BIM (Building Information Modeling)-based tower crane digital twinborn monitoring, early warning and anti-collision system and method

Through the BIM-based tower crane digital twin monitoring, early warning and anti-collision system, the operating status of the tower crane and the location of obstacles are monitored in real time, solving the problems of tower crane failure and collision risks, and achieving efficient construction safety and equipment management.

CN118833741APending Publication Date: 2024-10-25CHINA RAILWAY BRIDGE RES TECH CO LTD +3
View PDF 0 Cites 10 Cited by

Patent Information

Application Number
CN202411114497.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

Tower cranes are prone to equipment failures and collision risks during the construction process. It is difficult to achieve real-time monitoring and early warning with existing technology, affecting construction safety and efficiency.

Method used

A BIM-based tower crane digital twin monitoring, early warning and anti-collision system is used to collect data from multiple sensors, combined with AI intelligent image recognition and anti-collision algorithms, to monitor the operating status of the tower crane and the location of surrounding obstacles in real time, and conduct collision risk prediction and early warning, and Real-time display of operating status and collision risks through BIM models.

Benefits of technology

Real-time monitoring and automatic early warning are realized, which improves the safety and efficiency of the construction site, reduces the incidence of accidents, and improves the efficiency of tower crane equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118833741A_ABST
    Figure CN118833741A_ABST
Patent Text Reader

Abstract

The invention discloses a BIM-based tower crane digital twinborn monitoring, early warning and anti-collision system and method, and relates to the technical field of tower cranes, the system comprises a tower crane operation state monitoring module, a tower crane anti-collision module and a tower crane work efficiency analysis module, the tower crane operation state monitoring module is used for monitoring the operation state of a tower crane in real time, and the tower crane anti-collision module is used for monitoring the operation state of the tower crane in real time; correlating the monitoring data to a created digital twin tower crane BIM model, and realizing tower crane operation guidance based on a key index threshold value; the tower crane anti-collision module is used for acquiring data based on a plurality of sensors mounted on the tower crane, identifying positions and movement conditions of obstacles around the tower crane through a neural network, and performing collision risk prediction; and the tower crane work efficiency analysis module is used for counting and analyzing the operation data of the tower crane to obtain a work efficiency analysis result of the tower crane. The environment of a construction site and the operation state of the tower crane can be monitored in real time, and potential safety risks can be found in time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of tower cranes, and in particular to a BIM-based tower crane digital twin monitoring, early warning and anti-collision system and method. Background Art

[0002] Tower cranes are common lifting equipment in construction projects. They are responsible for transporting building materials. Equipment failure and lifting collision risks may occur during construction operations. The safety of tower cranes is directly related to the safety of personnel and property at the construction site, as well as the progress of on-site construction. Real-time monitoring and early warning of tower cranes can ensure the safety of operators and equipment, prevent collision accidents during construction, and perform work efficiency analysis on tower cranes. Therefore, it is particularly important to effectively realize real-time monitoring and early warning of tower cranes and improve the production efficiency of tower crane equipment.

[0003] As an emerging information technology, digital twin technology has developed rapidly in recent years. With the popularization of the Internet of Things, BIM (Building Information Modeling), sensors, cloud computing, big data, and AI (Artificial Intelligence) technology, it has also been promoted and applied in the field of construction equipment. Therefore, how to realize the monitoring and early warning of tower cranes based on digital twin technology has become an urgent problem to be solved. Summary of the invention

[0004] The present application provides a BIM-based tower crane digital twin monitoring, early warning and anti-collision system and method, which can monitor the construction site environment and the operating status of the tower crane in real time and promptly discover potential safety risks.

[0005] In a first aspect, an embodiment of the present application provides a BIM-based tower crane digital twin monitoring, early warning and anti-collision system, wherein the BIM-based tower crane digital twin monitoring, early warning and anti-collision system comprises:

[0006] The tower crane operation status monitoring module is used to monitor the operation status of the tower crane in real time, and associate the monitoring data with the created digital twin tower crane BIM model to display the operation status of the tower crane in real time, and implement tower crane operation guidance based on key indicator thresholds;

[0007] The tower crane anti-collision module is used to collect data based on multiple sensors installed on the tower crane, identify the position and movement of obstacles around the tower crane through a neural network, and predict the collision risk based on the position and movement of the tower crane itself;

[0008] The tower crane ergonomics analysis module is used to collect statistics and analyze the operation data of the tower crane to obtain the ergonomics analysis results of the tower crane.

