By adopting clustered steel pipe pile units in the high-level material source area of ​​the geological disaster chain, combining the structure of fully buried large-bore diameter and locally reamed steel pipe piles, a plum blossom-like layout is formed, and the grouting liquid is used to enhance soil strength, which solves the existing solution Technology cannot prevent the problem of erosion and shoveling, achieves the effect of solid source and anti-erosion, and improves the stability and corrosion resistance of construction.

CN118880810BActive Publication Date: 2024-11-22INST OF EXPLORATION TECH OF CHINESE ACAD OF GEOLOGICAL SCI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411345680.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-26
Publication Date
2024-11-22
Estimated Expiration
2044-09-26

AI Technical Summary

Technical Problem

When preventing and controlling high-level material sources of geological disaster chains, the prior art cannot effectively prevent the erosion of channels and slopes, and cannot play a role in solid source and anti-swage, resulting in an increase in the scale of the disaster body.

Method used

Cluster steel pipe pile units are adopted, including fully buried large-bore steel pipe piles and fully buried partially reamed steel pipe piles. They are connected by connecting rods to form a plum blossom-like structure. The soil strength is enhanced by poured concrete grouting liquid, combined with resistance The pulling force and the overall stiffness of the connecting rod achieve the solid source effect.

Benefits of technology

It effectively prevents soil from eroding and scraping the channel and slope, improves the stability of the material source and erosion resistance, avoids the increase in the scale of disasters, and solves the problem of inconvenience in construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880810B_ABST
    Figure CN118880810B_ABST
Patent Text Reader

Abstract

The present invention provides a high-level material source consolidation device, installation method and application based on a geological disaster chain. The device includes a cluster steel pipe pile unit, wherein one cluster steel pipe pile unit includes 3 fully buried large-aperture steel pipe piles, a plurality of fully buried partially expanded-aperture steel pipe piles and a connecting rod; in a key section of the geological disaster chain, a plurality of cluster steel pipe pile units are arranged, 3 fully buried large-aperture steel pipe piles are used as vertices of three angles, any two fully buried large-aperture steel pipe piles are connected by a connecting rod, 3-4 fully buried partially expanded-aperture steel pipe piles are arranged at equal intervals between adjacent fully buried large-aperture steel pipe piles, and 3-6 fully buried partially expanded-aperture steel pipe piles are arranged within the triangular area surrounded by the three connecting rods. The present invention has the characteristics of standardized construction, mechanized construction and ecological process, solves the problem of high-level material source consolidation broken chain of the existing geological disaster chain, and provides a new method for the prevention and control of geological disaster chains in high mountain areas.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of geological disaster prevention and water conservancy engineering, and in particular to a high-level material source consolidation device based on a geological disaster chain, an installation method and an application. Background Art

[0002] In recent years, extreme weather has become more and more frequent, and large-scale geological disasters represented by geological disaster chains have occurred frequently in mountainous areas, bringing new challenges to geological disaster prevention, and the disaster prevention situation has become increasingly severe. There are many deficiencies in the existing technology for the high-level source chain of geological disaster chains. For example, affected by the cascade amplification effect of the geological disaster chain, large-volume disaster bodies often use oversized retaining structures, which are extremely inconvenient to construct in high-altitude and cold mountainous areas; in the control of debris flows, cantilever pile forest dams are often selected. This structure can only play a blocking role and has a relatively single function; landslides are often treated with anti-slip piles. The cross-section of the anti-slip piles is a uniform diameter, which can effectively prevent the movement of the soil above the slope, but it is difficult to prevent scouring and scraping. Therefore, solving the problem of the high-level source chain of geological disaster chains is a key issue in the current prevention and control of geological disaster chains.

