Dustproof drilling device for building construction and dustproof method

By using a protective cover and a drilling device with a mounting ring structure during construction, the problem of crushing and dust caused by friction between the drill bit and the wall is solved, the dust is effectively captured and cleaned, and the health and safety of workers and the cleanliness of the construction environment are improved. Spend.

CN118849219APending Publication Date: 2024-10-29FUJIAN JIUDING CONSTR GRP CO LTD

Patent Information

Application Number
CN202410997193.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2024-10-29

AI Technical Summary

Technical Problem

During construction, the high-speed friction between the drill bit and the wall when drilling with a hand-held electric drill causes construction materials to be crushed. Parts of incompletely crushed materials fall to the ground or turn into dust, polluting the on-site environment and endangering the health of workers.

Method used

Design a dust-proof drilling device for construction. It adopts a protective cover and installation ring structure. The protective cover is close to the wall. The dust generated during the drilling process of the drill bit is covered. It combines magnetism, springs and rubber rings to improve the stability of the protective cover. performance and sealing, and equipped with a vacuum pump to clean dust.

Benefits of technology

It effectively avoids high-speed friction between the drill bit and the wall, reduces the falling of crushed materials and dust pollution, improves the health and safety of workers, and is easy to install and disassemble.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118849219A_ABST
    Figure CN118849219A_ABST
Patent Text Reader

Abstract

The invention provides a dustproof drilling device for building construction and a dustproof method, and relates to the technical field of drilling device.The dustproof drilling device comprises a drill body, a grip is fixedly connected to the drill body, a switch is arranged on the grip, a drill clamp is rotationally connected to the drill body, a drill bit is arranged on the drill clamp, a motor is fixedly connected to the interior of the drill body, and the motor is connected to the interior of the drill body. A motor is arranged on the drill body, an output shaft of the motor is fixedly connected with the drill clamp, a protective structure is arranged on the drill body, and the protective structure is mainly composed of a protective cover. The problems that part of building materials which are not thoroughly crushed fall onto the ground and need to be manually cleaned for the second time, part of the building materials which are thoroughly crushed become flying dust, the whole building site environment is polluted by the flying dust, the flying dust is easily inhaled by workers, and the body health of the workers is damaged are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of drilling devices, and in particular to a drilling device and a dust prevention method for building construction. Background Art

[0002] In construction, it is often necessary to drill holes in walls. Generally, workers will use a handheld electric drill to drill holes in the wall. The electric drill drives the drill bit on the gun head to rotate through the internal motor, and the drill bit drills the required holes in the wall.

[0003] When using the current dust-proof drilling device for construction, workers often find that when the current handheld electric drill is drilling, the drill bit rubs against the wall at high speed, causing the building materials on the wall to be crushed. Some of the building materials that are not crushed thoroughly will fall to the ground and need to be manually cleaned up again. Some of the building materials that are completely crushed will become dust, which will pollute the overall construction site environment and is easily inhaled by workers, causing damage to the workers' health. Summary of the invention

[0004] The purpose of the present invention is to solve the shortcomings of the prior art and to propose a dust-proof drilling device and a dust-proof method for construction.

[0005] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a dust-proof drilling device and dust-proof method for construction, comprising a drill body, a handle fixedly connected to the drill body, a switch provided on the handle, a drill clamp rotatably connected to the drill body, a drill bit provided on the drill clamp, a motor fixedly connected in the drill body, an output shaft of the motor fixedly connected to the drill clamp, a protective structure provided on the drill body, the protective structure mainly consisting of a protective cover, the protective cover provided on the drill body, a sliding ring fixedly connected to the protective cover, a connecting ring provided on the sliding ring, a mounting ring fixedly connected to the connecting ring, a mounting groove provided on the drill body, and the mounting ring is adapted to the size of the mounting groove.

