Launching and recycling method of deep-sea bottom-sitting long-term in-situ monitoring device
By determining the number and weight of floats and counterweights, combined with geophysical measurements and automated recovery technology, the accuracy and safety issues of the deployment and recovery of deep-sea mining monitoring devices are solved, and the efficiency and reliability of monitoring tasks are improved.
Patent Information
- Application Number
- CN202410787216.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-18
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing deployment and recovery methods of deep-sea mining monitoring devices suffer from complex manual operations, high costs, low recovery efficiency, and lack of topographic and geological assessments, resulting in inaccurate device deployment and high risk of damage, affecting data accuracy and reliability.
By determining the number and weight of floats and counterweights, conducting geophysical measurements, using the ship's hoisting device and winch cable deployment and recovery device, and using acoustic signals and pyrotechnic modules to achieve automated recovery, ensuring that the device sinks to the bottom and remains stable in the water. Precise control of levitation.
It improves the accuracy and safety of the placement of deep-sea mining monitoring devices, simplifies the recovery process, enhances the efficiency and reliability of monitoring tasks, and reduces labor costs and risks.
Smart Images

Figure CN118794482A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of deployment and recovery of a deep-sea bottom-mounted long-term in-situ monitoring device, and in particular to a deployment and recovery method of a deep-sea bottom-mounted long-term in-situ monitoring device. Background Art
[0002] Deep-sea mining is the mining of mineral resources at the bottom of the deep sea. Due to the global population growth and accelerated industrialization, the demand for important metals such as copper, iron, manganese, and rare earth elements has increased dramatically. The depletion of terrestrial mineral resources and the increase in mining costs have prompted people to turn to the deep sea as a new source of resource supply. However, since the deep-sea ecosystem is one of the least known and most fragile ecosystems on Earth, deep-sea mining activities may have irreversible effects on these ecosystems, so long-term in-situ observations of the seabed environment of deep-sea mining are indispensable.
[0003] The deep-sea ecosystem in existing technologies is very complex and responds slowly. Long-term in-situ monitoring helps to understand the impact of mining activities on biodiversity, ecological structure and function, thereby tracking environmental changes and trends, reducing negative impacts on the environment, and achieving sustainable use of deep-sea resources. Long-term in-situ monitoring data collected before mining activities begin can serve as a benchmark for assessing mining impacts and become an important basis for whether mining activities can be carried out reasonably.
[0004] Before conducting long-term in-situ observations, it is necessary to consider how to reasonably deploy and recover in-situ monitoring devices. However, the current methods of deploying and recovering devices have certain defects and limitations. First, traditional deployment methods require crew members to perform more manual operations, including physically connecting and disconnecting devices, which not only increases the complexity and risk of operations, but also means higher labor costs; second, relying on manual marking (buoy markers) to recover devices may be limited by weather conditions and sea conditions, resulting in reduced recovery efficiency, especially in bad weather or at night; third, the lack of detailed topographic and geological assessments of the deployment area may result in the deployment of devices in inappropriate locations.
[0005] These problems will have a great impact on the deployment and recovery of long-term in-situ monitoring equipment, thereby increasing the risk of device damage and affecting the accuracy and reliability of data. Therefore, a new deployment and recovery device and method suitable for deep-sea mining bottom monitoring platforms are urgently needed to overcome the above problems and achieve higher accuracy, safety and efficiency in-situ monitoring. Summary of the invention
[0006] One of the purposes of the present invention is to provide a method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device to achieve in-situ monitoring with higher accuracy, safety and efficiency.
[0007] The technical solution of the present invention is as follows:
[0008] A method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device comprises the following steps:
[0009] S100: Determine the number of floating balls and the weight of the counterweight in the deployment and recovery device;
[0010] S200: geophysical survey of the target area;
[0011] S300: placing the deployment and recovery device on the water surface along with the monitoring device using the lifting device and the winch cable of the vessel, and disconnecting the deployment and recovery device from the winch cable using the unhooking device;
[0012] S400: The monitoring device starts monitoring;
[0013] S500: After completing the monitoring, the vessel sends an acoustic signal: the monitoring device disconnects from the communication cable, discards the counterweight, and the communication cable floats up to the water surface under the buoyancy of the buoyant ball;
[0014] S600: The pyrotechnic module at the lower end of the buoy is disconnected when floating on the water surface, and the pyrotechnic module releases fireworks for the vessel to follow the fireworks;
[0015] S700: The vessel determines the location of the monitoring device through pyrotechnic signals and recovers it.