[0003] As mentioned above, the application of pile group technology in geological disaster prevention is relatively common. According to the burial situation, it is divided into cantilever piles, buried piles and buried piles, etc., and according to the construction method, it is divided into bored piles (square piles) and bored piles (round piles), etc. The existing technology often uses uniform diameter anti-slide pile technology to stabilize the slope soil in landslides, and uses uniform diameter cantilever pile forest dams to stabilize the debris flow channel. Although the above method can intercept sediment, peak flow control, and play a similar interception function to the upstream material as the sand dam and the valley dam, it cannot play a role in consolidating the channel bed and preventing the channel from scouring and cutting.

[0004] In summary, the existing conventional pile group technology cannot stabilize the soil on the upper part of the slope and upstream of the ditch during landslides, debris flows and geological disaster chains, cannot play the role of source consolidation, cannot prevent the moving soil from scouring and cutting the ditch and slope, and cannot achieve the effect of anti-scouring and scraping. Summary of the invention

[0005] The purpose of the present invention is to solve the defects of the above-mentioned prior art and provide a high-level material source consolidation device, installation method and application based on the geological disaster chain. The consolidation method based on the cluster root consolidation effect prevents the scouring and scraping of the channel and slope during the transportation of the upstream soil, prevents the increase of the material source scale, and makes up for the technical deficiencies of the existing geological disaster chain and other geological disasters in consolidation and anti-scouring and scraping.

[0006] The present invention adopts the following technical solution:

[0007] Based on the high-level material source consolidation device of the geological disaster chain, it includes cluster steel pipe pile units, wherein one cluster steel pipe pile unit includes 3 fully buried large-diameter steel pipe piles, several fully buried partially expanded-hole steel pipe piles and connecting rods. The 3 fully buried large-diameter steel pipe piles are the vertices of the three angles, any two fully buried large-diameter steel pipe piles are connected by connecting rods, 3-4 fully buried partially expanded-hole steel pipe piles are arranged at equal intervals between adjacent fully buried large-diameter steel pipe piles, and 3-6 fully buried partially expanded-hole steel pipe piles are arranged within the triangular area surrounded by the three connecting rods;

[0008] Among them, the fully buried large-diameter steel pipe piles and the fully buried partially expanded-hole steel pipe piles are both steel-concrete composite structure piles poured with concrete. The top surface of the fully buried large-diameter steel pipe piles is flush with the ground, and a pile cap made of concrete material or steel prefabricated material with a regular hexagonal cross-section is installed on the top of the pile. The pile cap is used to fix the connecting rod, which is an anchor rod, and the end of the connecting rod is fixed to the upper surface of the pile cap by bolts.

[0009] The expansion sections of two adjacent fully buried partially expanded steel pipe piles are arranged in a staggered manner (i.e., two adjacent fully buried partially expanded steel pipe piles are expanded at different buried depths to form a staggered expansion layout). Unevenly distributed circular holes are opened on the fully buried large-diameter steel pipe piles and the fully buried partially expanded steel pipe piles. When the grouting liquid penetrates into the space between the outside of the fully buried large-diameter steel pipe piles and the fully buried partially expanded steel pipe piles and the hole wall, the concrete grouting liquid will diffuse to the surroundings to increase the radius of influence of the grouting liquid, thereby improving the strength of the soil.

[0010] Furthermore, in the one cluster steel pipe pile unit, the combined shape of the fully buried large-diameter steel pipe piles and the fully buried partially expanded-hole steel pipe piles is a plum blossom shape.

[0011] Furthermore, the following formula is used to calculate the pull-out resistance of the fully buried large-diameter steel pipe pile or the fully buried partially enlarged-hole steel pipe pile: Where: -Pull-out force, kPa;

[0012] η-pile group effect coefficient, dimensionless;

[0013] n – number of piles;

[0014] -Pull-out strength, kPa;

[0015] The pile group effect coefficient η adopts the following formula: Where: -interaction coefficient of piles; -Pile top constraint effect coefficient. When calculating fully buried large-diameter steel pipe piles, the constraint effect of the pile cap and pile top needs to be considered. When the pile cap height is less than 300mm, take 2.05; when the pile cap height is 300-500mm, take 2.15; when the pile cap height is greater than 500mm, take 2.3; when calculating fully buried partially enlarged steel pipe piles, the constraint effect of the pile cap and pile top does not need to be considered. Take 1;