[0006] The effect achieved by the above components is: the drill bit is installed on the drill clamp, the staff holds the handle and presses the switch, the switch connects the internal circuit, and then drives the output shaft of the motor to drive the drill clamp to rotate, and then drives the drill bit to rotate. The staff inserts the mounting ring into the mounting groove to install the protective cover on the drill body. The staff puts one end of the protective cover close to the wall where the hole needs to be drilled. The dust generated during the drilling process of the drill bit will be covered by the protective cover and cannot fly in the external environment or fall on the ground, thereby avoiding the situation where the drill bit and the wall are rubbed at high speed when drilling with the current handheld electric drill, causing the building materials on the wall to be crushed. Some of the building materials that are not completely crushed will fall to the ground and need to be manually cleaned for a second time. Some of the building materials that are completely crushed will become dust, and the dust will pollute the overall construction site environment and is easily inhaled by workers, causing damage to the workers' health.

[0007] Preferably, three circular grooves are respectively provided on the inner walls on both sides of the mounting groove, a telescopic rod is fixedly connected in the circular groove, a round ball is fixedly connected to one end of the telescopic rod, a first spring is sleeved on the telescopic rod, one end of the first spring is fixedly connected to the round ball, and the other end of the first spring is fixedly connected to the inner wall of the circular groove, three limiting grooves are respectively provided on both sides of the mounting ring, and the round ball is adapted to the size of the limiting grooves.

[0008] The effect achieved by the above-mentioned components is: when the mounting ring is inserted into the mounting groove, the mounting ring will push the smooth surface of the ball to make it retract into the round groove. At this time, the telescopic rod and the first spring are both contracted. When the mounting ring is completely inserted into the mounting groove, the ball contacts the limiting groove, and the ball is inserted into the limiting groove under the action of the rebound force of the first spring, making the connection between the mounting ring and the mounting groove more stable, thereby improving the stability of the protective cover. Conversely, when the protective cover needs to be removed, the side wall of the limiting groove will push the ball into the round groove and squeeze the first spring to contract, making the installation and disassembly operations more convenient.

[0009] Preferably, a first magnetic block is fixedly connected to the mounting ring, a second magnetic block is fixedly connected to the mounting groove, and two surfaces of the first magnetic block and the second magnetic block in contact are attracted to each other with opposite poles.

[0010] The effect achieved by the above components is that when the mounting ring is inserted into the mounting groove, the first magnetic block and the second magnetic block are attracted together under the action of magnetic force, which can further improve the stability of the connection.

[0011] Preferably, a sliding groove is provided on the connecting ring, and the sliding groove is slidably connected to the sliding ring.

[0012] The effect achieved by the above components is: during the drilling process, the staff will hold the handle and continuously push the drill body so that the drill bit is continuously inserted into the wall. During this process, the sliding ring can slide into the slide groove to prevent affecting the depth of the drilling.

[0013] Preferably, three second springs are arranged in the slide groove, one end of the second spring is fixedly connected to the sliding ring, and the other end of the second spring is fixedly connected to the inner wall of the slide groove.

[0014] The effect achieved by the above components is: when the sliding ring slides into the sliding groove, it will squeeze the three second springs to shrink, so the rebound force of the three second springs will act on the sliding ring, and then act on the protective cover, so that the protective cover fits the wall more closely, thereby improving the protective effect.

[0015] Preferably, a rubber ring is fixedly connected to the protective cover.

[0016] The effects achieved by the above components are: the rubber ring can improve the sealing performance of the position where the protective cover is fitted to the wall, prevent dust and the like from leaking out from the gap where the protective cover is fitted to the wall, and further improve the protective effect.

[0017] Preferably, a cleaning structure is provided on the protective cover, and the cleaning structure is mainly composed of an ash receiving frame, the ash receiving frame is fixedly connected to the protective cover, and the protective cover is in communication with the ash receiving frame.

[0018] The effect achieved by the above components is: the dust and debris generated during the drilling process falls into the protective cover, and will slide along the inner wall of the protective cover to the dust receiving frame, which is convenient for collection and can prevent dust from accumulating on the inner wall of the protective cover. When the protective cover is removed after drilling is completed, the dust will slide to the ground.

[0019] Preferably, a baffle is slidably inserted on the ash receiving frame, and fixing blocks are fixedly connected to both sides of the ash receiving frame respectively, and a round rod is slidably inserted on the fixing block, and the round rod is fixedly connected to the baffle.

[0020] The effect achieved by the above components is: pulling the baffle outwards can make the dust and other debris in the ash receiving frame fall down, making it convenient to handle the debris collected in the ash receiving frame.

