Under-pressure bin opening method for shield tunneling machine in highly permeable stratum
By adopting normal pressure method and dual-liquid grouting technology in shield tunnel construction, the safety and geological risk problems caused by pressure fluctuations during the pressure opening are solved, and the construction safety and environmental protection effect are improved.
Patent Information
- Application Number
- CN202410993978.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-10-15
AI Technical Summary
The existing method of opening the chamber under pressure during shield construction involves pressure fluctuations, which may lead to safety risks for equipment and personnel, and pressure changes on groundwater and soil may cause geological disaster risks.
The normal pressure method is used to open the warehouse. Through steps such as shield tail sealing, closed water test, gas detection and double-liquid grouting, the excavation surface is stabilized and pressure fluctuations are reduced. Polyurethane chemical slurry and cement-water-glass double-liquid grout are used for the operation. Sealing, controlling grouting pressure, preventing breakdown and consolidation.
It effectively avoids safety risks caused by pressure fluctuations, reduces emergencies, improves operational safety, reduces pressure changes on groundwater and soil, protects the surrounding environment, and avoids geological disaster risks.
Smart Images

Figure CN118774848A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a method for opening a chamber under pressure for a shield machine in a highly permeable stratum. Background Art
[0002] Shield construction is a multi-process single-flow cycle construction mode, which is mainly reflected in the construction management technology level and process connection. The shield construction environment is complex and the construction intensity is high. The construction mode is 12-hour shift continuous construction. The shield opens the chamber under pressure. Because of its good practicality in complex formation environments with poor self-stability and high permeability, it has been widely used in shield tunnel construction. However, the current pressurized opening method still has some shortcomings: for example, the pressure fluctuation of the pressurized opening method can easily bring safety risks to equipment and personnel.
[0003] Therefore, it is necessary to provide a new method for opening the shield machine under pressure in highly permeable strata to solve the above technical problems. Summary of the invention
[0004] The technical problem solved by the present invention is to provide a method for opening a shield machine under pressure in a highly permeable stratum, which can effectively avoid the safety risks of equipment and personnel caused by pressure fluctuations, reduce the possibility of emergencies, and thus improve the safety of operations. At the same time, it can also reduce the pressure changes on groundwater and soil, effectively protect the surrounding environment, and avoid the risks of geological disasters caused by pressure changes.
[0005] In order to solve the above technical problems, the present invention provides a method for opening a shield machine under pressure in a highly permeable stratum, comprising the following steps:
[0006] Step 1: Preparation for opening a position:
[0007] S1. Shield tail seal, observe whether the shield tail drilling hole is leaking, as follows:
[0008] 1). If there is no water seepage, there is no need to construct a sealing water stop ring;
[0009] 2). If there is water seepage, perform secondary grouting on the 4-7 ring segments behind the shield tail to form a sealed water stop ring to ensure that the water seepage is no more than 0.5m 3 / h;
[0010] S2. The auxiliary method for water stopping at the rear of the shield should adopt a grouting method that combines step 2) synchronous grouting, secondary grouting behind the segment and radial grouting of the shield, and it needs to comply with regulations;
[0011] Step 2: Open a position:
[0012] S1. Preliminary determination of the geological stability of the tunnel face based on geological survey data combined with shield tunneling and slag discharge conditions, and selection of a suitable opening position;
[0013] S2. After determining the opening position, stop the machine and rotate the screw conveyor to reduce the silo to 1 / 3. After the silo is lowered, conduct a water-tightening test and observe the changes in the liquid level in the silo.