[0016]

[0017] in, - Pile spacing, - pile diameter, - Pile spacing diameter ratio, when checking fully buried large-diameter steel pipe piles, Value , Value ,in Indicates the spacing between adjacent fully buried large-diameter steel pipe piles. Indicates the diameter of fully buried large-diameter steel pipe piles; when accepting fully buried partially enlarged steel pipe piles, Value , Value ,in Indicates the spacing between adjacent fully buried partially expanded steel pipe piles. Indicates the diameter of fully buried partially expanded steel pipe piles; - Number of rows of steel pipe piles parallel to the force direction; -The number of columns of steel pipe piles perpendicular to the force direction;

[0018] The pull-out resistance Use the following formula:

[0019] Where: - horizontal deformation coefficient of pile, , is the horizontal resistance coefficient of the pile side, which is determined according to the Technical Specifications for Building Pile Foundations (JGJ94-2008) according to different rock and soil types. is the calculated width of the pile. When D is less than 1m, Calculation: When calculating the width of fully buried large-diameter steel pipe piles, Value , is the diameter of the fully buried large-diameter steel pipe pile. When calculating the width of the fully buried partially expanded steel pipe pile, Value , It is the diameter between fully buried partially expanded steel pipe piles; is the elastic modulus of the pile; is the cross-sectional inertia moment of the pile, and the piles are all steel pipe round piles. , when calculating the section inertia moment of fully buried large-diameter steel pipe piles, Value , is the diameter of the fully buried large-diameter steel pipe pile. When calculating the section inertia moment of the fully buried partially expanded steel pipe pile, Value , is the diameter between fully buried partially expanded steel pipe piles; - The horizontal displacement allowed at the top of the pile is 1%-3% of the pile length; -The horizontal displacement coefficient of the pile top is 0.6-1.05.

[0020] Furthermore, the spacing between adjacent fully buried large-diameter steel pipe piles Determined by the pull-out force, the diameter of the fully buried large-diameter steel pipe pile is 8-12 times the spacing between adjacent fully buried partially expanded steel pipe piles The diameter of the fully buried partially expanded steel pipe pile Compare, / The value range is 6-10.

[0021] Furthermore, the diameter of the fully buried large-diameter steel pipe pile Determined according to the pull-out force, the value range is 100-200mm. When the pull-out force cannot be shared by increasing the number of fully buried large-diameter steel pipe piles, consider a pile diameter of 200-300mm.

[0022] Furthermore, the length L of the fully buried large-diameter steel pipe pile is set and adjusted according to the pull-out force required, and the aspect ratio (ratio of length to pile diameter) L / The value range is 75-100.

[0023] Furthermore, the diameter of the fully buried large-diameter steel pipe pile is The diameter of the fully buried partially expanded steel pipe pile The relationship is: Greater than or equal to 2 .

[0024] Furthermore, the fully buried partially expanded steel pipe piles are configured with expanded sections in staggered sections according to the needs of the reinforcement object. The diameter of the expanded section is 2 , It is the diameter of the fully buried partially expanded steel pipe pile.

[0025] Note: The reinforcement object refers to the slope or channel in the high-level source area of ​​the geological disaster chain.

[0026] Furthermore, the length l of the fully buried partially expanded steel pipe pile is 75%-80% of the length L of the fully buried large-diameter steel pipe pile, and the aspect ratio l / The value range is: 120-150.

[0027] A method for installing a high-level material source solidification device based on a geological disaster chain: first, determine the location of a key section of the geological disaster chain based on an on-site investigation, then use a drilling rig to pre-drill holes, then insert corresponding steel pipes, and then pour mortar into the steel pipes. Fully buried large-diameter steel pipe piles and fully buried partially expanded steel pipe piles have uneven circular holes on their pipes, and grouting liquid penetrates between the outside of the pipe and the hole wall through the uneven circular holes. Then, install the pile cap of the fully buried large-diameter steel pipe pile, and finally install the connecting rod.

