Large-span high pier capping beam construction method

By optimizing the construction technology and support system and adopting a multi-step cap beam construction method, the risks and high costs in the construction of the existing large-span portal pier cap beams were solved, and a fast, safe, economical and efficient construction effect was achieved.

CN118854801APending Publication Date: 2024-10-29CHINA FIRST HIGHWAY ENGINEERING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411206236.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-10-29

AI Technical Summary

Technical Problem

The existing long-span portal pier cap beam construction method has problems such as high construction risks, high costs, long construction period, and material waste, and cannot meet the needs of construction safety and production.

Method used

A construction method including the installation of corbels, brackets, sand tubes, Bailey beams, transverse distribution beams, buckle brackets, bottom formwork and preloading is adopted. Through two concrete pourings and prestressed tensioning and grouting, operation, combined with a specific geometric support system, to optimize the construction process to improve efficiency and safety.

Benefits of technology

It achieves fast and efficient construction of high piers and large-span capped beams, shortens the construction period, saves materials, reduces costs, and ensures construction quality and safety. It is suitable for the construction of cast-in-place beams with high piers and complex terrain.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention discloses a construction method for a large-span high-pier bent cap. The construction method comprises the following steps: (1) mounting a bracket; (2) mounting a bracket; (3) mounting a sand cylinder and a main cross beam; (4) Bailey beam installation; (5) mounting a transverse distribution beam; (6) mounting a disc buckle bracket; (7) a bottom die is mounted and pre-pressed; (8) mounting reinforcing steel bars and side forms; (9) pouring concrete; and (10) pre-stress tensioning and grouting operation of the cover beam. Construction is rapid, efficient, safe and reliable, the construction efficiency can be greatly improved, the construction period can be greatly shortened, materials are saved, cost is reduced, quality is guaranteed, and economy and practicability are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a construction method for a large-span high-pier cap beam. Background Art

[0002] When a highway is built across an existing road or mountain, a portal pier + cap beam system is generally used. A large-span cast-in-place rectangular portal pier + concrete cap beam is a commonly used bridge pier column form. Prestressing after casting can increase the load-bearing capacity of the cap beam. The portal pier cap beam has problems such as large span, high pier height, heavy load, high construction risk and difficulty in crossing existing roads, high cost, and long construction period.

[0003] For the existing high-pier and large-span portal pier cap beam construction, the commonly used support systems are mostly steel pipe support method, hoop method or full-frame support method. The steel pipe support method occupies a large area, requires a lot of steel pipe materials for the high pier, has a long construction period and high cost; the support structure of other construction methods is not optimized enough, resulting in material waste, so the support optimization design for cap beam construction is particularly important. For the existing large-span portal pier prestressed concrete cast-in-place cap beam construction, traditional support erection methods, hoop method, full-frame support method, etc. can no longer meet the needs of on-site construction safety production. Summary of the invention

[0004] In order to solve the defects in the prior art, the present invention provides a large-span high pier cap beam construction method. The present invention is fast, efficient, safe and reliable, can greatly improve construction efficiency and shorten construction period, and can save materials, reduce costs, ensure quality and be economical and practical.

[0005] To achieve the above object, the present invention provides a method for constructing a long-span high pier cap beam, comprising the following steps:

[0006] (1) Install the corbels: After the pier column construction is completed, fix the corbels on the pier column;

[0007] (2) Install the bracket: Install the bracket on the corbel and install it symmetrically on both sides of the pier;

[0008] (3) Installation of sand cylinder and main beam: The main beam is placed on a triangular bracket, and a sand cylinder is installed on the upper part of the main beam to facilitate later removal;

[0009] (4) Bailey beam installation: First, assemble the Bailey beam under the bridge, connect it into a whole, then hoist it to the designed position and fix it;

[0010] (5) Installation of transverse distribution beam: Install the transverse distribution beam on top of the Bailey beam and connect the two firmly;

[0011] (6) Installation of the buckle bracket;

[0012] (7) Install the bottom formwork and preload; measure and release the elevation control point, install the bottom formwork of the cap beam, and then preload;

[0013] (8) Installation of steel bars and side formwork;

[0014] (9) Concrete pouring: two pouring methods are adopted;

[0015] (10) Prestressing and grouting operations of the cap beam.

