (3) Construction joint treatment should remove the floating slurry, loose stones and weak concrete layer on the hardened concrete surface; before pouring, the old concrete surface should be moistened with water, but no water should be left on the concrete surface.
[0095] (4) The concrete used in this project is self-mixed concrete. The slump of non-pump concrete is 140±20mm, and the slump of pumped concrete is 150±20mm.
[0096] Concrete curing is natural curing. Natural curing is divided into watering and plastic film curing. The former involves covering the concrete with straw mats and frequently watering it to keep it moist. The latter is suitable for high-rise structures and large concrete structures where watering is difficult. After pouring, the film is applied to the surface layer to isolate the concrete from air, preventing water evaporation and ensuring normal cement hydration.
[0097] A cast-in-place formwork for a panel-free construction process of a channel concrete breast wall with a steel face, comprising a cap formwork and a breast wall formwork, wherein the breast wall formwork is placed on one side of the cap formwork;
[0098] The platform formwork consists of side panels 1 on both sides, a template 2 with a panel, and a tail plate 3. Multiple sets of templates 2 are spliced together to form the water-facing surface, and multiple tail plates 3 are spliced together to form the water-repelling surface. There are mounting beams on the outside of the templates 2 and tail plates 3. Connecting rods 4 pass through the mounting beams on the outside of the end plates 2 and tail plates 3 and are locked with nuts.
[0099] The breast wall formwork includes two sets of front and rear mounting beams. Multiple sets of formwork 2 5 are spliced together to form the water-facing surface, and multiple sets of formwork 3 6 are spliced together to form the water-repelling surface. The connecting rod 2 7 passes through the mounting beams on the outside of formwork 2 5 and formwork 3 6 and is locked with nuts. There are side panels 2 8 at both ends of formwork 2 5 and formwork 3 6.
[0100] This panel-free construction process for the concrete breast wall of the steel-faced channel uses a cast-in-place formwork. The pedestal formwork and the breast wall formwork are spliced by corresponding formworks. After the formworks are stacked, the main bodies of the pedestal formwork and the breast wall formwork are formed respectively. On the side facing the water surface, formwork 1 2 and formwork 2 5 are steel membranes of the panel. When pouring, the surface of the breast wall is directly formed. There are multiple connecting rods 1 4 and connecting rods 2 7 on both sides of this formwork, which are locked with nuts, and ten groups of purlins are arranged on the outside of formwork 2 5 for support to ensure the strength of the entire formwork.
[0101] Finally, a few points should be explained: First, in the description of this application, it should be noted that, unless otherwise specified or limited, the terms "mounted," "connected," and "connected" should be understood in a broad sense, and may refer to mechanical or electrical connections, internal communication between two components, or direct connection. "Up," "down," "left," and "right" are only used to indicate relative positional relationships. When the absolute positions of the objects being described change, the relative positional relationships may also change.
[0102] Secondly: The drawings of the embodiments disclosed in the present invention only involve structures related to the embodiments disclosed in the present invention. Other structures may refer to conventional designs. The same embodiment and different embodiments of the present invention may be combined with each other without conflict.
[0103] Finally: The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A panel-free construction process for a steel-faced channel concrete breast wall, characterized in that: The process includes the following steps:
1. Construction preparation, measurement and layout; 2. Construction of cushion layer; 3. Steel bar binding; 4. Installation of the foundation formwork and protective surface; 5. C30 cap concrete pouring; 6. Installation of breast wall formwork and facing; 7. C30 breast wall concrete pouring; 8. Concrete maintenance; In step one, measurement and laying out of materials need to be carried out according to the requirements of the design drawings and the elevation control points to determine the elevation of the facing concrete and the axis position, and earth excavation is required. The steel bar raw materials have a factory certificate and are put into use after passing the laboratory inspection. According to the revetment section design drawing, the excavation boundary is delineated, and the site is cleaned by an excavator in conjunction with earth-moving transport vehicles to remove obstacles and silt within the excavation range, and the excavation path to the foundation pit is laid, and protection is provided between the excavation path and the foundation pit slope.