[0028] When the pile cap of the fully buried large-diameter steel pipe pile is made of steel prefabricated material, a center hole corresponding to the steel pipe of the fully buried large-diameter steel pipe pile is reserved during center cutting of the steel prefabricated part, and the pile cap is put on the pile top of the fully buried large-diameter steel pipe pile.

[0029] When the pile cap of the fully buried large-diameter steel pipe pile is made of concrete, a certain depth is directly reserved on the top of the fully buried large-diameter steel pipe pile for setting up the formwork and then pouring the concrete.

[0030] A method for using a high-level material source consolidation device based on a geological disaster chain is to arrange a number of clustered steel pipe pile units in key sections of the geological disaster chain, such as areas with severe slope scouring, sections with severe channel undercutting, or cascade amplification areas of geological disaster chain materials. When two clustered steel pipe pile units are arranged relative to each other, the two adjacent clustered steel pipe pile units share nodes and edges, that is, the first clustered steel pipe pile unit is forward, and the second clustered steel pipe pile unit is reversed 180°. Multiple clustered steel pipe pile units are arranged in the above manner, and so on.

[0031] Beneficial effects of the present invention:

[0032] The present invention adopts a high-level material source consolidation device based on the geological disaster chain to consolidate the soil on the upper part of the slope and the upstream of the ditch, so as to prevent the moving soil in the geological disaster source area from scouring and scraping the slope or the ditch, effectively avoiding the cutting of the slope or the ditch and increasing the scale of the disaster body.

[0033] Among them, the fully buried partially expanded steel pipe pile is used as the backbone component. Grouting is mainly injected into the fully buried partially expanded steel pipe pile. The slurry penetrates into the expanded hole section and the soil outside the pipe through the unevenly distributed circular holes on the fully buried partially expanded steel pipe (steel flower pipe) pile, so as to achieve the purpose of strengthening the soil strength and improving the stability of the source. On this basis, the fully buried large-diameter steel pipe pile is used as a core component to prevent the scouring, scraping and cutting of the soil. The two work together as a whole, using the pull-out resistance of the pile group and the overall stiffness formed by the connecting rod to improve the stability and anti-erosion ability of the loose source, realize the cluster rooting effect of the pile group, and avoid the increase in the scale of geological disasters caused by the cutting of channels or slopes.

[0034] Since the single pile structure of the pile group is a fully buried bored cast-in-place pile, the construction is mainly mechanical operation, which can better avoid disturbance to the ditch or slope terrain and environment, and at the same time can well solve the problem of inconvenient construction of high-altitude material sources in the geological disaster chain in mountainous areas. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a partial plan view of the components of the source solidification method of the present invention.

[0036] Figure 2 It is a schematic elevation view of the source solidification method of the present invention.

[0037] Figure 3 It is a plan view schematic diagram of the connection between the connecting rod and the pile cap of the present invention.

[0038] Figure 4 It is a schematic elevation diagram of the connection between the connecting rod and the pile cap of the present invention.

[0039] In the figure: 1-fully buried large-diameter steel pipe pile, 2-fully buried partially expanded steel pipe pile, 3-pile cap, 4-connecting rod, 5-expanded section, 6-bolt. DETAILED DESCRIPTION

[0040] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention is described clearly and completely below. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] The design method of the invention is mature, the calculation is simple, and the construction is mainly mechanized. It has high practical value and economic value for the geological disaster chain with poor traffic conditions in mountainous areas, difficult construction of high-level material sources, and increased material sources caused by gully scouring, scraping, and cutting. It can be widely used in the management of geological disaster chains with severe gully erosion in various mountainous areas, and solves the problem of solid source breaking of high-level material sources in the geological disaster chain.

[0042] Example:

[0043] Taking the debris flow disaster management in Zhibaigou as an example, anti-scouring and scraping management was implemented in the ditch.