[0014] S3. Close the slag outlet of the screw machine and the air inlet valve, let it stand for 2 hours, and observe the changes in the liquid level in the bin. If the liquid level changes within 0.5m 3 / h, it can be determined that there is no water leakage on the face;
[0015] S4. After the water-tightness test is completed, the pressure in the chamber should be gradually reduced to zero, and the earth pressure sensor should be observed for about 1 hour. If there is no change in the earth pressure sensor, it proves that the excavation surface is relatively stable;
[0016] S5. After confirming that the excavation surface is stable, arrange professional inspection personnel to conduct gas inspection in the warehouse;
[0017] S6. After the gas detection is passed, the warehouse should be ventilated immediately. After the ventilation is completed, gas detection should be carried out again. After meeting the requirements, the warehouse can be entered for operation. Continuous ventilation should be maintained during the operation in the warehouse, and the gas should be tested once every hour during the construction work in the warehouse.
[0018] As a further solution of the present invention, the grouting uses cement and water glass double liquid slurry for plugging, and the grouting pressure is controlled during plugging to prevent the shield tail from being penetrated or the slurry from being injected into the cutter head.
[0019] As a further solution of the present invention, the step S2 is defined as follows:
[0020] 1). The synchronous grouting should be full and fill the over-excavation gap;
[0021] 2) The secondary grouting behind the segment should adopt double liquid slurry, but at least 4 to 7 full ring segments behind the shield tail should be blocked;
[0022] 3). Polyurethane chemical slurry should be used for radial grouting of the shield to form a closed water stop outside the shield shell;
[0023] 4). Grouting consolidation of the shield should be prevented.
[0024] As a further solution of the present invention, during the water-tightness test, no pressurization or decompression operation is performed, and the test is performed at normal pressure, and the water-tightness test is for 2 hours.
[0025] As a further solution of the present invention, the warehouse is ventilated using a portable axial flow fan, the diameter of the air duct used by the portable axial flow fan is 300, and the ventilation time is 30 minutes.
[0026] As a further solution of the present invention, the geological survey data analysis steps are as follows:
[0027] (1) Geological map analysis: Based on the geological maps in the geological survey data, understand the stratigraphic structure, lithology, and geological structure information of the tunnel face, and make a preliminary judgment on the stratigraphic stability and possible geological risk points by analyzing the maps;
[0028] (2) Analysis of soil physical and mechanical properties: Based on the results of geotechnical tests, analyze the physical and mechanical properties of the soil layer, such as moisture content, internal friction angle, and cohesion, so as to preliminarily determine the stability of the soil layer and possible deformation;
[0029] (3) Analysis of groundwater level: The height and changes of groundwater level have a great impact on the stability of soil layer. Based on the groundwater level data in geological survey data, it can be preliminarily judged whether there is a risk of water inrush.
[0030] As a further solution of the present invention, the steps for conducting on-site judgment on the shield tunneling and slag discharge conditions are as follows:
[0031] (1) Slag discharge statistics: Statistics on the slag discharge during shield tunneling, combined with the stratum thickness in geological survey data, can be used to preliminarily determine whether the stratum has collapsed or has abnormal water inrush;
[0032] (2) Slag sample analysis: Detailed observation and analysis of the slag samples to understand the color, structure and composition of the soil layer, so as to preliminarily determine the nature and stability of the soil layer;
[0033] (3) Monitoring of the working status of the tunnel boring machine: By monitoring the propulsion speed, tunneling force and torque parameters of the tunnel boring machine, the geological stability of the tunnel face can be preliminarily judged. If abnormal parameter changes occur, it may indicate that there are geological risks on the tunnel face.
[0034] As a further solution of the present invention, before the warehouse is opened, it is necessary to compare the slag samples of the slag discharged from the slag soil with the existing geological exploration data to see whether they are consistent with the detailed geological exploration data.
[0035] As a further solution of the present invention, the gas detection in the warehouse is carried out at the opening of the partition of the excavated warehouse wall, and the warehouse operation can only be carried out after passing the inspection.
[0036] As a further solution of the present invention, the gas detection in the warehouse also includes living body detection, the living body is poultry, and the poultry is placed in the warehouse for observation for 10 to 30 minutes.
