Wind power plant high slope terrain finishing method based on sector distribution
Through the wind farm high-slope terrain modification method based on sector distribution, the high-slope terrain can be accurately judged and processed, which solves the impact of high-slope terrain on wind turbines, reduces construction costs and increases power generation, and realizes the realization of wind farm economy and safety.
Patent Information
- Application Number
- CN202410689158.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-30
- Publication Date
- 2024-10-15
AI Technical Summary
In the construction of wind farms, high slope terrain leads to increased local turbulence and wind speed loss, which affects the blade load and aerodynamic performance of wind turbines. Existing solutions are costly or affect power generation, and there are construction risks.
The wind farm high slope terrain modification method based on sector distribution is adopted. By mapping the micro-topography, calculating the high slope determination coefficient and comparing the construction amount of different modification methods, the modification method with the minimum construction amount is selected, including reducing the slope height, increasing Slope distance or reduce slope angle, accurately judge and handle high slope terrain.
It effectively reduces the impact of high slope terrain on wind turbines, reduces construction costs and wind farm construction costs, and improves power generation and project economy.
Smart Images

Figure CN118779558A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of micro-site selection for wind farms, and in particular relates to a method for modifying high slope terrain of a wind farm based on sector distribution. Background Art
[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] During the construction of a wind farm, due to the need to consider factors such as the layout of wind farm sites and land acquisition, some sites cannot be installed at the highest point of the local terrain, which will result in high slope terrain. When the airflow passes through the high slope terrain, the flow field will inevitably change, which leads to an increase in local environmental turbulence and a loss of local wind speed. If the wind turbine rotor is located in the local airflow affected by the high slope terrain, it will cause an increase in blade load and a loss of aerodynamic performance, and in some cases the blades will flap and oscillate violently.
[0004] In order to reduce the impact of high slope terrain, the following methods are generally used: First, increase the tower height so that the wind rotor is higher than the flow field area affected by the high slope terrain; second, perform sector management on the wind turbines, and reduce the load or even stop running in sectors with greater impact from high slope terrain. The first method is applicable before the wind turbine is installed. If the wind turbine is installed, the cost of increasing the tower height is too high. In addition, increasing the tower height will cause the base load to change, and customized design of individual units is required. The design cost, tower cost and installation cost are too high; the second method seriously affects the power generation of the unit, affects the income of the wind farm, and still has certain risks. Summary of the invention
[0005] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a method for high slope terrain trimming in a wind farm based on sector distribution. The method clarifies the trimming construction plan for the high slope terrain, and solves the problem that the impact of the high slope terrain on the wind turbine set is not obviously eliminated or the construction cost is high due to improper high slope terrain trimming methods.
[0006] In order to achieve the above object, the present invention is implemented through the following technical solutions:
[0007] In a first aspect, the present invention provides a method for modifying high slope terrain of a wind farm based on sector distribution, comprising the following steps:
[0008] Determine wind turbine locations in wind farms that may fall within high-slope terrain;
[0009] Map the micro-topography around the wind turbine location, collect terrain elevation data, and divide it into n sectors;
[0010] Obtain the wind turbine parameters and terrain parameters of each sector to determine whether the terrain is a high slope terrain;
[0011] If it is not a high slope terrain, no trimming is required. If it is a high slope terrain, the corresponding high slope terrain in each sector should be trimmed.
[0012] As a further technical solution, the location of wind turbines in the wind farm that may belong to high slope terrain is determined according to the height and inclination of the slope.
[0013] As a further technical solution, the location of wind turbines that may belong to high slope terrain is divided into sectors based on the north direction according to the set wind direction step, n≥72, and the wind direction step is not greater than 5°.
[0014] As a further technical solution, the wind turbine parameters are the minimum height of the wind turbine blade tip from the ground, and the terrain parameters are the height of the slope terrain relative to the wind turbine installation platform, the angle of the slope terrain relative to the wind turbine installation platform, and the distance from the center of the wind turbine foundation to the slope terrain.
[0015] As a further technical solution, a high slope terrain determination coefficient is calculated according to wind turbine parameters and terrain parameters, a high slope determination coefficient threshold α is set, and the high slope terrain is determined according to the high slope terrain determination coefficient.