2. A panel-free construction process for a steel-faced channel concrete breast wall according to claim 1, characterized in that: In step 2, the geology along the line is basically silty clay and silty clay. Therefore, when the foundation pit is excavated, a combination of open ditch drainage is adopted. A sump is set up in each construction trench section. During the construction period, drainage measures for the foundation trench are completed to prevent the revetment foundation pit from being disturbed and soaked in water during construction. During the foundation pit construction, a sump is set up at the bottom of the foundation pit, and drainage ditches are excavated around the bottom of the pit to allow water to flow into the sump, and then water is pumped out with a water pump. The foundation pit earthwork adopts the step excavation method. The specific stratification is determined according to the excavation depth of each revetment foundation pit. The earthwork is transported by dump trucks, and the foundation pit soil transportation access road adopts a slope with a slope ratio of 1:10 to connect to the top of the slope road. Backfill construction behind the wall can only be carried out when the concrete strength of the wall is greater than 80%. The backfill soil must be selected from clay with a better surface layer. It is strictly forbidden to use cultivated soil and silt soil for backfilling.
3. The panel-free construction process of a steel-faced channel concrete breast wall according to claim 1 is characterized by: In step three, the steel bars are piled on a flat ground, padded with square wood underneath and completely covered with plastic film to prevent surface rust. The lap joints of the steel bars meet the requirements of the specifications and do not exceed 50% on the same section. To ensure the protective layer of the steel bars, shaped concrete pads are used to ensure that the steel bars are not exposed and to prevent deformation of the steel mesh.
4. The panel-free construction process of a steel-faced channel concrete breast wall according to claim 1 is characterized by: In step four, the base formwork is divided into four pieces at a height and connected using angle steel.
5. The panel-free construction process of a steel-faced channel concrete breast wall according to claim 1 is characterized by: In step six, the breast wall formwork is a universal formwork with a length of 9.88m. The front wall formwork also has only horizontal and vertical purlins, and the steel facing can be used as the panel.
6. The panel-free construction process of a steel-faced channel concrete breast wall according to claim 1 is characterized by: In step 5 and step 7, the structural concrete should be poured in layers, and the thickness of each pouring should be controlled at about 30cm. When vibrating the upper layer of concrete, the vibrating rod should be inserted into the lower layer of concrete at the same time, and the top layer of concrete should be vibrated twice to avoid loose top phenomenon; Concrete vibration is carried out using an inserted vibrating rod. The vibration points should be evenly distributed, following the principle of fast insertion and slow withdrawal to ensure that no vibration is missed or over-vibrated. When treating construction joints, the floating slurry, loose stones and weak concrete layers on the hardened concrete surface should be removed; before pouring, the old concrete surface should be moistened with water, but no water should be left on the concrete surface.
7. The panel-free construction process of a steel-faced channel concrete breast wall according to claim 1 is characterized by: In step eight, after the concrete is poured, the cement gradually hardens under the action of hydration, and the hydration requires appropriate temperature and humidity to ensure that the concrete has suitable hardening conditions and ensures that its strength continues to increase.
8. A cast-in-place formwork for a panel-free construction process of a steel-faced channel concrete breast wall according to any one of claims 1 to 7, characterized in that: It includes a cap formwork and a breast wall formwork, wherein the breast wall formwork is placed on one side of the cap formwork; The cap formwork is composed of side plates (1) on both sides, a template (2) with a panel, and a tail plate (3). Multiple sets of templates (2) are spliced to form a water-facing surface, and multiple tail plates (3) are spliced to form a water-repelling surface. The outer sides of the templates (2) and the tail plates (3) are provided with mounting beams. A connecting rod (4) passes through the mounting beams on the outer sides of the end plates (2) and the tail plates (3) and is locked with nuts. The breast wall formwork comprises two groups of front and rear mounting beams. A plurality of groups of templates 2 (5) are spliced together to form a water-facing surface, and a plurality of groups of templates 3 (6) are spliced together to form a water-repelling surface. A connecting rod 2 (7) passes through the mounting beams outside the templates 2 (5) and 3 (6) and is locked with nuts. Side plates 2 (8) are provided at both ends of the templates 2 (5) and 3 (6).