[0016] Preferably, in the step (1), a Φ42 mm PVC pipe that passes through the pier is pre-embedded on the steel formwork at the top part of the pier according to the designed height, and is used as a tie rod hole after pouring concrete, and a corbel box is pre-embedded at the same time; after the concrete pouring construction of the pier is completed, the steel formwork at the top part of the pier is retained, and a Φ32 mm fine-rolled threaded steel bar is inserted into the Φ42 mm PVC pipe to fix the corbel on the steel formwork at the top part of the pier and fix it with a three-layer nut.

[0017] In any of the above schemes, it is preferred that in step (2), each group of brackets is composed of 3 groups of triangular load-bearing frames and is formed through a tensioning structure, and a flat joint is arranged between each group of brackets, and the flat joint is connected by 14b channel steel.

[0018] In any of the above schemes, it is preferred that in step (3), the main crossbeam is made of double-pieced I50b I-beams placed horizontally on a triangular bracket, and a sand cylinder is installed in the middle of the upper part of the main crossbeam; the sand cylinder is cylindrical, and a pull-out plate is provided at the bottom; after the construction of the cap beam is completed, the sand in the sand cylinder can be quickly taken out by pulling out the pull-out plate at the bottom of the sand cylinder, so that the construction components above the sand cylinder are separated from the cap beam, so that these construction components can be dismantled and recycled.

[0019] In any of the above schemes, it is preferred that in step (4), during installation, multiple Bailey plates are first connected into multiple groups of Bailey beams using 22.5 cm fixed flower racks under the bridge, and then the assembled Bailey beams are hoisted to the main beam positions determined by measurement and layout using a tower crane, and the Bailey beams are fixed to the main beam positions using U-shaped clips; [8 channel steel scissors braces are used in the transverse direction of the bridge, and multiple groups of Bailey beams are connected into a whole using bolts.

[0020] In any of the above schemes, it is preferred that in step (5), the transverse distribution beam is made of double-pieced I16 I-beams, which are arranged horizontally above the Bailey beam, and the spacing between adjacent transverse distribution beams is 0.6m. The transverse distribution beam and the lower Bailey beam are firmly connected with riding bolts.

[0021] In any of the above schemes, it is preferred that in step (6), an adjustable top support is provided after the installation of the disc buckle bracket is completed to achieve effective adjustment of the elevation of the bottom formwork of the cap beam.

[0022] In any of the above schemes, it is preferred that in step (7), the sandbag preloading method is used for preloading, and the preloading weight is divided into five levels, namely 55%, 75%, 95%, 105% and 120% of the weight of the cap beam cast concrete.

[0023] In any of the above schemes, it is preferred that in step (9), the first pouring is to 1.75m above the bottom of the cap beam, and the second pouring is to the designed elevation; before the second pouring, the concrete bonding surface of the first pouring needs to be roughened so that the two concretes are combined into a whole.

[0024] In any of the above solutions, preferably, after step (10), all construction components used in the above steps are removed in sequence.

[0025] Beneficial effects of the present invention:

[0026] 1. The invention is fast, efficient, safe and reliable in construction, can greatly improve construction efficiency and shorten construction period, and can save materials, reduce costs, ensure quality and be economical and practical.

[0027] 2. The present invention realizes the rapid and efficient construction of high-pier and large-span cap beams. The construction method and technology are mature and can ensure the construction quality of the cap beam. The construction personnel can have sufficient working platform space at high altitudes, which can effectively ensure the construction safety and high safety. At the same time, it will not affect the traffic of vehicles within the construction range of the cap beam.

[0028] 3. The present invention is suitable for the construction of cast-in-place beams with high pier heights and obstructed terrain conditions. It has the advantages of high construction safety factor and short construction period. The support system has a specific geometric system, and the support effect is more solid and stable. At the same time, through the mutual cooperation and coordination of various construction steps, the construction intensity is reduced, the construction time is saved, and the construction efficiency is improved. DETAILED DESCRIPTION

[0029] The technical solution of the present application will be described in detail below in conjunction with the specific implementation methods of the present application, but the following examples are only for understanding the present invention. The embodiments in the present application and the features in the embodiments can be combined with each other, and the present application can be implemented in a variety of different ways as defined and covered by the claims.