[0021] Preferably, a third spring is sleeved on the round rod, one end of the third spring is fixedly connected to the round rod, and the other end of the third spring is fixedly connected to the fixed block.

[0022] The effect achieved by the above components is: when the baffle is pulled outward, the two third springs are in a contracted state. Therefore, after the dust in the ash receiving frame is cleaned, the baffle is released, and the baffle slides inward under the action of the rebound force of the two third springs until it fits with the inner wall of the ash receiving frame. At this time, the third spring is still in a contracted state. The baffle will be tightly attached to the inner wall of the ash receiving frame under the action of the third spring, thereby preventing the baffle from sliding outward during the drilling process.

[0023] Preferably, a connecting pipe is fixedly connected to the ash receiving frame, the ash receiving frame is connected to the connecting pipe, one end of the connecting pipe is fixedly connected to a dust suction pump, the input end of the dust suction pump is connected to the connecting pipe, and the output end of the dust suction pump is fixedly connected to a dust collecting box.

[0024] The effect achieved by the above components is: when the workers continue drilling, a lot of dust and debris are generated, and the dust suction pump can be started. The dust suction pump can suck the generated dust into the dust collecting box through the connecting pipe, and then during long-term drilling, there is no need to constantly pull the baffle to clean the debris generated in the dust collecting frame.

[0025] Preferably, a method for preventing dust from drilling during construction is provided, and a drilling device for preventing dust from drilling during construction is provided.

[0026] Compared with the prior art, the advantages and positive effects of the present invention are that, in the present invention, by setting a protective structure, the staff can install the protective cover on the drill body by inserting the installation ring into the installation groove. The staff puts one end of the protective cover close to the wall where the hole needs to be drilled. The dust generated during the drilling process of the drill bit will be covered by the protective cover and cannot fly into the external environment or fall on the ground. When the installation ring is inserted into the installation groove, the installation ring will push the smooth surface of the round ball to make it retract into the round groove. At this time, the telescopic rod and the first spring are both contracted. When the installation ring is completely inserted into the installation groove, the round ball contacts the limiting groove, and the round ball is inserted into the limiting groove under the action of the rebound elastic force of the first spring, so that the connection between the installation ring and the installation groove is more stable, thereby improving the stability of the protective cover. On the contrary, when the protective cover needs to be removed, the side wall of the limiting groove will push the round ball to be retracted into the round groove and squeeze the first spring to contract, making the installation and disassembly operations more convenient. When the installation ring is inserted into the installation groove, the first magnetic block and the second magnetic block are attracted together under the action of magnetic force, which can further improve The stability of the connection. During the drilling process, the worker will hold the handle and continuously push the drill body so that the drill bit is continuously inserted into the wall. The sliding ring can slide into the slide groove during this process to prevent affecting the depth of the drilling hole. The sliding ring slides into the slide groove, which will squeeze the three second springs to shrink. Therefore, the rebound elastic force of the three second springs will act on the sliding ring, and then act on the protective cover, so that the protective cover and the wall are more closely fitted, thereby improving the protection effect. The rubber ring can improve the sealing of the position where the protective cover and the wall are fitted, and prevent dust from leaking from the gap where the protective cover and the wall are fitted, which can further improve the protection effect, thereby avoiding the situation where the drill bit and the wall are rubbed at high speed when the current handheld electric drill is drilling, causing the building materials on the wall to be crushed. Some of the building materials that are not completely crushed will fall to the ground and need to be manually cleaned for a second time. Some of the building materials that are completely crushed will become dust, and the dust will pollute the overall construction site environment and is easily inhaled by workers, causing damage to the workers' health. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 A three-dimensional structural schematic diagram of a drilling device and a dust prevention method for building construction proposed by the present invention;

[0028] Figure 2 A schematic diagram of the three-dimensional structure from another perspective of a drilling device and a dust prevention method for construction dust prevention proposed by the present invention;

[0029] Figure 3 A partial schematic diagram of a protective structure of a drilling device and a dust prevention method for construction dust prevention proposed by the present invention;

[0030] Figure 4 The present invention proposes a drilling device and a dust prevention method for building construction Figure 2 A magnified view of part A;

[0031] Figure 5 The present invention proposes a drilling device and a dust prevention method for building construction Figure 3 A magnified view of part B;

[0032] Figure 6 A partial schematic diagram of a chute in a drilling device and a dust prevention method for construction dust prevention proposed by the present invention;

[0033] Figure 7 The present invention proposes a drilling device and a dust prevention method for building construction Figure 6 Magnified view of part C.