[0037] Compared with the related art, the method for opening the shield machine under pressure in highly permeable strata provided by the present invention has the following beneficial effects:
[0038] 1. The present invention adopts normal pressure to open the warehouse, which can effectively avoid the safety risks of equipment and personnel caused by pressure fluctuations, reduce the possibility of emergencies, thereby improving the safety of operations, and at the same time reduce the pressure changes on groundwater and soil, effectively protect the surrounding environment, and avoid the risk of geological disasters caused by pressure changes. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.
[0040] Figure 1 It is a schematic diagram of the process of the present invention;
[0041] Figure 2 It is a schematic diagram of gas content requirements in the present invention;
[0042] Figure 3 It is a schematic diagram of drilling and grouting in the present invention. DETAILED DESCRIPTION
[0043] Please refer to Figure 1 , Figure 2 and Figure 3 ,in, Figure 1 It is a schematic diagram of the process of the present invention; Figure 2 It is a schematic diagram of gas content requirements in the present invention; Figure 3 The method for opening the shield machine under pressure in a highly permeable stratum comprises the following steps:
[0044] Step 1: Preparation for opening a position:
[0045] S1. Shield tail seal, observe whether the shield tail drilling hole is leaking, as follows:
[0046] 1). If there is no water seepage, there is no need to construct a sealing water stop ring;
[0047] 2). If there is water seepage, perform secondary grouting on the 4-7 ring segments behind the shield tail to form a sealed water stop ring to ensure that the water seepage is no more than 0.5m 3 / h;
[0048] S2. The auxiliary method for water stopping at the rear of the shield shell should adopt a grouting method that combines step 2) synchronous grouting, secondary grouting behind the segments and radial grouting of the shield body, and must comply with regulations.
[0049] The sealing water stop ring adopts double liquid slurry, and the double liquid slurry is injected into the 4-7 ring formed tunnels behind the shield tail through the grouting holes of the pipe segment to block the water coming from the rear of the pipe segment and increase the stability of the formed tunnel near the shield tail.
[0050] Verification of water-stopping effect: After the water-sealing construction is completed, check the water-stopping effect of the shield tail grouting, and check the holes of the 4-7 ring water-sealing rings. The holes must be opened at the top and bottom. The top hole point is located in the 11 o'clock to 1 o'clock area, and the bottom hole point is located in the 5 o'clock to 7 o'clock area (it can be adjusted appropriately according to the on-site conditions). There can be dripping after the holes are opened, but it must not form a linear flow. Otherwise, it is judged that the shield tail water-stopping cannot meet the construction requirements, and secondary grouting construction must be carried out again. The secondary grouting will continue 1 to 2 rings after the current water-sealing ring construction. The grouting position is preferably started from the leakage site.
[0051] Shield body grouting: polyurethane is injected into the shield shell through the radial holes of the shield body to form a closed waterstop outside the shield shell, which serves as the second waterstop ring. During construction, grouting should be prevented from consolidating the shield body.
[0052] 24 hours before grouting, sodium-based bentonite slurry (bentonite: water = 1:1.2) is continuously injected from the injection holes on the shield through the bentonite system of the shield. The pressure is slightly greater than the pressure in the silo, and a protective layer of sodium-based bentonite is formed on the shield.
[0053] Grouting uses an electric rock drill with a drill rod of Φ32mm and a drill bit of Φ42mm. Through the 6 advance holes reserved on the shield, the depth of the drill is 12-15 meters. The double-liquid grouting is carried out in stages to consolidate the formation and seal the fissure water in the formation. After the drill is fixed to the position of the segment assembly machine, the drill angle is adjusted to make it consistent with the advance hole angle, and then the next process can be carried out.
[0054] The drilling operation begins. During the drilling process, water is injected into two pipes at the same time to prevent blockage of the drill rod and to reduce the temperature of the drill rod. During the drilling process, the corresponding number of drill rods can be connected according to the scope of the advance grouting reinforcement.
[0055] Drilling depth is 12-15m, injecting 0.15m 3 Rinse the grouting pipe thoroughly with water.
