Preparation process of asphalt concrete

By setting a rotating roller and a driving plate in the aggregate mechanism, the synchronous opening of multiple switch valves is achieved, which solves the problem of inaccurate ingredients in the prior art, ensures the accuracy of ingredients and saves costs.

CN118880692AInactive Publication Date: 2024-11-01QINHUANGDAO HONGZHENG NEW BUILDING MATERIALS TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411113383.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-11-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When existing aggregate mechanisms need to open multiple switch valves at the same time to achieve a specific batch, due to slight differences in operation, it is difficult to achieve full synchronous opening, resulting in a deviation between the actual ratio and the designed ratio.

Method used

A aggregate mechanism is designed, by setting a rotating roller and driving plate in the main aggregate box and the secondary aggregate box, and the hoppers of multiple secondary aggregate boxes are rotated by power transmission, thereby achieving synchronous opening of multiple switch valves. , avoid operational errors.

Benefits of technology

The synchronous opening of multiple switch valves is achieved, ensuring the accuracy and consistency of ingredients. The batching operation is completed with only one switch valve, which greatly saves costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880692A_ABST
    Figure CN118880692A_ABST
Patent Text Reader

Abstract

The invention relates to a preparation process of asphalt concrete, which comprises the following steps: S1, proportioning coarse aggregate, fine aggregate, mineral powder, limestone powder, cement and pulverized coal in proportion through an aggregate mechanism, and stirring and mixing the coarse aggregate, the fine aggregate, the mineral powder, the limestone powder, the cement and the pulverized coal through a first stirrer to obtain a mixture; s2, drying the mixture through a drying roller at 170-180 DEG C to obtain a dry material; s3, the asphalt is heated to 140 DEG C to 160 DEG C; and S4, adding the heated asphalt into the dry material, and stirring and mixing through a second stirrer to obtain the asphalt concrete. Through the arrangement of the material collecting mechanism, the problem that when a plurality of switch valves of an existing material collecting mechanism need to be opened at the same time to achieve specific burdening, complete synchronous opening is difficult to achieve due to small difference in operation is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of asphalt concrete, and in particular to a preparation process of asphalt concrete. Background Art

[0002] Asphalt concrete is a pavement material made from a mixture of minerals and asphalt, and is widely used in the paving of roads such as highways, urban roads, and airport runways. Asphalt concrete has become an indispensable material in modern road engineering due to its good waterproof properties, smooth appearance, and moderate elasticity. Among them, the batching and supply of aggregates are important links in ensuring the quality of asphalt concrete. The existing aggregate mechanism is set up through multiple aggregate drums, and switch valves are set on multiple aggregate drums to achieve aggregate batching and leakage. However, when it is necessary to open multiple switch valves at the same time to achieve a specific batching, it is difficult to achieve completely synchronized opening due to slight differences in operation, which will lead to deviations between the actual ratio and the designed ratio. Summary of the Invention

[0003] The main purpose of the present invention is to provide a preparation process for asphalt concrete to solve the problem that when the existing aggregate mechanism needs to open multiple switch valves at the same time to achieve a specific ratio, it is difficult to achieve complete synchronous opening due to slight differences in operation, which will lead to deviations between the actual ratio and the designed ratio.

[0004] In order to achieve the above object, the present invention provides a process for preparing asphalt concrete, comprising the following steps: S1, coarse aggregate, fine aggregate, mineral powder, limestone powder, cement and pulverized coal are mixed in proportion by a gathering mechanism, and the mixed coarse aggregate, fine aggregate, mineral powder, limestone powder, cement and pulverized coal are mixed by a first mixer to obtain a mixture; S2. The mixed material is dried at 170-180°C through a drying drum to obtain a dry material; S3. Heat the asphalt to 140-160°C; S4, adding the heated asphalt to the dry material and stirring and mixing in a second mixer to obtain asphalt concrete; The material collection mechanism includes a frame, a main material collection box and multiple auxiliary material collection boxes; The main aggregate box and multiple auxiliary aggregate boxes are fixedly arranged side by side on the frame; The bottom of the main aggregate box has a first rectangular tube arranged vertically, and the bottoms of the plurality of auxiliary aggregate boxes each have a second rectangular tube arranged vertically; A switch valve is provided at the discharge port of the first rectangular tube, and two L-shaped plates are fixedly provided on one side of the first rectangular tube. A first rotating shaft is rotatably provided at one end of the two L-shaped plates away from the first rectangular tube, and a first spur gear is fixedly sleeved on one end of the first rotating shaft. A plurality of driving plates are arranged on the circumference of the first rotating shaft, and the driving plates rotate to form a rotating drum, and part of the structure of the rotating drum is located directly below the discharge port of the first rectangular tube; A second rotating shaft is rotatably provided on the second rectangular tube, and both ends of the second rotating shaft pass through the second rectangular tube and are fixedly sleeved with a second spur gear. A plurality of hoppers are arranged circumferentially on the second rotating shaft, and the plurality of hoppers are located in the second rectangular tube; A first chain is sleeved between the first spur gear and an adjacent second spur gear, and a second chain is sleeved between another second spur gear located on the same second rotating shaft as the next second spur gear and the next adjacent second spur gear; The second rotating shaft is in a stationary state, and the multiple hoppers on the second rotating shaft rotate so that the material cannot leak out of the auxiliary collecting box; The second rotating shaft is in a rotating state, and the multiple hoppers on the second rotating shaft rotate, causing the materials to leak out from the auxiliary collecting box.