[0034] Legend: 1. Drill body; 2. Handle; 3. Switch; 4. Drill clamp; 5. Drill bit; 6. Protective structure; 61. Protective cover; 62. Sliding ring; 63. Connecting ring; 64. Mounting ring; 65. Mounting groove; 66. Round groove; 67. Telescopic rod; 68. Round ball; 69. Limiting groove; 610. First spring; 611. First magnetic block; 612. Second magnetic block; 613. Slide groove; 614. Second spring; 615. Rubber ring; 7. Cleaning structure; 71. Dust receiving frame; 72. Baffle; 73. Fixed block; 74. Round rod; 75. Third spring; 76. Connecting pipe; 77. Dust collecting box; 78. Dust suction pump. DETAILED DESCRIPTION

[0035] Embodiment 1, as Figure 1-7 As shown, a dust-proof drilling device and dust-proof method for construction include a drill body 1, a handle 2 is fixedly connected to the drill body 1, a switch 3 is provided on the handle 2, a drill clamp 4 is rotatably connected to the drill body 1, a drill bit 5 is provided on the drill clamp 4, a motor is fixedly connected in the drill body 1, and the output shaft of the motor is fixedly connected to the drill clamp 4.

[0036] Reference Figures 2 to 4A protective structure 6 is provided on the drill body 1. The protective structure 6 is mainly composed of a protective cover 61. The protective cover 61 is provided on the drill body 1. A sliding ring 62 is fixedly connected to the protective cover 61. A connecting ring 63 is provided on the sliding ring 62. A mounting ring 64 is fixedly connected to the connecting ring 63. A mounting groove 65 is provided on the drill body 1. The mounting ring 64 is adapted to the mounting groove 65 in size. The drill bit 5 is installed on the drill clamp 4. The staff holds the handle 2 and presses the switch 3. The switch 3 connects the internal circuit, thereby driving the output shaft of the motor to drive the drill clamp 4 to rotate, thereby driving the drill bit 5 to rotate. The staff inserts the mounting ring 64 into the mounting groove 65 to install the protective cover 61 on the drill body 1. The staff puts one end of the protective cover 61 close to the hole to be drilled. The dust generated during the drilling process of the drill bit 5 will be covered by the protective cover 61 and cannot fly into the external environment or fall on the ground, thereby avoiding the situation that when the current handheld electric drill is drilling, the drill bit 5 rubs against the wall at high speed, causing the building materials on the wall to be crushed. Some of the building materials that are not completely crushed will fall to the ground and need to be manually cleaned for a second time. Some of the building materials that are completely crushed will become dust, which will pollute the overall construction site environment and is easily inhaled by workers, causing damage to the workers' health. Three circular grooves 66 are respectively opened on the inner walls of both sides of the installation groove 65. A telescopic rod 67 is fixedly connected in the circular groove 66. A round ball 68 is fixedly connected to one end of the telescopic rod 67. A first spring is sleeved on the telescopic rod 67 610, one end of the first spring 610 is fixedly connected to the ball 68, and the other end of the first spring 610 is fixedly connected to the inner wall of the circular groove 66. Three limiting grooves 69 are respectively provided on both sides of the mounting ring 64. The ball 68 and the limiting groove 69 are adapted in size. When the mounting ring 64 is inserted into the mounting groove 65, the mounting ring 64 will push the smooth surface of the ball 68 to retract it into the circular groove 66. At this time, the telescopic rod 67 and the first spring 610 are both contracted. When the mounting ring 64 is completely inserted into the mounting groove 65, the ball 68 contacts the limiting groove 69, and the ball 68 is inserted into the limiting groove 69 under the action of the rebound elastic force of the first spring 610, so that the connection between the mounting ring 64 and the mounting groove 65 is more stable, thereby improving the stability of the protective cover 61. Otherwise, the telescopic rod 67 and the first spring 610 are required to be fixedly connected to the circular groove 65. When the protective cover 61 is to be removed, the side wall of the limiting groove 69 will push the ball 68 into the groove 66 and squeeze the first spring 610 to contract, making the installation and disassembly operations more convenient. The first magnetic block 611 is fixedly connected to the installation ring 64, and the second magnetic block 612 is fixedly connected to the installation groove 65. The two surfaces of the first magnetic block 611 and the second magnetic block 612 in contact are oppositely polarized and attracted to each other. When the installation ring 64 is inserted into the installation groove 65, the first magnetic block 611 and the second magnetic block 612 are attracted together under the action of magnetic force, which can further improve the stability of the connection. A sliding groove 613 is provided on the connecting ring 63, and the sliding groove 613 is slidably connected to the sliding ring 62. During the drilling process, the staff will hold the handle 2 and continuously push the drill body 1, so that the drill bit 5 is continuously inserted into the wall.During this process, the sliding ring 62 can slide into the slide groove 613 to prevent affecting the depth of the drilling hole. Three second springs 614 are arranged in the slide groove 613. One end of the second spring 614 is fixedly connected to the sliding ring 62, and the other end of the second spring 614 is fixedly connected to the inner wall of the slide groove 613. When the sliding ring 62 slides into the slide groove 613, the three second springs 614 will be squeezed to shrink. Therefore, the rebound elastic force of the three second springs 614 will act on the sliding ring 62, and then act on the protective cover 61, so that the protective cover 61 is more closely fitted to the wall, thereby improving the protective effect. A rubber ring 615 is fixedly connected to the protective cover 61. The rubber ring 615 can improve the sealing performance of the protective cover 61 and the wall, prevent dust from leaking from the gap between the protective cover 61 and the wall, and further improve the protective effect.