[0056] Double-liquid slurry mix ratio: The water-cement ratio of cement slurry is prepared at 1.5-1:1, and the water glass stock solution is diluted at 1:4 before use. When injecting double-liquid grouting, cement slurry and water glass are mixed and injected at a ratio of 2:1. In addition, 1-3% of early strength agent is added to the cement slurry.
[0057] The grouting pressure is controlled at 1-1.5mpa, and backward grouting is adopted. After the double-liquid slurry is injected, the soil bin pressure rises to 3.0bar. Stop grouting and observe. At the same time, rotate the cutter head at a speed of 0.5r / min. If the soil bin pressure drops, continue grouting. During the grouting process, rotate the drill rod every 3 minutes or so to prevent it from being wrapped by the slurry. Each rotation of the drill rod should be no less than 8 turns. In sequence, until the soil bin pressure rises to 3.0bar, according to the soil bin pressure and fluctuation size, pull out about 10cm and grout again. Repeat the above operations until the drill rod is withdrawn. Grouting until the soil bin pressure rises to 3.0bar, continue to observe for 15 minutes until the soil bin pressure is basically stable, and then end grouting.
[0058] Precautions for advance grouting are as follows:
[0059] (1) Due to the limited space in the tunnel, in order to ensure safety during construction, the drilling rig is fixed to the middle of the segment assembly machine by bolt connection. The segment assembly machine can be rotated and the longitudinal angle can be adjusted to avoid setting up racks in the tunnel and ensure sufficient working space;
[0060] (2) Before drilling, make a sealing device for the advance grouting hole and connect it to the advance hole with a flange. The sealing device has a reserved ball valve and is connected with a hose to collect the mud and slurry generated by drilling. After the grouting operation is completed, it is sealed with a flange cover immediately;
[0061] (3) Before stopping the machine for grouting, first fill the shield body with bentonite and perform secondary grouting at the shield tail;
[0062] (4) During the advance grouting process, arrange the shield driver to stay in the shield operation room to observe the changes in the soil pressure in the soil bin. If the soil bin pressure increases, immediately stop the grouting operation and fill the drilled hole with slurry;
[0063] (5) During the advance grouting operation, the slurry was not prevented from entering the soil bin and blocking the cutter disc, cutter box or jamming. The cutter disc was started every 12 hours and rotated slightly;
[0064] During the entire advance grouting operation, the ground must monitor 24 hours a day and keep communication with the tunnel open. After each monitoring is completed, the monitoring data is analyzed and fed back to the driver on duty in the operation room in a timely manner, so that the grouting pressure and grouting volume can be adjusted reasonably in time, truly achieving information-based guidance for construction operations.
[0065] The mud film wall protection is used to assist the pressure operation. Sodium-based bentonite is used when applying the mud film wall protection. The specific method is as follows:
[0066] The construction adopts stepped mud pressure and mud of different grades of performance to make mud film, with the aim of increasing the permeability of mud, making the mud particles penetrate into the soil layer as much as possible and as far as possible, thus forming a thicker mud film.
[0067] The viscosity of the mud increases gradually during the mud film making process (to ensure that the formation cracks in front of the tunnel face can be filled by the filling effect of the high-viscosity mud, ensuring the safety of pressure opening). The proportion of the high-viscosity mud can be appropriately adjusted according to the actual effect of the mud film on the tunnel face checked by the pressure opening personnel, so as to ensure the quality of the mud film.
[0068] The slurry materials used to make mud film must be easy to mix, highly viscous, and have a high slurry making rate. The mixing of the slurry can be completed in a slurry barrel. The concentration of the slurry should be as thick as possible while ensuring its injectability. If necessary, add an appropriate amount of thickener, and the slurry viscosity should not be less than 80s.
[0069] After the slurry is completely dissolved, the bentonite system of the shield machine is used to pump it directly from the foam injection hole on the cutterhead and the reserved holes on the front shield partition to the tunnel face and soil bin, and simultaneously replace the debris in the excavation bin.