[0009] In combination with the first aspect, in one implementation,

[0010] The tower crane BIM model is used to display the position and operation status of the boom and hook in real time, as well as the current measured values ​​of the key indicators of the tower crane, including the position, height, tilt angle, wind speed, and rotation angle of the tower crane;

[0011] The tower crane operation status monitoring module provides tower crane operation guidance based on preset key indicator thresholds and current measured values ​​of the key indicators of the tower crane;

[0012] The tower crane operation guidance is to indicate the working status of the tower crane, such as normal operation, full load, overload, amplitude variation exceeding the upper limit, amplitude variation exceeding the lower limit, working environment, and inclination, and to perform corresponding alarms, prompts, and controls.

[0013] In combination with the first aspect, in one implementation,

[0014] The tower crane anti-collision module collects data through multiple sensors installed on the boom and tower of the tower crane, and transmits the collected data to the edge computer in the tower crane cockpit to monitor the operation of the tower crane in real time, and sends the collected data to the server through the wireless communication module to calculate the position and movement of the tower crane itself. At the same time, the position and movement of obstacles around the tower crane are identified based on the AI ​​intelligent image recognition algorithm, and the collision risk is predicted based on the anti-collision algorithm combined with the position and movement of obstacles around the tower crane and the position and movement of the tower crane itself;

[0015] The tower crane anti-collision module is also used to display the collision risk prediction results in the tower crane BIM model.

[0016] In combination with the first aspect, in one implementation, the sensor includes an amplitude sensor, a torque sensor, a height sensor, a rotation sensor, a wind speed sensor, an inclination sensor, a millimeter wave radar, and a high-definition camera.

[0017] In combination with the first aspect, in one implementation,

[0018] The amplitude sensor is used to measure the running amplitude of the tower crane trolley from the center of the tower crane, taking the tower crane shaft as the pole, and measuring the radial coordinates of the hook;

[0019] The torque sensor is used to measure the hoisting weight of the tower crane;

[0020] The height sensor is used to measure the height of the tower crane hook, taking the tower crane shaft as the pole, and measuring the vertical coordinate of the hook;

[0021] The slewing sensor is used to measure the rotation angle of the tower crane arm, taking the tower crane shaft as the pole, and measuring the arm polar angle coordinates;

[0022] The wind speed sensor is used to measure the ambient wind speed;

[0023] The inclination sensor is used to measure the inclination degree of the tower crane;

[0024] The millimeter wave radar is used to actively detect obstacles that invade the detection area, detect the size, profile, relative position and movement of obstacles within the working range of the tower crane, and measure the spatial coordinates of the obstacles;

[0025] The high-definition camera is used to collect image information near the working range of the tower crane and perform video monitoring of the environment around the tower crane.

[0026] In combination with the first aspect, in one implementation,

[0027] The system also includes an alarm and a display arranged in the tower crane cockpit;

[0028] The alarm is used to give an audible and visual alarm when the tower crane is in an abnormal working state or there is a risk of collision;

[0029] The display is used to display the tower crane operation status and collision risk prediction information.

[0030] In combination with the first aspect, in one implementation,

[0031] The server is used to store and transmit data collected by sensors, and to deploy AI intelligent image recognition algorithms and anti-collision algorithms;

[0032] The system also includes monitoring system software, which is used to process and analyze monitoring data, and to display the operating status of the tower crane in real time through the tower crane BIM model, as well as the relative position of the tower crane and obstacles, and to issue early warning information when the working status of the tower crane is abnormal or there is a risk of collision. The monitoring system software is also used to display on-site monitoring videos and work efficiency analysis results.

[0033] In combination with the first aspect, in one implementation,

[0034] The tower crane ergonomics analysis module is specifically used to count and analyze the number of times, weight and time of lifting of the tower crane to obtain the ergonomics analysis results of the tower crane;

[0035] The work efficiency analysis results include the number of hoisting times, hoisting time, hoisting statistics, on-site time, hoisting efficiency, and daily online rate;

[0036] The tower crane ergonomics analysis module is also used to display historical ergonomics analysis results through charts.

[0037] In a second aspect, an embodiment of the present application provides a BIM-based tower crane digital twin monitoring, early warning and collision avoidance method, which is implemented based on the above-mentioned system and includes:

[0038] The position data of the tower crane and obstacles around the tower crane are obtained based on sensor collection, and the position data is pre-processed;

[0039] Select the location feature points of the tower crane and the obstacle, and calculate the distance between the tower crane and the obstacle based on the coordinates of the location feature points;

[0040] According to the distance between the tower crane and the obstacle, collision risk warning and collision prevention control are carried out.