[0037] Reference Figure 1 and Figure 5 The protective cover 61 is provided with a cleaning structure 7, which is mainly composed of an ash receiving frame 71, which is fixedly connected to the protective cover 61, and the protective cover 61 is connected to the ash receiving frame 71. The dust and debris generated during the drilling process fall into the protective cover 61, and will slide along the inner wall of the protective cover 61 into the ash receiving frame 71, which is convenient for collection and can prevent dust from accumulating on the inner wall of the protective cover 61. When the protective cover 61 is removed after drilling, the dust will slide to the ground. The ash receiving frame 71 is provided with a sliding plug The baffle plate 72 and the ash receiving frame 71 are fixedly connected to fixed blocks 73 on both sides, and a round rod 74 is slidably inserted on the fixed block 73. The round rod 74 is fixedly connected to the baffle plate 72. Pulling the baffle plate 72 outward can make the dust and other debris in the ash receiving frame 71 fall down, so that it is convenient to deal with the debris collected in the ash receiving frame 71. A third spring 75 is sleeved on the round rod 74. One end of the third spring 75 is fixedly connected to the round rod 74, and the other end of the third spring 75 is fixedly connected to the fixed block 73. Pulling the baffle plate 72 outward can make the dust and other debris in the ash receiving frame 71 fall down, so that it is convenient to deal with the debris collected in the ash receiving frame 71. 2, the two third springs 75 are in a contracted state. Therefore, after the dust in the ash receiving frame 71 is cleaned, the baffle plate 72 is released, and the baffle plate 72 slides inwardly under the action of the rebound elastic force of the two third springs 75 until it fits with the inner wall of the ash receiving frame 71. At this time, the third spring 75 is still in a contracted state. The baffle plate 72 will fit closely with the inner wall of the ash receiving frame 71 under the action of the third spring 75, so as to prevent the baffle plate 72 from sliding outward during the drilling process. The ash receiving frame 71 is fixedly connected with a connecting pipe 76. 1 is connected to the connecting pipe 76, one end of the connecting pipe 76 is fixedly connected to a dust suction pump 78, the input end of the dust suction pump 78 is connected to the connecting pipe 76, and the output end of the dust suction pump 78 is fixedly connected to a dust collecting box 77. When the worker continues to drill, a lot of dust and debris are generated, and the dust suction pump 78 can be started. The dust suction pump 78 can suck the generated dust and the like into the dust collecting box 77 through the connecting pipe 76, and then during a long period of drilling, there is no need to constantly pull the baffle 72 to clean the debris generated in the dust receiving frame 71.