[0005] A preferred solution is that the material collecting mechanism further includes a conveyor belt, and the horizontally arranged conveyor belt is located directly below the first rectangular tube and the plurality of second rectangular tubes.

[0006] A preferred solution is that the switch valve includes a shielding plate and a cylinder, the first rectangular tube is provided with an L-shaped plate and a through groove is opened on the opposite side wall, the horizontally arranged shielding plate is slidably set on the through groove, the cylinder seat of the cylinder is fixedly connected to the side wall of the first rectangular tube, and the piston rod is fixedly connected to one end of the shielding plate, and the other end of the shielding plate can be abutted against the side wall of the first rectangular tube provided with the L-shaped plate.

[0007] A preferred solution is that the hoppers of the multiple auxiliary aggregate boxes have different material holding volumes.

[0008] A preferred solution is that pulse tanks are provided on the side walls of the main aggregate box and the multiple auxiliary aggregate boxes, and each pulse tank is connected to multiple air pipes, which respectively penetrate into the main aggregate box or the auxiliary aggregate box.

[0009] A preferred solution is that screen plates are horizontally arranged in the main aggregate box and the multiple auxiliary aggregate boxes.

[0010] The beneficial effects of the above scheme are: The coarse aggregate is stored in the main aggregate box, and the remaining fine aggregate, mineral powder, limestone powder, cement and pulverized coal are stored in the auxiliary aggregate box respectively. When the mixture needs to be batched, the switch valve is driven to open. After the switch valve is opened, the coarse aggregate flows out of the first rectangular tube. In the process of the coarse aggregate flowing out of the first rectangular tube, the flow of the coarse aggregate drives the multiple driving plates on the first rotating shaft to start rotating. The power transmission of the first rotating shaft causes the first spur gear to start rotating. The first spur gear drives the second spur gear adjacent to the first spur gear to rotate through the first chain. The second spur gear drives multiple hoppers to rotate through the second rotating shaft above it. The rotation process of multiple hoppers completes the material leakage. Further, a second spur gear and an adjacent second spur gear are sleeved with a second chain so that power is transmitted to the next second spur gear to rotate. The above action is repeated, so that multiple auxiliary aggregate boxes leak out to complete the material leakage action. This structural setting avoids the problem that the existing aggregate mechanism needs to open multiple switch valves at the same time to achieve specific batching. Due to slight differences in operation, it is difficult to achieve completely synchronous opening. The present invention also has the beneficial effect of requiring only one on / off valve, significantly saving costs. Furthermore, the coarse aggregate, fine aggregate, mineral powder, limestone powder, cement, and pulverized coal, after batching, are stirred and mixed in a first mixer according to the prior art to produce a mixture; the mixture is then dried in a drying drum at 170-180°C to produce a dry material; the asphalt is heated to 140-160°C; the heated asphalt is added to the dry material and stirred and mixed in a second mixer according to the prior art to produce asphalt concrete. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0012] Figure 1 It is a schematic diagram of the three-dimensional structure of the material collecting mechanism of the present invention; Figure 2 This is a schematic diagram of the three-dimensional structure of the material collecting mechanism of the present invention from another perspective; Figure 3 yes Figure 2 A magnified schematic diagram of area A in the middle; Figure 4 It is a schematic diagram of the three-dimensional structure of the material collecting mechanism of the present invention; Figure 5 A schematic diagram of the three-dimensional structure of the material collecting mechanism of the present invention in a cross-sectional state; Figure 6 It is a partial three-dimensional structural schematic diagram of the material collecting mechanism of the present invention.