[0030] Example 1

[0031] A method for constructing a long-span high pier cap beam comprises the following steps:

[0032] (1) Install the corbels: After the pier column construction is completed, fix the corbels on the pier column;

[0033] (2) Install the bracket: Install the bracket on the corbel and install it symmetrically on both sides of the pier;

[0034] (3) Installation of sand cylinder and main beam: The main beam is placed on a triangular bracket, and a sand cylinder is installed on the upper part of the main beam to facilitate later removal;

[0035] (4) Bailey beam installation: First, assemble the Bailey beam under the bridge, connect it into a whole, then hoist it to the designed position and fix it;

[0036] (5) Installation of transverse distribution beam: Install the transverse distribution beam on top of the Bailey beam and connect the two firmly;

[0037] (6) Installation of the buckle bracket;

[0038] (7) Install the bottom formwork and preload; measure and release the elevation control point, install the bottom formwork of the cap beam, and then preload;

[0039] (8) Installation of steel bars and side formwork;

[0040] (9) Concrete pouring: two pouring methods are adopted;

[0041] (10) Prestressing and grouting operations of the cap beam.

[0042] In the step (1), a 42 mm Φ PVC pipe that passes through the pier is embedded in the steel formwork at the top of the pier according to the designed height, and is used as a tie rod hole after concrete is poured, and a corbel box is embedded at the same time; after the concrete pouring construction of the pier is completed, the steel formwork at the top of the pier is retained, and a 32 mm Φ precision-rolled threaded steel bar is inserted into the 42 mm Φ PVC pipe, so that the corbel is fixed to the steel formwork at the top of the pier, and is fixed with a three-layer nut.

[0043] In the step (2), each group of brackets is composed of three groups of triangular load-bearing frames and is formed through a tensioning structure. A flat joint is arranged between each group of brackets, and the flat joint is connected by 14b channel steel.

[0044] In the step (3), the main crossbeam is made of double-pieced I50b I-beams and is placed horizontally on a triangular bracket, and a sand cylinder is installed in the middle of the upper part of the main crossbeam; the sand cylinder is cylindrical and has a pull-out plate at the bottom; after the construction of the cap beam is completed, the sand in the sand cylinder can be quickly taken out by pulling out the pull-out plate at the bottom of the sand cylinder, so that the construction components above the sand cylinder are separated from the cap beam, so that these construction components can be dismantled and recycled.

[0045] In the step (4), during installation, multiple Bailey plates are first connected into multiple groups of Bailey beams using 22.5 cm fixed flower racks under the bridge, and then the assembled Bailey beams are hoisted to the main beam positions determined by measurement and layout using a tower crane, and the Bailey beams are fixed to the main beam positions using U-shaped clips; [8 channel steel scissor braces are used in the transverse direction of the bridge, and multiple groups of Bailey beams are connected into a whole using bolts.

[0046] In the step (5), the transverse distribution beam is made of double-pieced I16 I-beams, which are arranged horizontally above the Bailey beam. The spacing between adjacent transverse distribution beams is 0.6m, and the transverse distribution beam is firmly connected to the lower Bailey beam with riding bolts.

[0047] In the step (6), after the installation of the buckle bracket is completed, an adjustable top support is provided to achieve effective adjustment of the elevation of the bottom formwork of the cap beam.

[0048] In the step (7), the sandbag preloading method is used for preloading, and the preloading weight is divided into five levels, namely 55%, 75%, 95%, 105% and 120% of the weight of the cap beam cast concrete.

[0049] In step (9), the first pouring is to 1.75 m above the bottom of the cap beam, and the second pouring is to the designed elevation; before the second pouring, the concrete bonding surface of the first pouring needs to be roughened to allow the two concretes to be combined into a whole.

[0050] After step (10), all construction components used in the above steps are removed in sequence.

[0051] Example 2

[0052] A method for constructing a long-span high pier cap beam comprises the following steps:

[0053] (1) Install the corbels: After the pier column construction is completed, fix the corbels on the pier column;

[0054] (2) Install the bracket: Install the bracket on the corbel and install it symmetrically on both sides of the pier;

[0055] (3) Installation of sand cylinder and main beam: The main beam is placed on a triangular bracket, and a sand cylinder is installed on the upper part of the main beam to facilitate later removal;

[0056] (4) Bailey beam installation: First, assemble the Bailey beam under the bridge, connect it into a whole, then hoist it to the designed position and fix it;

[0057] (5) Installation of transverse distribution beam: Install the transverse distribution beam on top of the Bailey beam and connect the two firmly;

[0058] (6) Installation of the buckle bracket;

[0059] (7) Install the bottom formwork and preload; measure and release the elevation control point, install the bottom formwork of the cap beam, and then preload;

[0060] (8) Installation of steel bars and side formwork;

[0061] (9) Concrete pouring: two pouring methods are adopted;

[0062] (10) Prestressing and grouting operations of the cap beam.