[0044] The Qinghai-Tibet Plateau is affected by key driving forces such as climate warming and earthquakes, and debris flows and geological disaster chains are extremely active, such as Zhibaigou, Sedongpu, Peilonggou, Guxianggou, etc. Zhibaigou is located in Milin County, Nyingchi City. It is a first-level tributary on the right bank of the Yarlung Zangbo River with a basin area of ​​57.5km 2 The main ditch is 11.5 km long. The terrain is generally high in the east and low in the west, with a relative height difference of 4574 m, an average longitudinal slope of 203.73‰, and an average slope of about 21.7°. Under the coupling of internal and external dynamics of earthquakes and climate warming, debris flows have occurred many times in Zhibaigou, causing serious damage to residential areas at the mouth of the ditch, transportation facilities, and rivers. In general, the debris flow in Zhibaigou has two excitation modes, namely glacial instability and rock and soil instability. The three debris flow disasters that broke out in 1950 and 1968 were all induced by glacial surges; the debris flow disaster in 2020 was induced by high-level ice and rock avalanches. The total source of Zhibaigou is about 6.45×10 6 m 3 , of which the channel source is about 1.00×10 6 m 3 Affected by the large longitudinal slope drop of the main channel, the debris flow generated upstream moves at high speed along the channel, causing erosion and side erosion of the channel and the slopes on both sides, causing the slopes on both sides to become steeper and even unstable, the channel to be cut deeper, and the channel to be widened at the original elevation.

[0045] like Figure 1-Figure 4 As shown, according to the disaster-prone conditions and material sources of the Zhibaigou debris flow, based on the current exploration and design specifications, and combined with the scouring and erosion conditions of the Zhibaigou channel, the following high-level material source consolidation device based on the geological disaster chain was designed.

[0046] The specific structure is as follows: the drilling diameter of the fully buried large-diameter steel pipe pile 1 is 200mm, the outer diameter of the steel pipe of the fully buried large-diameter steel pipe pile 1 is 180mm, the wall thickness of the steel pipe of the fully buried large-diameter steel pipe pile 1 is 6mm, and the pile length of the fully buried large-diameter steel pipe pile 1 is 16m; the cross-section of the pile cap 3 of the fully buried large-diameter steel pipe pile 1 is a regular hexagonal steel prefabricated component, the side length of the regular hexagon is 175mm, the height of the pile cap 3 of the fully buried large-diameter steel pipe pile 1 is 100mm, and bolts 6 are installed on the pile cap 3 of the fully buried large-diameter steel pipe pile 1 to connect the prefabricated holes; the connecting rod 4 is an anchor rod with a diameter of 100mm and a length of 1.7m, and bolt connection holes are respectively arranged at both ends.

[0047] The bore diameter of the fully buried partially expanded steel pipe pile 2 is 80 mm, the outer diameter of the steel pipe of the fully buried partially expanded steel pipe pile 2 is 76 mm, the wall thickness of the fully buried partially expanded steel pipe pile 2 is 4 mm, and the pile length of the fully buried partially expanded steel pipe pile 2 is 14 m. The adjacent fully buried partially expanded steel pipe piles 2 are staggered to set expansion sections 5 in sections, the diameter of the expansion sections 5 is 160 mm, the length of the expansion sections 5 is 100 mm, and the vertical spacing of the expansion sections 5 on the same fully buried partially expanded steel pipe pile 2 is 360 mm.

[0048] M30 mortar is poured into the pipes of the fully buried large-diameter steel pipe piles 1 and the fully buried partially expanded-hole steel pipe piles 2, and the M30 mortar seeps out between their pipe walls and hole walls through the uneven circular holes on their respective pipe walls.

[0049] 1 cluster steel pipe pile arrangement: the pitch-to-diameter ratio of the fully buried large-diameter steel pipe pile 1 is 10, and the pile spacing is 2000mm; 3 fully buried partially enlarged hole steel pipe piles 2 are arranged between adjacent fully buried large-diameter steel pipe piles 1, and the pile spacing between adjacent fully buried partially enlarged hole steel pipe piles 2 is 500mm.