[0016] Furthermore, step S100 includes:
[0017] S110: Calculate the total weight G of the monitoring device in water z ;
[0018] Including determining the length L of the communication cable and its weight G in water t , float weight in water G fz , cable clamp quantity N2 and weight in water G l , the underwater weight Gx of all sensors, batteries, communication equipment, etc.;
[0019] S120: Calculate the required weight of the counterweight in water G p , based on the total weight of the device in the water and the seismic requirements of the device, determine the expected sinking velocity V, and calculate the weight m that must be added x ;
[0020] S130: Determine the number of floats, based on the total weight of the device plus the counterweight, the buoyancy of a single float F f , calculate how much buoyancy is needed to make the device float back to the surface after releasing the counterweight, and determine the number of floats N1;
[0021] S140: Perform a water tank test, under controlled conditions, using actual floats and weights to test the sinking and floating of the device in a water tank or similar environment according to the calculated values;
[0022] Adjust the number of floats and the weight of the counterweight until the device sinks to the bottom as expected and returns to the surface after the counterweight is released. Determine the number of floats N again. 1-1 and the minimum counterweight mass m x-1 .
[0023] S150: Safety factors are added during calculation and testing to account for possible uncertainties under actual conditions, such as changes in seawater density and the effects of deep-sea pressure.
[0024] Furthermore, the calculation formula of the number of float balls N1 in step S130 is:
[0025] N1=F fz / F f ;
[0026] In the formula, F fz is the total buoyancy of the float (N);
[0027] F f is the buoyancy of a single float (N).
[0028] Furthermore, the calculation formula of the communication cable length L in step S110 is:
[0029]
[0030] Where H is the vertical distance from the bottom when the equipment is deployed (m);
[0031] X is the estimated movement and distance of the vessel when deploying the equipment (m).
[0032] Furthermore, the weight of the counterweight in step S120 is G p And the weight of counterweight m must be added x The calculation formula is:
[0033]
[0034] Where, f is the resistance of the monitoring device (N);
[0035] G z is the total weight of the monitoring device in water (N);
[0036] F is the buoyancy of the monitoring device in water (N);
[0037] A is the resistance area (m2);
[0038] V is the settling velocity of the monitoring device in water (m / s);
[0039] F p is the buoyancy of the weight in water (N);
[0040] Empirical values: c=0.85, ρ=1020kg / m3, g=9.8 (N / kg).
[0041] Furthermore, step S500 includes:
[0042] S510: Sending acoustic signals: After the monitoring mission is completed, the vessel sends acoustic signals through dedicated equipment to trigger the recovery procedure of the monitoring device.
[0043] S520: The releaser module responds. After receiving the acoustic release command, the releaser module opens the mechanism connected to the communication cable or the counterweight, disconnects the communication cable and discards the counterweight.
[0044] S530: Cable clamp falls off: As the counterweight is detached from the communication cable, the fuses in the cable clamp that originally fixed the communication cable are disconnected in sequence according to the command after receiving the signal, and the cable clamp falls off or unlocks in sequence from top to bottom and from right to left, thereby releasing the communication cable.
[0045] S540: The buoy rises. After losing the restraint of the counterweight, the buoy connected to one end of the communication cable drives the communication cable and the monitoring device to float from underwater to the surface with the help of its own buoyancy.
[0046] Furthermore, the deployment and recovery device includes a float, an ultra-short baseline beacon, a communication cable, a pyrotechnic module, an acoustic releaser and a counterweight;
[0047] The pyrotechnic module and the ultra-short baseline beacon are installed on the lower side of the floating ball, and the two ends of the communication cable are respectively connected to the floating ball and the monitoring device. The monitoring device includes a releaser module, and the releaser module is connected to the counterweight block.