[0016] As a further technical solution, the calculation formula of the high slope terrain determination coefficient is:
[0017]
[0018] Among them, A i , B i , C i is the high slope terrain determination coefficient, H is the distance between the lower blade tip and the ground, h i is the height of the slope terrain of the i-th sector relative to the wind turbine installation platform, is the angle of the slope terrain of the i-th sector relative to the wind turbine installation platform, x i is the distance from the center of the wind turbine foundation in the i-th sector to the slope terrain, where i = 1, 2, …, n.
[0019] As a further technical solution, the high slope determination coefficient threshold α=0, when A i >α or B i >α or C i >α, it is determined that the sector terrain does not belong to high slope terrain and does not need to be repaired; when A i <α and B i <α and C iWhen α is less than α, the terrain of the sector is determined to be a high slope terrain and needs to be repaired. The continuous sectors identified as high slope terrain are renumbered, marked as j, and counted sequentially from 1. The total number of sectors is recorded as m.
[0020] As a further technical solution, when trimming the corresponding high slope terrain in each sector, the construction volume of various different high slope terrain trimming methods is calculated, the construction volume calculation results of different high slope terrain trimming methods are compared, and the high slope terrain trimming method with the smallest construction volume is selected to trim the high slope terrain.
[0021] As a further technical solution, a variety of high slope terrain modification methods include:
[0022] Method 1: Excavate the high slope of the sector and reduce the slope height h of the jth sector belonging to the high slope terrain j , so that h j =H-10;
[0023] Method 2: Excavate the high slope of the sector and increase the distance x from the jth sector slope belonging to the high slope terrain to the center of the wind turbine foundation j , so that x j =10h j ;
[0024] Method 3: Excavate the high slope of the sector to reduce the angle of the jth sector slope belonging to the high slope terrain relative to the wind turbine installation platform make
[0025] As a further technical solution, the area calculation method is used to compare the earthwork excavation volume of various high slope terrain modification methods as the construction volume calculation result:
[0026] Method 1:
[0027] Method 2:
[0028]
[0029] Method 3:
[0030] Among them, S1, S2, S3 are the construction quantities calculated by high slope terrain modification methods 1, 2, and 3 respectively, j = 1, ..., m; h j is the slope height of the jth sector, h1j is the excavation height of the jth sector in method 1, y1 j is the width of the top of the slope after excavation of the jth sector in method 1, x j is the distance from the jth sector slope to the center of the wind turbine foundation, h2 j is the slope height close to the wind turbine after the jth sector is excavated in method 2, aj is the width of the jth sector from the top to the bottom, d j is the width of the slope at the height of the wind turbine engineering operation surface in the jth sector, b j is the distance from the top to the bottom of the slope close to the wind turbine in the jth sector, c j is the vertical distance from the jth sector to the top of the slope after excavation in method 3, j is the excavation angle of the jth sector using method 3, θ j is the angle of the jth sector slope relative to the wind turbine installation platform.
[0031] The beneficial effects of the present invention are as follows:
[0032] The method of the present invention proposes a method for determining high side slopes, provides a method for modifying high side slope terrain, converts a three-dimensional problem into two dimensions, calculates the construction volume of different high side slope terrain modification methods based on the sector distribution of wind turbines, selects the modification method with the minimum construction volume to eliminate the influence of high side slope terrain in the wind farm on the wind turbines, solves the problem of increased economic and time costs caused by blindly modifying high side slope terrain, increases the power generation of the wind farm, and reduces the construction cost of the wind farm.
[0033] The method of the present invention calculates the high slope terrain determination coefficient through the wind turbine parameters and the terrain parameters, and determines the high slope terrain according to the comparison between the high slope determination coefficient threshold and the high slope terrain determination coefficient, so as to realize the accurate determination of the high slope terrain.
[0034] The method of the present invention uses an area calculation method to compare the earth excavation volumes of a variety of high-slope terrain modification methods, and can accurately evaluate the engineering volumes of different high-slope terrain modification methods, and then select the modification method with the smallest engineering volume to modify the high-slope terrain, thereby reducing the construction volume of the high-slope terrain modification.