[0070] After the bentonite replacement is completed, the cutter head should be rotated slowly for stirring, and then the mud should be left to stand and the pressure in the excavation bin should be appropriately increased to allow the slurry to evenly penetrate the face and establish a mud film. After the pressure holding time is reached, the height of the slag or mud in the excavation bin should be lowered as required, and the quality of the mud film should be preliminarily judged based on the changes in the pressure and air supply volume in the bin.
[0071] When high-viscosity mud is injected to replace the slag, a screw conveyor is used to discharge the slag from the bottom of the soil bin, and the manual gas injection system is started at the same time. When adding gas, the size of the manual valve is adjusted according to the pressure changes in the soil bin to ensure that the pressure in the soil bin is stable. After 2 / 3 of the slag in the soil bin is discharged, the screw conveyor is immediately stopped to discharge the slag, and bentonite mud is injected into the top of the soil bin through the bentonite system. While adding bentonite, the manual gas injection is gradually closed. After the bentonite fills 2 / 3 of the volume of the soil bin, the pressure is maintained. During the injection process, the pressure in the bin should be basically stable. After the injection is completed, the cutter head should be rotated at a low speed for half an hour and the pressure should be maintained for 2 to 3 hours. At the same time, the pressure in the soil bin is continuously monitored. When the pressure drops, bentonite is added in time. The pressure is always basically stable. During the replacement process, the pressure in the bin should be 0.1 to 0.3 bar higher than the pressure entering the bin.
[0072] The mud film pressurization selects the graded pressurization method. The final pressurization pressure of the mud should be 1.1-1.3 times higher than the working pressure. During the construction process, it is divided into four stages of pressurization. The pressurization is carried out by injecting a small amount of mud multiple times, each stage is 0.2bar, that is, 2.4-2.6bar, 2.6-2.8bar, 2.8-3.0bar. The first two stages are dynamically pressurized for 2 hours, and the last stage is pressurized for 6 hours. During the pressure stabilization process, if the pressure does not drop to the starting pressure value within the specified pressure stabilization time, it means that the graded pressurization of this section is successful. During the 2.8-3.0bar graded pressurization process, the shield retreats 6-8cm to ensure that the bentonite forms a mud wall at the tunnel face position to ensure the stability of the tunnel face. It is guaranteed that the cutter head is slowly rotated twice per shift at a speed of 0.1-0.5rpm to ensure that the mud wall is formed at the tunnel face position. Try not to rotate the cutter head during the last stage of pressurization.
[0073] Before the air pressure operation, a pressure holding test should be carried out. The slag should be discharged before opening the warehouse, and gas should be added for replacement. When the pressure in the excavation warehouse reaches the preset value (the preset value shall not be lower than the calculated theoretical working pressure), the automatic pressure holding system is turned on. When the soil in the warehouse is lowered to the set height, if the excavation warehouse pressure remains unchanged for 2 hours or does not fluctuate greatly, it indicates that the pressure holding test is qualified. Before determining the air pressure and preparing for air compression, make sure that the amount of grease and mortar injected into the shield tail is sufficient to ensure that there is no leakage.
[0074] The pressure-maintaining operation process is as follows: when the pressurization pressure reaches 3.0 bar (the planned working pressure is 2.4 bar, and the pressurization is divided into three stages, and the final pressure is 1.1-1.3 times the working pressure), the high pressure state is maintained for 6 hours to ensure the formation of a sufficiently thick mud film. During the pressure-maintaining process, appropriate mud is retained in the slurry storage tank, and uninterrupted observation is maintained in the control room. After the mud has a certain degree of penetration under high pressure, the pressure will drop. At this time, it is necessary to replenish the cabin until the pressure returns to the maximum allowable pressure. The pressure change during the pressure-maintaining process should be less than 0.5 bar. When it is greater than 0.5 bar, the mud film must be re-applied. After the mud film is applied, the pressure-maintaining test is carried out again.