[0048] Further, the communication cable includes an electric wire and a Kevlar cable, and the Kevlar cable is located outside the electric wire;
[0049] The communication cable is wound into an "S"-shaped structure and is fixed by a cable clamp with an electrically controlled release function for the communication cable.
[0050] The working principle and beneficial effects of the present invention are:
[0051] Compared with the prior art, the present invention improves the efficiency and reliability of long-term in-situ monitoring tasks through the reasonable deployment and recovery of deep-sea mining equipment, thus making up for the shortcomings of existing deployment and recovery methods. Starting from determining the counterweight block and the float, the present invention establishes a deployment and recovery device and method suitable for the bottom monitoring platform of deep-sea mining by performing geophysical measurement, deployment, and recovery of the target area. It is worth noting that this method not only improves the accuracy and safety of the equipment deployment position, but also makes the recovery of the equipment simpler and more reliable. The establishment of the present invention will provide more accurate ideas and methods for the deployment and recovery of deep-sea mining in-situ devices. . BRIEF DESCRIPTION OF THE DRAWINGS
[0052] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0053] Figure 1 is an overall schematic diagram of the deployment and recovery device in this embodiment;
[0054] Figure 2 This is a schematic diagram of the process of deploying the monitoring device in this embodiment;
[0055] Figure 3 It is a schematic diagram of the process of recycling the monitoring device in this embodiment;
[0056] Figure 4 Schematic diagram of the fireworks module structure in this embodiment;
[0057] Figure 5 Schematic diagram of the circuit breaking process of the pyrotechnic module in this embodiment;
[0058] Figure 6 Schematic diagram of the structure of the cable clamp in this embodiment.
[0059] In the figure: 1. Float; 2. Ultra-short baseline beacon; 3. Fireworks module; 4. Communication cable; 5. Monitoring device; 6. Cable clamp. DETAILED DESCRIPTION
[0060] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0061] like Figure 1 As shown, a method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device 5 comprises the following steps:
[0062] S100: Determine the number of floating balls 1 and the weight of the counterweight in the deployment and recovery device in the laboratory. The weight of the counterweight should be sufficient to ensure that the monitoring device 5 can sink to the bottom of the sea as a whole. The number of floating balls 1 should be sufficient to ensure that after the releaser module discards the counterweight, the floating balls 1 can float to the surface when connected to the monitoring device 5;
[0063] Specifically, step S100 includes:
[0064] S110: Calculate the total weight G of the monitoring device 5 in water z ;
[0065] Including determining the length L of the communication cable 4 and the weight G in water t , float 1 weight in water G fz , cable clamp 6 quantity N2 and weight in water G l , the underwater weight Gx of all sensors, batteries, communication equipment, etc.;
[0066] The calculation formula of the length L of the communication cable 4 in step S110 is:
[0067]
[0068] Where H is the vertical distance from the bottom when the equipment is deployed (m);
[0069] X is the estimated movement and distance of the vessel when deploying the equipment (m).
[0070] The above formula determines the length L of the communication cable, which can ensure that the device can be quickly and reasonably deployed and recovered and avoid waste of resources.
[0071] S120: Calculate the required weight of the counterweight in water G p , based on the total weight of the device in the water and the seismic requirements of the device, determine the expected sinking velocity V, and calculate the weight m that must be added x , to ensure that the device can overcome the buoyancy of water and sink to the seabed;
[0072] The weight of the counterweight in the water in step S120 is G p And the weight of counterweight m must be added x The calculation formula is:
[0073] The calculation formula is based on the falling speed V of the object in water and the resistance f:
[0074]
[0075] Get the total weight G of the monitoring device in water z :
[0076]
[0077] Get the weight of the weight in water G p , the total weight of the monitoring device in water G z Remove the weight of the communication cable, buoy, cable clamp and other equipment except the counterweight in the water G t , G fz , G l and G x :
[0078]
[0079] Obtain the weight that must be added m x Need to meet:
[0080]
[0081] Where, f is the resistance of the monitoring device 5 (N);
[0082] G z is the total weight of the monitoring device 5 in water (N);
[0083] F is the buoyancy of the monitoring device 5 in water (N);
[0084] A is the resistance area (m 2 );
[0085] V is the settling velocity of the monitoring device 5 in water (m / s);
[0086] F p is the buoyancy of the weight in water (N);
[0087] Empirical values: c=0.85, ρ=1020kg / m3, g=9.8 (N / kg).