[0063] In the step (1), a 42 mm Φ PVC pipe that passes through the pier is embedded in the steel formwork at the top of the pier according to the designed height, and is used as a tie rod hole after concrete is poured, and a corbel box is embedded at the same time; after the concrete pouring construction of the pier is completed, the steel formwork at the top of the pier is retained, and a 32 mm Φ precision-rolled threaded steel bar is inserted into the 42 mm Φ PVC pipe, so that the corbel is fixed to the steel formwork at the top of the pier, and is fixed with a three-layer nut.

[0064] In the step (2), each group of brackets is composed of three groups of triangular load-bearing frames and is formed through a tensioning structure. A flat joint is arranged between each group of brackets, and the flat joint is connected by 14b channel steel.

[0065] In the step (3), the main crossbeam is made of double-pieced I50b I-beams and is placed horizontally on a triangular bracket, and a sand cylinder is installed in the middle of the upper part of the main crossbeam; the sand cylinder is cylindrical and has a pull-out plate at the bottom; after the construction of the cap beam is completed, the sand in the sand cylinder can be quickly taken out by pulling out the pull-out plate at the bottom of the sand cylinder, so that the construction components above the sand cylinder are separated from the cap beam, so that these construction components can be dismantled and recycled.

[0066] In the step (4), during installation, multiple Bailey plates are first connected into multiple groups of Bailey beams using 22.5 cm fixed flower racks under the bridge, and then the assembled Bailey beams are hoisted to the main beam positions determined by measurement and layout using a tower crane, and the Bailey beams are fixed to the main beam positions using U-shaped clips; [8 channel steel scissor braces are used in the transverse direction of the bridge, and multiple groups of Bailey beams are connected into a whole using bolts.

[0067] In the step (5), the transverse distribution beam is made of double-pieced I16 I-beams, which are arranged horizontally above the Bailey beam. The spacing between adjacent transverse distribution beams is 0.6m, and the transverse distribution beam is firmly connected to the lower Bailey beam with riding bolts.

[0068] In the step (6), after the installation of the buckle bracket is completed, an adjustable top support is provided to achieve effective adjustment of the elevation of the bottom formwork of the cap beam.

[0069] In the step (7), the sandbag preloading method is used for preloading, and the preloading weight is divided into five levels, namely 55%, 75%, 95%, 105% and 120% of the weight of the cap beam cast concrete.

[0070] In step (9), the first pouring is to 1.75 m above the bottom of the cap beam, and the second pouring is to the designed elevation; before the second pouring, the concrete bonding surface of the first pouring needs to be roughened to allow the two concretes to be combined into a whole.

[0071] After step (10), all construction components used in the above steps are removed in sequence.

[0072] In addition, in order to further improve the technical effect of the present invention, in this embodiment, in step (2), the bracket is assembled by double-piece I45a I-beams, and the bracket is provided with a reinforcement plate, using a 20m steel plate. During installation, three pieces of I20b I-beams are installed on the bracket, the bottom of the bracket is located on the I20b I-beam, and a 32mm finely rolled threaded steel bar is passed through the top to anchor the bracket, and fixed with three layers of nuts.

[0073] In step (4), the Bailey beam is composed of a truss steel beam composed of standard 321 type Bailey plates, and each group uses three rows of single-layer Bailey beams.

[0074] In step (6), the buckle bracket is set up in strict accordance with the specific requirements of the "Safety Technical Standard for Socket-type Disc-type Steel Pipe Scaffolding in Construction" (JCJ / T 231-2021). The adjustable top support is set to the designed elevation.