[0041] In conjunction with the second aspect, in one implementation, performing collision risk warning and collision prevention control according to the distance between the tower crane and the obstacle specifically includes:

[0042] According to the distance between the tower crane and the obstacle, determine whether the distance between the tower crane and the obstacle is greater than the preset distance:

[0043] If not, a collision warning is issued, and it is determined whether the tower crane is actively shut down within the set time after the collision warning is issued. If it is actively shut down, no processing is performed; if it is not actively shut down, the tower crane is controlled to shut down;

[0044] If yes, the tower crane continues to operate normally.

[0045] The beneficial effects brought by the technical solution provided in the embodiments of the present application include:

[0046] (1) Real-time monitoring: It can monitor the construction site environment and the operating status of the tower crane in real time, and promptly detect potential safety risks, such as equipment failure, excessive wind in the working environment, abnormal tower inclination, collision risk, etc.

[0047] (2) Automatic early warning: Based on the monitored data, it can automatically determine whether there is equipment failure, excessive wind in the working environment, abnormal tower inclination, or collision risk, and issue early warning signals in a timely manner to remind operators to take corresponding measures;

[0048] (3) High degree of visualization, simple and intuitive monitoring and display interface. Digital twin technology is used to display the working status indicators and sensor layout positions of the tower crane in real time through the tower crane BIM model, intuitively display the relative position of the tower crane and obstacles, realize the virtual-real connection between equipment and model, monitor, predict and optimize the behavior and status of the physical system in real time, and integrate video monitoring, work efficiency statistical analysis, driver information, etc. to facilitate construction management personnel;

[0049] (4) High degree of intelligence. Traditional monitoring methods often rely on the experience and judgment of operators. Digital twin monitoring, early warning, and collision prevention can not only manually judge safety risks, but also simulate and predict safety risks through AI intelligent recognition algorithms and collision algorithms, automatically issue early warnings, and take active control to avoid human errors and improve the accuracy and reliability of safety management.

[0050] (5) High construction efficiency. By avoiding collision accidents, construction efficiency can be improved and downtime and resource waste caused by accidents can be reduced. Tower crane ergonomics analysis can improve the efficiency of tower crane equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] Figure 1 This is a structural diagram of the tower crane digital twin monitoring, early warning and anti-collision system based on BIM in this application;

[0052] Figure 2 This is a schematic diagram of the sensor installation;

[0053] Figure 3 This is a schematic diagram of the logical structure of the BIM-based tower crane digital twin monitoring, early warning and anti-collision system during implementation;

[0054] Figure 4 This is a flow chart of the BIM-based tower crane digital twin monitoring, early warning and anti-collision method for this application. DETAILED DESCRIPTION

[0055] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0056] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below with reference to the accompanying drawings.

[0057] On the first aspect, the embodiment of the present application provides a BIM-based tower crane digital twin monitoring, early warning and collision avoidance system, which is used in high-altitude scenarios such as building construction, bridge construction and port operations. Through digital twin technology, the operation data of the tower crane can be deeply analyzed to realize fault diagnosis and prediction, and equipment failures can be discovered in advance, reducing downtime and maintenance costs. In-depth analysis can also be performed on data such as the number of tower crane hoisting times and hoisting time to obtain the ergonomic analysis results of the tower crane and improve the efficiency of equipment use. This application can not only significantly improve the safety and efficiency of the construction site, but also effectively reduce the incidence of accidents and protect the safety of life and property.

[0058] In one embodiment, referring to Figure 1 , Figure 1 This is a schematic diagram of the structure of the tower crane digital twin monitoring, early warning and anti-collision system based on BIM in this application. Figure 1 As shown, the BIM-based tower crane digital twin monitoring, early warning and anti-collision system includes: a tower crane operation status monitoring module, a tower crane anti-collision module, and a tower crane ergonomics analysis module.

[0059] The tower crane operation status monitoring module is used to monitor the operation status of the tower crane in real time, and associate the monitoring data with the created digital twin tower crane BIM model to display the operation status of the tower crane in real time, and implement tower crane operation guidance based on key indicator thresholds. Specifically, the tower crane BIM model (i.e., virtual BIM model) is used to display the position and operation status of the boom and hook in real time, as well as the current measured values ​​of the key indicators of the tower crane, including the position, height, inclination angle, wind speed, and rotation angle of the tower crane; the tower crane operation status monitoring module provides tower crane operation guidance based on the pre-set key indicator thresholds and the current measured values ​​of the key indicators of the tower crane; the tower crane operation guidance is to indicate the working status of the tower crane's normal operation, full load, overload, amplitude variation exceeding the upper limit, amplitude variation exceeding the lower limit, working environment, and tower crane inclination, and to perform corresponding alarms, prompts, and controls.