[0088] The above formula determines the weight of the counterweight in water G p And the weight of counterweight m must be added x , ensuring that the monitoring device can sit safely on the bottom.
[0089] S130: Determine the number of floats 1, based on the total weight of the device plus the counterweight, the buoyancy F of a single float 1 f , calculate how much buoyancy is needed to make the device float back to the surface after releasing the counterweight, and determine the number of floats 1 N1;
[0090] The calculation formula of the number of float balls N1 in step S130 is:
[0091] N1=F fz / F f ;
[0092] In the formula, F fz is the total buoyancy of the float (N);
[0093] F f is the buoyancy of a single float (N).
[0094] The above formula determines the number of floats N1 to ensure that when the monitoring device is recovered, the float can pull the monitoring device to the water surface through buoyancy.
[0095] S140: Perform a water pool test, under controlled conditions, use the actual float 1 and the counterweight block to test the sinking and floating of the device in a water pool or similar environment according to the calculated values;
[0096] Adjust the number of floats 1 and the weight of the counterweight until the device sinks to the bottom as expected and returns to the surface of the water after the counterweight is released. Determine the number of floats 1 N again. 1-1 and the minimum counterweight mass m x-1 .
[0097] S150: Safety factors are added during calculation and testing to account for possible uncertainties under actual conditions, such as changes in seawater density and the effects of deep-sea pressure.
[0098] S200: Conduct geophysical surveys of the target area to ensure that the deployment can be carried out at locations with flat terrain, uniform bottom and stable strata;
[0099] S300: placing the deployment and recovery device on the water surface along with the monitoring device 5 by using the lifting device and the winch cable of the vessel, and disconnecting the deployment and recovery device from the winch cable by using the unhooking device;
[0100] The monitoring device 5 falls slowly as a whole until it touches the bottom, and the communication cable 4 should be in a vertical state under the action of the float 1.
[0101] S400: The monitoring device 5 starts monitoring;
[0102] S500: After the monitoring is completed, the ship sends an acoustic signal: after receiving the release command, the releaser module disconnects from the communication cable 4, thereby discarding the counterweight, and the monitoring device 5 floats up to the water surface along with the communication cable 4 under the buoyancy of the buoy 1;
[0103] At the same time, after receiving the signal, the cable clamps 6 fall off from top to bottom in sequence.
[0104] Specifically, step S500 includes:
[0105] S510: Sending an acoustic signal: After the monitoring task is completed, the vessel sends an acoustic signal through a dedicated device, and after the acoustic receiving module on the monitoring device 5 receives the acoustic signal, the recovery procedure of the monitoring device 5 is triggered.
[0106] S520: The releaser module responds. After receiving the acoustic release command, the releaser module responds to open the mechanism connected to the communication cable 4 or the counterweight (such as an electrically controlled underwater automatic unhooking device, a clamp, or other electrically controlled connecting devices), disconnects from the communication cable 4, and discards the counterweight.
[0107] In this embodiment, the electric control connection device is installed on the counterweight by default, and then connected to the connection piece (such as a connection ring) on the communication cable 4.
[0108] S530: The cable clamp 6 falls off: As the counterweight block detaches from the communication cable 4, the fuse in the cable clamp 6 that originally fixed the communication cable 4 is disconnected in sequence according to the instruction after receiving the signal, and the cable clamp 6 falls off or unlocks in sequence from top to bottom and from right to left, thereby releasing the wound communication cable 4.
[0109] The cable clamp 6 in this embodiment can adopt a structure of two clamping plates to clamp the wound communication cable 4. The two clamping plates can be bound by a fuse, and then the fuse is electrically connected to the fuse circuit. When the clamping plates need to be disconnected, the fuse is directly blown by an electrical signal. Or other electric control clamping devices that can be used underwater can be used to clamp and fix the communication cable 4, which will not be described in detail in this embodiment. The number of clamps of the cable clamp 6 can be set according to needs.