[0013] Description of Reference Numerals 1. Aggregation mechanism; 2. Frame; 3. Main aggregate box; 31. First rectangular tube; 32. First rotating shaft; 33. First spur gear; 34. Driving plate; 4. Auxiliary aggregate box; 41. Second rectangular tube; 42. Second rotating shaft; 43. Second spur gear; 44. Hopper; 5. First chain; 6. Second chain; 7. Conveyor belt; 8. Switch valve; 81. Shielding plate; 82. Cylinder; 9. Pulse tank; 91. Air pipe; 100. L-shaped plate; 10. Sieve plate; 310. Through groove. DETAILED DESCRIPTION

[0014] The following is a clear and complete description of the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings in the embodiments of the present invention. In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can also be implemented in other ways different from those described herein, and those skilled in the art can make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below. Example:

[0015] like Figure 1-Figure 5 As shown, this embodiment provides a preparation process of asphalt concrete, comprising the following steps: S1, coarse aggregate, fine aggregate, mineral powder, limestone powder, cement and pulverized coal are mixed in proportion by the aggregate collecting mechanism 1, and the coarse aggregate, fine aggregate, mineral powder, limestone powder, cement and pulverized coal are mixed by the first mixer to obtain a mixture; S2. The mixed material is dried at 170-180°C through a drying drum to obtain a dry material; S3. Heat the asphalt to 140-160°C; S4, the heated asphalt is added to the dry material and stirred and mixed by the second mixer to obtain asphalt concrete. Wherein, the first mixer, the second mixer and the drying drum are all based on existing technology, so they are not described in detail.

[0016] The material collecting mechanism 1 includes a frame 2 , a main material collecting box 3 and a plurality of auxiliary material collecting boxes 4 .

[0017] like Figure 1 、 Figure 2 As shown, a single main aggregate box 3 and multiple auxiliary aggregate boxes 4 are fixedly arranged side by side on the frame 2. Figure 5 As shown, sieve plates 10 are horizontally installed in the main aggregate bin 3 and multiple auxiliary aggregate bins 4. These screens 10 filter out coarse aggregate, fine aggregate, mineral powder, limestone powder, cement, and larger impurities such as pulverized coal. The bottom of the main aggregate bin 3 features a vertically mounted first rectangular tube 31, with two L-shaped plates 100 fixed to one side of the tube. Each of the multiple auxiliary aggregate bins 4 features a vertically mounted second rectangular tube 41 at its bottom.

[0018] The discharge port of the first rectangular tube 31 is provided with a switch valve 8, which includes a shielding plate 81 and a cylinder 82. A through slot 310 is provided on the side wall of the first rectangular tube 31, and the horizontally arranged shielding plate 81 is slidably arranged on the through slot 310. The cylinder seat of the cylinder 82 is fixedly connected to the side wall of the first rectangular tube 31, and the piston rod of the cylinder 82 is fixedly connected to one end of the shielding plate 81. The other end of the shielding plate 81 can abut against the side wall of the first rectangular tube 31 provided with an L-shaped plate. To further explain, when one end of the shielding plate 81 abuts against the side wall of the first rectangular tube 31 provided with an L-shaped plate, the shielding plate 81 shields the discharge port of the first rectangular tube 31. When coarse aggregate needs to be unloaded, the piston rod of the cylinder 82 is driven to extend, and the piston rod of the cylinder 82 drives the shielding plate 81 to slide slowly, so that the discharge port of the first rectangular tube 31 slowly opens.

[0019] like Figures 1-6 As shown, two L-shaped plates 100 are rotatably mounted on one end of the first rectangular tube 31, and a first spur gear 33 is fixedly mounted on one end of the horizontally arranged first rotating shaft 32. A plurality of driving plates 34 are arranged circumferentially on the first rotating shaft 32, and the driving plates 34 rotate to form a rotating drum (not shown). Part of the rotating drum is located directly below the discharge port of the first rectangular tube 31, as shown in FIG. Figure 3 shown.