[0060] The tower crane operation status monitoring module needs to monitor the working conditions of the tower crane in real time. For the tower crane, the tower crane needs to change the working conditions according to the actual situation on site to perform lifting operations, such as changing the lifting angle, lifting arm length, etc. The maximum lifting weight and the maximum and minimum working amplitude changes are different under different working conditions. In addition, the tower crane needs to pay attention to the inclination angle of the tower crane and the surrounding wind force at all times during operation to ensure the safe operation of the equipment. Therefore, in order to realize comprehensive monitoring of the tower crane operation status, the detection data is linked to the digital twin BIM model in real time. The virtual BIM model can display the position and movement of the tower crane boom and hook in real time, and display the current measured values ​​of key indicators such as the position, height, inclination angle, wind speed, and rotation angle of the tower crane. Set the threshold of key indicators, make indications of the working conditions such as normal operation, full load, overload, amplitude change exceeding the upper limit, amplitude change exceeding the lower limit, working environment, and tower crane inclination, and give corresponding alarms, prompts, and controls to ensure the normal operation of the tower crane. By monitoring key indicators, if the tower crane operates abnormally, equipment failure can be discovered in advance, and measures to repair the equipment can be taken quickly to reduce the impact of equipment failure or equipment failure accidents on the construction period and save construction costs.

[0061] The tower crane anti-collision module is used to collect data based on multiple sensors installed on the tower crane, obtain the position and movement of obstacles around the tower crane through neural network recognition, and predict collision risks in combination with the position and movement of the tower crane itself. Specifically, the tower crane anti-collision module collects data through multiple sensors installed on the boom and tower body of the tower crane, and transmits the collected data to the edge computer in the tower crane cockpit to monitor the operation of the tower crane in real time, and sends the collected data to the server through the wireless communication module to calculate the position and movement of the tower crane itself. At the same time, the position and movement of obstacles around the tower crane are identified based on the AI ​​intelligent image recognition algorithm, and the collision risk is predicted based on the anti-collision algorithm combined with the position and movement of obstacles around the tower crane, as well as the position and movement of the tower crane itself; the tower crane anti-collision module is also used to display the collision risk prediction results in the tower crane BIM model, and can automatically send out prompts or control signals when the tower crane approaches a dangerous position, assisting operators to operate reasonably to avoid safety accidents, and improve construction efficiency.

[0062] The tower crane ergonomics analysis module is used to collect statistics and analyze the operation data of the tower crane to obtain the ergonomics analysis results of the tower crane. The tower crane ergonomics analysis module is specifically used to collect statistics and analyze the number of hoisting times, hoisting weight, and hoisting time of the tower crane to obtain the ergonomics analysis results of the tower crane; the ergonomics analysis results include the number of hoisting times, hoisting time, hoisting statistics, on-site time, hoisting efficiency, and daily online rate; the tower crane ergonomics analysis module is also used to display historical ergonomics analysis results through charts.

[0063] That is, the tower crane ergonomics analysis module conducts statistics and in-depth analysis on data such as the number of tower crane hoisting times, hoisting weight, and hoisting time, and obtains the ergonomics analysis results of the tower crane, such as the number of hoisting times, hoisting time, hoisting statistics, on-site time, hoisting efficiency, daily online rate and other ergonomics indicators, and displays historical ergonomics data in charts to help managers understand the working conditions of the tower crane and improve the efficiency of equipment use.

[0064] See also Figure 2 The figure shows the installation diagram of each sensor. Specifically, the sensors include amplitude sensor, torque sensor, height sensor, slew sensor, wind speed sensor, inclination sensor, millimeter wave radar, and high-definition camera. The amplitude sensor is used to measure the running amplitude of the tower crane trolley from the center of the tower crane, and the radial coordinates of the hook are measured with the tower crane shaft as the pole; the torque sensor is used to measure the weight of the tower crane; the height sensor is used to measure the height of the tower crane hook, and the vertical coordinates of the hook are measured with the tower crane shaft as the pole; the slew sensor is used to measure the rotation angle of the tower crane arm, and the polar angle coordinates of the arm are measured with the tower crane shaft as the pole; the wind speed sensor is used to measure the ambient wind speed; the inclination sensor is used to measure the inclination degree of the tower crane; the millimeter wave radar is used to actively detect obstacles that invade the detection area, detect the size, profile, relative position and movement of obstacles within the working range of the tower crane, and measure the spatial coordinates of the obstacles; the high-definition camera is used to collect image information near the working range of the tower crane and conduct video monitoring of the surrounding environment of the tower crane.