[0038] Working principle: install the drill bit 5 on the drill clamp 4, the staff holds the handle 2 and presses the switch 3, the switch 3 makes the internal circuit connected, and then drives the output shaft of the motor to drive the drill clamp 4 to rotate, and then drives the drill bit 5 to rotate, the staff inserts the mounting ring 64 into the mounting groove 65, and then installs the protective cover 61 on the drill body 1, the staff puts one end of the protective cover 61 close to the wall where the hole needs to be drilled, and the dust generated during the drilling process of the drill bit 5 will be covered by the protective cover 61, and cannot fly in the external environment or fall on the ground, thereby avoiding the high-speed friction between the drill bit 5 and the wall when drilling with the current handheld electric drill, which causes the building materials on the wall to be crushed, and some of the building materials that are not crushed thoroughly will fall to the ground, requiring manual secondary cleaning, Some of the construction materials that are completely crushed will turn into dust, which will pollute the overall construction site environment and can be easily inhaled by workers, causing damage to their health. When the mounting ring 64 is inserted into the mounting groove 65, the mounting ring 64 will push the smooth surface of the ball 68 to retract it into the circular groove 66. At this time, the telescopic rod 67 and the first spring 610 are both contracted. When the mounting ring 64 is completely inserted into the mounting groove 65, the ball 68 contacts the limiting groove 69. The ball 68 is inserted into the limiting groove 69 under the action of the rebound force of the first spring 610, making the connection between the mounting ring 64 and the mounting groove 65 more stable, thereby improving the stability of the protective cover 61. On the contrary, when the protective cover 61 needs to be removed, the side wall of the limiting groove 69 will push the ball 68 to retract into the circular groove 66, and squeeze the first spring 610 to shrink, making the installation and disassembly operations more convenient. When the installation ring 64 is stuck in the installation groove 65, the first magnetic block 611 and the second magnetic block 612 are attracted together under the action of magnetic force, which can further improve the stability of the connection. During the drilling process, the staff will hold the handle 2 and continuously push the drill body 1, so that the drill bit 5 is continuously inserted into the wall. During this process, the sliding ring 62 can slide into the sliding groove 613 to prevent affecting the depth of the drilling. The sliding ring 62 slides into the sliding groove 613, which will squeeze the three second springs 614 to shrink. Therefore, the rebound elastic force of the three second springs 614 will act on the sliding ring 62, and then act on the protective cover 61, so that the protective cover 61 has a higher fit with the wall, thereby improving the protection effect. The rubber ring 615 can improve the sealing performance of the position where the protective cover 61 fits the wall, prevent dust and the like from leaking out from the gap where the protective cover 61 fits the wall, and can further improve the protection effect. The dust and debris generated during the drilling process fall into the protective cover 61, and will slide along the inner wall of the protective cover 61 into the ash receiving frame 71, which is convenient for collection and can prevent dust and the like from accumulating on the inner wall of the protective cover 61. When the drilling is completed and the protective cover 61 is removed, the dust and the like will slide to the ground, and the baffle plate 72 can be pulled outward to make the dust and the like in the ash receiving frame 71 fall, which is convenient for handling the debris and the like collected in the ash receiving frame 71. When the baffle plate 72 is pulled outward, the two third springs 75 are in a contracted state. Therefore, after the dust in the ash receiving frame 71 is cleaned, the baffle plate 72 is released.The baffle 72 will slide inwards under the action of the rebound force of the two third springs 75 until it fits with the inner wall of the ash receiving frame 71, and at this time the third spring 75 is still in a contracted state. The baffle 72 will fit closely with the inner wall of the ash receiving frame 71 under the action of the third spring 75, which can prevent the baffle 72 from sliding outwards during the drilling process. When the staff continues to drill, a lot of dust and debris are generated. The dust suction pump 78 can be started. The dust suction pump 78 can suck the generated dust and the like into the dust collecting box 77 through the connecting pipe 76, and then during long-term drilling, there is no need to constantly pull the baffle 72 to clean the debris generated in the ash receiving frame 71.