[0075] In step (7), I16 I-beams are laid out on the adjustable top support along the transverse direction of the bridge. After the bottom formwork of the cap beam is installed, the surveying personnel arrange observation points for pre-stressing. Observation points are set at 7 sections along the length of the cap beam, located at both ends of the cap beam, 1 / 4L, 3 / 4L and 1 / 2L respectively. Six observation points are arranged at each section, and they are all set at intervals along the width direction of the cap beam. A monitoring graph of the settlement change over time is drawn. After the pre-stressing is unloaded, the buckle bracket is evaluated and put into use after it is determined to be qualified. In this way, the pre-arch of the bracket can be accurately and quickly determined to ensure that the construction of the cap beam meets the requirements, further ensuring the construction quality and safety.

[0076] The pull-out plate is made of ethylene-tetrafluoroethylene copolymer plate to reduce the friction between the pull-out plate and the sand accumulated in the sand barrel, so that the pull-out plate can be quickly pulled out of the sand barrel easily, thereby forming a sand outlet on the sand barrel to achieve the effect of rapid sand discharge.

[0077] In this embodiment, the corbel is directly fixed to the steel formwork at the top of the pier column during construction, so that it can be used as a formwork for pouring the pier column and a supporting device for pouring the cap beam. After the cap beam is constructed in the later stage, the steel formwork and the corbel are removed together, which can save construction materials and construction period, simplify the traditional construction process, effectively shorten the construction period, save materials and construction space. At the same time, when the corbel is erected, the poured pier column is protected from damage, further ensuring the overall construction quality.

[0078] In the step (1), a structural reinforcement is provided below the connection and fixing place of the 32 mm finely rolled threaded steel bar and the corbel. The structural reinforcement is an I-beam as a whole, and a plurality of parallel stiffening ribs are provided between the upper top plate and the lower bottom plate, and the plurality of stiffening ribs are welded and fixed to the upper top plate, the lower bottom plate and the web plate. One end of the structural reinforcement extends into the steel formwork, and the other end extends out of the steel formwork and supports the corbel. An inverted trapezoidal support plate is provided below the lower bottom plate where the I-beam extends out of the steel formwork, and is welded to the outer surface of the steel formwork.

[0079] By setting up structural reinforcements and using them as stress points for setting up the overall supporting structure, the overall supporting structure is made more solid and stable, the construction intensity is reduced, the construction time is saved, and the construction efficiency is improved.

[0080] Example 3

[0081] A method for constructing a long-span high pier cap beam comprises the following steps:

[0082] (1) Install the corbels: After the pier column construction is completed, fix the corbels on the pier column;

[0083] (2) Install the bracket: Install the bracket on the corbel and install it symmetrically on both sides of the pier;

[0084] (3) Installation of sand cylinder and main beam: The main beam is placed on a triangular bracket, and a sand cylinder is installed on the upper part of the main beam to facilitate later removal;

[0085] (4) Bailey beam installation: First, assemble the Bailey beam under the bridge, connect it into a whole, then hoist it to the designed position and fix it;

[0086] (5) Installation of transverse distribution beam: Install the transverse distribution beam on top of the Bailey beam and connect the two firmly;

[0087] (6) Installation of the buckle bracket;

[0088] (7) Install the bottom formwork and preload; measure and release the elevation control point, install the bottom formwork of the cap beam, and then preload;

[0089] (8) Installation of steel bars and side formwork;

[0090] (9) Concrete pouring: two pouring methods are adopted;

[0091] (10) Prestressing and grouting operations of the cap beam.

[0092] In the step (1), a 42 mm Φ PVC pipe that passes through the pier is embedded in the steel formwork at the top of the pier according to the designed height, and is used as a tie rod hole after concrete is poured, and a corbel box is embedded at the same time; after the concrete pouring construction of the pier is completed, the steel formwork at the top of the pier is retained, and a 32 mm Φ precision-rolled threaded steel bar is inserted into the 42 mm Φ PVC pipe, so that the corbel is fixed to the steel formwork at the top of the pier, and is fixed with a three-layer nut.

[0093] In the step (2), each group of brackets is composed of three groups of triangular load-bearing frames and is formed through a tensioning structure. A flat joint is arranged between each group of brackets, and the flat joint is connected by 14b channel steel.

[0094] In the step (3), the main crossbeam is made of double-pieced I50b I-beams and is placed horizontally on a triangular bracket, and a sand cylinder is installed in the middle of the upper part of the main crossbeam; the sand cylinder is cylindrical and has a pull-out plate at the bottom; after the construction of the cap beam is completed, the sand in the sand cylinder can be quickly taken out by pulling out the pull-out plate at the bottom of the sand cylinder, so that the construction components above the sand cylinder are separated from the cap beam, so that these construction components can be dismantled and recycled.