[0035] The present invention quantitatively analyzes the high-slope terrain, and only processes the high-slope terrain after determining that the terrain where the wind turbine is located is a high-slope terrain. At the same time, three high-slope terrain finishing methods and corresponding construction volume calculation methods are proposed. The high-slope terrain finishing method with the minimum construction volume is selected by calculating the construction volumes of different methods, thereby increasing the power generation of the wind farm, reducing the load of the wind turbine, avoiding the increase in the construction volume and earth excavation volume of the wind farm project due to the processing of the high-slope terrain, ensuring the economy of the project construction, reducing the cost of wind farm construction, and thus reducing the cost per kilowatt-hour of wind power projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0037] Figure 1 is a flow chart of a method for modifying high slope terrain of a wind farm based on sector distribution according to one or more embodiments of the present invention;
[0038] Figure 2 is a schematic diagram of a high slope terrain according to one or more embodiments of the present invention;
[0039] Figure 3 1 is a schematic diagram of a calculation method for high slope terrain modification according to one or more embodiments of the present invention (the shadow represents the modification area);
[0040] Figure 4 1 is a schematic diagram of a calculation method of a second high slope terrain modification method according to one or more embodiments of the present invention (the shadow indicates the modification area);
[0041] Figure 5 1 is a schematic diagram of a third calculation method of a high slope terrain modification method according to one or more embodiments of the present invention (the shadow indicates the modification area);
[0042] In the figure: the distances or sizes between parts are exaggerated to show the positions of various parts, and the schematic diagram is for illustration only. DETAILED DESCRIPTION
[0043] It should be noted that the following detailed descriptions are illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used in the present invention have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.
[0044] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the present invention explicitly states otherwise, singular forms are also intended to include plural forms. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0045] In a typical embodiment of the present invention, Figure 1 As shown, a high slope terrain modification method for a wind farm based on sector distribution is proposed, which includes the steps of calculating a high slope terrain determination coefficient, determining the high slope terrain, and calculating the construction volume of different high slope terrain modification methods.
[0046] This method can trim high slope terrain at a lower cost, reduce its impact on wind turbine rotors, and fill a gap in the industry.
[0047] Specifically, the method comprises the following steps:
[0048] S1. Determine the location of wind turbines in the wind farm that may belong to high slope terrain;
[0049] S2. Survey and map the micro-topography around the wind turbine location, collect terrain elevation data, and divide it into n sectors;
[0050] S3. Obtain the wind turbine parameters and terrain parameters of each sector, and determine whether the terrain is a high slope terrain;
[0051] S4. If it is not a high slope terrain, no trimming is required. If it is a high slope terrain, the corresponding high slope terrain in each sector is trimmed.
[0052] Among them, in this method, high slope terrain is a surface form generated by the excavation working surface of the wind turbine construction project, which refers to the terrain where the relative height from the top of the slope to the lower blade tip of the wind turbine is less than 10m or higher than the lower blade tip of the wind turbine. This terrain will reduce the power generation of the wind turbine and increase the fatigue load of the wind turbine blades.
[0053] Wherein, in step S1, the location of the wind turbines in the wind farm that may be affected by the high slope terrain is determined according to the height and inclination of the slope.
[0054] Among them, in step S2, the location of the wind turbine that may belong to the high slope terrain is divided into enough sectors based on the north direction according to the set wind direction step. It should be pointed out that in order to ensure the accuracy of data analysis, the 12 or 16 sector division method is not applicable, and a more refined sector division method is required. Therefore, n here is generally at least 72, that is, the wind direction step is not greater than 5°.
[0055] The first sector is centered on the aircraft position and based on true north. The sector angle is Rotate clockwise to form the second sector, with no gap between the two sectors.
[0056] In step S3, the minimum height of the blade tip of each sector wind turbine from the ground, that is, the wind turbine parameters, is obtained.
[0057] The height of the slope terrain relative to the wind turbine installation platform, the angle of the slope terrain relative to the wind turbine installation platform, and the distance from the center of the wind turbine foundation to the slope terrain are obtained, which are the terrain parameters.
[0058] The high slope terrain determination coefficient is calculated based on the wind turbine parameters and terrain parameters.
[0059] Furthermore, the calculation formula of the high slope terrain determination coefficient is:
[0060]
[0061] Among them, Ai , B i , C i is the high slope terrain determination coefficient, H is the distance between the lower blade tip and the ground, h i is the height of the slope terrain of the i-th sector relative to the wind turbine installation platform, is the angle of the slope terrain of the i-th sector relative to the wind turbine installation platform, x i is the distance from the center of the wind turbine foundation in the i-th sector to the slope terrain, where i = 1, 2, ..., n, such as Figure 2 shown.