[0065] The BIM-based tower crane digital twin monitoring, early warning and anti-collision system of the present application also includes an alarm, a display arranged in the tower crane cockpit, and monitoring system software.

[0066] The alarm is used to sound and light alarm when the tower crane is in abnormal working state or there is a risk of collision; the display is used to display the tower crane operating state and collision risk prediction information. The server is used to store and transmit data collected by the sensor, and to deploy AI intelligent image recognition algorithms and anti-collision algorithms. The monitoring system software is used to process and analyze the monitoring data, and to display the operating state of the tower crane in real time through the tower crane BIM model, as well as to display the relative position of the tower crane and obstacles, and to issue early warning information when the tower crane is in abnormal working state or there is a risk of collision. The monitoring system software is also used to display on-site monitoring videos and work efficiency analysis results.

[0067] See also Figure 3 As shown, this is a schematic diagram of the logical structure of the BIM-based tower crane digital twin monitoring, early warning and anti-collision system during implementation of this application, which includes the tower crane and monitoring equipment end, network end, monitoring system end, BIM model visualization end, and client end. Each end cooperates with each other to realize real-time monitoring, intelligent identification, early warning, statistical equipment efficiency analysis, etc.

[0068] The BIM-based tower crane digital twin monitoring, early warning and anti-collision system of this application also supports visual display. For the development of the visual interface, specifically, the upper left corner of the visual interface displays the basic information of the tower crane driver, such as photo, name, age, length of service, and professional qualification certificate number; the lower left corner of the visual interface displays the statistical analysis results of the tower crane's ergonomics, such as the number of lifting times, lifting time, lifting statistics, on-site time, lifting efficiency, daily online rate and other ergonomics indicators, and displays historical ergonomics data through charts.

[0069] The digital twin virtual BIM model of the tower crane is displayed in the middle of the visualization interface, which shows the top view and virtual model of the tower crane respectively. The virtual model is connected to the real-time position data of the tower crane, and can display the position and movement of the tower crane, as well as the virtual model position and movement of obstacles in the detection area in real time. The digital twin virtual BIM model can intuitively display the tower crane, obstacles and collision risks.

[0070] The lower part of the visualization interface displays the real-time operation data of the tower crane, such as the position, height, tilt angle, wind speed, rotation angle, hoisting weight and other parameter values ​​and operation status. The upper right corner of the visualization interface displays the video surveillance within the working range of the tower crane and the weather conditions of the day; the upper right corner of the visualization interface displays the early warning information statistics.

[0071] The BIM-based tower crane digital twin monitoring, early warning and anti-collision system of the embodiment of the present application has the functions of real-time monitoring, intelligent identification, early warning, statistical equipment ergonomics analysis and the like. Among them, real-time monitoring is the core business, and the tower crane operation and surrounding environment information are continuously collected to ensure the timeliness and accuracy of the data; intelligent identification can quickly identify obstacles and classify them, and then more accurately predict the risk of collision; the early warning function can immediately issue an alert to the operator when an abnormal situation is found, prompting him to take countermeasures; the tower crane ergonomics analysis can count and deeply analyze the data such as the number of tower crane lifting times, lifting weight, lifting time, etc., and obtain the ergonomics analysis results of the tower crane, such as the number of lifting times, lifting time, lifting statistics, entry time, lifting efficiency, daily online rate and other ergonomics indicators, and display historical ergonomics data through charts to help managers understand the working conditions of the tower crane and improve the efficiency of equipment use.

[0072] On the second aspect, an embodiment of the present application also provides a BIM-based tower crane digital twin monitoring, early warning and collision avoidance method, which is implemented based on the above-mentioned BIM-based tower crane digital twin monitoring, early warning and collision avoidance system.

[0073] In one embodiment, referring to Figure 4 , Figure 4 This is a flow chart of the tower crane digital twin monitoring, early warning and anti-collision method based on BIM in this application. Figure 4 As shown in the figure, the tower crane digital twin monitoring, early warning and collision avoidance methods based on BIM include:

[0074] S1: Obtain the location data of the tower crane and obstacles around the tower crane based on sensor collection, and pre-process the location data;

[0075] S2: Select the location feature points of the tower crane and the obstacle, and calculate the distance between the tower crane and the obstacle based on the coordinates of the location feature points;

[0076] S3: Perform collision risk warning and collision prevention control based on the distance between the tower crane and the obstacle.