[0050] When two cluster steel pipe pile units are arranged relative to each other, the two adjacent cluster steel pipe pile units share nodes and edge connections, that is, the first cluster steel pipe pile unit is positive, and the second cluster steel pipe pile unit is reversed 180°. Therefore, the fully buried large-diameter steel pipe piles 1 are arranged in a plum blossom shape on the plane, with a total of 4 rows, and the fully buried partially expanded steel pipe piles 2 are arranged in a total of 13 rows. Multiple cluster steel pipe pile units are arranged in the above manner, and so on.

[0051] When the upstream soil moves to the device of the present invention, due to the overall synergistic effect of the device of the present invention, the pulling force and energy of the upstream soil can be effectively reduced, thereby slowing down and reducing the scouring and scraping of the channel in the area where the device of the present invention is located and a certain range downstream thereof by the soil movement, thereby playing a role in consolidating the channel.

[0052] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. Based on the high-level material source consolidation device of geological disaster chain, it is characterized by: It includes cluster steel pipe pile units, wherein one cluster steel pipe pile unit includes three fully buried large-diameter steel pipe piles, a number of fully buried partially expanded-hole steel pipe piles and connecting rods; 3 fully buried large-diameter steel pipe piles are used as the vertices of the three angles. Any two fully buried large-diameter steel pipe piles are connected by connecting rods. 3-4 fully buried partially enlarged-hole steel pipe piles are arranged at equal intervals between adjacent fully buried large-diameter steel pipe piles. 3-6 fully buried partially enlarged-hole steel pipe piles are arranged within the triangular area surrounded by the three connecting rods. The fully buried large-diameter steel pipe piles and fully buried partially expanded-hole steel pipe piles are both steel-concrete composite structure piles poured with concrete. The top surface of the fully buried large-diameter steel pipe piles is flush with the ground. A pile cap made of concrete material or steel prefabricated material with a regular hexagonal cross-section is installed on the top of the pile. The pile cap is used to fix the connecting rod, which is an anchor rod. The end of the connecting rod is fixed to the upper surface of the pile cap by bolts. The expansion sections of two adjacent fully buried partially expanded steel pipe piles are arranged in a segmented and staggered distribution manner. Since the fully buried large-diameter steel pipe piles and the fully buried partially expanded steel pipe piles are provided with unevenly distributed circular holes, when the grouting liquid penetrates into the outside of the fully buried large-diameter steel pipe piles and the fully buried partially expanded steel pipe piles and the hole wall, the concrete grouting liquid will diffuse to the surroundings to increase the radius of influence of the grouting liquid, thereby improving the strength of the soil.

2. The device according to claim 1, characterized in that The combined shape of the fully buried large-diameter steel pipe piles and the fully buried partially expanded-hole steel pipe piles in the one cluster steel pipe pile unit is a plum blossom shape.