[0062] Furthermore, a high slope determination coefficient threshold α is set, and the high slope terrain is determined according to the high slope terrain determination coefficient to determine whether the terrain belongs to the high slope terrain.
[0063] Among them, the high slope determination coefficient threshold α=0, when A i >α or B i >α or C i >α, it is determined that the sector terrain does not belong to high slope terrain and does not need to be repaired; when A i <α and B i <α and C i When α is less than α, the terrain of the sector is determined to be a high slope terrain and needs to be repaired. The continuous sectors identified as high slope terrain are renumbered, marked as j, and counted sequentially from 1. The total number of sectors is recorded as m.
[0064] For discontinuous sectors determined to be high slope terrain, the sectors between the two closest high slope terrain sectors should also be identified as high slope terrain sectors.
[0065] Among them, in step S4, when the corresponding high slope terrain in each sector is trimmed, the construction volume of various different high slope terrain trimming methods is calculated, the construction volume calculation results of different high slope terrain trimming methods are compared, and the high slope terrain trimming method with the smallest construction volume is selected to trim the high slope terrain, thereby solving the high slope terrain problem in the wind farm.
[0066] A variety of high slope terrain modification methods include:
[0067] Method 1: Excavate the high slope of the sector and reduce the slope height h of the jth sector belonging to the high slope terrain j , so that h j =H-10, excavation method reference Figure 3 , where the shaded part is the excavation area;
[0068] Method 2: Excavate the high slope of the sector and increase the distance x from the jth sector slope belonging to the high slope terrain to the center of the wind turbine foundation j , so that x j =10hj , excavation method reference Figure 4 , where the shaded part is the excavation area;
[0069] Method 3: Excavate the high slope of the sector to reduce the angle of the jth sector slope belonging to the high slope terrain relative to the wind turbine installation platform make Excavation method reference Figure 5 , where the shaded part is the excavation area.
[0070] The main difference between the above three methods is that the excavation locations are different and the boundary conditions they meet are different. Based on the judgment of high slope terrain, any of the three methods can make the terrain no longer a high slope terrain, thereby no longer affecting the power generation and safety of the wind turbine.
[0071] Among them, the area calculation method is used to calculate the earthwork excavation volume (construction volume) of the high slope terrain modification method, that is, the construction volume of different high slope terrain modification methods is calculated according to the following formula:
[0072] Method 1:
[0073] Method 2:
[0074]
[0075] Method 3:
[0076] Among them, S1, S2, S3 are the construction quantities calculated by high slope terrain modification methods 1, 2, and 3 respectively, j = 1, ..., m; h j is the slope height of the jth sector, h1j is the excavation height of the jth sector in method 1, y1 j is the width of the top of the slope after excavation of the jth sector in method 1, x j is the distance from the jth sector slope to the center of the wind turbine foundation, h2 j is the slope height close to the wind turbine after the jth sector is excavated in method 2, a j is the width of the jth sector slope top from the slope bottom (the intersection of the slope and the wind turbine engineering operation surface), d j is the width of the slope at the height of the wind turbine engineering operation surface in the jth sector, b j is the distance from the top to the bottom of the slope close to the wind turbine in the jth sector, c j is the vertical distance from the jth sector to the top of the slope after excavation in method 3, j is the excavation angle of the jth sector using method 3, θ j is the angle of the jth sector slope relative to the wind turbine installation platform.
[0077] One of the three methods is selected for all sectors. The calculation method is: MIN(S1, S2, S3), MIN() is the minimum value function, and the result is used as the implementation method of slope repair.
[0078] The present invention realizes quantitative analysis and judgment of high slope terrain in wind farms by introducing high slope terrain judgment coefficient and setting threshold value, and further calculates the construction amount of different high slope terrain finishing methods based on the judgment result, so as to select the high slope terrain finishing method according to the principle of minimum construction amount; the accuracy of high slope terrain judgment in wind farms is improved, the construction amount of high slope terrain finishing is reduced, the power generation of wind farms is increased, and the construction cost of wind farms is reduced, which is of great significance.