[0077] Furthermore, in one embodiment, collision risk warning and collision prevention control are performed according to the distance between the tower crane and the obstacle, specifically including:

[0078] According to the distance between the tower crane and the obstacle, determine whether the distance between the tower crane and the obstacle is greater than the preset distance:

[0079] If not, a collision warning is issued, and it is determined whether the tower crane is actively shut down within the set time after the collision warning is issued. If it is actively shut down, no processing is performed; if it is not actively shut down, the tower crane is controlled to shut down;

[0080] If yes, the tower crane continues to operate normally.

[0081] The following describes the specific implementation process of the BIM-based tower crane digital twin monitoring, early warning and anti-collision method of this application.

[0082] The first step is to install the equipment. According to the actual situation of the construction site, choose a suitable installation location and install radar sensors, laser radars, high-definition cameras and other equipment.

[0083] The luffing sensor is installed on one side of the luffing mechanism drum bracket to monitor the distance between the tower crane trolley and the center of the tower crane in real time. The torque sensor is installed on the rear end of the boom on the crane arm to monitor the weight of the heavy objects lifted by the tower crane in real time. The height sensor is installed on one side of the hoisting mechanism drum bracket and connected with a universal joint to monitor the height and parameter values ​​of the hook to the ground in real time. The slewing sensor is installed on the slewing wheel of the tower crane to measure the current position of the boom in real time. The wind speed sensor is installed at the top of the tower crane in the windward position. The inclination sensor is on the side of the top of the tower body to measure the inclination of the tower crane. The millimeter wave radar is installed in the middle of the tower body, and the installation height can be adjusted according to the actual situation. The high-definition camera needs to use a wide-angle high-definition camera and be installed on the top of the tower body. Multiple cameras can be installed and the camera angle can be adjusted to ensure that there is no blind spot monitoring in the tower crane detection area.

[0084] The alarm is installed outside the cab to warn the crane driver and construction workers. The wireless communication module antenna is connected to the host interface and placed on the top of the cab. The edge computer and display are installed on the left front of the tower crane cab and should not affect the driver's line of sight.

[0085] Lay the above sensor signal lines away from the power line and connect them to the host. Confirm that the power supply of the equipment is AC220V50-60Hz, reliably grounded and the grounding resistance is not greater than 4Ω. The equipment working environment temperature is -20~60℃, the working environment humidity is ≤95% (45℃), the power supply voltage is AC220V±25%, the working mode is continuous, and the comprehensive error of the load sensor is ≤0.3%.

[0086] The second is to develop a monitoring system: develop tower crane monitoring and early warning, anti-collision analysis and processing of monitoring data, and visualize the monitoring results.

[0087] The development steps of the AI ​​intelligent image recognition algorithm are as follows: Step 1, data collection and annotation: collect image or video data containing obstacles to the tower crane work, and annotate them using annotation tools; Step 2, model training: use the deep learning framework and annotated data to train the model and obtain a model that can identify the types and sizes of obstacles; Step 3, model deployment: deploy the trained model to the actual application scenario, obtain real-time data through sensors such as cameras, and identify obstacles.

[0088] For the development of anti-collision algorithms, tower crane anti-collision algorithms are mainly based on sensor technology, real-time data processing technology and artificial intelligence technology. By installing sensors on the tower crane, the position, height, amplitude and other parameters of the tower crane's boom, boom trolley, hook, etc. are monitored in real time, and these data are transmitted to the server in a timely manner. Select the position feature points of the tower crane and obstacles. For example, the tower crane needs to select the front and rear position feature points of the boom, the tower body position feature points, and the rope and hook position feature points. The spacing between the position feature points is 1m, and the number of position feature points must meet the requirement that the feature points can reflect the length, width, height and other parameters of the tower crane and the specific shape of the tower crane. The spacing between the obstacle position feature points is 0.5m, and the number of feature points must meet the requirement that the selected position feature points can reflect the length, width, height and other parameters of the obstacle and the specific shape. The anti-collision algorithm performs real-time data processing and analysis based on the position information of all tower cranes, and determines the safe distance between the tower crane and the obstacle through the algorithm. Once a situation where a collision is likely to occur is detected, such as when the safe distance between the tower crane and the obstacle is less than 20m, the system will immediately trigger an alarm to prompt the tower crane driver to shut down the crane. If the driver fails to take effective measures within 3 seconds, the anti-collision algorithm will actively shut down the tower crane to ensure the safety of the construction site.