3. The device according to claim 1, characterized in that The following formula is used to calculate the pull-out resistance of the fully buried large-diameter steel pipe pile or the fully buried partially enlarged-hole steel pipe pile: Where: -Pull-out force, kPa; η-pile group effect coefficient, dimensionless; n – number of piles; -Pull-out strength, kPa; The pile group effect coefficient η adopts the following formula: Where: -interaction coefficient of piles; -Pile top constraint effect coefficient. When calculating fully buried large-diameter steel pipe piles, the pile cap and pile top constraint effects need to be considered. The pile cap height is less than 300mm. Take 2.05, when the pile cap height is 300-500mm, Take 2.15, when the pile cap height is greater than 500mm, Take 2.3; when calculating the fully buried partially enlarged steel pipe pile, it is not necessary to consider the constraint effect of the pile cap and pile top. Take 1; in - Pile spacing, - pile diameter, - Pile spacing diameter ratio, when checking fully buried large-diameter steel pipe piles, Value , Value ,in Indicates the spacing between adjacent fully buried large-diameter steel pipe piles. Indicates the diameter of fully buried large-diameter steel pipe piles; when calculating fully buried partially enlarged steel pipe piles, Value , Value ,in Indicates the spacing between adjacent fully buried partially expanded steel pipe piles. Indicates the diameter of fully buried partially expanded steel pipe piles; - Number of rows of steel pipe piles parallel to the force direction; -The number of columns of steel pipe piles perpendicular to the force direction; The pull-out resistance Use the following formula: Where: - horizontal deformation coefficient of pile, , is the horizontal resistance coefficient of the pile side, which is determined according to different rock and soil types in accordance with the Technical Specifications for Building Pile Foundations JGJ94-2008. is the calculated width of the pile, If it is less than 1m, calculate, - Pile diameter, when calculating the width of fully buried large-diameter steel pipe piles, Value , is the diameter of the fully buried large-diameter steel pipe pile. When calculating the width of the fully buried partially expanded steel pipe pile, Value , is the diameter of the fully buried partially expanded steel pipe pile; is the elastic modulus of the pile; is the cross-sectional inertia moment of the pile, and the piles are all steel pipe round piles. , when calculating the section inertia moment of fully buried large-diameter steel pipe piles, Value , when calculating the section inertia moment of fully buried partially expanded steel pipe piles, Value ; - The horizontal displacement allowed at the top of the pile is 1%-3% of the pile length; -The horizontal displacement coefficient of the pile top is 0.6-1.

05.

4. The device according to claim 3, characterized in that Spacing between adjacent fully buried large-diameter steel pipe piles Determined by the pull-out force, the diameter of the fully buried large-diameter steel pipe pile is 8-12 times the spacing between adjacent fully buried partially expanded steel pipe piles The diameter of the fully buried partially expanded steel pipe pile The ratio is 6-10.

5. The device according to claim 4, characterized in that The diameter of the fully buried large-diameter steel pipe pile Determined by the pull-out force, The value range is 100-200mm. When the pull-out force cannot be shared by increasing the number of fully buried large-diameter steel pipe piles, The value range is 200-300mm.

6. The device according to claim 5, characterized in that The length L of the fully buried large-diameter steel pipe pile is set and adjusted according to the pull-out force required, and the aspect ratio L / The value range is 75-100.

7. The device according to claim 5, characterized in that The diameter of the fully buried large-diameter steel pipe pile The diameter of the fully buried partially expanded steel pipe pile The relationship is: Greater than or equal to 2 ; Fully buried partially expanded steel pipe piles are designed to be staggered and divided into sections to expand the hole according to the needs of the reinforcement object. The diameter of the expanded section is 2 , It is the diameter of the fully buried partially expanded steel pipe pile.

8. The device according to claim 5, characterized in that The length l of the fully buried partially expanded steel pipe pile is 75%-80% of the length L of the fully buried large-diameter steel pipe pile. The value range is: 120-150.

9. The installation method of the high-level material source consolidation device based on the geological disaster chain according to claim 1 is characterized in that: First, determine the location of the key sections of the geological disaster chain based on on-site investigations, then use a drilling rig to pre-drill holes, and then insert the corresponding steel pipes. Secondly, pour mortar into the steel pipes. The fully buried large-diameter steel pipe piles and fully buried partially expanded steel pipe piles have uneven circular holes on their pipes. The grouting liquid penetrates into the space between the pipe wall and the hole wall through the uneven circular holes. Then install the pile caps of the fully buried large-diameter steel pipe piles, and finally install the connecting rods.

10. The method for using the high-level material source consolidation device based on the geological disaster chain according to claim 1, characterized in that: In the key section of the geological hazard chain, several clustered steel pipe pile units are arranged. When two clustered steel pipe pile units are arranged relative to each other, the two adjacent clustered steel pipe pile units share nodes and edges, that is, the first clustered steel pipe pile unit is positive, and the second clustered steel pipe pile unit is reversed 180°. Multiple clustered steel pipe pile units are arranged in the above manner, and so on.