[0079] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for modifying high slope terrain of a wind farm based on sector distribution, characterized in that: The following steps are involved: Determine the location of wind turbines in wind farms that may be located in high-slope terrain; Map the micro-topography around the wind turbine location, collect terrain elevation data, and divide it into n sectors; Obtain the wind turbine parameters and terrain parameters of each sector to determine whether the terrain is a high slope terrain; If it is not a high slope terrain, no trimming is required. If it is a high slope terrain, the corresponding high slope terrain in each sector should be trimmed.
2. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 1, characterized in that: The location of wind turbines in wind farms that may belong to high slope terrain is determined based on the height and inclination of the slope.
3. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 1, characterized in that: The locations of wind turbines that may belong to high slope terrain are divided into sectors based on the north direction according to the set wind direction step length, n ≥ 72, and the wind direction step length is no more than 5°.
4. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 1, characterized in that: The wind turbine parameters are the minimum height of the wind turbine blade tip from the ground, and the terrain parameters are the height of the slope terrain relative to the wind turbine installation platform, the angle of the slope terrain relative to the wind turbine installation platform, and the distance from the center of the wind turbine foundation to the slope terrain.
5. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 1 or 4, characterized in that: According to the wind turbine parameters and terrain parameters, the high slope terrain determination coefficient is calculated, the high slope determination coefficient threshold α is set, and the high slope terrain is determined according to the high slope terrain determination coefficient.
6. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 5, characterized in that: The calculation formula of high slope terrain determination coefficient is: Among them, A i , B i , C i is the high slope terrain determination coefficient, H is the distance between the lower blade tip and the ground, h i is the height of the slope terrain of the i-th sector relative to the wind turbine installation platform, is the angle of the slope terrain of the i-th sector relative to the wind turbine installation platform, x i is the distance from the center of the wind turbine foundation in the i-th sector to the slope terrain, where i = 1, 2, …, n.
7. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 6, characterized in that: High slope determination coefficient threshold α=0, when A i >α or B i >α or C i >α, it is determined that the sector terrain does not belong to high slope terrain and does not need to be repaired; when A i <α and B i <α and C i <α, the sector terrain is determined to be a high slope terrain and needs to be repaired. The continuous sectors identified as high slope terrain are renumbered, marked as j, and counted sequentially from 1. The total number of sectors is recorded as m.
8. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 1, characterized in that: When trimming the corresponding high slope terrain in each sector, calculate the construction volume of various high slope terrain trimming methods, compare the construction volume calculation results of different high slope terrain trimming methods, select the high slope terrain trimming method with the smallest construction volume, and trim the high slope terrain.
9. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 8, characterized in that: A variety of high slope terrain modification methods include: Method 1: Excavate the high slope of the sector and reduce the slope height h of the jth sector belonging to the high slope terrain j , so that h j =H-10; Method 2: Excavate the high slope of the sector and increase the distance x from the jth sector slope belonging to the high slope terrain to the center of the wind turbine foundation j , so that x j =10h j ; Method 3: Excavate the high slope of the sector to reduce the angle of the jth sector slope belonging to the high slope terrain relative to the wind turbine installation platform make 10. The method for modifying high slope terrain of a wind farm based on sector distribution according to claim 9, characterized in that: The area calculation method is used to compare the earthwork excavation volume of various high slope terrain modification methods as the construction volume calculation result: Method 1: h1 j =h j +10-H; Method 2: x2 j =10h j -x j ; Method 3: Among them, S1, S2, S3 are the construction quantities calculated by high slope terrain modification methods 1, 2, and 3 respectively, j = 1, ..., m; h j is the slope height of the jth sector, h1j is the excavation height of the jth sector in method 1, y1 j is the width of the top of the slope after excavation of the jth sector in method 1, x j is the distance from the jth sector slope to the center of the wind turbine foundation, h2 j is the slope height close to the wind turbine after the jth sector is excavated in method 2, a j is the width of the jth sector from the top to the bottom, d j is the width of the slope at the height of the wind turbine engineering operation surface in the jth sector, b j is the distance from the top to the bottom of the slope close to the wind turbine in the jth sector, c j is the vertical distance from the jth sector to the top of the slope after excavation in method 3, j is the excavation angle of the jth sector using method 3, θ j is the angle of the jth sector slope relative to the wind turbine installation platform.