[0095] In the step (4), during installation, multiple Bailey plates are first connected into multiple groups of Bailey beams using 22.5 cm fixed flower racks under the bridge, and then the assembled Bailey beams are hoisted to the main beam positions determined by measurement and layout using a tower crane, and the Bailey beams are fixed to the main beam positions using U-shaped clips; [8 channel steel scissor braces are used in the transverse direction of the bridge, and multiple groups of Bailey beams are connected into a whole using bolts.

[0096] In the step (5), the transverse distribution beam is made of double-pieced I16 I-beams, which are arranged horizontally above the Bailey beam. The spacing between adjacent transverse distribution beams is 0.6m, and the transverse distribution beam is firmly connected to the lower Bailey beam with riding bolts.

[0097] In the step (6), after the installation of the buckle bracket is completed, an adjustable top support is provided to achieve effective adjustment of the elevation of the bottom formwork of the cap beam.

[0098] In the step (7), the sandbag preloading method is used for preloading, and the preloading weight is divided into five levels, namely 55%, 75%, 95%, 105% and 120% of the weight of the cap beam cast concrete.

[0099] In step (9), the first pouring is to 1.75 m above the bottom of the cap beam, and the second pouring is to the designed elevation; before the second pouring, the concrete bonding surface of the first pouring needs to be roughened to allow the two concretes to be combined into a whole.

[0100] After step (10), all construction components used in the above steps are removed in sequence.

[0101] In addition, in order to further improve the technical effect of the present invention, in the embodiment, in the step (6), an auxiliary reinforcement support column is also provided on the transverse distribution beam and interspersed between the buckle brackets to better improve the support effect. A support seat is provided at the bottom of the auxiliary reinforcement support column, and the support column is inserted into the support seat. A grouting hole is provided on the lower surface of the support column, and an exhaust hole is provided on the opposite side. Grouting is injected into the interior of the support column through the grouting hole, and the exhaust hole is used to discharge excess gas during the pouring process.

[0102] Auxiliary reinforced support columns can enhance the stability of the disc bracket and reduce the vibration caused by pouring concrete on the cap beam, further enhancing the stability of the supporting structure.

[0103] Before construction, the cap beam and its supporting structure are 3D modeled using the building information model to obtain their 3D spatial relationship and load distribution. During the construction process, the 3D supporting structure model of the cap beam is analyzed in real time, the force is checked and calculated in real time, and the corresponding structure is adjusted at any time. Through continuous optimization, the material consumption is reduced and the construction cost is reduced while meeting the safety regulations.

[0104] In order to improve the construction quality and efficiency, after assembling the Bailey beam under the bridge, the transverse distribution beam can be directly arranged above it, and then the Bailey beam arranged with the transverse distribution beam can be hoisted to the main beam position. This makes it easier to construct and control the installation accuracy.

[0105] When installing corresponding components on the pier, the remote-controlled aerial photography equipment and the geographic information system are used in conjunction with each other to conduct real-time detection and control of the installation position and corresponding adjustments, so as to achieve the designed installation requirements and meet the construction needs, while reducing the construction difficulty and improving the construction quality.

[0106] It can be seen from the above embodiments that the present invention is fast, efficient, safe and reliable in construction, can greatly improve construction efficiency and shorten construction period, and can save materials, reduce costs, ensure quality and be economical and practical.

[0107] The present invention realizes the rapid and efficient construction of high-pier and large-span cap beams. The construction method and technology are mature and can ensure the construction quality of the cap beam. The construction personnel can have sufficient working platform space at high altitudes, which can effectively ensure the construction safety and high safety, and at the same time will not affect the passage of vehicles within the construction range of the cap beam.

[0108] The present invention is suitable for the construction of cast-in-place beams with high pier heights and obstructed terrain conditions, and has the advantages of high construction safety factor and short construction period; the support system has a specific geometric system, and the support effect is more firm and stable; at the same time, through the mutual cooperation and coordination of various construction steps, the construction intensity is reduced, the construction time is saved, and the construction efficiency is improved.