[0075] After 6 hours of pressure maintenance and continuous grouting, the mud film has formed to a certain scale. Whether the formed mud film can provide the protection during pressure operation requires a preliminary judgment through mud film inspection.
[0076] Step 2: Open a position:
[0077] S1. Preliminary determination of the geological stability of the tunnel face based on geological survey data combined with shield tunneling and slag discharge conditions, and selection of a suitable opening position;
[0078] S2. After determining the opening position, stop the machine and rotate the screw conveyor to reduce the silo to 1 / 3. After the silo is lowered, conduct a water-tightening test and observe the changes in the liquid level in the silo.
[0079] S3. Close the slag outlet of the screw machine and the air inlet valve, let it stand for 2 hours, and observe the changes in the liquid level in the bin. If the liquid level changes within 0.5m 3 / h, it can be determined that there is no water leakage on the face;
[0080] S4. After the water-tightness test is completed, the pressure in the chamber should be gradually reduced to zero, and the earth pressure sensor should be observed for about 1 hour. If there is no change in the earth pressure sensor, it proves that the excavation surface is relatively stable;
[0081] S5. After confirming that the excavation surface is stable, arrange professional inspection personnel to conduct gas inspection in the warehouse;
[0082] S6. After the gas detection is passed, the warehouse should be ventilated immediately. After the ventilation is completed, gas detection should be carried out again. After meeting the requirements, the warehouse can be entered for operation. Continuous ventilation should be maintained during the operation in the warehouse, and the gas should be tested once every hour during the construction work in the warehouse.
[0083] The grouting adopts cement and water glass double liquid slurry for plugging, and the grouting pressure is controlled during plugging to prevent the shield tail from being penetrated or the slurry from being injected into the cutter head.
[0084] The step S2 is defined as follows:
[0085] 1). The synchronous grouting should be full and fill the over-excavation gap;
[0086] 2) The secondary grouting behind the segment should adopt double liquid slurry, but at least 4 to 7 full ring segments behind the shield tail should be blocked;
[0087] 3). Polyurethane chemical slurry should be used for radial grouting of the shield to form a closed water stop outside the shield shell;
[0088] 4). Grouting consolidation of the shield should be prevented.
[0089] 4. The method for opening a shield machine under pressure in highly permeable strata according to claim 1 is characterized in that: during the water-tightness test, no pressurization or decompression operation is performed, the test is performed at normal pressure, and the water-tightness test is for 2 hours.
[0090] The warehouse is ventilated by a portable axial flow fan, the diameter of the air duct used by the portable axial flow fan is 300, and the ventilation time is 30 minutes.
[0091] The steps of analyzing the geological survey data are as follows:
[0092] (1) Geological map analysis: Based on the geological maps in the geological survey data, understand the stratigraphic structure, lithology, and geological structure information of the tunnel face, and make a preliminary judgment on the stratigraphic stability and possible geological risk points by analyzing the maps;
[0093] (2) Analysis of soil physical and mechanical properties: Based on the results of geotechnical tests, analyze the physical and mechanical properties of the soil layer, such as moisture content, internal friction angle, and cohesion, so as to preliminarily determine the stability of the soil layer and possible deformation;
[0094] (3) Analysis of groundwater level: The height and changes of groundwater level have a great impact on the stability of soil layer. Based on the groundwater level data in geological survey data, it can be preliminarily judged whether there is a risk of water inrush.
[0095] The steps for on-site judgment of the shield tunneling and slag discharge are as follows:
[0096] (1) Slag discharge statistics: Statistics on the slag discharge during shield tunneling, combined with the stratum thickness in geological survey data, can be used to preliminarily determine whether the stratum has collapsed or has abnormal water inrush;
[0097] (2) Slag sample analysis: Detailed observation and analysis of the slag samples to understand the color, structure and composition of the soil layer, so as to preliminarily determine the nature and stability of the soil layer;
[0098] (3) Monitoring of the working status of the tunnel boring machine: By monitoring the propulsion speed, tunneling force and torque parameters of the tunnel boring machine, the geological stability of the tunnel face can be preliminarily judged. If abnormal parameter changes occur, it may indicate that there are geological risks on the tunnel face.