[0110] S540: The buoy 1 floats up. After losing the restraint of the counterweight, the buoy 1 connected to one end of the communication cable 4 drives the communication cable 4 and the monitoring device 5 to float up from underwater to the surface of the water by virtue of its own buoyancy.
[0111] S600: The pyrotechnic module 3 at the lower end of the buoy 1 is disconnected when the buoy 1 floats to the surface of the water, and the pyrotechnic module 3 releases fireworks toward the water surface for the vessel to follow the fireworks;
[0112] S700: The ship determines and tracks the location of the monitoring device 5 through fireworks signals, connects one end of the communication cable 4 connected to the buoy 1 to the ship, and uses a lifting device to recover the monitoring device.
[0113] In addition, in order to cooperate with the above method, the deployment and recovery device in this embodiment should at least include a floating ball 1, an ultra-short baseline beacon 2, a communication cable 4, a pyrotechnic module 3, an acoustic releaser and a counterweight;
[0114] The pyrotechnic module 3 and the ultra-short baseline beacon 2 (which can be electrically connected to the monitoring device 5) are installed on the lower side or side of the float 1. The pyrotechnic module 3 can be controlled and release fireworks by the monitoring device 5 through wired or wireless communication. It can also be closed underwater through its own circuit design, disconnected when the float 1 comes out of water, and then release fireworks. This embodiment will not be repeated here.
[0115] The two ends of the communication cable 4 are respectively connected to the float 1 and the monitoring device 5 (or it can be understood that the monitoring device 5 is fixed on the communication cable 4). The monitoring device 5 includes a releaser module for connecting or disconnecting the counterweight.
[0116] Since the communication cable 4 is separated from the counterweight in this embodiment, it is mainly to allow the communication cable 4 to float and straighten under the drive of the float 1. In order to facilitate the recovery of the counterweight, one end of the communication cable 4 can be always connected to the counterweight. The releaser module is mainly used to prevent the communication cable 4 from being stretched and floating. Therefore, the releaser module is fixed in the middle of the communication cable 4, and moves to the lower part to connect with the counterweight through the winding of the communication cable 4. After the releaser module releases the counterweight, it does not affect the connection between the end of the communication cable 4 and the counterweight.
[0117] The communication cable 4 includes electric wires and Kevlar cables. The Kevlar cables are high in strength and corrosion-resistant. They are located outside the electric wires and can protect the electric wires underwater. They are also lightweight and easy to carry.
[0118] In addition, in this embodiment, the communication cable 4 is wound into an "S"-shaped structure, which can reduce the length of the communication cable 4 during deployment to facilitate deployment, and then is fixed by a cable clamp 6 with an electrically controlled release function of the communication cable 4. When it is recovered, it is easy to release the communication cable 4, allowing the communication cable 4 to stretch and the buoy 1 to float to the surface.
[0119] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5), characterized in that: The steps include: S100: Determine the number of floating balls (1) and the weight of the counterweight in the deployment and recovery device; S200: geophysical survey of the target area; S300: Using the lifting device and winch cable of the vessel to place the deployment and recovery device together with the monitoring device (5) on the water surface, and using the unhooking device to disconnect the deployment and recovery device from the winch cable; S400: the monitoring device (5) starts monitoring; S500: After completing the monitoring, the vessel sends an acoustic signal: the monitoring device (5) disconnects from the communication cable (4), discards the counterweight, and the communication cable (4) floats up to the water surface under the buoyancy of the buoy (1); S600: The pyrotechnic module (3) at the lower end of the buoy (1) is disconnected when floating on the water surface, and the pyrotechnic module (3) releases fireworks for the vessel to follow the fireworks; S700: The vessel determines the location of the monitoring device (5) through pyrotechnic signals and recovers it.