[0109] The above is only a preferred embodiment of the present invention, and does not limit the present invention in other forms. Any technician familiar with the profession may use the above disclosed technical content to change or modify it into an equivalent embodiment with equivalent changes. However, any simple modification, equivalent change and modification made to the above embodiment according to the technical essence of the present invention without departing from the technical solution of the present invention still belongs to the protection scope of the technical solution of the present invention.

Claims

1. A construction method for a large-span high pier cap beam. It is characterized in that The following steps are involved: (1) Install the corbels: After the pier column construction is completed, fix the corbels on the pier column; (2) Install the bracket: Install the bracket on the corbel and install it symmetrically on both sides of the pier; (3) Installation of sand cylinder and main beam: The main beam is placed on a triangular bracket, and a sand cylinder is installed on the upper part of the main beam to facilitate later removal; (4) Bailey beam installation: First, assemble the Bailey beam under the bridge, connect it into a whole, then hoist it to the designed position and fix it; (5) Installation of transverse distribution beam: Install the transverse distribution beam on top of the Bailey beam and connect the two firmly; (6) Installation of the buckle bracket; (7) Install the bottom formwork and preload; measure and release the elevation control point, install the bottom formwork of the cap beam, and then preload; (8) Installation of steel bars and side formwork; (9) Concrete pouring: two pouring methods are adopted; (10) Prestressing and grouting operations of the cap beam.

2. The method for constructing a long-span high pier cap beam according to claim 1, It is characterized in that In the step (1), a 42 mm Φ PVC pipe that passes through the pier is embedded in the steel formwork at the top of the pier according to the designed height, and is used as a tie rod hole after concrete is poured, and a corbel box is embedded at the same time; after the concrete pouring construction of the pier is completed, the steel formwork at the top of the pier is retained, and a 32 mm Φ precision-rolled threaded steel bar is inserted into the 42 mm Φ PVC pipe, so that the corbel is fixed to the steel formwork at the top of the pier, and is fixed with a three-layer nut.

3. The method for constructing a long-span high pier cap beam according to claim 1 or 2, It is characterized in that In the step (2), each group of brackets is composed of three groups of triangular load-bearing frames and is formed through a tensioning structure. A flat joint is arranged between each group of brackets, and the flat joint is connected by 14b channel steel.

4. The method for constructing a long-span high pier cap beam according to claim 3, It is characterized in that In the step (3), the main crossbeam is made of double I50b I-beams and is placed horizontally on a triangular bracket, and a sand cylinder is installed in the middle of the upper part of the main crossbeam; the sand cylinder is cylindrical and has a pull-out plate at the bottom.

5. The method for constructing a long-span high pier cap beam according to claim 4, It is characterized in that In the step (4), during installation, multiple Bailey plates are first connected into multiple groups of Bailey beams using 22.5 cm fixed flower racks under the bridge, and then the assembled Bailey beams are hoisted to the main beam positions determined by measurement and layout using a tower crane, and the Bailey beams are fixed to the main beam positions using U-shaped clips; [8 channel steel scissor braces are used in the transverse direction of the bridge, and multiple groups of Bailey beams are connected into a whole using bolts.

6. The method for constructing a long-span high pier cap beam according to claim 4 or 5, It is characterized in that In the step (5), the transverse distribution beam is made of double-pieced I16 I-beams, which are arranged horizontally above the Bailey beam. The spacing between adjacent transverse distribution beams is 0.6m, and the transverse distribution beam is firmly connected to the lower Bailey beam with riding bolts.

7. The method for constructing a long-span high pier cap beam according to claim 6, It is characterized in that In the step (6), an adjustable top support is provided after the installation of the buckle bracket is completed.

8. The method for constructing a long-span high pier cap beam according to claim 7, It is characterized in that In the step (7), the sandbag preloading method is used for preloading, and the preloading weight is divided into five levels, namely 55%, 75%, 95%, 105% and 120% of the weight of the cap beam cast concrete.

9. The method for constructing a long-span high pier cap beam according to claim 7 or 8, It is characterized in that In step (9), the first pouring is to 1.75 m above the bottom of the cap beam, and the second pouring is to the designed elevation; before the second pouring, the concrete bonding surface of the first pouring needs to be roughened to allow the two concretes to be combined into a whole.

10. The method for constructing a long-span high pier cap beam according to claim 9, It is characterized in that After step (10), all construction components used in the above steps are removed in sequence.