[0099] Before the warehouse is opened, it is necessary to compare the existing geological exploration data with the slag samples of the slag soil to see whether they are consistent with the detailed geological exploration data.
[0100] The gas detection in the warehouse is carried out at the opening of the partition of the excavated warehouse wall. Only after passing the test can the warehouse be entered for operation.
[0101] The gas detection in the warehouse also includes living body detection, where the living body is poultry, and the poultry is placed in the warehouse for observation for 10 to 30 minutes.
[0102] According to the groundwater level and geological conditions, determine the air pressure that needs to be maintained in the warehouse when entering the warehouse.
[0103] All shield pressure-maintaining systems must be in normal operation and on standby: the airlock system, low-pressure air system, and all required grouting and discharging ports must be in working order;
[0104] Confirm the stability of the formation. In unstable formations, high-viscosity bentonite should be added to form a thin film on the tunnel face to form a closed space inside the soil bin.
[0105] During operation, ensure that the air compressor works normally and can provide sufficient air supply. Before operation, the gas content in the warehouse must be checked to ensure that there is no toxic gas and sufficient oxygen content;
[0106] Check and confirm the performance and reliability of various instruments, buttons, switch valves, and lighting facilities installed inside and outside the pressure chamber; calibrate all instruments entering the chamber under pressure to ensure the accuracy of the instruments and the integrity of the seal inside the chamber;
[0107] Debug the sealing performance of the man warehouse, pressure-maintaining system and soil warehouse;
[0108] Check the conditions of the wind, water and electrical circuits of the shield machine, and ensure the normal operation of the fan outside the tunnel and the smooth flow of air inside the tunnel.
[0109] According to the technical specifications for shield tunneling and pneumatic operation, the formula for calculating the working pressure of pneumatic operation is as follows:
[0110] P=P W +P T
[0111] Where: P W —Calculate the head pressure to the center of the tunnel excavation;
[0112] P T —Pressure adjustment value considering different geological conditions, ground environment and excavation face position;
[0113] Where: P W = ρgh
[0114] The present invention adopts normal pressure to open the warehouse, which can effectively avoid the safety risks of equipment and personnel caused by pressure fluctuations. Compared with opening the warehouse under pressure, normal pressure operation is more stable in environmental control, reduces the possibility of emergencies, and thus improves the safety of operations. At the same time, normal pressure opening can also reduce the pressure changes on groundwater and soil, and effectively protect the surrounding environment. This is in line with the current trend of environmental protection, and also avoids the risk of geological disasters caused by pressure changes.
[0115] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A method for opening a shield machine under pressure in a highly permeable stratum, characterized in that: The following steps are involved: Step 1: Preparation for opening a position: S1. Shield tail seal, observe whether the shield tail drilling hole is leaking, as follows: 1). If there is no water seepage, there is no need to construct a sealing water stop ring; 2). If there is water seepage, perform secondary grouting on the 4-7 ring segments behind the shield tail to form a sealed water stop ring to ensure that the water seepage is no more than 0.5m 3 / h; S2. The auxiliary method for water stopping at the rear of the shield should adopt a grouting method that combines step 2) synchronous grouting, secondary grouting behind the segment and radial grouting of the shield, and it needs to comply with regulations; Step 2: Open a position: S1. Preliminary determination of the geological stability of the tunnel face based on geological survey data combined with shield tunneling and slag discharge conditions, and selection of a suitable opening position; S2. After determining the opening position, stop the machine and rotate the screw conveyor to reduce the silo to 1 / 3. After the silo is lowered, conduct a water-tightening test and observe the changes in the liquid level in the silo. S3. Close the slag outlet of the screw machine and the air inlet valve, let it stand for 2 hours, and observe the changes in the liquid level in the bin. If the liquid level changes within 0.5m 3 / h, it can be determined that there is no water leakage on the face; S4. After the water-tightness test is completed, the pressure in the chamber should be gradually reduced to zero, and the earth pressure sensor should be observed for about 1 hour. If there is no change in the earth pressure sensor, it proves that the excavation surface is relatively stable; S5. After confirming that the excavation surface is stable, arrange professional inspection personnel to conduct gas inspection in the warehouse; S6. After the gas detection is passed, the warehouse should be ventilated immediately. After the ventilation is completed, gas detection should be carried out again. After meeting the requirements, the warehouse can be entered for operation. Continuous ventilation should be maintained during the operation in the warehouse, and the gas should be tested once every hour during the construction work in the warehouse.
2. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: The grouting adopts cement and water glass double liquid slurry for plugging, and the grouting pressure is controlled during plugging to prevent the shield tail from being penetrated or the slurry from being injected into the cutter head.
3. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: The step S2 is defined as follows: 1). The synchronous grouting should be full and fill the over-excavation gap; 2) The secondary grouting behind the segment should adopt double liquid slurry, but at least 4 to 7 full ring segments behind the shield tail should be blocked; 3). Polyurethane chemical slurry should be used for radial grouting of the shield to form a closed water stop outside the shield shell; 4). Grouting consolidation of the shield should be prevented.
4. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: During the water-tightness test, no pressurization or decompression operation is performed, and the test is carried out at normal pressure. The water-tightness test lasts for 2 hours.
5. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: The warehouse is ventilated by a portable axial flow fan, the diameter of the air duct used by the portable axial flow fan is 300, and the ventilation time is 30 minutes.
6. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: The steps of analyzing the geological survey data are as follows: (1) Geological map analysis: Based on the geological maps in the geological survey data, understand the stratigraphic structure, lithology, and geological structure information of the tunnel face, and make a preliminary judgment on the stratigraphic stability and possible geological risk points by analyzing the maps; (2) Analysis of soil physical and mechanical properties: Based on the results of geotechnical tests, analyze the physical and mechanical properties of the soil layer, such as moisture content, internal friction angle, and cohesion, so as to preliminarily determine the stability of the soil layer and possible deformation; (3) Analysis of groundwater level: The height and changes of groundwater level have a great impact on the stability of soil layer. Based on the groundwater level data in geological survey data, it can be preliminarily judged whether there is a risk of water inrush.
7. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: The steps for on-site judgment of the shield tunneling and slag discharge are as follows: (1) Slag discharge statistics: Statistics on the slag discharge during shield tunneling, combined with the stratum thickness in geological survey data, can be used to preliminarily determine whether the stratum has collapsed or has abnormal water inrush; (2) Slag sample analysis: Detailed observation and analysis of the slag samples to understand the color, structure and composition of the soil layer, so as to preliminarily determine the nature and stability of the soil layer; (3) Monitoring of the working status of the tunnel boring machine: By monitoring the propulsion speed, tunneling force and torque parameters of the tunnel boring machine, the geological stability of the tunnel face can be preliminarily judged. If abnormal parameter changes occur, it may indicate that there are geological risks on the tunnel face.
8. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: Before the warehouse is opened, it is necessary to compare the existing geological exploration data with the slag samples of the slag soil to see whether they are consistent with the detailed geological exploration data.
9. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: The gas detection in the warehouse is carried out at the opening of the partition of the excavated warehouse wall. Only after passing the test can the warehouse be entered for operation.
10. The method for opening a shield machine under pressure in a highly permeable stratum according to claim 1, characterized in that: The gas detection in the warehouse also includes living body detection, where the living body is poultry, and the poultry is placed in the warehouse for observation for 10 to 30 minutes.