[0039] The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention in other forms. Any technician familiar with the profession may use the above disclosed technical content to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the technical solution of the present invention still belongs to the protection scope of the technical solution of the present invention. In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

Claims

1. A dust-proof drilling device for construction, comprising a drilling body (1), Features: The drill body (1) is fixedly connected with a handle (2), and a switch (3) is arranged on the handle (2). The drill body (1) is rotatably connected with a drill clamp (4), and a drill bit (5) is arranged on the drill clamp (4). The drill body (1) is fixedly connected with a motor, and the output shaft of the motor is fixedly connected with the drill clamp (4). The drill body (1) is provided with a protective structure (6), and the protective structure (6) mainly consists of a protective cover (61). The protective cover (61) is arranged on the drill body (1), and a sliding ring (62) is fixedly connected to the protective cover (61). A connecting ring (63) is arranged on the sliding ring (62), and a mounting ring (64) is fixedly connected to the connecting ring (63). A mounting groove (65) is opened on the drill body (1), and the mounting ring (64) is adapted to the mounting groove (65) in size.

2. The construction dust-proof drilling device according to claim 1, Features: Three circular grooves (66) are respectively provided on the inner walls on both sides of the installation groove (65), a telescopic rod (67) is fixedly connected in the circular groove (66), one end of the telescopic rod (67) is fixedly connected to a round ball (68), a first spring (610) is sleeved on the telescopic rod (67), one end of the first spring (610) is fixedly connected to the round ball (68), and the other end of the first spring (610) is fixedly connected to the inner wall of the circular groove (66), and three limiting grooves (69) are respectively provided on both sides of the installation ring (64), and the round ball (68) is adapted to the limiting groove (69) in size.

3. The construction dust-proof drilling device according to claim 2, Features: A first magnetic block (611) is fixedly connected to the mounting ring (64), and a second magnetic block (612) is fixedly connected to the mounting groove (65); the two surfaces of the first magnetic block (611) and the second magnetic block (612) in contact are mutually attracted with opposite poles.

4. The construction dust-proof drilling device according to claim 3, Features: The connecting ring (63) is provided with a sliding groove (613), and the sliding groove (613) is slidably connected to the sliding ring (62).

5. The construction dust-proof drilling device according to claim 4, Features: Three second springs (614) are arranged in the slide groove (613), one end of the second spring (614) is fixedly connected to the sliding ring (62), and the other end of the second spring (614) is fixedly connected to the inner wall of the slide groove (613).

6. The construction dust-proof drilling device according to claim 5, Features: A rubber ring (615) is fixedly connected to the protective cover (61).

7. The dust-proof drilling device for construction according to claim 6, Features: The protective cover (61) is provided with a cleaning structure (7), and the cleaning structure (7) is mainly composed of an ash receiving frame (71). The ash receiving frame (71) is fixedly connected to the protective cover (61), and the protective cover (61) is in communication with the ash receiving frame (71).

8. The dust-proof drilling device for construction according to claim 7, Features: A baffle (72) is slidably inserted on the ash receiving frame (71), and fixed blocks (73) are respectively fixedly connected to both sides of the ash receiving frame (71). A round rod (74) is slidably inserted on the fixed block (73), and the round rod (74) is fixedly connected to the baffle (72).

9. The construction dust-proof drilling device according to claim 7, Features: A third spring (75) is sleeved on the round rod (74), one end of the third spring (75) is fixedly connected to the round rod (74), and the other end of the third spring (75) is fixedly connected to the fixed block (73). A connecting pipe (76) is fixedly connected to the ash receiving frame (71), the ash receiving frame (71) is connected to the connecting pipe (76), one end of the connecting pipe (76) is fixedly connected to a dust suction pump (78), the input end of the dust suction pump (78) is connected to the connecting pipe (76), and the output end of the dust suction pump (78) is fixedly connected to a dust collecting box (77).

10. A method for preventing dust from drilling holes in construction. Features: A drilling device for preventing dust in construction as claimed in any one of claims 1 to 9.

Citation Information

Patent Citations

  • Extension type protective cover for drilling machine

    CN108526994A

  • Wall perforating machine with dust removal function

    CN210148437U

  • Drilling dustproof device

    CN213563613U

  • Dustproof electric drill

    CN214517750U

  • Wall dustproof drilling machine for house building construction

    CN216068097U

Cited By

  • Drilling device for tunnel construction

    CN122190616A

  • A drilling device for tunnel construction

    CN122190616B

  • Tunnel side wall bush hammer

    CN122560265A