[0089] The specific implementation steps are as follows: Step 1, data collection and transmission: Select high-precision and high-reliability sensors to ensure the accuracy and real-time nature of the data, and adopt a stable data transmission protocol to ensure that the data can be transmitted to the server in real time and accurately; Step 2, data processing and analysis: Real-time processing of the data collected by the sensor, including data cleaning, data conversion and other steps, and then make a safe distance judgment. According to the location information of the tower crane, the safe distance between the tower crane and the obstacle is calculated through an algorithm; Step 3, early warning and shutdown mechanism: When a possible collision is found, an early warning signal should be issued immediately to remind the operator to pay attention to safety. If the early warning is invalid or the risk of collision continues to increase, the shutdown device should be automatically triggered to ensure that the tower crane stops running and avoid collision accidents.

[0090] This application continuously optimizes the algorithm by introducing artificial intelligence technology to improve the accuracy and reliability of collision avoidance. According to the actual construction environment and tower crane operation conditions, the algorithm parameters and strategies are adjusted to adapt to different construction scenarios and needs.

[0091] The terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned drawings are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but optionally includes steps or units that are not listed, or optionally includes other steps or units inherent to these processes, methods, products or devices. The terms "first", "second" and "third" are used to distinguish different objects, etc., and do not represent a sequence, nor do they limit "first", "second" and "third" to different types.

[0092] In the description of the embodiments of the present application, "exemplary", "for example" or "for example" are used to indicate examples, illustrations or descriptions. Any embodiment or design described as "exemplary", "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "exemplary", "for example" or "for example" is intended to present related concepts in a specific way.

[0093] In the description of the embodiments of the present application, unless otherwise specified, “ / ” means or, for example, A / B can mean A or B; the “and / or” in the text is merely a description of the association relationship of associated objects, indicating that three relationships may exist, for example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. In addition, in the description of the embodiments of the present application, “multiple” refers to two or more than two.

[0094] In some processes described in the embodiments of the present application, multiple operations or steps that appear in a specific order are included, but it should be understood that these operations or steps may not be executed in the order in which they appear in the embodiments of the present application or in parallel, and the sequence number of the operation is only used to distinguish the different operations, and the sequence number itself does not represent any execution order. In addition, these processes may include more or fewer operations, and these operations or steps may be executed in sequence or in parallel, and these operations or steps may be combined.

[0095] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above-mentioned embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present application is essentially or the part that contributes to the prior art can be embodied in the form of a software product, which is stored in a storage medium (such as ROM / RAM, disk, CD) as described above, and includes a number of instructions for a terminal device to execute the methods described in each embodiment of the present application.

[0096] The above are only preferred embodiments of the present application, and are not intended to limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the present application specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present application.

Claims

1. A tower crane digital twin monitoring, early warning and anti-collision system based on BIM, characterized in that: The BIM-based tower crane digital twin monitoring, early warning and anti-collision system includes: The tower crane operation status monitoring module is used to monitor the operation status of the tower crane in real time, and associate the monitoring data with the created digital twin tower crane BIM model to display the operation status of the tower crane in real time, and implement tower crane operation guidance based on key indicator thresholds; The tower crane anti-collision module is used to collect data based on multiple sensors installed on the tower crane, identify the position and movement of obstacles around the tower crane through a neural network, and predict the collision risk based on the position and movement of the tower crane itself; The tower crane ergonomics analysis module is used to collect statistics and analyze the operation data of the tower crane to obtain the ergonomics analysis results of the tower crane.

2. A BIM-based tower crane digital twin monitoring, early warning and anti-collision system as claimed in claim 1, characterized in that: The tower crane BIM model is used to display the position and operation status of the boom and hook in real time, as well as the current measured values ​​of the key indicators of the tower crane, including the position, height, tilt angle, wind speed, and rotation angle of the tower crane; The tower crane operation status monitoring module provides tower crane operation guidance based on preset key indicator thresholds and current measured values ​​of the key indicators of the tower crane; The tower crane operation guidance is to indicate the working status of the tower crane, such as normal operation, full load, overload, amplitude variation exceeding the upper limit, amplitude variation exceeding the lower limit, working environment, and inclination, and to perform corresponding alarms, prompts, and controls.

3. A BIM-based tower crane digital twin monitoring, early warning and anti-collision system as claimed in claim 1, characterized in that: The tower crane anti-collision module collects data through multiple sensors installed on the boom and tower of the tower crane, and transmits the collected data to the edge computer in the tower crane cockpit to monitor the operation of the tower crane in real time, and sends the collected data to the server through the wireless communication module to calculate the position and movement of the tower crane itself. At the same time, the position and movement of obstacles around the tower crane are identified based on the AI ​​intelligent image recognition algorithm, and the collision risk is predicted based on the anti-collision algorithm combined with the position and movement of obstacles around the tower crane and the position and movement of the tower crane itself; The tower crane anti-collision module is also used to display the collision risk prediction results in the tower crane BIM model.