2. The method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5) as claimed in claim 1, characterized in that: Step S100 includes: S110: Calculate the total weight G of the monitoring device (5) in water z ; Including determining the length L and underwater weight G of the communication cable (4) t , float (1) weight in water G fz , the number of cable clamps (6) N2 and their weight in water G l , the underwater weight Gx of all sensors, batteries, communication equipment, etc.; S120: Calculate the required weight of the counterweight in water G p , based on the total weight of the device in the water and the seismic requirements of the device, determine the expected sinking velocity V, and calculate the weight m that must be added x ; S130: Determine the number of floating balls (1), based on the total weight of the device plus the counterweight, the buoyancy F of a single floating ball (1) f , calculate the buoyancy required to make the device float back to the surface after releasing the counterweight, and determine the number N1 of the floats (1); S140: Perform a water tank test, under controlled conditions, use an actual float (1) and a weight block to test the sinking and floating of the device in a water tank or similar environment according to the calculated values; Adjust the number of floats (1) and the weight of the counterweight until the device sinks to the bottom as expected and returns to the surface of the water after the counterweight is released. Determine the number of floats (1) N again. 1-1 and the minimum counterweight mass m x-1 . S150: Safety factors are added during calculation and testing to account for possible uncertainties under actual conditions, such as changes in seawater density and the effects of deep-sea pressure.
3. The method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5) according to claim 2 is characterized in that: The calculation formula of the number of float balls N1 in step S130 is: N1=F fz / F f ; In the formula, F fz is the total buoyancy of the float (N); F f is the buoyancy of a single float (N).
4. The method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5) according to claim 2 is characterized in that: The calculation formula of the length L of the communication cable (4) in step S110 is: Where H is the vertical distance from the bottom when the equipment is deployed (m); X is the estimated movement and distance of the vessel when deploying the equipment (m).
5. The method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5) according to claim 2 is characterized in that: The weight of the counterweight in the water in step S120 is G p And the weight of counterweight m must be added x The calculation formula is: Where, f is the resistance (N) of the monitoring device (5); G z is the total weight of the monitoring device (5) in water (N); F is the buoyancy of the monitoring device (5) in water (N); A is the resistance area (m2); V is the settling speed of the monitoring device (5) in water (m / s); F p is the buoyancy of the weight in water (N); Empirical values: c=0.85, ρ=1020kg / m3, g=9.8 (N / kg).
6. The method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5) according to claim 1, characterized in that: Step S500 includes: S510: Sending acoustic signals: After the monitoring task is completed, the vessel sends acoustic signals through dedicated equipment to trigger the recovery procedure of the monitoring device (5). S520: The releaser module responds. After receiving the acoustic release command, the releaser module opens the mechanism connected to the communication cable (4) or the counterweight block, disconnects the communication cable (4) and discards the counterweight block. S530: The cable clamp (6) falls off: As the counterweight is separated from the communication cable (4), the fuses in the cable clamp (6) that originally fixed the communication cable (4) are disconnected in sequence according to the command after receiving the signal, and the cable clamp (6) falls off or unlocks in sequence from top to bottom and from right to left, thereby releasing the communication cable (4). S540: The buoy (1) floats up. After losing the restraint of the counterweight, the buoy (1) connected to one end of the communication cable (4) drives the communication cable (4) and the monitoring device (5) to float up from underwater to the surface of the water by virtue of its own buoyancy.
7. The method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5) according to claim 1, characterized in that: The deployment and recovery device comprises a floating ball (1), an ultra-short baseline beacon (2), a communication cable (4), a pyrotechnic module (3), an acoustic releaser and a counterweight; The pyrotechnic module (3) and the ultra-short baseline beacon (2) are installed on the lower side of the floating ball (1), and the two ends of the communication cable (4) are respectively connected to the floating ball (1) and the monitoring device (5), and the monitoring device (5) includes a releaser module, and the releaser module is connected to the counterweight block.
8. The method for deploying and recovering a deep-sea bottom-mounted long-term in-situ monitoring device (5) according to claim 7, characterized in that: The communication cable (4) comprises an electric wire and a Kevlar cable, wherein the Kevlar cable is located outside the electric wire; The communication cable (4) is wound into an "S"-shaped structure and is fixed by a cable clamp (6) having the function of electrically controlling the release of the communication cable (4).
Citation Information
Patent Citations
Underwater target indication fuming device
CN102030082A
Fusing type releasing device for underwater anchor type heavy object and using method thereof
CN104118547A
An identification system for recovering offshore equipment and method of identifying offshore equipment using same
CN110937085A
Beacon device recycled by marine detection device
CN111137404A
Seabed boundary layer observation device and laying and recovering method thereof