[0020] A second rotating shaft 42 is rotatably mounted on the second rectangular tube 41. Both ends of the horizontally mounted second rotating shaft 42 extend beyond the second rectangular tube 41 and are fixedly mounted with second spur gears 43. Multiple hoppers 44 are circumferentially arranged on the second rotating shaft 42 and located within the second rectangular tube 41. A first chain 5 is mounted between the first spur gear 33 and an adjacent second spur gear 43. Another second spur gear 43 located on the same second rotating shaft 42 as the second spur gear 43 is mounted between the next adjacent second spur gear 43 and a second chain 6 is mounted between the first chain 5 and the multiple second chains 6 located on the front and rear sides of the primary and secondary aggregate boxes 3 and 4, respectively. (That is, the first chain 5 and the multiple second chains 6 located on the front and rear sides of the primary and secondary aggregate boxes 3 and 4 are staggered and connected end to end along their lengths.)

[0021] The second rotating shaft 42 is in a stationary state, and the multiple hoppers 44 on the second rotating shaft 42 rotate, so that the material cannot leak out of the auxiliary aggregate box 4, that is, the multiple hoppers completely cover the discharge port of the second rectangular tube 41. When the second rotating shaft 42 is in a rotating state, the multiple hoppers 44 on the second rotating shaft 42 rotate, so that the material leaks out of the auxiliary aggregate box 4.

[0022] The coarse aggregate is stored in the main aggregate box 3, and the remaining fine aggregate, mineral powder, limestone powder, cement and pulverized coal are stored in the auxiliary aggregate box 4 respectively. When the mixture needs to be batched, the piston rod of the cylinder 82 drives the shielding plate 81 to slide slowly, so that the discharge port of the first rectangular tube 31 is slowly opened, and the coarse aggregate flows out of the first rectangular tube 31. It is further explained that part of the structure of the rotating drum coincides with the position directly below the discharge port of the first rectangular tube 31, and is located at the place where the discharge port of the first rectangular tube 31 is first opened. That is to say, if the shielding plate 81 is opened to open only a small part of the discharge port, the coarse aggregate that leaks out can directly hit the driving drum. The plate 34 is on the driving plate 34, and since only one side of the driving plate 34 is directly below the first rectangular tube 31, the coarse aggregate only hits and drives the driving plate 34 on one side to rotate during the falling process. In this way, the coarse aggregate can continuously drive the driving plate 34 directly below the first rectangular tube 31 to rotate during the falling process, continuously providing power to the first rotating shaft 32 and the first spur gear 33 to rotate in the same direction. In other words, the present invention only locates part of the structure of the rotating drum directly below the discharge port of the first rectangular tube 31, avoiding the coarse aggregate indiscriminately hitting all the driving plates 34, resulting in unstable rotation direction of the rotating drum. In the process of the coarse aggregate flowing out of the first rectangular tube 31, the flow of the coarse aggregate hits the driving plate 34, and the driving plate 34 drives the first spur gear 33 to rotate counterclockwise through the first rotating shaft 32. The first spur gear 33 drives the second spur gear 43 adjacent to the first spur gear 33 to rotate through the first chain 5, as shown in FIG. Figure 5 、 Figure 6 As shown, the second spur gear 43 drives the hopper 44 above to rotate, and the multiple hoppers 44 complete the material leakage during the rotation process. Further, a second spur gear 43 and an adjacent second spur gear 43 are sleeved with a second chain 6, so that the power is transmitted to the next second spur gear 43 to rotate, and the above action is repeated, so that multiple auxiliary collection boxes 4 leak out and complete the material leakage action. This structural setting avoids the problem of the existing collection mechanism 1 needing to open multiple switch valves 8 at the same time to achieve a specific ratio. Due to slight differences in operation, it is difficult to achieve complete synchronous opening. In addition, the present invention has the beneficial effect that the collection mechanism 1 only requires one switch valve 8, which greatly saves costs.

[0023] like Figure 1 As shown, the collecting mechanism 1 further comprises a conveyor belt 7, and the horizontally arranged conveyor belt 7 is located directly below the first rectangular tube 31 and the plurality of second rectangular tubes 41. The conveying tail end of the conveyor belt 7 is arranged at the feeding port of the first mixer to facilitate feeding.

[0024] like Figure 6As shown, the hoppers 44 of the multiple auxiliary aggregate boxes 4 have different material storage volumes. The proportions of coarse aggregate, fine aggregate, mineral powder, limestone powder, cement, and pulverized coal vary, so the different material storage volumes can achieve the desired proportions. Furthermore, the second spur gear 43 and the first spur gear 33 have the same diameter, and the first rotating shaft 32 and the multiple second rotating shafts 42 rotate at the same speed.