4. A BIM-based tower crane digital twin monitoring, early warning and anti-collision system as claimed in claim 3, characterized in that: The sensors include amplitude sensors, torque sensors, height sensors, rotation sensors, wind speed sensors, inclination sensors, millimeter wave radars, and high-definition cameras.

5. A BIM-based tower crane digital twin monitoring, early warning and anti-collision system as claimed in claim 4, characterized in that: The amplitude sensor is used to measure the running amplitude of the tower crane trolley from the center of the tower crane, taking the tower crane shaft as the pole, and measuring the radial coordinates of the hook; The torque sensor is used to measure the hoisting weight of the tower crane; The height sensor is used to measure the height of the tower crane hook, taking the tower crane shaft as the pole, and measuring the vertical coordinate of the hook; The slewing sensor is used to measure the rotation angle of the tower crane arm, taking the tower crane shaft as the pole, and measuring the arm polar angle coordinates; The wind speed sensor is used to measure the ambient wind speed; The inclination sensor is used to measure the inclination degree of the tower crane; The millimeter wave radar is used to actively detect obstacles that invade the detection area, detect the size, profile, relative position and movement of obstacles within the working range of the tower crane, and measure the spatial coordinates of the obstacles; The high-definition camera is used to collect image information near the working range of the tower crane and perform video monitoring of the environment around the tower crane.

6. A BIM-based tower crane digital twin monitoring, early warning and anti-collision system as claimed in claim 3, characterized in that: The system also includes an alarm and a display arranged in the tower crane cockpit; The alarm is used to give an audible and visual alarm when the tower crane is in an abnormal working state or there is a risk of collision; The display is used to display the tower crane operation status and collision risk prediction information.

7. A BIM-based tower crane digital twin monitoring, early warning and anti-collision system as claimed in claim 3, characterized in that: The server is used to store and transmit data collected by sensors, and to deploy AI intelligent image recognition algorithms and anti-collision algorithms; The system also includes monitoring system software, which is used to process and analyze monitoring data, and to display the operating status of the tower crane in real time through the tower crane BIM model, as well as the relative position of the tower crane and obstacles, and to issue early warning information when the working status of the tower crane is abnormal or there is a risk of collision. The monitoring system software is also used to display on-site monitoring videos and work efficiency analysis results.

8. The BIM-based tower crane digital twin monitoring, early warning and anti-collision system according to claim 1, characterized in that: The tower crane ergonomics analysis module is specifically used to count and analyze the number of times, weight and time of lifting of the tower crane to obtain the ergonomics analysis results of the tower crane; The work efficiency analysis results include the number of hoisting times, hoisting time, hoisting statistics, on-site time, hoisting efficiency, and daily online rate; The tower crane ergonomics analysis module is also used to display historical ergonomics analysis results through charts.

9. A tower crane digital twin monitoring, early warning and collision avoidance method based on BIM, implemented based on the system described in any one of claims 1 to 8, characterized in that: include: The position data of the tower crane and obstacles around the tower crane are obtained based on sensor collection, and the position data is pre-processed; Select the location feature points of the tower crane and the obstacle, and calculate the distance between the tower crane and the obstacle based on the coordinates of the location feature points; According to the distance between the tower crane and the obstacle, collision risk warning and collision prevention control are carried out.

10. A tower crane digital twin monitoring, early warning and collision avoidance method based on BIM as claimed in claim 9, characterized in that: The collision risk warning and collision prevention control are performed according to the distance between the tower crane and the obstacle, specifically including: According to the distance between the tower crane and the obstacle, determine whether the distance between the tower crane and the obstacle is greater than the preset distance: If not, a collision warning is issued, and it is determined whether the tower crane is actively shut down within the set time after the collision warning is issued. If it is actively shut down, no processing is performed; if it is not actively shut down, the tower crane is controlled to shut down; If yes, the tower crane continues to operate normally.

Citation Information

Cited By

  • Safety monitoring method and system for lifted objects of tower crane

    CN119580197A

  • Safety Monitoring Method and System for Lifted Articles of Tower Crane

    CN119580197B

  • Management method and system of wharf crane, control device, storage medium and computer program product

    CN119929673A

  • Building construction safety detection method and system based on BIM and VR technology

    CN120450447A

  • Intelligent identification and alarm system for area hoisted by tower crane

    CN120622314A