[0025] like Figure 5 As shown, pulse tanks 9 are installed on the side walls of the main aggregate bin 3 and the multiple auxiliary aggregate bins 4. Each pulse tank 9 is connected to multiple air pipes 91, which extend into the main aggregate bin 3 or the auxiliary aggregate bin 4. When material discharge from the main aggregate bin 3 or the multiple auxiliary aggregate bins 4 is blocked, the pulse tanks 9 are activated, and compressed gas from the pulse tanks 9 is instantly released through the air pipes 91. This instantaneous release of gas pushes the material inside the main aggregate bin 3 or the auxiliary aggregate bin 4, smoothing material discharge. The pulse tanks 9 utilize existing technology, so detailed description is omitted.

[0026] Obviously, the embodiments described are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

Claims

1. A process for preparing asphalt concrete, characterized in that: The following steps are involved: S1, coarse aggregate, fine aggregate, mineral powder, limestone powder, cement and pulverized coal are proportioned by a gathering mechanism, and the coarse aggregate, fine aggregate, mineral powder, limestone powder, cement and pulverized coal are stirred and mixed by a first mixer to obtain a mixture; S2, the mixed material is dried at 170-180° C. by a drying drum to obtain a dry material; S3, heating the asphalt to 140-160°C; S4, adding the heated asphalt to the dry material and mixing them by a second mixer to obtain asphalt concrete; The material collection mechanism comprises a frame, a main material collection box and a plurality of auxiliary material collection boxes; The main material collection box and the plurality of auxiliary material collection boxes are fixedly arranged side by side in sequence on the frame; The bottom of the main material collecting box has a first rectangular tube arranged vertically, and the bottoms of the plurality of auxiliary material collecting boxes all have a second rectangular tube arranged vertically; A switch valve is provided at the discharge port of the first rectangular tube, and two L-shaped plates are fixedly provided on one side of the first rectangular tube, a first rotating shaft is rotatably provided at one end of the two L-shaped plates away from the first rectangular tube, and a first spur gear is fixedly sleeved on one end of the first rotating shaft; A plurality of driving plates are arranged on the circumference of the first rotating shaft, and the driving plates rotate to form a rotating drum, and a part of the structure of the rotating drum is located directly below the discharge port of the first rectangular tube; A second rotating shaft is rotatably arranged on the second rectangular tube, both ends of the second rotating shaft pass through the second rectangular tube and are fixedly sleeved with second spur gears, a plurality of hoppers are arranged circumferentially on the second rotating shaft, and the plurality of hoppers are located in the second rectangular tube; The first spur gear and an adjacent second spur gear are sleeved with a first chain, and another second spur gear located on the same second rotating shaft as the next second spur gear and an adjacent next second spur gear are sleeved with a second chain; Wherein, the second rotating shaft is in a stationary state, and the plurality of hoppers on the second rotating shaft rotate so that the material cannot leak out of the auxiliary collecting box; The second rotating shaft is in a rotating state, and the multiple hoppers on the second rotating shaft rotate, so that the materials leak out from the auxiliary collecting box.

2. The process for preparing asphalt concrete according to claim 1, characterized in that: The material collecting mechanism also includes a conveyor belt, and the horizontally arranged conveyor belt is located directly below the first rectangular tube and the plurality of second rectangular tubes.

3. The process for preparing asphalt concrete according to claim 1, characterized in that: The switch valve includes a shielding plate and a cylinder. The first rectangular tube is provided with an L-shaped plate and a through groove is opened on the opposite side wall. The horizontally arranged shielding plate is slidably arranged on the through groove. The cylinder seat of the cylinder is fixedly connected to the side wall of the first rectangular tube, and the piston rod is fixedly connected to one end of the shielding plate. The other end of the shielding plate can be abutted against the side wall of the first rectangular tube provided with the L-shaped plate.

4. The process for preparing asphalt concrete according to claim 1, characterized in that: The material storage volumes of the hoppers of the multiple auxiliary aggregate boxes are different.

5. The process for preparing asphalt concrete according to any one of claims 1 to 4, characterized in that: Pulse tanks are arranged on the side walls of the main aggregate box and the plurality of auxiliary aggregate boxes, and each of the pulse tanks is connected with a plurality of air pipes, which respectively penetrate into the main aggregate box or the auxiliary aggregate box.

6. The process for preparing asphalt concrete according to any one of claims 1 to 4, characterized in that: Screen plates are horizontally arranged in the main aggregate box and the plurality of auxiliary aggregate boxes.